SlideShare a Scribd company logo
Formulas / Math for PMP
Name (Abbreviation) Formula Interpretation (Result)
1. Program evaluation and
review technique (PERT)
(P + 4M + O)/ 6
Pessimistic, Most Likely, Optimistic
Estimated duration of a
schedule activity expressed
as a weight average
2. PERT Standard Deviation
(Single Activity)
(P - O) / 6 Standard deviation from the
mean of a schedule activity
3. PERT Activity Variance
(AV)
[(P - O)/6] ^2 The expected variance in
the activity duration. For
instance: +/- 3 days
4. PERT Standard Deviation
(All Activity)
√(
𝑃−𝑂
6
)^2 === √𝑉 Standard deviation from the
mean of the given series
activities
5. Float or Slack LS-ES and LF-EF
LS: Late Start, ES: Early Start,
LS: Late Finish, EF: Early Finish
If = 0 on critical path
If < 0 Behind schedule
6. Cost Variance (CV) EV – AC
EV = Earned Value
AC = Actual Cost
< 0 Over budget
(negative)
= 0 On budget
> 0 Within budget
(positive)
7. Schedule Variance (SV) EV – PV
PV = Planned Value
< 0 Behind schedule
= 0 On schedule
> 0 Ahead of schedule
8. Cost Perf. Index (CPI) EV / AC < 1 Over budget
= 1 On budget
> 1 Under budget
9. Sched. Perf. Index (SPI) EV / PV < 1 behind schedule
= 1 on schedule
> 1 ahead of schedule
10. Est. At Completion (EAC) BAC / CPI -- CPI remains the same
- if the CPI would remain the same till end
of project, i.e. the original estimation is
not accurate.
- Use formula if no variances from the BAC
have occurred or are expected to
continue at the same rate of spending.
original budget modified by
the cost performance. The
result is a monetary value.
AC + ETC -- Initial Estimates are flawed (original
is flawed)
- if the original estimate is based on
wrong data/assumptions or
circumstances have changed.
- Use formula if original estimate was
fundamentally flawed or condition have
Actual cost plus a new
estimate for the remaining
work. The result is a
monetary value.
change and invalided original estimating
assumption
AC + BAC - EV -- Future variance is Atypical
(BAC remains the same)
- the variance is caused by a one-time
event and is not likely to happen again.
- Use formula if current variances are
thought to be atypical in the future.
Actual cost to date plus
remaining budget. Result is
monetary value.
AC + (BAC - EV) / CPI -- Future Variance would
be typical
- Use formula if current variances are
thought to be typical in the future.
Actual cost to date plus
remaining budget, result is
monetary value.
BAC = Budget at completion
New ETC = New Estimate to Completion
11. Est. To Complete (ETC)
Percentage complete
EAC – AC -- we recommended using it, if no
keywords are given.
EV/ BAC *100 -- in percentage
Result is a monetary value
that will tell us how much
more the project will cost
12. Var. At Completion (VAC) BAC – EAC
The different between the originally estimated
BAC and a newly calculated EAC
< 0 Over budget
= 0 On budget
> 0 Under budget
13. To Complete
Performance Index (TCPI)
Values for the TCPI index of less than 1.0 is good
because it indicates the efficiency to complete is
less than planned. How efficient must the project
team be to complete the remaining work with
the remaining money?
(BAC - EV) / (BAC - AC); remaining work /
remaining funds
< 1 Under budget
= 1 On budget
> 1 Over budget
13. Net Present Value Method for financial evaluation long term project,
not required for the exam
Bigger is better (NPV)
14. Present Value PV FV / (1 + r) ^n
Receiving money in the future has different value
than receiving money in the present(today). This
formula calculated how much.
The result is the amount of
money you will end up with
FV if you invest a sum of
money PV for n years at r
% interest
15. Internal Rate of Return Bigger is better (IRR) Not required for the exam
16. Benefit Cost Ratio Bigger is better ((BCR or Benefit / Cost) revenue
or payback VS. cost)
Or PV or Revenue / PV of Cost
17. Payback Period Less is better
Net Investment / Avg. Annual cash flow.
The project with the
shorted period is better and
should be selected.
18. BCWS PV
19. BCWP EV
20. ACWP AC
21. Order of Magnitude
Estimate
-25% - +75% (-50 to +100% PMBOK)
22. Budget Estimate -10% - +25%
23. Definitive Estimate -5% - +10%
24. Comm. Channels N (N -1)/2 – N #of People in one team
25. Expected Monetary
Value
Probability * Impact
26. Point of Total
Assumption (PTA)
((Ceiling Price - Target Price)/buyer's Share
Ratio) + Target Cost
Sigma σ  1σ = 68.27%
 2σ = 95.45%
 3σ = 99.73%
 6σ = 99.99985%

Return on Sales (ROS) Net Income Before Taxes (NEBT) / Total Sales
OR
Net Income After Taxes (NEAT) / Total Sales
Return on Assets (ROA) NEBT / Total Assets OR
NEAT / Total Assets
Return on Investment (ROI) NEBT / Total Investment OR
NEAT / Total Investment
Working Capital Current Assets - Current Liabilities
Discounted Cash Flow Cash Flow X Discount Factor
Contract related formulas Savings = Target Cost – Actual Cost
Bonus = Savings x Percentage
Contract Cost = Bonus + Fees
Total Cost = Actual Cost + Contract Cost
Free Float ES of following activity – ES of present activity –
Duration pf present activity
Number of days this activity
can be delayed without
delaying the early start of
the next activity
Total Float LS- ES or LF-EF Number of days this activity
can be delayed without
delaying the project
Early Finish (EF) ES+duration-1 Day on which this activity
can finish earliest
Early Start (ES) EF of Predecessor +1 Day on which this activity
can start earliest
Late Finish (LF) LS of successor -1 Day on which this activity
can finish latest
Late Start (LS) LF - duration +1 Day on which this activity
can start latest
Critical Path formulas
Forward Pass: (Add 1 day to Early Start)
EF = (ES + Duration - 1)
Backward Pass: (Minus 1 day to Late Finish)
LS = (LF - Duration + 1)
ES = Early Start; EF = Early Finish;
LS = Late Start; LF = Late Finish
EVA = Net Operating Profit After Tax - Cost of Capital (Revenue - Op. Exp - Taxes) - (Investment Capital X % Cost of
Capital) EVA - Economic Value Add Benefit Measurement - Bigger is better
Source Selection = (Weightage X Price) + (Weightage X Quality)

More Related Content

What's hot

Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
ADITYA GHUMARE
 
PROJECT CHARTER
PROJECT CHARTERPROJECT CHARTER
PROJECT CHARTER
Muneeb HaXan
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
Ciprian Rusen
 
Linear Scheduling 101
Linear Scheduling 101Linear Scheduling 101
Linear Scheduling 101
James Wonneberg, PE, CCM
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path method
Prathima Girish
 
Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...
Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...
Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...
SlideTeam
 
Project scope statement template v2.3
Project scope statement template v2.3Project scope statement template v2.3
Project scope statement template v2.3
Aditya Pandey
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2
danieljohn810
 
6.3 sequence activities
6.3 sequence activities6.3 sequence activities
6.3 sequence activities
PMVISION Training
 
Primavera training 02- Creating a new project
Primavera training  02- Creating a new projectPrimavera training  02- Creating a new project
Primavera training 02- Creating a new project
Civil Millennium Design Complex (CMDC)
 
Project Status Report With Budget Estimation And Milestones Printable Report ...
Project Status Report With Budget Estimation And Milestones Printable Report ...Project Status Report With Budget Estimation And Milestones Printable Report ...
Project Status Report With Budget Estimation And Milestones Printable Report ...
SlideTeam
 
Project Controls Framework
Project Controls FrameworkProject Controls Framework
Project Controls FrameworkReuben Gonzales
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure ReportCheryl Burcham
 
Building Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms ProjectBuilding Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms Project
Relu Rosenberg
 
Network scheduling
Network scheduling Network scheduling
Network scheduling
Abhijit Abhik Das
 
Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
Dr Ezzat Mansour
 
Project Closure Powerpoint Presentation Slides
Project Closure Powerpoint Presentation SlidesProject Closure Powerpoint Presentation Slides
Project Closure Powerpoint Presentation Slides
SlideTeam
 
Pmp formulas
Pmp formulasPmp formulas
Pmp formulas
FARISH V M
 

What's hot (20)

Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
PROJECT CHARTER
PROJECT CHARTERPROJECT CHARTER
PROJECT CHARTER
 
EP Project Charter OpenWells2.3
EP Project Charter OpenWells2.3EP Project Charter OpenWells2.3
EP Project Charter OpenWells2.3
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Linear Scheduling 101
Linear Scheduling 101Linear Scheduling 101
Linear Scheduling 101
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path method
 
Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...
Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...
Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...
 
Project scope statement template v2.3
Project scope statement template v2.3Project scope statement template v2.3
Project scope statement template v2.3
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2
 
6.3 sequence activities
6.3 sequence activities6.3 sequence activities
6.3 sequence activities
 
Primavera training 02- Creating a new project
Primavera training  02- Creating a new projectPrimavera training  02- Creating a new project
Primavera training 02- Creating a new project
 
Project Status Report With Budget Estimation And Milestones Printable Report ...
Project Status Report With Budget Estimation And Milestones Printable Report ...Project Status Report With Budget Estimation And Milestones Printable Report ...
Project Status Report With Budget Estimation And Milestones Printable Report ...
 
Project Controls Framework
Project Controls FrameworkProject Controls Framework
Project Controls Framework
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure Report
 
Building Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms ProjectBuilding Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms Project
 
Network scheduling
Network scheduling Network scheduling
Network scheduling
 
Project Management
Project ManagementProject Management
Project Management
 
Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
 
Project Closure Powerpoint Presentation Slides
Project Closure Powerpoint Presentation SlidesProject Closure Powerpoint Presentation Slides
Project Closure Powerpoint Presentation Slides
 
Pmp formulas
Pmp formulasPmp formulas
Pmp formulas
 

Viewers also liked

ASSESSMENT DEVELOPMENT CENTRE
ASSESSMENT DEVELOPMENT CENTREASSESSMENT DEVELOPMENT CENTRE
ASSESSMENT DEVELOPMENT CENTREpritinashikkar
 
Formula List Math 1230
Formula List Math 1230Formula List Math 1230
Formula List Math 1230
samhui48
 
Jeopardy math - geometry
Jeopardy   math - geometryJeopardy   math - geometry
Jeopardy math - geometry
kbrach
 
Sex and relationships education 2015
Sex and relationships education 2015Sex and relationships education 2015
Sex and relationships education 2015
Chris Hildrew
 
The Sales Formula Interactive Pdf
The Sales Formula Interactive PdfThe Sales Formula Interactive Pdf
The Sales Formula Interactive Pdf
lizgilmour
 
Gas lawsjeopardy
Gas lawsjeopardyGas lawsjeopardy
Gas lawsjeopardy
jpalmertree
 
Intro to Perimeter, Area and Volume
Intro to Perimeter, Area and VolumeIntro to Perimeter, Area and Volume
Intro to Perimeter, Area and Volumeiteclearners
 
Math 114 formulas of whole session for okanagan college students
Math 114   formulas of whole session for okanagan college studentsMath 114   formulas of whole session for okanagan college students
Math 114 formulas of whole session for okanagan college students
Jach Inder
 
COMMON MATH FORMULAS
COMMON MATH FORMULASCOMMON MATH FORMULAS
COMMON MATH FORMULAS
hannagrauser1
 
presentationMs excel
presentationMs excelpresentationMs excel
presentationMs excel
Tanveer Ahmed
 
Adoloscent education
Adoloscent educationAdoloscent education
Adoloscent education
Avinash Bhondwe
 
Sex Education : Come out of the Taboo
Sex Education : Come out of the TabooSex Education : Come out of the Taboo
Sex Education : Come out of the Taboo
ABDULLAH AL MUHSI
 
Math of Sales: Your Formula for Sales Success
Math of Sales: Your Formula for Sales SuccessMath of Sales: Your Formula for Sales Success
Math of Sales: Your Formula for Sales Success
DK New Media
 
Statutory Interpretation 2
Statutory Interpretation 2Statutory Interpretation 2
Statutory Interpretation 2thorogl01
 
Handa ka funda math formulas 5.0
Handa ka funda   math formulas 5.0Handa ka funda   math formulas 5.0
Handa ka funda math formulas 5.0
Chandan Kumar
 

Viewers also liked (17)

Traduccion
TraduccionTraduccion
Traduccion
 
ASSESSMENT DEVELOPMENT CENTRE
ASSESSMENT DEVELOPMENT CENTREASSESSMENT DEVELOPMENT CENTRE
ASSESSMENT DEVELOPMENT CENTRE
 
Formula List Math 1230
Formula List Math 1230Formula List Math 1230
Formula List Math 1230
 
Jeopardy math - geometry
Jeopardy   math - geometryJeopardy   math - geometry
Jeopardy math - geometry
 
Sex and relationships education 2015
Sex and relationships education 2015Sex and relationships education 2015
Sex and relationships education 2015
 
The Sales Formula Interactive Pdf
The Sales Formula Interactive PdfThe Sales Formula Interactive Pdf
The Sales Formula Interactive Pdf
 
Gas lawsjeopardy
Gas lawsjeopardyGas lawsjeopardy
Gas lawsjeopardy
 
Intro to Perimeter, Area and Volume
Intro to Perimeter, Area and VolumeIntro to Perimeter, Area and Volume
Intro to Perimeter, Area and Volume
 
Math 114 formulas of whole session for okanagan college students
Math 114   formulas of whole session for okanagan college studentsMath 114   formulas of whole session for okanagan college students
Math 114 formulas of whole session for okanagan college students
 
COMMON MATH FORMULAS
COMMON MATH FORMULASCOMMON MATH FORMULAS
COMMON MATH FORMULAS
 
Body image
Body imageBody image
Body image
 
presentationMs excel
presentationMs excelpresentationMs excel
presentationMs excel
 
Adoloscent education
Adoloscent educationAdoloscent education
Adoloscent education
 
Sex Education : Come out of the Taboo
Sex Education : Come out of the TabooSex Education : Come out of the Taboo
Sex Education : Come out of the Taboo
 
Math of Sales: Your Formula for Sales Success
Math of Sales: Your Formula for Sales SuccessMath of Sales: Your Formula for Sales Success
Math of Sales: Your Formula for Sales Success
 
Statutory Interpretation 2
Statutory Interpretation 2Statutory Interpretation 2
Statutory Interpretation 2
 
Handa ka funda math formulas 5.0
Handa ka funda   math formulas 5.0Handa ka funda   math formulas 5.0
Handa ka funda math formulas 5.0
 

Similar to Formulas for pmp exam

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Matt Stehling
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
Mark Troncone MBA, PMP, CBAP, ITILv3, CSM
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
RedhaElhuni
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Anand Subramaniam
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
Bhaskara Reddy Sannapureddy
 
PMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdfPMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdf
Saravanan Subramanian
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
Essam Lotffy, PMP®, CCP®
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
ProfDrAnbalaganChinn
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Vivek Prakash
 
Day 1 - Revision
Day 1  - RevisionDay 1  - Revision
Day 1 - Revision
Joyce Wong
 
Day 1 - Revision
Day 1 - RevisionDay 1 - Revision
Day 1 - Revision
Jeffrey Cheah
 
PMP - Math Formulas
PMP - Math FormulasPMP - Math Formulas
PMP - Math Formulas
gijoeusa
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
eidalin95
 
Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
KhalidMahmood253
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
Jamil Faraj , PMP
 
Formula pocket guide
Formula pocket guideFormula pocket guide
Formula pocket guide
Vicky Maly
 
Earned value management
Earned value managementEarned value management
Earned value management
Gautam Kumar
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
BECM, RUET, Bangladesh
 

Similar to Formulas for pmp exam (20)

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
PMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdfPMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdf
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 
Project Health.doc
Project Health.docProject Health.doc
Project Health.doc
 
Day 1 - Revision
Day 1  - RevisionDay 1  - Revision
Day 1 - Revision
 
Day 1 - Revision
Day 1 - RevisionDay 1 - Revision
Day 1 - Revision
 
PMP - Math Formulas
PMP - Math FormulasPMP - Math Formulas
PMP - Math Formulas
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
Formula pocket guide
Formula pocket guideFormula pocket guide
Formula pocket guide
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 

Recently uploaded

Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Dr. Vinod Kumar Kanvaria
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
David Douglas School District
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
Krisztián Száraz
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
Kartik Tiwari
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
kimdan468
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
Wasim Ak
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
chanes7
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Atul Kumar Singh
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 

Recently uploaded (20)

Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 

Formulas for pmp exam

  • 1. Formulas / Math for PMP Name (Abbreviation) Formula Interpretation (Result) 1. Program evaluation and review technique (PERT) (P + 4M + O)/ 6 Pessimistic, Most Likely, Optimistic Estimated duration of a schedule activity expressed as a weight average 2. PERT Standard Deviation (Single Activity) (P - O) / 6 Standard deviation from the mean of a schedule activity 3. PERT Activity Variance (AV) [(P - O)/6] ^2 The expected variance in the activity duration. For instance: +/- 3 days 4. PERT Standard Deviation (All Activity) √( 𝑃−𝑂 6 )^2 === √𝑉 Standard deviation from the mean of the given series activities 5. Float or Slack LS-ES and LF-EF LS: Late Start, ES: Early Start, LS: Late Finish, EF: Early Finish If = 0 on critical path If < 0 Behind schedule 6. Cost Variance (CV) EV – AC EV = Earned Value AC = Actual Cost < 0 Over budget (negative) = 0 On budget > 0 Within budget (positive) 7. Schedule Variance (SV) EV – PV PV = Planned Value < 0 Behind schedule = 0 On schedule > 0 Ahead of schedule 8. Cost Perf. Index (CPI) EV / AC < 1 Over budget = 1 On budget > 1 Under budget 9. Sched. Perf. Index (SPI) EV / PV < 1 behind schedule = 1 on schedule > 1 ahead of schedule 10. Est. At Completion (EAC) BAC / CPI -- CPI remains the same - if the CPI would remain the same till end of project, i.e. the original estimation is not accurate. - Use formula if no variances from the BAC have occurred or are expected to continue at the same rate of spending. original budget modified by the cost performance. The result is a monetary value. AC + ETC -- Initial Estimates are flawed (original is flawed) - if the original estimate is based on wrong data/assumptions or circumstances have changed. - Use formula if original estimate was fundamentally flawed or condition have Actual cost plus a new estimate for the remaining work. The result is a monetary value.
  • 2. change and invalided original estimating assumption AC + BAC - EV -- Future variance is Atypical (BAC remains the same) - the variance is caused by a one-time event and is not likely to happen again. - Use formula if current variances are thought to be atypical in the future. Actual cost to date plus remaining budget. Result is monetary value. AC + (BAC - EV) / CPI -- Future Variance would be typical - Use formula if current variances are thought to be typical in the future. Actual cost to date plus remaining budget, result is monetary value. BAC = Budget at completion New ETC = New Estimate to Completion 11. Est. To Complete (ETC) Percentage complete EAC – AC -- we recommended using it, if no keywords are given. EV/ BAC *100 -- in percentage Result is a monetary value that will tell us how much more the project will cost 12. Var. At Completion (VAC) BAC – EAC The different between the originally estimated BAC and a newly calculated EAC < 0 Over budget = 0 On budget > 0 Under budget 13. To Complete Performance Index (TCPI) Values for the TCPI index of less than 1.0 is good because it indicates the efficiency to complete is less than planned. How efficient must the project team be to complete the remaining work with the remaining money? (BAC - EV) / (BAC - AC); remaining work / remaining funds < 1 Under budget = 1 On budget > 1 Over budget 13. Net Present Value Method for financial evaluation long term project, not required for the exam Bigger is better (NPV) 14. Present Value PV FV / (1 + r) ^n Receiving money in the future has different value than receiving money in the present(today). This formula calculated how much. The result is the amount of money you will end up with FV if you invest a sum of money PV for n years at r % interest 15. Internal Rate of Return Bigger is better (IRR) Not required for the exam 16. Benefit Cost Ratio Bigger is better ((BCR or Benefit / Cost) revenue or payback VS. cost) Or PV or Revenue / PV of Cost 17. Payback Period Less is better Net Investment / Avg. Annual cash flow. The project with the shorted period is better and should be selected. 18. BCWS PV 19. BCWP EV 20. ACWP AC 21. Order of Magnitude Estimate -25% - +75% (-50 to +100% PMBOK) 22. Budget Estimate -10% - +25% 23. Definitive Estimate -5% - +10%
  • 3. 24. Comm. Channels N (N -1)/2 – N #of People in one team 25. Expected Monetary Value Probability * Impact 26. Point of Total Assumption (PTA) ((Ceiling Price - Target Price)/buyer's Share Ratio) + Target Cost Sigma σ  1σ = 68.27%  2σ = 95.45%  3σ = 99.73%  6σ = 99.99985%  Return on Sales (ROS) Net Income Before Taxes (NEBT) / Total Sales OR Net Income After Taxes (NEAT) / Total Sales Return on Assets (ROA) NEBT / Total Assets OR NEAT / Total Assets Return on Investment (ROI) NEBT / Total Investment OR NEAT / Total Investment Working Capital Current Assets - Current Liabilities Discounted Cash Flow Cash Flow X Discount Factor Contract related formulas Savings = Target Cost – Actual Cost Bonus = Savings x Percentage Contract Cost = Bonus + Fees Total Cost = Actual Cost + Contract Cost Free Float ES of following activity – ES of present activity – Duration pf present activity Number of days this activity can be delayed without delaying the early start of the next activity Total Float LS- ES or LF-EF Number of days this activity can be delayed without delaying the project Early Finish (EF) ES+duration-1 Day on which this activity can finish earliest Early Start (ES) EF of Predecessor +1 Day on which this activity can start earliest Late Finish (LF) LS of successor -1 Day on which this activity can finish latest Late Start (LS) LF - duration +1 Day on which this activity can start latest
  • 4. Critical Path formulas Forward Pass: (Add 1 day to Early Start) EF = (ES + Duration - 1) Backward Pass: (Minus 1 day to Late Finish) LS = (LF - Duration + 1) ES = Early Start; EF = Early Finish; LS = Late Start; LF = Late Finish EVA = Net Operating Profit After Tax - Cost of Capital (Revenue - Op. Exp - Taxes) - (Investment Capital X % Cost of Capital) EVA - Economic Value Add Benefit Measurement - Bigger is better Source Selection = (Weightage X Price) + (Weightage X Quality)