32  Chapter 1
exam questions
1. Which of the following is NOT a type of project management office?
A.	 Directive
B.	 Value-driven
C.	 Supportive
D.	 Controlling
2. Which of the following is NOT a characteristic of a project?
A.	 Temporary
B.	 Strategic
C.	 Specific result
D.	 Progressively elaborated
3. An energy company is investing in a series of initiatives to look for alternative energy sources so that the
company can be competitive in 10 years. The initiatives are tracked and managed together because this goal
is vital to the success of the company. This is an example of:
A.	 A portfolio
B.	 A program
C.	 A project
D.	 A enterprise environmental factor
4. Which of the following is NOT a responsibility of a project manager?
A.	 Managing stakeholder expectations
B.	 Managing project constraints
C.	 Gathering product requirements
D.	 Sponsoring the project
5. Which of the following is NOT an interpersonal skill?
A.	 Motivation
B.	 Brainstorming
C.	 Team building
D.	 Coaching
Exam Questions
you are here 4  33
introduction to the pmp exam
6. Which of the following is NOT true about interpersonal skills?
A.	 Coaching means helping your team to get more exercise.
B.	 Motivation means helping team members get what they want out of the project.
C.	 Influencing means sharing power with people to get something done.
D.	 Conflict management means finding positive solutions to conflicts during the project.
7. Which of the following is NOT true about portfolio management?
A.	 The portfolio manager judges the success of the portfolio by combining data from all of its programs and
projects.
B.	 A portfolio can contain projects and programs.
C.	 A portfolio is organized around a business goal.
D.	 A portfolio is always a group of programs.
8. You’re managing a project to remodel a kitchen. You use earned value calculations to figure out that
you’re going to run $500 over budget if your project continues at the current rate. Which of the following
core characteristics of a project manager are you using to find the problem?
A.	 Knowledge
B.	 Performance
C.	 Personal
D.	 None of the above
9. At the beginning of a project, a software team project manager is given a schedule with everyone’s
vacations on it. She realizes that because the software will be delivered to the QA team exactly when they
have overlapping vacations, there is a serious risk of quality problems, because there won’t be anyone to
test the software before it goes into production. What BEST describes the constraint this places on the
project?
A.	 Quality constraint
B.	 Time constraint
C.	 Resource constraint
D.	 Risk constraint
10. A project manager is having trouble with his project because one of his team members is not performing,
which is causing him to miss an important date he promised to a stakeholder. He discovers that the team
member knew about the project problem, but didn’t tell him because the team members are all afraid of his
bad temper. Which BEST describes how the project manager can avoid this situation in the future?
A.	 Increasing his knowledge of the PMBOK Guide
B.	 Measuring personal performance
C.	 Improving his personal skills
D.	 Managing stakeholder expectations
Exam Questions

More Related Content

What's hot (20)

04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
Exam1
Exam1Exam1
Exam1
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
09 pmp human resource management exam
09 pmp human resource  management exam09 pmp human resource  management exam
09 pmp human resource management exam
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
Pmp3
Pmp3Pmp3
Pmp3
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 
05 pmp scope management exam
05 pmp scope management exam05 pmp scope management exam
05 pmp scope management exam
 
Pmp test 03
Pmp test 03Pmp test 03
Pmp test 03
 
Pmp test 01
Pmp test 01Pmp test 01
Pmp test 01
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
Pmp5
Pmp5Pmp5
Pmp5
 
12 pmp procurement management exam
12 pmp procurement management exam12 pmp procurement management exam
12 pmp procurement management exam
 
02 pmp project life cycle exam
02 pmp project life cycle exam02 pmp project life cycle exam
02 pmp project life cycle exam
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
Full length mock test useful for PMP Exam folks
Full length mock test useful for PMP Exam folksFull length mock test useful for PMP Exam folks
Full length mock test useful for PMP Exam folks
 
PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360
 
150 PMP Questions
150 PMP Questions 150 PMP Questions
150 PMP Questions
 

Viewers also liked

Viewers also liked (8)

2
22
2
 
Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility exam
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 
175 pmp sample_questions
175 pmp sample_questions175 pmp sample_questions
175 pmp sample_questions
 

Similar to Project Management Exam Questions Chapter 1

PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfProject Cubicle
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions CompleteKareemBullard1
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docxjackiewalcutt
 
Chapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxChapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxwalterl4
 
Workbook answers
Workbook answersWorkbook answers
Workbook answersqtntpam
 
Certified Associate in Project Management
Certified Associate in Project ManagementCertified Associate in Project Management
Certified Associate in Project ManagementEllina Beckman
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfMoncefMakni1
 
910 - Questions.pdf
910 - Questions.pdf910 - Questions.pdf
910 - Questions.pdfNguyen Hai
 
BICSI Registered Communications Distribution Designer RCDDv14 Study Guide
BICSI Registered Communications Distribution Designer RCDDv14 Study GuideBICSI Registered Communications Distribution Designer RCDDv14 Study Guide
BICSI Registered Communications Distribution Designer RCDDv14 Study GuidewilliamLeo13
 

Similar to Project Management Exam Questions Chapter 1 (20)

PMP Certificate- introduction
PMP Certificate- introductionPMP Certificate- introduction
PMP Certificate- introduction
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
Chapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxChapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docx
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Workbook answers
Workbook answersWorkbook answers
Workbook answers
 
Certified Associate in Project Management
Certified Associate in Project ManagementCertified Associate in Project Management
Certified Associate in Project Management
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Pmp Five Sample Questions
Pmp Five Sample QuestionsPmp Five Sample Questions
Pmp Five Sample Questions
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
PgMP
PgMP PgMP
PgMP
 
Itpm question bank
Itpm   question bankItpm   question bank
Itpm question bank
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
910 - Questions.pdf
910 - Questions.pdf910 - Questions.pdf
910 - Questions.pdf
 
Pmp sample qa3
Pmp sample qa3Pmp sample qa3
Pmp sample qa3
 
BICSI Registered Communications Distribution Designer RCDDv14 Study Guide
BICSI Registered Communications Distribution Designer RCDDv14 Study GuideBICSI Registered Communications Distribution Designer RCDDv14 Study Guide
BICSI Registered Communications Distribution Designer RCDDv14 Study Guide
 
PMP® Sample Questions 3
PMP® Sample Questions 3PMP® Sample Questions 3
PMP® Sample Questions 3
 
PMI-RMP a test mod 00
PMI-RMP a test  mod 00PMI-RMP a test  mod 00
PMI-RMP a test mod 00
 
Project management
Project managementProject management
Project management
 

Project Management Exam Questions Chapter 1

  • 1. 32  Chapter 1 exam questions 1. Which of the following is NOT a type of project management office? A. Directive B. Value-driven C. Supportive D. Controlling 2. Which of the following is NOT a characteristic of a project? A. Temporary B. Strategic C. Specific result D. Progressively elaborated 3. An energy company is investing in a series of initiatives to look for alternative energy sources so that the company can be competitive in 10 years. The initiatives are tracked and managed together because this goal is vital to the success of the company. This is an example of: A. A portfolio B. A program C. A project D. A enterprise environmental factor 4. Which of the following is NOT a responsibility of a project manager? A. Managing stakeholder expectations B. Managing project constraints C. Gathering product requirements D. Sponsoring the project 5. Which of the following is NOT an interpersonal skill? A. Motivation B. Brainstorming C. Team building D. Coaching Exam Questions
  • 2. you are here 4  33 introduction to the pmp exam 6. Which of the following is NOT true about interpersonal skills? A. Coaching means helping your team to get more exercise. B. Motivation means helping team members get what they want out of the project. C. Influencing means sharing power with people to get something done. D. Conflict management means finding positive solutions to conflicts during the project. 7. Which of the following is NOT true about portfolio management? A. The portfolio manager judges the success of the portfolio by combining data from all of its programs and projects. B. A portfolio can contain projects and programs. C. A portfolio is organized around a business goal. D. A portfolio is always a group of programs. 8. You’re managing a project to remodel a kitchen. You use earned value calculations to figure out that you’re going to run $500 over budget if your project continues at the current rate. Which of the following core characteristics of a project manager are you using to find the problem? A. Knowledge B. Performance C. Personal D. None of the above 9. At the beginning of a project, a software team project manager is given a schedule with everyone’s vacations on it. She realizes that because the software will be delivered to the QA team exactly when they have overlapping vacations, there is a serious risk of quality problems, because there won’t be anyone to test the software before it goes into production. What BEST describes the constraint this places on the project? A. Quality constraint B. Time constraint C. Resource constraint D. Risk constraint 10. A project manager is having trouble with his project because one of his team members is not performing, which is causing him to miss an important date he promised to a stakeholder. He discovers that the team member knew about the project problem, but didn’t tell him because the team members are all afraid of his bad temper. Which BEST describes how the project manager can avoid this situation in the future? A. Increasing his knowledge of the PMBOK Guide B. Measuring personal performance C. Improving his personal skills D. Managing stakeholder expectations Exam Questions