SlideShare a Scribd company logo
1 of 38
Download to read offline
COMPOSITE CONSTRUCTION
PROCESS AND CAMBERING
Submitted by
GURUVIGNESH N
Reg. No :910018413004
M.E.-STRUCTURAL
ENGINEERING (FULL TIME)
ANNAUNIVERSITY REGIONAL
CAMPUS MADURAI
1
2
Introduction to Composite Construction
 Composite construction refers to two load-carrying
structural members that are integrally connected and
deflect as a single unit
 An example of this is composite metal deck with
concrete fill, steel filler beams, and girders made
composite by using headed stud connectors
COMPOSITE CONSTRUCTION
PROCESS
3
 A steel beam which is made composite by using shear
connectors, composite metal decking and concrete is much
stronger and stiffer than the base beam alone
 Composite floor systems are considered by many to be the
highest quality type of construction
 This has become a standard type of construction selected by
many architects, engineers, and developers (AISC 1991)
INTRODUCTION
4
Advantages of Composite Construction
In a composite floor system the concrete acts together with
the steel to create a stiffer, lighter, less expensive structure
(Allen 1999)
5
Advantages of Composite Construction
 It is typical to have a reduced
structural steel frame cost
 Weight of the structural steel
frame may be decreased which
may reduce foundation costs
 Reduced live load deflections
 Shallower beams may be
used which might reduce
building height
 Increased span lengths are
possible
 Stiffer floors
6
Disadvantages of Composite
Construction
 The additional subcontractor needed for shear connector
installation will increase field costs
 Installation of shear connectors is another operation to be
included in the schedule
 A concrete flatwork contractor who has experience with
elevated composite slabs should be secured for the job
7
 Composite decking works together with the concrete fill
to make a stiff, light-weight, economical floor system
 Compare the composite decking (above left), non-
composite decking (above center), and the form decking
(above right)
 Composite decking is available in various profiles and
thicknesses
Metal Decking
8
 Decking with deformed ribs (or
embossed decking), as shown, is
commonly used
 The deformations on the ribs allow
for a stronger bond between the
concrete and the decking
 (ASCE 2002)
Composite Metal Decking
9
Less common styles of composite decking include:
 Decking with the ribs formed in a dovetail or fluted
pattern (above)
 Decking with welded wire fabric welded to the ribs
 Decking with steel rods welded across the ribs
Composite Metal Decking
10
 Metal decking is placed on the structural steel at
predetermined points in the erection sequence
 Metal decking may be installed by the steel erection
contractor or a separate decking contractor
Installation of Decking
11
 As an alternative to welding, powder
actuated tools may be used to attach metal
decking to structural steel
 Powder actuated tools use the expanding
gases from a powder load, or booster, to
drive a fastener
 A nail-like fastener is driven through the
metal deck into the steel beam
 The powder actuated tool, powder load, and
fastener must be matched to the thickness
of the structural steel beam flanges
Installation of Decking
12
 Shear connectors are commonly
referred to as “studs” or “shear studs”
in the trade
 They are available in a range of sizes,
materials, and grades
 Headed studs (as shown) are most
commonly used
 Other, less common options for shear
connectors include hooked studs or
pieces of C-channel
Shear Connectors
13
 Depending on the welding process used, the tip
of the shear connector may be placed in a
ceramic ferrule (arc shield) during welding to
retain the weld
 Shear connectors create a strong bond between
the steel beam and the concrete floor slab
which is poured on top of the metal decking
 This bond allows the concrete slab to work with
the steel beams to reduce live load deflection
Shear Connectors
14
 The electrical arc process is commonly used for stud welding
 An arc is drawn between the stud and the base metal
 The stud is plunged into the molten steel which is contained by
the ceramic ferrule
 The metal solidifies and the weld is complete
Installation of Shear Connectors
15
 There is an art to the placement of concrete on metal deck and
structural steel
 The work, unless shoring is used, must be executed on a
deflecting surface
 An experienced concrete contractor should be employed for
this work
 Concrete should be deposited over supporting members first,
then spread toward the deck midspans
Installation of Concrete
16
Installation of Concrete
 Concrete construction joints should be located over the beam or
girder webs
 Sometimes this is not possible and the joint is located near the
decking midspan
 Shoring should be placed beneath the construction joints until
the concrete on both sides of the construction joint has
reached 75% strength
 This avoids a bond failure between the hardened concrete and
the metal deck when the adjoining concrete is placed
17
 Concrete is installed by a concrete contractor on top of the
composite metal decking, shear connectors, and welded wire
fabric or rebar grid (crack control reinforcing)
 Pumping is a typical installation method for concrete being
placed on metal decking
 10,000 to 15,000 sq. ft. of concrete slab may be installed per
day depending on slab thickness and crew size (Ruddy 1986)
Installation of Concrete
18
 Required quality control procedures for shear connectors include
pre-production tests and fabrication inspections
 Pre-production testing is performed by the shear stud
installer at the beginning of each work shift and includes the
following steps:
• Weld two sample
studs
• Inspect for flash
• Perform bending test
• Equipment settings are
recorded
Quality Control
19
 The shear connectors used in composite construction require
specific inspections and quality control
 Testing procedures are specified in the contract documents
or by a local building authority
 AWS D1.1 – Structural Welding Code – Steel, Section 7: Stud
Welding (AWS 2004) specifies the tests and inspections for
shear studs
Quality Control
20
When used appropriately, typical overall building costs will
be less for composite construction than non-composite
construction
Cost Impacts of Composite
Construction
21
 As per The U.S. national average installation cost for shear
studs ranges from $1.15 to $1.72 per connector (Means 2004)
 A cost comparison should be made between the reduced
structural steel cost and the additional shear connector cost
when determining whether or not to use composite construction
Cost Impacts of Composite
Construction
22
CAMBERING
Cambering is
the process of
creating an
intentional
slight
curvature in a
beam
23Camber is usually designed to compensate for deflections
caused by pre-composite dead loads
Camber in a beam can be designed to compensate for
either:
 A certain percentage of the dead load deflection
 The full dead load deflection
 The full dead load deflection as well as a
percentage of the live load deflection
Introduction to Cambering
24
 Supporting beams will deflect under the load of concrete being
placed
 This deflection can be exaggerated in a composite floor system
where the full strength of the system is not achieved until the
concrete has cured
 Cambered beams (top diagram above) should deflect to a
straight line (bottom diagram above), if load and deflection are
predicted accurately and camber equals deflection
Advantages of Cambering
25
 The use of cambered beams will, to a certain degree, be limited
by other aspects of the design for a structure
 Due to the complexity in detailing, fabrication, and fit-up
associated with moment connections (above left), camber should
not be used in moment connected beams
 Beams with simple framing connections (above right) may be
cambered because the end rotational resistance of a simple
connection is small in comparison to that of a moment connection
Disadvantages of Cambering
26
Alternative methods for
achieving a level floor slab
without using cambered
beams include:
 Pouring a slab of varying
thickness over deflecting
beams
 Using over-sized beams
to minimize deflection
 Shore the beams before
placing the concrete
Alternatives to Cambering
1 2
3
Shorin
g
Concrete At
75%
Strength
27
 The installation of cambered beams is similar to that of
other structural steel members
 No additional tooling, equipment, or hardware should be
required
Installation of Cambered Beams
28
 Shoring may be used in lieu of cambering
 The construction documents must specify the use of shoring
 There are several advantages to using shoring:
• Lighter floor beams may be used
• Cambers do not need to be designed or fabricated
• Less beam deflection allows for better control of the
slab thickness
• Shoring can accommodate a contractor’s special loading
requirements
Shoring
29
 Girder Beams
 Members with uniform cross
section
 Filler Beams
 Composite Floor Beams
When to Camber
30
 Braced Beams (above
right)
 Spandrel Beams (above
right)
 Cantilevered Beams (above
left)
 Crane Beams
 Moment Connected Beams
When Not to Camber
31
 Beams under 20 feet in
length (above right)
 Beams with end plate
connections
 Beams with moment
connections (above left)
 Beams with non-
symmetrical loading
When Not to Camber
32
 Cambering is most commonly done at the fabricator’s shop
after the connections are fabricated (AISC 2000)
 The fabricator may mark cambered beams to ensure proper
installation
Creating Camber
Image courtesy of CAMBCO Inc.
33
 Beams may be cambered by applying
heat to small wedge-shaped areas at
specific increments along the beam
 The beam is place upside down on
supports so the “bottom” flange can
be heated
 The heated flange expands under the
heat and contracts as it cools
 Camber is induced in the opposite side
of the beam as the heated flange
cools
 Advancing this slide will begin an
animation which shows the expansion
and contraction that occurs in a heat
cambered beam
Heat Cambering
34
 A heat cambered beam should be erected with the heat marks
on the bottom side of the beam (see top diagram above)
 This places the beam in a camber up (or concave down)
orientation
 Heat marks can be seen on the beams in the bottom picture
above
Installation of Heat Cambered Beams
35
 Cold cambering methods are more widely used and generally
more economical than heat cambering
 The beam is mounted in a frame and force from a ram(s) is
used to bend the beam to create camber
Cold Cambering
Image courtesy of CAMBCO Inc.
36
 Natural mill camber, which is a slight camber present in a
beam when it is received from the mill, will exist in most
beams
 If the natural mill camber is at least 75% of the specified
camber, no further cambering by the fabricator is required
 If camber is not specified, the beams will be fabricated
and erected with any natural mill camber oriented up (or
concave down) (AISC 2000)
Natural Mill Camber
37
 Cambered beams require additional fabrication resources which
will make them cost more than non-cambered beams
 The additional cambering cost should be compared with
• Cost of additional concrete due to “ponding”
• Cost of using shored construction
• Cost of using a heavier section that does not need to be
cambered
Cost of Cambering
Image courtesy of CAMBCO Inc.
THANK YOU
38

More Related Content

What's hot

Cable strucutres(presentation)
Cable strucutres(presentation)Cable strucutres(presentation)
Cable strucutres(presentation)Waseem Akbar
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Designmaylene san luis
 
Structural steel
Structural steelStructural steel
Structural steelvinod singh
 
New materials used in building industry
New materials used in building industryNew materials used in building industry
New materials used in building industryTanzil Faraz
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionMadan Mohan Jana
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Buildingppt_master
 
REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1Natalie Ulza
 
Introduction to prestressed concrete structures
Introduction to prestressed concrete structuresIntroduction to prestressed concrete structures
Introduction to prestressed concrete structuresPraveenKumar Shanmugam
 
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaPrestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaMukesh Singh Ghuraiya
 
Composite Concrete-Steel Construction in Tall Buildings by Dr. Naveed
Composite Concrete-Steel Construction in Tall Buildings by Dr. NaveedComposite Concrete-Steel Construction in Tall Buildings by Dr. Naveed
Composite Concrete-Steel Construction in Tall Buildings by Dr. NaveedAIT Solutions
 
Expansion joints
Expansion jointsExpansion joints
Expansion jointsnamePPS
 

What's hot (20)

Steel & Construction
Steel & ConstructionSteel & Construction
Steel & Construction
 
Cable strucutres(presentation)
Cable strucutres(presentation)Cable strucutres(presentation)
Cable strucutres(presentation)
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Design
 
Structural steel
Structural steelStructural steel
Structural steel
 
Timber structure
Timber structureTimber structure
Timber structure
 
Ductile detailing
Ductile detailingDuctile detailing
Ductile detailing
 
Rigid frame systems
Rigid frame systemsRigid frame systems
Rigid frame systems
 
New materials used in building industry
New materials used in building industryNew materials used in building industry
New materials used in building industry
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
 
REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1
 
Shoring
ShoringShoring
Shoring
 
Introduction to prestressed concrete structures
Introduction to prestressed concrete structuresIntroduction to prestressed concrete structures
Introduction to prestressed concrete structures
 
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaPrestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
 
Composite Concrete-Steel Construction in Tall Buildings by Dr. Naveed
Composite Concrete-Steel Construction in Tall Buildings by Dr. NaveedComposite Concrete-Steel Construction in Tall Buildings by Dr. Naveed
Composite Concrete-Steel Construction in Tall Buildings by Dr. Naveed
 
Shear walls
Shear wallsShear walls
Shear walls
 
Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
 
Polymer concrete
Polymer concretePolymer concrete
Polymer concrete
 
Expansion joints
Expansion jointsExpansion joints
Expansion joints
 

Similar to Composite construction and cambering

Lecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptxLecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptxanik7nziza
 
compositestructure31-38.pdf
compositestructure31-38.pdfcompositestructure31-38.pdf
compositestructure31-38.pdfPrakashM970621
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabIRJET Journal
 
AISCBoltingWelding1.ppt
AISCBoltingWelding1.pptAISCBoltingWelding1.ppt
AISCBoltingWelding1.pptZarnaModi1
 
111562940 aisc-bolting-and-welding-190606215451
111562940 aisc-bolting-and-welding-190606215451111562940 aisc-bolting-and-welding-190606215451
111562940 aisc-bolting-and-welding-190606215451AnhKSLT
 
Lectures Note 1. Civil Construction.pptx
Lectures Note 1. Civil Construction.pptxLectures Note 1. Civil Construction.pptx
Lectures Note 1. Civil Construction.pptx2020CEB005POTNURUSAI
 
concrete filled steel tube structure.pptx
concrete filled steel tube structure.pptxconcrete filled steel tube structure.pptx
concrete filled steel tube structure.pptxURVESHKUMARPATEL1
 
aisc-bolting-and-welding
aisc-bolting-and-weldingaisc-bolting-and-welding
aisc-bolting-and-weldingtecnidibujos
 
cfst columns
cfst columnscfst columns
cfst columnsNandhuH
 
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...Hossam Shafiq II
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 
Bolting & Welding.pptx
Bolting & Welding.pptxBolting & Welding.pptx
Bolting & Welding.pptxMedrekAbraham1
 
Reinforced Concrete
Reinforced ConcreteReinforced Concrete
Reinforced ConcreteCivil Manage
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs632k18BilalAhmad
 
prestressed concrete and precast concrete technology.pptx
prestressed concrete and precast concrete technology.pptxprestressed concrete and precast concrete technology.pptx
prestressed concrete and precast concrete technology.pptxPRASANNABHAVANGR1
 

Similar to Composite construction and cambering (20)

Lecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptxLecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptx
 
compositestructure31-38.pdf
compositestructure31-38.pdfcompositestructure31-38.pdf
compositestructure31-38.pdf
 
BUILDING TECH 5_04.pptx
BUILDING TECH 5_04.pptxBUILDING TECH 5_04.pptx
BUILDING TECH 5_04.pptx
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
 
AISCBoltingWelding1.ppt
AISCBoltingWelding1.pptAISCBoltingWelding1.ppt
AISCBoltingWelding1.ppt
 
7344574 bolting-welding-1
7344574 bolting-welding-17344574 bolting-welding-1
7344574 bolting-welding-1
 
presentation
presentationpresentation
presentation
 
Bracing connections
Bracing connectionsBracing connections
Bracing connections
 
111562940 aisc-bolting-and-welding-190606215451
111562940 aisc-bolting-and-welding-190606215451111562940 aisc-bolting-and-welding-190606215451
111562940 aisc-bolting-and-welding-190606215451
 
Lectures Note 1. Civil Construction.pptx
Lectures Note 1. Civil Construction.pptxLectures Note 1. Civil Construction.pptx
Lectures Note 1. Civil Construction.pptx
 
concrete filled steel tube structure.pptx
concrete filled steel tube structure.pptxconcrete filled steel tube structure.pptx
concrete filled steel tube structure.pptx
 
aisc-bolting-and-welding
aisc-bolting-and-weldingaisc-bolting-and-welding
aisc-bolting-and-welding
 
cfst columns
cfst columnscfst columns
cfst columns
 
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
Bolting & Welding.pptx
Bolting & Welding.pptxBolting & Welding.pptx
Bolting & Welding.pptx
 
Reinforced Concrete
Reinforced ConcreteReinforced Concrete
Reinforced Concrete
 
Presentation
PresentationPresentation
Presentation
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs
 
prestressed concrete and precast concrete technology.pptx
prestressed concrete and precast concrete technology.pptxprestressed concrete and precast concrete technology.pptx
prestressed concrete and precast concrete technology.pptx
 

Recently uploaded

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 

Recently uploaded (20)

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 

Composite construction and cambering

  • 1. COMPOSITE CONSTRUCTION PROCESS AND CAMBERING Submitted by GURUVIGNESH N Reg. No :910018413004 M.E.-STRUCTURAL ENGINEERING (FULL TIME) ANNAUNIVERSITY REGIONAL CAMPUS MADURAI 1
  • 2. 2 Introduction to Composite Construction  Composite construction refers to two load-carrying structural members that are integrally connected and deflect as a single unit  An example of this is composite metal deck with concrete fill, steel filler beams, and girders made composite by using headed stud connectors COMPOSITE CONSTRUCTION PROCESS
  • 3. 3  A steel beam which is made composite by using shear connectors, composite metal decking and concrete is much stronger and stiffer than the base beam alone  Composite floor systems are considered by many to be the highest quality type of construction  This has become a standard type of construction selected by many architects, engineers, and developers (AISC 1991) INTRODUCTION
  • 4. 4 Advantages of Composite Construction In a composite floor system the concrete acts together with the steel to create a stiffer, lighter, less expensive structure (Allen 1999)
  • 5. 5 Advantages of Composite Construction  It is typical to have a reduced structural steel frame cost  Weight of the structural steel frame may be decreased which may reduce foundation costs  Reduced live load deflections  Shallower beams may be used which might reduce building height  Increased span lengths are possible  Stiffer floors
  • 6. 6 Disadvantages of Composite Construction  The additional subcontractor needed for shear connector installation will increase field costs  Installation of shear connectors is another operation to be included in the schedule  A concrete flatwork contractor who has experience with elevated composite slabs should be secured for the job
  • 7. 7  Composite decking works together with the concrete fill to make a stiff, light-weight, economical floor system  Compare the composite decking (above left), non- composite decking (above center), and the form decking (above right)  Composite decking is available in various profiles and thicknesses Metal Decking
  • 8. 8  Decking with deformed ribs (or embossed decking), as shown, is commonly used  The deformations on the ribs allow for a stronger bond between the concrete and the decking  (ASCE 2002) Composite Metal Decking
  • 9. 9 Less common styles of composite decking include:  Decking with the ribs formed in a dovetail or fluted pattern (above)  Decking with welded wire fabric welded to the ribs  Decking with steel rods welded across the ribs Composite Metal Decking
  • 10. 10  Metal decking is placed on the structural steel at predetermined points in the erection sequence  Metal decking may be installed by the steel erection contractor or a separate decking contractor Installation of Decking
  • 11. 11  As an alternative to welding, powder actuated tools may be used to attach metal decking to structural steel  Powder actuated tools use the expanding gases from a powder load, or booster, to drive a fastener  A nail-like fastener is driven through the metal deck into the steel beam  The powder actuated tool, powder load, and fastener must be matched to the thickness of the structural steel beam flanges Installation of Decking
  • 12. 12  Shear connectors are commonly referred to as “studs” or “shear studs” in the trade  They are available in a range of sizes, materials, and grades  Headed studs (as shown) are most commonly used  Other, less common options for shear connectors include hooked studs or pieces of C-channel Shear Connectors
  • 13. 13  Depending on the welding process used, the tip of the shear connector may be placed in a ceramic ferrule (arc shield) during welding to retain the weld  Shear connectors create a strong bond between the steel beam and the concrete floor slab which is poured on top of the metal decking  This bond allows the concrete slab to work with the steel beams to reduce live load deflection Shear Connectors
  • 14. 14  The electrical arc process is commonly used for stud welding  An arc is drawn between the stud and the base metal  The stud is plunged into the molten steel which is contained by the ceramic ferrule  The metal solidifies and the weld is complete Installation of Shear Connectors
  • 15. 15  There is an art to the placement of concrete on metal deck and structural steel  The work, unless shoring is used, must be executed on a deflecting surface  An experienced concrete contractor should be employed for this work  Concrete should be deposited over supporting members first, then spread toward the deck midspans Installation of Concrete
  • 16. 16 Installation of Concrete  Concrete construction joints should be located over the beam or girder webs  Sometimes this is not possible and the joint is located near the decking midspan  Shoring should be placed beneath the construction joints until the concrete on both sides of the construction joint has reached 75% strength  This avoids a bond failure between the hardened concrete and the metal deck when the adjoining concrete is placed
  • 17. 17  Concrete is installed by a concrete contractor on top of the composite metal decking, shear connectors, and welded wire fabric or rebar grid (crack control reinforcing)  Pumping is a typical installation method for concrete being placed on metal decking  10,000 to 15,000 sq. ft. of concrete slab may be installed per day depending on slab thickness and crew size (Ruddy 1986) Installation of Concrete
  • 18. 18  Required quality control procedures for shear connectors include pre-production tests and fabrication inspections  Pre-production testing is performed by the shear stud installer at the beginning of each work shift and includes the following steps: • Weld two sample studs • Inspect for flash • Perform bending test • Equipment settings are recorded Quality Control
  • 19. 19  The shear connectors used in composite construction require specific inspections and quality control  Testing procedures are specified in the contract documents or by a local building authority  AWS D1.1 – Structural Welding Code – Steel, Section 7: Stud Welding (AWS 2004) specifies the tests and inspections for shear studs Quality Control
  • 20. 20 When used appropriately, typical overall building costs will be less for composite construction than non-composite construction Cost Impacts of Composite Construction
  • 21. 21  As per The U.S. national average installation cost for shear studs ranges from $1.15 to $1.72 per connector (Means 2004)  A cost comparison should be made between the reduced structural steel cost and the additional shear connector cost when determining whether or not to use composite construction Cost Impacts of Composite Construction
  • 22. 22 CAMBERING Cambering is the process of creating an intentional slight curvature in a beam
  • 23. 23Camber is usually designed to compensate for deflections caused by pre-composite dead loads Camber in a beam can be designed to compensate for either:  A certain percentage of the dead load deflection  The full dead load deflection  The full dead load deflection as well as a percentage of the live load deflection Introduction to Cambering
  • 24. 24  Supporting beams will deflect under the load of concrete being placed  This deflection can be exaggerated in a composite floor system where the full strength of the system is not achieved until the concrete has cured  Cambered beams (top diagram above) should deflect to a straight line (bottom diagram above), if load and deflection are predicted accurately and camber equals deflection Advantages of Cambering
  • 25. 25  The use of cambered beams will, to a certain degree, be limited by other aspects of the design for a structure  Due to the complexity in detailing, fabrication, and fit-up associated with moment connections (above left), camber should not be used in moment connected beams  Beams with simple framing connections (above right) may be cambered because the end rotational resistance of a simple connection is small in comparison to that of a moment connection Disadvantages of Cambering
  • 26. 26 Alternative methods for achieving a level floor slab without using cambered beams include:  Pouring a slab of varying thickness over deflecting beams  Using over-sized beams to minimize deflection  Shore the beams before placing the concrete Alternatives to Cambering 1 2 3 Shorin g Concrete At 75% Strength
  • 27. 27  The installation of cambered beams is similar to that of other structural steel members  No additional tooling, equipment, or hardware should be required Installation of Cambered Beams
  • 28. 28  Shoring may be used in lieu of cambering  The construction documents must specify the use of shoring  There are several advantages to using shoring: • Lighter floor beams may be used • Cambers do not need to be designed or fabricated • Less beam deflection allows for better control of the slab thickness • Shoring can accommodate a contractor’s special loading requirements Shoring
  • 29. 29  Girder Beams  Members with uniform cross section  Filler Beams  Composite Floor Beams When to Camber
  • 30. 30  Braced Beams (above right)  Spandrel Beams (above right)  Cantilevered Beams (above left)  Crane Beams  Moment Connected Beams When Not to Camber
  • 31. 31  Beams under 20 feet in length (above right)  Beams with end plate connections  Beams with moment connections (above left)  Beams with non- symmetrical loading When Not to Camber
  • 32. 32  Cambering is most commonly done at the fabricator’s shop after the connections are fabricated (AISC 2000)  The fabricator may mark cambered beams to ensure proper installation Creating Camber Image courtesy of CAMBCO Inc.
  • 33. 33  Beams may be cambered by applying heat to small wedge-shaped areas at specific increments along the beam  The beam is place upside down on supports so the “bottom” flange can be heated  The heated flange expands under the heat and contracts as it cools  Camber is induced in the opposite side of the beam as the heated flange cools  Advancing this slide will begin an animation which shows the expansion and contraction that occurs in a heat cambered beam Heat Cambering
  • 34. 34  A heat cambered beam should be erected with the heat marks on the bottom side of the beam (see top diagram above)  This places the beam in a camber up (or concave down) orientation  Heat marks can be seen on the beams in the bottom picture above Installation of Heat Cambered Beams
  • 35. 35  Cold cambering methods are more widely used and generally more economical than heat cambering  The beam is mounted in a frame and force from a ram(s) is used to bend the beam to create camber Cold Cambering Image courtesy of CAMBCO Inc.
  • 36. 36  Natural mill camber, which is a slight camber present in a beam when it is received from the mill, will exist in most beams  If the natural mill camber is at least 75% of the specified camber, no further cambering by the fabricator is required  If camber is not specified, the beams will be fabricated and erected with any natural mill camber oriented up (or concave down) (AISC 2000) Natural Mill Camber
  • 37. 37  Cambered beams require additional fabrication resources which will make them cost more than non-cambered beams  The additional cambering cost should be compared with • Cost of additional concrete due to “ponding” • Cost of using shored construction • Cost of using a heavier section that does not need to be cambered Cost of Cambering Image courtesy of CAMBCO Inc.