3. Continuous Concrete Bridges Advantages
Reduction of joint installation and maintenance costs
Protection of beam ends and pier caps
Improved ride quality
3
4. Continuity design concepts
Fully continuous:
Slab and beams are continuous
Possible to design for continuous behavior for superimposed dead and live loads
Partially continuous:
Only the deck is continuous
Spans behave as a series of simple spans
Link slab
Discontinuous
Spans behave as a simple spans
Tied slab
Messenger slab
4
6. Fully continuous
Requires girder ends to be embedded in a
common diaphragm.
Requires connection for positive and
negative moments to be established.
6
7. Phases of construction stages
Placement of pre-cast girders
Forms and rebar are installed for
deck slab
Cast slab on pre-cast girders in
assembly areas
Leave slab block out for eventual
closure pour and pier diaphragm
Form pier diaphragm and closure
slab
Place diaphragm and slab
reinforcing
Pour and cure the final closure
Complete railing closures
7
8. General considerations
Subsequent applied loads (Barrier, wearing surface, live load) applied to a
continuous system
Remaining creep and shrinkage potential of the system must be resisted by the
pier joints
Need to check joint effectiveness
Might still have to design as simple spans due to construction stages
8
11. Modeling
Slab shells are continuous for all spans
Pre-cast beams frames are continuous for
all spans
Construction stages load case is defined
to account for stages of construction,
creep and shrinkage
11
20. Creep and shrinkage effects
It is though that creep
and shrinkage will
redistribute dead load, so
simple spans may be
used for dead load and
assuming a continuous
bridge for live load and
superimposed dead load.
20
Shrinkage strainCreep coefficient
21. Creep and shrinkage effects
21
Moments are in ton.m on the entire
bridge section
-1200
-1000
-800
-600
-400
-200
0
200
400
600
800
1000
0 10 20 30 40 50 60 70 80
0 days 60 days 365 days 36500
0.0
200.0
400.0
600.0
800.0
1000.0
sec 1 (Mid span) sec 2 (Support span) sec 3 (Mid span)
0 days 60 days 365 days 36500
Sec-1 Sec-2
Sec-3
Sec-2 Sec-1
0 days 60 days 365 days 36500
sec 1 (Mid span) 696.5 771.6 727.3 710.7 10%
sec 2 (Support span) 949.8 764.6 849.0 883.3 -9%
sec 3 (Mid span) 175.5 375.1 304.8 277.3 53%
22. Creep and shrinkage effects
After final placement, the beams will
continue to creep and shrink; cambering
up
Temperature will also cause camber
Positive moments will form causing
cracking
22
24. Partially continuous
Only the deck is to be made continuous
for practical reasons
Reduced exposure of beam ends,
Better ride quality
In some cases, it may be more
advantageous than the fully continuous
due to simpler forming and reduced field
pour volume
24
26. Modeling
Slab shells are continuous for all spans
Pre-cast beams frames are NOT
continuous at supports
Construction stages load case is defined
to account for stages of construction,
creep and shrinkage
26
37. Link slab
Slab provides minimal continuity over
center supports
Applied loads produce end rotations
Slab is forced to bend or comply with the
induced curvature
37
38. Modeling
Typically, SCI bridge models the
composed action between slab and pre-
cast by creating a body constrain between
each joint of the frames and each
corresponding joint of the slab.
The linked slab will be modeled same as
the partially continuous model. Only at the
slab at the link slab part, will not have any
constrains with the frame.
38
39. General Considerations
Link slabs are used to eliminate deck joints
at piers where each span is supported on
elastomeric deck with a length that extends
approximately 5% of each adjacent span.
Shear stud connectors shall be omitted
within the limits of the link slab and a bond
breaker is applied between the top flange
and the kink slab to prevent composite
action.
only spray applied membrane waterproofing
shall be used on decks with link slabs.
39
41. Discontinuous Slab
Beams behave as simply supported spans
Separate bearings and end diaphragms
are provided for each span
Tied slab
Messenger slab (Created by ACE)
41
Messenger slab
Additional rebar for
messenger slab detail
T T/3
Tied slab
42. General considerations
The tie reinforcement at mid depth of the slab deboned for a short length either
side of the joint to permit deck rotation.
No moment of continuity between spans
Slabs between spans are separated using compressible joint fillers but deck
waterproofing and dick surfacing are continuous and special seals are provided
over the joint for double protection
In case of settlement. Simply supported span are most favorable
42
43. Modeling
As shown in the deformed shape figure,
neither the shells nor the frames are
continuous.
All joints between the spans are separated
43
44. Results (Dead)
44
The effect of dead load on the entire deck
Of messenger slab
The effect of dead load on the entire deck
Of tied slab
45. Results (live)
45
The effect of moving load on the entire deck
Of messenger slab
The effect of moving load on the entire deck
Of tied slab
46. Results of tied slab
46
The effect of moving load on the Slab The effect of moving load on the Pre-cast
47. Results of messenger slab
47
The effect of moving load on the Slab The effect of moving load on the Pre-cast
49. Conclusion
Provision of continuous spans in place of single span causes considerable
reduction in moment due to dead load, live load. However, in case of construction
stages, the continuity has a slight effect on reinforcement especially in dead load.
49
50. Conclusion
For fully continuous, Shrinkage produces considerable additional moments.
For partially continuous, Shrinkage produces slight additional moments.
50
-500
0
500
1000
1500
0 20 40 60 80
Start End
-1500
-1000
-500
0
500
1000
0 10 20 30 40 50 60 70 80
0 days 60 days 365 days 36500
51. Conclusion
Fully continuous girders are more durable than partially continuous girders
because main reinforcement covers the negative tension moment which controls
the crack width. This effect is partially archived in the partially contiguous case.
Generally, partial continuity is more preferred than full continuity for the following
reasons:
Elimination of the cost of expansion joints
Better riding quality
51
52. Moving load comparison
52
-1000
-500
0
500
1000
1500
Sec.1 Sec.2 Sec.3
Moving load
Cont Part. Cont tied slab Messenger slab
-1000
-500
0
500
1000
1500
0 10 20 30 40 50 60 70 80
Moving load comparison
Cont min Cont max Part. Cont Max Part. Cont min
tied slab max tied slab min Messenger slab max Messenger slab min
54. Important notes
The continuity of moment in girder is not affected by the bearing pad stiffness.
54
-1500
-1000
-500
0
500
1000
1500
0 10 20 30 40 50 60 70 80
k=400000
k=200000
k=100000
Pad bearing
stiffness