Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘no variances’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + ETC
EAC ‘atypical’ = AC + BAC - EV
EAC ‘typical’ = AC + ((BAC - EV) / CPI)
ETC = EAC - AC
ETC ‘atypical’ = BAC - EV
ETC ‘typical’ = (BAC - EV) / CPI
ETC ‘flawed’ = new estimate
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
PERT
PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6
PERT σ = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Variance all activities = √sum((Pessimistic - Optimistic) / 6)^2
Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1
Total Float = LS - ES or Total Float = LF – EF
Free Float = ES of Following - ES of Present - DUR of Present
EF = ES + duration - 1
ES = EF of predecessor + 1
LF = LS of successor - 1
LS = LF - duration + 1
Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Formula not required. Select biggest number.
ROI = Formula not required. Select biggest number.
IRR = Formula not required. Select biggest number.
Payback Period = Add up the projected cash inflow minus expenses
until you reach the initial investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.
Communications
Communication Channels = n * (n-1) / 2
Probability
EMV = Probability * Impact in currency
Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target
Cost
Depreciation
Straight-line Depreciation:
Depr. Expense = Asset Cost / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
Mathematical Basics
Average (Mean) = Sum of all members divided by the number of items.
Median = Arrange values from lowest value to highest. Pick the middle
one. If there is an even number of values, calculate the mean of the
two middle values.
Mode = Find the value in a data set that occurs most often.
Values
1 sigma = 68.26%
2 sigma = 95.46%
3 sigma = 99.73%
6 sigma = 99.99%
Control Limits = 3 sigma from mean
Control Specifications = Defined by customer; looser than
the control limits
Order of Magnitude estimate = -25% to +75%
Preliminary estimate = -15% to + 50%
Budget estimate = -10% to +25%
Definitive estimate = -5% to +10%
Final estimate = 0%
Float on the critical path = 0 days
Pareto Diagram = 80/20
Time a PM spends communicating = 90%
Crashing a project = Crash least expensive tasks on critical
path.
JIT inventory = 0% (or very close to 0%.)
Minus 100 = (100) or -100
Acronyms
AC Actual Cost
BAC Budget at Completion
BCR Benefit Cost Ratio
CBR Cost Benefit Ratio
CPI Cost Performance Index
CV Cost Variance
DUR Duration
EAC Estimate at Completion
EF Early Finish
EMV Expected Monetary Value
ES Early Start
ETC Estimate to Complete
EV Earned Value
FV Future Value
IRR Internal Rate of Return
LF Late Finish
LS Late Start
NPV Net Present Value
PERT Program Evaluation and Review Technique
PTA Point of Total Assumption
PV Planned Value
PV Present Value
ROI Return on Investment
SPI Schedule Performance Index
SV Schedule Variance
VAC Variance at Completion
σ Sigma / Standard Deviation
^ “To the power of” (2^3 = 2*2*2 = 8)

More Related Content

What's hot

PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
Shamil Habet
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slides
Wilber Tuttleman
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
MoncefMakni1
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP)
Ahmad Maharma, PMP,RMP
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
Chris Carson
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
Anand Bobade
 
Project Management: Business Case
Project Management: Business CaseProject Management: Business Case
Project Management: Business Case
Yerbol Buranbay
 
Pmp handbook
Pmp handbookPmp handbook
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
Jamil Faraj , PMP
 
Project Management Tutorial | PMP Certification | Edureka
Project Management Tutorial | PMP Certification | EdurekaProject Management Tutorial | PMP Certification | Edureka
Project Management Tutorial | PMP Certification | Edureka
Edureka!
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
ProPM Academy
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
Zaur Ahmadov, PMP
 
chap 4.4 Manage knowledge
chap 4.4 Manage knowledgechap 4.4 Manage knowledge
chap 4.4 Manage knowledge
Anand Bobade
 
Pmp formulas v5
Pmp formulas v5Pmp formulas v5
Pmp formulas v5
Dr Ezzat Mansour
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
OxfordCambridge
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
Jamil Faraj , PMP
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
Anand Bobade
 
PMP_Project Integration Management
PMP_Project Integration ManagementPMP_Project Integration Management
PMP_Project Integration Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
Anand Bobade
 
How to Setup a High-IMPACT PMO
How to Setup a High-IMPACT PMOHow to Setup a High-IMPACT PMO
How to Setup a High-IMPACT PMO
Laura Barnard, PMP
 

What's hot (20)

PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slides
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP)
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
Project Management: Business Case
Project Management: Business CaseProject Management: Business Case
Project Management: Business Case
 
Pmp handbook
Pmp handbookPmp handbook
Pmp handbook
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 
Project Management Tutorial | PMP Certification | Edureka
Project Management Tutorial | PMP Certification | EdurekaProject Management Tutorial | PMP Certification | Edureka
Project Management Tutorial | PMP Certification | Edureka
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
chap 4.4 Manage knowledge
chap 4.4 Manage knowledgechap 4.4 Manage knowledge
chap 4.4 Manage knowledge
 
Pmp formulas v5
Pmp formulas v5Pmp formulas v5
Pmp formulas v5
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
PMP_Project Integration Management
PMP_Project Integration ManagementPMP_Project Integration Management
PMP_Project Integration Management
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
How to Setup a High-IMPACT PMO
How to Setup a High-IMPACT PMOHow to Setup a High-IMPACT PMO
How to Setup a High-IMPACT PMO
 

Similar to Pmp Formula Pocket_Guide

Pmp formulas
Pmp formulasPmp formulas
Pmp formulas
Poonam Anand
 
PMP Exam Formulas
PMP Exam FormulasPMP Exam Formulas
PMP Exam Formulas
Amr Miqdadi
 
PMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdfPMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdf
Saravanan Subramanian
 
PMP Exam Formulas To Know
PMP Exam Formulas To KnowPMP Exam Formulas To Know
PMP Exam Formulas To Know
Joanne Greene-Blose
 
cheat sheet.ppt
cheat sheet.pptcheat sheet.ppt
cheat sheet.ppt
IrfanAwan25
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
Mark Troncone MBA, PMP, CBAP, ITILv3, CSM
 
Formulas for pmp exam
Formulas for pmp examFormulas for pmp exam
Formulas for pmp exam
Ibrahem Faheem
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
RedhaElhuni
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
Important formules for ugc net commerce,management (most important) downl...
Important  formules  for  ugc net commerce,management (most important)  downl...Important  formules  for  ugc net commerce,management (most important)  downl...
Important formules for ugc net commerce,management (most important) downl...
DIwakar Rajput
 
fm_formula__ipcc-2.pdf
fm_formula__ipcc-2.pdffm_formula__ipcc-2.pdf
fm_formula__ipcc-2.pdf
hitishaagrawal
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
Najm Naqvi
 
Chapter 7 cost of production
Chapter 7 cost of productionChapter 7 cost of production
Chapter 7 cost of production
Yesica Adicondro
 
Risk Concept And Management 5
Risk Concept And Management 5Risk Concept And Management 5
Risk Concept And Management 5
rajeevgupta
 
Project : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoringProject : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoring
tarzan1990
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)Nita Cristian
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
AMARAYYA
 

Similar to Pmp Formula Pocket_Guide (20)

Pmp formulas
Pmp formulasPmp formulas
Pmp formulas
 
Pmp formulas
Pmp  formulasPmp  formulas
Pmp formulas
 
PMP Exam Formulas
PMP Exam FormulasPMP Exam Formulas
PMP Exam Formulas
 
PMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdfPMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdf
 
PMP Exam Formulas To Know
PMP Exam Formulas To KnowPMP Exam Formulas To Know
PMP Exam Formulas To Know
 
cheat sheet.ppt
cheat sheet.pptcheat sheet.ppt
cheat sheet.ppt
 
Cost analysis
Cost analysisCost analysis
Cost analysis
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
Formulas for pmp exam
Formulas for pmp examFormulas for pmp exam
Formulas for pmp exam
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Important formules for ugc net commerce,management (most important) downl...
Important  formules  for  ugc net commerce,management (most important)  downl...Important  formules  for  ugc net commerce,management (most important)  downl...
Important formules for ugc net commerce,management (most important) downl...
 
fm_formula__ipcc-2.pdf
fm_formula__ipcc-2.pdffm_formula__ipcc-2.pdf
fm_formula__ipcc-2.pdf
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Chapter 7 cost of production
Chapter 7 cost of productionChapter 7 cost of production
Chapter 7 cost of production
 
F0dd9 cost
F0dd9 costF0dd9 cost
F0dd9 cost
 
Risk Concept And Management 5
Risk Concept And Management 5Risk Concept And Management 5
Risk Concept And Management 5
 
Project : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoringProject : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoring
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 

More from Jamil Faraj , PMP

Corona-virus PMP study plan
Corona-virus PMP study planCorona-virus PMP study plan
Corona-virus PMP study plan
Jamil Faraj , PMP
 
PMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMPPMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMP
Jamil Faraj , PMP
 
Jamil Faraj CV 2020
Jamil Faraj CV 2020Jamil Faraj CV 2020
Jamil Faraj CV 2020
Jamil Faraj , PMP
 
Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
Jamil Faraj , PMP
 
PMP ITTOs Quick Review
PMP ITTOs Quick Review PMP ITTOs Quick Review
PMP ITTOs Quick Review
Jamil Faraj , PMP
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
Jamil Faraj , PMP
 
2
22
1
11
Pmp6
Pmp6Pmp6
Pmp5
Pmp5Pmp5
Pmp4
Pmp4Pmp4
Pmp3
Pmp3Pmp3
Pmp2
Pmp2Pmp2
Exam1
Exam1Exam1
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
Jamil Faraj , PMP
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
Jamil Faraj , PMP
 
دورة وظيفة العمر
دورة وظيفة العمردورة وظيفة العمر
دورة وظيفة العمر
Jamil Faraj , PMP
 
02 pmp project life cycle exam
02 pmp project life cycle exam02 pmp project life cycle exam
02 pmp project life cycle exam
Jamil Faraj , PMP
 

More from Jamil Faraj , PMP (20)

Corona-virus PMP study plan
Corona-virus PMP study planCorona-virus PMP study plan
Corona-virus PMP study plan
 
PMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMPPMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMP
 
Jamil Faraj CV 2020
Jamil Faraj CV 2020Jamil Faraj CV 2020
Jamil Faraj CV 2020
 
Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
 
PMP ITTOs Quick Review
PMP ITTOs Quick Review PMP ITTOs Quick Review
PMP ITTOs Quick Review
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 
2
22
2
 
1
11
1
 
Pmp exam q&a
Pmp exam q&aPmp exam q&a
Pmp exam q&a
 
Pmp6
Pmp6Pmp6
Pmp6
 
Pmp5
Pmp5Pmp5
Pmp5
 
Pmp4
Pmp4Pmp4
Pmp4
 
Pmp3
Pmp3Pmp3
Pmp3
 
Pmp2
Pmp2Pmp2
Pmp2
 
Pmp1
Pmp1Pmp1
Pmp1
 
Exam1
Exam1Exam1
Exam1
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
دورة وظيفة العمر
دورة وظيفة العمردورة وظيفة العمر
دورة وظيفة العمر
 
02 pmp project life cycle exam
02 pmp project life cycle exam02 pmp project life cycle exam
02 pmp project life cycle exam
 

Pmp Formula Pocket_Guide

  • 1. PMP® Formula Pocket Guide Print it - Fold it - Study wherever you go. Visit www.pmprepcast.com for more PMP resources. Please see disclaimer on the PMP Formula Study Guide. © 2008 ScopeCreep Project Management Consultants. All rights reserved. Version 1.1 Earned Value CV = EV - AC CPI = EV / AC SV = EV - PV SPI = EV / PV EAC ‘no variances’ = BAC / CPI EAC ‘fundamentally flawed’ = AC + ETC EAC ‘atypical’ = AC + BAC - EV EAC ‘typical’ = AC + ((BAC - EV) / CPI) ETC = EAC - AC ETC ‘atypical’ = BAC - EV ETC ‘typical’ = (BAC - EV) / CPI ETC ‘flawed’ = new estimate Percent Complete = EV / BAC * 100 VAC = BAC - EAC EV = % complete * BAC PERT PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6 PERT σ = (Pessimistic - Optimistic) / 6 PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2 PERT Variance all activities = √sum((Pessimistic - Optimistic) / 6)^2 Network Diagram Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1 Total Float = LS - ES or Total Float = LF – EF Free Float = ES of Following - ES of Present - DUR of Present EF = ES + duration - 1 ES = EF of predecessor + 1 LF = LS of successor - 1 LS = LF - duration + 1 Project Selection PV = FV / (1+r)^n FV = PV * (1+r)^n NPV = Formula not required. Select biggest number. ROI = Formula not required. Select biggest number. IRR = Formula not required. Select biggest number. Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment. BCR = Benefit / Cost CBR = Cost / Benefit Opportunity Cost = The value of the project not chosen. Communications Communication Channels = n * (n-1) / 2 Probability EMV = Probability * Impact in currency Procurement PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost Depreciation Straight-line Depreciation: Depr. Expense = Asset Cost / Useful Life Depr. Rate = 100% / Useful Life Double Declining Balance Method: Depr. Rate = 2 * (100% / Useful Life) Depr. Expense = Depreciation Rate * Book Value at Beginning of Year Book Value = Book Value at beginning of year - Depreciation Expense Sum-of-Years' Digits Method: Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc. Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th) Mathematical Basics Average (Mean) = Sum of all members divided by the number of items. Median = Arrange values from lowest value to highest. Pick the middle one. If there is an even number of values, calculate the mean of the two middle values. Mode = Find the value in a data set that occurs most often. Values 1 sigma = 68.26% 2 sigma = 95.46% 3 sigma = 99.73% 6 sigma = 99.99% Control Limits = 3 sigma from mean Control Specifications = Defined by customer; looser than the control limits Order of Magnitude estimate = -25% to +75% Preliminary estimate = -15% to + 50% Budget estimate = -10% to +25% Definitive estimate = -5% to +10% Final estimate = 0% Float on the critical path = 0 days Pareto Diagram = 80/20 Time a PM spends communicating = 90% Crashing a project = Crash least expensive tasks on critical path. JIT inventory = 0% (or very close to 0%.) Minus 100 = (100) or -100 Acronyms AC Actual Cost BAC Budget at Completion BCR Benefit Cost Ratio CBR Cost Benefit Ratio CPI Cost Performance Index CV Cost Variance DUR Duration EAC Estimate at Completion EF Early Finish EMV Expected Monetary Value ES Early Start ETC Estimate to Complete EV Earned Value FV Future Value IRR Internal Rate of Return LF Late Finish LS Late Start NPV Net Present Value PERT Program Evaluation and Review Technique PTA Point of Total Assumption PV Planned Value PV Present Value ROI Return on Investment SPI Schedule Performance Index SV Schedule Variance VAC Variance at Completion σ Sigma / Standard Deviation ^ “To the power of” (2^3 = 2*2*2 = 8)