SlideShare a Scribd company logo
1 of 54
Pre-cast beam / continuity
Senior Structural Engineer
Structural Engineer
1
kamel Farid;
Ashraf Alsayed;
Objective
 The discussion of continuity creation and its consideration in pre-cast concrete
bridges
2
Continuous Concrete Bridges Advantages
 Reduction of joint installation and maintenance costs
 Protection of beam ends and pier caps
 Improved ride quality
3
Continuity design concepts
 Fully continuous:
 Slab and beams are continuous
 Possible to design for continuous behavior for superimposed dead and live loads
 Partially continuous:
 Only the deck is continuous
 Spans behave as a series of simple spans
 Link slab
 Discontinuous
Spans behave as a simple spans
 Tied slab
 Messenger slab
4
Fully continuous
DESIGN AND CONSTRUCTION CONSIDERATIONS
5
Fully continuous
 Requires girder ends to be embedded in a
common diaphragm.
 Requires connection for positive and
negative moments to be established.
6
Phases of construction stages
 Placement of pre-cast girders
 Forms and rebar are installed for
deck slab
 Cast slab on pre-cast girders in
assembly areas
 Leave slab block out for eventual
closure pour and pier diaphragm
 Form pier diaphragm and closure
slab
 Place diaphragm and slab
reinforcing
 Pour and cure the final closure
 Complete railing closures
7
General considerations
 Subsequent applied loads (Barrier, wearing surface, live load) applied to a
continuous system
 Remaining creep and shrinkage potential of the system must be resisted by the
pier joints
 Need to check joint effectiveness
 Might still have to design as simple spans due to construction stages
8
General considerations
9
Modeling
10
Modeling
 Slab shells are continuous for all spans
 Pre-cast beams frames are continuous for
all spans
 Construction stages load case is defined
to account for stages of construction,
creep and shrinkage
11
Modeling
Precast beam Continuity Model
12
Modeling
Rigid link Continuity Model
13
Modeling
Bearing Continuity Model
14
Modeling
Rigid link Continuity Model
15
Modeling
Cap beam Continuity Model
16
Modeling
Column Continuity Model
17
Results
18
Construction stages: before continuity Construction stages: after continuity
Results
19
The effect of moving load
Creep and shrinkage effects
It is though that creep
and shrinkage will
redistribute dead load, so
simple spans may be
used for dead load and
assuming a continuous
bridge for live load and
superimposed dead load.
20
Shrinkage strainCreep coefficient
Creep and shrinkage effects
21
Moments are in ton.m on the entire
bridge section
-1200
-1000
-800
-600
-400
-200
0
200
400
600
800
1000
0 10 20 30 40 50 60 70 80
0 days 60 days 365 days 36500
0.0
200.0
400.0
600.0
800.0
1000.0
sec 1 (Mid span) sec 2 (Support span) sec 3 (Mid span)
0 days 60 days 365 days 36500
Sec-1 Sec-2
Sec-3
Sec-2 Sec-1
0 days 60 days 365 days 36500
sec 1 (Mid span) 696.5 771.6 727.3 710.7 10%
sec 2 (Support span) 949.8 764.6 849.0 883.3 -9%
sec 3 (Mid span) 175.5 375.1 304.8 277.3 53%
Creep and shrinkage effects
 After final placement, the beams will
continue to creep and shrink; cambering
up
 Temperature will also cause camber
 Positive moments will form causing
cracking
22
Partially continuous
DESIGN AND CONSTRUCTION CONSIDERATIONS
23
Partially continuous
 Only the deck is to be made continuous
for practical reasons
 Reduced exposure of beam ends,
 Better ride quality
 In some cases, it may be more
advantageous than the fully continuous
due to simpler forming and reduced field
pour volume
24
Modeling
25
Modeling
 Slab shells are continuous for all spans
 Pre-cast beams frames are NOT
continuous at supports
 Construction stages load case is defined
to account for stages of construction,
creep and shrinkage
26
Modeling (slab)
27
Modeling (Pre-cast)
28
Modeling (Diaphragm)
29
Modeling (Rigid links)
30
Modeling (Bearing)
31
Modeling (Columns)
32
Results
33
The effect of dead load before continuity The effect of dead load after continuity
Results Creep and shrinkage effects
34
-500
0
500
1000
1500
0 10 20 30 40 50 60 70 80
Start End
35
The effect of moving load on the entire deck
Results
36
The effect of moving load on the Slab The effect of moving load on the Pre-cast
Link slab
 Slab provides minimal continuity over
center supports
 Applied loads produce end rotations
 Slab is forced to bend or comply with the
induced curvature
37
Modeling
 Typically, SCI bridge models the
composed action between slab and pre-
cast by creating a body constrain between
each joint of the frames and each
corresponding joint of the slab.
 The linked slab will be modeled same as
the partially continuous model. Only at the
slab at the link slab part, will not have any
constrains with the frame.
38
General Considerations
 Link slabs are used to eliminate deck joints
at piers where each span is supported on
elastomeric deck with a length that extends
approximately 5% of each adjacent span.
 Shear stud connectors shall be omitted
within the limits of the link slab and a bond
breaker is applied between the top flange
and the kink slab to prevent composite
action.
 only spray applied membrane waterproofing
shall be used on decks with link slabs.
39
Discontinuous Slab
TIED SLAB
MESSENGER HINGE SLAB
40
Discontinuous Slab
 Beams behave as simply supported spans
 Separate bearings and end diaphragms
are provided for each span
 Tied slab
 Messenger slab (Created by ACE)
41
Messenger slab
Additional rebar for
messenger slab detail
T T/3
Tied slab
General considerations
 The tie reinforcement at mid depth of the slab deboned for a short length either
side of the joint to permit deck rotation.
 No moment of continuity between spans
 Slabs between spans are separated using compressible joint fillers but deck
waterproofing and dick surfacing are continuous and special seals are provided
over the joint for double protection
 In case of settlement. Simply supported span are most favorable
42
Modeling
 As shown in the deformed shape figure,
neither the shells nor the frames are
continuous.
 All joints between the spans are separated
43
Results (Dead)
44
The effect of dead load on the entire deck
Of messenger slab
The effect of dead load on the entire deck
Of tied slab
Results (live)
45
The effect of moving load on the entire deck
Of messenger slab
The effect of moving load on the entire deck
Of tied slab
Results of tied slab
46
The effect of moving load on the Slab The effect of moving load on the Pre-cast
Results of messenger slab
47
The effect of moving load on the Slab The effect of moving load on the Pre-cast
Conclusion
Reinforcement (Ton)
Beams Slab Diaphragms Total
simple 4.0 23.5 1.1 28.6
Patially continuous 3.9 24.0 1.1 29.0
Continuous 4.4 23.5 0.7 28.6
48
0
5
10
15
20
25
30
35
Beams Slab Diaphragms Total
simple Patially continuous Continuous
Conclusion
 Provision of continuous spans in place of single span causes considerable
reduction in moment due to dead load, live load. However, in case of construction
stages, the continuity has a slight effect on reinforcement especially in dead load.
49
Conclusion
 For fully continuous, Shrinkage produces considerable additional moments.
 For partially continuous, Shrinkage produces slight additional moments.
50
-500
0
500
1000
1500
0 20 40 60 80
Start End
-1500
-1000
-500
0
500
1000
0 10 20 30 40 50 60 70 80
0 days 60 days 365 days 36500
Conclusion
 Fully continuous girders are more durable than partially continuous girders
because main reinforcement covers the negative tension moment which controls
the crack width. This effect is partially archived in the partially contiguous case.
 Generally, partial continuity is more preferred than full continuity for the following
reasons:
 Elimination of the cost of expansion joints
 Better riding quality
51
Moving load comparison
52
-1000
-500
0
500
1000
1500
Sec.1 Sec.2 Sec.3
Moving load
Cont Part. Cont tied slab Messenger slab
-1000
-500
0
500
1000
1500
0 10 20 30 40 50 60 70 80
Moving load comparison
Cont min Cont max Part. Cont Max Part. Cont min
tied slab max tied slab min Messenger slab max Messenger slab min
SIDL comparison
53
-300
-200
-100
0
100
200
300
400
0 10 20 30 40 50 60 70 80
SIDL
Partially continuous Continuous Tied slab Messenger slab
-300
-200
-100
0
100
200
300
400
Sec.1 Sec.2 Sec.3
SIDL
Continuous Partially continuous
Tied slab Messenger slab
Important notes
 The continuity of moment in girder is not affected by the bearing pad stiffness.
54
-1500
-1000
-500
0
500
1000
1500
0 10 20 30 40 50 60 70 80
k=400000
k=200000
k=100000
Pad bearing
stiffness

More Related Content

What's hot

Basic components and parts of bridge structures
Basic components and parts of bridge structuresBasic components and parts of bridge structures
Basic components and parts of bridge structuresMuhammad Qasim Jameel
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Hossam Shafiq II
 
Bridge
BridgeBridge
Bridgeillpa
 
Rc corbel example
Rc corbel exampleRc corbel example
Rc corbel examplemamilli
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTUVATSAL PATEL
 
Bridge introduction-8th-civil
Bridge introduction-8th-civilBridge introduction-8th-civil
Bridge introduction-8th-civilAssad ULlah
 
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]Muhammad Irfan
 
Influence line for indeterminate structures
Influence line for indeterminate structuresInfluence line for indeterminate structures
Influence line for indeterminate structuresMaruf Uddin Khaled
 
Steel concrete composite bridges
Steel concrete composite bridges Steel concrete composite bridges
Steel concrete composite bridges David Collings
 
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)Hossam Shafiq II
 
Analysis of Behaviour of U-Girder Bridge Decks
Analysis of Behaviour of U-Girder Bridge DecksAnalysis of Behaviour of U-Girder Bridge Decks
Analysis of Behaviour of U-Girder Bridge DecksIDES Editor
 
52436966 lecture-13-plate-girders
52436966 lecture-13-plate-girders52436966 lecture-13-plate-girders
52436966 lecture-13-plate-girdersSaleem Malik
 
Bridge
Bridge Bridge
Bridge illpa
 
Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Shekh Muhsen Uddin Ahmed
 
Rehabilitation and Strengthening Techniques.pptx
Rehabilitation and Strengthening Techniques.pptxRehabilitation and Strengthening Techniques.pptx
Rehabilitation and Strengthening Techniques.pptxAnanthakumar75
 

What's hot (20)

Basic components and parts of bridge structures
Basic components and parts of bridge structuresBasic components and parts of bridge structures
Basic components and parts of bridge structures
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
 
Bridge
BridgeBridge
Bridge
 
Bridge loading
Bridge loadingBridge loading
Bridge loading
 
Rc corbel example
Rc corbel exampleRc corbel example
Rc corbel example
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
 
Bridge introduction-8th-civil
Bridge introduction-8th-civilBridge introduction-8th-civil
Bridge introduction-8th-civil
 
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
 
Influence line for indeterminate structures
Influence line for indeterminate structuresInfluence line for indeterminate structures
Influence line for indeterminate structures
 
Steel concrete composite bridges
Steel concrete composite bridges Steel concrete composite bridges
Steel concrete composite bridges
 
Deep beams
Deep beamsDeep beams
Deep beams
 
Bridge introduction
Bridge introductionBridge introduction
Bridge introduction
 
Bridge Loading.ppt
Bridge Loading.pptBridge Loading.ppt
Bridge Loading.ppt
 
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
 
Analysis of Behaviour of U-Girder Bridge Decks
Analysis of Behaviour of U-Girder Bridge DecksAnalysis of Behaviour of U-Girder Bridge Decks
Analysis of Behaviour of U-Girder Bridge Decks
 
Bridge
BridgeBridge
Bridge
 
52436966 lecture-13-plate-girders
52436966 lecture-13-plate-girders52436966 lecture-13-plate-girders
52436966 lecture-13-plate-girders
 
Bridge
Bridge Bridge
Bridge
 
Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)
 
Rehabilitation and Strengthening Techniques.pptx
Rehabilitation and Strengthening Techniques.pptxRehabilitation and Strengthening Techniques.pptx
Rehabilitation and Strengthening Techniques.pptx
 

Similar to Pre-cast Beam Continuity Design and Modeling Techniques

Eurocode 2 design of composite concrete
Eurocode 2 design of composite concreteEurocode 2 design of composite concrete
Eurocode 2 design of composite concreteJo Gijbels
 
CE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsCE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsFawad Najam
 
Thesis Poster Presentation
Thesis Poster PresentationThesis Poster Presentation
Thesis Poster PresentationPaul Trofimov
 
Presentation on Prestressing prepared by Rais Uddin
Presentation on Prestressing prepared by Rais UddinPresentation on Prestressing prepared by Rais Uddin
Presentation on Prestressing prepared by Rais UddinRais Uddin
 
Presentation on prestressing prepared by Rais Uddin
Presentation on prestressing prepared by Rais UddinPresentation on prestressing prepared by Rais Uddin
Presentation on prestressing prepared by Rais UddinRais Uddin
 
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Hossam Shafiq II
 
Analysisanddesignofamulti storeyreinforcedconcrete-120923065657-phpapp01
Analysisanddesignofamulti storeyreinforcedconcrete-120923065657-phpapp01Analysisanddesignofamulti storeyreinforcedconcrete-120923065657-phpapp01
Analysisanddesignofamulti storeyreinforcedconcrete-120923065657-phpapp01ARUNTHEGEOTECH
 
Reinforced concrete Course assignments, 2019
Reinforced concrete Course assignments, 2019Reinforced concrete Course assignments, 2019
Reinforced concrete Course assignments, 2019JanneHanka
 
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdfDeflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdfvijayvijay327286
 
rectangular and section analysis in bending and shear
rectangular and section analysis in bending and shearrectangular and section analysis in bending and shear
rectangular and section analysis in bending and shearqueripan
 
Civil engeering
Civil engeeringCivil engeering
Civil engeeringsmumbahelp
 
Design of Flat Slab and Bridges
Design of Flat Slab and BridgesDesign of Flat Slab and Bridges
Design of Flat Slab and BridgesAnanthakumar75
 
Chapter 6 column
Chapter 6   columnChapter 6   column
Chapter 6 columnSimon Foo
 
IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...
IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...
IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...IRJET Journal
 

Similar to Pre-cast Beam Continuity Design and Modeling Techniques (20)

Eurocode 2 design of composite concrete
Eurocode 2 design of composite concreteEurocode 2 design of composite concrete
Eurocode 2 design of composite concrete
 
CE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsCE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie Models
 
Escape Bridge
Escape BridgeEscape Bridge
Escape Bridge
 
Thesis Poster Presentation
Thesis Poster PresentationThesis Poster Presentation
Thesis Poster Presentation
 
Stress ribbon-bridges
Stress ribbon-bridgesStress ribbon-bridges
Stress ribbon-bridges
 
Intze PPT
Intze PPTIntze PPT
Intze PPT
 
Bo Shan_Glubam and Concrete composite beams
Bo Shan_Glubam and Concrete composite beamsBo Shan_Glubam and Concrete composite beams
Bo Shan_Glubam and Concrete composite beams
 
Presentation on Prestressing prepared by Rais Uddin
Presentation on Prestressing prepared by Rais UddinPresentation on Prestressing prepared by Rais Uddin
Presentation on Prestressing prepared by Rais Uddin
 
Presentation on prestressing prepared by Rais Uddin
Presentation on prestressing prepared by Rais UddinPresentation on prestressing prepared by Rais Uddin
Presentation on prestressing prepared by Rais Uddin
 
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
 
Analysisanddesignofamulti storeyreinforcedconcrete-120923065657-phpapp01
Analysisanddesignofamulti storeyreinforcedconcrete-120923065657-phpapp01Analysisanddesignofamulti storeyreinforcedconcrete-120923065657-phpapp01
Analysisanddesignofamulti storeyreinforcedconcrete-120923065657-phpapp01
 
Reinforced concrete Course assignments, 2019
Reinforced concrete Course assignments, 2019Reinforced concrete Course assignments, 2019
Reinforced concrete Course assignments, 2019
 
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdfDeflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
H slabs
H slabsH slabs
H slabs
 
rectangular and section analysis in bending and shear
rectangular and section analysis in bending and shearrectangular and section analysis in bending and shear
rectangular and section analysis in bending and shear
 
Civil engeering
Civil engeeringCivil engeering
Civil engeering
 
Design of Flat Slab and Bridges
Design of Flat Slab and BridgesDesign of Flat Slab and Bridges
Design of Flat Slab and Bridges
 
Chapter 6 column
Chapter 6   columnChapter 6   column
Chapter 6 column
 
IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...
IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...
IRJET- Comparative Analysis of Concrete Filled Steel Tubular Truss Bridge wit...
 

Recently uploaded

IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 

Recently uploaded (20)

IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 

Pre-cast Beam Continuity Design and Modeling Techniques

  • 1. Pre-cast beam / continuity Senior Structural Engineer Structural Engineer 1 kamel Farid; Ashraf Alsayed;
  • 2. Objective  The discussion of continuity creation and its consideration in pre-cast concrete bridges 2
  • 3. Continuous Concrete Bridges Advantages  Reduction of joint installation and maintenance costs  Protection of beam ends and pier caps  Improved ride quality 3
  • 4. Continuity design concepts  Fully continuous:  Slab and beams are continuous  Possible to design for continuous behavior for superimposed dead and live loads  Partially continuous:  Only the deck is continuous  Spans behave as a series of simple spans  Link slab  Discontinuous Spans behave as a simple spans  Tied slab  Messenger slab 4
  • 5. Fully continuous DESIGN AND CONSTRUCTION CONSIDERATIONS 5
  • 6. Fully continuous  Requires girder ends to be embedded in a common diaphragm.  Requires connection for positive and negative moments to be established. 6
  • 7. Phases of construction stages  Placement of pre-cast girders  Forms and rebar are installed for deck slab  Cast slab on pre-cast girders in assembly areas  Leave slab block out for eventual closure pour and pier diaphragm  Form pier diaphragm and closure slab  Place diaphragm and slab reinforcing  Pour and cure the final closure  Complete railing closures 7
  • 8. General considerations  Subsequent applied loads (Barrier, wearing surface, live load) applied to a continuous system  Remaining creep and shrinkage potential of the system must be resisted by the pier joints  Need to check joint effectiveness  Might still have to design as simple spans due to construction stages 8
  • 11. Modeling  Slab shells are continuous for all spans  Pre-cast beams frames are continuous for all spans  Construction stages load case is defined to account for stages of construction, creep and shrinkage 11
  • 18. Results 18 Construction stages: before continuity Construction stages: after continuity
  • 20. Creep and shrinkage effects It is though that creep and shrinkage will redistribute dead load, so simple spans may be used for dead load and assuming a continuous bridge for live load and superimposed dead load. 20 Shrinkage strainCreep coefficient
  • 21. Creep and shrinkage effects 21 Moments are in ton.m on the entire bridge section -1200 -1000 -800 -600 -400 -200 0 200 400 600 800 1000 0 10 20 30 40 50 60 70 80 0 days 60 days 365 days 36500 0.0 200.0 400.0 600.0 800.0 1000.0 sec 1 (Mid span) sec 2 (Support span) sec 3 (Mid span) 0 days 60 days 365 days 36500 Sec-1 Sec-2 Sec-3 Sec-2 Sec-1 0 days 60 days 365 days 36500 sec 1 (Mid span) 696.5 771.6 727.3 710.7 10% sec 2 (Support span) 949.8 764.6 849.0 883.3 -9% sec 3 (Mid span) 175.5 375.1 304.8 277.3 53%
  • 22. Creep and shrinkage effects  After final placement, the beams will continue to creep and shrink; cambering up  Temperature will also cause camber  Positive moments will form causing cracking 22
  • 23. Partially continuous DESIGN AND CONSTRUCTION CONSIDERATIONS 23
  • 24. Partially continuous  Only the deck is to be made continuous for practical reasons  Reduced exposure of beam ends,  Better ride quality  In some cases, it may be more advantageous than the fully continuous due to simpler forming and reduced field pour volume 24
  • 26. Modeling  Slab shells are continuous for all spans  Pre-cast beams frames are NOT continuous at supports  Construction stages load case is defined to account for stages of construction, creep and shrinkage 26
  • 33. Results 33 The effect of dead load before continuity The effect of dead load after continuity
  • 34. Results Creep and shrinkage effects 34 -500 0 500 1000 1500 0 10 20 30 40 50 60 70 80 Start End
  • 35. 35 The effect of moving load on the entire deck
  • 36. Results 36 The effect of moving load on the Slab The effect of moving load on the Pre-cast
  • 37. Link slab  Slab provides minimal continuity over center supports  Applied loads produce end rotations  Slab is forced to bend or comply with the induced curvature 37
  • 38. Modeling  Typically, SCI bridge models the composed action between slab and pre- cast by creating a body constrain between each joint of the frames and each corresponding joint of the slab.  The linked slab will be modeled same as the partially continuous model. Only at the slab at the link slab part, will not have any constrains with the frame. 38
  • 39. General Considerations  Link slabs are used to eliminate deck joints at piers where each span is supported on elastomeric deck with a length that extends approximately 5% of each adjacent span.  Shear stud connectors shall be omitted within the limits of the link slab and a bond breaker is applied between the top flange and the kink slab to prevent composite action.  only spray applied membrane waterproofing shall be used on decks with link slabs. 39
  • 41. Discontinuous Slab  Beams behave as simply supported spans  Separate bearings and end diaphragms are provided for each span  Tied slab  Messenger slab (Created by ACE) 41 Messenger slab Additional rebar for messenger slab detail T T/3 Tied slab
  • 42. General considerations  The tie reinforcement at mid depth of the slab deboned for a short length either side of the joint to permit deck rotation.  No moment of continuity between spans  Slabs between spans are separated using compressible joint fillers but deck waterproofing and dick surfacing are continuous and special seals are provided over the joint for double protection  In case of settlement. Simply supported span are most favorable 42
  • 43. Modeling  As shown in the deformed shape figure, neither the shells nor the frames are continuous.  All joints between the spans are separated 43
  • 44. Results (Dead) 44 The effect of dead load on the entire deck Of messenger slab The effect of dead load on the entire deck Of tied slab
  • 45. Results (live) 45 The effect of moving load on the entire deck Of messenger slab The effect of moving load on the entire deck Of tied slab
  • 46. Results of tied slab 46 The effect of moving load on the Slab The effect of moving load on the Pre-cast
  • 47. Results of messenger slab 47 The effect of moving load on the Slab The effect of moving load on the Pre-cast
  • 48. Conclusion Reinforcement (Ton) Beams Slab Diaphragms Total simple 4.0 23.5 1.1 28.6 Patially continuous 3.9 24.0 1.1 29.0 Continuous 4.4 23.5 0.7 28.6 48 0 5 10 15 20 25 30 35 Beams Slab Diaphragms Total simple Patially continuous Continuous
  • 49. Conclusion  Provision of continuous spans in place of single span causes considerable reduction in moment due to dead load, live load. However, in case of construction stages, the continuity has a slight effect on reinforcement especially in dead load. 49
  • 50. Conclusion  For fully continuous, Shrinkage produces considerable additional moments.  For partially continuous, Shrinkage produces slight additional moments. 50 -500 0 500 1000 1500 0 20 40 60 80 Start End -1500 -1000 -500 0 500 1000 0 10 20 30 40 50 60 70 80 0 days 60 days 365 days 36500
  • 51. Conclusion  Fully continuous girders are more durable than partially continuous girders because main reinforcement covers the negative tension moment which controls the crack width. This effect is partially archived in the partially contiguous case.  Generally, partial continuity is more preferred than full continuity for the following reasons:  Elimination of the cost of expansion joints  Better riding quality 51
  • 52. Moving load comparison 52 -1000 -500 0 500 1000 1500 Sec.1 Sec.2 Sec.3 Moving load Cont Part. Cont tied slab Messenger slab -1000 -500 0 500 1000 1500 0 10 20 30 40 50 60 70 80 Moving load comparison Cont min Cont max Part. Cont Max Part. Cont min tied slab max tied slab min Messenger slab max Messenger slab min
  • 53. SIDL comparison 53 -300 -200 -100 0 100 200 300 400 0 10 20 30 40 50 60 70 80 SIDL Partially continuous Continuous Tied slab Messenger slab -300 -200 -100 0 100 200 300 400 Sec.1 Sec.2 Sec.3 SIDL Continuous Partially continuous Tied slab Messenger slab
  • 54. Important notes  The continuity of moment in girder is not affected by the bearing pad stiffness. 54 -1500 -1000 -500 0 500 1000 1500 0 10 20 30 40 50 60 70 80 k=400000 k=200000 k=100000 Pad bearing stiffness