SlideShare a Scribd company logo
COMPONENTS OF CONCRETE
PAVEMENT
A. Concrete slabs with a determinedthickness
Concrete is a construction material that is made of portland
cement ,aggregate s and water mixed in predetermined
proportions. Concrete solidifies and hardens after mixing
and placement due to a chemical process known asb
hydration.
B. Joints (both transverse and longitudinal)
Concrete slabs will crack randomly from natural
actions such as shrinkage or curling.
Therefore, joints are vital elements introduced into
CP to control cracking and horizontal
movements of the slabs.
Transverse Joints Perpendicular to Lane
Lines and Longitudinal Joints
Longitudinal Joint at Lane Line
Tie bars are typically used at longitudinal joints and
transverse construction joint in a nondoweled
shoulder addition/reconstruction to hold tight the
faces of abutting concrete in contact.
C. Tie bars
Load transfer is the ability of a joint to transfer a portion of
an applied load (the truck wheel)
from one side of the joint to the other.
Dowel Bars in a Transverse Joint
Slab Movements in Non-doweled SlabSlab Movements in Doweled Slab
E. Base layer
~It can provide a stable platform for the
concrete paving, provides for additional load
distribution, and contributes to drainage (if
permeable base is used) and frost resistance.
F.Subbase layer (if required),
~the subbase layer is a planned thickness of
specified material that is placed on the subgrade
or under the basement material.
G.Subgrade
~greater subgrade structural capacity can
result in more economical pavement structures.
The general pavement
Construction
practices involve:
• subgrade, base and subbase preparation
conforming to the thickness and cross section
requirements,
• proper placement of tie bars and dowel bars to
be embedded, carefully examining for bending
which could injure the material, oil, dirt, rust and
other coatings that would prevent or reduce
bonding to concrete.
• proper concrete placement including
consolidation, finishing, texturing, curing and
jointing essential for a strong durable pavement
Sub-grade, Sub-base and Base Preparation
Sub-grade Preparation
~ minimum depth of 0.5 feet below the grading plane
for the width between the outer edges of shoulders, or
~ minimum depth of 2.5 feet below the finished grade for
the width of the traveled way and auxiliary lanes
including 3 feet on both sides as specified in Section
19-5.03 of the Standard Specifications
Sub-base Layer Preparation
•The Department uses Aggregate Sub-base (AS)
for use in JPCP construction to provide a foundation
or working platform for the base when the sub-grade R-
value is less than 40.
•The maximum thickness of any one layer should not
exceed 0.50 foot after watering and compaction.
Where the required thickness is more than 0.50 foot,
spreading, watering and compaction should be
conducted in 2 or more lifts of approximately equal
thickness.
Base Layer Preparation
The Department uses Hot Mix Asphalt (HMA) Type A,
Lean Concrete Base (LCB), Asphalt Treated Permeable Base
(ATPB), and Aggregate Base (AB) to provide a construction
platform underneath the CP.
•Hot Mix Asphalt Type A (HMA-A)
HMA-Type A consists of one or more layers
placed on a prepared sub-base or sub-grade in conformity
with the alignment and grades shown on the project plans.
HMA-A is placed at a 20 temperature of no less than 310
°F and only when the sub-base or sub-grade surface is dry
and in satisfactory condition.
•Lean Concrete Base (LCB) ~ LCB is placed,
constructed and finished in no less than 12-foot widths
separated by contact joints. Widths that are greater than
26 feet are constructed with longitudinal weakened plane
joints at no more than 3 feet from the centerline of the
width being constructed.
•Aggregate Base (AB) ~ where the required thickness
is 0.50-foot or less, is spread and compacted in one layer.
If the required thickness is more than 0.50-foot, spread
and compact AB in two or more lifts in approximately
equal thickness, and each lift shall not exceed 0.50-foot.
Steel Placement
Tie Bar Placement
Tie bars are not to be used at a
joint where concrete and asphalt
concrete pavements abut. Tie bars
are placed:
(a) along longitudinal weakened
plane in multilane paving, and
(b) at longitudinal and transverse
contact joint in a nondoweled
lane/shoulder addition or
reconstruction. These tie bars are
placed at mid depth of the
concrete slab.
• Dowel Bar Placement
Dowel bars are placed as shown on the plans
by using either dowel bar baskets, drilling and
bonding, or mechanical insertion.
• Bar Reinforcement Placement
Although CP does not typically have bar
reinforcement, bar reinforcement can be
found in a few situations such as pavement
transitions ,gore areas, and around drainage
inlets.
• Concrete Placement ~ Concrete is transported to
the paving site by dump trucks or ready-mix trucks
with the goal to deliver a uniform, well-mixed and
workable concrete from batch to batch.
• Consolidation ~ it is the process that compacts
fresh concrete to mold it within the forms and
around steel reinforcements and to remove
undesirable voids.
• Finishing ~it involves any equipment or procedures
used to impart desirable surface characteristics.
• Curing ~ it is the maintenance of satisfactory
moisture and temperature in the concrete as it sets
and hardens such that the desired properties can
develop.
Flexible pavement design
This section describes the design for both asphalt
concrete pavements and surface treatments which
carry significant levels of traffic over the
performance period
Modifications Included in Flexible Pavement
design procedures
• The soil support number is replaced by the resilient modulus
to provide a rational testing procedure that may be used by an
agency to define the material properties.
• The layer coefficients for the various materials are defined in
terms of resilient modulus as well as standard methods (CBR
and R-value).
• The environmental factors of moisture and temperature
objectively included in the Guide so that the environmental
consdiderations could be ratioanally accounted for in the
design procedure.
• Reliability is introduced to permit the designer to use the
concept of risk analysis for various classes of roadways.
• Stage construction design procedures are incorporated.
Design Of Flexible Pavement
• Design Of Flexible Pavement By Group Index Method
Group Index is function of percentage material passing 200 mesh sieve
(0.074mm), liquid limit and plasticity index of soil and is given by
equation:
GI=0.2a+0.005ac+0.01bd
Here,
a=that portion of material passing 0.074mm sieve, greater than 35 And not
exceeding 75 %
b=that portion of material passing 0.074mm sieve, greater than 15 And not
exceeding 35%
c = that value of liquid limit in excess of 40 and less than 60
d = that value of plasticity index exceeding 10 and not more than 30
California Resistance Value Method
pavements thickness varies directly with R value and
logarithm of load repetitions. It varies inversely with fifth
root of Computer value.
T=K (TI) (90-R)/C1/5
Here :
T=total thickness of pavement, cm
K=numerical constant=0.166
TI=traffic index
R=stabilometer resistance value
C =Cohesiometer value
Triaxial Method
Here
T=Pavement thickness, cm
Es=modulus of elasticity of sub grade from triaxial test
result, Kg/cm2
A=radius of contact area, cm
∆=design deflection (0.25 cm)
Other.....
Rigid pavement design
As the name implies, rigid pavements are rigid , they do not
extend much under loading like flexible pavements. They are
constructed using cement concrete. In this case, the load carrying
capacity is mainly due to the rigidity and high modulus of elasticity
of the slab (slab action).
Modifications Included in Rigid
Pavement design procedures:
• Reliability concepts identical to those used
for the flexible pavements are introduced.
• The environmental aspects of design are
introduced in the same format as for flexible
pavements.
• The design procedure is modified to include
such factors as tied shoulders, subbase
erosion, and lean subbase designs.
Rigid Pavement Response
• Curling stress
– Differences in temperature between the top and
bottom surfaces of a PCC slab will cause the
slab to curl. Since slab weight and contact with
the base restrict its movement, stresses are
created.
where:
σt=slab interior warping stress
E=modulus of elasticity of PCC
e=thermal coefficient of PCC (» 0.000005/°F)
Δ T=temperature differential between the top and bottom of the
slab
µ=Poisson’s ratio for PCC (» 0.15)
β=radius of wheel load distribution for corner loading
where:
l=radius of relative stiffness
E=modulus of elasticity of PCC
h=slab thickness
k=modulus of subgrade reaction
m=Poisson’s ratio for PCC (» 0.15)
Load stress
Loads on a PCC slab will create both compressive and
tensile stresses within the slab and any adjacent one (as
long as load transfer efficiency is > 0).
a. Interior loading. Occurs when a load is applied on the
interior of a slab s.urface which is “remote” from all edges.
b. Edge loading. Occurs when a load is applied on a slab
edge “remote” from a slab corner.
c. Corner loading. Occurs when the center of a load is
located on the bisector of the corner angle.
Shrinkage and expansion
• In addition to curling, environmental temperatures will
cause PCC slabs to expand (when hot) and contract
(when cool), which causes joint movement.
where:
z=joint opening = change in slab length (inches)
C=base/slab frictional restraint factor
= 0.65 for stabilized bases
= 0.80 for granular bases
L=slab length (inches)
It is observed that flexible pavements are more economical for
lesser volume of traffic.The life of flexible pavement is near about 15
years whose initial cost is low needs a periodic maintenance after a
certain period and maintenance costs very high.
The life of rigid pavement is much more than the
flexible pavement of about 40 years approx 2.5 times life of
flexible pavement whose initial cost is much more then the
flexible pavement but maintenance cost is very less.
References:
http://www.pavementinteractive.org/article/rigid
-pavement-response/#sthash.ISwV8mbT.dpuf
pavement-procedures-construction-and-re-
construction.pdf
“Start by doing what’s necessary;
then do what’s possible;
and suddenly your are doing the
impossible.”
~Francis of Assisi~
Prepared by:
FONTE, EDDIE RED
ZULUETA, ERWIN JOHN

More Related Content

What's hot

Rigid Pavement Design Part II
Rigid Pavement Design Part IIRigid Pavement Design Part II
Rigid Pavement Design Part II
Sachin Kulkarni
 
BITUMINOUS ROAD PPT
BITUMINOUS ROAD PPTBITUMINOUS ROAD PPT
BITUMINOUS ROAD PPT
shubham paliwal
 
Lecture#01
Lecture#01Lecture#01
Lecture#01
arslan000
 
Pavement materials and testing
Pavement materials and testingPavement materials and testing
Pavement materials and testing
Archana Shagoti
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. I
Gauri kadam
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
VATSAL PATEL
 
Sub grade
Sub gradeSub grade
Sub grade
gjgunit
 
Dense bituminous macadam
Dense bituminous macadamDense bituminous macadam
Dense bituminous macadam
Himanshu Pipaliya
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 
Subgrade Stabilization: Materials & Methods
Subgrade Stabilization: Materials & MethodsSubgrade Stabilization: Materials & Methods
Subgrade Stabilization: Materials & Methods
Jill Reeves
 
Project presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash GargProject presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash Garg
harshit315
 
rigid and flexiable pavement design ppt
rigid and flexiable pavement design pptrigid and flexiable pavement design ppt
rigid and flexiable pavement design ppt
rakeshchoudhary129
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavement
Rafi Khan
 
Unit 4
Unit 4Unit 4
BITUMINOUS PAVING MIXES PPT
BITUMINOUS PAVING MIXES PPTBITUMINOUS PAVING MIXES PPT
BITUMINOUS PAVING MIXES PPT
Nischay N Gowda
 
6. Pavement Engineering.pdf
6. Pavement Engineering.pdf6. Pavement Engineering.pdf
6. Pavement Engineering.pdf
Er. Bam Bhandari
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
VATSAL PATEL
 
Dense Bituminous Macadam Road
Dense Bituminous Macadam RoadDense Bituminous Macadam Road
Dense Bituminous Macadam Road
SaratMishra4
 
Pdce
PdcePdce
Embankment
EmbankmentEmbankment
Embankment
civilguna
 

What's hot (20)

Rigid Pavement Design Part II
Rigid Pavement Design Part IIRigid Pavement Design Part II
Rigid Pavement Design Part II
 
BITUMINOUS ROAD PPT
BITUMINOUS ROAD PPTBITUMINOUS ROAD PPT
BITUMINOUS ROAD PPT
 
Lecture#01
Lecture#01Lecture#01
Lecture#01
 
Pavement materials and testing
Pavement materials and testingPavement materials and testing
Pavement materials and testing
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. I
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
 
Sub grade
Sub gradeSub grade
Sub grade
 
Dense bituminous macadam
Dense bituminous macadamDense bituminous macadam
Dense bituminous macadam
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
Subgrade Stabilization: Materials & Methods
Subgrade Stabilization: Materials & MethodsSubgrade Stabilization: Materials & Methods
Subgrade Stabilization: Materials & Methods
 
Project presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash GargProject presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash Garg
 
rigid and flexiable pavement design ppt
rigid and flexiable pavement design pptrigid and flexiable pavement design ppt
rigid and flexiable pavement design ppt
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavement
 
Unit 4
Unit 4Unit 4
Unit 4
 
BITUMINOUS PAVING MIXES PPT
BITUMINOUS PAVING MIXES PPTBITUMINOUS PAVING MIXES PPT
BITUMINOUS PAVING MIXES PPT
 
6. Pavement Engineering.pdf
6. Pavement Engineering.pdf6. Pavement Engineering.pdf
6. Pavement Engineering.pdf
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
 
Dense Bituminous Macadam Road
Dense Bituminous Macadam RoadDense Bituminous Macadam Road
Dense Bituminous Macadam Road
 
Pdce
PdcePdce
Pdce
 
Embankment
EmbankmentEmbankment
Embankment
 

Viewers also liked

Lect 6 pavement design
Lect 6 pavement designLect 6 pavement design
Lect 6 pavement designM Firdaus
 
Modern Trends In Pavement Design
Modern Trends In Pavement DesignModern Trends In Pavement Design
Modern Trends In Pavement Design
Latif Hyder Wadho
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
Pawan Kumar
 
Design Of Flexible Pavements
Design Of Flexible PavementsDesign Of Flexible Pavements
Design Of Flexible Pavements
whutton1
 
Flexible Pavement Design
Flexible Pavement DesignFlexible Pavement Design
Flexible Pavement Design
Latif Hyder Wadho
 
Pavement design
Pavement designPavement design
Pavement design
husna004
 
Pavement design
Pavement designPavement design
Pavement design
Garvit Goyal
 
Introduction to Pavement Design Concepts
Introduction to Pavement Design ConceptsIntroduction to Pavement Design Concepts
Introduction to Pavement Design Concepts
Latif Hyder Wadho
 
Highway engineering at high altitudes
Highway engineering at high altitudesHighway engineering at high altitudes
Highway engineering at high altitudes
Prashant Shekhar
 
Lec 09 Pavement Design (Transportation Engineering)
Lec 09 Pavement Design (Transportation Engineering) Lec 09 Pavement Design (Transportation Engineering)
Lec 09 Pavement Design (Transportation Engineering)
Hossam Shafiq I
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
pjainrahul
 
Design and construction of highway (flexible pavement
Design and construction of highway (flexible pavementDesign and construction of highway (flexible pavement
Design and construction of highway (flexible pavement
suraj vishwakarma
 
Rigid pavement distress
Rigid pavement distress Rigid pavement distress
Rigid pavement distress
Ankit Sarkar
 
28 pavement design
28 pavement design28 pavement design
28 pavement design
AHMED NADIM JILANI
 
Pavement ppt
Pavement pptPavement ppt
Pavement ppt
Harsha Singh
 
Construction of flexible pavement in brief.
Construction of flexible pavement in brief.Construction of flexible pavement in brief.
Construction of flexible pavement in brief.
AJINKYA THAKRE
 
Pavement thickness design
Pavement thickness designPavement thickness design
Pavement thickness design
Sohail Khan
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
UTU Dehradun
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
GLA University
 
Soil mechanics in_pavement_engineering
Soil mechanics in_pavement_engineeringSoil mechanics in_pavement_engineering
Soil mechanics in_pavement_engineeringAlexander Gómez
 

Viewers also liked (20)

Lect 6 pavement design
Lect 6 pavement designLect 6 pavement design
Lect 6 pavement design
 
Modern Trends In Pavement Design
Modern Trends In Pavement DesignModern Trends In Pavement Design
Modern Trends In Pavement Design
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
 
Design Of Flexible Pavements
Design Of Flexible PavementsDesign Of Flexible Pavements
Design Of Flexible Pavements
 
Flexible Pavement Design
Flexible Pavement DesignFlexible Pavement Design
Flexible Pavement Design
 
Pavement design
Pavement designPavement design
Pavement design
 
Pavement design
Pavement designPavement design
Pavement design
 
Introduction to Pavement Design Concepts
Introduction to Pavement Design ConceptsIntroduction to Pavement Design Concepts
Introduction to Pavement Design Concepts
 
Highway engineering at high altitudes
Highway engineering at high altitudesHighway engineering at high altitudes
Highway engineering at high altitudes
 
Lec 09 Pavement Design (Transportation Engineering)
Lec 09 Pavement Design (Transportation Engineering) Lec 09 Pavement Design (Transportation Engineering)
Lec 09 Pavement Design (Transportation Engineering)
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Design and construction of highway (flexible pavement
Design and construction of highway (flexible pavementDesign and construction of highway (flexible pavement
Design and construction of highway (flexible pavement
 
Rigid pavement distress
Rigid pavement distress Rigid pavement distress
Rigid pavement distress
 
28 pavement design
28 pavement design28 pavement design
28 pavement design
 
Pavement ppt
Pavement pptPavement ppt
Pavement ppt
 
Construction of flexible pavement in brief.
Construction of flexible pavement in brief.Construction of flexible pavement in brief.
Construction of flexible pavement in brief.
 
Pavement thickness design
Pavement thickness designPavement thickness design
Pavement thickness design
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
Soil mechanics in_pavement_engineering
Soil mechanics in_pavement_engineeringSoil mechanics in_pavement_engineering
Soil mechanics in_pavement_engineering
 

Similar to PAVEMENT DESIGN (Group 9)

Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
sfQyoom
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
JaySinghchib1
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
pradip dangar
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
chiranjeevulu chinthala
 
Ppt rcc road design
Ppt rcc road designPpt rcc road design
Ppt rcc road design
Anjani Shukla
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
pradip dangar
 
highway materials and desihn.pptx
highway materials and desihn.pptxhighway materials and desihn.pptx
highway materials and desihn.pptx
SekharJ4
 
Pavements and paths
Pavements and pathsPavements and paths
Pavements and paths
Amr Samir Shaban
 
Pavement
PavementPavement
Pavement
kamariya keyur
 
Types of Pavements.pptx
Types of Pavements.pptxTypes of Pavements.pptx
Types of Pavements.pptx
ssuser33b5501
 
Pavement
PavementPavement
Highway Pavement
Highway PavementHighway Pavement
Highway Pavement
Moses Payma Dukuly
 
Formwork
FormworkFormwork
Formwork
Lavanya Singh
 
Conen 442 module3 S2021 Pavement Design and Construction
Conen  442 module3  S2021 Pavement Design and Construction Conen  442 module3  S2021 Pavement Design and Construction
Conen 442 module3 S2021 Pavement Design and Construction
Wael ElDessouki
 
Minor Project on design and analysis of flexible pavement with cement treated...
Minor Project on design and analysis of flexible pavement with cement treated...Minor Project on design and analysis of flexible pavement with cement treated...
Minor Project on design and analysis of flexible pavement with cement treated...
PrashannaKumar2
 
Design of concrete Structure 2
Design of concrete Structure 2Design of concrete Structure 2
Design of concrete Structure 2
SHARIQUE AHMAD
 
CONCRETE GROUND FLOORS.ppt
CONCRETE GROUND FLOORS.pptCONCRETE GROUND FLOORS.ppt
CONCRETE GROUND FLOORS.ppt
Ashraf Zayed Abu Mahfouz
 
Pavement construction methods
Pavement construction methodsPavement construction methods
Pavement construction methods
shrikanth16
 
Flat_slab.pptx
Flat_slab.pptxFlat_slab.pptx
Flat_slab.pptx
ssuserdd13b81
 
Ishfaq Rashid.pptx
Ishfaq Rashid.pptxIshfaq Rashid.pptx
Ishfaq Rashid.pptx
lovish34
 

Similar to PAVEMENT DESIGN (Group 9) (20)

Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
Ppt rcc road design
Ppt rcc road designPpt rcc road design
Ppt rcc road design
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
highway materials and desihn.pptx
highway materials and desihn.pptxhighway materials and desihn.pptx
highway materials and desihn.pptx
 
Pavements and paths
Pavements and pathsPavements and paths
Pavements and paths
 
Pavement
PavementPavement
Pavement
 
Types of Pavements.pptx
Types of Pavements.pptxTypes of Pavements.pptx
Types of Pavements.pptx
 
Pavement
PavementPavement
Pavement
 
Highway Pavement
Highway PavementHighway Pavement
Highway Pavement
 
Formwork
FormworkFormwork
Formwork
 
Conen 442 module3 S2021 Pavement Design and Construction
Conen  442 module3  S2021 Pavement Design and Construction Conen  442 module3  S2021 Pavement Design and Construction
Conen 442 module3 S2021 Pavement Design and Construction
 
Minor Project on design and analysis of flexible pavement with cement treated...
Minor Project on design and analysis of flexible pavement with cement treated...Minor Project on design and analysis of flexible pavement with cement treated...
Minor Project on design and analysis of flexible pavement with cement treated...
 
Design of concrete Structure 2
Design of concrete Structure 2Design of concrete Structure 2
Design of concrete Structure 2
 
CONCRETE GROUND FLOORS.ppt
CONCRETE GROUND FLOORS.pptCONCRETE GROUND FLOORS.ppt
CONCRETE GROUND FLOORS.ppt
 
Pavement construction methods
Pavement construction methodsPavement construction methods
Pavement construction methods
 
Flat_slab.pptx
Flat_slab.pptxFlat_slab.pptx
Flat_slab.pptx
 
Ishfaq Rashid.pptx
Ishfaq Rashid.pptxIshfaq Rashid.pptx
Ishfaq Rashid.pptx
 

Recently uploaded

CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 

Recently uploaded (20)

CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 

PAVEMENT DESIGN (Group 9)

  • 1.
  • 3. A. Concrete slabs with a determinedthickness Concrete is a construction material that is made of portland cement ,aggregate s and water mixed in predetermined proportions. Concrete solidifies and hardens after mixing and placement due to a chemical process known asb hydration.
  • 4. B. Joints (both transverse and longitudinal) Concrete slabs will crack randomly from natural actions such as shrinkage or curling. Therefore, joints are vital elements introduced into CP to control cracking and horizontal movements of the slabs. Transverse Joints Perpendicular to Lane Lines and Longitudinal Joints Longitudinal Joint at Lane Line
  • 5. Tie bars are typically used at longitudinal joints and transverse construction joint in a nondoweled shoulder addition/reconstruction to hold tight the faces of abutting concrete in contact. C. Tie bars
  • 6. Load transfer is the ability of a joint to transfer a portion of an applied load (the truck wheel) from one side of the joint to the other. Dowel Bars in a Transverse Joint Slab Movements in Non-doweled SlabSlab Movements in Doweled Slab
  • 7. E. Base layer ~It can provide a stable platform for the concrete paving, provides for additional load distribution, and contributes to drainage (if permeable base is used) and frost resistance. F.Subbase layer (if required), ~the subbase layer is a planned thickness of specified material that is placed on the subgrade or under the basement material. G.Subgrade ~greater subgrade structural capacity can result in more economical pavement structures.
  • 8.
  • 10. • subgrade, base and subbase preparation conforming to the thickness and cross section requirements, • proper placement of tie bars and dowel bars to be embedded, carefully examining for bending which could injure the material, oil, dirt, rust and other coatings that would prevent or reduce bonding to concrete. • proper concrete placement including consolidation, finishing, texturing, curing and jointing essential for a strong durable pavement
  • 11. Sub-grade, Sub-base and Base Preparation Sub-grade Preparation ~ minimum depth of 0.5 feet below the grading plane for the width between the outer edges of shoulders, or ~ minimum depth of 2.5 feet below the finished grade for the width of the traveled way and auxiliary lanes including 3 feet on both sides as specified in Section 19-5.03 of the Standard Specifications
  • 12. Sub-base Layer Preparation •The Department uses Aggregate Sub-base (AS) for use in JPCP construction to provide a foundation or working platform for the base when the sub-grade R- value is less than 40. •The maximum thickness of any one layer should not exceed 0.50 foot after watering and compaction. Where the required thickness is more than 0.50 foot, spreading, watering and compaction should be conducted in 2 or more lifts of approximately equal thickness.
  • 13. Base Layer Preparation The Department uses Hot Mix Asphalt (HMA) Type A, Lean Concrete Base (LCB), Asphalt Treated Permeable Base (ATPB), and Aggregate Base (AB) to provide a construction platform underneath the CP. •Hot Mix Asphalt Type A (HMA-A) HMA-Type A consists of one or more layers placed on a prepared sub-base or sub-grade in conformity with the alignment and grades shown on the project plans. HMA-A is placed at a 20 temperature of no less than 310 °F and only when the sub-base or sub-grade surface is dry and in satisfactory condition.
  • 14. •Lean Concrete Base (LCB) ~ LCB is placed, constructed and finished in no less than 12-foot widths separated by contact joints. Widths that are greater than 26 feet are constructed with longitudinal weakened plane joints at no more than 3 feet from the centerline of the width being constructed. •Aggregate Base (AB) ~ where the required thickness is 0.50-foot or less, is spread and compacted in one layer. If the required thickness is more than 0.50-foot, spread and compact AB in two or more lifts in approximately equal thickness, and each lift shall not exceed 0.50-foot.
  • 15. Steel Placement Tie Bar Placement Tie bars are not to be used at a joint where concrete and asphalt concrete pavements abut. Tie bars are placed: (a) along longitudinal weakened plane in multilane paving, and (b) at longitudinal and transverse contact joint in a nondoweled lane/shoulder addition or reconstruction. These tie bars are placed at mid depth of the concrete slab.
  • 16. • Dowel Bar Placement Dowel bars are placed as shown on the plans by using either dowel bar baskets, drilling and bonding, or mechanical insertion. • Bar Reinforcement Placement Although CP does not typically have bar reinforcement, bar reinforcement can be found in a few situations such as pavement transitions ,gore areas, and around drainage inlets.
  • 17. • Concrete Placement ~ Concrete is transported to the paving site by dump trucks or ready-mix trucks with the goal to deliver a uniform, well-mixed and workable concrete from batch to batch. • Consolidation ~ it is the process that compacts fresh concrete to mold it within the forms and around steel reinforcements and to remove undesirable voids. • Finishing ~it involves any equipment or procedures used to impart desirable surface characteristics. • Curing ~ it is the maintenance of satisfactory moisture and temperature in the concrete as it sets and hardens such that the desired properties can develop.
  • 18.
  • 19. Flexible pavement design This section describes the design for both asphalt concrete pavements and surface treatments which carry significant levels of traffic over the performance period
  • 20. Modifications Included in Flexible Pavement design procedures • The soil support number is replaced by the resilient modulus to provide a rational testing procedure that may be used by an agency to define the material properties. • The layer coefficients for the various materials are defined in terms of resilient modulus as well as standard methods (CBR and R-value). • The environmental factors of moisture and temperature objectively included in the Guide so that the environmental consdiderations could be ratioanally accounted for in the design procedure. • Reliability is introduced to permit the designer to use the concept of risk analysis for various classes of roadways. • Stage construction design procedures are incorporated.
  • 21. Design Of Flexible Pavement • Design Of Flexible Pavement By Group Index Method Group Index is function of percentage material passing 200 mesh sieve (0.074mm), liquid limit and plasticity index of soil and is given by equation: GI=0.2a+0.005ac+0.01bd Here, a=that portion of material passing 0.074mm sieve, greater than 35 And not exceeding 75 % b=that portion of material passing 0.074mm sieve, greater than 15 And not exceeding 35% c = that value of liquid limit in excess of 40 and less than 60 d = that value of plasticity index exceeding 10 and not more than 30
  • 22. California Resistance Value Method pavements thickness varies directly with R value and logarithm of load repetitions. It varies inversely with fifth root of Computer value. T=K (TI) (90-R)/C1/5 Here : T=total thickness of pavement, cm K=numerical constant=0.166 TI=traffic index R=stabilometer resistance value C =Cohesiometer value
  • 23. Triaxial Method Here T=Pavement thickness, cm Es=modulus of elasticity of sub grade from triaxial test result, Kg/cm2 A=radius of contact area, cm ∆=design deflection (0.25 cm)
  • 25. Rigid pavement design As the name implies, rigid pavements are rigid , they do not extend much under loading like flexible pavements. They are constructed using cement concrete. In this case, the load carrying capacity is mainly due to the rigidity and high modulus of elasticity of the slab (slab action).
  • 26. Modifications Included in Rigid Pavement design procedures: • Reliability concepts identical to those used for the flexible pavements are introduced. • The environmental aspects of design are introduced in the same format as for flexible pavements. • The design procedure is modified to include such factors as tied shoulders, subbase erosion, and lean subbase designs.
  • 27. Rigid Pavement Response • Curling stress – Differences in temperature between the top and bottom surfaces of a PCC slab will cause the slab to curl. Since slab weight and contact with the base restrict its movement, stresses are created.
  • 28. where: σt=slab interior warping stress E=modulus of elasticity of PCC e=thermal coefficient of PCC (» 0.000005/°F) Δ T=temperature differential between the top and bottom of the slab µ=Poisson’s ratio for PCC (» 0.15) β=radius of wheel load distribution for corner loading where: l=radius of relative stiffness E=modulus of elasticity of PCC h=slab thickness k=modulus of subgrade reaction m=Poisson’s ratio for PCC (» 0.15)
  • 29. Load stress Loads on a PCC slab will create both compressive and tensile stresses within the slab and any adjacent one (as long as load transfer efficiency is > 0). a. Interior loading. Occurs when a load is applied on the interior of a slab s.urface which is “remote” from all edges. b. Edge loading. Occurs when a load is applied on a slab edge “remote” from a slab corner.
  • 30. c. Corner loading. Occurs when the center of a load is located on the bisector of the corner angle.
  • 31. Shrinkage and expansion • In addition to curling, environmental temperatures will cause PCC slabs to expand (when hot) and contract (when cool), which causes joint movement. where: z=joint opening = change in slab length (inches) C=base/slab frictional restraint factor = 0.65 for stabilized bases = 0.80 for granular bases L=slab length (inches)
  • 32.
  • 33.
  • 34. It is observed that flexible pavements are more economical for lesser volume of traffic.The life of flexible pavement is near about 15 years whose initial cost is low needs a periodic maintenance after a certain period and maintenance costs very high. The life of rigid pavement is much more than the flexible pavement of about 40 years approx 2.5 times life of flexible pavement whose initial cost is much more then the flexible pavement but maintenance cost is very less.
  • 36. “Start by doing what’s necessary; then do what’s possible; and suddenly your are doing the impossible.” ~Francis of Assisi~ Prepared by: FONTE, EDDIE RED ZULUETA, ERWIN JOHN

Editor's Notes

  1. 1