SlideShare a Scribd company logo
Presentation on
“Project formulation,evaluation
& monitoring”
By Avinash kumar
PROJECT
Characteristics of project
1. Objectives-Every project has aimed to achieve
certain objective.
Once the objective is achieved the project is
said to be completed .
2.Life cycle- stages of Life cycle are as follows:
a.conception
b.Design
c.Implementation
d.Commissoning
3. Definite time limit
4. Uniqueness
5. Change
6. Optimality
7. Control mechanism
Classification of projects
Phases in project cycle
1.Identification
2.Formulation
3.Appraisal
4.Implementation
5.Monitoring
6.Evaluation
project cycle
TIME VALUE OF MONEY
 It involves two types of cost-
1. Compounding cost:- Future value of present
sum is known as compounding.
 Formula: A=C(1+r)n
2. Discounting cost:- Present value of future
sum is called discounting.
 Formula:Present worth=R(A)/(1+r)n
Techniques of risk analysis
Following are the popular techniques :
1. Break even analysis
2. Sensitive analysis
3. Decision tree analysis
4. Monto carlo
5. Game theory
Break even analysis
Here we can find out break even point (BEP).
* BEP refers to the level of production at which
farmer neither incurred profit nor incurred
losses .
* Its also known as no-profit no loss situation.
Break even production = fixed cost
selling price per unit - variable cost per unit
Estimation of break Even point
Costs&returns(inRs)
Q
B
K
L
M
O
X
Y
S
Quantity
Where,
SM= Total fixed cost
SL= Total cost curve
OK= Total revenue curve
B= Break Even Point
OQ=Break-Even Quantity
Zoneof loss
Zoneof profit
SENSITIVE ANALYSIS
It’s a technique that measures change in
profitability level of the project caused by a
change in factors affecting the profitability
level.
Sensitive Analysis provides answer to the
folloeing questions –
what happens to the profitability level if……
1. Demand of the product fall down.
2. If selling price of the product fall down.
3. If the level of production is declined.
Evaluation techniques for
selection of profitable
project It is nothing but benefit cost analysis of
various aspects of a project.
 These techniques are divided into two
groups:
1.Non –discounted techniques
2.Discounted techniques
Non- discounted techniques
1. Payback period (PBP)
2. Average rate of return (ARR)
3. Urgency
Payback Period (PBP)
 It is the length of period required to get back
or recover orignal investment incurred on a
project through cash inflow or income.
 Payback period=Orignal investment/Annual
cash inflow.
 Thumb rule:Project which have minimum
PBP is selected.
Average rate of return
(ARR)
 This method is obtained by the formula :
AVERAGE INFLOW
AVERAGE OUTFLOW
 Thumb rule: A project having highest ARR
value is selected
Urgency
 Urgency : In this method no formula or
method is used. Only those projects are
selected which are urgently required.
Discounted techniques
It includes :
1. Net present worth (NPW)
2. Profitability index
3. Internal rate of return (IRR)
4. Discounted benefit cost ratio
Net Present Worth (NPW)
 This is the present worth of cash flow stream.
 It is referred as Net Present Value(NPV).
 NPW=P1/(1+i)t
+P2/(1+i)t
+....+Pn/(1+i)t
-C.
 P1=Net cash flow in first year,
 i=Discount rate,
 t=Time period,
 C=Initial cost of the investment.
 Thumb rule:A Project having +ve & max
value of NPW is selected.
Profitability Index (PI)
 It is ratio of net present values of cash flows
to the initial capital expenditure.
 PI = Present value of cash inflow/Present
value of cash outflow.
 Thumb rule: A Project with highest value of
Profitability index is selected
Internal Rate of Return (IRR)
 IRR is the discounted rate which makes NPV
equal to ZERO.
 IRR is calculated by TRIAL and ERROR
method.
 IRR=(Lower discount rate)+(Diff b/w the two
discont rates)*[(Present worth of the cash
flow at the lower discount rate)/(Absolute diff
b/w the present worths of the the cash flow at
two discount rates)]
Benefit Cost Ratio
 We compare the present worth of costs with
present worth of benefits.
 B-C Ratio =Present value of cash
inflow/Present value of cash outflow.
 Thumb rule: A project with highest B-C
Ratio is selected.
NETWORK BASED SCHEDULING
 It is a technique used for planning , scheduling
and controlling of a project.
 It is represented by graphical plan which consist
of activity and event.
 ACTIVITY: Any operation which consume
resources( man, material, time),has start point
and end point.
 Activity is represented by straight arrow with
circle at two points.

TYPES OF ACTIVITIES
1. PRECEEDING ACTIVITY: Activity which
occur immediately before the succeeding
activity.
2. SUCCEEDING ACTIVITY: Activity which
cannot be started until one or more activities
are completed.
3. DUMMY ACTIVITY: Activity which does not
consume resources. It is represented by
dotted arrow.
EVENT
 They are called nodes.
 It does not consume resources and time.
 Event is the beginning and end of an activity
and is represented by a circle at specific point
of time.
TYPES OF EVENTS
1. Merge event: It represent joint completion of
more than one activity.
2. Burst event: Event which represent the
beginning of more than one activity.
3. Merge and Burst event : It is for sometime
nerge and sometime burst.
ERRORS IN DRAWING A NETWORK
1. Looping: Drawing an endless loop in a
network .
2. Dangling: to disconnect an activity before
the completion of all the activities in a
network.
3. Redundancy: inserting the dummy activity in
a network diagram.
NETWOK SCHEDULING TECHNIQUE
 CPM: (Critical path method) represent a
logical sequence of an activity and events in a
project. The duration of all these paths are
added in the total duration of the path.
 The path that has a longer duration duration
is called critical path and activities drawn in
that path are critical activities.
FORWARD PATH COMPUTATION
In this method earliest start time of all the
events is is computed which begin from initial
event and move toward the final event.
BACKWARD PATH COMPUTATION
Here we calculate the latest time. This
method is start from last event and move
toward initial event.
Slack time: It is the diff b/w latest finish time
and earliest start time.
Activity float analysis
 A study of non- critical path with regard to free
time is necessary because it help in better
control of project implementation and better
allocation of resources.
 In critical path latest finish time and earliest start
time both are equal.
 The slack of the event is given by diff b/w the TL
and TE.
 The free time available for an activity is called
“float”.
TYPES OF FLOAT
1. Total float: It represents the max time by
whhich completion of an activity can be
delayed w/o affecting the project completion
time.
Total float=[Tl of head event-Te of tail event-
Duration of activity]
2. FREE
FLOAT
 Delay that can be permitted in an activity so
that succeeding activity in the path are not
affected.
3.INDEPENDENT FLOAT
 IT is the spare time available for an activity .
Project : formulation,evaluation and monitoring

More Related Content

What's hot

Detailed project report
Detailed project reportDetailed project report
Detailed project report
Selva Prakash
 
Technical analysis in project management
Technical analysis in project managementTechnical analysis in project management
Technical analysis in project management
Parminder Kaur
 
Ppt for Agricultural Project Planning Evaluation and Analysis in 2021
Ppt  for Agricultural Project Planning Evaluation and Analysis  in 2021Ppt  for Agricultural Project Planning Evaluation and Analysis  in 2021
Ppt for Agricultural Project Planning Evaluation and Analysis in 2021
Derresa Bulcha
 
PARTICIPATORY RURAL APPRAISAL
PARTICIPATORY  RURAL  APPRAISALPARTICIPATORY  RURAL  APPRAISAL
PARTICIPATORY RURAL APPRAISALPrabin Poudel
 
Financial & Economic Evaluation of projects
Financial & Economic Evaluation of projectsFinancial & Economic Evaluation of projects
Financial & Economic Evaluation of projects
amanideutsch
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
hoang tung
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)tomeh
 
advantage of farm mechanization in Nepal
 advantage of farm mechanization in Nepal    advantage of farm mechanization in Nepal
advantage of farm mechanization in Nepal
Aditya Mahato
 
Project Planning
Project PlanningProject Planning
Project Planning
Srinivasan Rengasamy
 
Project evalaution techniques
Project evalaution techniquesProject evalaution techniques
Project evalaution techniquesMohd Arif
 
Agriculture finance
Agriculture financeAgriculture finance
Agriculture finance
Dr. Shweta Uppadhyay
 
Project controls
Project controlsProject controls
Project controls
Ashok Kumar
 
Agricultural project planning
Agricultural project planningAgricultural project planning
Agricultural project planning
M'mama Sawaneh
 
Chapter 3 Project Identification BnFn.pptx
Chapter 3  Project Identification BnFn.pptxChapter 3  Project Identification BnFn.pptx
Chapter 3 Project Identification BnFn.pptx
FedaEtefa
 
Project formulation
Project formulationProject formulation
Project formulation
Rohit Malik
 
Project management cycle
Project management  cycleProject management  cycle
Project management cycle
Megha BHardwaj
 
Generation and Screening of Project Ideas
Generation and Screening of Project Ideas Generation and Screening of Project Ideas
Generation and Screening of Project Ideas
Vivek Goyal
 
STAKEHOLDER-IDENTIFICATION.pptx
STAKEHOLDER-IDENTIFICATION.pptxSTAKEHOLDER-IDENTIFICATION.pptx
STAKEHOLDER-IDENTIFICATION.pptx
Jo Balucanag - Bitonio
 

What's hot (20)

Detailed project report
Detailed project reportDetailed project report
Detailed project report
 
Technical analysis in project management
Technical analysis in project managementTechnical analysis in project management
Technical analysis in project management
 
Ppt for Agricultural Project Planning Evaluation and Analysis in 2021
Ppt  for Agricultural Project Planning Evaluation and Analysis  in 2021Ppt  for Agricultural Project Planning Evaluation and Analysis  in 2021
Ppt for Agricultural Project Planning Evaluation and Analysis in 2021
 
PARTICIPATORY RURAL APPRAISAL
PARTICIPATORY  RURAL  APPRAISALPARTICIPATORY  RURAL  APPRAISAL
PARTICIPATORY RURAL APPRAISAL
 
Financial & Economic Evaluation of projects
Financial & Economic Evaluation of projectsFinancial & Economic Evaluation of projects
Financial & Economic Evaluation of projects
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
advantage of farm mechanization in Nepal
 advantage of farm mechanization in Nepal    advantage of farm mechanization in Nepal
advantage of farm mechanization in Nepal
 
Resource allocation
Resource allocationResource allocation
Resource allocation
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Project evalaution techniques
Project evalaution techniquesProject evalaution techniques
Project evalaution techniques
 
Agriculture finance
Agriculture financeAgriculture finance
Agriculture finance
 
Project controls
Project controlsProject controls
Project controls
 
Project Life Cycle and Phases
Project Life Cycle and PhasesProject Life Cycle and Phases
Project Life Cycle and Phases
 
Agricultural project planning
Agricultural project planningAgricultural project planning
Agricultural project planning
 
Chapter 3 Project Identification BnFn.pptx
Chapter 3  Project Identification BnFn.pptxChapter 3  Project Identification BnFn.pptx
Chapter 3 Project Identification BnFn.pptx
 
Project formulation
Project formulationProject formulation
Project formulation
 
Project management cycle
Project management  cycleProject management  cycle
Project management cycle
 
Generation and Screening of Project Ideas
Generation and Screening of Project Ideas Generation and Screening of Project Ideas
Generation and Screening of Project Ideas
 
STAKEHOLDER-IDENTIFICATION.pptx
STAKEHOLDER-IDENTIFICATION.pptxSTAKEHOLDER-IDENTIFICATION.pptx
STAKEHOLDER-IDENTIFICATION.pptx
 

Viewers also liked

Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisal
Surya C D
 
Methodology For Formulation And Appraisal of a Project
Methodology For Formulation And Appraisal of a ProjectMethodology For Formulation And Appraisal of a Project
Methodology For Formulation And Appraisal of a Projectimrohan1
 
Project Monitoring & Evaluation
Project Monitoring & EvaluationProject Monitoring & Evaluation
Project Monitoring & Evaluation
Srinivasan Rengasamy
 
Project formulation
Project formulationProject formulation
Project formulationyuarchu
 
Project formulation by shalini
Project formulation by shaliniProject formulation by shalini
Project formulation by shaliniDr. Shalini Pandey
 
18611 project identification
18611 project identification18611 project identification
18611 project identificationSingh Deep
 
Project_Formulation
Project_FormulationProject_Formulation
Project_Formulationjorpetit
 
Project identification
Project  identificationProject  identification
Project identification
Vasanth Rvk
 
Monitoring and Evaluation Framework
Monitoring and Evaluation FrameworkMonitoring and Evaluation Framework
Monitoring and Evaluation Framework
Dr. Joy Kenneth Sala Biasong
 
Agriculture finnance
Agriculture  finnanceAgriculture  finnance
Agriculture finnance
Yagnesh sondarva
 
Farms loans and its procedural steps
Farms loans and its procedural steps Farms loans and its procedural steps
Farms loans and its procedural steps
tarzan1990
 
Dilli
DilliDilli
Sampoorna Grameen rozgar Yojna
Sampoorna Grameen rozgar YojnaSampoorna Grameen rozgar Yojna
Sampoorna Grameen rozgar Yojna
Joshin Thomas Cherian
 
Monitoring mgnrega
Monitoring mgnregaMonitoring mgnrega
Monitoring mgnrega
Dibyendu Sarkar, IAS
 
Afid project monitoring and evaluation practices and lessons
Afid project monitoring and evaluation  practices and lessonsAfid project monitoring and evaluation  practices and lessons
Afid project monitoring and evaluation practices and lessons
Rosemirta Birungi
 
Monitoring and evaluation (Part 1)
Monitoring and evaluation (Part 1)Monitoring and evaluation (Part 1)
Monitoring and evaluation (Part 1)
Vilimaka Foliaki
 
Project Monitoring and Evaluation
Project Monitoring and EvaluationProject Monitoring and Evaluation
Project Monitoring and Evaluation
Kirithika Thushyantha
 
NOMAD Project on Policy Formulation and Validation through non-moderated Crow...
NOMAD Project on Policy Formulation and Validation through non-moderated Crow...NOMAD Project on Policy Formulation and Validation through non-moderated Crow...
NOMAD Project on Policy Formulation and Validation through non-moderated Crow...
Yannis Charalabidis
 

Viewers also liked (20)

Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisal
 
Methodology For Formulation And Appraisal of a Project
Methodology For Formulation And Appraisal of a ProjectMethodology For Formulation And Appraisal of a Project
Methodology For Formulation And Appraisal of a Project
 
Project formulation and management
Project formulation and managementProject formulation and management
Project formulation and management
 
Project Monitoring & Evaluation
Project Monitoring & EvaluationProject Monitoring & Evaluation
Project Monitoring & Evaluation
 
Project formulation
Project formulationProject formulation
Project formulation
 
Project formulation by shalini
Project formulation by shaliniProject formulation by shalini
Project formulation by shalini
 
18611 project identification
18611 project identification18611 project identification
18611 project identification
 
Project_Formulation
Project_FormulationProject_Formulation
Project_Formulation
 
Project identification
Project  identificationProject  identification
Project identification
 
Project evaluation
Project evaluationProject evaluation
Project evaluation
 
Monitoring and Evaluation Framework
Monitoring and Evaluation FrameworkMonitoring and Evaluation Framework
Monitoring and Evaluation Framework
 
Agriculture finnance
Agriculture  finnanceAgriculture  finnance
Agriculture finnance
 
Farms loans and its procedural steps
Farms loans and its procedural steps Farms loans and its procedural steps
Farms loans and its procedural steps
 
Dilli
DilliDilli
Dilli
 
Sampoorna Grameen rozgar Yojna
Sampoorna Grameen rozgar YojnaSampoorna Grameen rozgar Yojna
Sampoorna Grameen rozgar Yojna
 
Monitoring mgnrega
Monitoring mgnregaMonitoring mgnrega
Monitoring mgnrega
 
Afid project monitoring and evaluation practices and lessons
Afid project monitoring and evaluation  practices and lessonsAfid project monitoring and evaluation  practices and lessons
Afid project monitoring and evaluation practices and lessons
 
Monitoring and evaluation (Part 1)
Monitoring and evaluation (Part 1)Monitoring and evaluation (Part 1)
Monitoring and evaluation (Part 1)
 
Project Monitoring and Evaluation
Project Monitoring and EvaluationProject Monitoring and Evaluation
Project Monitoring and Evaluation
 
NOMAD Project on Policy Formulation and Validation through non-moderated Crow...
NOMAD Project on Policy Formulation and Validation through non-moderated Crow...NOMAD Project on Policy Formulation and Validation through non-moderated Crow...
NOMAD Project on Policy Formulation and Validation through non-moderated Crow...
 

Similar to Project : formulation,evaluation and monitoring

CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
SimranGrewal33
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
S.Vijaya Bhaskar
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
Naganna Chetty
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
TecnicoItca
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pertBhim Upadhyaya
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
BahredinAbdella1
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
Top Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh MahasnehTop Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Alecsis Roe Frasco
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
ahsanrabbani
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.ppt
RajnikantPatel45
 
CPM and PERT
CPM and  PERTCPM and  PERT
CPM and PERT
Mamatha Upadhya
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisation
Charul Sharma
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...Aravind NC
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
Guhan M
 
7.project costmanagement
7.project costmanagement7.project costmanagement
7.project costmanagement
Niranjana K.R.
 

Similar to Project : formulation,evaluation and monitoring (20)

CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
vk1
vk1vk1
vk1
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pert
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
Top Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh MahasnehTop Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh Mahasneh
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.ppt
 
CPM and PERT
CPM and  PERTCPM and  PERT
CPM and PERT
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisation
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
7.project costmanagement
7.project costmanagement7.project costmanagement
7.project costmanagement
 

Recently uploaded

一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
Aurelien Domont, MBA
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Avirahi City Dholera
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
zechu97
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 

Recently uploaded (20)

一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 

Project : formulation,evaluation and monitoring

  • 3. Characteristics of project 1. Objectives-Every project has aimed to achieve certain objective. Once the objective is achieved the project is said to be completed .
  • 4. 2.Life cycle- stages of Life cycle are as follows: a.conception b.Design c.Implementation d.Commissoning
  • 5. 3. Definite time limit 4. Uniqueness 5. Change 6. Optimality 7. Control mechanism
  • 7.
  • 8.
  • 9. Phases in project cycle 1.Identification 2.Formulation 3.Appraisal 4.Implementation 5.Monitoring 6.Evaluation
  • 11. TIME VALUE OF MONEY  It involves two types of cost- 1. Compounding cost:- Future value of present sum is known as compounding.  Formula: A=C(1+r)n 2. Discounting cost:- Present value of future sum is called discounting.  Formula:Present worth=R(A)/(1+r)n
  • 12. Techniques of risk analysis Following are the popular techniques : 1. Break even analysis 2. Sensitive analysis 3. Decision tree analysis 4. Monto carlo 5. Game theory
  • 13. Break even analysis Here we can find out break even point (BEP). * BEP refers to the level of production at which farmer neither incurred profit nor incurred losses . * Its also known as no-profit no loss situation. Break even production = fixed cost selling price per unit - variable cost per unit
  • 14. Estimation of break Even point Costs&returns(inRs) Q B K L M O X Y S Quantity Where, SM= Total fixed cost SL= Total cost curve OK= Total revenue curve B= Break Even Point OQ=Break-Even Quantity Zoneof loss Zoneof profit
  • 15. SENSITIVE ANALYSIS It’s a technique that measures change in profitability level of the project caused by a change in factors affecting the profitability level. Sensitive Analysis provides answer to the folloeing questions – what happens to the profitability level if…… 1. Demand of the product fall down. 2. If selling price of the product fall down. 3. If the level of production is declined.
  • 16. Evaluation techniques for selection of profitable project It is nothing but benefit cost analysis of various aspects of a project.  These techniques are divided into two groups: 1.Non –discounted techniques 2.Discounted techniques
  • 17. Non- discounted techniques 1. Payback period (PBP) 2. Average rate of return (ARR) 3. Urgency
  • 18. Payback Period (PBP)  It is the length of period required to get back or recover orignal investment incurred on a project through cash inflow or income.  Payback period=Orignal investment/Annual cash inflow.  Thumb rule:Project which have minimum PBP is selected.
  • 19. Average rate of return (ARR)  This method is obtained by the formula : AVERAGE INFLOW AVERAGE OUTFLOW  Thumb rule: A project having highest ARR value is selected
  • 20. Urgency  Urgency : In this method no formula or method is used. Only those projects are selected which are urgently required.
  • 21. Discounted techniques It includes : 1. Net present worth (NPW) 2. Profitability index 3. Internal rate of return (IRR) 4. Discounted benefit cost ratio
  • 22. Net Present Worth (NPW)  This is the present worth of cash flow stream.  It is referred as Net Present Value(NPV).  NPW=P1/(1+i)t +P2/(1+i)t +....+Pn/(1+i)t -C.  P1=Net cash flow in first year,  i=Discount rate,  t=Time period,  C=Initial cost of the investment.  Thumb rule:A Project having +ve & max value of NPW is selected.
  • 23. Profitability Index (PI)  It is ratio of net present values of cash flows to the initial capital expenditure.  PI = Present value of cash inflow/Present value of cash outflow.  Thumb rule: A Project with highest value of Profitability index is selected
  • 24. Internal Rate of Return (IRR)  IRR is the discounted rate which makes NPV equal to ZERO.  IRR is calculated by TRIAL and ERROR method.  IRR=(Lower discount rate)+(Diff b/w the two discont rates)*[(Present worth of the cash flow at the lower discount rate)/(Absolute diff b/w the present worths of the the cash flow at two discount rates)]
  • 25. Benefit Cost Ratio  We compare the present worth of costs with present worth of benefits.  B-C Ratio =Present value of cash inflow/Present value of cash outflow.  Thumb rule: A project with highest B-C Ratio is selected.
  • 26. NETWORK BASED SCHEDULING  It is a technique used for planning , scheduling and controlling of a project.  It is represented by graphical plan which consist of activity and event.  ACTIVITY: Any operation which consume resources( man, material, time),has start point and end point.  Activity is represented by straight arrow with circle at two points. 
  • 27. TYPES OF ACTIVITIES 1. PRECEEDING ACTIVITY: Activity which occur immediately before the succeeding activity. 2. SUCCEEDING ACTIVITY: Activity which cannot be started until one or more activities are completed. 3. DUMMY ACTIVITY: Activity which does not consume resources. It is represented by dotted arrow.
  • 28. EVENT  They are called nodes.  It does not consume resources and time.  Event is the beginning and end of an activity and is represented by a circle at specific point of time.
  • 29. TYPES OF EVENTS 1. Merge event: It represent joint completion of more than one activity. 2. Burst event: Event which represent the beginning of more than one activity. 3. Merge and Burst event : It is for sometime nerge and sometime burst.
  • 30. ERRORS IN DRAWING A NETWORK 1. Looping: Drawing an endless loop in a network . 2. Dangling: to disconnect an activity before the completion of all the activities in a network. 3. Redundancy: inserting the dummy activity in a network diagram.
  • 31. NETWOK SCHEDULING TECHNIQUE  CPM: (Critical path method) represent a logical sequence of an activity and events in a project. The duration of all these paths are added in the total duration of the path.  The path that has a longer duration duration is called critical path and activities drawn in that path are critical activities.
  • 32. FORWARD PATH COMPUTATION In this method earliest start time of all the events is is computed which begin from initial event and move toward the final event. BACKWARD PATH COMPUTATION Here we calculate the latest time. This method is start from last event and move toward initial event. Slack time: It is the diff b/w latest finish time and earliest start time.
  • 33. Activity float analysis  A study of non- critical path with regard to free time is necessary because it help in better control of project implementation and better allocation of resources.  In critical path latest finish time and earliest start time both are equal.  The slack of the event is given by diff b/w the TL and TE.  The free time available for an activity is called “float”.
  • 34. TYPES OF FLOAT 1. Total float: It represents the max time by whhich completion of an activity can be delayed w/o affecting the project completion time. Total float=[Tl of head event-Te of tail event- Duration of activity]
  • 35. 2. FREE FLOAT  Delay that can be permitted in an activity so that succeeding activity in the path are not affected.
  • 36. 3.INDEPENDENT FLOAT  IT is the spare time available for an activity .