SlideShare a Scribd company logo
Sanjay Gupta
Ravi Sundaram
CENGRS GEOTECHNICA PVT. LTD.CENGRS GEOTECHNICA PVT. LTD.
Sanjay Gupta
Ravi Sundaram
CENGRS GEOTECHNICA PVT. LTD.CENGRS GEOTECHNICA PVT. LTD.
FOUNDATION STRUCTURAL
DISTRESS
GEO PROFESSIONAL
To act as a
Doctor with
healing touch
& not as
Policeman
Foundation Distress
MAN MADE NATURAL
DISASTER /
CASUALTIES
MAY OR MAY
NOT LEAD TO
Well / pond
Artesian
Ignorance of soil /
Loads / additional load
Variation in Loads
on Foundations
• Additional floors
• Change in space
utilization
• Change in structural /
architectural layout
Soil Conditions
• Unusual soil conditions – loose soils,
unmapped tunnels, localized problems
• Strata not behaving as envisaged
• Inadequate soil data - misinterpretation
and / or wrong analysis
•• DESIGN BASISDESIGN BASIS –– WITHOUTWITHOUT
REFERENCE TO SITE CONDITIONSREFERENCE TO SITE CONDITIONS
(MISTRY APPROACH)(MISTRY APPROACH)
Underground Tunnel / Cavity
Hill Slope Failure
Settlement Crack in Wall
Building Damage Due to
Earthquake
TOTALTOTAL
FOUNDATION DISTRESSFOUNDATION DISTRESS
SETTLEMENTSSETTLEMENTS SHEAR FAILURESHEAR FAILURE SERVICEABILITYSERVICEABILITY
FAILUREFAILURE
DIFFERENTIALDIFFERENTIAL
LOWER FACTORLOWER FACTOR
OF SAFETYOF SAFETY
Approach same as FORENSICApproach same as FORENSIC
BUT without court of LAWBUT without court of LAW
MITIGATING
Mitigating Distress
• Steps taken before
disaster strikes or on
noticing first signs of
distress
• Preventive action to
avoid failure
• Experienced engineer
can identify telltale
signs
Mitigating Foundation Distress
• Ensure desired factor of
safety
• Meet Serviceability
criterion
• Restrict further settlements
• Allow additional load
-vertical expansion
• Facilitate adjoining
constructions
RULE TO MITIGATION
4 W’ S - What Went Wrong
& Why
Brain StormingBrain Storming InteractiveInteractive
The 4 W’s
• Identify the problem
• Investigate causes, assess
risk
• Review structural details &
geotechnical data
• Assess foundation
behavior, perform back-
analysis of data
4W’s - Approach
Mitigating distress
Selection of Investigation
Techniques
Geology of Area
& soil data
Foundation detail
Assessment of
Reasons & nature
of distress
Design Profile Appropriate
Analysis
4 W
Implementation
• Develop technically feasible
solutions
• Review merits & demerits
• Select final solution
• Monitoring during
Implementation
ProjectProject
ProblemProblem
Inadequate foundation /
excessive settlement
Solution ConceptsSolution Concepts
Geotechnical DataGeotechnical Data
ReviewReview
Merits/DemeritsMerits/Demerits
Structural DetailsStructural Details
Analysis
Prediction ofPrediction of
Foundation BehaviorFoundation Behavior
Final SchemeFinal Scheme
Implementation
Failure - Distress
• Actual Failure:
– May be able to work back the soil
parameters , by Back Analysis
• Partial Failure / Distress
– Serviceability Problem: May not be
able to do back-analysis. Requires
ingenuity of the engineer
Mitigating Distress -Approaches
• Improve soil / strata strength properties
– Engineer the supporting ground
• Confinement of foundations
– To restrict settlements
– To increase shear resistance
• Restrict lateral soil movement
– Grouting
– Contiguous piles / in combination with
different techniques
Mitigating - Foundation
Distress
Projects executed - CENGRS
Janmabhoomi Temple,
Mangarh
Main Temple
Garba Griha
Platform
Small Temples/
Corridor
Small Temples/
Corridor
Mitigating Foundation Distress
Janmabhoomi Temple , MangarhJanmabhoomi Temple , Mangarh
• Distress – minor tilting of foundation
block
• Distress mitigated to achieve:
– Desired factor of safety
– Serviceability criterion
– Stability – dome type structures
Temple at Birth Place of
His Holiness KripaluHis Holiness Kripalu
MaharajMaharaj
a highly respected saint at
MangarhMangarh, about 35 km from
Allahabad towards Lucknow
Janmabhoomi Temple,
Mangarh
• Massive structure – traditional ancient
Hindu temple architecture
• Granite blocks – upto platform level
• Carved granite blocks - temple structure
• Architecture on same lines as
– Ancient Somnath Temples
– Modern Akshardham
A View of the Constructed Temple
Garba GrihaGarba Griha
MandapMandap
Small TemplesSmall Temples
CorridorCorridor
PlatformPlatform
Structural Details of Temple
• Foundation depth 3 m below G.L.
• Platform constructed upto 2.4 m above G.L.
• Total 5.4 m thick massive granite structure
– bearing pressure at foundation level equal to
14-15 T/m2 for platform (foundation block)
only
• Main block surrounded by 1.2 m wide
peripheral granite stone walls for small
temples/corridors
Geotechnical Considerations
• Total settlements : no major problem
• Tilting : not permissible
• Differential settlement : to be minimized
• Dome type structure : Cannot withstand tilt
• Different loadings:
– Platform : 15 ∼ 16.0 T/m2
– Main temple : 25 ∼ 27 T/m2
– Small temples : 20 ∼ 21 T/m2
Problem
• Cracks noticed when constructed
upto +2.4 m level (at loading of approx.
15.5 T/m2) even before construction of
superstructure began
• Engineers opined differential settlements /
tilt critical under varied loading conditions
vs. Soil characteristics especially in view of
Dome type construction
Limitations to Solutions
• MYTH
– No steel should touch temple structures
– No steel to be used in Mandap area
• Limited work space for additional
foundation system
• No RCC for taking tensile / bending stresses
• Basic structure not to be altered
Soil Profile – Mangarh
SPT Results – Mangarh
Foundation Level
SCPT Results – Mangarh
Foundation
Level
Engineering Solution
• Create confinement to main
temple
• Restrict outward flow of soil ,
in MANDAP
• Improve soils around small
temples / corridor
Foundation
Stabilization Scheme
Confinement of Main Temple
• To create cut-off-wall
– Pressure distribution more uniform
– Increase bearing capacity safety factor
– Restrict lateral soil movement
– Restrict differential settlement
• Ensures total settlement more uniform in
more controlled manner
Piles for Confinement
• All around main temple block 500 ∼ 800
mm wide space available
• RCC pile 400 mm dia, 12 m depth below
G.L. (i.e. 9 m below foundn level)
• Piles cast 700 mm below Platform level
• Interconnecting beam in annular space
• Top of beam 300 mm below platform level
Confinement Piles – Mangarh
Myth, Concept – Mangarh
• RCC of beam and stone masonry separated
by Shailtex board
• Open space covered by granite slabs
maintaining air gap between RCC beam and
stone masonry
Details of Piles (for Confinement)
Mandap Area
• Octagonal opening in
centre
• Big dome supported
over 8 columns
• Cannot tolerate
differential settlement
Mandap Area
CONCERNCONCERN
• Soil plug may squeeze &
may move up due to lateral
soil pressure
• No R.C.C. piles could be
used - MYTH
DECISIONDECISION
• Concrete piles to confine
Mandap area with concrete
slab
Piles Layout – Mandap,
Mangarh
• Dome
– Supported by
8 columns
– Sensitive to
tilting /
differential
settlement
Pile Details – Mandap,
Mangarh
Small Temples / Corridor
• Strip footing 1.2 m wide
• Loading 21 T/m2
• Soils weak shear failure / punching failure
• Settlement excessive under loading
• Differential settlement due to variance in
rigidity /stiffness of structure – main
temple, small temples & platform
Small Temples - Improvement
• By granular piles / stone columns
– φ of composite material : 35 ∼ 45°
– Avoid punching / shear failure
• Compact soils around strip footing
– improve bearing capacity
– reduce settlements under loading of 21 T/m2
• Greater compatibility with main block
reducing differential settlements
Ground Improvement
• Rammed stone columns / granular piles
500 mm dia : 5 m below foundation level
• To provide upto 1.5 m above foundation
level or upto 1.5 m below ground level
• Sand filling compacted above stone
columns up to platform level
Stone Column Layout
Mangarh
Small Temples – A View
Foundation Stabilized
Effectively
• Construction done at slow rate due
to elaborate onsite carving
– Advantageous from the geotechnical
point of view
– Controlled and uniform settlement
THE TEMPLE IS PLANNED TOTHE TEMPLE IS PLANNED TO
SURVIVE FOR CENTURIES!!SURVIVE FOR CENTURIES!!
Mitigating Foundation
Distress
Serviceability Criterion
Over head water tank – 4 W’s
• OHT of 30 m high
• Has cyclic loading conditions – filling &
emptying daily
• During hydrotest , slight tilt was observed
• Designs were checked & found O.K.
• Investigations carried out
• Inferred – soil strata is responsible
Domain of GeoDomain of Geo –– ProfessionalProfessional
Stratigraphy Under Tank
Loose Sandy SiltLoose Sandy Silt
N = 8N = 8--1010
Sandy silt with gravels /hard strataSandy silt with gravels /hard strata
• Geotechnical problem
– understand what
went wrong & why --
4W’S
– Differential settlement
– Variation in
compressible layer
thickness
– Under ground flow of
water
Foundation Strengthening
Scheme
• Curtain wall to create confinement, restrict
lateral soil movement and control migration
of fines
• A combination of closely spaced short piles
seated on underlying hard strata and cement
grouting of the loose soils
Foundation Strengthening -
Schematic
Foundation Strengthening
Scheme
PilesPiles Grout HolesGrout Holes Edge of RaftEdge of Raft
FoundationFoundation
First Phase
• 300 mm diameter auger piles
extending to top of
hard/refusal strata
• A conduit pipe was placed in
pile bores prior to concreting
• After concreting, cement
grout was pumped through
the conduit pipes
Conduit PipeConduit Pipe
FromFrom
Grout PumpGrout Pump
300mm
GLGL
Hard/Refusal StrataHard/Refusal Strata
Concrete PileConcrete Pile
ReinforcementReinforcement
steelsteel
Second Phase
• Grout holes of 75mm diameter
were drilled in the space
between the piles and raft
foundation up to the refusal/hard
layer
• The grout holes were plugged at
foundation level
• Pressure grouting with cement
slurry was done till refusal to
further grout intake was met
under a pressure of 2 to 2.5
kg/cm2
Conduit PipeConduit Pipe
FromFrom
Grout PumpGrout Pump
75mm
GLGL
Hard/Refusal StrataHard/Refusal Strata
Founding LevelFounding Level
RESULT
• Tank in operation on daily basis
• Water filling / emptying daily
• No further distress / Tilt noticed over last
few years
Mitigating Foundation
Distress
Factor of Safety - Criterion
Residential Complex – 4 W’s
• 4 storeyed residential blocks constructed
• During excavations for services
– Observed that foundations were extending just
beyond wall widths & to shallower depths
• Alarm soundedAlarm sounded – other wall foundations
were checked
– less foundation widths & depths were observed
• Though structures were not showing any distress
BUT FACTOR OF SAFETY WAS
LOWER THAN THE REQUIRED
Typical Strata Structural
Details
• Load bearing walls
with few columns
• Spread footings
• Foundation depth as
1.5 M , below GL
• Designs - All.
Loading intensity as
15 T / Sq.M
• Weathered Quartzite
bed rock
Evaluating the Foundations
• At several locations, small pits were
excavated to measure the actual foundation
sizes
• From the loading data, the actual bearing
pressures were computed
• Actual computed factor of safety ranged
from 1.3 to 2.1 , i.e. less than desired F.O.S.
of 2.5
SOLUTIONS
• Various solutions were reviewed for
supporting structural loads by additional
foundation system w.r.t merits & demerits
– By under pinning
– By providing ISMB S , etc.
FINAL CHOICE
By providing
PILESPILES –– NEEDLE BEAM SYSTEMNEEDLE BEAM SYSTEM
Piles – Needle Beam System
• Providing piles on either side of wall
• Connecting piles by Needle Beam over
piles & through the wall
• Concreting & grouting the gap between the
beam & wall
• Provide Re-bar in walls upto 1.2 m ht.
Above plinth level to act as beam for
distribution of loads
The Needle Beam Concept
Brick WallBrick Wall
Damp Proof Course (DPC)Damp Proof Course (DPC)
Needle BeamNeedle Beam
Existing BrickExisting Brick
FootingFooting
PilePile
Hard StrataHard Strata
Typical SectionTypical Section
750 mm750 mm750 mm750 mm
300300
300300
APPROACH
• STEPS
– Excavate pits for each wall
foundation
– Measure existing foundation sizes
– Calculate load that can be transferred
– Compare with structural loading
– Compute deficiency in loading
– Design spacing for pile group to meet
deficiency
Installing the Needle Beam
Typical Layout
16 T/m2
16 T/m2
17 T/m2
17 T/m2
9.5 T/m2
11T/m2
9.5T/m2
9.5T/m2
11 T/m2
BED ROOMBED ROOM
DRAWING CUMDRAWING CUM
DINING ROOMDINING ROOM
KITCHENKITCHEN
BED ROOMBED ROOM
CourtyardLineCourtyardLine
RESULT
•Housing complex handed over after
strengthening
•All houses under occupation
NO DISTRESS / CRACKSNO DISTRESS / CRACKS
OBSERVEDOBSERVED
Structures in use for over 6Structures in use for over 6--7 years7 years
with Desired Factor of Safetywith Desired Factor of Safety
CONCLUDING REMARKS
• MITIGATING FOUNDATION DISTRESS
• A STEP PRIOR TO DISASTER / FAILURE
• Approach similar to human body
• Diagnostic approach - 4 W’s
– History
– Pathological Investigation
• Treatment - check response
• Consult your GEOGEO--PROFESSIONALPROFESSIONAL
as you would consult your DOCTOR
ThankThank
You!You!

More Related Content

What's hot

Underground rock reinforcement and support
Underground rock reinforcement and supportUnderground rock reinforcement and support
Underground rock reinforcement and support
Balraj Joshi
 
Re retaining walls1
Re retaining walls1Re retaining walls1
Re retaining walls1
astraeaeos
 
Conservation methods 13 2-2013
Conservation methods 13 2-2013Conservation methods 13 2-2013
Conservation methods 13 2-2013
ALI HYDER GADHI
 
Innovative Slope Stabilisation
Innovative Slope StabilisationInnovative Slope Stabilisation
Innovative Slope Stabilisation
selvem
 
ASCE Geopier Presentation March 2015
ASCE Geopier Presentation March 2015ASCE Geopier Presentation March 2015
ASCE Geopier Presentation March 2015
American Society of Civil Engineers, Orange County Branch
 
Ceng chapter 1
Ceng chapter 1Ceng chapter 1
Ceng chapter 1
dumesagudissa
 
Jet-grouting Technology
Jet-grouting TechnologyJet-grouting Technology
Jet-grouting Technology
MECandPMV
 
Reinforced earth walls
Reinforced earth wallsReinforced earth walls
Reinforced earth walls
Raju Sabarish
 
Soil improvement report final
Soil improvement report finalSoil improvement report final
Soil improvement report final
Mohd Usama
 
Ground imrovement introduction
Ground imrovement   introductionGround imrovement   introduction
Ground imrovement introduction
Sanjay Thakare
 
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Vladimir Popovic
 
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Vladimir Popovic
 
Abhishek, tarachand and satyanarayana reddy igc 2013 roorkee
Abhishek, tarachand and satyanarayana reddy   igc 2013 roorkeeAbhishek, tarachand and satyanarayana reddy   igc 2013 roorkee
Abhishek, tarachand and satyanarayana reddy igc 2013 roorkee
Tarachand Veeragattapu
 
Ground improvement techniques qb
Ground improvement techniques   qbGround improvement techniques   qb
Ground improvement techniques qb
Preethi Abinaya
 
Research in geotechnical engineering
Research in geotechnical engineeringResearch in geotechnical engineering
Research in geotechnical engineeringAbhineet Godayal CE
 
Soil improvement
Soil improvementSoil improvement
Soil improvement
Mithra G
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
ajinkya gaikwad
 
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Vladimir Popovic
 
Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakambaJohn Chakamba
 

What's hot (20)

Underground rock reinforcement and support
Underground rock reinforcement and supportUnderground rock reinforcement and support
Underground rock reinforcement and support
 
Re retaining walls1
Re retaining walls1Re retaining walls1
Re retaining walls1
 
Conservation methods 13 2-2013
Conservation methods 13 2-2013Conservation methods 13 2-2013
Conservation methods 13 2-2013
 
Innovative Slope Stabilisation
Innovative Slope StabilisationInnovative Slope Stabilisation
Innovative Slope Stabilisation
 
ASCE Geopier Presentation March 2015
ASCE Geopier Presentation March 2015ASCE Geopier Presentation March 2015
ASCE Geopier Presentation March 2015
 
Ceng chapter 1
Ceng chapter 1Ceng chapter 1
Ceng chapter 1
 
Jet-grouting Technology
Jet-grouting TechnologyJet-grouting Technology
Jet-grouting Technology
 
Reinforced earth walls
Reinforced earth wallsReinforced earth walls
Reinforced earth walls
 
Soil improvement report final
Soil improvement report finalSoil improvement report final
Soil improvement report final
 
Ground imrovement introduction
Ground imrovement   introductionGround imrovement   introduction
Ground imrovement introduction
 
Download
DownloadDownload
Download
 
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)
 
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
 
Abhishek, tarachand and satyanarayana reddy igc 2013 roorkee
Abhishek, tarachand and satyanarayana reddy   igc 2013 roorkeeAbhishek, tarachand and satyanarayana reddy   igc 2013 roorkee
Abhishek, tarachand and satyanarayana reddy igc 2013 roorkee
 
Ground improvement techniques qb
Ground improvement techniques   qbGround improvement techniques   qb
Ground improvement techniques qb
 
Research in geotechnical engineering
Research in geotechnical engineeringResearch in geotechnical engineering
Research in geotechnical engineering
 
Soil improvement
Soil improvementSoil improvement
Soil improvement
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing ConditionsRehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
Rehabilitation of Oragvis-Gele Water RC Reservoir, Existing Conditions
 
Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakamba
 

Similar to Mitigating foundation distress

Akash verma.pptx
Akash verma.pptxAkash verma.pptx
Akash verma.pptx
AMITYADAV960525
 
analysis of soil and suggested ground improvement techniques
analysis of soil and suggested ground improvement techniquesanalysis of soil and suggested ground improvement techniques
analysis of soil and suggested ground improvement techniques
Kuldeepkulshrestha2
 
Foundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarhFoundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarh
Infocengrs63
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
Shubham Parab
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
IEI GSC
 
Failures of an earthen dam
Failures of an earthen damFailures of an earthen dam
Failures of an earthen dam
Divya Vishnoi
 
Final_ppt_puneeth.pptx
Final_ppt_puneeth.pptxFinal_ppt_puneeth.pptx
Final_ppt_puneeth.pptx
Doctor Sadaf Qasim
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
Andhra University
 
Ann vii -structure repairs bihar
Ann vii -structure repairs biharAnn vii -structure repairs bihar
Ann vii -structure repairs biharVaishnav Mishra
 
Influence of geological condition on foundation and design of building
Influence of geological condition on  foundation and design of buildingInfluence of geological condition on  foundation and design of building
Influence of geological condition on foundation and design of building
Darshan Darji
 
Reservoirs_and_dams their components.ppt
Reservoirs_and_dams their components.pptReservoirs_and_dams their components.ppt
Reservoirs_and_dams their components.ppt
muk7971
 
MODULE 1.pptx
MODULE 1.pptxMODULE 1.pptx
MODULE 1.pptx
SEKHARJ3
 
Environment impact of landslides
Environment impact of landslidesEnvironment impact of landslides
Environment impact of landslides
MonaliBose
 
Dams.ppt
Dams.pptDams.ppt
Dams.ppt
indrajeetsahu20
 
Ground freezing
Ground freezingGround freezing
Ground freezing
AVINASH PANDEY
 
Michalis presentation_2015
Michalis presentation_2015Michalis presentation_2015
Michalis presentation_2015ILIAS MICHALIS
 
GeoSS,18SEAGS,CTS,04062013, A
GeoSS,18SEAGS,CTS,04062013, AGeoSS,18SEAGS,CTS,04062013, A
GeoSS,18SEAGS,CTS,04062013, ATong Seng Chua
 
GeoSS,18SEAGS, 2013, Singapore
GeoSS,18SEAGS, 2013, SingaporeGeoSS,18SEAGS, 2013, Singapore
GeoSS,18SEAGS, 2013, SingaporeTong Seng Chua
 
GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES
harshitha alishetty
 

Similar to Mitigating foundation distress (20)

Akash verma.pptx
Akash verma.pptxAkash verma.pptx
Akash verma.pptx
 
analysis of soil and suggested ground improvement techniques
analysis of soil and suggested ground improvement techniquesanalysis of soil and suggested ground improvement techniques
analysis of soil and suggested ground improvement techniques
 
Foundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarhFoundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarh
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
 
Failures of an earthen dam
Failures of an earthen damFailures of an earthen dam
Failures of an earthen dam
 
Final_ppt_puneeth.pptx
Final_ppt_puneeth.pptxFinal_ppt_puneeth.pptx
Final_ppt_puneeth.pptx
 
W16 ground improvement techniques-dycus
W16 ground improvement techniques-dycusW16 ground improvement techniques-dycus
W16 ground improvement techniques-dycus
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
 
Ann vii -structure repairs bihar
Ann vii -structure repairs biharAnn vii -structure repairs bihar
Ann vii -structure repairs bihar
 
Influence of geological condition on foundation and design of building
Influence of geological condition on  foundation and design of buildingInfluence of geological condition on  foundation and design of building
Influence of geological condition on foundation and design of building
 
Reservoirs_and_dams their components.ppt
Reservoirs_and_dams their components.pptReservoirs_and_dams their components.ppt
Reservoirs_and_dams their components.ppt
 
MODULE 1.pptx
MODULE 1.pptxMODULE 1.pptx
MODULE 1.pptx
 
Environment impact of landslides
Environment impact of landslidesEnvironment impact of landslides
Environment impact of landslides
 
Dams.ppt
Dams.pptDams.ppt
Dams.ppt
 
Ground freezing
Ground freezingGround freezing
Ground freezing
 
Michalis presentation_2015
Michalis presentation_2015Michalis presentation_2015
Michalis presentation_2015
 
GeoSS,18SEAGS,CTS,04062013, A
GeoSS,18SEAGS,CTS,04062013, AGeoSS,18SEAGS,CTS,04062013, A
GeoSS,18SEAGS,CTS,04062013, A
 
GeoSS,18SEAGS, 2013, Singapore
GeoSS,18SEAGS, 2013, SingaporeGeoSS,18SEAGS, 2013, Singapore
GeoSS,18SEAGS, 2013, Singapore
 
GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES
 

More from Infocengrs63

Geotechnics of artesian flow – case study of river shivganga, nepal
Geotechnics of artesian flow – case study of river shivganga, nepalGeotechnics of artesian flow – case study of river shivganga, nepal
Geotechnics of artesian flow – case study of river shivganga, nepal
Infocengrs63
 
In situ testing – current trends in geotechnical investigations
In situ testing – current trends in geotechnical investigationsIn situ testing – current trends in geotechnical investigations
In situ testing – current trends in geotechnical investigations
Infocengrs63
 
Geotechnical investigations dune sands of the thar desert
Geotechnical investigations  dune sands of the thar desertGeotechnical investigations  dune sands of the thar desert
Geotechnical investigations dune sands of the thar desert
Infocengrs63
 
Dynamic characteristics of alluvial deposits a case study
Dynamic characteristics of alluvial deposits a case studyDynamic characteristics of alluvial deposits a case study
Dynamic characteristics of alluvial deposits a case study
Infocengrs63
 
Geotechnical characterization of dune sands of the thar desert
Geotechnical characterization of dune sands of the thar desertGeotechnical characterization of dune sands of the thar desert
Geotechnical characterization of dune sands of the thar desert
Infocengrs63
 
Pile integrity testing for monitoring pile construction
Pile integrity testing for monitoring pile constructionPile integrity testing for monitoring pile construction
Pile integrity testing for monitoring pile construction
Infocengrs63
 
Pump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case studyPump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case study
Infocengrs63
 
Liquefaction susceptibility study at commonwealth games village delhi
Liquefaction susceptibility study at commonwealth games village delhiLiquefaction susceptibility study at commonwealth games village delhi
Liquefaction susceptibility study at commonwealth games village delhi
Infocengrs63
 
Performance of a large diameter oil storage tank on improved clay deposit
Performance of a large diameter oil storage tank on improved clay depositPerformance of a large diameter oil storage tank on improved clay deposit
Performance of a large diameter oil storage tank on improved clay deposit
Infocengrs63
 
Constructing foundations on red mud
Constructing foundations on red mudConstructing foundations on red mud
Constructing foundations on red mud
Infocengrs63
 
Dynamic compaction to mitigate liquefaction potential
Dynamic compaction to mitigate liquefaction potentialDynamic compaction to mitigate liquefaction potential
Dynamic compaction to mitigate liquefaction potential
Infocengrs63
 
Liquefaction risk mitigation for a power plant in the indo gengatic alluvium
Liquefaction risk mitigation for a power plant in the indo gengatic alluviumLiquefaction risk mitigation for a power plant in the indo gengatic alluvium
Liquefaction risk mitigation for a power plant in the indo gengatic alluvium
Infocengrs63
 
Geotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari deltaGeotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari delta
Infocengrs63
 
Quality assurance for_deep_bored_piles
Quality assurance for_deep_bored_pilesQuality assurance for_deep_bored_piles
Quality assurance for_deep_bored_piles
Infocengrs63
 
DFI india 2014 defects in piles
DFI india 2014 defects in pilesDFI india 2014 defects in piles
DFI india 2014 defects in piles
Infocengrs63
 
In-situ testing to verify ground improvement
In-situ testing to verify ground improvementIn-situ testing to verify ground improvement
In-situ testing to verify ground improvement
Infocengrs63
 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sands
Infocengrs63
 

More from Infocengrs63 (17)

Geotechnics of artesian flow – case study of river shivganga, nepal
Geotechnics of artesian flow – case study of river shivganga, nepalGeotechnics of artesian flow – case study of river shivganga, nepal
Geotechnics of artesian flow – case study of river shivganga, nepal
 
In situ testing – current trends in geotechnical investigations
In situ testing – current trends in geotechnical investigationsIn situ testing – current trends in geotechnical investigations
In situ testing – current trends in geotechnical investigations
 
Geotechnical investigations dune sands of the thar desert
Geotechnical investigations  dune sands of the thar desertGeotechnical investigations  dune sands of the thar desert
Geotechnical investigations dune sands of the thar desert
 
Dynamic characteristics of alluvial deposits a case study
Dynamic characteristics of alluvial deposits a case studyDynamic characteristics of alluvial deposits a case study
Dynamic characteristics of alluvial deposits a case study
 
Geotechnical characterization of dune sands of the thar desert
Geotechnical characterization of dune sands of the thar desertGeotechnical characterization of dune sands of the thar desert
Geotechnical characterization of dune sands of the thar desert
 
Pile integrity testing for monitoring pile construction
Pile integrity testing for monitoring pile constructionPile integrity testing for monitoring pile construction
Pile integrity testing for monitoring pile construction
 
Pump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case studyPump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case study
 
Liquefaction susceptibility study at commonwealth games village delhi
Liquefaction susceptibility study at commonwealth games village delhiLiquefaction susceptibility study at commonwealth games village delhi
Liquefaction susceptibility study at commonwealth games village delhi
 
Performance of a large diameter oil storage tank on improved clay deposit
Performance of a large diameter oil storage tank on improved clay depositPerformance of a large diameter oil storage tank on improved clay deposit
Performance of a large diameter oil storage tank on improved clay deposit
 
Constructing foundations on red mud
Constructing foundations on red mudConstructing foundations on red mud
Constructing foundations on red mud
 
Dynamic compaction to mitigate liquefaction potential
Dynamic compaction to mitigate liquefaction potentialDynamic compaction to mitigate liquefaction potential
Dynamic compaction to mitigate liquefaction potential
 
Liquefaction risk mitigation for a power plant in the indo gengatic alluvium
Liquefaction risk mitigation for a power plant in the indo gengatic alluviumLiquefaction risk mitigation for a power plant in the indo gengatic alluvium
Liquefaction risk mitigation for a power plant in the indo gengatic alluvium
 
Geotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari deltaGeotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari delta
 
Quality assurance for_deep_bored_piles
Quality assurance for_deep_bored_pilesQuality assurance for_deep_bored_piles
Quality assurance for_deep_bored_piles
 
DFI india 2014 defects in piles
DFI india 2014 defects in pilesDFI india 2014 defects in piles
DFI india 2014 defects in piles
 
In-situ testing to verify ground improvement
In-situ testing to verify ground improvementIn-situ testing to verify ground improvement
In-situ testing to verify ground improvement
 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sands
 

Recently uploaded

Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
itech2017
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 

Recently uploaded (20)

Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 

Mitigating foundation distress

  • 1. Sanjay Gupta Ravi Sundaram CENGRS GEOTECHNICA PVT. LTD.CENGRS GEOTECHNICA PVT. LTD. Sanjay Gupta Ravi Sundaram CENGRS GEOTECHNICA PVT. LTD.CENGRS GEOTECHNICA PVT. LTD.
  • 2.
  • 3. FOUNDATION STRUCTURAL DISTRESS GEO PROFESSIONAL To act as a Doctor with healing touch & not as Policeman
  • 4.
  • 5. Foundation Distress MAN MADE NATURAL DISASTER / CASUALTIES MAY OR MAY NOT LEAD TO Well / pond Artesian Ignorance of soil / Loads / additional load
  • 6. Variation in Loads on Foundations • Additional floors • Change in space utilization • Change in structural / architectural layout
  • 7. Soil Conditions • Unusual soil conditions – loose soils, unmapped tunnels, localized problems • Strata not behaving as envisaged • Inadequate soil data - misinterpretation and / or wrong analysis •• DESIGN BASISDESIGN BASIS –– WITHOUTWITHOUT REFERENCE TO SITE CONDITIONSREFERENCE TO SITE CONDITIONS (MISTRY APPROACH)(MISTRY APPROACH)
  • 11. Building Damage Due to Earthquake
  • 12. TOTALTOTAL FOUNDATION DISTRESSFOUNDATION DISTRESS SETTLEMENTSSETTLEMENTS SHEAR FAILURESHEAR FAILURE SERVICEABILITYSERVICEABILITY FAILUREFAILURE DIFFERENTIALDIFFERENTIAL LOWER FACTORLOWER FACTOR OF SAFETYOF SAFETY Approach same as FORENSICApproach same as FORENSIC BUT without court of LAWBUT without court of LAW MITIGATING
  • 13. Mitigating Distress • Steps taken before disaster strikes or on noticing first signs of distress • Preventive action to avoid failure • Experienced engineer can identify telltale signs
  • 14. Mitigating Foundation Distress • Ensure desired factor of safety • Meet Serviceability criterion • Restrict further settlements • Allow additional load -vertical expansion • Facilitate adjoining constructions
  • 16. 4 W’ S - What Went Wrong & Why Brain StormingBrain Storming InteractiveInteractive
  • 17. The 4 W’s • Identify the problem • Investigate causes, assess risk • Review structural details & geotechnical data • Assess foundation behavior, perform back- analysis of data
  • 18. 4W’s - Approach Mitigating distress Selection of Investigation Techniques Geology of Area & soil data Foundation detail Assessment of Reasons & nature of distress Design Profile Appropriate Analysis 4 W
  • 19. Implementation • Develop technically feasible solutions • Review merits & demerits • Select final solution • Monitoring during Implementation
  • 20. ProjectProject ProblemProblem Inadequate foundation / excessive settlement Solution ConceptsSolution Concepts Geotechnical DataGeotechnical Data ReviewReview Merits/DemeritsMerits/Demerits Structural DetailsStructural Details Analysis Prediction ofPrediction of Foundation BehaviorFoundation Behavior Final SchemeFinal Scheme Implementation
  • 21. Failure - Distress • Actual Failure: – May be able to work back the soil parameters , by Back Analysis • Partial Failure / Distress – Serviceability Problem: May not be able to do back-analysis. Requires ingenuity of the engineer
  • 22. Mitigating Distress -Approaches • Improve soil / strata strength properties – Engineer the supporting ground • Confinement of foundations – To restrict settlements – To increase shear resistance • Restrict lateral soil movement – Grouting – Contiguous piles / in combination with different techniques
  • 24. Janmabhoomi Temple, Mangarh Main Temple Garba Griha Platform Small Temples/ Corridor Small Temples/ Corridor
  • 25. Mitigating Foundation Distress Janmabhoomi Temple , MangarhJanmabhoomi Temple , Mangarh • Distress – minor tilting of foundation block • Distress mitigated to achieve: – Desired factor of safety – Serviceability criterion – Stability – dome type structures
  • 26. Temple at Birth Place of His Holiness KripaluHis Holiness Kripalu MaharajMaharaj a highly respected saint at MangarhMangarh, about 35 km from Allahabad towards Lucknow
  • 27. Janmabhoomi Temple, Mangarh • Massive structure – traditional ancient Hindu temple architecture • Granite blocks – upto platform level • Carved granite blocks - temple structure • Architecture on same lines as – Ancient Somnath Temples – Modern Akshardham
  • 28. A View of the Constructed Temple Garba GrihaGarba Griha MandapMandap Small TemplesSmall Temples CorridorCorridor PlatformPlatform
  • 29. Structural Details of Temple • Foundation depth 3 m below G.L. • Platform constructed upto 2.4 m above G.L. • Total 5.4 m thick massive granite structure – bearing pressure at foundation level equal to 14-15 T/m2 for platform (foundation block) only • Main block surrounded by 1.2 m wide peripheral granite stone walls for small temples/corridors
  • 30. Geotechnical Considerations • Total settlements : no major problem • Tilting : not permissible • Differential settlement : to be minimized • Dome type structure : Cannot withstand tilt • Different loadings: – Platform : 15 ∼ 16.0 T/m2 – Main temple : 25 ∼ 27 T/m2 – Small temples : 20 ∼ 21 T/m2
  • 31. Problem • Cracks noticed when constructed upto +2.4 m level (at loading of approx. 15.5 T/m2) even before construction of superstructure began • Engineers opined differential settlements / tilt critical under varied loading conditions vs. Soil characteristics especially in view of Dome type construction
  • 32. Limitations to Solutions • MYTH – No steel should touch temple structures – No steel to be used in Mandap area • Limited work space for additional foundation system • No RCC for taking tensile / bending stresses • Basic structure not to be altered
  • 33. Soil Profile – Mangarh
  • 34. SPT Results – Mangarh Foundation Level
  • 35. SCPT Results – Mangarh Foundation Level
  • 36. Engineering Solution • Create confinement to main temple • Restrict outward flow of soil , in MANDAP • Improve soils around small temples / corridor
  • 38. Confinement of Main Temple • To create cut-off-wall – Pressure distribution more uniform – Increase bearing capacity safety factor – Restrict lateral soil movement – Restrict differential settlement • Ensures total settlement more uniform in more controlled manner
  • 39. Piles for Confinement • All around main temple block 500 ∼ 800 mm wide space available • RCC pile 400 mm dia, 12 m depth below G.L. (i.e. 9 m below foundn level) • Piles cast 700 mm below Platform level • Interconnecting beam in annular space • Top of beam 300 mm below platform level
  • 41. Myth, Concept – Mangarh • RCC of beam and stone masonry separated by Shailtex board • Open space covered by granite slabs maintaining air gap between RCC beam and stone masonry
  • 42. Details of Piles (for Confinement)
  • 43. Mandap Area • Octagonal opening in centre • Big dome supported over 8 columns • Cannot tolerate differential settlement
  • 44. Mandap Area CONCERNCONCERN • Soil plug may squeeze & may move up due to lateral soil pressure • No R.C.C. piles could be used - MYTH DECISIONDECISION • Concrete piles to confine Mandap area with concrete slab
  • 45. Piles Layout – Mandap, Mangarh • Dome – Supported by 8 columns – Sensitive to tilting / differential settlement
  • 46. Pile Details – Mandap, Mangarh
  • 47. Small Temples / Corridor • Strip footing 1.2 m wide • Loading 21 T/m2 • Soils weak shear failure / punching failure • Settlement excessive under loading • Differential settlement due to variance in rigidity /stiffness of structure – main temple, small temples & platform
  • 48. Small Temples - Improvement • By granular piles / stone columns – φ of composite material : 35 ∼ 45° – Avoid punching / shear failure • Compact soils around strip footing – improve bearing capacity – reduce settlements under loading of 21 T/m2 • Greater compatibility with main block reducing differential settlements
  • 49. Ground Improvement • Rammed stone columns / granular piles 500 mm dia : 5 m below foundation level • To provide upto 1.5 m above foundation level or upto 1.5 m below ground level • Sand filling compacted above stone columns up to platform level
  • 52. Foundation Stabilized Effectively • Construction done at slow rate due to elaborate onsite carving – Advantageous from the geotechnical point of view – Controlled and uniform settlement THE TEMPLE IS PLANNED TOTHE TEMPLE IS PLANNED TO SURVIVE FOR CENTURIES!!SURVIVE FOR CENTURIES!!
  • 54.
  • 55. Over head water tank – 4 W’s • OHT of 30 m high • Has cyclic loading conditions – filling & emptying daily • During hydrotest , slight tilt was observed • Designs were checked & found O.K. • Investigations carried out • Inferred – soil strata is responsible Domain of GeoDomain of Geo –– ProfessionalProfessional
  • 56. Stratigraphy Under Tank Loose Sandy SiltLoose Sandy Silt N = 8N = 8--1010 Sandy silt with gravels /hard strataSandy silt with gravels /hard strata • Geotechnical problem – understand what went wrong & why -- 4W’S – Differential settlement – Variation in compressible layer thickness – Under ground flow of water
  • 57. Foundation Strengthening Scheme • Curtain wall to create confinement, restrict lateral soil movement and control migration of fines • A combination of closely spaced short piles seated on underlying hard strata and cement grouting of the loose soils
  • 59. Foundation Strengthening Scheme PilesPiles Grout HolesGrout Holes Edge of RaftEdge of Raft FoundationFoundation
  • 60. First Phase • 300 mm diameter auger piles extending to top of hard/refusal strata • A conduit pipe was placed in pile bores prior to concreting • After concreting, cement grout was pumped through the conduit pipes Conduit PipeConduit Pipe FromFrom Grout PumpGrout Pump 300mm GLGL Hard/Refusal StrataHard/Refusal Strata Concrete PileConcrete Pile ReinforcementReinforcement steelsteel
  • 61. Second Phase • Grout holes of 75mm diameter were drilled in the space between the piles and raft foundation up to the refusal/hard layer • The grout holes were plugged at foundation level • Pressure grouting with cement slurry was done till refusal to further grout intake was met under a pressure of 2 to 2.5 kg/cm2 Conduit PipeConduit Pipe FromFrom Grout PumpGrout Pump 75mm GLGL Hard/Refusal StrataHard/Refusal Strata Founding LevelFounding Level
  • 62. RESULT • Tank in operation on daily basis • Water filling / emptying daily • No further distress / Tilt noticed over last few years
  • 64.
  • 65. Residential Complex – 4 W’s • 4 storeyed residential blocks constructed • During excavations for services – Observed that foundations were extending just beyond wall widths & to shallower depths • Alarm soundedAlarm sounded – other wall foundations were checked – less foundation widths & depths were observed • Though structures were not showing any distress BUT FACTOR OF SAFETY WAS LOWER THAN THE REQUIRED
  • 66. Typical Strata Structural Details • Load bearing walls with few columns • Spread footings • Foundation depth as 1.5 M , below GL • Designs - All. Loading intensity as 15 T / Sq.M • Weathered Quartzite bed rock
  • 67. Evaluating the Foundations • At several locations, small pits were excavated to measure the actual foundation sizes • From the loading data, the actual bearing pressures were computed • Actual computed factor of safety ranged from 1.3 to 2.1 , i.e. less than desired F.O.S. of 2.5
  • 68. SOLUTIONS • Various solutions were reviewed for supporting structural loads by additional foundation system w.r.t merits & demerits – By under pinning – By providing ISMB S , etc. FINAL CHOICE By providing PILESPILES –– NEEDLE BEAM SYSTEMNEEDLE BEAM SYSTEM
  • 69. Piles – Needle Beam System • Providing piles on either side of wall • Connecting piles by Needle Beam over piles & through the wall • Concreting & grouting the gap between the beam & wall • Provide Re-bar in walls upto 1.2 m ht. Above plinth level to act as beam for distribution of loads
  • 70. The Needle Beam Concept Brick WallBrick Wall Damp Proof Course (DPC)Damp Proof Course (DPC) Needle BeamNeedle Beam Existing BrickExisting Brick FootingFooting PilePile Hard StrataHard Strata Typical SectionTypical Section 750 mm750 mm750 mm750 mm 300300 300300
  • 71. APPROACH • STEPS – Excavate pits for each wall foundation – Measure existing foundation sizes – Calculate load that can be transferred – Compare with structural loading – Compute deficiency in loading – Design spacing for pile group to meet deficiency
  • 73. Typical Layout 16 T/m2 16 T/m2 17 T/m2 17 T/m2 9.5 T/m2 11T/m2 9.5T/m2 9.5T/m2 11 T/m2 BED ROOMBED ROOM DRAWING CUMDRAWING CUM DINING ROOMDINING ROOM KITCHENKITCHEN BED ROOMBED ROOM CourtyardLineCourtyardLine
  • 74. RESULT •Housing complex handed over after strengthening •All houses under occupation NO DISTRESS / CRACKSNO DISTRESS / CRACKS OBSERVEDOBSERVED Structures in use for over 6Structures in use for over 6--7 years7 years with Desired Factor of Safetywith Desired Factor of Safety
  • 75. CONCLUDING REMARKS • MITIGATING FOUNDATION DISTRESS • A STEP PRIOR TO DISASTER / FAILURE • Approach similar to human body • Diagnostic approach - 4 W’s – History – Pathological Investigation • Treatment - check response • Consult your GEOGEO--PROFESSIONALPROFESSIONAL as you would consult your DOCTOR