Navi Mumbai Metro Project
Project Details
Belapur-Kharghar Rapid Transit system
CIDCO
Introduction
The government of maharashtra (gom) has entrusted City and Industrial Development Corporation of
maharashtra ltd. (CIDCO) to plan and create Environment-friendly, model urban settlement with full-fledged
physical and Social infrastructure to meet residential, commercial and industrial needs of The population at
present and in the years to come. To boost the earlier Development, a rail-based transport was suggested in the
80s and mass Rapid transportation master plan was prepared with six suburban corridor Routes as under:
Sr.No Corridor Length status
1. Mankhurd-Belapur-Panvel 29kms Completed
2. Thane-Tubhe-Nerul/Vashi 20kms Completed
3. Nerul-Seawoods-Uran 27kms In Progress
4. Panvel-Ulwe-Uran 32kms Under planning
5. Ring Railway around CBD 15kms Under Planning
Out of these, first two are completed and the third one is in progress. Meanwhile, it was found that land use in the Navi
Mumbai area has changed to a large extent due to the proposed SEZ and Navi Mumbai International Airport. Hence, CIDCO
decided to review the master plan for transportation connectivity.
Consultants
 The Louis Berger Group Inc. (LBG) has been appointed by CIDCO as "General Consultant" for Navi Mumbai Metro Line project. LBG would provide
General Consultancy Services for Implementation of Navi Mumbai Metro Line 1 from Belapur to Kharghar.
 Team:-
 Mr John R Gretton
Project Director, GC (LBG)
Navi Mumbai Metro Project.
 Mr Surjit S. Madan
Head - Rail Systems, GC (LBG)
Navi Mumbai Metro Project
 Mr Umakanta Mahapatra
Sr. Project Manager/Head - Metro Civil Infra, GC (LBG)
Navi Mumbai Metro Project.
 Project General Consultant Office Address
The Louis Berger Group Inc.
Institution of Engineers Building,
Plot No. 106, Sector 15, Belapur (E),
Navi Mumbai - 400614, India
Website: w w w .louisberger.com
Email: info.nmm@lbconsult.net
Taking the first step
 After studying the various modes of transports such as Monorail, Bus, etc., the consultant
proposed connectivity by Metro Rail System due to various merits on account of it being
energy efficient, pollution free and occupying less land space as compared to other modes
of transport. The passenger carrying capacity of medium Metro Rail System can be up to
35000 PHPDT (Peak Hour Per Direction Traffic) whereas Monorail System is suitable up to
20000 PHPDT. Hence, Metro Rail System was preferred for Navi Mumbai.
 The consultants proposed six metro corridors in Navi Mumbai, out of these Belapur-kharghar
and Kharghar-kalamboli-khandeshwar which were considered as metro corridors have now
been decided to be suburban corridors. Since Navi Mumbai International Airport is
approved, need was felt to review the Master Plan of Navi Mumbai’s connectivity.
Map of NMMC’s Metro Rail project
Phase one
 CBD Belapur-Kharghar
 International Airport Corridor, The study recommended that rail-based corridor of Belapur-Kharghar-
Proposed Airport is the only potentially developable corridor at present. It was further recommended by
DMRC to take up Metro Rail Project from Belapur to kharghar in the 1st stage, taloja to Khandeshwar as
2nd stage and interlink between kharghar and taloja in 3rd stage due to the following Reasons :-
1) The area is developing and Metro will boost the development and will fetch additional premium on
land price (which may supplement a part of the construction cost).
2) This is alternative to Mansarovar - Taloja suburban line. The suburban alignment is away from the human
settlement and the proposed Metro is passing through the settlement to serve the occupants. Proposed
ridership is adequate to make the project viable for operation.
 Maharashtra Government has authorised CIDCO as MRT system administration Implementing Agency
under Indian Tramway Act 1886 for implementation of Belapur-kharghar-Kalamboli-Khandeshwar Metro
Rail Project on September 30, 2010.
Project Cost
 Project cost details for CBD Belapur-kharghar-Khandeshwar-Navi Mumbai International Airport Corridor
 CBD Belapur-kharghar-Kalamboli-Khandeshwar Corridor is recommended by DMRC to be executed in three
stages as given below:
 Stage - I: Line No. 1 from Belapur to Kharghar (11.10 km). The cost of the project will be approximately 1,985
crores.
 Stage - II: Line No. 2 from Khandeshwar to Taloja MIDC (8.35 km). The cost of the project will be approximately
1,509 crores.
 Stage - III: Line No. 3 from Interconnection of Line - I & II (2.00 km). The cost of the project will be approximately
574 crores. This cost is tentative and subject to change as per site feasibility.
 The above work of Corridor 1 is expected to be completed in 5 years, along with the completion of 1st Phase of
Navi Mumbai International Airport (NMIA) and is proposed to be extended up to NMIA.
Thank you
Made By:-
Parth S. Patil
Fr. Y. B.Arch.
Project Management
021

More Related Content

What's hot

Ahmedabad metro.
Ahmedabad metro.Ahmedabad metro.
Ahmedabad metro.
Axay Sharma
 
Draft Development Plan 2021 (Review) AUDA - D Thara, IAS
Draft Development Plan 2021 (Review) AUDA - D Thara, IASDraft Development Plan 2021 (Review) AUDA - D Thara, IAS
Draft Development Plan 2021 (Review) AUDA - D Thara, IAS
WRI Ross Center for Sustainable Cities
 
OVERVIEW OF BANGLORE CMP
OVERVIEW OF BANGLORE CMPOVERVIEW OF BANGLORE CMP
OVERVIEW OF BANGLORE CMP
Akash Sthavaramath
 
Analysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land UseAnalysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land UseAnirban Mahajan
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase I
Karan Shah
 
Mumbai metro - Planning
Mumbai metro - PlanningMumbai metro - Planning
Mumbai metro - Planning
RADHIKASARDA8
 
Transit hub
Transit hub Transit hub
Transit hub
Athira Suresh
 
Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach
Nishanth Patil
 
Revised Developement Plan, Ahmedabad 2013 - 2021
Revised Developement Plan, Ahmedabad 2013 - 2021Revised Developement Plan, Ahmedabad 2013 - 2021
Revised Developement Plan, Ahmedabad 2013 - 2021Manaan Choksi
 
CHENNAI CITY -URBAN SPRAWL
CHENNAI CITY -URBAN  SPRAWL CHENNAI CITY -URBAN  SPRAWL
CHENNAI CITY -URBAN SPRAWL
Manju Arjunan
 
Ahmedabad Metro Project
Ahmedabad Metro ProjectAhmedabad Metro Project
Ahmedabad Metro Project
ASHISH SINGH
 
Multi model integration of bus and train services mira bhayandar
Multi model integration of bus and train services mira bhayandarMulti model integration of bus and train services mira bhayandar
Multi model integration of bus and train services mira bhayandar
unclecruise
 
Nepal east west rail project-feasibility study draft report presentation
Nepal east west rail project-feasibility study draft report presentationNepal east west rail project-feasibility study draft report presentation
Nepal east west rail project-feasibility study draft report presentationBhim Upadhyaya
 
URBAN GOVERNANCE OF CHENNAI
URBAN GOVERNANCE OF CHENNAIURBAN GOVERNANCE OF CHENNAI
URBAN GOVERNANCE OF CHENNAI
michellesahay
 
planning of central railway station
planning of central railway stationplanning of central railway station
planning of central railway station
Upasana Panchal
 
Overview of Municipal Impact fees
Overview of Municipal Impact feesOverview of Municipal Impact fees
Overview of Municipal Impact fees
Jim Damicis
 
Eia mumbai metro
Eia mumbai metroEia mumbai metro
Eia mumbai metro
1392pramod
 
TRANSPORTATION EXISTING SCENARIO AND PROPOSALS FOR UJJAIN CITY
TRANSPORTATION EXISTING SCENARIO AND PROPOSALS FOR UJJAIN CITYTRANSPORTATION EXISTING SCENARIO AND PROPOSALS FOR UJJAIN CITY
TRANSPORTATION EXISTING SCENARIO AND PROPOSALS FOR UJJAIN CITY
shrikrishna kesharwani
 
Urban Management & Governance Structures in India
Urban Management & Governance Structures in IndiaUrban Management & Governance Structures in India
Urban Management & Governance Structures in India
Ravikant Joshi
 
World Class Bus Rapid Transit System (BRTS) for Bangalore
World Class Bus Rapid Transit System (BRTS) for BangaloreWorld Class Bus Rapid Transit System (BRTS) for Bangalore
World Class Bus Rapid Transit System (BRTS) for Bangalore
Kiran Shaw
 

What's hot (20)

Ahmedabad metro.
Ahmedabad metro.Ahmedabad metro.
Ahmedabad metro.
 
Draft Development Plan 2021 (Review) AUDA - D Thara, IAS
Draft Development Plan 2021 (Review) AUDA - D Thara, IASDraft Development Plan 2021 (Review) AUDA - D Thara, IAS
Draft Development Plan 2021 (Review) AUDA - D Thara, IAS
 
OVERVIEW OF BANGLORE CMP
OVERVIEW OF BANGLORE CMPOVERVIEW OF BANGLORE CMP
OVERVIEW OF BANGLORE CMP
 
Analysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land UseAnalysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land Use
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase I
 
Mumbai metro - Planning
Mumbai metro - PlanningMumbai metro - Planning
Mumbai metro - Planning
 
Transit hub
Transit hub Transit hub
Transit hub
 
Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach
 
Revised Developement Plan, Ahmedabad 2013 - 2021
Revised Developement Plan, Ahmedabad 2013 - 2021Revised Developement Plan, Ahmedabad 2013 - 2021
Revised Developement Plan, Ahmedabad 2013 - 2021
 
CHENNAI CITY -URBAN SPRAWL
CHENNAI CITY -URBAN  SPRAWL CHENNAI CITY -URBAN  SPRAWL
CHENNAI CITY -URBAN SPRAWL
 
Ahmedabad Metro Project
Ahmedabad Metro ProjectAhmedabad Metro Project
Ahmedabad Metro Project
 
Multi model integration of bus and train services mira bhayandar
Multi model integration of bus and train services mira bhayandarMulti model integration of bus and train services mira bhayandar
Multi model integration of bus and train services mira bhayandar
 
Nepal east west rail project-feasibility study draft report presentation
Nepal east west rail project-feasibility study draft report presentationNepal east west rail project-feasibility study draft report presentation
Nepal east west rail project-feasibility study draft report presentation
 
URBAN GOVERNANCE OF CHENNAI
URBAN GOVERNANCE OF CHENNAIURBAN GOVERNANCE OF CHENNAI
URBAN GOVERNANCE OF CHENNAI
 
planning of central railway station
planning of central railway stationplanning of central railway station
planning of central railway station
 
Overview of Municipal Impact fees
Overview of Municipal Impact feesOverview of Municipal Impact fees
Overview of Municipal Impact fees
 
Eia mumbai metro
Eia mumbai metroEia mumbai metro
Eia mumbai metro
 
TRANSPORTATION EXISTING SCENARIO AND PROPOSALS FOR UJJAIN CITY
TRANSPORTATION EXISTING SCENARIO AND PROPOSALS FOR UJJAIN CITYTRANSPORTATION EXISTING SCENARIO AND PROPOSALS FOR UJJAIN CITY
TRANSPORTATION EXISTING SCENARIO AND PROPOSALS FOR UJJAIN CITY
 
Urban Management & Governance Structures in India
Urban Management & Governance Structures in IndiaUrban Management & Governance Structures in India
Urban Management & Governance Structures in India
 
World Class Bus Rapid Transit System (BRTS) for Bangalore
World Class Bus Rapid Transit System (BRTS) for BangaloreWorld Class Bus Rapid Transit System (BRTS) for Bangalore
World Class Bus Rapid Transit System (BRTS) for Bangalore
 

Viewers also liked

Cidco- NAVI MUMBAI
Cidco- NAVI MUMBAICidco- NAVI MUMBAI
Cidco- NAVI MUMBAI
Dhawal Kataria
 
Top investments destination in mumbai mmr jan-jun15
Top investments destination in mumbai mmr  jan-jun15Top investments destination in mumbai mmr  jan-jun15
Top investments destination in mumbai mmr jan-jun15
Green Realtech Projects Pvt. Ltd
 
Presentation e socialwork
Presentation e socialworkPresentation e socialwork
Presentation e socialworkDavy Nijs
 
Cidco+new
Cidco+newCidco+new
Cidco+new
Amit
 
Mthl( Mumbai Transe Harbour link)
Mthl( Mumbai Transe Harbour link)Mthl( Mumbai Transe Harbour link)
Mthl( Mumbai Transe Harbour link)Jayesh Kambli
 
Golden Gate Bridge Suicide Project 2010 07
Golden Gate Bridge Suicide Project 2010 07Golden Gate Bridge Suicide Project 2010 07
Golden Gate Bridge Suicide Project 2010 07
David Covington
 
10 - Explore Budapest by Metro Line 2 (March 6)
10 - Explore Budapest by Metro Line 2 (March 6)10 - Explore Budapest by Metro Line 2 (March 6)
10 - Explore Budapest by Metro Line 2 (March 6)Lee Reaney
 
Prop Tiger Navi Mumbai Residential Analysis Jan 2014
Prop Tiger Navi Mumbai Residential Analysis Jan 2014Prop Tiger Navi Mumbai Residential Analysis Jan 2014
Prop Tiger Navi Mumbai Residential Analysis Jan 2014
PROPTIGER
 
Go Underground Mumbai Metro
Go Underground Mumbai MetroGo Underground Mumbai Metro
Go Underground Mumbai Metro
Hansel D'Souza
 
Truth behindmetro3yardinaarey
Truth behindmetro3yardinaareyTruth behindmetro3yardinaarey
Truth behindmetro3yardinaarey
Samiir Halady
 
Law presentation
Law presentationLaw presentation
Law presentation
Rachit Shiv
 
Reliance Mumbai Metro Project Management
Reliance Mumbai Metro Project ManagementReliance Mumbai Metro Project Management
Reliance Mumbai Metro Project Management
Swapnil Borkar
 
Hamad International Airport
Hamad International AirportHamad International Airport
Hamad International Airport
Kingspan Insulated Panels
 
indian infrastructure and pune metro project (feasibility analysis)
indian infrastructure and pune metro project (feasibility analysis)indian infrastructure and pune metro project (feasibility analysis)
indian infrastructure and pune metro project (feasibility analysis)
Gurjit Kaur Kaler
 
Analysis of Mumbai Metro III Yard Venue Options - Aarey Conservation Group
Analysis of Mumbai Metro III Yard Venue Options - Aarey Conservation GroupAnalysis of Mumbai Metro III Yard Venue Options - Aarey Conservation Group
Analysis of Mumbai Metro III Yard Venue Options - Aarey Conservation Group
Samiir Halady
 
Urban planning CIDCO
Urban planning CIDCOUrban planning CIDCO
Urban planning CIDCO
Pramod Vishwakarma
 
Combined & Eccentric Footing
Combined & Eccentric FootingCombined & Eccentric Footing
Combined & Eccentric Footing
Parth Patil
 
Tunnel ventilation ppt tunnel asia 2013
Tunnel ventilation ppt tunnel asia 2013Tunnel ventilation ppt tunnel asia 2013
Tunnel ventilation ppt tunnel asia 2013
Hitesh Khanna
 

Viewers also liked (20)

Cidco- NAVI MUMBAI
Cidco- NAVI MUMBAICidco- NAVI MUMBAI
Cidco- NAVI MUMBAI
 
Top investments destination in mumbai mmr jan-jun15
Top investments destination in mumbai mmr  jan-jun15Top investments destination in mumbai mmr  jan-jun15
Top investments destination in mumbai mmr jan-jun15
 
eOffice new
eOffice neweOffice new
eOffice new
 
Presentation e socialwork
Presentation e socialworkPresentation e socialwork
Presentation e socialwork
 
Cidco+new
Cidco+newCidco+new
Cidco+new
 
Mthl( Mumbai Transe Harbour link)
Mthl( Mumbai Transe Harbour link)Mthl( Mumbai Transe Harbour link)
Mthl( Mumbai Transe Harbour link)
 
Golden Gate Bridge Suicide Project 2010 07
Golden Gate Bridge Suicide Project 2010 07Golden Gate Bridge Suicide Project 2010 07
Golden Gate Bridge Suicide Project 2010 07
 
10 - Explore Budapest by Metro Line 2 (March 6)
10 - Explore Budapest by Metro Line 2 (March 6)10 - Explore Budapest by Metro Line 2 (March 6)
10 - Explore Budapest by Metro Line 2 (March 6)
 
Prop Tiger Navi Mumbai Residential Analysis Jan 2014
Prop Tiger Navi Mumbai Residential Analysis Jan 2014Prop Tiger Navi Mumbai Residential Analysis Jan 2014
Prop Tiger Navi Mumbai Residential Analysis Jan 2014
 
Go Underground Mumbai Metro
Go Underground Mumbai MetroGo Underground Mumbai Metro
Go Underground Mumbai Metro
 
Truth behindmetro3yardinaarey
Truth behindmetro3yardinaareyTruth behindmetro3yardinaarey
Truth behindmetro3yardinaarey
 
Cost effective healthcare in medical imaging
Cost effective healthcare in medical imagingCost effective healthcare in medical imaging
Cost effective healthcare in medical imaging
 
Law presentation
Law presentationLaw presentation
Law presentation
 
Reliance Mumbai Metro Project Management
Reliance Mumbai Metro Project ManagementReliance Mumbai Metro Project Management
Reliance Mumbai Metro Project Management
 
Hamad International Airport
Hamad International AirportHamad International Airport
Hamad International Airport
 
indian infrastructure and pune metro project (feasibility analysis)
indian infrastructure and pune metro project (feasibility analysis)indian infrastructure and pune metro project (feasibility analysis)
indian infrastructure and pune metro project (feasibility analysis)
 
Analysis of Mumbai Metro III Yard Venue Options - Aarey Conservation Group
Analysis of Mumbai Metro III Yard Venue Options - Aarey Conservation GroupAnalysis of Mumbai Metro III Yard Venue Options - Aarey Conservation Group
Analysis of Mumbai Metro III Yard Venue Options - Aarey Conservation Group
 
Urban planning CIDCO
Urban planning CIDCOUrban planning CIDCO
Urban planning CIDCO
 
Combined & Eccentric Footing
Combined & Eccentric FootingCombined & Eccentric Footing
Combined & Eccentric Footing
 
Tunnel ventilation ppt tunnel asia 2013
Tunnel ventilation ppt tunnel asia 2013Tunnel ventilation ppt tunnel asia 2013
Tunnel ventilation ppt tunnel asia 2013
 

Similar to NMMC Metro Rail Project

Latest News for the Navi Mumbai Metro in 2023.pdf
Latest News for the Navi Mumbai Metro in 2023.pdfLatest News for the Navi Mumbai Metro in 2023.pdf
Latest News for the Navi Mumbai Metro in 2023.pdf
yamunaNMH
 
Market research on the Bandra Skywalk
Market research on the Bandra SkywalkMarket research on the Bandra Skywalk
Market research on the Bandra SkywalkHeemanish Midde
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in indiaSourav Paul
 
Introduction to metro system (1).pptx
Introduction to metro system (1).pptxIntroduction to metro system (1).pptx
Introduction to metro system (1).pptx
BalpreetSingh47890
 
Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India ppt
Nikita James
 
Navi Mumbai Metro.pdf
Navi Mumbai Metro.pdfNavi Mumbai Metro.pdf
Navi Mumbai Metro.pdf
nayanaNMH
 
Case Study on Mumbai Trans Harbor link
Case Study on Mumbai Trans Harbor linkCase Study on Mumbai Trans Harbor link
Case Study on Mumbai Trans Harbor link
AbhijeetTambade3
 
Effectiveness of skywalks in mumbai
Effectiveness of skywalks in mumbaiEffectiveness of skywalks in mumbai
Effectiveness of skywalks in mumbaiSamik Roy
 
Sewri-Navi Mumbai Sea Link.pdf
Sewri-Navi Mumbai Sea Link.pdfSewri-Navi Mumbai Sea Link.pdf
Sewri-Navi Mumbai Sea Link.pdf
yamunaNMH
 
JMRC PRESENTATION
JMRC PRESENTATIONJMRC PRESENTATION
JMRC PRESENTATION
Rohit kumar nagar
 
lucknow metro ppt
lucknow metro pptlucknow metro ppt
lucknow metro ppt
ravindra sonkar
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro rail
libin paul
 
Infrastructure and aviation - Business environment
Infrastructure and aviation - Business environmentInfrastructure and aviation - Business environment
Infrastructure and aviation - Business environmentPrabhat Taneja
 
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailTime Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
IRJET Journal
 
Mumbai Western Freeway Sealink Project
Mumbai Western Freeway Sealink ProjectMumbai Western Freeway Sealink Project
Mumbai Western Freeway Sealink ProjectOmkar Bhaskar Palande
 
Project brief updated_aug081
Project brief updated_aug081Project brief updated_aug081
Project brief updated_aug081
Anush verma
 
Metro Development and Pedestrian Concerns
Metro Development and Pedestrian ConcernsMetro Development and Pedestrian Concerns
Metro Development and Pedestrian Concerns
IRJET Journal
 
Mumbai Trans Harbour Link.pdf
Mumbai Trans Harbour Link.pdfMumbai Trans Harbour Link.pdf
Mumbai Trans Harbour Link.pdf
nayanaNMH
 
Role of metro for traffic in kolkata
Role of metro for traffic in kolkataRole of metro for traffic in kolkata
Role of metro for traffic in kolkata
Piter Biswas
 

Similar to NMMC Metro Rail Project (20)

Latest News for the Navi Mumbai Metro in 2023.pdf
Latest News for the Navi Mumbai Metro in 2023.pdfLatest News for the Navi Mumbai Metro in 2023.pdf
Latest News for the Navi Mumbai Metro in 2023.pdf
 
Market research on the Bandra Skywalk
Market research on the Bandra SkywalkMarket research on the Bandra Skywalk
Market research on the Bandra Skywalk
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in india
 
Introduction to metro system (1).pptx
Introduction to metro system (1).pptxIntroduction to metro system (1).pptx
Introduction to metro system (1).pptx
 
Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India ppt
 
Navi Mumbai Metro.pdf
Navi Mumbai Metro.pdfNavi Mumbai Metro.pdf
Navi Mumbai Metro.pdf
 
Case Study on Mumbai Trans Harbor link
Case Study on Mumbai Trans Harbor linkCase Study on Mumbai Trans Harbor link
Case Study on Mumbai Trans Harbor link
 
Effectiveness of skywalks in mumbai
Effectiveness of skywalks in mumbaiEffectiveness of skywalks in mumbai
Effectiveness of skywalks in mumbai
 
Sewri-Navi Mumbai Sea Link.pdf
Sewri-Navi Mumbai Sea Link.pdfSewri-Navi Mumbai Sea Link.pdf
Sewri-Navi Mumbai Sea Link.pdf
 
JMRC PRESENTATION
JMRC PRESENTATIONJMRC PRESENTATION
JMRC PRESENTATION
 
lucknow metro ppt
lucknow metro pptlucknow metro ppt
lucknow metro ppt
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro rail
 
Infrastructure and aviation - Business environment
Infrastructure and aviation - Business environmentInfrastructure and aviation - Business environment
Infrastructure and aviation - Business environment
 
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailTime Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
 
Study of real estate market chembur
Study of real estate market   chemburStudy of real estate market   chembur
Study of real estate market chembur
 
Mumbai Western Freeway Sealink Project
Mumbai Western Freeway Sealink ProjectMumbai Western Freeway Sealink Project
Mumbai Western Freeway Sealink Project
 
Project brief updated_aug081
Project brief updated_aug081Project brief updated_aug081
Project brief updated_aug081
 
Metro Development and Pedestrian Concerns
Metro Development and Pedestrian ConcernsMetro Development and Pedestrian Concerns
Metro Development and Pedestrian Concerns
 
Mumbai Trans Harbour Link.pdf
Mumbai Trans Harbour Link.pdfMumbai Trans Harbour Link.pdf
Mumbai Trans Harbour Link.pdf
 
Role of metro for traffic in kolkata
Role of metro for traffic in kolkataRole of metro for traffic in kolkata
Role of metro for traffic in kolkata
 

Recently uploaded

Let's Summon Demons Shirt Let's Summon Demons Shirt
Let's Summon Demons Shirt Let's Summon Demons ShirtLet's Summon Demons Shirt Let's Summon Demons Shirt
Let's Summon Demons Shirt Let's Summon Demons Shirt
TeeFusion
 
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
smpc3nvg
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
boryssutkowski
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
PlanitIsrael
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
jyz59f4j
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
ameli25062005
 
Can AI do good? at 'offtheCanvas' India HCI prelude
Can AI do good? at 'offtheCanvas' India HCI preludeCan AI do good? at 'offtheCanvas' India HCI prelude
Can AI do good? at 'offtheCanvas' India HCI prelude
Alan Dix
 
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
n0tivyq
 
Portfolio.pdf
Portfolio.pdfPortfolio.pdf
Portfolio.pdf
garcese
 
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
7sd8fier
 
projectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdfprojectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdf
farazahmadas6
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
smpc3nvg
 
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
7sd8fier
 
Exploring the Future of Smart Garages.pdf
Exploring the Future of Smart Garages.pdfExploring the Future of Smart Garages.pdf
Exploring the Future of Smart Garages.pdf
fastfixgaragedoor
 
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Mansi Shah
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
cy0krjxt
 
Mohannad Abdullah portfolio _ V2 _22-24
Mohannad Abdullah  portfolio _ V2 _22-24Mohannad Abdullah  portfolio _ V2 _22-24
Mohannad Abdullah portfolio _ V2 _22-24
M. A. Architect
 
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
9a93xvy
 
20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf
ameli25062005
 

Recently uploaded (20)

Let's Summon Demons Shirt Let's Summon Demons Shirt
Let's Summon Demons Shirt Let's Summon Demons ShirtLet's Summon Demons Shirt Let's Summon Demons Shirt
Let's Summon Demons Shirt Let's Summon Demons Shirt
 
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
 
Can AI do good? at 'offtheCanvas' India HCI prelude
Can AI do good? at 'offtheCanvas' India HCI preludeCan AI do good? at 'offtheCanvas' India HCI prelude
Can AI do good? at 'offtheCanvas' India HCI prelude
 
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
 
Portfolio.pdf
Portfolio.pdfPortfolio.pdf
Portfolio.pdf
 
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
 
projectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdfprojectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdf
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
 
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
 
Exploring the Future of Smart Garages.pdf
Exploring the Future of Smart Garages.pdfExploring the Future of Smart Garages.pdf
Exploring the Future of Smart Garages.pdf
 
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
 
Mohannad Abdullah portfolio _ V2 _22-24
Mohannad Abdullah  portfolio _ V2 _22-24Mohannad Abdullah  portfolio _ V2 _22-24
Mohannad Abdullah portfolio _ V2 _22-24
 
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
 
20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf
 

NMMC Metro Rail Project

  • 1. Navi Mumbai Metro Project Project Details Belapur-Kharghar Rapid Transit system CIDCO
  • 2. Introduction The government of maharashtra (gom) has entrusted City and Industrial Development Corporation of maharashtra ltd. (CIDCO) to plan and create Environment-friendly, model urban settlement with full-fledged physical and Social infrastructure to meet residential, commercial and industrial needs of The population at present and in the years to come. To boost the earlier Development, a rail-based transport was suggested in the 80s and mass Rapid transportation master plan was prepared with six suburban corridor Routes as under: Sr.No Corridor Length status 1. Mankhurd-Belapur-Panvel 29kms Completed 2. Thane-Tubhe-Nerul/Vashi 20kms Completed 3. Nerul-Seawoods-Uran 27kms In Progress 4. Panvel-Ulwe-Uran 32kms Under planning 5. Ring Railway around CBD 15kms Under Planning Out of these, first two are completed and the third one is in progress. Meanwhile, it was found that land use in the Navi Mumbai area has changed to a large extent due to the proposed SEZ and Navi Mumbai International Airport. Hence, CIDCO decided to review the master plan for transportation connectivity.
  • 3. Consultants  The Louis Berger Group Inc. (LBG) has been appointed by CIDCO as "General Consultant" for Navi Mumbai Metro Line project. LBG would provide General Consultancy Services for Implementation of Navi Mumbai Metro Line 1 from Belapur to Kharghar.  Team:-  Mr John R Gretton Project Director, GC (LBG) Navi Mumbai Metro Project.  Mr Surjit S. Madan Head - Rail Systems, GC (LBG) Navi Mumbai Metro Project  Mr Umakanta Mahapatra Sr. Project Manager/Head - Metro Civil Infra, GC (LBG) Navi Mumbai Metro Project.  Project General Consultant Office Address The Louis Berger Group Inc. Institution of Engineers Building, Plot No. 106, Sector 15, Belapur (E), Navi Mumbai - 400614, India Website: w w w .louisberger.com Email: info.nmm@lbconsult.net
  • 4. Taking the first step  After studying the various modes of transports such as Monorail, Bus, etc., the consultant proposed connectivity by Metro Rail System due to various merits on account of it being energy efficient, pollution free and occupying less land space as compared to other modes of transport. The passenger carrying capacity of medium Metro Rail System can be up to 35000 PHPDT (Peak Hour Per Direction Traffic) whereas Monorail System is suitable up to 20000 PHPDT. Hence, Metro Rail System was preferred for Navi Mumbai.  The consultants proposed six metro corridors in Navi Mumbai, out of these Belapur-kharghar and Kharghar-kalamboli-khandeshwar which were considered as metro corridors have now been decided to be suburban corridors. Since Navi Mumbai International Airport is approved, need was felt to review the Master Plan of Navi Mumbai’s connectivity.
  • 5. Map of NMMC’s Metro Rail project
  • 6. Phase one  CBD Belapur-Kharghar  International Airport Corridor, The study recommended that rail-based corridor of Belapur-Kharghar- Proposed Airport is the only potentially developable corridor at present. It was further recommended by DMRC to take up Metro Rail Project from Belapur to kharghar in the 1st stage, taloja to Khandeshwar as 2nd stage and interlink between kharghar and taloja in 3rd stage due to the following Reasons :- 1) The area is developing and Metro will boost the development and will fetch additional premium on land price (which may supplement a part of the construction cost). 2) This is alternative to Mansarovar - Taloja suburban line. The suburban alignment is away from the human settlement and the proposed Metro is passing through the settlement to serve the occupants. Proposed ridership is adequate to make the project viable for operation.  Maharashtra Government has authorised CIDCO as MRT system administration Implementing Agency under Indian Tramway Act 1886 for implementation of Belapur-kharghar-Kalamboli-Khandeshwar Metro Rail Project on September 30, 2010.
  • 7. Project Cost  Project cost details for CBD Belapur-kharghar-Khandeshwar-Navi Mumbai International Airport Corridor  CBD Belapur-kharghar-Kalamboli-Khandeshwar Corridor is recommended by DMRC to be executed in three stages as given below:  Stage - I: Line No. 1 from Belapur to Kharghar (11.10 km). The cost of the project will be approximately 1,985 crores.  Stage - II: Line No. 2 from Khandeshwar to Taloja MIDC (8.35 km). The cost of the project will be approximately 1,509 crores.  Stage - III: Line No. 3 from Interconnection of Line - I & II (2.00 km). The cost of the project will be approximately 574 crores. This cost is tentative and subject to change as per site feasibility.  The above work of Corridor 1 is expected to be completed in 5 years, along with the completion of 1st Phase of Navi Mumbai International Airport (NMIA) and is proposed to be extended up to NMIA.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12. Thank you Made By:- Parth S. Patil Fr. Y. B.Arch. Project Management 021