Project master schedule daughter station cng mini plant
38 Avenue Road- Rev 1, Detailed Programme
1. ID Task Name Duration Start Finish
1 38 Avenue Road - Master Programme 41.4 wks 01 Oct '15 29 Jul '16
2 Key Milestones 2 wks 06 Oct '15 19 Oct '15
3 Project Start 0 wks 06 Oct '15 06 Oct '15
4 Mobilization 2 wks 06 Oct '15 19 Oct '15
5 Kick off Meeting 0 wks 13 Oct '15 13 Oct '15
6 Construction Issue Drawings 0 wks 13 Oct '15 13 Oct '15
7 2nd Floor 0 wks 13 Oct '15 13 Oct '15
8 1st Floor 0 wks 13 Oct '15 13 Oct '15
9 Ground Floor 0 wks 13 Oct '15 13 Oct '15
10 Basement 0 wks 13 Oct '15 13 Oct '15
11 Lower Ground Floor 0 wks 13 Oct '15 13 Oct '15
12 Key Procurement Items 30 wks 13 Oct '15 23 May '16
13 Kitchen, Cinema & Gym Equipment 30 wks 13 Oct '15 23 May '16
14 Joinery and Marble 16 wks 05 Jan '16 25 Apr '16
15 Construction Works 40.6 wks 01 Oct '15 25 Jul '16
16 Ground Floor Level 36.4 wks 01 Oct '15 24 Jun '16
17 Kitchen 28 wks 19 Oct '15 13 May '16
18 Remove Fire place 1 wk 19 Oct '15 23 Oct '15
19 Remove Existing Shelf and Install Frame 1 wk 26 Oct '15 30 Oct '15
20 Fireplace for kitchen units installation 1 wk 02 Nov '15 06 Nov '15
21 M&E 1st & 2nd Fix 7 wks 26 Oct '15 11 Dec '15
22 Kitchen Equipment Installation 5 wks 30 Nov '15 15 Jan '16
23 Audio Video Connections 2 wks 14 Dec '15 08 Jan '16
24 Windows Security Systems 2 wks 11 Jan '16 22 Jan '16
25 Make Good Ceiling and Plaster where Necessary 1 wk 15 Feb '16 19 Feb '16
26 Walls subway tiles 1 wk 22 Feb '16 26 Feb '16
27 Make Good Flooring for Parquet Installation 1 wk 29 Feb '16 04 Mar '16
28 Architraves and Plinth blocks repaint 1 wk 29 Feb '16 04 Mar '16
29 Doors Repaint 1 wk 07 Mar '16 11 Mar '16
30 Window Treatment Sheer Curtains 1 wk 04 Apr '16 08 Apr '16
31 Lighting Pendants above Island 1 wk 11 Apr '16 15 Apr '16
32 Windows Frames repaint and Window Opaque Paint 2 wks 18 Apr '16 29 Apr '16
33 Furniture 2 wks 02 May '16 13 May '16
34 Entrance and Central Hall 32 wks 19 Oct '15 10 Jun '16
35 Install Protection 1 wk 19 Oct '15 23 Oct '15
36 Cutout and Rebuild Wall 1 wk 26 Oct '15 30 Oct '15
37 Remove Fire Door and Install Door 1 wk 02 Nov '15 06 Nov '15
38 Nickel Cold Plated Doors 1 wk 07 Mar '16 11 Mar '16
39 Cold plate lining inside of Architrave 1 wk 14 Mar '16 18 Mar '16
40 Audio Video Connections 2 wks 21 Mar '16 01 Apr '16
41 Windows Security Systems 2 wks 04 Apr '16 15 Apr '16
42 Wall Covering 2 wks 18 Apr '16 29 Apr '16
43 Hang Wall Covering 2 wks 02 May '16 13 May '16
44 Skirting Repaint 1 wk 16 May '16 20 May '16
45 Install Ceilings Lighting As Required/Chandelier 1 wk 16 May '16 20 May '16
46 Joinery 1 wk 23 May '16 27 May '16
47 Furniture 1 wk 30 May '16 03 Jun '16
48 Upholstery 1 wk 06 Jun '16 10 Jun '16
49 Drawing Room 28.4 wks 01 Oct '15 29 Apr '16
50 Install Protection 1 wk 01 Oct '15 07 Oct '15
51 M&E 1st Fix 3 wks 11 Jan '16 29 Jan '16
52 Window Treatment 1 wk 01 Feb '16 05 Feb '16
53 Audio Video Connections 2 wks 01 Feb '16 12 Feb '16
54 Windows Security Systems 2 wks 15 Feb '16 26 Feb '16
55 Door 1 wk 08 Feb '16 12 Feb '16
56 Install Parquet flooring 3 wks 15 Feb '16 04 Mar '16
57 Skirting Repaint 1 wk 07 Mar '16 11 Mar '16
58 Wall Covering 1 wk 14 Mar '16 18 Mar '16
59 Hang Wall Covering 1 wk 21 Mar '16 25 Mar '16
60 Upholstery 1 wk 28 Mar '16 01 Apr '16
38 Avenue Road - Master Progra
Key Milestones
06-10
4
13-10
13-10
13-10
13-10
13-10
13-10
13-10
Key Procurement Items
13
14
Construction Works
Ground Floor Level
Kitchen
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
Entrance and Central Hall
35
36
37
38
39
40
41
42
43
44
45
46
47
48
Drawing Room
50
51
52
53
54
55
56
57
58
59
60
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2016
38 Avenue Road- Rev 1.mpp
Master Programme
Page 1 / 8
2. ID Task Name Duration Start Finish
61 Furniture 1 wk 04 Apr '16 08 Apr '16
62 Lighting and Chandelier 1 wk 11 Apr '16 15 Apr '16
63 Accessories 1 wk 18 Apr '16 22 Apr '16
64 Equipment 1 wk 25 Apr '16 29 Apr '16
65 Dining Room 29.4 wks 08 Oct '15 13 May '16
66 Install Protection 1 wk 08 Oct '15 14 Oct '15
67 Remove Existing Kitchen shelves & Equipment 1 wk 15 Oct '15 21 Oct '15
68 M&E 1st Fix 2 wks 18 Jan '16 29 Jan '16
69 Audio Video Connections 2 wks 01 Feb '16 12 Feb '16
70 Windows Security Systems 2 wks 15 Feb '16 26 Feb '16
71 Dinning Room Floating Ceiling 2 wks 01 Feb '16 12 Feb '16
72 Make Good Walls and Fully Plaster 1 wk 15 Feb '16 19 Feb '16
73 Parquet flooring 2 wks 22 Feb '16 04 Mar '16
74 Nickel Cold Plated Doors 1 wk 07 Mar '16 11 Mar '16
75 Window Treatment 1 wk 07 Mar '16 11 Mar '16
76 New Cornice and paint to match 1 wk 14 Mar '16 18 Mar '16
77 Make Good Flooring for Parquet Installation 1 wk 21 Mar '16 25 Mar '16
78 Windows Frames repaint and Window Opaque Paint 1 wk 21 Mar '16 25 Mar '16
79 New Skirting and paint 1 wk 28 Mar '16 01 Apr '16
80 Wall Covering 1 wk 04 Apr '16 08 Apr '16
81 Install Wall Sconces 1 wk 11 Apr '16 15 Apr '16
82 Joinery 2 wks 11 Apr '16 22 Apr '16
83 Upholstery 1 wk 25 Apr '16 29 Apr '16
84 Lighting and Chandelier 1 wk 25 Apr '16 29 Apr '16
85 Accessories 1 wk 02 May '16 06 May '16
86 Furniture 1 wk 09 May '16 13 May '16
87 Family Room 21.4 wks 15 Oct '15 25 Mar '16
88 Install Protection 1 wk 15 Oct '15 21 Oct '15
89 M&E 1st Fix 1 wk 25 Jan '16 29 Jan '16
90 Audio Video Connections 2 wks 01 Feb '16 12 Feb '16
91 Windows Security Systems 2 wks 15 Feb '16 26 Feb '16
92 Nickel Cold Plated Doors 1 wk 01 Feb '16 05 Feb '16
93 Window Treatment 1 wk 01 Feb '16 05 Feb '16
94 Install Parquet Flooring 2 wks 08 Feb '16 19 Feb '16
95 Lighting and Chandelier 1 wk 22 Feb '16 26 Feb '16
96 Furniture 1 wk 29 Feb '16 04 Mar '16
97 Upholstery 1 wk 07 Mar '16 11 Mar '16
98 Accessories 1 wk 14 Mar '16 18 Mar '16
99 Equipment 1 wk 21 Mar '16 25 Mar '16
100 Reading Room 21.4 wks 22 Oct '15 01 Apr '16
101 Install Protection 1 wk 22 Oct '15 28 Oct '15
102 Remove Existing Fire Place and Prepare for New 1 wk 29 Oct '15 04 Nov '15
103 M&E 1st Fix 1 wk 01 Feb '16 05 Feb '16
104 Audio Video Connections 2 wks 08 Feb '16 19 Feb '16
105 Windows Security Systems 2 wks 22 Feb '16 04 Mar '16
106 Install Parquet Flooring 2 wks 08 Feb '16 19 Feb '16
107 Skirting Repaint 1 wk 22 Feb '16 26 Feb '16
108 Joinery 1 wk 29 Feb '16 04 Mar '16
109 Lighting 1 wk 07 Mar '16 11 Mar '16
110 Window Treatment (Sheer Curtains) 1 wk 07 Mar '16 11 Mar '16
111 Upholstery 1 wk 14 Mar '16 18 Mar '16
112 Furniture 1 wk 21 Mar '16 25 Mar '16
113 Accessories 1 wk 28 Mar '16 01 Apr '16
114 Cloakroom Area 3 wks 29 Oct '15 18 Nov '15
115 Install Protection 1 wk 29 Oct '15 04 Nov '15
116 Remove Doors 1 wk 05 Nov '15 11 Nov '15
117 Cold Plate Lining to inside of Architraves 1 wk 12 Nov '15 18 Nov '15
118 WC 2 wks 05 Nov '15 18 Nov '15
119 Install Protection 1 wk 05 Nov '15 11 Nov '15
120 Nickel Cold Plated Doors 1 wk 12 Nov '15 18 Nov '15
61
62
63
64
Dining Room
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
Family Room
88
89
90
91
92
93
94
95
96
97
98
99
Reading Room
101
102
103
104
105
106
107
108
109
110
111
112
113
Cloakroom Area
115
116
117
WC
119
120
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2016
38 Avenue Road- Rev 1.mpp
Master Programme
Page 2 / 8
3. ID Task Name Duration Start Finish
121 Study 15 wks 14 Dec '15 08 Apr '16
122 M&E 1st and M&E 2nd Fix 2 wks 14 Dec '15 08 Jan '16
123 Nickel Cold Plated Doors 1 wk 11 Jan '16 15 Jan '16
124 Audio Video Connections 2 wks 11 Jan '16 22 Jan '16
125 Windows Security Systems 2 wks 25 Jan '16 05 Feb '16
126 Window Treatment 1 wk 18 Jan '16 22 Jan '16
127 Window sill and Windows repaint 1 wk 25 Jan '16 29 Jan '16
128 Wall Covering 2 wks 01 Feb '16 12 Feb '16
129 Hand Wall Covering 2 wks 15 Feb '16 26 Feb '16
130 Skirting Repaint 1 wk 29 Feb '16 04 Mar '16
131 Lighting and Chandelier 1 wk 07 Mar '16 11 Mar '16
132 Flooring 3 wks 29 Feb '16 18 Mar '16
133 Joinery 1 wk 14 Mar '16 18 Mar '16
134 Upholstery 1 wk 21 Mar '16 25 Mar '16
135 Furniture 1 wk 28 Mar '16 01 Apr '16
136 Equipment 1 wk 04 Apr '16 08 Apr '16
137 Stair 1 8 wks 07 Mar '16 29 Apr '16
138 M&E 1st Fix & M&E 2nd Fix 2 wks 07 Mar '16 18 Mar '16
139 Bound Runner 1 wk 21 Mar '16 25 Mar '16
140 Wall Covering 1 wk 28 Mar '16 01 Apr '16
141 Skirting Repaint 1 wk 04 Apr '16 08 Apr '16
142 Window Frame and Sill Repainted 1 wk 11 Apr '16 15 Apr '16
143 Wall Sconces 1 wk 18 Apr '16 22 Apr '16
144 Leather Cladded Hand Rail 1 wk 25 Apr '16 29 Apr '16
145 Common Works 3 wks 06 Jun '16 24 Jun '16
146 Builders Cleaning 1 wk 06 Jun '16 10 Jun '16
147 Design Team Snagging 2 wks 13 Jun '16 24 Jun '16
148 2nd Floor Level 21 wks 04 Dec '15 12 May '16
149 Bedroom 3 (Charlie) 11 wks 04 Dec '15 03 Mar '16
150 Bedroom 3 Area 11 wks 04 Dec '15 03 Mar '16
151 M&E 1st Fix 2 wks 04 Dec '15 17 Dec '15
152 M&E 2nd Fix 1 wk 18 Dec '15 07 Jan '16
153 Audio Video Connections 3 wks 08 Jan '16 28 Jan '16
154 Windows Security Systems 2 wks 08 Jan '16 21 Jan '16
155 Joinery 1st Fix 1 wk 08 Jan '16 14 Jan '16
156 Walls Repaint 1 wk 15 Jan '16 21 Jan '16
157 Window Treatment 1 wk 22 Jan '16 28 Jan '16
158 Skirting Repaint 1 wk 22 Jan '16 28 Jan '16
159 Carpet 1 wk 29 Jan '16 04 Feb '16
160 Joinery 2nd Fix 1 wk 05 Feb '16 11 Feb '16
161 Nickel Cold Plated Door 1 wk 12 Feb '16 18 Feb '16
162 Install FFE Inc Tables, Bed base,Lights 1 wk 19 Feb '16 25 Feb '16
163 Final Decorations 1 wk 26 Feb '16 03 Mar '16
164 Ensuite Bathroom 1 wk 29 Jan '16 04 Feb '16
165 Window Treatment 1 wk 29 Jan '16 04 Feb '16
166 Bedroom 4 (Louis) 12 wks 11 Dec '15 17 Mar '16
167 Bedroom 4 Area 12 wks 11 Dec '15 17 Mar '16
168 M&E 1st Fix 3 wks 11 Dec '15 14 Jan '16
169 M&E 2nd Fix 1 wk 15 Jan '16 21 Jan '16
170 Audio Video Connections 3 wks 22 Jan '16 11 Feb '16
171 Windows Security Systems 2 wks 22 Jan '16 04 Feb '16
172 Joinery 1st Fix 1 wk 22 Jan '16 28 Jan '16
173 Walls Repaint 1 wk 29 Jan '16 04 Feb '16
174 Skirting Repaint 1 wk 05 Feb '16 11 Feb '16
175 Window Treatment 1 wk 05 Feb '16 11 Feb '16
176 Carpet 1 wk 12 Feb '16 18 Feb '16
177 Joinery 2nd Fix 1 wk 19 Feb '16 25 Feb '16
178 Nickel Cold Plated Door 1 wk 26 Feb '16 03 Mar '16
179 Install FFE Inc Tables, Bed base,Lights 1 wk 04 Mar '16 10 Mar '16
180 Final Decorations 1 wk 11 Mar '16 17 Mar '16
Study
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
Stair 1
138
139
140
141
142
143
144
Common Works
146
147
2nd Floor Level
Bedroom 3 (Charlie)
Bedroom 3 Area
151
152
153
154
155
156
157
158
159
160
161
162
163
Ensuite Bathroom
165
Bedroom 4 (Louis)
Bedroom 4 Area
168
169
170
171
172
173
174
175
176
177
178
179
180
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2016
38 Avenue Road- Rev 1.mpp
Master Programme
Page 3 / 8
4. ID Task Name Duration Start Finish
181 Ensuite Bathroom 1 wk 12 Feb '16 18 Feb '16
182 Window Treatment 1 wk 12 Feb '16 18 Feb '16
183 Bedroom 5 (Nanny) 11 wks 18 Dec '15 17 Mar '16
184 Bedroom 5 Area 11 wks 18 Dec '15 17 Mar '16
185 M&E 1st Fix 2 wks 18 Dec '15 14 Jan '16
186 M&E 2nd Fix 1 wk 15 Jan '16 21 Jan '16
187 Audio Video Connections 3 wks 22 Jan '16 11 Feb '16
188 Windows Security Systems 2 wks 22 Jan '16 04 Feb '16
189 Joinery 1st Fix 1 wk 22 Jan '16 28 Jan '16
190 Walls Repaint 1 wk 29 Jan '16 04 Feb '16
191 Skirting Repaint 1 wk 05 Feb '16 11 Feb '16
192 Window Treatment 1 wk 05 Feb '16 11 Feb '16
193 Carpet 1 wk 12 Feb '16 18 Feb '16
194 Joinery 2nd Fix 1 wk 19 Feb '16 25 Feb '16
195 Nickel Cold Plated Door 1 wk 26 Feb '16 03 Mar '16
196 Install FFE Inc Tables, Bed base,Lights 1 wk 04 Mar '16 10 Mar '16
197 Final Decorations 1 wk 11 Mar '16 17 Mar '16
198 Ensuite Bathroom 1 wk 12 Feb '16 18 Feb '16
199 Window Treatment 1 wk 12 Feb '16 18 Feb '16
200 Bedroom 6 (Arthur) 11 wks 08 Jan '16 24 Mar '16
201 Bedroom 6 Area 11 wks 08 Jan '16 24 Mar '16
202 M&E 1st Fix 2 wks 08 Jan '16 21 Jan '16
203 M&E 2nd Fix 1 wk 22 Jan '16 28 Jan '16
204 Audio Video Connections 3 wks 29 Jan '16 18 Feb '16
205 Windows Security Systems 2 wks 29 Jan '16 11 Feb '16
206 Joinery 1st Fix 1 wk 29 Jan '16 04 Feb '16
207 Walls Repaint 1 wk 05 Feb '16 11 Feb '16
208 Skirting Repaint 1 wk 12 Feb '16 18 Feb '16
209 Window Treatment 1 wk 12 Feb '16 18 Feb '16
210 Carpet 1 wk 19 Feb '16 25 Feb '16
211 Joinery 2nd Fix 1 wk 26 Feb '16 03 Mar '16
212 Nickel Cold Plated Door 1 wk 04 Mar '16 10 Mar '16
213 Install FFE Inc Tables, Bed base,Lights 1 wk 11 Mar '16 17 Mar '16
214 Final Decorations 1 wk 18 Mar '16 24 Mar '16
215 Ensuite Bathroom 1 wk 19 Feb '16 25 Feb '16
216 Window Treatment 1 wk 19 Feb '16 25 Feb '16
217 Children's TV Room 11 wks 15 Jan '16 31 Mar '16
218 M&E 1st Fix 2 wks 15 Jan '16 28 Jan '16
219 M&E 2nd Fix 1 wk 29 Jan '16 04 Feb '16
220 Audio Video Connections 3 wks 05 Feb '16 25 Feb '16
221 Windows Security Systems 2 wks 05 Feb '16 18 Feb '16
222 Joinery 1st Fix 1 wk 05 Feb '16 11 Feb '16
223 Walls Repaint 1 wk 12 Feb '16 18 Feb '16
224 Window Treatment 1 wk 19 Feb '16 25 Feb '16
225 Skirting Repaint 1 wk 19 Feb '16 25 Feb '16
226 Carpet 1 wk 26 Feb '16 03 Mar '16
227 Joinery 2nd Fix 1 wk 04 Mar '16 10 Mar '16
228 Nickel Cold Plated Door 1 wk 11 Mar '16 17 Mar '16
229 Install FFE Inc Tables, TV,Lights 1 wk 18 Mar '16 24 Mar '16
230 Final Decorations 1 wk 25 Mar '16 31 Mar '16
231 Landing & Stairs 8 wks 26 Feb '16 21 Apr '16
232 Wall Coverings 2 wks 26 Feb '16 10 Mar '16
233 Hang Wall Covering 2 wks 11 Mar '16 24 Mar '16
234 Skirting Repaint 1 wk 25 Mar '16 31 Mar '16
235 Carpet Flooring 1 wk 01 Apr '16 07 Apr '16
236 Carpet Runner 1 wk 08 Apr '16 14 Apr '16
237 Leather Cladded Hand Rail 1 wk 15 Apr '16 21 Apr '16
238 Common Works 3 wks 22 Apr '16 12 May '16
239 Builders Cleaning 1 wk 22 Apr '16 28 Apr '16
240 Design Team Snagging 2 wks 29 Apr '16 12 May '16
Ensuite Bathroom
182
Bedroom 5 (Nanny)
Bedroom 5 Area
185
186
187
188
189
190
191
192
193
194
195
196
197
Ensuite Bathroom
199
Bedroom 6 (Arthur)
Bedroom 6 Area
202
203
204
205
206
207
208
209
210
211
212
213
214
Ensuite Bathroom
216
Children's TV Room
218
219
220
221
222
223
224
225
226
227
228
229
230
Landing & Stairs
232
233
234
235
236
237
Common Works
239
240
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2016
38 Avenue Road- Rev 1.mpp
Master Programme
Page 4 / 8
5. ID Task Name Duration Start Finish
241 1st Floor Level 24.8 wks 16 Nov '15 19 May '16
242 HIS Suite Dressing & Bathrooms Inc WC 19 wks 16 Nov '15 08 Apr '16
243 M&E 1st Fix 3 wks 16 Nov '15 04 Dec '15
244 M&E 2nd Fix 2 wks 07 Dec '15 18 Dec '15
245 Marble for his Bathroom 3 wks 04 Jan '16 22 Jan '16
246 Audio Video Connections 2 wks 25 Jan '16 05 Feb '16
247 Window Security system 2 wks 25 Jan '16 05 Feb '16
248 Joinery 1st Fix 1 wk 25 Jan '16 29 Jan '16
249 Wall Covering 1 wk 01 Feb '16 05 Feb '16
250 Skirting Repaint 1 wk 08 Feb '16 12 Feb '16
251 Nickel Cold Plated Doors 1 wk 15 Feb '16 19 Feb '16
252 Window Treatment 1 wk 22 Feb '16 26 Feb '16
253 Headboard Joinery wall 1 wk 29 Feb '16 04 Mar '16
254 Flooring in dressing 2 wks 07 Mar '16 18 Mar '16
255 Joinery 2nd Fix 1 wk 21 Mar '16 25 Mar '16
256 Upholstery 1 wk 28 Mar '16 01 Apr '16
257 Final Decorations 1 wk 04 Apr '16 08 Apr '16
258 HER Suite Dressing & Bathrooms Inc WC 13 wks 23 Nov '15 04 Mar '16
259 M&E 1st Fix 2 wks 23 Nov '15 04 Dec '15
260 M&E 2nd Fix 1 wk 07 Dec '15 11 Dec '15
261 Audio Video Connections 2 wks 14 Dec '15 08 Jan '16
262 Window Security system 2 wks 14 Dec '15 08 Jan '16
263 Joinery 1st Fix 1 wk 14 Dec '15 18 Dec '15
264 Wall Covering 1 wk 04 Jan '16 08 Jan '16
265 Skirting Repaint 1 wk 11 Jan '16 15 Jan '16
266 Nickel Cold Plated Doors 1 wk 18 Jan '16 22 Jan '16
267 Window Treatment 1 wk 25 Jan '16 29 Jan '16
268 Headboard Joinery wall 1 wk 01 Feb '16 05 Feb '16
269 Flooring in dressing 1 wk 08 Feb '16 12 Feb '16
270 Joinery 2nd Fix 1 wk 15 Feb '16 19 Feb '16
271 Upholstery 1 wk 22 Feb '16 26 Feb '16
272 Final Decorations 1 wk 29 Feb '16 04 Mar '16
273 Master Bedroom 13 wks 30 Nov '15 11 Mar '16
274 M&E 1st Fix 2 wks 30 Nov '15 11 Dec '15
275 M&E 2nd Fix 1 wk 14 Dec '15 18 Dec '15
276 Audio Video Connections 2 wks 04 Jan '16 15 Jan '16
277 Windows Security Systems 2 wks 04 Jan '16 15 Jan '16
278 Make Good To Walls Floors & Ceilings 1 wk 18 Jan '16 22 Jan '16
279 Window sill and Windows repaint 1 wk 25 Jan '16 29 Jan '16
280 Wall Covering 1 wk 01 Feb '16 05 Feb '16
281 Window Treatment 1 wk 01 Feb '16 05 Feb '16
282 Lighting and Chandelier 1 wk 08 Feb '16 12 Feb '16
283 Skirting Repaint 1 wk 08 Feb '16 12 Feb '16
284 Nickel Cold Plated Doors 1 wk 08 Feb '16 12 Feb '16
285 Joinery 1 wk 15 Feb '16 19 Feb '16
286 Flooring Carpet 1 wk 22 Feb '16 26 Feb '16
287 Furniture 1 wk 29 Feb '16 04 Mar '16
288 Upholstery 1 wk 07 Mar '16 11 Mar '16
289 Guest Bedroom 13 wks 07 Dec '15 18 Mar '16
290 M&E 1st Fix 2 wks 07 Dec '15 18 Dec '15
291 M&E 2nd Fix 1 wk 04 Jan '16 08 Jan '16
292 Audio Video Connections 2 wks 11 Jan '16 22 Jan '16
293 Windows Security Systems 2 wks 11 Jan '16 22 Jan '16
294 Make Good To Walls Floors & Ceilings 1 wk 25 Jan '16 29 Jan '16
295 Window sill and Windows repaint 1 wk 01 Feb '16 05 Feb '16
296 Wall Covering 1 wk 08 Feb '16 12 Feb '16
297 Window Treatment 1 wk 08 Feb '16 12 Feb '16
298 Lighting and Chandelier 1 wk 15 Feb '16 19 Feb '16
299 Skirting Repaint 1 wk 15 Feb '16 19 Feb '16
300 Nickel Cold Plated Doors 1 wk 15 Feb '16 19 Feb '16
1st Floor Level
HIS Suite Dressing & Bathrooms Inc WC
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
HER Suite Dressing & Bathrooms Inc WC
259
260
261
262
263
264
265
266
267
268
269
270
271
272
Master Bedroom
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
Guest Bedroom
290
291
292
293
294
295
296
297
298
299
300
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2016
38 Avenue Road- Rev 1.mpp
Master Programme
Page 5 / 8
6. ID Task Name Duration Start Finish
301 Joinery 1 wk 22 Feb '16 26 Feb '16
302 Flooring Carpet 1 wk 29 Feb '16 04 Mar '16
303 Furniture 1 wk 07 Mar '16 11 Mar '16
304 Upholstery 1 wk 14 Mar '16 18 Mar '16
305 Stair 1 and Landing 10 wks 14 Dec '15 04 Mar '16
306 M&E 1st Fix 2 wks 14 Dec '15 08 Jan '16
307 M&E 2nd Fix 1 wk 11 Jan '16 15 Jan '16
308 Audio Video Connections 2 wks 18 Jan '16 29 Jan '16
309 Skirting Repaint 1 wk 01 Feb '16 05 Feb '16
310 Wall Sconces 1 wk 08 Feb '16 12 Feb '16
311 Wall covering 1 wk 15 Feb '16 19 Feb '16
312 Hang Wall Covering 1 wk 22 Feb '16 26 Feb '16
313 Bound Runner 1 wk 29 Feb '16 04 Mar '16
314 Guest Bath Room 1 wk 15 Feb '16 19 Feb '16
315 Window Treatment 1 wk 15 Feb '16 19 Feb '16
316 Lobby South 3 wks 29 Feb '16 18 Mar '16
317 Wall Covering 1 wk 29 Feb '16 04 Mar '16
318 Skirting Repaint 1 wk 07 Mar '16 11 Mar '16
319 Nickel Cold Plated Doors 1 wk 14 Mar '16 18 Mar '16
320 Common Works 3 wks 29 Apr '16 19 May '16
321 Builders Cleaning 1 wk 29 Apr '16 05 May '16
322 Design Team Snagging 2 wks 06 May '16 19 May '16
323 Basement 25.8 wks 16 Nov '15 26 May '16
324 Cinema 18 wks 16 Nov '15 01 Apr '16
325 M&E 1st Fix 3 wks 16 Nov '15 04 Dec '15
326 M&E 2nd Fix 2 wks 07 Dec '15 18 Dec '15
327 Audio Video System 6 wks 07 Dec '15 29 Jan '16
328 Joinery 1st Fix 2 wks 04 Jan '16 15 Jan '16
329 Timber Flooring to include insulation 2 wks 18 Jan '16 29 Jan '16
330 Nickel Cold Plated Doors 1 wk 01 Feb '16 05 Feb '16
331 New Skirting 1 wk 08 Feb '16 12 Feb '16
332 Leather Panelled Walls 2 wks 15 Feb '16 26 Feb '16
333 Hang Wall Covering 1 wk 29 Feb '16 04 Mar '16
334 Carpet Flooring 1 wk 07 Mar '16 11 Mar '16
335 Joinery 2nd Fix 2 wks 14 Mar '16 25 Mar '16
336 Upholstery & Soft Furnishing 1 wk 28 Mar '16 01 Apr '16
337 Stair 2 & 3 1 wk 07 Dec '15 11 Dec '15
338 Install Protection 1 wk 07 Dec '15 11 Dec '15
339 Wet Leisure Corridor 2 wks 14 Dec '15 08 Jan '16
340 Install Protection 1 wk 14 Dec '15 18 Dec '15
341 Walls Mosaic 1 wk 04 Jan '16 08 Jan '16
342 Football Ground 4 wks 14 Dec '15 22 Jan '16
343 Football Ground Works 2 wks 14 Dec '15 08 Jan '16
344 Foot ball Ground Pictch 2 wks 11 Jan '16 22 Jan '16
345 Salon 4 wks 11 Jan '16 05 Feb '16
346 Install Protection 1 wk 11 Jan '16 15 Jan '16
347 Wall Covering 1 wk 18 Jan '16 22 Jan '16
348 Hang Wall Covering 1 wk 25 Jan '16 29 Jan '16
349 Equipment 1 wk 01 Feb '16 05 Feb '16
350 Staff Kitchen 3 wks 08 Feb '16 26 Feb '16
351 Install Protection 1 wk 08 Feb '16 12 Feb '16
352 Preparation of Surfaces 1 wk 15 Feb '16 19 Feb '16
353 Equipment 1 wk 22 Feb '16 26 Feb '16
354 Laundry Area 3 wks 15 Feb '16 04 Mar '16
355 Install Protection 1 wk 15 Feb '16 19 Feb '16
356 Joinery 1 wk 22 Feb '16 26 Feb '16
357 Equipment 1 wk 29 Feb '16 04 Mar '16
358 Hall 1 & 2 4 wks 15 Feb '16 11 Mar '16
359 Install Protection 1 wk 15 Feb '16 19 Feb '16
360 Wall Covering 1 wk 22 Feb '16 26 Feb '16
301
302
303
304
Stair 1 and Landing
306
307
308
309
310
311
312
313
Guest Bath Room
315
Lobby South
317
318
319
Common Works
321
322
Basement
Cinema
325
326
327
328
329
330
331
332
333
334
335
336
Stair 2 & 3
338
Wet Leisure Corridor
340
341
Football Ground
343
344
Salon
346
347
348
349
Staff Kitchen
351
352
353
Laundry Area
355
356
357
Hall 1 & 2
359
360
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2016
38 Avenue Road- Rev 1.mpp
Master Programme
Page 6 / 8
7. ID Task Name Duration Start Finish
361 Hang Wall Covering 2 wks 29 Feb '16 11 Mar '16
362 Common Works 3 wks 06 May '16 26 May '16
363 Builders Cleaning 1 wk 06 May '16 12 May '16
364 Design Team Snagging 2 wks 13 May '16 26 May '16
365 Lower Ground Floor 18.8 wks 25 Jan '16 02 Jun '16
366 Children's Play Room 8 wks 25 Jan '16 18 Mar '16
367 Install Protection 1 wk 25 Jan '16 29 Jan '16
368 Walls & Columns 1 wk 01 Feb '16 05 Feb '16
369 AV System 2 wks 08 Feb '16 19 Feb '16
370 Nickel Cold Plated Doors 1 wk 22 Feb '16 26 Feb '16
371 Carpet Flooring 1 wk 29 Feb '16 04 Mar '16
372 Skirting 1 wk 07 Mar '16 11 Mar '16
373 Joinery 1 wk 14 Mar '16 18 Mar '16
374 Upholstery 1 wk 14 Mar '16 18 Mar '16
375 Equipment 1 wk 14 Mar '16 18 Mar '16
376 Children's Music Room 7 wks 01 Feb '16 18 Mar '16
377 Install Protection 1 wk 01 Feb '16 05 Feb '16
378 AV System 2 wks 08 Feb '16 19 Feb '16
379 Nickel Cold Plated Doors 1 wk 22 Feb '16 26 Feb '16
380 Walls Repaint 1 wk 29 Feb '16 04 Mar '16
381 Skirting Repaint 1 wk 07 Mar '16 11 Mar '16
382 Carpet Tiles 1 wk 14 Mar '16 18 Mar '16
383 Hall 2 (upper & lower landing) & Stair 2 2 wks 08 Feb '16 19 Feb '16
384 Install Protection 1 wk 08 Feb '16 12 Feb '16
385 Hand Rail and Leather Cladding 1 wk 15 Feb '16 19 Feb '16
386 Pool 2 wks 15 Feb '16 26 Feb '16
387 Install Protection 1 wk 15 Feb '16 19 Feb '16
388 Furniture 1 wk 22 Feb '16 26 Feb '16
389 Stair 1 6 wks 22 Feb '16 01 Apr '16
390 Install Protection 1 wk 22 Feb '16 26 Feb '16
391 MEP 1st Fix & 2nd fix 1 wk 29 Feb '16 04 Mar '16
392 Wall covering 1 wk 07 Mar '16 11 Mar '16
393 Hang Wallcovering 1 wk 14 Mar '16 18 Mar '16
394 Wall Sconces 1 wk 21 Mar '16 25 Mar '16
395 Skirting Repaint 1 wk 28 Mar '16 01 Apr '16
396 Flooring bound runner 1 wk 28 Mar '16 01 Apr '16
397 GYM 9 wks 22 Feb '16 22 Apr '16
398 Install Protection 1 wk 22 Feb '16 26 Feb '16
399 MEP services 2 wks 29 Feb '16 11 Mar '16
400 Wall covering 1 wk 14 Mar '16 18 Mar '16
401 Hang Wall Covering 1 wk 21 Mar '16 25 Mar '16
402 Flooring with Carpet tiles 2 wks 28 Mar '16 08 Apr '16
403 Skirting Repaint 1 wk 11 Apr '16 15 Apr '16
404 Joinery and Equipment 1 wk 18 Apr '16 22 Apr '16
405 Hall 1 5 wks 29 Feb '16 01 Apr '16
406 Install Protection 1 wk 29 Feb '16 04 Mar '16
407 Wall covering 1 wk 07 Mar '16 11 Mar '16
408 Lift Door and other doors 1 wk 14 Mar '16 18 Mar '16
409 Skirting Repaint 1 wk 21 Mar '16 25 Mar '16
410 Architraves & Plinth Blocks 1 wk 28 Mar '16 01 Apr '16
411 Staff Flat 7 wks 07 Mar '16 22 Apr '16
412 Install Protection 1 wk 07 Mar '16 11 Mar '16
413 Bath for bathroom 1 wk 14 Mar '16 18 Mar '16
414 Dog Wash in Lobby 1 wk 21 Mar '16 25 Mar '16
415 Carpet Flooring 1 wk 28 Mar '16 01 Apr '16
416 Joinery 1 wk 04 Apr '16 08 Apr '16
417 Upholstery 1 wk 11 Apr '16 15 Apr '16
418 Equipment 1 wk 18 Apr '16 22 Apr '16
419 Powder Room/WC1 2 wks 07 Mar '16 18 Mar '16
420 Install Protection 1 wk 07 Mar '16 11 Mar '16
361
Common Works
363
364
Lower Ground Floor
Children's Play Room
367
368
369
370
371
372
373
374
375
Children's Music Room
377
378
379
380
381
382
Hall 2 (upper & lower landing) & Stair 2
384
385
Pool
387
388
Stair 1
390
391
392
393
394
395
396
GYM
398
399
400
401
402
403
404
Hall 1
406
407
408
409
410
Staff Flat
412
413
414
415
416
417
418
Powder Room/WC1
420
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2016
38 Avenue Road- Rev 1.mpp
Master Programme
Page 7 / 8
8. ID Task Name Duration Start Finish
421 Doors 1 wk 14 Mar '16 18 Mar '16
422 Storage Room 4 wks 14 Mar '16 08 Apr '16
423 Install Protection 1 wk 14 Mar '16 18 Mar '16
424 Wall Repainted 1 wk 21 Mar '16 25 Mar '16
425 Joinery (shelves) 2 wks 28 Mar '16 08 Apr '16
426 Common Works 3 wks 13 May '16 02 Jun '16
427 Builders Cleaning 1 wk 13 May '16 19 May '16
428 Design Team Snagging 2 wks 20 May '16 02 Jun '16
429 External Works 32 wks 01 Dec '15 25 Jul '16
430 Landscaping Works 32 wks 01 Dec '15 25 Jul '16
431 Gas Meter Dismantle 2 wks 01 Dec '15 14 Dec '15
432 M&E Works for Gas Meter 2 wks 15 Dec '15 11 Jan '16
433 Gas Meter Construction Works 4 wks 12 Jan '16 08 Feb '16
434 Irrigation works - Testing & Repair, as needed 8 wks 09 Feb '16 04 Apr '16
435 External Gate (Demolish old gate, elec work, install
new gate)
12 wks 09 Feb '16 02 May '16
436 External Scaffolding 2 wks 03 May '16 16 May '16
437 External Repair and Cleaning Works 10 wks 17 May '16 25 Jul '16
438 Testing & Commissioning 8 wks 16 May '16 08 Jul '16
439 Testing & Comm. Of M&E works 8 wks 16 May '16 08 Jul '16
440 Testing & Comm. of Security System 5 wks 30 May '16 01 Jul '16
441 Snagging & Handing Over 4 wks 04 Jul '16 29 Jul '16
442 Final Snagging 4 wks 04 Jul '16 29 Jul '16
443 Handing Over 0 wks 29 Jul '16 29 Jul '16
421
Storage Room
423
424
425
Common Works
427
428
External Works
430
431
432
433
434
435
436
437
Testing & Commissioning
439
440
Snagging & Handing Over
442
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2016
38 Avenue Road- Rev 1.mpp
Master Programme
Page 8 / 8