SlideShare a Scribd company logo
1 of 57
Download to read offline
PUMP-OUT TESTS IN
ALLUVIAL SANDS
– A CASE STUDY
Sorabh Gupta, Sanjay Gupta & Ravi Sundaram
Cengrs Geotechnica Pvt. Ltd.
1
PUMP-OUT TESTS IN
ALLUVIAL SANDS
– A CASE STUDY
Sorabh Gupta, Sanjay Gupta & Ravi Sundaram
Cengrs Geotechnica Pvt. Ltd.
1
The Need
2
Dewatering
3
Dewatering
3
The Challenge
Effective Design of Dewatering Systems for
construction sites requires precise estimates of
hydrogeological parameters of the aquifer,
such as hydraulic conductivity / permeability,
etc.
4
The Challenge
Effective Design of Dewatering Systems for
construction sites requires precise estimates of
hydrogeological parameters of the aquifer,
such as hydraulic conductivity / permeability,
etc.
..particularly on sites where alluvial sands are
encountered
4
Definitions
1. Hydraulic Conductivity (K), m/sec
Volume of water (m3) through unit section of soil (m2) in unit
time (s) under unit hydraulic gradient.
2. Transmissivity (T), m2/day (Productivity of an aquifer)
Water capacity which flows per unit length through an
aquifer under hydraulic gradient
3. Storage coefficient (%)
Volume of water it takes / releases per unit surface area of
aquifer under unit change of head.
4. Specific capacity
Discharge for unit time for unit draw down
c = Q / s
5
Laboratory Permeability Tests (Falling Head,
Constant Head)
Tracer Tests
Borehole Tests
Falling Head in Soils
Packer Tests in Rock
Full Scale Pump Out / Aquifer Tests
Geotechnical Investigations
6
Laboratory Permeability Tests (Falling Head,
Constant Head)
Tracer Tests
Borehole Tests
Falling Head in Soils
Packer Tests in Rock
Full Scale Pump Out / Aquifer Tests
Geotechnical Investigations
6
Pump Out / Aquifer Test
Advantages
Determine hydraulic parameters on global scale
Results directly used for design of dewatering
systems
Design the test as per site/project requirements
7
Case Study 1 : Mall at Noida
8
Project Location
9
Project Location
9
Project Overview
Located in a densely populated area
As per Initial Planning:
G+5, 3 basements
Foundation Level = 18 m below OGL
10
Site Conditions
Site Stratigraphy:
✓ Medium dense sand (SP) to
35~40 m depth
✓ Static GWT at 8 m
Purpose:
✓ Lower the GW level to 21 m
depth below OGL?? (i.e. 13 m
drawdown!)
✓ Test performed from excavated
level (~7 m below OGL)
11
10.0m10.0m
PW
OW1 OW2
OW3
OW410.0m10.0m
Well Setup
12
Pump Well Setup
13
Pump Well Setup
25.0m
PUMP WELL DIA 300 mm
GRAVEL 250 mm
13
Pump Well Setup
6.0m
3.0m
15.0m
BLANK CASING
200mm DIA
BLANK CASING
200mm DIA
SLOTTED CASING
200 mm DIA
BOTTOM CAP
25.0m
PUMP WELL DIA 300 mm
GRAVEL 250 mm
13
Pump Well Setup
6.0m
3.0m
15.0m
BLANK CASING
200mm DIA
BLANK CASING
200mm DIA
SLOTTED CASING
200 mm DIA
BOTTOM CAP
Pea Gravels
25.0m
PUMP WELL DIA 300 mm
GRAVEL 250 mm
13
Pump Well Setup
6.0m
3.0m
15.0m
BLANK CASING
200mm DIA
BLANK CASING
200mm DIA
SLOTTED CASING
200 mm DIA
BOTTOM CAP
Pea Gravels
PUMP
25.0m
PUMP WELL DIA 300 mm
GRAVEL 250 mm
13
LVL (-7.0 m)
3..0m
PRESENT EXCAVATION
WORKING, LVL
OBSERVATION WELL DIA 150 mm
GRAVEL 250 mm
SLOTTED CASING
100 mm DIA
BLANK CASING
100mm DIA
18.0m
LVL (-25.0 m)
15.0m
OW2
BOTTOM CAP
3..0m
LVL (-7.0 m)
GRAVEL 250 mm
LVL (-31.0 m)
OW1
OBSERVATION WELL DIA 150 mm
21.0m
24.0m
Pea Gravels
Observation Well Setup
14
Well Installation
15
Pump Well Setup
12.5
16
Pump Well Setup
16
Pump Well Setup
17
Pump Well Setup
17
Pump Well Setup
17
Flow Meter
18
Testing Procedure
Installation of PW & OW
Well Development
Trial Runs
Step drawdown test – SDD test
Constant discharge test – CD test
Recuperation / Recovery test
19
Testing Procedure
Installation of PW & OW
Well Development
Trial Runs
Step drawdown test – SDD test
Constant discharge test – CD test
Recuperation / Recovery test
19
Testing Procedure
Installation of PW & OW
Well Development
Trial Runs
Step drawdown test – SDD test
Constant discharge test – CD test
Recuperation / Recovery test
20
Testing Procedure
Installation of PW & OW
Well Development
Trial Runs
Step drawdown test – SDD test
Constant discharge test – CD test
Recuperation / Recovery test
20
Step Drawdown Test
Purpose
To estimate...
Short-term yield-drawdown relationship
Estimate ‘Q’ for CD test
Determine Well Efficiency, etc.
21
Step Drawdown Test
Overview
Steps estimated on maximum yield of the well
based upon trial runs
Discharge is increased in 4~6 steps of 60~100 min
each
Discharge controlled by Control Valve
Average discharge and drawdown recorded with
time for each step
22
Step Drawdown Test
Step
Discharge
(lt/min)
Discharge
(lt/hour)
I
II
III
IV
V
VI
619,200 10,320
1,022,400 17,040
1,260,000 21,000
2,016,000 33,600
2,484,000 41,400
2,793,600 46,560
24
Location : Mall at Noida
Time vs Drawdown in all wells
Step Time Flowmeter Discharge PW OW-1 OW-2 OW-3 OW-4
No Interval Reading (Litr/hr) Draw Draw Draw Draw Draw
(min) (m) down(m) down(m) down(m) down(m) down(m)
I 0 1.72 0.000 0.300 0.300 0.300 0.300
5 1.91 0.190 0.600 0.600 0.600 0.600
10 1.925 0.205 0.900 0.900 0.900 0.900
15 1.925 0.205 1.200 1.200 1.200 1.200
20 1.925 0.205 1.500 1.500 1.500 1.500
25 1.93 0.210 1.800 1.800 1.800 1.800
30 1.93 0.210 2.100 2.100 2.100 2.100
35 1.93 0.210 2.400 2.400 2.400 2.400
40 1.93 0.210 2.700 2.700 2.700 2.700
45 1.93 0.210 3.000 3.000 3.000 3.000
50 1.93 0.210 3.300 3.300 3.300 3.300
55 1.93 0.210 3.600 3.600 3.600 3.600
60 1.93 10320 0.210 3.900 3.900 3.900 3.900
II 65 2.23 0.510 4.200 4.200 4.200 4.200
70 2.24 0.520 4.500 4.500 4.500 4.500
75 2.245 0.525 4.800 4.800 4.800 4.800
80 2.25 0.530 5.100 5.100 5.100 5.100
85 2.25 0.530 5.400 5.400 5.400 5.400
90 2.255 0.535 5.700 5.700 5.700 5.700
95 2.255 0.535 6.000 6.000 6.000 6.000
100 2.255 0.535 6.300 6.300 6.300 6.300
105 2.255 0.535 6.600 6.600 6.600 6.600
110 2.255 0.535 6.900 6.900 6.900 6.900
115 2.255 0.535 7.200 7.200 7.200 7.200
120 2.255 17040 0.535 7.500 7.450 7.500 7.500
III 125 2.3 0.580 7.800 7.750 7.800 7.800
130 2.35 0.630 8.100 8.080 8.080 8.100
STEP DRAWDOWN TEST DATA
Step Drawdown Test Data
25
Drawdown Measurement
23
Drawdown Measurement
23
Step Drawdown Test Results
26
Step Drawdown Test Results
26
Step Drawdown Test Results
26
Testing Procedure
Installation of PW & OW
Well Development
Trial Runs
Step drawdown test – SDD test
Constant discharge test – CD test
Recuperation / Recovery test
27
Testing Procedure
Installation of PW & OW
Well Development
Trial Runs
Step drawdown test – SDD test
Constant discharge test – CD test
Recuperation / Recovery test
27
Constant Discharge Test
Overview
To determine hydraulic characteristics of the
aquifer within the radius of influence of PW
PW continuously pumped to ensure desired
drawdown at steady state.
Water level readings are recorded in PW and
OW’s at regular intervals.
Test continues till steady state / equilibrium
28
CONSTANT DISCHARGE TEST DATA
Location: Mall at Noida
Time vs Draw Down in all wells
Discharge = 48,000 lph = 48 m3
/hr
PW ROBW-1 ROBW-2 TOBW-1 TOBW-2
r = 0 m r = 10 m r = 20 m r = 10 m r = 20 m
0 0.000 0.000 0.000 0.000 0.000
1 1.330 0.160 0.000 0.200 0.000
2 1.340 0.190 0.060 0.210 0.010
3 1.350 0.195 0.100 0.210 0.100
4 1.360 0.200 0.130 0.210 0.100
5 1.370 0.200 0.130 0.210 0.110
6 1.370 0.200 0.130 0.220 0.160
7 1.380 0.210 0.130 0.220 0.160
8 1.390 0.210 0.130 0.220 0.160
9 1.400 0.215 0.130 0.230 0.160
10 1.410 0.220 0.130 0.230 0.160
15 1.410 0.225 0.135 0.240 0.160
20 1.410 0.227 0.140 0.250 0.160
25 1.410 0.230 0.140 0.250 0.160
30 1.410 0.230 0.140 0.260 0.160
35 1.410 0.235 0.140 0.260 0.160
40 1.410 0.240 0.140 0.260 0.160
45 1.410 0.245 0.140 0.270 0.160
50 1.410 0.250 0.140 0.270 0.160
55 1.410 0.260 0.140 0.280 0.160
60 1.410 0.260 0.140 0.280 0.160
75 1.410 0.270 0.140 0.280 0.160
90 1.415 0.290 0.140 0.290 0.160
105 1.420 0.320 0.150 0.290 0.165
120 1.430 0.320 0.160 0.290 0.170
135 1.440 0.320 0.170 0.300 0.175
150 1.450 0.325 0.175 0.305 0.175
165 1.460 0.330 0.180 0.320 0.180
Time
(min)
Drawdown, metres
CD Test Data
29
CD Test Results
30
CD Test Results
30
Testing Procedure
Installation of PW & OW
Well Development
Trial Runs
Step draw down test – SDD test
Constant discharge test – CD test
Recuperation / Recovery test
31
Testing Procedure
Installation of PW & OW
Well Development
Trial Runs
Step draw down test – SDD test
Constant discharge test – CD test
Recuperation / Recovery test
31
Recuperation / Recovery Test
After CD test is complete, Pump is stopped
Take water level readings in same sequence
as for CD
Test continues till water level rises up to
static level
Provides independent check of CD Results
32
Formation Method
Aquifer Parameters
Coefficient of
Permeability
from Borehole
Data (cm/sec)
Tav
(m2/day)
Kav
(cm/sec)
Sav
Alluvium
Strata
(Yamuna
Sands)
CD Test 1782 1.9 × 10−1 4.1 × 10−2
2.0 × 10−4
~ 5.0 × 10−4
Recovery Test 4046 4.3 × 10−1 -
Summary of Results
33
Formation Method
Aquifer Parameters
Coefficient of
Permeability
from Borehole
Data (cm/sec)
Tav
(m2/day)
Kav
(cm/sec)
Sav
Alluvium
Strata
(Yamuna
Sands)
CD Test 1782 1.9 × 10−1 4.1 × 10−2
2.0 × 10−4
~ 5.0 × 10−4
Recovery Test 4046 4.3 × 10−1 -
Summary of Results
33
Test Summary
Large unconfined aquifer with very high
permeability and storage capacity
Actual K three orders of magnitude higher
than original estimate (based on borehole
tests)
Very low drawdown (<2.0 m) even at high
discharge (48,000 lph)
For 13 m drawdown:
• > 3,00,000 lph discharge required
• 7.2 million litres of water would need to be
discharged into the adjoining drain every day!
• Affect on adjoining structures?
34
Test Consequences
Design altered - raised final excavation level
Deep diaphragm wall constructed, which acts as
cut-off-barrier to GW flow, restricts the aquifer
extent, and protects nearby structures from
subsistence due to migration of fines etc.
Installed dewatering wells spaced at 25~30 m
35
Geotechnical Engineering is a Science,
But its Practice, an Art...
36

More Related Content

What's hot

Drill stem test (mtm)
Drill stem test (mtm)Drill stem test (mtm)
Drill stem test (mtm)majeed talal
 
ADVANCED PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATION
ADVANCED  PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATIONADVANCED  PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATION
ADVANCED PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATIONpetroEDGE
 
Iapg jornadas shale neuquén vaca muerta a regional vision- 2013 neuquén
Iapg jornadas shale neuquén vaca muerta a regional vision- 2013 neuquénIapg jornadas shale neuquén vaca muerta a regional vision- 2013 neuquén
Iapg jornadas shale neuquén vaca muerta a regional vision- 2013 neuquénJuan Carlos Bonapace
 
05 well testing trisakti 25 nov 2007
05 well testing   trisakti 25 nov 200705 well testing   trisakti 25 nov 2007
05 well testing trisakti 25 nov 2007yudi05
 
Coulometer for low level water determination in sample matrix
Coulometer for low level water determination in sample matrixCoulometer for low level water determination in sample matrix
Coulometer for low level water determination in sample matrixMetrohm India Limited
 
EST Group brochure
EST Group brochureEST Group brochure
EST Group brochureseisenhauer
 
First use of cesium formate LSOBM as well perforating fluid (2002)
First use of cesium formate LSOBM as well perforating fluid (2002) First use of cesium formate LSOBM as well perforating fluid (2002)
First use of cesium formate LSOBM as well perforating fluid (2002) John Downs
 
110510 tracers in heavy oil
110510 tracers in heavy oil110510 tracers in heavy oil
110510 tracers in heavy oilifeinfo
 
Máy lạnh Daikin âm trần
Máy lạnh Daikin âm trầnMáy lạnh Daikin âm trần
Máy lạnh Daikin âm trầnMyLnhGiGc
 
Impact of physicochemical characteristics of water on coefficient of pipe fri...
Impact of physicochemical characteristics of water on coefficient of pipe fri...Impact of physicochemical characteristics of water on coefficient of pipe fri...
Impact of physicochemical characteristics of water on coefficient of pipe fri...eSAT Publishing House
 
Compressor Synthetic 46
Compressor Synthetic 46Compressor Synthetic 46
Compressor Synthetic 46Eko Kiswanto
 

What's hot (20)

SPE-174119
SPE-174119SPE-174119
SPE-174119
 
Drill stem test (mtm)
Drill stem test (mtm)Drill stem test (mtm)
Drill stem test (mtm)
 
Hank Rawlins
Hank RawlinsHank Rawlins
Hank Rawlins
 
Water balance diagram
Water balance diagramWater balance diagram
Water balance diagram
 
ADVANCED PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATION
ADVANCED  PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATIONADVANCED  PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATION
ADVANCED PRODUCTION LOGGING, CASED HOLE & PRODUCTION LOG EVALUATION
 
Iapg jornadas shale neuquén vaca muerta a regional vision- 2013 neuquén
Iapg jornadas shale neuquén vaca muerta a regional vision- 2013 neuquénIapg jornadas shale neuquén vaca muerta a regional vision- 2013 neuquén
Iapg jornadas shale neuquén vaca muerta a regional vision- 2013 neuquén
 
SPE-164580
SPE-164580SPE-164580
SPE-164580
 
05 well testing trisakti 25 nov 2007
05 well testing   trisakti 25 nov 200705 well testing   trisakti 25 nov 2007
05 well testing trisakti 25 nov 2007
 
Coulometer for low level water determination in sample matrix
Coulometer for low level water determination in sample matrixCoulometer for low level water determination in sample matrix
Coulometer for low level water determination in sample matrix
 
EST Group brochure
EST Group brochureEST Group brochure
EST Group brochure
 
First use of cesium formate LSOBM as well perforating fluid (2002)
First use of cesium formate LSOBM as well perforating fluid (2002) First use of cesium formate LSOBM as well perforating fluid (2002)
First use of cesium formate LSOBM as well perforating fluid (2002)
 
GT360 - KOLD-DRAFT Commercial Ice Machines
GT360 - KOLD-DRAFT Commercial Ice MachinesGT360 - KOLD-DRAFT Commercial Ice Machines
GT360 - KOLD-DRAFT Commercial Ice Machines
 
110510 tracers in heavy oil
110510 tracers in heavy oil110510 tracers in heavy oil
110510 tracers in heavy oil
 
Máy lạnh Daikin âm trần
Máy lạnh Daikin âm trầnMáy lạnh Daikin âm trần
Máy lạnh Daikin âm trần
 
Impact of physicochemical characteristics of water on coefficient of pipe fri...
Impact of physicochemical characteristics of water on coefficient of pipe fri...Impact of physicochemical characteristics of water on coefficient of pipe fri...
Impact of physicochemical characteristics of water on coefficient of pipe fri...
 
Grilletes y tensores gunnebo
Grilletes y tensores gunneboGrilletes y tensores gunnebo
Grilletes y tensores gunnebo
 
D4943 astm
D4943 astmD4943 astm
D4943 astm
 
Toni Carroll: Caltrans Section 39 specification changes
Toni Carroll: Caltrans Section 39 specification changesToni Carroll: Caltrans Section 39 specification changes
Toni Carroll: Caltrans Section 39 specification changes
 
Well Testing
Well TestingWell Testing
Well Testing
 
Compressor Synthetic 46
Compressor Synthetic 46Compressor Synthetic 46
Compressor Synthetic 46
 

Similar to Pump out tests in alluvial sands – a case study

03 drilling recent development ui 17 sep 2007
03 drilling recent development   ui 17 sep 200703 drilling recent development   ui 17 sep 2007
03 drilling recent development ui 17 sep 2007yudi05
 
Sc 0009-rwpc-pip-civ-cal-0511 0-a
Sc 0009-rwpc-pip-civ-cal-0511 0-aSc 0009-rwpc-pip-civ-cal-0511 0-a
Sc 0009-rwpc-pip-civ-cal-0511 0-ajulio-civil
 
Hydraulic jump location control
Hydraulic jump location control Hydraulic jump location control
Hydraulic jump location control siddharth upadhyay
 
FLUID MECHANICS LAB MANUAL BSc Civil Technology 3rd Semster
FLUID  MECHANICS LAB  MANUAL BSc Civil Technology 3rd Semster FLUID  MECHANICS LAB  MANUAL BSc Civil Technology 3rd Semster
FLUID MECHANICS LAB MANUAL BSc Civil Technology 3rd Semster Bsc Civil Engineering Technology
 
Stage presentation v07
Stage presentation v07Stage presentation v07
Stage presentation v07Garth Braun
 
11 projects on well top testing and remidiation of annular integrity loss (1)
11 projects on well top testing and remidiation of annular integrity loss (1)11 projects on well top testing and remidiation of annular integrity loss (1)
11 projects on well top testing and remidiation of annular integrity loss (1)Sigve Hamilton Aspelund
 
Lokesh Training report from BHEL
Lokesh Training report from BHELLokesh Training report from BHEL
Lokesh Training report from BHELLokesh Khatri
 
Paper 43 - OPT 2015_BHI 9_2_15
Paper 43 - OPT 2015_BHI 9_2_15Paper 43 - OPT 2015_BHI 9_2_15
Paper 43 - OPT 2015_BHI 9_2_15John Grover
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...Egyptian Engineers Association
 
CV6314_Lect_1_excavation_4slides_2012.pdf
CV6314_Lect_1_excavation_4slides_2012.pdfCV6314_Lect_1_excavation_4slides_2012.pdf
CV6314_Lect_1_excavation_4slides_2012.pdfjclimkanghai
 
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanHDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanIndiaMART InterMESH Limited
 
CONING CONTROL AND RECOVERY IMPROVEMENT IN BOTTOM WATER
CONING CONTROL AND RECOVERY IMPROVEMENT IN BOTTOM WATERCONING CONTROL AND RECOVERY IMPROVEMENT IN BOTTOM WATER
CONING CONTROL AND RECOVERY IMPROVEMENT IN BOTTOM WATERMOHD RUZAINI RUSLI
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverterRidhoIrawan12
 
Txmer quality plan 2
Txmer quality plan 2Txmer quality plan 2
Txmer quality plan 2Naresh Raju
 
Chapter 01 Drilling Fluids Functions (1).pdf
Chapter 01 Drilling Fluids Functions (1).pdfChapter 01 Drilling Fluids Functions (1).pdf
Chapter 01 Drilling Fluids Functions (1).pdfAbdallahTayea99
 
MPD familiarization Presentation april 2016.pptx
MPD familiarization Presentation april 2016.pptxMPD familiarization Presentation april 2016.pptx
MPD familiarization Presentation april 2016.pptxcVNguyn5
 
KHRI-Webinar (22-04-2020)-Introduction to Performance Grade Bitumen -Er. T K ...
KHRI-Webinar (22-04-2020)-Introduction to Performance Grade Bitumen -Er. T K ...KHRI-Webinar (22-04-2020)-Introduction to Performance Grade Bitumen -Er. T K ...
KHRI-Webinar (22-04-2020)-Introduction to Performance Grade Bitumen -Er. T K ...SandipPaul46
 
26-grover-john-final
26-grover-john-final26-grover-john-final
26-grover-john-finalJohn Grover
 

Similar to Pump out tests in alluvial sands – a case study (20)

03 drilling recent development ui 17 sep 2007
03 drilling recent development   ui 17 sep 200703 drilling recent development   ui 17 sep 2007
03 drilling recent development ui 17 sep 2007
 
Sc 0009-rwpc-pip-civ-cal-0511 0-a
Sc 0009-rwpc-pip-civ-cal-0511 0-aSc 0009-rwpc-pip-civ-cal-0511 0-a
Sc 0009-rwpc-pip-civ-cal-0511 0-a
 
Cosan Ayan
Cosan AyanCosan Ayan
Cosan Ayan
 
Hydraulic jump location control
Hydraulic jump location control Hydraulic jump location control
Hydraulic jump location control
 
FLUID MECHANICS LAB MANUAL BSc Civil Technology 3rd Semster
FLUID  MECHANICS LAB  MANUAL BSc Civil Technology 3rd Semster FLUID  MECHANICS LAB  MANUAL BSc Civil Technology 3rd Semster
FLUID MECHANICS LAB MANUAL BSc Civil Technology 3rd Semster
 
Stage presentation v07
Stage presentation v07Stage presentation v07
Stage presentation v07
 
11 projects on well top testing and remidiation of annular integrity loss (1)
11 projects on well top testing and remidiation of annular integrity loss (1)11 projects on well top testing and remidiation of annular integrity loss (1)
11 projects on well top testing and remidiation of annular integrity loss (1)
 
filters
filtersfilters
filters
 
Lokesh Training report from BHEL
Lokesh Training report from BHELLokesh Training report from BHEL
Lokesh Training report from BHEL
 
Paper 43 - OPT 2015_BHI 9_2_15
Paper 43 - OPT 2015_BHI 9_2_15Paper 43 - OPT 2015_BHI 9_2_15
Paper 43 - OPT 2015_BHI 9_2_15
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
CV6314_Lect_1_excavation_4slides_2012.pdf
CV6314_Lect_1_excavation_4slides_2012.pdfCV6314_Lect_1_excavation_4slides_2012.pdf
CV6314_Lect_1_excavation_4slides_2012.pdf
 
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanHDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
 
CONING CONTROL AND RECOVERY IMPROVEMENT IN BOTTOM WATER
CONING CONTROL AND RECOVERY IMPROVEMENT IN BOTTOM WATERCONING CONTROL AND RECOVERY IMPROVEMENT IN BOTTOM WATER
CONING CONTROL AND RECOVERY IMPROVEMENT IN BOTTOM WATER
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverter
 
Txmer quality plan 2
Txmer quality plan 2Txmer quality plan 2
Txmer quality plan 2
 
Chapter 01 Drilling Fluids Functions (1).pdf
Chapter 01 Drilling Fluids Functions (1).pdfChapter 01 Drilling Fluids Functions (1).pdf
Chapter 01 Drilling Fluids Functions (1).pdf
 
MPD familiarization Presentation april 2016.pptx
MPD familiarization Presentation april 2016.pptxMPD familiarization Presentation april 2016.pptx
MPD familiarization Presentation april 2016.pptx
 
KHRI-Webinar (22-04-2020)-Introduction to Performance Grade Bitumen -Er. T K ...
KHRI-Webinar (22-04-2020)-Introduction to Performance Grade Bitumen -Er. T K ...KHRI-Webinar (22-04-2020)-Introduction to Performance Grade Bitumen -Er. T K ...
KHRI-Webinar (22-04-2020)-Introduction to Performance Grade Bitumen -Er. T K ...
 
26-grover-john-final
26-grover-john-final26-grover-john-final
26-grover-john-final
 

More from Infocengrs63

Foundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarhFoundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarhInfocengrs63
 
Geotechnics of artesian flow – case study of river shivganga, nepal
Geotechnics of artesian flow – case study of river shivganga, nepalGeotechnics of artesian flow – case study of river shivganga, nepal
Geotechnics of artesian flow – case study of river shivganga, nepalInfocengrs63
 
In situ testing – current trends in geotechnical investigations
In situ testing – current trends in geotechnical investigationsIn situ testing – current trends in geotechnical investigations
In situ testing – current trends in geotechnical investigationsInfocengrs63
 
Geotechnical investigations dune sands of the thar desert
Geotechnical investigations  dune sands of the thar desertGeotechnical investigations  dune sands of the thar desert
Geotechnical investigations dune sands of the thar desertInfocengrs63
 
Mitigating foundation distress
Mitigating foundation distressMitigating foundation distress
Mitigating foundation distressInfocengrs63
 
Dynamic characteristics of alluvial deposits a case study
Dynamic characteristics of alluvial deposits a case studyDynamic characteristics of alluvial deposits a case study
Dynamic characteristics of alluvial deposits a case studyInfocengrs63
 
Geotechnical characterization of dune sands of the thar desert
Geotechnical characterization of dune sands of the thar desertGeotechnical characterization of dune sands of the thar desert
Geotechnical characterization of dune sands of the thar desertInfocengrs63
 
Pile integrity testing for monitoring pile construction
Pile integrity testing for monitoring pile constructionPile integrity testing for monitoring pile construction
Pile integrity testing for monitoring pile constructionInfocengrs63
 
Liquefaction susceptibility study at commonwealth games village delhi
Liquefaction susceptibility study at commonwealth games village delhiLiquefaction susceptibility study at commonwealth games village delhi
Liquefaction susceptibility study at commonwealth games village delhiInfocengrs63
 
Performance of a large diameter oil storage tank on improved clay deposit
Performance of a large diameter oil storage tank on improved clay depositPerformance of a large diameter oil storage tank on improved clay deposit
Performance of a large diameter oil storage tank on improved clay depositInfocengrs63
 
Constructing foundations on red mud
Constructing foundations on red mudConstructing foundations on red mud
Constructing foundations on red mudInfocengrs63
 
Dynamic compaction to mitigate liquefaction potential
Dynamic compaction to mitigate liquefaction potentialDynamic compaction to mitigate liquefaction potential
Dynamic compaction to mitigate liquefaction potentialInfocengrs63
 
Liquefaction risk mitigation for a power plant in the indo gengatic alluvium
Liquefaction risk mitigation for a power plant in the indo gengatic alluviumLiquefaction risk mitigation for a power plant in the indo gengatic alluvium
Liquefaction risk mitigation for a power plant in the indo gengatic alluviumInfocengrs63
 
Geotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari deltaGeotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari deltaInfocengrs63
 
Quality assurance for_deep_bored_piles
Quality assurance for_deep_bored_pilesQuality assurance for_deep_bored_piles
Quality assurance for_deep_bored_pilesInfocengrs63
 
DFI india 2014 defects in piles
DFI india 2014 defects in pilesDFI india 2014 defects in piles
DFI india 2014 defects in pilesInfocengrs63
 
In-situ testing to verify ground improvement
In-situ testing to verify ground improvementIn-situ testing to verify ground improvement
In-situ testing to verify ground improvementInfocengrs63
 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsInfocengrs63
 

More from Infocengrs63 (18)

Foundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarhFoundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarh
 
Geotechnics of artesian flow – case study of river shivganga, nepal
Geotechnics of artesian flow – case study of river shivganga, nepalGeotechnics of artesian flow – case study of river shivganga, nepal
Geotechnics of artesian flow – case study of river shivganga, nepal
 
In situ testing – current trends in geotechnical investigations
In situ testing – current trends in geotechnical investigationsIn situ testing – current trends in geotechnical investigations
In situ testing – current trends in geotechnical investigations
 
Geotechnical investigations dune sands of the thar desert
Geotechnical investigations  dune sands of the thar desertGeotechnical investigations  dune sands of the thar desert
Geotechnical investigations dune sands of the thar desert
 
Mitigating foundation distress
Mitigating foundation distressMitigating foundation distress
Mitigating foundation distress
 
Dynamic characteristics of alluvial deposits a case study
Dynamic characteristics of alluvial deposits a case studyDynamic characteristics of alluvial deposits a case study
Dynamic characteristics of alluvial deposits a case study
 
Geotechnical characterization of dune sands of the thar desert
Geotechnical characterization of dune sands of the thar desertGeotechnical characterization of dune sands of the thar desert
Geotechnical characterization of dune sands of the thar desert
 
Pile integrity testing for monitoring pile construction
Pile integrity testing for monitoring pile constructionPile integrity testing for monitoring pile construction
Pile integrity testing for monitoring pile construction
 
Liquefaction susceptibility study at commonwealth games village delhi
Liquefaction susceptibility study at commonwealth games village delhiLiquefaction susceptibility study at commonwealth games village delhi
Liquefaction susceptibility study at commonwealth games village delhi
 
Performance of a large diameter oil storage tank on improved clay deposit
Performance of a large diameter oil storage tank on improved clay depositPerformance of a large diameter oil storage tank on improved clay deposit
Performance of a large diameter oil storage tank on improved clay deposit
 
Constructing foundations on red mud
Constructing foundations on red mudConstructing foundations on red mud
Constructing foundations on red mud
 
Dynamic compaction to mitigate liquefaction potential
Dynamic compaction to mitigate liquefaction potentialDynamic compaction to mitigate liquefaction potential
Dynamic compaction to mitigate liquefaction potential
 
Liquefaction risk mitigation for a power plant in the indo gengatic alluvium
Liquefaction risk mitigation for a power plant in the indo gengatic alluviumLiquefaction risk mitigation for a power plant in the indo gengatic alluvium
Liquefaction risk mitigation for a power plant in the indo gengatic alluvium
 
Geotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari deltaGeotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari delta
 
Quality assurance for_deep_bored_piles
Quality assurance for_deep_bored_pilesQuality assurance for_deep_bored_piles
Quality assurance for_deep_bored_piles
 
DFI india 2014 defects in piles
DFI india 2014 defects in pilesDFI india 2014 defects in piles
DFI india 2014 defects in piles
 
In-situ testing to verify ground improvement
In-situ testing to verify ground improvementIn-situ testing to verify ground improvement
In-situ testing to verify ground improvement
 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sands
 

Recently uploaded

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 

Recently uploaded (20)

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 

Pump out tests in alluvial sands – a case study

  • 1. PUMP-OUT TESTS IN ALLUVIAL SANDS – A CASE STUDY Sorabh Gupta, Sanjay Gupta & Ravi Sundaram Cengrs Geotechnica Pvt. Ltd. 1
  • 2. PUMP-OUT TESTS IN ALLUVIAL SANDS – A CASE STUDY Sorabh Gupta, Sanjay Gupta & Ravi Sundaram Cengrs Geotechnica Pvt. Ltd. 1
  • 6. The Challenge Effective Design of Dewatering Systems for construction sites requires precise estimates of hydrogeological parameters of the aquifer, such as hydraulic conductivity / permeability, etc. 4
  • 7. The Challenge Effective Design of Dewatering Systems for construction sites requires precise estimates of hydrogeological parameters of the aquifer, such as hydraulic conductivity / permeability, etc. ..particularly on sites where alluvial sands are encountered 4
  • 8. Definitions 1. Hydraulic Conductivity (K), m/sec Volume of water (m3) through unit section of soil (m2) in unit time (s) under unit hydraulic gradient. 2. Transmissivity (T), m2/day (Productivity of an aquifer) Water capacity which flows per unit length through an aquifer under hydraulic gradient 3. Storage coefficient (%) Volume of water it takes / releases per unit surface area of aquifer under unit change of head. 4. Specific capacity Discharge for unit time for unit draw down c = Q / s 5
  • 9. Laboratory Permeability Tests (Falling Head, Constant Head) Tracer Tests Borehole Tests Falling Head in Soils Packer Tests in Rock Full Scale Pump Out / Aquifer Tests Geotechnical Investigations 6
  • 10. Laboratory Permeability Tests (Falling Head, Constant Head) Tracer Tests Borehole Tests Falling Head in Soils Packer Tests in Rock Full Scale Pump Out / Aquifer Tests Geotechnical Investigations 6
  • 11. Pump Out / Aquifer Test Advantages Determine hydraulic parameters on global scale Results directly used for design of dewatering systems Design the test as per site/project requirements 7
  • 12. Case Study 1 : Mall at Noida 8
  • 15. Project Overview Located in a densely populated area As per Initial Planning: G+5, 3 basements Foundation Level = 18 m below OGL 10
  • 16. Site Conditions Site Stratigraphy: ✓ Medium dense sand (SP) to 35~40 m depth ✓ Static GWT at 8 m Purpose: ✓ Lower the GW level to 21 m depth below OGL?? (i.e. 13 m drawdown!) ✓ Test performed from excavated level (~7 m below OGL) 11
  • 19. Pump Well Setup 25.0m PUMP WELL DIA 300 mm GRAVEL 250 mm 13
  • 20. Pump Well Setup 6.0m 3.0m 15.0m BLANK CASING 200mm DIA BLANK CASING 200mm DIA SLOTTED CASING 200 mm DIA BOTTOM CAP 25.0m PUMP WELL DIA 300 mm GRAVEL 250 mm 13
  • 21. Pump Well Setup 6.0m 3.0m 15.0m BLANK CASING 200mm DIA BLANK CASING 200mm DIA SLOTTED CASING 200 mm DIA BOTTOM CAP Pea Gravels 25.0m PUMP WELL DIA 300 mm GRAVEL 250 mm 13
  • 22. Pump Well Setup 6.0m 3.0m 15.0m BLANK CASING 200mm DIA BLANK CASING 200mm DIA SLOTTED CASING 200 mm DIA BOTTOM CAP Pea Gravels PUMP 25.0m PUMP WELL DIA 300 mm GRAVEL 250 mm 13
  • 23. LVL (-7.0 m) 3..0m PRESENT EXCAVATION WORKING, LVL OBSERVATION WELL DIA 150 mm GRAVEL 250 mm SLOTTED CASING 100 mm DIA BLANK CASING 100mm DIA 18.0m LVL (-25.0 m) 15.0m OW2 BOTTOM CAP 3..0m LVL (-7.0 m) GRAVEL 250 mm LVL (-31.0 m) OW1 OBSERVATION WELL DIA 150 mm 21.0m 24.0m Pea Gravels Observation Well Setup 14
  • 31. Testing Procedure Installation of PW & OW Well Development Trial Runs Step drawdown test – SDD test Constant discharge test – CD test Recuperation / Recovery test 19
  • 32. Testing Procedure Installation of PW & OW Well Development Trial Runs Step drawdown test – SDD test Constant discharge test – CD test Recuperation / Recovery test 19
  • 33. Testing Procedure Installation of PW & OW Well Development Trial Runs Step drawdown test – SDD test Constant discharge test – CD test Recuperation / Recovery test 20
  • 34. Testing Procedure Installation of PW & OW Well Development Trial Runs Step drawdown test – SDD test Constant discharge test – CD test Recuperation / Recovery test 20
  • 35. Step Drawdown Test Purpose To estimate... Short-term yield-drawdown relationship Estimate ‘Q’ for CD test Determine Well Efficiency, etc. 21
  • 36. Step Drawdown Test Overview Steps estimated on maximum yield of the well based upon trial runs Discharge is increased in 4~6 steps of 60~100 min each Discharge controlled by Control Valve Average discharge and drawdown recorded with time for each step 22
  • 37. Step Drawdown Test Step Discharge (lt/min) Discharge (lt/hour) I II III IV V VI 619,200 10,320 1,022,400 17,040 1,260,000 21,000 2,016,000 33,600 2,484,000 41,400 2,793,600 46,560 24
  • 38. Location : Mall at Noida Time vs Drawdown in all wells Step Time Flowmeter Discharge PW OW-1 OW-2 OW-3 OW-4 No Interval Reading (Litr/hr) Draw Draw Draw Draw Draw (min) (m) down(m) down(m) down(m) down(m) down(m) I 0 1.72 0.000 0.300 0.300 0.300 0.300 5 1.91 0.190 0.600 0.600 0.600 0.600 10 1.925 0.205 0.900 0.900 0.900 0.900 15 1.925 0.205 1.200 1.200 1.200 1.200 20 1.925 0.205 1.500 1.500 1.500 1.500 25 1.93 0.210 1.800 1.800 1.800 1.800 30 1.93 0.210 2.100 2.100 2.100 2.100 35 1.93 0.210 2.400 2.400 2.400 2.400 40 1.93 0.210 2.700 2.700 2.700 2.700 45 1.93 0.210 3.000 3.000 3.000 3.000 50 1.93 0.210 3.300 3.300 3.300 3.300 55 1.93 0.210 3.600 3.600 3.600 3.600 60 1.93 10320 0.210 3.900 3.900 3.900 3.900 II 65 2.23 0.510 4.200 4.200 4.200 4.200 70 2.24 0.520 4.500 4.500 4.500 4.500 75 2.245 0.525 4.800 4.800 4.800 4.800 80 2.25 0.530 5.100 5.100 5.100 5.100 85 2.25 0.530 5.400 5.400 5.400 5.400 90 2.255 0.535 5.700 5.700 5.700 5.700 95 2.255 0.535 6.000 6.000 6.000 6.000 100 2.255 0.535 6.300 6.300 6.300 6.300 105 2.255 0.535 6.600 6.600 6.600 6.600 110 2.255 0.535 6.900 6.900 6.900 6.900 115 2.255 0.535 7.200 7.200 7.200 7.200 120 2.255 17040 0.535 7.500 7.450 7.500 7.500 III 125 2.3 0.580 7.800 7.750 7.800 7.800 130 2.35 0.630 8.100 8.080 8.080 8.100 STEP DRAWDOWN TEST DATA Step Drawdown Test Data 25
  • 41. Step Drawdown Test Results 26
  • 42. Step Drawdown Test Results 26
  • 43. Step Drawdown Test Results 26
  • 44. Testing Procedure Installation of PW & OW Well Development Trial Runs Step drawdown test – SDD test Constant discharge test – CD test Recuperation / Recovery test 27
  • 45. Testing Procedure Installation of PW & OW Well Development Trial Runs Step drawdown test – SDD test Constant discharge test – CD test Recuperation / Recovery test 27
  • 46. Constant Discharge Test Overview To determine hydraulic characteristics of the aquifer within the radius of influence of PW PW continuously pumped to ensure desired drawdown at steady state. Water level readings are recorded in PW and OW’s at regular intervals. Test continues till steady state / equilibrium 28
  • 47. CONSTANT DISCHARGE TEST DATA Location: Mall at Noida Time vs Draw Down in all wells Discharge = 48,000 lph = 48 m3 /hr PW ROBW-1 ROBW-2 TOBW-1 TOBW-2 r = 0 m r = 10 m r = 20 m r = 10 m r = 20 m 0 0.000 0.000 0.000 0.000 0.000 1 1.330 0.160 0.000 0.200 0.000 2 1.340 0.190 0.060 0.210 0.010 3 1.350 0.195 0.100 0.210 0.100 4 1.360 0.200 0.130 0.210 0.100 5 1.370 0.200 0.130 0.210 0.110 6 1.370 0.200 0.130 0.220 0.160 7 1.380 0.210 0.130 0.220 0.160 8 1.390 0.210 0.130 0.220 0.160 9 1.400 0.215 0.130 0.230 0.160 10 1.410 0.220 0.130 0.230 0.160 15 1.410 0.225 0.135 0.240 0.160 20 1.410 0.227 0.140 0.250 0.160 25 1.410 0.230 0.140 0.250 0.160 30 1.410 0.230 0.140 0.260 0.160 35 1.410 0.235 0.140 0.260 0.160 40 1.410 0.240 0.140 0.260 0.160 45 1.410 0.245 0.140 0.270 0.160 50 1.410 0.250 0.140 0.270 0.160 55 1.410 0.260 0.140 0.280 0.160 60 1.410 0.260 0.140 0.280 0.160 75 1.410 0.270 0.140 0.280 0.160 90 1.415 0.290 0.140 0.290 0.160 105 1.420 0.320 0.150 0.290 0.165 120 1.430 0.320 0.160 0.290 0.170 135 1.440 0.320 0.170 0.300 0.175 150 1.450 0.325 0.175 0.305 0.175 165 1.460 0.330 0.180 0.320 0.180 Time (min) Drawdown, metres CD Test Data 29
  • 50. Testing Procedure Installation of PW & OW Well Development Trial Runs Step draw down test – SDD test Constant discharge test – CD test Recuperation / Recovery test 31
  • 51. Testing Procedure Installation of PW & OW Well Development Trial Runs Step draw down test – SDD test Constant discharge test – CD test Recuperation / Recovery test 31
  • 52. Recuperation / Recovery Test After CD test is complete, Pump is stopped Take water level readings in same sequence as for CD Test continues till water level rises up to static level Provides independent check of CD Results 32
  • 53. Formation Method Aquifer Parameters Coefficient of Permeability from Borehole Data (cm/sec) Tav (m2/day) Kav (cm/sec) Sav Alluvium Strata (Yamuna Sands) CD Test 1782 1.9 × 10−1 4.1 × 10−2 2.0 × 10−4 ~ 5.0 × 10−4 Recovery Test 4046 4.3 × 10−1 - Summary of Results 33
  • 54. Formation Method Aquifer Parameters Coefficient of Permeability from Borehole Data (cm/sec) Tav (m2/day) Kav (cm/sec) Sav Alluvium Strata (Yamuna Sands) CD Test 1782 1.9 × 10−1 4.1 × 10−2 2.0 × 10−4 ~ 5.0 × 10−4 Recovery Test 4046 4.3 × 10−1 - Summary of Results 33
  • 55. Test Summary Large unconfined aquifer with very high permeability and storage capacity Actual K three orders of magnitude higher than original estimate (based on borehole tests) Very low drawdown (<2.0 m) even at high discharge (48,000 lph) For 13 m drawdown: • > 3,00,000 lph discharge required • 7.2 million litres of water would need to be discharged into the adjoining drain every day! • Affect on adjoining structures? 34
  • 56. Test Consequences Design altered - raised final excavation level Deep diaphragm wall constructed, which acts as cut-off-barrier to GW flow, restricts the aquifer extent, and protects nearby structures from subsistence due to migration of fines etc. Installed dewatering wells spaced at 25~30 m 35
  • 57. Geotechnical Engineering is a Science, But its Practice, an Art... 36