SlideShare a Scribd company logo
“PMP® Certification Readiness”
Training Program
Module:Module:
Earned Value and Budget ForecastingEarned Value and Budget ForecastingEarned Value and Budget ForecastingEarned Value and Budget Forecasting
Ravikumar Kalose N, PMP®
http://www.propmacademy.com
1
ProPM Academy - 2011
"PMP® Exam Prep Course"
Understanding –
• Measurements - Subjective Vs Objective
• What is Earned Value (EV)
• Work Performance MeasurementsWork Performance Measurements
• Budget Forecasts
• Performance measurement parameters
• Various formulae and their interpretation
2
ProPM Academy - 2011
"PMP® Exam Prep Course"
Green
OR Red
?
What
IF…??
?
Can defend the
current Project
StatusAssertive
Relies on assumptions, interpretations based on
high level work status
Lack of any measured data and facts
Project Health (Red/Amber/Green) is debatable
and subjective
Relies on measured values derived from triple
constraints – Scope, Time and Cost
Project Status reported based on defined matrix
Unambiguous, No Assumptions
Easily understandable by Stakeholders
ProPM Academy - 2011
"PMP® Exam Prep Course" 3
An objective method to measure project progress based on triple
constraints (Scope, Time, Cost)
EV measurements helps to determine if a project is on track
EV is an indicator of current project performance
Provides early warnings and trends on any cost, schedule over runs
Earned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value Characteristics
Earned value indicates how much of “value” you have “earned” on
the project at any given point of time.
Helps determine variance against Planned Value (PV).
ProPM Academy - 2011
"PMP® Exam Prep Course" 4
Let us consider the following example to understand the
concepts better
An ERP implementation project for ABC company is estimated
to cost $500,000 with an estimated duration of 40 weeks.At
the end of 10 weeks the project is 20% complete withthe end of 10 weeks the project is 20% complete with
$150,000 being already spent on the project.
BAC =500,000,AC = 150,000
PV = 10/40*500,000 = 125,000
EV = 20/100*500,000 = 100,000
ProPM Academy - 2011
"PMP® Exam Prep Course" 5
ProPM Academy - 2011
"PMP® Exam Prep Course" 6
BAC = 500,000BAC = 500,000BAC = 500,000BAC = 500,000 PV = 125,000PV = 125,000PV = 125,000PV = 125,000 EV = 100,000EV = 100,000EV = 100,000EV = 100,000 AC = 150,000AC = 150,000AC = 150,000AC = 150,000
MetricMetricMetricMetric FormulaFormulaFormulaFormula ValueValueValueValue AnalysisAnalysisAnalysisAnalysis
CV EV-AC -50,000 This indicates $50,000 has already been
additionally spent in excess of the project worth of
work up-to this point
ProPM Academy - 2011
"PMP® Exam Prep Course" 7
SV EV-PV -25000 The negative value indicates the project is lagging
behind its planned schedule.
CPI EV/AC 0.67 A value less than 1 indicates over utilization of
funds against the actual work. In this case the
project is earning $0.67 worth value for every $
spent, not a good sign.
SPI EV/PV 0.80 A value less than 1 indicates that the project is
behind planned schedule and progress has only
been at 80% .
SV
CV
ProPM Academy - 2011
"PMP® Exam Prep Course" 8
MetricMetricMetricMetric FormulaFormulaFormulaFormula ValueValueValueValue AnalysisAnalysisAnalysisAnalysis
EAC BAC/CPI 746,268.65 The revised estimates now for project
completion based on current performance is
$746,268.65 as against planned $500,000.
BAC = 500,000BAC = 500,000BAC = 500,000BAC = 500,000 PV = 125,000PV = 125,000PV = 125,000PV = 125,000 EV = 100,000EV = 100,000EV = 100,000EV = 100,000 AC = 150,000AC = 150,000AC = 150,000AC = 150,000
CV = -50,000 SV = -25,000 CPI = 0.67 SPI = 0.80
ETC EAC-AC 596,268.65 The project would now require $596,268.65
to complete
VAC BAC-EAC -246,268.65 There is an additional $246,268.65 required
to complete the project compared to original
estimates
TCPI (BAC-EV)/(BAC-AC)
(WORK LEFT TO
DO)/ MONEY
REMAINING)
1.14 The project need to now perform at 1.14 times
in order to stay within the estimated budget
ProPM Academy - 2011
"PMP® Exam Prep Course" 9
Terminology Description Formula
Budget At CompletionBudget At CompletionBudget At CompletionBudget At Completion
(BAC)(BAC)(BAC)(BAC)
The original estimated (planned) project CostThe original estimated (planned) project CostThe original estimated (planned) project CostThe original estimated (planned) project Cost NoneNoneNoneNone
Planned Value (PV)Planned Value (PV)Planned Value (PV)Planned Value (PV) Indicates amount of work which “SHOULD haveIndicates amount of work which “SHOULD haveIndicates amount of work which “SHOULD haveIndicates amount of work which “SHOULD have
been completed” or “Authorized work forbeen completed” or “Authorized work forbeen completed” or “Authorized work forbeen completed” or “Authorized work for
completion” as per plan at any pointcompletion” as per plan at any pointcompletion” as per plan at any pointcompletion” as per plan at any point
PV=Planned %PV=Planned %PV=Planned %PV=Planned %
complete X BACcomplete X BACcomplete X BACcomplete X BAC
Earned Value (EV)Earned Value (EV)Earned Value (EV)Earned Value (EV) Actual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any point EV= Actual %EV= Actual %EV= Actual %EV= Actual %
ProPM Academy - 2011
"PMP® Exam Prep Course" 10
Earned Value (EV)Earned Value (EV)Earned Value (EV)Earned Value (EV) Actual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any point EV= Actual %EV= Actual %EV= Actual %EV= Actual %
complete X BACcomplete X BACcomplete X BACcomplete X BAC
Actual Cost (AC)Actual Cost (AC)Actual Cost (AC)Actual Cost (AC) The actual money spent at any point of timeThe actual money spent at any point of timeThe actual money spent at any point of timeThe actual money spent at any point of time AC= CumulativeAC= CumulativeAC= CumulativeAC= Cumulative
money spent till datemoney spent till datemoney spent till datemoney spent till date
Cost Variance (CV)Cost Variance (CV)Cost Variance (CV)Cost Variance (CV) The difference between howThe difference between howThe difference between howThe difference between how much was actuallymuch was actuallymuch was actuallymuch was actually
EarnedEarnedEarnedEarned and how muchand how muchand how muchand how much was awas awas awas actually spentctually spentctually spentctually spent
CV=EVCV=EVCV=EVCV=EV----ACACACAC
ScheduleScheduleScheduleSchedule Variance (SV)Variance (SV)Variance (SV)Variance (SV) The difference between plannedThe difference between plannedThe difference between plannedThe difference between planned schedule Vsschedule Vsschedule Vsschedule Vs
Actual ScheduleActual ScheduleActual ScheduleActual Schedule
SV = EVSV = EVSV = EVSV = EV----PVPVPVPV
TerminologyTerminologyTerminologyTerminology DescriptionDescriptionDescriptionDescription FormulaFormulaFormulaFormula
CostCostCostCost Performance IndexPerformance IndexPerformance IndexPerformance Index
(CPI)(CPI)(CPI)(CPI)
Indicates the projectIndicates the projectIndicates the projectIndicates the project performance for every $performance for every $performance for every $performance for every $
spentspentspentspent
CPCPCPCPI = EV / ACI = EV / ACI = EV / ACI = EV / AC
Schedule PerformanceSchedule PerformanceSchedule PerformanceSchedule Performance
Index (SPI)Index (SPI)Index (SPI)Index (SPI)
Indicate actualIndicate actualIndicate actualIndicate actual schedule progress of theschedule progress of theschedule progress of theschedule progress of the
against the planned scheduleagainst the planned scheduleagainst the planned scheduleagainst the planned schedule
SPI = EV / PVSPI = EV / PVSPI = EV / PVSPI = EV / PV
Estimate At CompletionEstimate At CompletionEstimate At CompletionEstimate At Completion
(EAC)(EAC)(EAC)(EAC)
TheTheTheThe revised project Budget for completionrevised project Budget for completionrevised project Budget for completionrevised project Budget for completion
based on current performance indicatorsbased on current performance indicatorsbased on current performance indicatorsbased on current performance indicators
EAC = BAC /EAC = BAC /EAC = BAC /EAC = BAC /
Cumulative CPICumulative CPICumulative CPICumulative CPI
Estimate To CompleteEstimate To CompleteEstimate To CompleteEstimate To Complete
(ETC)(ETC)(ETC)(ETC)
How much more (cost)How much more (cost)How much more (cost)How much more (cost) would be needed towould be needed towould be needed towould be needed to
complete the project based on currentcomplete the project based on currentcomplete the project based on currentcomplete the project based on current
performance indicatorsperformance indicatorsperformance indicatorsperformance indicators
ETC = EACETC = EACETC = EACETC = EAC –––– ACACACAC
Variance At CompletionVariance At CompletionVariance At CompletionVariance At Completion
(VAC)(VAC)(VAC)(VAC)
TheTheTheThe difference between the budgeted costdifference between the budgeted costdifference between the budgeted costdifference between the budgeted cost
and revised estimates based on currentand revised estimates based on currentand revised estimates based on currentand revised estimates based on current
performance indicatorsperformance indicatorsperformance indicatorsperformance indicators
VAC = BACVAC = BACVAC = BACVAC = BAC –––– EACEACEACEAC
ToToToTo----CompleteCompleteCompleteComplete
Performance Index (TCPI)Performance Index (TCPI)Performance Index (TCPI)Performance Index (TCPI)
ProjectProjectProjectProject Performance required to be achievedPerformance required to be achievedPerformance required to be achievedPerformance required to be achieved
in order to stay within the original budgetin order to stay within the original budgetin order to stay within the original budgetin order to stay within the original budget
using the remaining fundsusing the remaining fundsusing the remaining fundsusing the remaining funds
TCPI = (BACTCPI = (BACTCPI = (BACTCPI = (BAC----EV) /EV) /EV) /EV) /
(BAC(BAC(BAC(BAC----AC)AC)AC)AC)
ProPM Academy - 2011
"PMP® Exam Prep Course" 11
Variance Value (SV, CV, VAC) :Variance Value (SV, CV, VAC) :Variance Value (SV, CV, VAC) :Variance Value (SV, CV, VAC) : If Negative, it is below planned performance,
If Positive, it is above planned performance
If Zero, it is exactly meeting the planned
performance
Performance Index (CPI,SPI):Performance Index (CPI,SPI):Performance Index (CPI,SPI):Performance Index (CPI,SPI): If the Value is less than 1, it is below planned
performance
If the Value is more than 1, it is above
planned performance
ProPM Academy - 2011
"PMP® Exam Prep Course" 12
planned performance
If the Value is equal to 1, it is exactly meeting
the planned performance
TCPI:TCPI:TCPI:TCPI: If the Value is Less than 1, it is above
planned performance
If the Value is more than 1, it is below
planned performance
If the Value is Equal to 1, it is exactly meeting
the planned performance
ProPM Academy - 2011
"PMP® Exam Prep Course" 13
http://www.propmacademy.com
Learn, Apply, Deliver, Succeed
Thank You
ProPM Academy - 2011
"PMP® Exam Prep Course" 14
Thank You

More Related Content

What's hot

PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
Edureka!
 
Project integration management
Project  integration managementProject  integration management
Project integration management
deep sharma
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
M Maged Hegazy, LLM, MBA, CCP, P3O
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
Anand Bobade
 
PMP Training - 05 project scope management
PMP Training - 05 project scope managementPMP Training - 05 project scope management
PMP Training - 05 project scope managementejlp12
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Saqib Raza
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
Procept Associates
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
Anand Bobade
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
Maher Almohamad
 
10 Project Management Knowledge Areas
10 Project Management Knowledge Areas10 Project Management Knowledge Areas
10 Project Management Knowledge Areas
Elizabeth Harrin FAPM
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
Ciprian Rusen
 
How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)
Insaf Ali Soomro PMP
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 
Projects, programmes and portfolios, so what is the difference?
Projects, programmes and portfolios, so what is the difference?Projects, programmes and portfolios, so what is the difference?
Projects, programmes and portfolios, so what is the difference?
Association for Project Management
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
Robert Kelly
 
project management
project managementproject management
project management
Patrick McPartland, E.I.T.
 
Project scope management
Project scope managementProject scope management
Project scope management
Anit Roy
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality managementejlp12
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
Anand Bobade
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
Agus Suhanto
 

What's hot (20)

PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
 
Project integration management
Project  integration managementProject  integration management
Project integration management
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
PMP Training - 05 project scope management
PMP Training - 05 project scope managementPMP Training - 05 project scope management
PMP Training - 05 project scope management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
 
10 Project Management Knowledge Areas
10 Project Management Knowledge Areas10 Project Management Knowledge Areas
10 Project Management Knowledge Areas
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Projects, programmes and portfolios, so what is the difference?
Projects, programmes and portfolios, so what is the difference?Projects, programmes and portfolios, so what is the difference?
Projects, programmes and portfolios, so what is the difference?
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
project management
project managementproject management
project management
 
Project scope management
Project scope managementProject scope management
Project scope management
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality management
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 

Viewers also liked

Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVAAhmed Bamasdoos
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
Ricardo Viana Vargas
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
G K, BE,MS,ISTQB Certified Expert
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Ahmed Rami Elsherif, PMP, ITBMC
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
Nikhil Raj
 
Cost Reduction of a product through Value Analysis & Value Engineering
Cost Reduction of a product through Value Analysis & Value EngineeringCost Reduction of a product through Value Analysis & Value Engineering
Cost Reduction of a product through Value Analysis & Value EngineeringQuEST Global
 

Viewers also liked (6)

Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVA
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Cost Reduction of a product through Value Analysis & Value Engineering
Cost Reduction of a product through Value Analysis & Value EngineeringCost Reduction of a product through Value Analysis & Value Engineering
Cost Reduction of a product through Value Analysis & Value Engineering
 

Similar to Earned value analysis - presentation

A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
ProPM Academy
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
Najm Naqvi
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Tipsographic . com
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
Baroness PM
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
Bhaskara Reddy Sannapureddy
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Russell Taylor BEng CEng FAPM FIET
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
Anand Bobade
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
ProfDrAnbalaganChinn
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
Essam Lotffy, PMP®, CCP®
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
guy_davis
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indicesGlen Alleman
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
Harshit Mahajan
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
Nabeel Ahmad
 
PMP - Math Formulas
PMP - Math FormulasPMP - Math Formulas
PMP - Math Formulas
gijoeusa
 

Similar to Earned value analysis - presentation (20)

A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Project Health.doc
Project Health.docProject Health.doc
Project Health.doc
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
PMP - Math Formulas
PMP - Math FormulasPMP - Math Formulas
PMP - Math Formulas
 

Recently uploaded

A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
Nguyen Thanh Tu Collection
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
Peter Windle
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
Levi Shapiro
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 

Recently uploaded (20)

A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 

Earned value analysis - presentation

  • 1. “PMP® Certification Readiness” Training Program Module:Module: Earned Value and Budget ForecastingEarned Value and Budget ForecastingEarned Value and Budget ForecastingEarned Value and Budget Forecasting Ravikumar Kalose N, PMP® http://www.propmacademy.com 1 ProPM Academy - 2011 "PMP® Exam Prep Course"
  • 2. Understanding – • Measurements - Subjective Vs Objective • What is Earned Value (EV) • Work Performance MeasurementsWork Performance Measurements • Budget Forecasts • Performance measurement parameters • Various formulae and their interpretation 2 ProPM Academy - 2011 "PMP® Exam Prep Course"
  • 3. Green OR Red ? What IF…?? ? Can defend the current Project StatusAssertive Relies on assumptions, interpretations based on high level work status Lack of any measured data and facts Project Health (Red/Amber/Green) is debatable and subjective Relies on measured values derived from triple constraints – Scope, Time and Cost Project Status reported based on defined matrix Unambiguous, No Assumptions Easily understandable by Stakeholders ProPM Academy - 2011 "PMP® Exam Prep Course" 3
  • 4. An objective method to measure project progress based on triple constraints (Scope, Time, Cost) EV measurements helps to determine if a project is on track EV is an indicator of current project performance Provides early warnings and trends on any cost, schedule over runs Earned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value Characteristics Earned value indicates how much of “value” you have “earned” on the project at any given point of time. Helps determine variance against Planned Value (PV). ProPM Academy - 2011 "PMP® Exam Prep Course" 4
  • 5. Let us consider the following example to understand the concepts better An ERP implementation project for ABC company is estimated to cost $500,000 with an estimated duration of 40 weeks.At the end of 10 weeks the project is 20% complete withthe end of 10 weeks the project is 20% complete with $150,000 being already spent on the project. BAC =500,000,AC = 150,000 PV = 10/40*500,000 = 125,000 EV = 20/100*500,000 = 100,000 ProPM Academy - 2011 "PMP® Exam Prep Course" 5
  • 6. ProPM Academy - 2011 "PMP® Exam Prep Course" 6
  • 7. BAC = 500,000BAC = 500,000BAC = 500,000BAC = 500,000 PV = 125,000PV = 125,000PV = 125,000PV = 125,000 EV = 100,000EV = 100,000EV = 100,000EV = 100,000 AC = 150,000AC = 150,000AC = 150,000AC = 150,000 MetricMetricMetricMetric FormulaFormulaFormulaFormula ValueValueValueValue AnalysisAnalysisAnalysisAnalysis CV EV-AC -50,000 This indicates $50,000 has already been additionally spent in excess of the project worth of work up-to this point ProPM Academy - 2011 "PMP® Exam Prep Course" 7 SV EV-PV -25000 The negative value indicates the project is lagging behind its planned schedule. CPI EV/AC 0.67 A value less than 1 indicates over utilization of funds against the actual work. In this case the project is earning $0.67 worth value for every $ spent, not a good sign. SPI EV/PV 0.80 A value less than 1 indicates that the project is behind planned schedule and progress has only been at 80% .
  • 8. SV CV ProPM Academy - 2011 "PMP® Exam Prep Course" 8
  • 9. MetricMetricMetricMetric FormulaFormulaFormulaFormula ValueValueValueValue AnalysisAnalysisAnalysisAnalysis EAC BAC/CPI 746,268.65 The revised estimates now for project completion based on current performance is $746,268.65 as against planned $500,000. BAC = 500,000BAC = 500,000BAC = 500,000BAC = 500,000 PV = 125,000PV = 125,000PV = 125,000PV = 125,000 EV = 100,000EV = 100,000EV = 100,000EV = 100,000 AC = 150,000AC = 150,000AC = 150,000AC = 150,000 CV = -50,000 SV = -25,000 CPI = 0.67 SPI = 0.80 ETC EAC-AC 596,268.65 The project would now require $596,268.65 to complete VAC BAC-EAC -246,268.65 There is an additional $246,268.65 required to complete the project compared to original estimates TCPI (BAC-EV)/(BAC-AC) (WORK LEFT TO DO)/ MONEY REMAINING) 1.14 The project need to now perform at 1.14 times in order to stay within the estimated budget ProPM Academy - 2011 "PMP® Exam Prep Course" 9
  • 10. Terminology Description Formula Budget At CompletionBudget At CompletionBudget At CompletionBudget At Completion (BAC)(BAC)(BAC)(BAC) The original estimated (planned) project CostThe original estimated (planned) project CostThe original estimated (planned) project CostThe original estimated (planned) project Cost NoneNoneNoneNone Planned Value (PV)Planned Value (PV)Planned Value (PV)Planned Value (PV) Indicates amount of work which “SHOULD haveIndicates amount of work which “SHOULD haveIndicates amount of work which “SHOULD haveIndicates amount of work which “SHOULD have been completed” or “Authorized work forbeen completed” or “Authorized work forbeen completed” or “Authorized work forbeen completed” or “Authorized work for completion” as per plan at any pointcompletion” as per plan at any pointcompletion” as per plan at any pointcompletion” as per plan at any point PV=Planned %PV=Planned %PV=Planned %PV=Planned % complete X BACcomplete X BACcomplete X BACcomplete X BAC Earned Value (EV)Earned Value (EV)Earned Value (EV)Earned Value (EV) Actual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any point EV= Actual %EV= Actual %EV= Actual %EV= Actual % ProPM Academy - 2011 "PMP® Exam Prep Course" 10 Earned Value (EV)Earned Value (EV)Earned Value (EV)Earned Value (EV) Actual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any point EV= Actual %EV= Actual %EV= Actual %EV= Actual % complete X BACcomplete X BACcomplete X BACcomplete X BAC Actual Cost (AC)Actual Cost (AC)Actual Cost (AC)Actual Cost (AC) The actual money spent at any point of timeThe actual money spent at any point of timeThe actual money spent at any point of timeThe actual money spent at any point of time AC= CumulativeAC= CumulativeAC= CumulativeAC= Cumulative money spent till datemoney spent till datemoney spent till datemoney spent till date Cost Variance (CV)Cost Variance (CV)Cost Variance (CV)Cost Variance (CV) The difference between howThe difference between howThe difference between howThe difference between how much was actuallymuch was actuallymuch was actuallymuch was actually EarnedEarnedEarnedEarned and how muchand how muchand how muchand how much was awas awas awas actually spentctually spentctually spentctually spent CV=EVCV=EVCV=EVCV=EV----ACACACAC ScheduleScheduleScheduleSchedule Variance (SV)Variance (SV)Variance (SV)Variance (SV) The difference between plannedThe difference between plannedThe difference between plannedThe difference between planned schedule Vsschedule Vsschedule Vsschedule Vs Actual ScheduleActual ScheduleActual ScheduleActual Schedule SV = EVSV = EVSV = EVSV = EV----PVPVPVPV
  • 11. TerminologyTerminologyTerminologyTerminology DescriptionDescriptionDescriptionDescription FormulaFormulaFormulaFormula CostCostCostCost Performance IndexPerformance IndexPerformance IndexPerformance Index (CPI)(CPI)(CPI)(CPI) Indicates the projectIndicates the projectIndicates the projectIndicates the project performance for every $performance for every $performance for every $performance for every $ spentspentspentspent CPCPCPCPI = EV / ACI = EV / ACI = EV / ACI = EV / AC Schedule PerformanceSchedule PerformanceSchedule PerformanceSchedule Performance Index (SPI)Index (SPI)Index (SPI)Index (SPI) Indicate actualIndicate actualIndicate actualIndicate actual schedule progress of theschedule progress of theschedule progress of theschedule progress of the against the planned scheduleagainst the planned scheduleagainst the planned scheduleagainst the planned schedule SPI = EV / PVSPI = EV / PVSPI = EV / PVSPI = EV / PV Estimate At CompletionEstimate At CompletionEstimate At CompletionEstimate At Completion (EAC)(EAC)(EAC)(EAC) TheTheTheThe revised project Budget for completionrevised project Budget for completionrevised project Budget for completionrevised project Budget for completion based on current performance indicatorsbased on current performance indicatorsbased on current performance indicatorsbased on current performance indicators EAC = BAC /EAC = BAC /EAC = BAC /EAC = BAC / Cumulative CPICumulative CPICumulative CPICumulative CPI Estimate To CompleteEstimate To CompleteEstimate To CompleteEstimate To Complete (ETC)(ETC)(ETC)(ETC) How much more (cost)How much more (cost)How much more (cost)How much more (cost) would be needed towould be needed towould be needed towould be needed to complete the project based on currentcomplete the project based on currentcomplete the project based on currentcomplete the project based on current performance indicatorsperformance indicatorsperformance indicatorsperformance indicators ETC = EACETC = EACETC = EACETC = EAC –––– ACACACAC Variance At CompletionVariance At CompletionVariance At CompletionVariance At Completion (VAC)(VAC)(VAC)(VAC) TheTheTheThe difference between the budgeted costdifference between the budgeted costdifference between the budgeted costdifference between the budgeted cost and revised estimates based on currentand revised estimates based on currentand revised estimates based on currentand revised estimates based on current performance indicatorsperformance indicatorsperformance indicatorsperformance indicators VAC = BACVAC = BACVAC = BACVAC = BAC –––– EACEACEACEAC ToToToTo----CompleteCompleteCompleteComplete Performance Index (TCPI)Performance Index (TCPI)Performance Index (TCPI)Performance Index (TCPI) ProjectProjectProjectProject Performance required to be achievedPerformance required to be achievedPerformance required to be achievedPerformance required to be achieved in order to stay within the original budgetin order to stay within the original budgetin order to stay within the original budgetin order to stay within the original budget using the remaining fundsusing the remaining fundsusing the remaining fundsusing the remaining funds TCPI = (BACTCPI = (BACTCPI = (BACTCPI = (BAC----EV) /EV) /EV) /EV) / (BAC(BAC(BAC(BAC----AC)AC)AC)AC) ProPM Academy - 2011 "PMP® Exam Prep Course" 11
  • 12. Variance Value (SV, CV, VAC) :Variance Value (SV, CV, VAC) :Variance Value (SV, CV, VAC) :Variance Value (SV, CV, VAC) : If Negative, it is below planned performance, If Positive, it is above planned performance If Zero, it is exactly meeting the planned performance Performance Index (CPI,SPI):Performance Index (CPI,SPI):Performance Index (CPI,SPI):Performance Index (CPI,SPI): If the Value is less than 1, it is below planned performance If the Value is more than 1, it is above planned performance ProPM Academy - 2011 "PMP® Exam Prep Course" 12 planned performance If the Value is equal to 1, it is exactly meeting the planned performance TCPI:TCPI:TCPI:TCPI: If the Value is Less than 1, it is above planned performance If the Value is more than 1, it is below planned performance If the Value is Equal to 1, it is exactly meeting the planned performance
  • 13. ProPM Academy - 2011 "PMP® Exam Prep Course" 13 http://www.propmacademy.com Learn, Apply, Deliver, Succeed
  • 14. Thank You ProPM Academy - 2011 "PMP® Exam Prep Course" 14 Thank You