SlideShare a Scribd company logo
PRE COMMISSONING TESTS , PERIODIC TESTS &
CHECKS FOR POWER TRANSFORMERS
4-Oct-15 1S.AYYADURAI
4-Oct-15 2S.AYYADURAI
Commissioning checks
 The following tests and checks should be
performed at a minimum to ensure that the
transformer is ready to be energized.
 Do not energize the transformer without
performing these tests and checks.
 If any tests fail and transformer is energized
overlooking the test results, it may lead to the
serious hazard, and that may result in serious
consequences and failure of the transformer.
4-Oct-15 3S.AYYADURAI
1. Insulating Fluid Test
 Draw a fluid sample and
test its dielectric strength.
Dielectric strength of new fluid
should be 26 KV or greater.
 The breakdown voltage
indicates how well insulating
oil can withstand an electrical
load and is therefore decisive
for the operational efficiency
of a transformer.
 The breakdown voltage is
measured according to VDE
0370 part 5 (IEC 60156).
4-Oct-15 4S.AYYADURAI
2. Pressure Test
• Check the transformer tank for leaks by
pressurizing the tank with dry air or dry
nitrogen through the pressure test fitting to
a pressure of 3 to 4 PSIG. let the tank stand
under pressure for one to two hours, then
examine the tank and fittings for leaks. leaks
above the fluid level can be detected by
applying soap solution to all welds, joints,
pipe fittings, and cable connections.
• Upon completion of this test, reduce the
internal pressure to 1 or 2 PSIG.
• The best way at site is to keep it idle for two
days after filling with oil to the required
level and check for leakage . This test is one
of the test to be carried out as factory
acceptance test.
• The above mentioned test shoul invariably
carried out in factory during FAT . The
pressure test , vacuum tests on fabrication
should also be done
4-Oct-15 5S.AYYADURAI
3. Insulation Megger Test
Perform a 1000-volt Megger test and a power factor test to
ensure that none of the windings is grounded.
4-Oct-15 6S.AYYADURAI
4. Ratio Test
Perform a ratio test at each tap position to ensure that transformer coil
ratios and tap changer connections are correct. Read the complete
procedure of transformer turns ratio test step by step.
5. Continuity Test and Resistance Test
Perform a continuity check on each winding. Measure the winding
resistance of each winding and compare results to factory test values. An
increase of more than 10% could indicate a loose internal connection.
6. Line Connections
In preparation for making line connections, check to make sure that all
mating connector surfaces are clean and smooth. Connections must be
tightened appropriately to prevent overheating and possible subsequent
failure of the connection. Connections to should be made with care to
avoid placing undue stress on the bushings.
4-Oct-15 7S.AYYADURAI
7. Tap Changer Setting
Check the tap changer setting to ensure it is set to the proper
position for the required voltage.
8. Delta/Wye and Series/Multiple Switch Settings
Check delta/wye and series/multiple switch settings to make sure
they are set correctly. If these connections are made using an
internal terminal board, check to ensure that these connections are
made properly according to the chart on the transformer nameplate
9. Grounding
Check to ensure that the transformer tank is permanently and
effectively grounded. The transformer tank ground pad is located
near the bottom of the tank.
10. Wiring
Check wiring of control and alarm circuits (if provided) to make sure
there are no loose connections and no damage to insulation.
4-Oct-15 8S.AYYADURAI
11. Fluid level
Check to make sure the fluid level as
indicated by the fluid level gauge is as
follows:
The fluid level gauge indicates the fluid
level inside the tank. The transformer
tank is filled with fluid at the factory to
the normal level at a reference
temperature.
12. Tank Finish
Check all painted surfaces to make sure
that there is no damage or corrosion.
13. Bolted Connections
Check all bolted connections for
tightness.
4-Oct-15 9S.AYYADURAI
13. Bolted Connections
Check all bolted connections for tightness.
4-Oct-15 10S.AYYADURAI
14. Tools
Check to make sure that all tools and equipment are accounted for and
have been removed from the transformer.
15. Fluid Temperature
Read the fluid temperature gauge and make sure the temperature is no
lower than minus 20°C before the unit is energized.
4-Oct-15 11S.AYYADURAI
Periodic Tests And Inspections
• The following periodic tests and inspections are
recommended for routine maintenance of the
medium power substation transformer.
Gauge readings
Cooling fans
Control wiring
Paint finish
Fluid dielectric test
Bushing and surge arrester insulators
Bushing terminals
Gaskets
4-Oct-15 12S.AYYADURAI
Gauge readings
• One month after initial
energization and annually
there after .
• Tank leaks must be
repaired immediately to
prevent serious damage to
the transformer and danger
to life.
• Transformer winding and
liquid temperature
measuring .
4-Oct-15 13S.AYYADURAI
2. Cooling fans (annual)
Check the cooling fans (if any) by setting the fan
“auto/manual” control switch to the “manual” position.
The fans should rotate at full speed within approximately
five seconds. The fans should rotate smoothly with
minimal vibration.
4-Oct-15 14S.AYYADURAI
3. Control wiring (annual)
Control wiring should be checked to insure that wire insulation is in good
condition. The control cabinet and associated conduit should be inspected to
ensure that weather seals are intact. Control power supply voltage should be
checked and compared to the voltage stated on the wiring diagram.
4-Oct-15 15S.AYYADURAI
4. Paint finish (annual)
Inspect the paint
finish for damage or
weathering that
exposes the primer
coat or bare metal.
Repair any paint
damage that might be
found.
4-Oct-15 16S.AYYADURAI
5. Fluid dielectric test (annual)
Sample the insulating fluid as described below. The dielectric
strength of the insulating fluid should measure at least 26 kV.
Sampling of Insulating Fluid //
Transformers are filled with insulating fluid, which provides
electrical insulation within the transformer tank and transfers
heat generated in the coils to the tank wall and radiators.
Periodically check the transformer for proper fluid level by
reading the fluid level gauge. Add fluid if necessary. When adding
fluid, add only the same type fluid that is in the transformer. It is
also recommended that a fluid sample be drawn annually and
tested for dielectric strength. Samples should be drawn from the
bottom of the tank. Use proper sampling procedures to prevent
erroneous test results. Dielectric strength should measure 26 kv
minimum.
6. Bushing and surge arrester insulators (annual)
Bushing and surge arrester insulators should be clean. If the
surfaces are excessively dirty, they should be cleaned while the
transformer is not energized after availing Line clear.
4-Oct-15 17S.AYYADURAI
7. Bushing terminals
One month after initial energization and annually thereafter
If the transformer is energized and under load, measure bushing terminal
temperatures using an infrared scanner. Excessive bushing terminal temperature
indicates a loose or dirty connection. If the transformer is not energized, use a
torque measuring device to make sure terminal connections are tight.
4-Oct-15 18S.AYYADURAI
8.Check the gaskets
Visually check all gaskets for cracking or other signs of deterioration. Replace as
necessary.
When replacing a gasket carefully clean mating surfaces to remove any rust, dirt,
transformer fluid, old gasket material, or other contamination that might prevent a
good seal. Use an appropriate gasket cement when installing new gaskets.
Do not reuse old gaskets. Six months after replacing a gasket, check and retighten if
necessary.
4-Oct-15 19S.AYYADURAI
4-Oct-15 20S.AYYADURAI

More Related Content

What's hot

RTCC & AVR
RTCC & AVRRTCC & AVR
RTCC & AVR
Indiran K
 
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
AHMED MOHAMED HEGAB
 
Motor Control Centre
Motor Control CentreMotor Control Centre
Motor Control Centre
salehkhan
 
MV Switchgear from IEEE
MV Switchgear from IEEEMV Switchgear from IEEE
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
Himansu Pradhan
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)J. FR
 
Transformer tests
Transformer testsTransformer tests
Transformer tests
pandiyarajanc
 
Panel designing
Panel designingPanel designing
Panel designing
AKANSHA GURELE
 
Iec 60364 4-442
Iec 60364 4-442Iec 60364 4-442
Iec 60364 4-442
Maria Jimenez
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
Geetesh Verma
 
Low voltage cables
Low voltage cablesLow voltage cables
Low voltage cables
hanin zeg
 
Manufaturing transformer
Manufaturing transformerManufaturing transformer
Manufaturing transformer
suman
 
Busbar sizing
Busbar sizingBusbar sizing
Busbar sizing
Jay Ranvir
 
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv JimitPRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
Jimit Dhruv
 
Sld for pmcc
Sld for pmccSld for pmcc
Sld for pmcc
Avneet Monga
 
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
AHMED MOHAMED HEGAB
 
Power Transformer ( Summer Training presentation BHEL )
Power Transformer ( Summer Training presentation BHEL )Power Transformer ( Summer Training presentation BHEL )
Power Transformer ( Summer Training presentation BHEL )
Dheeraj Upadhyay
 
Ieee std-1313-2-1999
Ieee std-1313-2-1999Ieee std-1313-2-1999
Ieee std-1313-2-1999
Noel Ramos
 
2 manual de_construccion
2 manual de_construccion2 manual de_construccion
2 manual de_construccion
Edwin Tatayo
 

What's hot (20)

RTCC & AVR
RTCC & AVRRTCC & AVR
RTCC & AVR
 
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
 
Motor Control Centre
Motor Control CentreMotor Control Centre
Motor Control Centre
 
MV Switchgear from IEEE
MV Switchgear from IEEEMV Switchgear from IEEE
MV Switchgear from IEEE
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
Transformer guide
Transformer guideTransformer guide
Transformer guide
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
 
Transformer tests
Transformer testsTransformer tests
Transformer tests
 
Panel designing
Panel designingPanel designing
Panel designing
 
Iec 60364 4-442
Iec 60364 4-442Iec 60364 4-442
Iec 60364 4-442
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
 
Low voltage cables
Low voltage cablesLow voltage cables
Low voltage cables
 
Manufaturing transformer
Manufaturing transformerManufaturing transformer
Manufaturing transformer
 
Busbar sizing
Busbar sizingBusbar sizing
Busbar sizing
 
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv JimitPRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
 
Sld for pmcc
Sld for pmccSld for pmcc
Sld for pmcc
 
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
 
Power Transformer ( Summer Training presentation BHEL )
Power Transformer ( Summer Training presentation BHEL )Power Transformer ( Summer Training presentation BHEL )
Power Transformer ( Summer Training presentation BHEL )
 
Ieee std-1313-2-1999
Ieee std-1313-2-1999Ieee std-1313-2-1999
Ieee std-1313-2-1999
 
2 manual de_construccion
2 manual de_construccion2 manual de_construccion
2 manual de_construccion
 

Viewers also liked

Steam turbine
Steam turbineSteam turbine
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
vikasgupta1965
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protectionashwin fcc
 
Transformer testing
Transformer testingTransformer testing
Transformer testingajayknows
 
Transformer construction,types and working
Transformer construction,types and workingTransformer construction,types and working
Transformer construction,types and working
maharshi dayanand university rohtak
 
Studytransformers
StudytransformersStudytransformers
Studytransformers
zakuan salim
 
Electrical Power Experience1
Electrical Power Experience1Electrical Power Experience1
Electrical Power Experience1Kendall Pinder
 
Internship Report at a 132/33 KV transmission station
Internship Report at a 132/33 KV transmission stationInternship Report at a 132/33 KV transmission station
Internship Report at a 132/33 KV transmission station
Oluwaseun Amodu
 
Transformer protection commissioning tools
Transformer protection commissioning toolsTransformer protection commissioning tools
Transformer protection commissioning tools
michaeljmack
 
Trainingreport 132 KV
Trainingreport 132 KVTrainingreport 132 KV
Trainingreport 132 KV
Abrar Ahamed
 
Testing and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsTesting and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation Equipments
Sumeet Ratnawat
 
On-line Heater & Boiler Chemical Cleaning Technology
On-line Heater & Boiler Chemical Cleaning TechnologyOn-line Heater & Boiler Chemical Cleaning Technology
On-line Heater & Boiler Chemical Cleaning TechnologyGTC Technology
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
eSAT Journals
 
Commissioning and Operations
Commissioning and OperationsCommissioning and Operations
Commissioning and OperationsAchal Gupta
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
Living Online
 
T 1 transformer insulation oil sensing system
T 1  transformer insulation oil sensing systemT 1  transformer insulation oil sensing system
T 1 transformer insulation oil sensing system
Chung Da-woon
 
Transformer 2
Transformer 2Transformer 2
Transformer 2
Viswa Nathan
 
Commissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating ConsiderationsCommissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating Considerations
Doina Dobre, P.Eng, GSC
 
Best transformer-test-procedures-en
Best transformer-test-procedures-enBest transformer-test-procedures-en
Best transformer-test-procedures-enSuresh Patil
 

Viewers also liked (20)

Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protection
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
 
Transformer construction,types and working
Transformer construction,types and workingTransformer construction,types and working
Transformer construction,types and working
 
Studytransformers
StudytransformersStudytransformers
Studytransformers
 
Electrical Power Experience1
Electrical Power Experience1Electrical Power Experience1
Electrical Power Experience1
 
Internship Report at a 132/33 KV transmission station
Internship Report at a 132/33 KV transmission stationInternship Report at a 132/33 KV transmission station
Internship Report at a 132/33 KV transmission station
 
Transformer protection commissioning tools
Transformer protection commissioning toolsTransformer protection commissioning tools
Transformer protection commissioning tools
 
Trainingreport 132 KV
Trainingreport 132 KVTrainingreport 132 KV
Trainingreport 132 KV
 
final yr project-1
final yr project-1final yr project-1
final yr project-1
 
Testing and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsTesting and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation Equipments
 
On-line Heater & Boiler Chemical Cleaning Technology
On-line Heater & Boiler Chemical Cleaning TechnologyOn-line Heater & Boiler Chemical Cleaning Technology
On-line Heater & Boiler Chemical Cleaning Technology
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Commissioning and Operations
Commissioning and OperationsCommissioning and Operations
Commissioning and Operations
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 
T 1 transformer insulation oil sensing system
T 1  transformer insulation oil sensing systemT 1  transformer insulation oil sensing system
T 1 transformer insulation oil sensing system
 
Transformer 2
Transformer 2Transformer 2
Transformer 2
 
Commissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating ConsiderationsCommissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating Considerations
 
Best transformer-test-procedures-en
Best transformer-test-procedures-enBest transformer-test-procedures-en
Best transformer-test-procedures-en
 

Similar to Pre commissioning checks & periodic inspection on power transformers

Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
Rakesh Joshi
 
13-Webinar-Transformer-Maintenance-Testing-Fundamentals-06-26-18.pdf
13-Webinar-Transformer-Maintenance-Testing-Fundamentals-06-26-18.pdf13-Webinar-Transformer-Maintenance-Testing-Fundamentals-06-26-18.pdf
13-Webinar-Transformer-Maintenance-Testing-Fundamentals-06-26-18.pdf
vikram desai
 
SD.pptx
SD.pptxSD.pptx
SD.pptx
hemant9402
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
SMRITI KESHARWANI
 
control valve functional testing - Swetha
control valve functional testing - Swethacontrol valve functional testing - Swetha
control valve functional testing - SwethaSwetha Sundaram
 
Service_C-CC-CW-Valve.pdf
Service_C-CC-CW-Valve.pdfService_C-CC-CW-Valve.pdf
Service_C-CC-CW-Valve.pdf
rheri1
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
Satish Pydimarla
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
ssuser9e9be71
 
Maintenance and inspection_of_transformer
Maintenance and inspection_of_transformerMaintenance and inspection_of_transformer
Maintenance and inspection_of_transformer
Somkene Mbakwe
 
F500 series floco positive displacement meters
F500 series floco positive displacement metersF500 series floco positive displacement meters
F500 series floco positive displacement meters
Willy Orosco Mariscal
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100
Ali Sepehri
 
Wiring diagram krisbow 26 13
Wiring diagram krisbow 26 13Wiring diagram krisbow 26 13
Wiring diagram krisbow 26 13-
 
quy trình bảo dưỡng máy thở
quy trình bảo dưỡng máy thởquy trình bảo dưỡng máy thở
quy trình bảo dưỡng máy thở
Hung Nguyen
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
ChristinaBoyd12
 
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
santubanga333
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
ssuser1f60f6
 
8013 _0
8013  _08013  _0
8013 _0
Preeti Joshi
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTCRohit Dave
 

Similar to Pre commissioning checks & periodic inspection on power transformers (20)

Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
 
13-Webinar-Transformer-Maintenance-Testing-Fundamentals-06-26-18.pdf
13-Webinar-Transformer-Maintenance-Testing-Fundamentals-06-26-18.pdf13-Webinar-Transformer-Maintenance-Testing-Fundamentals-06-26-18.pdf
13-Webinar-Transformer-Maintenance-Testing-Fundamentals-06-26-18.pdf
 
SD.pptx
SD.pptxSD.pptx
SD.pptx
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
control valve functional testing - Swetha
control valve functional testing - Swethacontrol valve functional testing - Swetha
control valve functional testing - Swetha
 
Service_C-CC-CW-Valve.pdf
Service_C-CC-CW-Valve.pdfService_C-CC-CW-Valve.pdf
Service_C-CC-CW-Valve.pdf
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
 
Maintenance and inspection_of_transformer
Maintenance and inspection_of_transformerMaintenance and inspection_of_transformer
Maintenance and inspection_of_transformer
 
F500 series floco positive displacement meters
F500 series floco positive displacement metersF500 series floco positive displacement meters
F500 series floco positive displacement meters
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100
 
Wiring diagram krisbow 26 13
Wiring diagram krisbow 26 13Wiring diagram krisbow 26 13
Wiring diagram krisbow 26 13
 
quy trình bảo dưỡng máy thở
quy trình bảo dưỡng máy thởquy trình bảo dưỡng máy thở
quy trình bảo dưỡng máy thở
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
8013 _0
8013  _08013  _0
8013 _0
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
 
3208 maintenance
3208 maintenance3208 maintenance
3208 maintenance
 
16950
1695016950
16950
 

Recently uploaded

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 

Recently uploaded (20)

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 

Pre commissioning checks & periodic inspection on power transformers

  • 1. PRE COMMISSONING TESTS , PERIODIC TESTS & CHECKS FOR POWER TRANSFORMERS 4-Oct-15 1S.AYYADURAI
  • 3. Commissioning checks  The following tests and checks should be performed at a minimum to ensure that the transformer is ready to be energized.  Do not energize the transformer without performing these tests and checks.  If any tests fail and transformer is energized overlooking the test results, it may lead to the serious hazard, and that may result in serious consequences and failure of the transformer. 4-Oct-15 3S.AYYADURAI
  • 4. 1. Insulating Fluid Test  Draw a fluid sample and test its dielectric strength. Dielectric strength of new fluid should be 26 KV or greater.  The breakdown voltage indicates how well insulating oil can withstand an electrical load and is therefore decisive for the operational efficiency of a transformer.  The breakdown voltage is measured according to VDE 0370 part 5 (IEC 60156). 4-Oct-15 4S.AYYADURAI
  • 5. 2. Pressure Test • Check the transformer tank for leaks by pressurizing the tank with dry air or dry nitrogen through the pressure test fitting to a pressure of 3 to 4 PSIG. let the tank stand under pressure for one to two hours, then examine the tank and fittings for leaks. leaks above the fluid level can be detected by applying soap solution to all welds, joints, pipe fittings, and cable connections. • Upon completion of this test, reduce the internal pressure to 1 or 2 PSIG. • The best way at site is to keep it idle for two days after filling with oil to the required level and check for leakage . This test is one of the test to be carried out as factory acceptance test. • The above mentioned test shoul invariably carried out in factory during FAT . The pressure test , vacuum tests on fabrication should also be done 4-Oct-15 5S.AYYADURAI
  • 6. 3. Insulation Megger Test Perform a 1000-volt Megger test and a power factor test to ensure that none of the windings is grounded. 4-Oct-15 6S.AYYADURAI
  • 7. 4. Ratio Test Perform a ratio test at each tap position to ensure that transformer coil ratios and tap changer connections are correct. Read the complete procedure of transformer turns ratio test step by step. 5. Continuity Test and Resistance Test Perform a continuity check on each winding. Measure the winding resistance of each winding and compare results to factory test values. An increase of more than 10% could indicate a loose internal connection. 6. Line Connections In preparation for making line connections, check to make sure that all mating connector surfaces are clean and smooth. Connections must be tightened appropriately to prevent overheating and possible subsequent failure of the connection. Connections to should be made with care to avoid placing undue stress on the bushings. 4-Oct-15 7S.AYYADURAI
  • 8. 7. Tap Changer Setting Check the tap changer setting to ensure it is set to the proper position for the required voltage. 8. Delta/Wye and Series/Multiple Switch Settings Check delta/wye and series/multiple switch settings to make sure they are set correctly. If these connections are made using an internal terminal board, check to ensure that these connections are made properly according to the chart on the transformer nameplate 9. Grounding Check to ensure that the transformer tank is permanently and effectively grounded. The transformer tank ground pad is located near the bottom of the tank. 10. Wiring Check wiring of control and alarm circuits (if provided) to make sure there are no loose connections and no damage to insulation. 4-Oct-15 8S.AYYADURAI
  • 9. 11. Fluid level Check to make sure the fluid level as indicated by the fluid level gauge is as follows: The fluid level gauge indicates the fluid level inside the tank. The transformer tank is filled with fluid at the factory to the normal level at a reference temperature. 12. Tank Finish Check all painted surfaces to make sure that there is no damage or corrosion. 13. Bolted Connections Check all bolted connections for tightness. 4-Oct-15 9S.AYYADURAI
  • 10. 13. Bolted Connections Check all bolted connections for tightness. 4-Oct-15 10S.AYYADURAI
  • 11. 14. Tools Check to make sure that all tools and equipment are accounted for and have been removed from the transformer. 15. Fluid Temperature Read the fluid temperature gauge and make sure the temperature is no lower than minus 20°C before the unit is energized. 4-Oct-15 11S.AYYADURAI
  • 12. Periodic Tests And Inspections • The following periodic tests and inspections are recommended for routine maintenance of the medium power substation transformer. Gauge readings Cooling fans Control wiring Paint finish Fluid dielectric test Bushing and surge arrester insulators Bushing terminals Gaskets 4-Oct-15 12S.AYYADURAI
  • 13. Gauge readings • One month after initial energization and annually there after . • Tank leaks must be repaired immediately to prevent serious damage to the transformer and danger to life. • Transformer winding and liquid temperature measuring . 4-Oct-15 13S.AYYADURAI
  • 14. 2. Cooling fans (annual) Check the cooling fans (if any) by setting the fan “auto/manual” control switch to the “manual” position. The fans should rotate at full speed within approximately five seconds. The fans should rotate smoothly with minimal vibration. 4-Oct-15 14S.AYYADURAI
  • 15. 3. Control wiring (annual) Control wiring should be checked to insure that wire insulation is in good condition. The control cabinet and associated conduit should be inspected to ensure that weather seals are intact. Control power supply voltage should be checked and compared to the voltage stated on the wiring diagram. 4-Oct-15 15S.AYYADURAI
  • 16. 4. Paint finish (annual) Inspect the paint finish for damage or weathering that exposes the primer coat or bare metal. Repair any paint damage that might be found. 4-Oct-15 16S.AYYADURAI
  • 17. 5. Fluid dielectric test (annual) Sample the insulating fluid as described below. The dielectric strength of the insulating fluid should measure at least 26 kV. Sampling of Insulating Fluid // Transformers are filled with insulating fluid, which provides electrical insulation within the transformer tank and transfers heat generated in the coils to the tank wall and radiators. Periodically check the transformer for proper fluid level by reading the fluid level gauge. Add fluid if necessary. When adding fluid, add only the same type fluid that is in the transformer. It is also recommended that a fluid sample be drawn annually and tested for dielectric strength. Samples should be drawn from the bottom of the tank. Use proper sampling procedures to prevent erroneous test results. Dielectric strength should measure 26 kv minimum. 6. Bushing and surge arrester insulators (annual) Bushing and surge arrester insulators should be clean. If the surfaces are excessively dirty, they should be cleaned while the transformer is not energized after availing Line clear. 4-Oct-15 17S.AYYADURAI
  • 18. 7. Bushing terminals One month after initial energization and annually thereafter If the transformer is energized and under load, measure bushing terminal temperatures using an infrared scanner. Excessive bushing terminal temperature indicates a loose or dirty connection. If the transformer is not energized, use a torque measuring device to make sure terminal connections are tight. 4-Oct-15 18S.AYYADURAI
  • 19. 8.Check the gaskets Visually check all gaskets for cracking or other signs of deterioration. Replace as necessary. When replacing a gasket carefully clean mating surfaces to remove any rust, dirt, transformer fluid, old gasket material, or other contamination that might prevent a good seal. Use an appropriate gasket cement when installing new gaskets. Do not reuse old gaskets. Six months after replacing a gasket, check and retighten if necessary. 4-Oct-15 19S.AYYADURAI