SlideShare a Scribd company logo
1
Sanjay Gupta Ravi Sundaram
Sorabh Gupta
CENGRS GEOTECHNICA PVT. LTD.
Pile Integrity Testing for
Monitoring Pile Construction
2
What makes a “good pile”?
To perform successfully, a pileTo perform successfully, a pile
must:must:
•• Have adequate soilHave adequate soil
resistanceresistance
•• Be structurally soundBe structurally sound
These are two separate requirements
Both must be satisfied
3
Low Strain Integrity Methods
PILE INTEGRITY TESTING (PIT)PILE INTEGRITY TESTING (PIT)
Measure Pile Top Motion, Reflections from Defects
CROSS-HOLE SONIC LOGGING (CSL)
Determines Concrete Quality Between Tubes in Shaft
For larger augercast piles
SINGLE-HOLE SONIC LOGGING (SSL)
For smaller augercast piles
PARALLEL SEISMIC (PS)
Hit Pile, Measure Hydrophone in Parallel Tube
Determines only Pile Length
4
QA/QC:
Unplanned Inspection
In response to something gone wrong
Unplanned costs - project delays
Planned Inspection (PreferredPreferred)
Included in project specifications
Planned costs - normal pay item
5
Why Do Pile Integrity Testing?
• prime function is to locate major defects (to evaluate
questionable shafts)
• inexpensive, can test many piles (good for quality
assurance)
• no advance selection required (good for forensic purposes)
6
Defective Piles
7
PIT Equipment
Accelerometers
Non-Instrumented
Hammer
Instrumented
Hammer
8
PIT looks for defects
Small Hammer
Impact Device Accelerometer
Measures
Response
Defect
One Person Operated
FF
∆∆∆∆∆∆∆∆LL
Compressed Zone, races
along pile at wave speed c
cc is the wave speed of the pile materialis the wave speed of the pile material
In a timeIn a time ““∆∆∆∆∆∆∆∆tt”” the wave travels a distancethe wave travels a distance ∆∆∆∆∆∆∆∆L = cL = c ∆∆∆∆∆∆∆∆tt
Wave Propagation
10
11
Good PileGood Pile
800 mm drilled shafts
L = 25 m (L/D = 31)
Bad PileBad Pile
Normal test (pile top “free”)
PIT - Basic Interpretations
12Any of these piles could have a defect..
How many piles should I test?
13
Grinding top surface to make flat spot
Pile top preparation is key to good data
which is the key to best interpretation.
Shortcuts cause questionable data.
Preparation..
14
Remove loose
contaminated or fractured
concrete from core; cut
rebar to min lengths
15
Case Study 1: Noida Mall
Ongoing Project
800 mm dia BCIS piles in
sand
Initial Cyclic Pile Load Test:
Qult = 270 MT
Qsafe = 135 MT
14 PIT were performed on
initial and routine piles
0
10
20
30
40
50
60
70
80
90
0 50 100 150 200 250 300 350
Load (MT)
Field Data
Extrapolated Values
(Hyperbolic Model)
Qsafe (MT) = 135.0
270 MT
16
Case Study 1: Noida Mall
7 m
Original Ground Level
Excavated Level, Pile COL
Pile Toe Level
27 m
17
Case Study 1: Noida Mall
Variations in Pile Cross-sectionMajor defect at 16~18 m depth (or short pile)
18
Case Study 2: ROB in Malout, Punjab
Good Pile (14 m length)Weak Toe Response
19
PIT - Low Strain Integrity Testing
Standards
ASTM D5882 (1996)
Deep Foundations Institute “Inspector’s Guide to Augered Cast-in-Place
Piles” 1994
Australian Standard AS 2159 (1995)
Eurocode 7, Section 7, Pile Foundations
Specification for Piling - Institution of Civil Engineers (1988) - England
CIRIA Document CP/28 (1995) - England
Norme Francaise NF P94-160-2 (1993) - France
DGGT Com.2.1 for Pile Integrity Testing (draft Sept 1997) - Germany
Slovenia Highway Code
Spain Driven Pile Foundations Art.670 (draft 1996)
Bangladesh National Building Code (1993)
CED 43 (4917) for concrete piles in IS-2911 (draft 1998) - India
Other documents…...
(Draft standards may have been further updated and made official)
20
PIT Limitations
As per published literature, piles with L/D ratio upto 30 give reasonably
good results
Highly non-uniform piles may be difficult to interpret
Cracks or mechanical joints block waves
Small defects or short length hard to find
Not always applicable: pile type, walls, in structure
No direct correlation to pile capacity; but can help to identify which
piles to load-test
21
Let us strive to achieve.. quality in pile
construction
THANK YOU…
Cengrs Geotechnica Pvt. Ltd

More Related Content

What's hot

Pile foundation
Pile  foundation Pile  foundation
Pile foundation
Sherchandra Shrestha
 
Standard penetration test (spt)
Standard penetration test (spt)Standard penetration test (spt)
Standard penetration test (spt)
Faizan Tanoli
 
Lecture 3 foundation settlement
Lecture 3 foundation settlementLecture 3 foundation settlement
Lecture 3 foundation settlement
Dr.Abdulmannan Orabi
 
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Muhammad Irfan
 
DFI india 2014 defects in piles
DFI india 2014 defects in pilesDFI india 2014 defects in piles
DFI india 2014 defects in piles
Infocengrs63
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testingSravan Muguda
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Make Mannan
 
Geotechnical Engineering-I [Lec #12: AASHTO Soil Classification]
Geotechnical Engineering-I [Lec #12: AASHTO Soil Classification]Geotechnical Engineering-I [Lec #12: AASHTO Soil Classification]
Geotechnical Engineering-I [Lec #12: AASHTO Soil Classification]
Muhammad Irfan
 
Soil testing
Soil testingSoil testing
Soil testing
karthik V
 
Analysis and design of reinforced concrete stepped cantilever retaining wall
Analysis and design of reinforced concrete stepped cantilever retaining wallAnalysis and design of reinforced concrete stepped cantilever retaining wall
Analysis and design of reinforced concrete stepped cantilever retaining wall
eSAT Journals
 
Settlement of soil/foundation
Settlement of soil/foundationSettlement of soil/foundation
Settlement of soil/foundation
Jam Shoaib Ahmed veeha
 
Standard penetration test(spt)
Standard penetration test(spt)Standard penetration test(spt)
Standard penetration test(spt)
KHK karimi
 
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Muhammad Irfan
 
Standard Penetration Test
Standard Penetration TestStandard Penetration Test
Standard Penetration Test
INDRANIL BANERJEE
 
Soil investigation
Soil investigationSoil investigation
Soil investigation
Simarpreet Singh
 
Vane shear test
Vane shear testVane shear test
Vane shear test
Sabna Thilakan
 
Pile load test ppt
Pile load test pptPile load test ppt
Pile load test ppt
Dharmendra Kumar
 
Plate load test and its interpretations
Plate load test and its interpretationsPlate load test and its interpretations
Plate load test and its interpretations
Satyartha Saxena
 
Pile foundation
Pile foundationPile foundation
Pile foundation
ghildiyal8811
 
Pavement design
Pavement designPavement design
Pavement design
Garvit Goyal
 

What's hot (20)

Pile foundation
Pile  foundation Pile  foundation
Pile foundation
 
Standard penetration test (spt)
Standard penetration test (spt)Standard penetration test (spt)
Standard penetration test (spt)
 
Lecture 3 foundation settlement
Lecture 3 foundation settlementLecture 3 foundation settlement
Lecture 3 foundation settlement
 
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
Geotechnical Engineering-II [Lec #17: Bearing Capacity of Soil]
 
DFI india 2014 defects in piles
DFI india 2014 defects in pilesDFI india 2014 defects in piles
DFI india 2014 defects in piles
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testing
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
 
Geotechnical Engineering-I [Lec #12: AASHTO Soil Classification]
Geotechnical Engineering-I [Lec #12: AASHTO Soil Classification]Geotechnical Engineering-I [Lec #12: AASHTO Soil Classification]
Geotechnical Engineering-I [Lec #12: AASHTO Soil Classification]
 
Soil testing
Soil testingSoil testing
Soil testing
 
Analysis and design of reinforced concrete stepped cantilever retaining wall
Analysis and design of reinforced concrete stepped cantilever retaining wallAnalysis and design of reinforced concrete stepped cantilever retaining wall
Analysis and design of reinforced concrete stepped cantilever retaining wall
 
Settlement of soil/foundation
Settlement of soil/foundationSettlement of soil/foundation
Settlement of soil/foundation
 
Standard penetration test(spt)
Standard penetration test(spt)Standard penetration test(spt)
Standard penetration test(spt)
 
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
 
Standard Penetration Test
Standard Penetration TestStandard Penetration Test
Standard Penetration Test
 
Soil investigation
Soil investigationSoil investigation
Soil investigation
 
Vane shear test
Vane shear testVane shear test
Vane shear test
 
Pile load test ppt
Pile load test pptPile load test ppt
Pile load test ppt
 
Plate load test and its interpretations
Plate load test and its interpretationsPlate load test and its interpretations
Plate load test and its interpretations
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Pavement design
Pavement designPavement design
Pavement design
 

Similar to Pile integrity testing for monitoring pile construction

Shear testing of prestressed concrete girders
Shear testing of prestressed concrete girdersShear testing of prestressed concrete girders
Shear testing of prestressed concrete girders
Eva Lantsoght
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testing
cfpbolivia
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeTong Seng Chua
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Box culverts
Box culvertsBox culverts
Box culverts
sunil choudhary
 
Sfobb Dec08
Sfobb Dec08Sfobb Dec08
Sfobb Dec08
Sean Merrell
 
Shear tests of reinforced concrete slabs and slab strips under concentrated l...
Shear tests of reinforced concrete slabs and slab strips under concentrated l...Shear tests of reinforced concrete slabs and slab strips under concentrated l...
Shear tests of reinforced concrete slabs and slab strips under concentrated l...
Eva Lantsoght
 
Quality assurance for_deep_bored_piles
Quality assurance for_deep_bored_pilesQuality assurance for_deep_bored_piles
Quality assurance for_deep_bored_piles
Infocengrs63
 
Sellountou evalaución integridad de pilotes
Sellountou   evalaución integridad de pilotesSellountou   evalaución integridad de pilotes
Sellountou evalaución integridad de pilotes
cfpbolivia
 
KTU CE 204 Construction Technology - Module 2
KTU CE 204 Construction Technology - Module 2KTU CE 204 Construction Technology - Module 2
KTU CE 204 Construction Technology - Module 2
Bennet Kuriakose, PhD
 
Civil - Structural Works
Civil - Structural WorksCivil - Structural Works
Civil - Structural Works
Babu Arumugam
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefitPerwez Ahmad
 
SEMI DESTRUCTIVE Test On Concrete _by Imran B K
SEMI DESTRUCTIVE  Test On Concrete _by Imran B KSEMI DESTRUCTIVE  Test On Concrete _by Imran B K
SEMI DESTRUCTIVE Test On Concrete _by Imran B K
Bk Imran
 
publication_1580218342.pdf
publication_1580218342.pdfpublication_1580218342.pdf
publication_1580218342.pdf
PradeepPokhrel5
 
Numerical Investigation of Failure Mechanisms of Cast Iron Watermains
Numerical Investigation of Failure Mechanisms of Cast Iron WatermainsNumerical Investigation of Failure Mechanisms of Cast Iron Watermains
Numerical Investigation of Failure Mechanisms of Cast Iron Watermainskasuni200
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha university
Aman Jain
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
ktx500
 
Bridge Deck-Guardrail Anchorage Detailing For Sustainable Construction
Bridge Deck-Guardrail Anchorage Detailing For Sustainable ConstructionBridge Deck-Guardrail Anchorage Detailing For Sustainable Construction
Bridge Deck-Guardrail Anchorage Detailing For Sustainable Construction
Mahmoud Sayed Ahmed
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
SaurabhSingh20590
 

Similar to Pile integrity testing for monitoring pile construction (20)

Shear testing of prestressed concrete girders
Shear testing of prestressed concrete girdersShear testing of prestressed concrete girders
Shear testing of prestressed concrete girders
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testing
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, Singapore
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
Box culverts
Box culvertsBox culverts
Box culverts
 
Sfobb Dec08
Sfobb Dec08Sfobb Dec08
Sfobb Dec08
 
Shear tests of reinforced concrete slabs and slab strips under concentrated l...
Shear tests of reinforced concrete slabs and slab strips under concentrated l...Shear tests of reinforced concrete slabs and slab strips under concentrated l...
Shear tests of reinforced concrete slabs and slab strips under concentrated l...
 
Quality assurance for_deep_bored_piles
Quality assurance for_deep_bored_pilesQuality assurance for_deep_bored_piles
Quality assurance for_deep_bored_piles
 
Sellountou evalaución integridad de pilotes
Sellountou   evalaución integridad de pilotesSellountou   evalaución integridad de pilotes
Sellountou evalaución integridad de pilotes
 
KTU CE 204 Construction Technology - Module 2
KTU CE 204 Construction Technology - Module 2KTU CE 204 Construction Technology - Module 2
KTU CE 204 Construction Technology - Module 2
 
Civil - Structural Works
Civil - Structural WorksCivil - Structural Works
Civil - Structural Works
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
ghatefar
ghatefarghatefar
ghatefar
 
SEMI DESTRUCTIVE Test On Concrete _by Imran B K
SEMI DESTRUCTIVE  Test On Concrete _by Imran B KSEMI DESTRUCTIVE  Test On Concrete _by Imran B K
SEMI DESTRUCTIVE Test On Concrete _by Imran B K
 
publication_1580218342.pdf
publication_1580218342.pdfpublication_1580218342.pdf
publication_1580218342.pdf
 
Numerical Investigation of Failure Mechanisms of Cast Iron Watermains
Numerical Investigation of Failure Mechanisms of Cast Iron WatermainsNumerical Investigation of Failure Mechanisms of Cast Iron Watermains
Numerical Investigation of Failure Mechanisms of Cast Iron Watermains
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha university
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
 
Bridge Deck-Guardrail Anchorage Detailing For Sustainable Construction
Bridge Deck-Guardrail Anchorage Detailing For Sustainable ConstructionBridge Deck-Guardrail Anchorage Detailing For Sustainable Construction
Bridge Deck-Guardrail Anchorage Detailing For Sustainable Construction
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 

More from Infocengrs63

Foundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarhFoundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarh
Infocengrs63
 
Geotechnics of artesian flow – case study of river shivganga, nepal
Geotechnics of artesian flow – case study of river shivganga, nepalGeotechnics of artesian flow – case study of river shivganga, nepal
Geotechnics of artesian flow – case study of river shivganga, nepal
Infocengrs63
 
In situ testing – current trends in geotechnical investigations
In situ testing – current trends in geotechnical investigationsIn situ testing – current trends in geotechnical investigations
In situ testing – current trends in geotechnical investigations
Infocengrs63
 
Geotechnical investigations dune sands of the thar desert
Geotechnical investigations  dune sands of the thar desertGeotechnical investigations  dune sands of the thar desert
Geotechnical investigations dune sands of the thar desert
Infocengrs63
 
Mitigating foundation distress
Mitigating foundation distressMitigating foundation distress
Mitigating foundation distress
Infocengrs63
 
Dynamic characteristics of alluvial deposits a case study
Dynamic characteristics of alluvial deposits a case studyDynamic characteristics of alluvial deposits a case study
Dynamic characteristics of alluvial deposits a case study
Infocengrs63
 
Geotechnical characterization of dune sands of the thar desert
Geotechnical characterization of dune sands of the thar desertGeotechnical characterization of dune sands of the thar desert
Geotechnical characterization of dune sands of the thar desert
Infocengrs63
 
Pump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case studyPump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case study
Infocengrs63
 
Liquefaction susceptibility study at commonwealth games village delhi
Liquefaction susceptibility study at commonwealth games village delhiLiquefaction susceptibility study at commonwealth games village delhi
Liquefaction susceptibility study at commonwealth games village delhi
Infocengrs63
 
Performance of a large diameter oil storage tank on improved clay deposit
Performance of a large diameter oil storage tank on improved clay depositPerformance of a large diameter oil storage tank on improved clay deposit
Performance of a large diameter oil storage tank on improved clay deposit
Infocengrs63
 
Constructing foundations on red mud
Constructing foundations on red mudConstructing foundations on red mud
Constructing foundations on red mud
Infocengrs63
 
Dynamic compaction to mitigate liquefaction potential
Dynamic compaction to mitigate liquefaction potentialDynamic compaction to mitigate liquefaction potential
Dynamic compaction to mitigate liquefaction potential
Infocengrs63
 
Liquefaction risk mitigation for a power plant in the indo gengatic alluvium
Liquefaction risk mitigation for a power plant in the indo gengatic alluviumLiquefaction risk mitigation for a power plant in the indo gengatic alluvium
Liquefaction risk mitigation for a power plant in the indo gengatic alluvium
Infocengrs63
 
Geotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari deltaGeotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari delta
Infocengrs63
 
In-situ testing to verify ground improvement
In-situ testing to verify ground improvementIn-situ testing to verify ground improvement
In-situ testing to verify ground improvement
Infocengrs63
 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sands
Infocengrs63
 

More from Infocengrs63 (16)

Foundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarhFoundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarh
 
Geotechnics of artesian flow – case study of river shivganga, nepal
Geotechnics of artesian flow – case study of river shivganga, nepalGeotechnics of artesian flow – case study of river shivganga, nepal
Geotechnics of artesian flow – case study of river shivganga, nepal
 
In situ testing – current trends in geotechnical investigations
In situ testing – current trends in geotechnical investigationsIn situ testing – current trends in geotechnical investigations
In situ testing – current trends in geotechnical investigations
 
Geotechnical investigations dune sands of the thar desert
Geotechnical investigations  dune sands of the thar desertGeotechnical investigations  dune sands of the thar desert
Geotechnical investigations dune sands of the thar desert
 
Mitigating foundation distress
Mitigating foundation distressMitigating foundation distress
Mitigating foundation distress
 
Dynamic characteristics of alluvial deposits a case study
Dynamic characteristics of alluvial deposits a case studyDynamic characteristics of alluvial deposits a case study
Dynamic characteristics of alluvial deposits a case study
 
Geotechnical characterization of dune sands of the thar desert
Geotechnical characterization of dune sands of the thar desertGeotechnical characterization of dune sands of the thar desert
Geotechnical characterization of dune sands of the thar desert
 
Pump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case studyPump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case study
 
Liquefaction susceptibility study at commonwealth games village delhi
Liquefaction susceptibility study at commonwealth games village delhiLiquefaction susceptibility study at commonwealth games village delhi
Liquefaction susceptibility study at commonwealth games village delhi
 
Performance of a large diameter oil storage tank on improved clay deposit
Performance of a large diameter oil storage tank on improved clay depositPerformance of a large diameter oil storage tank on improved clay deposit
Performance of a large diameter oil storage tank on improved clay deposit
 
Constructing foundations on red mud
Constructing foundations on red mudConstructing foundations on red mud
Constructing foundations on red mud
 
Dynamic compaction to mitigate liquefaction potential
Dynamic compaction to mitigate liquefaction potentialDynamic compaction to mitigate liquefaction potential
Dynamic compaction to mitigate liquefaction potential
 
Liquefaction risk mitigation for a power plant in the indo gengatic alluvium
Liquefaction risk mitigation for a power plant in the indo gengatic alluviumLiquefaction risk mitigation for a power plant in the indo gengatic alluvium
Liquefaction risk mitigation for a power plant in the indo gengatic alluvium
 
Geotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari deltaGeotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari delta
 
In-situ testing to verify ground improvement
In-situ testing to verify ground improvementIn-situ testing to verify ground improvement
In-situ testing to verify ground improvement
 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sands
 

Recently uploaded

KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 

Recently uploaded (20)

KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 

Pile integrity testing for monitoring pile construction

  • 1. 1 Sanjay Gupta Ravi Sundaram Sorabh Gupta CENGRS GEOTECHNICA PVT. LTD. Pile Integrity Testing for Monitoring Pile Construction
  • 2. 2 What makes a “good pile”? To perform successfully, a pileTo perform successfully, a pile must:must: •• Have adequate soilHave adequate soil resistanceresistance •• Be structurally soundBe structurally sound These are two separate requirements Both must be satisfied
  • 3. 3 Low Strain Integrity Methods PILE INTEGRITY TESTING (PIT)PILE INTEGRITY TESTING (PIT) Measure Pile Top Motion, Reflections from Defects CROSS-HOLE SONIC LOGGING (CSL) Determines Concrete Quality Between Tubes in Shaft For larger augercast piles SINGLE-HOLE SONIC LOGGING (SSL) For smaller augercast piles PARALLEL SEISMIC (PS) Hit Pile, Measure Hydrophone in Parallel Tube Determines only Pile Length
  • 4. 4 QA/QC: Unplanned Inspection In response to something gone wrong Unplanned costs - project delays Planned Inspection (PreferredPreferred) Included in project specifications Planned costs - normal pay item
  • 5. 5 Why Do Pile Integrity Testing? • prime function is to locate major defects (to evaluate questionable shafts) • inexpensive, can test many piles (good for quality assurance) • no advance selection required (good for forensic purposes)
  • 8. 8 PIT looks for defects Small Hammer Impact Device Accelerometer Measures Response Defect One Person Operated
  • 9. FF ∆∆∆∆∆∆∆∆LL Compressed Zone, races along pile at wave speed c cc is the wave speed of the pile materialis the wave speed of the pile material In a timeIn a time ““∆∆∆∆∆∆∆∆tt”” the wave travels a distancethe wave travels a distance ∆∆∆∆∆∆∆∆L = cL = c ∆∆∆∆∆∆∆∆tt Wave Propagation
  • 10. 10
  • 11. 11 Good PileGood Pile 800 mm drilled shafts L = 25 m (L/D = 31) Bad PileBad Pile Normal test (pile top “free”) PIT - Basic Interpretations
  • 12. 12Any of these piles could have a defect.. How many piles should I test?
  • 13. 13 Grinding top surface to make flat spot Pile top preparation is key to good data which is the key to best interpretation. Shortcuts cause questionable data. Preparation..
  • 14. 14 Remove loose contaminated or fractured concrete from core; cut rebar to min lengths
  • 15. 15 Case Study 1: Noida Mall Ongoing Project 800 mm dia BCIS piles in sand Initial Cyclic Pile Load Test: Qult = 270 MT Qsafe = 135 MT 14 PIT were performed on initial and routine piles 0 10 20 30 40 50 60 70 80 90 0 50 100 150 200 250 300 350 Load (MT) Field Data Extrapolated Values (Hyperbolic Model) Qsafe (MT) = 135.0 270 MT
  • 16. 16 Case Study 1: Noida Mall 7 m Original Ground Level Excavated Level, Pile COL Pile Toe Level 27 m
  • 17. 17 Case Study 1: Noida Mall Variations in Pile Cross-sectionMajor defect at 16~18 m depth (or short pile)
  • 18. 18 Case Study 2: ROB in Malout, Punjab Good Pile (14 m length)Weak Toe Response
  • 19. 19 PIT - Low Strain Integrity Testing Standards ASTM D5882 (1996) Deep Foundations Institute “Inspector’s Guide to Augered Cast-in-Place Piles” 1994 Australian Standard AS 2159 (1995) Eurocode 7, Section 7, Pile Foundations Specification for Piling - Institution of Civil Engineers (1988) - England CIRIA Document CP/28 (1995) - England Norme Francaise NF P94-160-2 (1993) - France DGGT Com.2.1 for Pile Integrity Testing (draft Sept 1997) - Germany Slovenia Highway Code Spain Driven Pile Foundations Art.670 (draft 1996) Bangladesh National Building Code (1993) CED 43 (4917) for concrete piles in IS-2911 (draft 1998) - India Other documents…... (Draft standards may have been further updated and made official)
  • 20. 20 PIT Limitations As per published literature, piles with L/D ratio upto 30 give reasonably good results Highly non-uniform piles may be difficult to interpret Cracks or mechanical joints block waves Small defects or short length hard to find Not always applicable: pile type, walls, in structure No direct correlation to pile capacity; but can help to identify which piles to load-test
  • 21. 21 Let us strive to achieve.. quality in pile construction THANK YOU… Cengrs Geotechnica Pvt. Ltd