SlideShare a Scribd company logo
WELCOME
CONSTRUCTION SUPERVISION CONSULTANT, PMBP
BANGLADESH ARMY
PRESTRESSING OF
BRIDGE GIRDER
INTRODUCTION
ADVANTAGE OF PRESTRESSING
The prestressing of concrete has several advantages as compared to traditional
reinforced concrete (RC) without prestressing. A fully prestressed concrete member is
usually subjected to compression during service life. The advantages of prestress
concrete are as follows:
 Section remains uncracked under service loads.
 Reduction of steel corrosion and thereby increase in durability.
 Full section is utilised.
● Higher moment of inertia.
● Less deformations (improved serviceability).
 Increase in shear, bending and torsional capacities.
ADVANTAGE OF PRESTRESSING
 Improved performance (resilience) under dynamic and fatigue loading.
 Sections can behave elastically.
 Larger spans possible with prestressing (bridges, buildings).
 For the same span, less depth compared to RC member.
● Reduction in self weight.
● More aesthetic appeal due to slender sections.
● More economical sections.
ADVANTAGE OF PRESTRESSING
 Suitabality for precast construction
● Rapid construction
● Better quality control
● Reduced maintenance
● Suitable for repetitive construction
● Multiple use of formwork
● Availability of standard shapes
LIMITATIONS OF PRESTRESSING
● Prestressing needs skilled manpower
● The use of high strength materials is costly
● There is additional cost in auxiliary equipments
● There is need for quality control and inspection
TERMINOLOGY
Post-Tensioning
The application of a compressive force to the concrete by stressing tendons or bars
after the concrete has been cast and cured. The force in the stressed tendons or
bars in transferred to the concrete by means of anchorages.
Wires
Prestressing wire is a single unit made of steel.
Strands
An assembly of several high strength steel wires wound together. Stands usually
have six outer wires helically wound around a single straight wire of a similar
diameter.
Tendon
A group of strands or wires are wound to form a prestressing tendon.
TERMINOLOGY
Anchorage
An assembly of various hardware components which secure a tendon at its ends
after it has been stressed and imparts the tendon force into the concrete.
Anchor Plate (Tube Unit)
The part of the anchorage which bears directly on the concrete and through which
the tendon force is transmitted.
Wedges
A small conically shaped steel component placed around a strand to grip and
secure it by wedge action in a tapered hole through a wedge plate.
Wedge Plate
A circular steel component of the anchorage containing a number of tapered holes
through which the strands pass and are secured by conical wedges.
GIRDER SECTION INCLUDING
REBAR PLACEMENT
Reinforcement placing (Side view) Reinforcement placing (Top view)
GIRDER SECTION INCLUDING
REBAR PLACEMENT
End Section Mid Section
SHEATHING DUCT
Raw Material for Sheathing Duct
SHEATHING DUCT
Preparation of Sheathing Duct
SHEATHING DUCT
Prepared Sheathing Duct
PRESTRESSING STRAND
Coil Strand (7 wire)Wire
STRESSING CABLE & THEIR PLACEMENT
WITHIN RABAR
Cable Profile checking of cable ductCable within the rebar inside
sheating duct
ANCHORAGE MATERIALS
Tube Unit (Anchor Plate) Wedge Plate Wedges
CONCRETE MIX DESIGN
Concrete class : C50
28 days cube strength : 50 mpa
Materials
Cement : Bashundhara (Ordinary Portland Cement) OPC
Fine Aggregate : Sylhet Sand, Bangladesh
Coarse Aggregate : Meghaloy, India
Admixture : Master Polyheed 8632
Water Cement Ratio : 0.3
Slump : 150mm ~ 200mm
CONCRETE MIX DESIGN
Batch Weight per cum of Concrete on SSD Condition
Cement : 470 kg
Water : 141 kg
Fine Aggregate : 658.6 kg
Coarse Aggregate : 1152 kg
Admixture : 5.9 kg
Mix Proportion : Cement : Sand : Stone
1 : 1.40 : 2.45
CONCRETING WORK OF PC GIRDER
Girder ready for concreting Concrete Transit Mixer Car Slump Test
CONCRETING WORK OF PC GIRDER
Concreting is going on Form Vibrator
CURING
PRESTRESSING JACK & ITS FUNCTION
Jack (Front Side) Jack (Back Side)
PRESTRESSING JACK & ITS FUNCTION
Jack Setting Prestressing Pump Machine
GIRDER END ARRANGEMENT
FOR PRESTRESSING
Tube Unit Wedge Plate
GIRDER END ARRANGEMENT
FOR PRESTRESSING
Collar Setting Safety Protection
GIRDER END ARRANGEMENT
FOR PRESTRESSING
Master Grip
Inserting
Master Grip
Inserting
Master Grip
Jack
Setting
PRESTRESSING PULL (ELONGATION)
FROM BOTH END
1st Reading : 62 mm Final Reading : 163 mm Reading after lock off : 153 mm
Slip : 163-153= 10 mm
PRESTRESSING PULL (ELONGATION)
FROM BOTH END
Work supervised by CSC Engr. Reading just after stressing : 200 mm Reading after 24 hours : 200 mm
After 24 hours slip: 200-200=0
STRUCTURE LOAD ON EACH GIRDER AND HOW IT IS
MAINTAINED BY PRESTRESSING
Total load (LL+DL) on each 30m girder = 1643.19 kN
Jacking force on each cable = 2475 kN (As per Contract Drawings)
Jacking force on each girder (3 no cable) = 2475 x 3 = 7425 kN
Hence 7425 kN>1643 kN
Factor of Safety, FS = 7425÷1643 = 4.5 [Minimum FS is required 1.5]
So Girder is safe.
PRESTRESSING PULL IS CONVERTED INTO STRESS
Jacking force, F = 2475 kN [As per Contract Drawings]
= 2475÷0.96 [Jack efficiency 96%]
= 2578.125 kN
= 2578.125 x 1000 N [1 kN = 1000 N]
= 2578.125 x 1000÷9.81 kg [1 Kg = 9.81 N]
= 262805.81 kg
Jacking Ram Area, A = 563.72 cm2
Stress = Force/Area = F/A = 262805.81/563.72 kg/cm2
= 466.19 kg/cm2
HOGGING & IT’S MEASUREMENT
After Stressing Hogging at centre : 33 mm Measurement taking by level machine
BUCKLING & IT’S MEASUREMENT
After Stressing Reading at end section : 100 mm Reading at max buckling point
90 mm
GROUT MIX DESIGN
Water cement ratio : 0.45
Mix proportion : Water : Cement : Admixture (Cebex-100)
22.5 Kg : 50 Kg : 1 Pkt
GROUTING PROCESS
Setting Grout Inlet Pipe Washing Duct Pipe by Air
Compressor
Washing Duct Pipe by Air
Compressor
GROUTING PROCESS
Pouring Water in Agitator Pouring Cement in Agitator Mixing Grout Materials in Agitator
GROUTING PROCESS
Grouting Pump Machine Grout Come out from Agitator Grouting in Progress
GROUTING PROCESS
Grout Come out from Outlet Pipe Lock off Outlet Pipe Provide Pressure 5.25 Kg/cm2
WEIGHT OF 30M GIRDER
CRANE CAPACITY
PIER CAP SEAT ARRANGEMENT
BEARING PAD (ELASTOMERIC PAD)
Size of Bearing Pad : 500 x 250 x 60mmPlan of Bearing and Pedestal
BEARING PAD (ELASTOMERIC PAD)
BEARING PAD (ELASTOMERIC PAD)
PLACING OF RUBBER BEARING PAD
(ELASTOMERIC PAD)
Bearing Pedestal Placing Bearing Pad on Pedestal
PLACING OF GIRDER ON BEARING PAD
TIEING WITH CRANE AT GIRDER END
GIRDER LIFTING AND PLACING
GIRDER LIFTING AND PLACING
LEAVE THE GIRDER AFTER PLACING
ON PIER CAP
Cross Girder Rebar is
welded for Tieing Girders
GAP BETWEEN FLANGE TO
FLANGE OF GIRDER
Design Gap : 40mm Maximum Gap (Actual) : 85mm
GAP BETWEEN FLANGE TO
FLANGE OF GIRDER
Design Gap : 40mm Minimum Gap (Actual) : 12mm
GAP BETWEEN TWO GIRDER
Design Gap : 100mm Gap (Actual) : 115mm
CONCLUSION

More Related Content

What's hot

Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Udisha15
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
mominzaki
 
Retaining wall - design of reinforced concrete structure
Retaining wall - design of reinforced concrete structureRetaining wall - design of reinforced concrete structure
Retaining wall - design of reinforced concrete structure
Kavin Raval
 
Foundation Failure
Foundation FailureFoundation Failure
Foundation Failureguest70cc59
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
Vishvendu pandey
 
What is post tensioning
What is post tensioningWhat is post tensioning
What is post tensioning
Charlie Gupta
 
Shear strengthening of structural members
Shear strengthening of structural membersShear strengthening of structural members
Shear strengthening of structural members
Ashutosh Maurya
 
Prestresses concrete
Prestresses concrete Prestresses concrete
Prestresses concrete
jaiveer singh
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
Andhra University
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
SnehaKothari13
 
Comparative study on solid and coupled shear wall
Comparative study on solid and coupled shear wallComparative study on solid and coupled shear wall
Comparative study on solid and coupled shear wall
IAEME Publication
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
Rahul bhatnagar
 
Fundamentals of-psc-bridge
Fundamentals of-psc-bridgeFundamentals of-psc-bridge
Fundamentals of-psc-bridge
University of Tikrit
 
Pile cap
Pile cap Pile cap
Pile cap
Lam Yu
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
GourhariBiswas1
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concrete
GPT Stvd
 
Ppt of pre casting yard
Ppt of pre casting yardPpt of pre casting yard
Ppt of pre casting yard
Ravinder Singh
 
Foundation & Pile driving equipment
Foundation & Pile driving equipment Foundation & Pile driving equipment
Foundation & Pile driving equipment
shebina a
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
ABHISHEK THAKKAE
 
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaPrestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Mukesh Singh Ghuraiya
 

What's hot (20)

Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
Retaining wall - design of reinforced concrete structure
Retaining wall - design of reinforced concrete structureRetaining wall - design of reinforced concrete structure
Retaining wall - design of reinforced concrete structure
 
Foundation Failure
Foundation FailureFoundation Failure
Foundation Failure
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
What is post tensioning
What is post tensioningWhat is post tensioning
What is post tensioning
 
Shear strengthening of structural members
Shear strengthening of structural membersShear strengthening of structural members
Shear strengthening of structural members
 
Prestresses concrete
Prestresses concrete Prestresses concrete
Prestresses concrete
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Comparative study on solid and coupled shear wall
Comparative study on solid and coupled shear wallComparative study on solid and coupled shear wall
Comparative study on solid and coupled shear wall
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
Fundamentals of-psc-bridge
Fundamentals of-psc-bridgeFundamentals of-psc-bridge
Fundamentals of-psc-bridge
 
Pile cap
Pile cap Pile cap
Pile cap
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concrete
 
Ppt of pre casting yard
Ppt of pre casting yardPpt of pre casting yard
Ppt of pre casting yard
 
Foundation & Pile driving equipment
Foundation & Pile driving equipment Foundation & Pile driving equipment
Foundation & Pile driving equipment
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaPrestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
 

Viewers also liked

Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Rais Uddin
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Rajesh Burde
 
Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12hlksd
 
Reinforced earth wall and its design parameters
Reinforced earth wall and its design parametersReinforced earth wall and its design parameters
Reinforced earth wall and its design parameters
Amir nazir paray
 
Prestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemPrestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing System
Latif Hyder Wadho
 
Bc prestressing
Bc prestressingBc prestressing
Bc prestressing
Anuj Singhal
 
Presentation on Expansion Joint
Presentation on Expansion JointPresentation on Expansion Joint
Presentation on Expansion Joint
Rais Uddin
 
Sheet pile presentation
Sheet pile presentationSheet pile presentation
Sheet pile presentation
Jahangirnagar University
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
Ravi Savani
 
Prestressed concrete baru
Prestressed concrete baruPrestressed concrete baru
Prestressed concrete baruKartina Sazali
 
Geotextiles
Geotextiles Geotextiles
Geotextiles
Seminar Links
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiiting
Ankit Patel
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete9833356555
 
Repairs and rehabilitation 2012
Repairs and rehabilitation 2012Repairs and rehabilitation 2012
Repairs and rehabilitation 2012
Dhaval Jadhav
 
Shear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteShear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concrete
MAHFUZUR RAHMAN
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
GAURAV. H .TANDON
 
Earthquake Presentation
Earthquake PresentationEarthquake Presentation
Earthquake Presentation
Ryan Cataga
 

Viewers also liked (20)

Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
CSC-PMBP
CSC-PMBPCSC-PMBP
CSC-PMBP
 
Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12
 
Reinforced earth wall and its design parameters
Reinforced earth wall and its design parametersReinforced earth wall and its design parameters
Reinforced earth wall and its design parameters
 
Prestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemPrestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing System
 
Bc prestressing
Bc prestressingBc prestressing
Bc prestressing
 
Prestress loss
Prestress lossPrestress loss
Prestress loss
 
Presentation on Expansion Joint
Presentation on Expansion JointPresentation on Expansion Joint
Presentation on Expansion Joint
 
Sheet pile presentation
Sheet pile presentationSheet pile presentation
Sheet pile presentation
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
 
Prestressed concrete baru
Prestressed concrete baruPrestressed concrete baru
Prestressed concrete baru
 
7 losses in prestress
7 losses in prestress7 losses in prestress
7 losses in prestress
 
Geotextiles
Geotextiles Geotextiles
Geotextiles
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiiting
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
Repairs and rehabilitation 2012
Repairs and rehabilitation 2012Repairs and rehabilitation 2012
Repairs and rehabilitation 2012
 
Shear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteShear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concrete
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
Earthquake Presentation
Earthquake PresentationEarthquake Presentation
Earthquake Presentation
 

Similar to Presentation on Prestressing prepared by Rais Uddin

design of steel flyover
design of steel flyoverdesign of steel flyover
design of steel flyover
Peer Mohideen
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
atchitect and design
 
continuity of pre-cast concrete girders
 continuity of pre-cast concrete girders continuity of pre-cast concrete girders
continuity of pre-cast concrete girders
Kamel Farid
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design PresentationKeith Kong
 
DESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTUREDESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTURE
AHMED NADIM JILANI
 
Pipe bending machine
Pipe bending machinePipe bending machine
Pipe bending machine
Manas Panigrahi
 
Composite construction and cambering
Composite construction and camberingComposite construction and cambering
Composite construction and cambering
guruvignesh N
 
PNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxPNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docx
stilliegeorgiana
 
Expansion joints in bridge
Expansion joints in bridgeExpansion joints in bridge
Expansion joints in bridge
Divya Vishnoi
 
FL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfFL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdf
ad_gordon
 
Rehab Solutions for Today's Infrastructure
Rehab Solutions for Today's InfrastructureRehab Solutions for Today's Infrastructure
Rehab Solutions for Today's Infrastructure
Contech Engineered Solutions
 
Design and Preparation of Aluminium Nozzle Using Metal Spinning Process
Design and Preparation of Aluminium Nozzle Using Metal Spinning ProcessDesign and Preparation of Aluminium Nozzle Using Metal Spinning Process
Design and Preparation of Aluminium Nozzle Using Metal Spinning Process
Nitesh Sharma
 
Shear lug verification example
Shear lug verification exampleShear lug verification example
Shear lug verification example
Joseph Marie TCHOUANI NANA
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
GARRE RAVI KUMAR
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs
632k18BilalAhmad
 
FYP Presentation group 1.pptx
FYP Presentation group 1.pptxFYP Presentation group 1.pptx
FYP Presentation group 1.pptx
longwalls4
 
Drilling Engineering - Casing Design
Drilling Engineering - Casing DesignDrilling Engineering - Casing Design
Drilling Engineering - Casing Design
James Craig
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
Korutla Harish
 
Design of tension member.pptx
Design of tension member.pptxDesign of tension member.pptx
Design of tension member.pptx
mayur280524
 
Bo Shan_Glubam and Concrete composite beams
Bo Shan_Glubam and Concrete composite beamsBo Shan_Glubam and Concrete composite beams
Bo Shan_Glubam and Concrete composite beams
International Bamboo and Rattan Organisation
 

Similar to Presentation on Prestressing prepared by Rais Uddin (20)

design of steel flyover
design of steel flyoverdesign of steel flyover
design of steel flyover
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
continuity of pre-cast concrete girders
 continuity of pre-cast concrete girders continuity of pre-cast concrete girders
continuity of pre-cast concrete girders
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design Presentation
 
DESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTUREDESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTURE
 
Pipe bending machine
Pipe bending machinePipe bending machine
Pipe bending machine
 
Composite construction and cambering
Composite construction and camberingComposite construction and cambering
Composite construction and cambering
 
PNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxPNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docx
 
Expansion joints in bridge
Expansion joints in bridgeExpansion joints in bridge
Expansion joints in bridge
 
FL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfFL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdf
 
Rehab Solutions for Today's Infrastructure
Rehab Solutions for Today's InfrastructureRehab Solutions for Today's Infrastructure
Rehab Solutions for Today's Infrastructure
 
Design and Preparation of Aluminium Nozzle Using Metal Spinning Process
Design and Preparation of Aluminium Nozzle Using Metal Spinning ProcessDesign and Preparation of Aluminium Nozzle Using Metal Spinning Process
Design and Preparation of Aluminium Nozzle Using Metal Spinning Process
 
Shear lug verification example
Shear lug verification exampleShear lug verification example
Shear lug verification example
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs
 
FYP Presentation group 1.pptx
FYP Presentation group 1.pptxFYP Presentation group 1.pptx
FYP Presentation group 1.pptx
 
Drilling Engineering - Casing Design
Drilling Engineering - Casing DesignDrilling Engineering - Casing Design
Drilling Engineering - Casing Design
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 
Design of tension member.pptx
Design of tension member.pptxDesign of tension member.pptx
Design of tension member.pptx
 
Bo Shan_Glubam and Concrete composite beams
Bo Shan_Glubam and Concrete composite beamsBo Shan_Glubam and Concrete composite beams
Bo Shan_Glubam and Concrete composite beams
 

Recently uploaded

Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Steel & Timber Design according to British Standard
Steel & Timber Design according to British StandardSteel & Timber Design according to British Standard
Steel & Timber Design according to British Standard
AkolbilaEmmanuel1
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 

Recently uploaded (20)

Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Steel & Timber Design according to British Standard
Steel & Timber Design according to British StandardSteel & Timber Design according to British Standard
Steel & Timber Design according to British Standard
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 

Presentation on Prestressing prepared by Rais Uddin

  • 4. ADVANTAGE OF PRESTRESSING The prestressing of concrete has several advantages as compared to traditional reinforced concrete (RC) without prestressing. A fully prestressed concrete member is usually subjected to compression during service life. The advantages of prestress concrete are as follows:  Section remains uncracked under service loads.  Reduction of steel corrosion and thereby increase in durability.  Full section is utilised. ● Higher moment of inertia. ● Less deformations (improved serviceability).  Increase in shear, bending and torsional capacities.
  • 5. ADVANTAGE OF PRESTRESSING  Improved performance (resilience) under dynamic and fatigue loading.  Sections can behave elastically.  Larger spans possible with prestressing (bridges, buildings).  For the same span, less depth compared to RC member. ● Reduction in self weight. ● More aesthetic appeal due to slender sections. ● More economical sections.
  • 6. ADVANTAGE OF PRESTRESSING  Suitabality for precast construction ● Rapid construction ● Better quality control ● Reduced maintenance ● Suitable for repetitive construction ● Multiple use of formwork ● Availability of standard shapes
  • 7. LIMITATIONS OF PRESTRESSING ● Prestressing needs skilled manpower ● The use of high strength materials is costly ● There is additional cost in auxiliary equipments ● There is need for quality control and inspection
  • 8. TERMINOLOGY Post-Tensioning The application of a compressive force to the concrete by stressing tendons or bars after the concrete has been cast and cured. The force in the stressed tendons or bars in transferred to the concrete by means of anchorages. Wires Prestressing wire is a single unit made of steel. Strands An assembly of several high strength steel wires wound together. Stands usually have six outer wires helically wound around a single straight wire of a similar diameter. Tendon A group of strands or wires are wound to form a prestressing tendon.
  • 9. TERMINOLOGY Anchorage An assembly of various hardware components which secure a tendon at its ends after it has been stressed and imparts the tendon force into the concrete. Anchor Plate (Tube Unit) The part of the anchorage which bears directly on the concrete and through which the tendon force is transmitted. Wedges A small conically shaped steel component placed around a strand to grip and secure it by wedge action in a tapered hole through a wedge plate. Wedge Plate A circular steel component of the anchorage containing a number of tapered holes through which the strands pass and are secured by conical wedges.
  • 10. GIRDER SECTION INCLUDING REBAR PLACEMENT Reinforcement placing (Side view) Reinforcement placing (Top view)
  • 11. GIRDER SECTION INCLUDING REBAR PLACEMENT End Section Mid Section
  • 12. SHEATHING DUCT Raw Material for Sheathing Duct
  • 16. STRESSING CABLE & THEIR PLACEMENT WITHIN RABAR Cable Profile checking of cable ductCable within the rebar inside sheating duct
  • 17. ANCHORAGE MATERIALS Tube Unit (Anchor Plate) Wedge Plate Wedges
  • 18. CONCRETE MIX DESIGN Concrete class : C50 28 days cube strength : 50 mpa Materials Cement : Bashundhara (Ordinary Portland Cement) OPC Fine Aggregate : Sylhet Sand, Bangladesh Coarse Aggregate : Meghaloy, India Admixture : Master Polyheed 8632 Water Cement Ratio : 0.3 Slump : 150mm ~ 200mm
  • 19. CONCRETE MIX DESIGN Batch Weight per cum of Concrete on SSD Condition Cement : 470 kg Water : 141 kg Fine Aggregate : 658.6 kg Coarse Aggregate : 1152 kg Admixture : 5.9 kg Mix Proportion : Cement : Sand : Stone 1 : 1.40 : 2.45
  • 20. CONCRETING WORK OF PC GIRDER Girder ready for concreting Concrete Transit Mixer Car Slump Test
  • 21. CONCRETING WORK OF PC GIRDER Concreting is going on Form Vibrator
  • 23. PRESTRESSING JACK & ITS FUNCTION Jack (Front Side) Jack (Back Side)
  • 24. PRESTRESSING JACK & ITS FUNCTION Jack Setting Prestressing Pump Machine
  • 25. GIRDER END ARRANGEMENT FOR PRESTRESSING Tube Unit Wedge Plate
  • 26. GIRDER END ARRANGEMENT FOR PRESTRESSING Collar Setting Safety Protection
  • 27. GIRDER END ARRANGEMENT FOR PRESTRESSING Master Grip Inserting Master Grip Inserting Master Grip Jack Setting
  • 28. PRESTRESSING PULL (ELONGATION) FROM BOTH END 1st Reading : 62 mm Final Reading : 163 mm Reading after lock off : 153 mm Slip : 163-153= 10 mm
  • 29. PRESTRESSING PULL (ELONGATION) FROM BOTH END Work supervised by CSC Engr. Reading just after stressing : 200 mm Reading after 24 hours : 200 mm After 24 hours slip: 200-200=0
  • 30. STRUCTURE LOAD ON EACH GIRDER AND HOW IT IS MAINTAINED BY PRESTRESSING Total load (LL+DL) on each 30m girder = 1643.19 kN Jacking force on each cable = 2475 kN (As per Contract Drawings) Jacking force on each girder (3 no cable) = 2475 x 3 = 7425 kN Hence 7425 kN>1643 kN Factor of Safety, FS = 7425÷1643 = 4.5 [Minimum FS is required 1.5] So Girder is safe.
  • 31. PRESTRESSING PULL IS CONVERTED INTO STRESS Jacking force, F = 2475 kN [As per Contract Drawings] = 2475÷0.96 [Jack efficiency 96%] = 2578.125 kN = 2578.125 x 1000 N [1 kN = 1000 N] = 2578.125 x 1000÷9.81 kg [1 Kg = 9.81 N] = 262805.81 kg Jacking Ram Area, A = 563.72 cm2 Stress = Force/Area = F/A = 262805.81/563.72 kg/cm2 = 466.19 kg/cm2
  • 32. HOGGING & IT’S MEASUREMENT After Stressing Hogging at centre : 33 mm Measurement taking by level machine
  • 33. BUCKLING & IT’S MEASUREMENT After Stressing Reading at end section : 100 mm Reading at max buckling point 90 mm
  • 34. GROUT MIX DESIGN Water cement ratio : 0.45 Mix proportion : Water : Cement : Admixture (Cebex-100) 22.5 Kg : 50 Kg : 1 Pkt
  • 35. GROUTING PROCESS Setting Grout Inlet Pipe Washing Duct Pipe by Air Compressor Washing Duct Pipe by Air Compressor
  • 36. GROUTING PROCESS Pouring Water in Agitator Pouring Cement in Agitator Mixing Grout Materials in Agitator
  • 37. GROUTING PROCESS Grouting Pump Machine Grout Come out from Agitator Grouting in Progress
  • 38. GROUTING PROCESS Grout Come out from Outlet Pipe Lock off Outlet Pipe Provide Pressure 5.25 Kg/cm2
  • 39. WEIGHT OF 30M GIRDER
  • 41. PIER CAP SEAT ARRANGEMENT
  • 42. BEARING PAD (ELASTOMERIC PAD) Size of Bearing Pad : 500 x 250 x 60mmPlan of Bearing and Pedestal
  • 45. PLACING OF RUBBER BEARING PAD (ELASTOMERIC PAD) Bearing Pedestal Placing Bearing Pad on Pedestal
  • 46. PLACING OF GIRDER ON BEARING PAD
  • 47. TIEING WITH CRANE AT GIRDER END
  • 50. LEAVE THE GIRDER AFTER PLACING ON PIER CAP Cross Girder Rebar is welded for Tieing Girders
  • 51. GAP BETWEEN FLANGE TO FLANGE OF GIRDER Design Gap : 40mm Maximum Gap (Actual) : 85mm
  • 52. GAP BETWEEN FLANGE TO FLANGE OF GIRDER Design Gap : 40mm Minimum Gap (Actual) : 12mm
  • 53. GAP BETWEEN TWO GIRDER Design Gap : 100mm Gap (Actual) : 115mm