ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
3 Project Reinitiated 0 days Thu 1/1/15 Thu 1/1/15 Fri 8/3/18 Fri 8/3/18 2 days 937 days
4 Review technical, sustainability and program changes with
team
5 days Mon 1/5/15 Fri 1/9/15 Fri 8/3/18 Thu 8/9/18 0 days 935 days 3
5 Project reinitiation meeting with client and stakeholders on
any scope changes
1 day Mon 1/12/15 Mon 1/12/15 Fri 8/10/18 Fri 8/10/18 0 days 935 days 4
6 Edit design permit and tender drawings according to
feedback
10 days Mon 1/12/15 Fri 1/23/15 Fri 8/10/18 Thu 8/23/18 0 days 935 days 5SS
7 Review safety by construction with electrical, mechanical,
structural engineers
5 days Mon 1/26/15 Fri 1/30/15 Fri 8/31/18 Thu 9/6/18 0 days 940 days 6
8 Meeting with engineers and operation & mangament staff
on safety by construction designs
1 day Mon 2/2/15 Mon 2/2/15 Fri 9/7/18 Fri 9/7/18 0 days 940 days 7
9 Edit design according to safety by construction review
meeting
10 days Mon 2/2/15 Fri 2/13/15 Fri 9/7/18 Thu 9/20/18 0 days 940 days 8SS
10 Value engineering of design permit and tender drawings 5 days Mon 2/16/15 Fri 2/20/15 Fri 9/21/18 Thu 9/27/18 940 days 940 days 9
11 Meeting with value engineering group and review permit
and tender drawings
1 day Mon 3/23/15 Mon 3/23/15 Fri 8/3/18 Fri 8/3/18 0 days 880 days
12 Edit design permit and tender drawings according to value
engineering
10 days Mon 3/23/15 Fri 4/3/15 Fri 8/3/18 Thu 8/16/18 0 days 880 days 11SS
13 Review meeting with client and stakeholders on design
changes
1 day Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 12
14 Design Complete 0 days Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 13SS
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
1/1
12/7 12/21
December 1
November 2014
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
1/1
4/6
12/21 1/4 1/18 2/1 2/15 3/1 3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13
December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1
November 2014 January 2015 March 2015 May 2015 July 2015 September 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days
17 Develop recommendation report to UBC Board of
Governors
15 days Mon 1/26/15 Fri 2/13/15 Fri 8/24/18 Thu 9/13/18 9 days 935 days 6
18 Submit recommendation to UBC Board of Governors 0 days Fri 2/27/15 Fri 2/27/15 Fri 9/14/18 Fri 9/14/18 1 day 926 days 17
19 UBC Board of Governors review project
recommendations
10 days Mon 3/2/15 Fri 3/13/15 Fri 9/14/18 Thu 9/27/18 0 days 925 days 18
20 Approval from UBC Board of Governors 0 days Mon 3/16/15 Mon 3/16/15 Thu 9/27/18 Thu 9/27/18 925 days 925 days 19
21 Submit construction permits from UBC 0 days Mon 4/6/15 Mon 4/6/15 Fri 9/14/18 Fri 9/14/18 0 days 900 days 14
22 UBC review construction permit 10 days Mon 4/6/15 Fri 4/17/15 Fri 9/14/18 Thu 9/27/18 0 days 900 days 21
23 Approval of construction permit from UBC 0 days Fri 4/17/15 Fri 4/17/15 Thu 9/27/18 Thu 9/27/18 900 days 900 days 22
24 Develop traffic control plans for the delivery of
equipment and supplies for project
15 days Mon 7/13/15 Fri 7/31/15 Thu 5/10/18 Wed 5/30/18 0 days 739 days 47
25 Submit traffic control plans to UBC 0 days Fri 7/31/15 Fri 7/31/15 Thu 5/31/18 Thu 5/31/18 0 days 739 days 24
26 UBC review traffic control plans 10 days Mon 8/3/15 Fri 8/14/15 Thu 5/31/18 Wed 6/13/18 0 days 739 days 25
27 Approval from UBC on traffic control plans 0 days Fri 8/14/15 Fri 8/14/15 Thu 6/14/18 Thu 6/14/18 0 days 739 days 26
28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days
35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days
43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days
56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
12/28 1/18
December 21
September 2014 January 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
2/27
3/16
4/6
4/17
7/31
8/14
1/18 2/8 3/1 3/22 4/12 5/3 5/24 6/14 7/5 7/26 8/16 9/6 9/27 10/18 11/8 11/29 12/20 1/10 1/31 2/21 3/13 4/3 4/24 5/15
December 21 February 11 April 1 May 21 July 11 September 1 October 21 December 11 February 1 March 21 May 11
January 2015 May 2015 September 2015 January 2016 May 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days
28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days
29 Submit construction permits from the City 0 days Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 14
30 City reviews construction permits 30 days Mon 4/6/15 Fri 5/15/15 Fri 8/17/18 Thu 9/27/18 0 days 880 days 29SS
31 Approval from City on Construction permits 0 days Fri 5/15/15 Fri 5/15/15 Thu 9/27/18 Thu 9/27/18 880 days 880 days 30
32 Submit file grading permit to City 0 days Fri 7/10/15 Fri 7/10/15 Fri 9/7/18 Fri 9/7/18 0 days 825 days 47
33 City reviews file grading permits 15 days Mon 7/13/15 Fri 7/31/15 Fri 9/7/18 Thu 9/27/18 0 days 825 days 32SS
34 Approval from City on file grading permits 0 days Fri 7/31/15 Fri 7/31/15 Thu 9/27/18 Thu 9/27/18 825 days 825 days 33
35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days
36 Issue Bid Proposal for Concrete Services 0 days Thu 4/9/15 Thu 4/9/15 Wed 2/7/18 Wed 2/7/18 0 days 740 days
37 Acquire proposals for concrete services 10 days Thu 4/9/15 Wed 4/22/15 Wed 2/7/18 Tue 2/20/18 0 days 740 days 36
38 Evaluation of proposals for concrete services 5 days Thu 4/23/15 Wed 4/29/15 Wed 2/21/18 Tue 2/27/18 1 day 740 days 37
39 Award concrete services to qualified contractors 0 days Fri 5/1/15 Fri 5/1/15 Wed 2/28/18 Wed 2/28/18 0 days 739 days 38
40 Schedule for Concrete supplies and services 15 days Mon 5/4/15 Fri 5/22/15 Wed 10/10/18 Tue 10/30/18 898 days 898 days
41 Order and schedule for steel rebar 15 days Mon 5/4/15 Fri 5/22/15 Fri 9/7/18 Thu 9/27/18 0 days 875 days 39
42 Order and schedule for concrete 15 days Mon 5/4/15 Fri 5/22/15 Fri 9/7/18 Thu 9/27/18 875 days 875 days 41SS
43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days
56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
3/1
March 1
March 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
4/6
5/15
7/10
7/31
4/9
5/1
3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 11/8 11/22 12/6 12/20 1/3
March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1
March 2015 May 2015 July 2015 September 2015 November 2015 January 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days
28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days
35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days
43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days
44 Acquire quotations from qualified suppliers (equipment,
machinery, elevator, piping, cables, fixtures, duct,
landscaping material)
15 days Fri 5/1/15 Thu 5/21/15 Wed 2/28/18 Tue 3/20/18 0 days 739 days 39
45 Evaluate subcontractor quotations 30 days Mon 5/4/15 Fri 6/12/15 Thu 3/1/18 Wed 4/11/18 0 days 739 days 44SS+1 day
46 Award contract for subcontractors to work on utility and
trades work
5 days Mon 6/15/15 Fri 6/19/15 Thu 4/12/18 Wed 4/18/18 0 days 739 days 45
47 Schedule for subcontractor supplies and services 15 days Mon 6/22/15 Fri 7/10/15 Tue 5/22/18 Mon 6/11/18 0 days 762 days
48 Order and schedule for excavation machinery and
workers
15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
49 Order and schedule for elevator and necessary parts
and workers
15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
50 Order and schedule for HVAC parts and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
51 Order and schedule for plumbing parts and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
52 Order and schedule for electrical and SCADA cables
and parts and workers
15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
53 Order and schedule for drywall and paint and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
54 Order and schedule for carpets, windows, frames,
doors and workers
15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
55 Order and schedule for landscapers and plants 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
3/29
March 1 April 1
March 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
3/29
March 1 April 1
March 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25
April 1 May 1 June 1 July 1 August 1 September 1 October 1
March 2015 May 2015 July 2015 September 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25
April 1 May 1 June 1 July 1 August 1 September 1 October 1
March 2015 May 2015 July 2015 September 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days
28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days
35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days
43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days
56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days
57 Qualify contractors for Project 70 days Mon 6/22/15 Fri 9/25/15 Mon 6/4/18 Mon 8/27/18 762 days 762 days
58 Develop Request for Qualifications (RFQ) Specifications and
Documents
31 days Mon 6/22/15 Mon 8/3/15 Mon 6/4/18 Tue 7/17/18 9 days 771 days
59 Meet with legal team to discuss details on RFQ 1 day Mon 6/22/15 Mon 6/22/15 Wed 5/2/18 Wed 5/2/18 0 days 748 days 47SS
60 Edit RFQ specifications according to legal team details 15 days Tue 6/23/15 Mon 7/13/15 Thu 5/3/18 Wed 5/23/18 0 days 748 days 59
61 Legal team reviews and makes changes to RFQ documents 15 days Tue 7/14/15 Mon 8/3/15 Thu 5/24/18 Wed 6/13/18 0 days 748 days 60
62 RFQ specifications and documents complete 0 days Mon 8/3/15 Mon 8/3/15 Thu 6/14/18 Thu 6/14/18 748 days 748 days 61
63 RFQ Opens 0 days Fri 8/14/15 Fri 8/14/15 Thu 6/14/18 Thu 6/14/18 0 days 739 days 27,58
64 Acquire RFQ 15 days Mon 8/17/15 Fri 9/4/15 Thu 6/14/18 Wed 7/4/18 0 days 739 days 63
65 RFQ Closes 0 days Fri 9/4/15 Fri 9/4/15 Thu 7/5/18 Thu 7/5/18 0 days 739 days 64
66 Evaluation of RFQs 10 days Mon 9/7/15 Fri 9/18/15 Thu 7/5/18 Wed 7/18/18 0 days 739 days 65
67 Create short list of contractors from evaluated RFQs 5 days Mon 9/21/15 Fri 9/25/15 Thu 7/19/18 Wed 7/25/18 0 days 739 days 66
68 Tender/Bid Project 155 days Mon 9/28/15 Mon 5/2/16 Tue 8/28/18 Tue 10/30/18 653 days 653 days
79 Meet with contractors to discuss construction and subcontractor
details
1 day Mon 5/2/16 Mon 5/2/16 Thu 8/16/18 Thu 8/16/18 0 days 599 days 78
6/7
June 1
May 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
80 Review and edit costs, supply list, schedules and subcontractors
and their qualifications
30 days Tue 5/3/16 Mon 6/13/16 Fri 8/17/18 Thu 9/27/18 599 days 599 days 79
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
6/7
June 1
May 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
8/3
8/14
9/4
6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 11/8 11/22 12/6 12/20 1/3 1/17 1/31 2/14
June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1
May 2015 July 2015 September 2015 November 2015 January 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 11/8 11/22 12/6 12/20 1/3 1/17 1/31 2/14
June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1
May 2015 July 2015 September 2015 November 2015 January 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days
28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days
35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days
43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days
56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days
57 Qualify contractors for Project 70 days Mon 6/22/15 Fri 9/25/15 Mon 6/4/18 Mon 8/27/18 762 days 762 days
68 Tender/Bid Project 155 days Mon 9/28/15 Mon 5/2/16 Tue 8/28/18 Tue 10/30/18 653 days 653 days
69 Develop Tender Specifications and Documents 31 days Mon 9/28/15 Mon 11/9/15 Tue 8/28/18 Wed 10/10/18 79 days 762 days
70 Meet with legal team to discuss details on Tender
Specifications
1 day Mon 9/28/15 Mon 9/28/15 Thu 7/26/18 Thu 7/26/18 0 days 739 days 67
71 Edit tender specifications according to legal team details 15 days Tue 9/29/15 Mon 10/19/15 Fri 7/27/18 Thu 8/16/18 0 days 739 days 70
72 Legal team reviews and makes changes to tender
specifications documents
15 days Tue 10/20/15 Mon 11/9/15 Fri 8/17/18 Thu 9/6/18 0 days 739 days 71
73 Tender specifications and documents complete 0 days Mon 11/9/15 Mon 11/9/15 Fri 9/7/18 Fri 9/7/18 739 days 739 days 72
74 Bid Opens on BCBids 0 days Mon 2/29/16 Mon 2/29/16 Fri 9/7/18 Fri 9/7/18 0 days 660 days 27,69,66,76SS-15 days
75 Acquire Request for Proposal (RFP) for project construction 15 days Mon 2/29/16 Fri 3/18/16 Fri 9/7/18 Thu 9/27/18 660 days 660 days 74
76 Bid Closes 0 days Mon 3/21/16 Mon 3/21/16 Fri 8/17/18 Fri 8/17/18 0 days 630 days 78SS-30 days
77 Evaluation of Proposals for project construction 30 days Mon 3/21/16 Fri 4/29/16 Fri 8/17/18 Thu 9/27/18 630 days 630 days 76SS
78 Award project to qualified contractors 0 days Mon 5/2/16 Mon 5/2/16 Thu 8/16/18 Thu 8/16/18 0 days 599 days
79 Meet with contractors to discuss construction and subcontractor
details
1 day Mon 5/2/16 Mon 5/2/16 Thu 8/16/18 Thu 8/16/18 0 days 599 days 78
8/30
July 1 September 1
May 2015 September 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
80 Review and edit costs, supply list, schedules and subcontractors
and their qualifications
30 days Tue 5/3/16 Mon 6/13/16 Fri 8/17/18 Thu 9/27/18 599 days 599 days 79
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
8/30
July 1 September 1
May 2015 September 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
11/9
2/29
3/21
5/2
9/27 10/25 11/22 12/20 1/17 2/14 3/13 4/10 5/8 6/5 7/3 7/31 8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4
September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1 May 1
September 2015 January 2016 May 2016 September 2016 January 2017 May 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
9/27 10/25 11/22 12/20 1/17 2/14 3/13 4/10 5/8 6/5 7/3 7/31 8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4
September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1 May 1
September 2015 January 2016 May 2016 September 2016 January 2017 May 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days
88 Level Ground 10 days Wed 7/13/16 Tue 7/26/16 Fri 4/22/16 Thu 5/5/16 0 days -59 days 84
89 Bulk Excavate 30 days Wed 7/20/16 Tue 8/30/16 Fri 4/29/16 Thu 6/9/16 0 days -59 days 88FS-5 days
90 Excavate for Elevator 5 days Wed 7/27/16 Tue 8/2/16 Fri 6/3/16 Thu 6/9/16 0 days -39 days 89SS+5 days
91 Install Shoring 47 days Wed 8/31/16 Thu 11/3/16 Fri 6/10/16 Fri 8/12/16 0 days -59 days 89,90
92 Excavate Footings 25 days Fri 11/4/16 Thu 12/8/16 Mon 8/15/16 Fri 9/16/16 0 days -59 days 91
93 Loading of ground work 10 days Fri 12/9/16 Thu 12/22/16 Mon 9/19/16 Fri 9/30/16 0 days -59 days 92
94 Remove loadings 2 days Thu 12/22/16 Fri 12/23/16 Tue 2/7/17 Wed 2/8/17 0 days 33 days 93FS-1 day
95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days
111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days
124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days
137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days
156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF
7/4
6/5
May 11
May 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
6/5
May 11
May 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7/4
6/26 7/17 8/7 8/28 9/18 10/9 10/30 11/20 12/11 1/1 1/22 2/12 3/5 3/26 4/16 5/7 5/28 6/18 7/9 7/30 8/20
May 11 July 1 August 21 October 11 December 1 January 21 March 11 May 1 June 21 August 11
May 2016 September 2016 January 2017 May 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
6/26 7/17 8/7 8/28 9/18 10/9 10/30 11/20 12/11 1/1 1/22 2/12 3/5 3/26 4/16 5/7 5/28 6/18 7/9 7/30 8/20
May 11 July 1 August 21 October 11 December 1 January 21 March 11 May 1 June 21 August 11
May 2016 September 2016 January 2017 May 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days
95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days
96 Foundations (Ground Floor) 127 days Mon 10/3/16 Tue 3/28/17 Mon 10/3/16 Fri 5/12/17 0 days 0 days 93
97 Steel rebars get delivered on site (stored offsite) 10 days Mon 10/3/16 Fri 10/14/16 Wed 7/25/18 Wed 8/8/18 472 days 472 days 92SS
98 Form Footings 35 days Fri 12/23/16 Thu 2/9/17 Wed 2/8/17 Tue 3/28/17 0 days 33 days 94FS-1 day
99 Install Reinforcing Steel Footings 15 days Fri 1/20/17 Thu 2/9/17 Wed 3/8/17 Tue 3/28/17 0 days 33 days 98FF
100 Footing inspections 2 days Fri 2/10/17 Mon 2/13/17 Wed 3/29/17 Thu 3/30/17 0 days 33 days 99
101 Place Concrete Footings 2 days Tue 2/14/17 Wed 2/15/17 Fri 3/31/17 Mon 4/3/17 0 days 33 days 100
102 Strip Forms for Footings 10 days Wed 2/15/17 Tue 2/28/17 Mon 4/3/17 Fri 4/14/17 0 days 33 days 101FS-1 day
103 Backfill footings 10 days Wed 3/1/17 Tue 3/14/17 Mon 4/17/17 Fri 4/28/17 0 days 33 days 102
104 Pour concrete for ground floor 10 days Wed 3/15/17 Tue 3/28/17 Mon 5/1/17 Fri 5/12/17 0 days 33 days 103
105 Interior Supports (Ground Floor) 31 days Wed 3/29/17 Wed 5/10/17 Mon 5/15/17 Mon 6/26/17 33 days 33 days
106 Form Supports 16 days Wed 3/29/17 Wed 4/19/17 Mon 5/15/17 Mon 6/5/17 0 days 33 days 104
107 Install Reinforcing Steel Supports 15 days Thu 3/30/17 Wed 4/19/17 Tue 5/16/17 Mon 6/5/17 0 days 33 days 98,106FF
7/4
7/31
July 1
May 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
108 Support inspection 2 days Fri 4/21/17 Mon 4/24/17 Wed 6/7/17 Thu 6/8/17 0 days 33 days 107FS+1 day,106FS+1 day
109 Place Concrete Supports 2 days Tue 4/25/17 Wed 4/26/17 Fri 6/9/17 Mon 6/12/17 0 days 33 days 108
110 Strip forms for interior supports 10 days Thu 4/27/17 Wed 5/10/17 Tue 6/13/17 Mon 6/26/17 0 days 33 days 109
111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days
124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days
137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days
156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
7/31
July 1
May 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7/4
8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4 7/2 7/30 8/27 9/24 10/22 11/19 12/17 1/14 2/11 3/11 4/8
July 1 September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1
May 2016 September 2016 January 2017 May 2017 September 2017 January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3/2
7/3
8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4 7/2 7/30 8/27 9/24 10/22 11/19 12/17 1/14 2/11 3/11 4/8
July 1 September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1
May 2016 September 2016 January 2017 May 2017 September 2017 January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days
95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days
111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days
112 Foundation (Mezzanine) 24 days Wed 5/10/17 Mon 6/12/17 Mon 6/26/17 Thu 7/27/17 33 days 33 days
113 Form Mezzanine Floor 15 days Wed 5/10/17 Tue 5/30/17 Mon 6/26/17 Fri 7/14/17 0 days 33 days 110FS-1 day
114 Install Reinforcing Steel for Mezzanine Floor 7 days Mon 5/22/17 Tue 5/30/17 Thu 7/6/17 Fri 7/14/17 0 days 33 days 110FS-5 days,113FF
115 Mezzanine Floor inspections 1 day Thu 6/1/17 Thu 6/1/17 Tue 7/18/17 Tue 7/18/17 0 days 33 days 114FS+1 day
116 Place Concrete for Mezzanine Floor 2 days Fri 6/2/17 Mon 6/5/17 Wed 7/19/17 Thu 7/20/17 0 days 33 days 115
117 Strip Forms for Mezzanine Floor 5 days Tue 6/6/17 Mon 6/12/17 Fri 7/21/17 Thu 7/27/17 0 days 33 days 116
118 Interior Supports (Mezzanine) 16 days Tue 6/13/17 Tue 7/4/17 Fri 7/28/17 Fri 8/18/17 33 days 33 days
119 Form Supports 7 days Tue 6/13/17 Wed 6/21/17 Fri 7/28/17 Mon 8/7/17 0 days 33 days 117
120 Install Reinforcing Steel Supports 7 days Tue 6/13/17 Wed 6/21/17 Fri 7/28/17 Mon 8/7/17 0 days 33 days 113,119FF
121 Support inspection 1 day Fri 6/23/17 Fri 6/23/17 Wed 8/9/17 Wed 8/9/17 0 days 33 days 120FS+1 day
122 Place Concrete Supports 2 days Mon 6/26/17 Tue 6/27/17 Thu 8/10/17 Fri 8/11/17 0 days 33 days 121
4/23
April
Qtr 2, 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
123 Strip forms for interior supports 5 days Wed 6/28/17 Tue 7/4/17 Mon 8/14/17 Fri 8/18/17 0 days 33 days 122
124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days
137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days
156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
4/23
April
Qtr 2, 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
4/30 5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24
April May June July August September
Qtr 2, 2017 Qtr 3, 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
4/30 5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24
April May June July August September
Qtr 2, 2017 Qtr 3, 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days
95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days
111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days
124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days
125 Foundation (Second Floor) 35 days Wed 7/5/17 Tue 8/22/17 Mon 8/21/17 Fri 10/6/17 33 days 33 days
126 Form Second Floor 21 days Wed 7/5/17 Wed 8/2/17 Mon 8/21/17 Mon 9/18/17 0 days 33 days 123
127 Install Reinforcing Steel for Second Floor 15 days Thu 7/13/17 Wed 8/2/17 Tue 8/29/17 Mon 9/18/17 0 days 33 days 123FF-5 days,126FF
128 Second Floor inspections 2 days Thu 8/3/17 Fri 8/4/17 Tue 9/19/17 Wed 9/20/17 0 days 33 days 127,126
129 Place Concrete for Second Floor 2 days Mon 8/7/17 Tue 8/8/17 Thu 9/21/17 Fri 9/22/17 0 days 33 days 128
130 Strip Forms for Second Floor 10 days Wed 8/9/17 Tue 8/22/17 Mon 9/25/17 Fri 10/6/17 0 days 33 days 129
131 Interior Supports (Second) 30 days Wed 8/23/17 Tue 10/3/17 Mon 10/9/17 Fri 11/17/17 33 days 33 days
132 Form Supports 15 days Wed 8/23/17 Tue 9/12/17 Mon 10/9/17 Fri 10/27/17 0 days 33 days 130
133 Install Reinforcing Steel Supports 15 days Wed 8/23/17 Tue 9/12/17 Mon 10/9/17 Fri 10/27/17 0 days 33 days 132FF,126
134 Support inspection 2 days Thu 9/14/17 Fri 9/15/17 Tue 10/31/17 Wed 11/1/17 0 days 33 days 133FS+1 day,132FS+1 day
6/4
June 1
May 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
135 Place Concrete Supports 2 days Mon 9/18/17 Tue 9/19/17 Thu 11/2/17 Fri 11/3/17 0 days 33 days 134
136 Strip forms for interior supports 10 days Wed 9/20/17 Tue 10/3/17 Mon 11/6/17 Fri 11/17/17 0 days 33 days 135
137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days
156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
6/4
June 1
May 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
6/18 7/2 7/16 7/30 8/13 8/27 9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25
June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1
May 2017 July 2017 September 2017 November 2017 January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3/2
6/18 7/2 7/16 7/30 8/13 8/27 9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25
June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1
May 2017 July 2017 September 2017 November 2017 January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days
95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days
111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days
124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days
137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
138 Foundation (Third Floor) 35 days Wed 10/4/17 Tue 11/21/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
139 Form Third Floor 21 days Wed 10/4/17 Wed 11/1/17 Mon 11/20/17 Mon 12/18/17 0 days 33 days 136
140 Install Reinforcing Steel for Third Floor 15 days Thu 10/12/17 Wed 11/1/17 Tue 11/28/17 Mon 12/18/17 0 days 33 days 139FF,135FF-5 days
141 Third Floor inspections 2 days Thu 11/2/17 Fri 11/3/17 Tue 12/19/17 Wed 12/20/17 0 days 33 days 140
142 Place Concrete for Third Floor 2 days Mon 11/6/17 Tue 11/7/17 Mon 7/23/18 Tue 7/24/18 0 days 185 days 141
143 Strip Forms for Third Floor 10 days Wed 11/8/17 Tue 11/21/17 Wed 7/25/18 Tue 8/7/18 185 days 185 days 142
144 Interior Supports (Third ) 36 days Mon 11/6/17 Mon 12/25/17 Thu 12/21/17 Tue 1/30/18 26 days 26 days
145 Form Supports 15 days Mon 11/6/17 Fri 11/24/17 Thu 12/21/17 Wed 1/10/18 0 days 33 days 141
146 Install Reinforcing Steel Supports 15 days Mon 11/6/17 Fri 11/24/17 Thu 12/21/17 Wed 1/10/18 0 days 33 days 139,145FF
8/27
August 1
July 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
147 Support inspection 2 days Mon 11/27/17 Tue 11/28/17 Thu 1/11/18 Fri 1/12/18 7 days 33 days 146
148 Place Concrete Supports 2 days Fri 12/8/17 Mon 12/11/17 Wed 12/13/17 Thu 12/14/17 0 days 3 days 147
149 Strip forms for interior supports 10 days Tue 12/12/17 Mon 12/25/17 Wed 1/17/18 Tue 1/30/18 0 days 26 days 148
150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days
156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
8/27
August 1
July 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8
September 1 October 1 November 1 December 1 January 1 February 1 March 1 April 1
September 2017 November 2017 January 2018 March 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3/2
9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8
September 1 October 1 November 1 December 1 January 1 February 1 March 1 April 1
September 2017 November 2017 January 2018 March 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days
95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days
111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days
124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days
137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days
151 Form Roof 35 days Tue 12/26/17 Mon 2/12/18 Wed 1/31/18 Tue 3/20/18 0 days 26 days 149
152 Install Reinforcing Steel for Roof 15 days Tue 1/23/18 Mon 2/12/18 Mon 1/29/18 Fri 2/16/18 0 days 4 days 148FF-5 days,151FF
153 Roof inspections 2 days Tue 2/13/18 Wed 2/14/18 Thu 3/22/18 Fri 3/23/18 0 days 27 days 152,151
154 Place Concrete for Roof 2 days Fri 2/16/18 Mon 2/19/18 Mon 3/26/18 Tue 3/27/18 0 days 26 days 153
155 Strip Forms for Roof 10 days Mon 2/19/18 Fri 3/2/18 Thu 2/22/18 Wed 3/7/18 0 days 3 days 154FS-1 day
156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
12/3
December 1
November 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
12/3
December 1
November 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3/2
12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17
December 1 January 1 February 1 March 1 April 1 May 1 June 1
November 2017 January 2018 March 2018 May 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7/3
12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17
December 1 January 1 February 1 March 1 April 1 May 1 June 1
November 2017 January 2018 March 2018 May 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days
159 Pipes get delivered to site (stored off site) 14 days Tue 12/26/17 Fri 1/12/18 Wed 3/7/18 Mon 3/26/18 0 days 51 days 149
160 Inspect pipe supplies 15 days Mon 12/25/17 Fri 1/12/18 Thu 2/1/18 Wed 2/21/18 0 days 28 days 159SS-1 day
161 Weld pipes together prior to installation 30 days Mon 1/1/18 Fri 2/9/18 Tue 3/13/18 Mon 4/23/18 25 days 51 days 160SS+5 days
162 Install pipes 18 days Mon 2/12/18 Wed 3/7/18 Tue 3/20/18 Thu 4/12/18 26 days 26 days
163 Install Pipes for Ground Floor 3 days Mon 2/12/18 Wed 2/14/18 Thu 2/15/18 Mon 2/19/18 0 days 3 days 152FS-5 days,151FS-1 day,123,161SS+5 days
164 Install Pipes for Mezzainine Floor 3 days Mon 2/19/18 Wed 2/21/18 Tue 3/27/18 Thu 3/29/18 0 days 26 days 168,136
165 Install Pipes for Second Floor 3 days Mon 2/26/18 Wed 2/28/18 Tue 4/3/18 Thu 4/5/18 0 days 26 days 169,149
166 Install Pipes for Third Floor 3 days Mon 3/5/18 Wed 3/7/18 Tue 4/10/18 Thu 4/12/18 0 days 26 days 170,155
167 Pipe inspections 17 days Thu 2/15/18 Fri 3/9/18 Fri 3/23/18 Mon 4/16/18 26 days 26 days
168 Pipe Inspection for Ground Floor 2 days Thu 2/15/18 Fri 2/16/18 Fri 3/23/18 Mon 3/26/18 0 days 26 days 163
169 Pipe Inspection for Mezzainine Floor 2 days Thu 2/22/18 Fri 2/23/18 Fri 3/30/18 Mon 4/2/18 0 days 26 days 164
170 Pipe Inspection for Second Floor 2 days Thu 3/1/18 Fri 3/2/18 Fri 4/6/18 Mon 4/9/18 0 days 26 days 165
12/3
December 1
November 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
171 Pipe Inspection for Third Floor 2 days Thu 3/8/18 Fri 3/9/18 Fri 4/13/18 Mon 4/16/18 0 days 26 days 166
172 Plumbing fixtures get delivered (toilets, sinks, drains,
handrails, soap and paper towel dispensers)
5 days Mon 2/12/18 Fri 2/16/18 Fri 6/29/18 Thu 7/5/18 0 days 99 days 163SS
173 Inspection of plumbing fixtures 5 days Mon 2/12/18 Fri 2/16/18 Fri 6/29/18 Thu 7/5/18 99 days 99 days 172SS
174 Install plumbing fixtures 3 days Mon 3/12/18 Wed 3/14/18 Wed 8/1/18 Fri 8/3/18 0 days 102 days 171
175 Inspection of servicability of plumbing fixtures 2 days Thu 3/15/18 Fri 3/16/18 Mon 8/6/18 Tue 8/7/18 102 days 102 days 174
176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days
194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days
216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days
224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
12/3
December 1
November 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15
December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1
November 2017 January 2018 March 2018 May 2018 July 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7/3
7/3
12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15
December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1
November 2017 January 2018 March 2018 May 2018 July 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days
176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days
177 Ducting, air vents, heating and air conditioning units
get delivered on site
5 days Mon 12/25/17 Fri 12/29/17 Fri 6/29/18 Thu 7/5/18 134 days 134 days 178SS
178 Inspection of equipment and parts 30 days Mon 12/25/17 Fri 2/2/18 Fri 5/25/18 Thu 7/5/18 0 days 109 days 179FF-5 days
179 Weld ducting together 30 days Mon 1/1/18 Mon 2/12/18 Fri 5/25/18 Thu 7/5/18 0 days 104 days 181SF-5 days
180 Install ducting and air vents 18 days Mon 2/19/18 Wed 3/14/18 Tue 4/17/18 Thu 4/26/18 31 days 31 days
181 Install ducting and air vents (Ground Floor) 3 days Mon 2/19/18 Wed 2/21/18 Tue 4/17/18 Thu 4/19/18 0 days 41 days 168,123
182 Install ducting and air vents (Mezzainine Floor) 3 days Mon 2/26/18 Wed 2/28/18 Fri 4/20/18 Wed 4/25/18 0 days 39.5 days 169,136
183 Install ducting and air vents (Second Floor) 3 days Mon 3/5/18 Wed 3/7/18 Tue 4/24/18 Thu 4/26/18 0 days 36 days 170,149
184 Install ducting and air vents (Third Floor) 3 days Mon 3/12/18 Wed 3/14/18 Tue 4/17/18 Thu 4/19/18 0 days 26 days 171,155
185 Inspection of completed ducting and air vents 17 days Thu 2/22/18 Fri 3/16/18 Fri 4/20/18 Mon 4/30/18 31 days 31 days
12/3
November 21
September 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
186 HVAC Inspection of Ground Floor 2 days Thu 2/22/18 Fri 2/23/18 Fri 4/20/18 Mon 4/23/18 15 days 41 days 181
187 HVAC Inspection of Mezzainine Floor 2 days Thu 3/1/18 Fri 3/2/18 Wed 4/25/18 Fri 4/27/18 11 days 39.5 days 182
188 HVAC Inspection of Second Floor 2 days Thu 3/8/18 Fri 3/9/18 Fri 4/27/18 Mon 4/30/18 0 days 36 days 183
189 HVAC Inspection of Third Floor 2 days Thu 3/15/18 Fri 3/16/18 Fri 4/20/18 Mon 4/23/18 0 days 26 days 184
190 Heating and air conditioning units get delivered on site 5 days Mon 2/19/18 Fri 2/23/18 Fri 6/29/18 Thu 7/5/18 0 days 94 days 181SS
191 Inspection of heating and air conditioning units 5 days Mon 2/19/18 Fri 2/23/18 Fri 6/29/18 Thu 7/5/18 94 days 94 days 190SS
192 Install heating and air conditioning units (for each
room, elevator)
5 days Tue 4/10/18 Mon 4/16/18 Wed 5/23/18 Tue 5/29/18 0 days 31 days 189,232,240
193 30 day test of HVAC system 30 days Tue 4/17/18 Mon 5/28/18 Wed 6/27/18 Tue 8/7/18 11 days 51 days 192
194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days
216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days
224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
12/3
November 21
September 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
12/24 1/14 2/4 2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12 9/2 9/23 10/14 11/4 11/25 12/16 1/6 1/27
November 21 January 11 March 1 April 21 June 11 August 1 September 21 November 11 January 1
September 2017 January 2018 May 2018 September 2018 January 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
5/28
7/3
7/3
12/24 1/14 2/4 2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12 9/2 9/23 10/14 11/4 11/25 12/16 1/6 1/27
November 21 January 11 March 1 April 21 June 11 August 1 September 21 November 11 January 1
September 2017 January 2018 May 2018 September 2018 January 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days
176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days
194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days
195 Lighting fixtures, cables, cable trays get delivered on
site
5 days Mon 3/12/18 Fri 3/16/18 Wed 8/1/18 Tue 8/7/18 1 day 102 days 188
196 Inspection of delivered parts 5 days Tue 3/13/18 Mon 3/19/18 Fri 6/29/18 Thu 7/5/18 78 days 78 days 195SS,198FS-5 days
197 Install cable tray 4 days Mon 3/19/18 Thu 3/22/18 Tue 4/24/18 Fri 5/4/18 26 days 26 days
198 Install cable tray on Ground Floor 1 day Mon 3/19/18 Mon 3/19/18 Tue 4/24/18 Tue 4/24/18 0 days 26 days 186,189
199 Install cable tray on Mezzainine 0.5 days Tue 3/20/18 Tue 3/20/18 Fri 4/27/18 Fri 4/27/18 0.5 days 28.5 days 198,187
200 Install cable tray on Second Floor 1 day Wed 3/21/18 Wed 3/21/18 Tue 5/1/18 Tue 5/1/18 0 days 29 days 199,188
201 Install cable tray on Third Floor 1 day Thu 3/22/18 Thu 3/22/18 Fri 5/4/18 Fri 5/4/18 6 days 31 days 200,189
202 Route electrical connections 12 days Tue 3/20/18 Wed 4/4/18 Wed 4/25/18 Wed 5/9/18 25 days 25 days
203 Route connections on Ground Floor 3 days Tue 3/20/18 Thu 3/22/18 Wed 4/25/18 Fri 4/27/18 0 days 26 days 198
2/25
February 1
January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
204 Route connections on Mezzainine 2 days Mon 3/26/18 Tue 3/27/18 Mon 4/30/18 Tue 5/1/18 0 days 25 days 199,203
205 Route connections on Second Floor 3 days Wed 3/28/18 Fri 3/30/18 Wed 5/2/18 Fri 5/4/18 0 days 25 days 200,204
206 Route connections on Third Floor 3 days Mon 4/2/18 Wed 4/4/18 Mon 5/7/18 Wed 5/9/18 0 days 25 days 201,205
207 Label cables with asset tags and input into system 21 days Tue 3/20/18 Tue 4/17/18 Thu 6/7/18 Thu 7/5/18 57 days 57 days 203SS,206FF
208 Install electric boxes 2 days Tue 4/10/18 Wed 4/11/18 Tue 5/15/18 Wed 5/16/18 0 days 25 days 206,232,240
209 Install electric service panel 4 days Thu 4/12/18 Tue 4/17/18 Thu 5/17/18 Tue 5/22/18 0 days 25 days 208,232,240
210 Security cameras, sensors for lights and projectors
delivered on site
1 day Thu 4/12/18 Thu 4/12/18 Fri 5/18/18 Fri 5/18/18 0 days 26 days 208
211 Inspection of security and educational equipment 2 days Fri 4/13/18 Mon 4/16/18 Mon 5/21/18 Tue 5/22/18 1 day 26 days 210
212 Install security cameras, sensors for lights, projectors 5 days Wed 4/18/18 Tue 4/24/18 Wed 5/23/18 Tue 5/29/18 0 days 25 days 209,211
213 Connect electrical and SCADA cables with electric
boxes, lighting fixtures, heating unit, elevator unit
15 days Wed 4/25/18 Tue 5/15/18 Wed 5/30/18 Tue 6/19/18 0 days 25 days 208,209,212,192
214 Inspection of electrical and SCADA connections 5 days Wed 5/16/18 Tue 5/22/18 Wed 6/20/18 Tue 6/26/18 0 days 25 days 213
215 30 day testing of electrical system 30 days Wed 5/23/18 Tue 7/3/18 Wed 6/27/18 Tue 8/7/18 25 days 25 days 214
216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days
224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
2/25
February 1
January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2 12/16 12/30
March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1
March 2018 May 2018 July 2018 September 2018 November 2018 January 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7/3
7/3
7/3
3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2 12/16 12/30
March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1
March 2018 May 2018 July 2018 September 2018 November 2018 January 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days
176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days
194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days
216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days
217 Elevator equipment and parts delivered to site 0 days Wed 2/14/18 Wed 2/14/18 Mon 4/23/18 Mon 4/23/18 0 days 47 days 153
218 Inspection of equipment and parts 2 days Thu 2/15/18 Fri 2/16/18 Thu 5/24/18 Fri 5/25/18 0 days 70 days 217
219 Assemble and install elevator shaft 15 days Mon 2/19/18 Fri 3/9/18 Mon 5/28/18 Fri 6/15/18 0 days 70 days 218
220 Inspection of elevator shaft assembly 2 days Mon 3/12/18 Tue 3/13/18 Wed 5/16/18 Thu 5/17/18 30 days 47 days 153FF+5 days,219
221 Connect electrical and mechanical parts 3 days Wed 4/25/18 Fri 4/27/18 Fri 5/18/18 Tue 5/22/18 0 days 17 days 220,213SS
222 Inspection of elevator operations 2 days Mon 4/30/18 Tue 5/1/18 Mon 6/25/18 Tue 6/26/18 0 days 40 days 221
223 30 day test of elevators 30 days Wed 5/2/18 Tue 6/12/18 Fri 5/25/18 Thu 7/5/18 17 days 17 days 193FF,222
224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
1/14
January 1
January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
1/14
January 1
January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
2/14
6/12
7/3
1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2
January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1
January 2018 March 2018 May 2018 July 2018 September 2018 November 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7/3
1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2
January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1
January 2018 March 2018 May 2018 July 2018 September 2018 November 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
226 Drywall 15 days Mon 3/19/18 Fri 4/6/18 Fri 4/27/18 Fri 5/11/18 25 days 25 days
227 Delivery of drywall 0 days Mon 3/19/18 Mon 3/19/18 Tue 3/27/18 Tue 3/27/18 0 days 6 days 198SS
228 Install drywall 10 days Mon 3/26/18 Fri 4/6/18 Fri 5/4/18 Fri 5/11/18 25 days 25 days
229 Install drywall for Ground Floor 3 days Mon 3/26/18 Wed 3/28/18 Fri 5/4/18 Tue 5/8/18 4 days 29 days 168,186,203,227FS+5 days
230 Install drywall for Mezzainine 3 days Wed 3/28/18 Fri 3/30/18 Mon 5/7/18 Wed 5/9/18 3 days 28 days 169,187,204
231 Install drywall for Second Floor 3 days Mon 4/2/18 Wed 4/4/18 Tue 5/8/18 Thu 5/10/18 1 day 26 days 170,188,205
232 Install drywall for Third Floor 3 days Wed 4/4/18 Fri 4/6/18 Fri 4/6/18 Tue 4/10/18 0 days 2 days 171,189,206FS-1 day
233 Carpentry 16 days Mon 3/19/18 Mon 4/9/18 Wed 5/9/18 Tue 8/7/18 37 days 37 days
234 Windows, doors, cabintry delivered on site 0 days Mon 3/19/18 Mon 3/19/18 Wed 7/4/18 Wed 7/4/18 0 days 77 days 227
235 Inspection of parts 2 days Mon 3/19/18 Tue 3/20/18 Wed 7/4/18 Thu 7/5/18 77 days 77 days 234
236 Install windows, doors and cabintry 4 days Wed 4/4/18 Mon 4/9/18 Wed 5/9/18 Mon 5/14/18 25 days 25 days
237 Install Windows/Doors for Ground Floor 1 day Wed 4/4/18 Wed 4/4/18 Fri 4/6/18 Fri 4/6/18 0 days 2 days 229,232SS
3/19
3/19
T
Mar 11, '18
B
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
238 Install Windows/Doors for Mezzainine 1 day Thu 4/5/18 Thu 4/5/18 Thu 5/10/18 Thu 5/10/18 0 days 25 days 237,230
239 Install Windows/Doors for Second Floor 1 day Fri 4/6/18 Fri 4/6/18 Fri 5/11/18 Fri 5/11/18 0 days 25 days 238,231
240 Install Windows/Doors for Third Floor 1 day Mon 4/9/18 Mon 4/9/18 Mon 5/14/18 Mon 5/14/18 0 days 25 days 239,232
241 Insulation 15 days Mon 4/9/18 Fri 4/27/18 Wed 6/13/18 Tue 7/3/18 25 days 47 days
243 Paint (walls) 13 days Mon 4/30/18 Wed 5/16/18 Wed 7/4/18 Fri 7/20/18 12 days 47 days
247 Floor Finishes 15 days Mon 5/14/18 Fri 6/1/18 Wed 7/25/18 Wed 8/8/18 0 days 47 days
252 Trades Complete 0 days Fri 6/1/18 Fri 6/1/18 Fri 7/6/18 Fri 7/6/18 24 days 24 days 226FF,233FF,241FF,243FF,247FF
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
T
Mar 11, '18
B
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3/19
3/19
S W S T F M T S W S T F M T S W S T F M T
Mar 18, '18 Mar 25, '18 Apr 1, '18 Apr 8, '18 Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18
B E M B
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
S W S T F M T S W S T F M T S W S T F M T
Mar 18, '18 Mar 25, '18 Apr 1, '18 Apr 8, '18 Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18
B E M B
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
226 Drywall 15 days Mon 3/19/18 Fri 4/6/18 Fri 4/27/18 Fri 5/11/18 25 days 25 days
233 Carpentry 16 days Mon 3/19/18 Mon 4/9/18 Wed 5/9/18 Tue 8/7/18 37 days 37 days
241 Insulation 15 days Mon 4/9/18 Fri 4/27/18 Wed 6/13/18 Tue 7/3/18 25 days 47 days
242 Caulking, air sealing, and draft and fire stop 15 days Mon 4/9/18 Fri 4/27/18 Wed 6/13/18 Tue 7/3/18 0 days 47 days
243 Paint (walls) 13 days Mon 4/30/18 Wed 5/16/18 Wed 7/4/18 Fri 7/20/18 12 days 47 days
244 Prep drywall for prime coat 3 days Mon 4/30/18 Wed 5/2/18 Wed 7/4/18 Fri 7/6/18 0 days 47 days
245 Prime paint drywall 3 days Mon 5/7/18 Wed 5/9/18 Wed 7/11/18 Fri 7/13/18 0 days 47 days
246 Paint wall 3 days Mon 5/14/18 Wed 5/16/18 Wed 7/18/18 Fri 7/20/18 0 days 47 days
247 Floor Finishes 15 days Mon 5/14/18 Fri 6/1/18 Wed 7/25/18 Wed 8/8/18 0 days 47 days
248 Delivery of carpets 0 days Mon 5/14/18 Mon 5/14/18 Fri 7/6/18 Fri 7/6/18 0 days 39 days
249 Cleaning of floors 5 days Mon 5/21/18 Fri 5/25/18 Wed 7/25/18 Tue 7/31/18 0 days 47 days
250 Waxing of floors 2 days Mon 5/28/18 Tue 5/29/18 Wed 8/1/18 Thu 8/2/18 0 days 47 days
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
251 Installing carpets 3 days Wed 5/30/18 Fri 6/1/18 Fri 8/3/18 Tue 8/7/18 47 days 47 days
252 Trades Complete 0 days Fri 6/1/18 Fri 6/1/18 Fri 7/6/18 Fri 7/6/18 24 days 24 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
254 Landscaping 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 93 days 93 days
255 Sidewalks, ramps and stairs 10 days Mon 5/14/18 Fri 5/25/18 Mon 8/20/18 Fri 8/31/18 0 days 70 days
256 Handrails 1 day Mon 5/28/18 Mon 5/28/18 Wed 10/10/18 Wed 10/10/18 97 days 97 days
257 Plants 5 days Mon 5/28/18 Fri 6/1/18 Thu 10/4/18 Wed 10/10/18 93 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
Predecessors
82
83
232
242
244FS+2 days
245FS+2 days
249SS-5 days
246FS+2 days
249
5/14
T W T F S S M T W T F S S M T
Mar 18, '18 Apr 8, '18 Apr 29, '18 May 20, '18 Jun 10, '18 Jul 1, '18
B E M
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
Predecessors
250
226FF,233FF,241FF,243FF,247FF
248SS
255
255
85FF,253FF
6/1
7/3
T W T F S S M T W T F S S M T
Mar 18, '18 Apr 8, '18 Apr 29, '18 May 20, '18 Jun 10, '18 Jul 1, '18
B E M
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
260 Document and Stakeholder Control 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
261 Biweekly meetings with stakeholders and subcontractors 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 85SS
262 Confirm all documents (transmittals, change orders, shop
drawings, reports, manuals) are complete
600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 85SS
263 Total all change orders and submit to client as a report 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 85SS
264 Complete all deficiency items 60 days Wed 7/4/18 Tue 9/25/18 Fri 7/6/18 Thu 9/27/18 2 days 2 days 85
265 Cleaning of site and building 3 days Wed 7/4/18 Fri 7/6/18 Thu 9/6/18 Mon 9/10/18 0 days 46 days 85
266 Contractor final inspection of building 1 day Mon 7/9/18 Mon 7/9/18 Tue 9/11/18 Tue 9/11/18 0 days 46 days 265
267 City final inspection of building 1 day Tue 7/17/18 Tue 7/17/18 Wed 9/19/18 Wed 9/19/18 0 days 46 days 266FS+5 days
268 Issue City user and occupancy certificate 0 days Tue 8/7/18 Tue 8/7/18 Thu 10/11/18 Thu 10/11/18 0 days 46 days 267FS+15 days
269 Meet with client to confirm all requirements were tended to 1 day Wed 8/8/18 Wed 8/8/18 Thu 10/11/18 Thu 10/11/18 0 days 46 days 258,268
270 Meet and train operators on the functionality of building 5 days Thu 8/16/18 Wed 8/22/18 Fri 10/19/18 Thu 10/25/18 0 days 46 days 269FS+5 days
271 Demobilize site trailers 3 days Thu 8/23/18 Mon 8/27/18 Fri 10/26/18 Tue 10/30/18 46 days 46 days 270
272 Grand opening of Engineering Design Center 0 days Fri 9/7/18 Fri 9/7/18 Tue 10/30/18 Tue 10/30/18 38 days 38 days 267
3/13
September 1
July 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
8/7
9/7
6/19 9/25 1/1 4/9 7/16 10/22 1/28 5/6 8/12 11/18 2/24 6/2 9/8 12/15 3/22 6/28 10/4 1/10 4/18 7/25 10/31 2/6 5/15
March 21 October 11 May 1 November 21 June 11 January 1 July 21 February 11 September 1 March 21 October 11 May 1
July 2015 September 2016 November 2017 January 2019 March 2020 May 2021 July 2022
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15

More Related Content

Similar to Engineering Design Center Project Schedule

Rehoboth Beach City Hall Construction Schedule
Rehoboth Beach City Hall Construction ScheduleRehoboth Beach City Hall Construction Schedule
Rehoboth Beach City Hall Construction Schedulerehobothbeachde
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015) Ali Yousef
 
POW STTF 1 2023 (PT. SAM)NEW.pdf
POW STTF 1 2023 (PT. SAM)NEW.pdfPOW STTF 1 2023 (PT. SAM)NEW.pdf
POW STTF 1 2023 (PT. SAM)NEW.pdfSitiAuliaRamadhany1
 
Project management plan for Global Project Management Conference (GPM)
Project management plan for Global Project Management Conference (GPM)Project management plan for Global Project Management Conference (GPM)
Project management plan for Global Project Management Conference (GPM)Lúcia Dénis
 
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Encanex - Hebron  Access, Captens Brdidge, Power, Cement Barge and ICS Basket...Encanex - Hebron  Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...Ali Yousef
 
Presentation
PresentationPresentation
PresentationKrm Chari
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisDeborah Obasogie
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Ayon Pal
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis ayonpal
 
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptKingHaroldDeLeon
 
MOL Schedule about health and environment
MOL Schedule about health and environmentMOL Schedule about health and environment
MOL Schedule about health and environmentFasiullahShah1
 
Gant Chart - Wedding2
Gant Chart - Wedding2Gant Chart - Wedding2
Gant Chart - Wedding2Yarong Liu
 
Proposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdfProposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdfMarkGeraldCuadra1
 

Similar to Engineering Design Center Project Schedule (20)

Popop
PopopPopop
Popop
 
MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation Schedule
 
Rehoboth Beach City Hall Construction Schedule
Rehoboth Beach City Hall Construction ScheduleRehoboth Beach City Hall Construction Schedule
Rehoboth Beach City Hall Construction Schedule
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
 
Projec
ProjecProjec
Projec
 
WBS
WBSWBS
WBS
 
POW STTF 1 2023 (PT. SAM)NEW.pdf
POW STTF 1 2023 (PT. SAM)NEW.pdfPOW STTF 1 2023 (PT. SAM)NEW.pdf
POW STTF 1 2023 (PT. SAM)NEW.pdf
 
program
programprogram
program
 
Project management plan for Global Project Management Conference (GPM)
Project management plan for Global Project Management Conference (GPM)Project management plan for Global Project Management Conference (GPM)
Project management plan for Global Project Management Conference (GPM)
 
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Encanex - Hebron  Access, Captens Brdidge, Power, Cement Barge and ICS Basket...Encanex - Hebron  Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
 
Presentation
PresentationPresentation
Presentation
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis
 
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
 
MOL Schedule about health and environment
MOL Schedule about health and environmentMOL Schedule about health and environment
MOL Schedule about health and environment
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
Gant Chart - Wedding2
Gant Chart - Wedding2Gant Chart - Wedding2
Gant Chart - Wedding2
 
CPM
CPMCPM
CPM
 
Proposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdfProposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdf
 

Engineering Design Center Project Schedule

  • 1. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 3 Project Reinitiated 0 days Thu 1/1/15 Thu 1/1/15 Fri 8/3/18 Fri 8/3/18 2 days 937 days 4 Review technical, sustainability and program changes with team 5 days Mon 1/5/15 Fri 1/9/15 Fri 8/3/18 Thu 8/9/18 0 days 935 days 3 5 Project reinitiation meeting with client and stakeholders on any scope changes 1 day Mon 1/12/15 Mon 1/12/15 Fri 8/10/18 Fri 8/10/18 0 days 935 days 4 6 Edit design permit and tender drawings according to feedback 10 days Mon 1/12/15 Fri 1/23/15 Fri 8/10/18 Thu 8/23/18 0 days 935 days 5SS 7 Review safety by construction with electrical, mechanical, structural engineers 5 days Mon 1/26/15 Fri 1/30/15 Fri 8/31/18 Thu 9/6/18 0 days 940 days 6 8 Meeting with engineers and operation & mangament staff on safety by construction designs 1 day Mon 2/2/15 Mon 2/2/15 Fri 9/7/18 Fri 9/7/18 0 days 940 days 7 9 Edit design according to safety by construction review meeting 10 days Mon 2/2/15 Fri 2/13/15 Fri 9/7/18 Thu 9/20/18 0 days 940 days 8SS 10 Value engineering of design permit and tender drawings 5 days Mon 2/16/15 Fri 2/20/15 Fri 9/21/18 Thu 9/27/18 940 days 940 days 9 11 Meeting with value engineering group and review permit and tender drawings 1 day Mon 3/23/15 Mon 3/23/15 Fri 8/3/18 Fri 8/3/18 0 days 880 days 12 Edit design permit and tender drawings according to value engineering 10 days Mon 3/23/15 Fri 4/3/15 Fri 8/3/18 Thu 8/16/18 0 days 880 days 11SS 13 Review meeting with client and stakeholders on design changes 1 day Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 12 14 Design Complete 0 days Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 13SS 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 1/1 12/7 12/21 December 1 November 2014 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 1/1 4/6 12/21 1/4 1/18 2/1 2/15 3/1 3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1 November 2014 January 2015 March 2015 May 2015 July 2015 September 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days 17 Develop recommendation report to UBC Board of Governors 15 days Mon 1/26/15 Fri 2/13/15 Fri 8/24/18 Thu 9/13/18 9 days 935 days 6 18 Submit recommendation to UBC Board of Governors 0 days Fri 2/27/15 Fri 2/27/15 Fri 9/14/18 Fri 9/14/18 1 day 926 days 17 19 UBC Board of Governors review project recommendations 10 days Mon 3/2/15 Fri 3/13/15 Fri 9/14/18 Thu 9/27/18 0 days 925 days 18 20 Approval from UBC Board of Governors 0 days Mon 3/16/15 Mon 3/16/15 Thu 9/27/18 Thu 9/27/18 925 days 925 days 19 21 Submit construction permits from UBC 0 days Mon 4/6/15 Mon 4/6/15 Fri 9/14/18 Fri 9/14/18 0 days 900 days 14 22 UBC review construction permit 10 days Mon 4/6/15 Fri 4/17/15 Fri 9/14/18 Thu 9/27/18 0 days 900 days 21 23 Approval of construction permit from UBC 0 days Fri 4/17/15 Fri 4/17/15 Thu 9/27/18 Thu 9/27/18 900 days 900 days 22 24 Develop traffic control plans for the delivery of equipment and supplies for project 15 days Mon 7/13/15 Fri 7/31/15 Thu 5/10/18 Wed 5/30/18 0 days 739 days 47 25 Submit traffic control plans to UBC 0 days Fri 7/31/15 Fri 7/31/15 Thu 5/31/18 Thu 5/31/18 0 days 739 days 24 26 UBC review traffic control plans 10 days Mon 8/3/15 Fri 8/14/15 Thu 5/31/18 Wed 6/13/18 0 days 739 days 25 27 Approval from UBC on traffic control plans 0 days Fri 8/14/15 Fri 8/14/15 Thu 6/14/18 Thu 6/14/18 0 days 739 days 26 28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days 35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days 43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days 56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 12/28 1/18 December 21 September 2014 January 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 2/27 3/16 4/6 4/17 7/31 8/14 1/18 2/8 3/1 3/22 4/12 5/3 5/24 6/14 7/5 7/26 8/16 9/6 9/27 10/18 11/8 11/29 12/20 1/10 1/31 2/21 3/13 4/3 4/24 5/15 December 21 February 11 April 1 May 21 July 11 September 1 October 21 December 11 February 1 March 21 May 11 January 2015 May 2015 September 2015 January 2016 May 2016 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 2. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days 28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days 29 Submit construction permits from the City 0 days Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 14 30 City reviews construction permits 30 days Mon 4/6/15 Fri 5/15/15 Fri 8/17/18 Thu 9/27/18 0 days 880 days 29SS 31 Approval from City on Construction permits 0 days Fri 5/15/15 Fri 5/15/15 Thu 9/27/18 Thu 9/27/18 880 days 880 days 30 32 Submit file grading permit to City 0 days Fri 7/10/15 Fri 7/10/15 Fri 9/7/18 Fri 9/7/18 0 days 825 days 47 33 City reviews file grading permits 15 days Mon 7/13/15 Fri 7/31/15 Fri 9/7/18 Thu 9/27/18 0 days 825 days 32SS 34 Approval from City on file grading permits 0 days Fri 7/31/15 Fri 7/31/15 Thu 9/27/18 Thu 9/27/18 825 days 825 days 33 35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days 36 Issue Bid Proposal for Concrete Services 0 days Thu 4/9/15 Thu 4/9/15 Wed 2/7/18 Wed 2/7/18 0 days 740 days 37 Acquire proposals for concrete services 10 days Thu 4/9/15 Wed 4/22/15 Wed 2/7/18 Tue 2/20/18 0 days 740 days 36 38 Evaluation of proposals for concrete services 5 days Thu 4/23/15 Wed 4/29/15 Wed 2/21/18 Tue 2/27/18 1 day 740 days 37 39 Award concrete services to qualified contractors 0 days Fri 5/1/15 Fri 5/1/15 Wed 2/28/18 Wed 2/28/18 0 days 739 days 38 40 Schedule for Concrete supplies and services 15 days Mon 5/4/15 Fri 5/22/15 Wed 10/10/18 Tue 10/30/18 898 days 898 days 41 Order and schedule for steel rebar 15 days Mon 5/4/15 Fri 5/22/15 Fri 9/7/18 Thu 9/27/18 0 days 875 days 39 42 Order and schedule for concrete 15 days Mon 5/4/15 Fri 5/22/15 Fri 9/7/18 Thu 9/27/18 875 days 875 days 41SS 43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days 56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 3/1 March 1 March 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 4/6 5/15 7/10 7/31 4/9 5/1 3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 11/8 11/22 12/6 12/20 1/3 March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 March 2015 May 2015 July 2015 September 2015 November 2015 January 2016 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 3. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days 28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days 35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days 43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days 44 Acquire quotations from qualified suppliers (equipment, machinery, elevator, piping, cables, fixtures, duct, landscaping material) 15 days Fri 5/1/15 Thu 5/21/15 Wed 2/28/18 Tue 3/20/18 0 days 739 days 39 45 Evaluate subcontractor quotations 30 days Mon 5/4/15 Fri 6/12/15 Thu 3/1/18 Wed 4/11/18 0 days 739 days 44SS+1 day 46 Award contract for subcontractors to work on utility and trades work 5 days Mon 6/15/15 Fri 6/19/15 Thu 4/12/18 Wed 4/18/18 0 days 739 days 45 47 Schedule for subcontractor supplies and services 15 days Mon 6/22/15 Fri 7/10/15 Tue 5/22/18 Mon 6/11/18 0 days 762 days 48 Order and schedule for excavation machinery and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46 49 Order and schedule for elevator and necessary parts and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46 50 Order and schedule for HVAC parts and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46 51 Order and schedule for plumbing parts and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46 52 Order and schedule for electrical and SCADA cables and parts and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46 53 Order and schedule for drywall and paint and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46 54 Order and schedule for carpets, windows, frames, doors and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46 55 Order and schedule for landscapers and plants 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46 3/29 March 1 April 1 March 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 3/29 March 1 April 1 March 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 April 1 May 1 June 1 July 1 August 1 September 1 October 1 March 2015 May 2015 July 2015 September 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 April 1 May 1 June 1 July 1 August 1 September 1 October 1 March 2015 May 2015 July 2015 September 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 4. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days 28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days 35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days 43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days 56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days 57 Qualify contractors for Project 70 days Mon 6/22/15 Fri 9/25/15 Mon 6/4/18 Mon 8/27/18 762 days 762 days 58 Develop Request for Qualifications (RFQ) Specifications and Documents 31 days Mon 6/22/15 Mon 8/3/15 Mon 6/4/18 Tue 7/17/18 9 days 771 days 59 Meet with legal team to discuss details on RFQ 1 day Mon 6/22/15 Mon 6/22/15 Wed 5/2/18 Wed 5/2/18 0 days 748 days 47SS 60 Edit RFQ specifications according to legal team details 15 days Tue 6/23/15 Mon 7/13/15 Thu 5/3/18 Wed 5/23/18 0 days 748 days 59 61 Legal team reviews and makes changes to RFQ documents 15 days Tue 7/14/15 Mon 8/3/15 Thu 5/24/18 Wed 6/13/18 0 days 748 days 60 62 RFQ specifications and documents complete 0 days Mon 8/3/15 Mon 8/3/15 Thu 6/14/18 Thu 6/14/18 748 days 748 days 61 63 RFQ Opens 0 days Fri 8/14/15 Fri 8/14/15 Thu 6/14/18 Thu 6/14/18 0 days 739 days 27,58 64 Acquire RFQ 15 days Mon 8/17/15 Fri 9/4/15 Thu 6/14/18 Wed 7/4/18 0 days 739 days 63 65 RFQ Closes 0 days Fri 9/4/15 Fri 9/4/15 Thu 7/5/18 Thu 7/5/18 0 days 739 days 64 66 Evaluation of RFQs 10 days Mon 9/7/15 Fri 9/18/15 Thu 7/5/18 Wed 7/18/18 0 days 739 days 65 67 Create short list of contractors from evaluated RFQs 5 days Mon 9/21/15 Fri 9/25/15 Thu 7/19/18 Wed 7/25/18 0 days 739 days 66 68 Tender/Bid Project 155 days Mon 9/28/15 Mon 5/2/16 Tue 8/28/18 Tue 10/30/18 653 days 653 days 79 Meet with contractors to discuss construction and subcontractor details 1 day Mon 5/2/16 Mon 5/2/16 Thu 8/16/18 Thu 8/16/18 0 days 599 days 78 6/7 June 1 May 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 80 Review and edit costs, supply list, schedules and subcontractors and their qualifications 30 days Tue 5/3/16 Mon 6/13/16 Fri 8/17/18 Thu 9/27/18 599 days 599 days 79 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 6/7 June 1 May 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 8/3 8/14 9/4 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 11/8 11/22 12/6 12/20 1/3 1/17 1/31 2/14 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1 May 2015 July 2015 September 2015 November 2015 January 2016 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 11/8 11/22 12/6 12/20 1/3 1/17 1/31 2/14 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1 May 2015 July 2015 September 2015 November 2015 January 2016 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 5. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days 28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days 35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days 43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days 56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days 57 Qualify contractors for Project 70 days Mon 6/22/15 Fri 9/25/15 Mon 6/4/18 Mon 8/27/18 762 days 762 days 68 Tender/Bid Project 155 days Mon 9/28/15 Mon 5/2/16 Tue 8/28/18 Tue 10/30/18 653 days 653 days 69 Develop Tender Specifications and Documents 31 days Mon 9/28/15 Mon 11/9/15 Tue 8/28/18 Wed 10/10/18 79 days 762 days 70 Meet with legal team to discuss details on Tender Specifications 1 day Mon 9/28/15 Mon 9/28/15 Thu 7/26/18 Thu 7/26/18 0 days 739 days 67 71 Edit tender specifications according to legal team details 15 days Tue 9/29/15 Mon 10/19/15 Fri 7/27/18 Thu 8/16/18 0 days 739 days 70 72 Legal team reviews and makes changes to tender specifications documents 15 days Tue 10/20/15 Mon 11/9/15 Fri 8/17/18 Thu 9/6/18 0 days 739 days 71 73 Tender specifications and documents complete 0 days Mon 11/9/15 Mon 11/9/15 Fri 9/7/18 Fri 9/7/18 739 days 739 days 72 74 Bid Opens on BCBids 0 days Mon 2/29/16 Mon 2/29/16 Fri 9/7/18 Fri 9/7/18 0 days 660 days 27,69,66,76SS-15 days 75 Acquire Request for Proposal (RFP) for project construction 15 days Mon 2/29/16 Fri 3/18/16 Fri 9/7/18 Thu 9/27/18 660 days 660 days 74 76 Bid Closes 0 days Mon 3/21/16 Mon 3/21/16 Fri 8/17/18 Fri 8/17/18 0 days 630 days 78SS-30 days 77 Evaluation of Proposals for project construction 30 days Mon 3/21/16 Fri 4/29/16 Fri 8/17/18 Thu 9/27/18 630 days 630 days 76SS 78 Award project to qualified contractors 0 days Mon 5/2/16 Mon 5/2/16 Thu 8/16/18 Thu 8/16/18 0 days 599 days 79 Meet with contractors to discuss construction and subcontractor details 1 day Mon 5/2/16 Mon 5/2/16 Thu 8/16/18 Thu 8/16/18 0 days 599 days 78 8/30 July 1 September 1 May 2015 September 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 80 Review and edit costs, supply list, schedules and subcontractors and their qualifications 30 days Tue 5/3/16 Mon 6/13/16 Fri 8/17/18 Thu 9/27/18 599 days 599 days 79 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 8/30 July 1 September 1 May 2015 September 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 11/9 2/29 3/21 5/2 9/27 10/25 11/22 12/20 1/17 2/14 3/13 4/10 5/8 6/5 7/3 7/31 8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4 September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1 May 1 September 2015 January 2016 May 2016 September 2016 January 2017 May 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 9/27 10/25 11/22 12/20 1/17 2/14 3/13 4/10 5/8 6/5 7/3 7/31 8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4 September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1 May 1 September 2015 January 2016 May 2016 September 2016 January 2017 May 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 6. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days 83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82 84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83 85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days 88 Level Ground 10 days Wed 7/13/16 Tue 7/26/16 Fri 4/22/16 Thu 5/5/16 0 days -59 days 84 89 Bulk Excavate 30 days Wed 7/20/16 Tue 8/30/16 Fri 4/29/16 Thu 6/9/16 0 days -59 days 88FS-5 days 90 Excavate for Elevator 5 days Wed 7/27/16 Tue 8/2/16 Fri 6/3/16 Thu 6/9/16 0 days -39 days 89SS+5 days 91 Install Shoring 47 days Wed 8/31/16 Thu 11/3/16 Fri 6/10/16 Fri 8/12/16 0 days -59 days 89,90 92 Excavate Footings 25 days Fri 11/4/16 Thu 12/8/16 Mon 8/15/16 Fri 9/16/16 0 days -59 days 91 93 Loading of ground work 10 days Fri 12/9/16 Thu 12/22/16 Mon 9/19/16 Fri 9/30/16 0 days -59 days 92 94 Remove loadings 2 days Thu 12/22/16 Fri 12/23/16 Tue 2/7/17 Wed 2/8/17 0 days 33 days 93FS-1 day 95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days 111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days 124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days 137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days 150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days 156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF 7/4 6/5 May 11 May 2016 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days 225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days 253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days 258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 6/5 May 11 May 2016 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 7/4 6/26 7/17 8/7 8/28 9/18 10/9 10/30 11/20 12/11 1/1 1/22 2/12 3/5 3/26 4/16 5/7 5/28 6/18 7/9 7/30 8/20 May 11 July 1 August 21 October 11 December 1 January 21 March 11 May 1 June 21 August 11 May 2016 September 2016 January 2017 May 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 6/26 7/17 8/7 8/28 9/18 10/9 10/30 11/20 12/11 1/1 1/22 2/12 3/5 3/26 4/16 5/7 5/28 6/18 7/9 7/30 8/20 May 11 July 1 August 21 October 11 December 1 January 21 March 11 May 1 June 21 August 11 May 2016 September 2016 January 2017 May 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 7. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days 83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82 84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83 85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days 95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days 96 Foundations (Ground Floor) 127 days Mon 10/3/16 Tue 3/28/17 Mon 10/3/16 Fri 5/12/17 0 days 0 days 93 97 Steel rebars get delivered on site (stored offsite) 10 days Mon 10/3/16 Fri 10/14/16 Wed 7/25/18 Wed 8/8/18 472 days 472 days 92SS 98 Form Footings 35 days Fri 12/23/16 Thu 2/9/17 Wed 2/8/17 Tue 3/28/17 0 days 33 days 94FS-1 day 99 Install Reinforcing Steel Footings 15 days Fri 1/20/17 Thu 2/9/17 Wed 3/8/17 Tue 3/28/17 0 days 33 days 98FF 100 Footing inspections 2 days Fri 2/10/17 Mon 2/13/17 Wed 3/29/17 Thu 3/30/17 0 days 33 days 99 101 Place Concrete Footings 2 days Tue 2/14/17 Wed 2/15/17 Fri 3/31/17 Mon 4/3/17 0 days 33 days 100 102 Strip Forms for Footings 10 days Wed 2/15/17 Tue 2/28/17 Mon 4/3/17 Fri 4/14/17 0 days 33 days 101FS-1 day 103 Backfill footings 10 days Wed 3/1/17 Tue 3/14/17 Mon 4/17/17 Fri 4/28/17 0 days 33 days 102 104 Pour concrete for ground floor 10 days Wed 3/15/17 Tue 3/28/17 Mon 5/1/17 Fri 5/12/17 0 days 33 days 103 105 Interior Supports (Ground Floor) 31 days Wed 3/29/17 Wed 5/10/17 Mon 5/15/17 Mon 6/26/17 33 days 33 days 106 Form Supports 16 days Wed 3/29/17 Wed 4/19/17 Mon 5/15/17 Mon 6/5/17 0 days 33 days 104 107 Install Reinforcing Steel Supports 15 days Thu 3/30/17 Wed 4/19/17 Tue 5/16/17 Mon 6/5/17 0 days 33 days 98,106FF 7/4 7/31 July 1 May 2016 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 108 Support inspection 2 days Fri 4/21/17 Mon 4/24/17 Wed 6/7/17 Thu 6/8/17 0 days 33 days 107FS+1 day,106FS+1 day 109 Place Concrete Supports 2 days Tue 4/25/17 Wed 4/26/17 Fri 6/9/17 Mon 6/12/17 0 days 33 days 108 110 Strip forms for interior supports 10 days Thu 4/27/17 Wed 5/10/17 Tue 6/13/17 Mon 6/26/17 0 days 33 days 109 111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days 124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days 137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days 150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days 156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF 157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days 225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days 253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days 258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 7/31 July 1 May 2016 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 7/4 8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4 7/2 7/30 8/27 9/24 10/22 11/19 12/17 1/14 2/11 3/11 4/8 July 1 September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1 May 2016 September 2016 January 2017 May 2017 September 2017 January 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 3/2 7/3 8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4 7/2 7/30 8/27 9/24 10/22 11/19 12/17 1/14 2/11 3/11 4/8 July 1 September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1 May 2016 September 2016 January 2017 May 2017 September 2017 January 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 8. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days 83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82 84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83 85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days 95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days 111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days 112 Foundation (Mezzanine) 24 days Wed 5/10/17 Mon 6/12/17 Mon 6/26/17 Thu 7/27/17 33 days 33 days 113 Form Mezzanine Floor 15 days Wed 5/10/17 Tue 5/30/17 Mon 6/26/17 Fri 7/14/17 0 days 33 days 110FS-1 day 114 Install Reinforcing Steel for Mezzanine Floor 7 days Mon 5/22/17 Tue 5/30/17 Thu 7/6/17 Fri 7/14/17 0 days 33 days 110FS-5 days,113FF 115 Mezzanine Floor inspections 1 day Thu 6/1/17 Thu 6/1/17 Tue 7/18/17 Tue 7/18/17 0 days 33 days 114FS+1 day 116 Place Concrete for Mezzanine Floor 2 days Fri 6/2/17 Mon 6/5/17 Wed 7/19/17 Thu 7/20/17 0 days 33 days 115 117 Strip Forms for Mezzanine Floor 5 days Tue 6/6/17 Mon 6/12/17 Fri 7/21/17 Thu 7/27/17 0 days 33 days 116 118 Interior Supports (Mezzanine) 16 days Tue 6/13/17 Tue 7/4/17 Fri 7/28/17 Fri 8/18/17 33 days 33 days 119 Form Supports 7 days Tue 6/13/17 Wed 6/21/17 Fri 7/28/17 Mon 8/7/17 0 days 33 days 117 120 Install Reinforcing Steel Supports 7 days Tue 6/13/17 Wed 6/21/17 Fri 7/28/17 Mon 8/7/17 0 days 33 days 113,119FF 121 Support inspection 1 day Fri 6/23/17 Fri 6/23/17 Wed 8/9/17 Wed 8/9/17 0 days 33 days 120FS+1 day 122 Place Concrete Supports 2 days Mon 6/26/17 Tue 6/27/17 Thu 8/10/17 Fri 8/11/17 0 days 33 days 121 4/23 April Qtr 2, 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 123 Strip forms for interior supports 5 days Wed 6/28/17 Tue 7/4/17 Mon 8/14/17 Fri 8/18/17 0 days 33 days 122 124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days 137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days 150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days 156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF 157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days 225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days 253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days 258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 4/23 April Qtr 2, 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 4/30 5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 April May June July August September Qtr 2, 2017 Qtr 3, 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 4/30 5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24 April May June July August September Qtr 2, 2017 Qtr 3, 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 9. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days 83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82 84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83 85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days 95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days 111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days 124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days 125 Foundation (Second Floor) 35 days Wed 7/5/17 Tue 8/22/17 Mon 8/21/17 Fri 10/6/17 33 days 33 days 126 Form Second Floor 21 days Wed 7/5/17 Wed 8/2/17 Mon 8/21/17 Mon 9/18/17 0 days 33 days 123 127 Install Reinforcing Steel for Second Floor 15 days Thu 7/13/17 Wed 8/2/17 Tue 8/29/17 Mon 9/18/17 0 days 33 days 123FF-5 days,126FF 128 Second Floor inspections 2 days Thu 8/3/17 Fri 8/4/17 Tue 9/19/17 Wed 9/20/17 0 days 33 days 127,126 129 Place Concrete for Second Floor 2 days Mon 8/7/17 Tue 8/8/17 Thu 9/21/17 Fri 9/22/17 0 days 33 days 128 130 Strip Forms for Second Floor 10 days Wed 8/9/17 Tue 8/22/17 Mon 9/25/17 Fri 10/6/17 0 days 33 days 129 131 Interior Supports (Second) 30 days Wed 8/23/17 Tue 10/3/17 Mon 10/9/17 Fri 11/17/17 33 days 33 days 132 Form Supports 15 days Wed 8/23/17 Tue 9/12/17 Mon 10/9/17 Fri 10/27/17 0 days 33 days 130 133 Install Reinforcing Steel Supports 15 days Wed 8/23/17 Tue 9/12/17 Mon 10/9/17 Fri 10/27/17 0 days 33 days 132FF,126 134 Support inspection 2 days Thu 9/14/17 Fri 9/15/17 Tue 10/31/17 Wed 11/1/17 0 days 33 days 133FS+1 day,132FS+1 day 6/4 June 1 May 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 135 Place Concrete Supports 2 days Mon 9/18/17 Tue 9/19/17 Thu 11/2/17 Fri 11/3/17 0 days 33 days 134 136 Strip forms for interior supports 10 days Wed 9/20/17 Tue 10/3/17 Mon 11/6/17 Fri 11/17/17 0 days 33 days 135 137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days 150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days 156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF 157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days 225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days 253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days 258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 6/4 June 1 May 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 6/18 7/2 7/16 7/30 8/13 8/27 9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1 May 2017 July 2017 September 2017 November 2017 January 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 3/2 6/18 7/2 7/16 7/30 8/13 8/27 9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1 May 2017 July 2017 September 2017 November 2017 January 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 10. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days 83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82 84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83 85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days 95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days 111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days 124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days 137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days 138 Foundation (Third Floor) 35 days Wed 10/4/17 Tue 11/21/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days 139 Form Third Floor 21 days Wed 10/4/17 Wed 11/1/17 Mon 11/20/17 Mon 12/18/17 0 days 33 days 136 140 Install Reinforcing Steel for Third Floor 15 days Thu 10/12/17 Wed 11/1/17 Tue 11/28/17 Mon 12/18/17 0 days 33 days 139FF,135FF-5 days 141 Third Floor inspections 2 days Thu 11/2/17 Fri 11/3/17 Tue 12/19/17 Wed 12/20/17 0 days 33 days 140 142 Place Concrete for Third Floor 2 days Mon 11/6/17 Tue 11/7/17 Mon 7/23/18 Tue 7/24/18 0 days 185 days 141 143 Strip Forms for Third Floor 10 days Wed 11/8/17 Tue 11/21/17 Wed 7/25/18 Tue 8/7/18 185 days 185 days 142 144 Interior Supports (Third ) 36 days Mon 11/6/17 Mon 12/25/17 Thu 12/21/17 Tue 1/30/18 26 days 26 days 145 Form Supports 15 days Mon 11/6/17 Fri 11/24/17 Thu 12/21/17 Wed 1/10/18 0 days 33 days 141 146 Install Reinforcing Steel Supports 15 days Mon 11/6/17 Fri 11/24/17 Thu 12/21/17 Wed 1/10/18 0 days 33 days 139,145FF 8/27 August 1 July 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 147 Support inspection 2 days Mon 11/27/17 Tue 11/28/17 Thu 1/11/18 Fri 1/12/18 7 days 33 days 146 148 Place Concrete Supports 2 days Fri 12/8/17 Mon 12/11/17 Wed 12/13/17 Thu 12/14/17 0 days 3 days 147 149 Strip forms for interior supports 10 days Tue 12/12/17 Mon 12/25/17 Wed 1/17/18 Tue 1/30/18 0 days 26 days 148 150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days 156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF 157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days 225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days 253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days 258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 8/27 August 1 July 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 September 1 October 1 November 1 December 1 January 1 February 1 March 1 April 1 September 2017 November 2017 January 2018 March 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 3/2 9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 September 1 October 1 November 1 December 1 January 1 February 1 March 1 April 1 September 2017 November 2017 January 2018 March 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 11. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days 83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82 84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83 85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days 95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days 111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days 124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days 137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days 150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days 151 Form Roof 35 days Tue 12/26/17 Mon 2/12/18 Wed 1/31/18 Tue 3/20/18 0 days 26 days 149 152 Install Reinforcing Steel for Roof 15 days Tue 1/23/18 Mon 2/12/18 Mon 1/29/18 Fri 2/16/18 0 days 4 days 148FF-5 days,151FF 153 Roof inspections 2 days Tue 2/13/18 Wed 2/14/18 Thu 3/22/18 Fri 3/23/18 0 days 27 days 152,151 154 Place Concrete for Roof 2 days Fri 2/16/18 Mon 2/19/18 Mon 3/26/18 Tue 3/27/18 0 days 26 days 153 155 Strip Forms for Roof 10 days Mon 2/19/18 Fri 3/2/18 Thu 2/22/18 Wed 3/7/18 0 days 3 days 154FS-1 day 156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF 157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days 225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days 12/3 December 1 November 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days 258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 12/3 December 1 November 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 3/2 12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 December 1 January 1 February 1 March 1 April 1 May 1 June 1 November 2017 January 2018 March 2018 May 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 7/3 12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 December 1 January 1 February 1 March 1 April 1 May 1 June 1 November 2017 January 2018 March 2018 May 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 12. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days 83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82 84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83 85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days 158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days 159 Pipes get delivered to site (stored off site) 14 days Tue 12/26/17 Fri 1/12/18 Wed 3/7/18 Mon 3/26/18 0 days 51 days 149 160 Inspect pipe supplies 15 days Mon 12/25/17 Fri 1/12/18 Thu 2/1/18 Wed 2/21/18 0 days 28 days 159SS-1 day 161 Weld pipes together prior to installation 30 days Mon 1/1/18 Fri 2/9/18 Tue 3/13/18 Mon 4/23/18 25 days 51 days 160SS+5 days 162 Install pipes 18 days Mon 2/12/18 Wed 3/7/18 Tue 3/20/18 Thu 4/12/18 26 days 26 days 163 Install Pipes for Ground Floor 3 days Mon 2/12/18 Wed 2/14/18 Thu 2/15/18 Mon 2/19/18 0 days 3 days 152FS-5 days,151FS-1 day,123,161SS+5 days 164 Install Pipes for Mezzainine Floor 3 days Mon 2/19/18 Wed 2/21/18 Tue 3/27/18 Thu 3/29/18 0 days 26 days 168,136 165 Install Pipes for Second Floor 3 days Mon 2/26/18 Wed 2/28/18 Tue 4/3/18 Thu 4/5/18 0 days 26 days 169,149 166 Install Pipes for Third Floor 3 days Mon 3/5/18 Wed 3/7/18 Tue 4/10/18 Thu 4/12/18 0 days 26 days 170,155 167 Pipe inspections 17 days Thu 2/15/18 Fri 3/9/18 Fri 3/23/18 Mon 4/16/18 26 days 26 days 168 Pipe Inspection for Ground Floor 2 days Thu 2/15/18 Fri 2/16/18 Fri 3/23/18 Mon 3/26/18 0 days 26 days 163 169 Pipe Inspection for Mezzainine Floor 2 days Thu 2/22/18 Fri 2/23/18 Fri 3/30/18 Mon 4/2/18 0 days 26 days 164 170 Pipe Inspection for Second Floor 2 days Thu 3/1/18 Fri 3/2/18 Fri 4/6/18 Mon 4/9/18 0 days 26 days 165 12/3 December 1 November 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 171 Pipe Inspection for Third Floor 2 days Thu 3/8/18 Fri 3/9/18 Fri 4/13/18 Mon 4/16/18 0 days 26 days 166 172 Plumbing fixtures get delivered (toilets, sinks, drains, handrails, soap and paper towel dispensers) 5 days Mon 2/12/18 Fri 2/16/18 Fri 6/29/18 Thu 7/5/18 0 days 99 days 163SS 173 Inspection of plumbing fixtures 5 days Mon 2/12/18 Fri 2/16/18 Fri 6/29/18 Thu 7/5/18 99 days 99 days 172SS 174 Install plumbing fixtures 3 days Mon 3/12/18 Wed 3/14/18 Wed 8/1/18 Fri 8/3/18 0 days 102 days 171 175 Inspection of servicability of plumbing fixtures 2 days Thu 3/15/18 Fri 3/16/18 Mon 8/6/18 Tue 8/7/18 102 days 102 days 174 176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days 194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days 216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days 224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF 225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days 253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days 258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 12/3 December 1 November 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1 November 2017 January 2018 March 2018 May 2018 July 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 7/3 7/3 12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1 November 2017 January 2018 March 2018 May 2018 July 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 13. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days 83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82 84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83 85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days 158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days 176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days 177 Ducting, air vents, heating and air conditioning units get delivered on site 5 days Mon 12/25/17 Fri 12/29/17 Fri 6/29/18 Thu 7/5/18 134 days 134 days 178SS 178 Inspection of equipment and parts 30 days Mon 12/25/17 Fri 2/2/18 Fri 5/25/18 Thu 7/5/18 0 days 109 days 179FF-5 days 179 Weld ducting together 30 days Mon 1/1/18 Mon 2/12/18 Fri 5/25/18 Thu 7/5/18 0 days 104 days 181SF-5 days 180 Install ducting and air vents 18 days Mon 2/19/18 Wed 3/14/18 Tue 4/17/18 Thu 4/26/18 31 days 31 days 181 Install ducting and air vents (Ground Floor) 3 days Mon 2/19/18 Wed 2/21/18 Tue 4/17/18 Thu 4/19/18 0 days 41 days 168,123 182 Install ducting and air vents (Mezzainine Floor) 3 days Mon 2/26/18 Wed 2/28/18 Fri 4/20/18 Wed 4/25/18 0 days 39.5 days 169,136 183 Install ducting and air vents (Second Floor) 3 days Mon 3/5/18 Wed 3/7/18 Tue 4/24/18 Thu 4/26/18 0 days 36 days 170,149 184 Install ducting and air vents (Third Floor) 3 days Mon 3/12/18 Wed 3/14/18 Tue 4/17/18 Thu 4/19/18 0 days 26 days 171,155 185 Inspection of completed ducting and air vents 17 days Thu 2/22/18 Fri 3/16/18 Fri 4/20/18 Mon 4/30/18 31 days 31 days 12/3 November 21 September 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 186 HVAC Inspection of Ground Floor 2 days Thu 2/22/18 Fri 2/23/18 Fri 4/20/18 Mon 4/23/18 15 days 41 days 181 187 HVAC Inspection of Mezzainine Floor 2 days Thu 3/1/18 Fri 3/2/18 Wed 4/25/18 Fri 4/27/18 11 days 39.5 days 182 188 HVAC Inspection of Second Floor 2 days Thu 3/8/18 Fri 3/9/18 Fri 4/27/18 Mon 4/30/18 0 days 36 days 183 189 HVAC Inspection of Third Floor 2 days Thu 3/15/18 Fri 3/16/18 Fri 4/20/18 Mon 4/23/18 0 days 26 days 184 190 Heating and air conditioning units get delivered on site 5 days Mon 2/19/18 Fri 2/23/18 Fri 6/29/18 Thu 7/5/18 0 days 94 days 181SS 191 Inspection of heating and air conditioning units 5 days Mon 2/19/18 Fri 2/23/18 Fri 6/29/18 Thu 7/5/18 94 days 94 days 190SS 192 Install heating and air conditioning units (for each room, elevator) 5 days Tue 4/10/18 Mon 4/16/18 Wed 5/23/18 Tue 5/29/18 0 days 31 days 189,232,240 193 30 day test of HVAC system 30 days Tue 4/17/18 Mon 5/28/18 Wed 6/27/18 Tue 8/7/18 11 days 51 days 192 194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days 216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days 224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF 225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days 253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days 258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 12/3 November 21 September 2017 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 12/24 1/14 2/4 2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12 9/2 9/23 10/14 11/4 11/25 12/16 1/6 1/27 November 21 January 11 March 1 April 21 June 11 August 1 September 21 November 11 January 1 September 2017 January 2018 May 2018 September 2018 January 2019 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 5/28 7/3 7/3 12/24 1/14 2/4 2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12 9/2 9/23 10/14 11/4 11/25 12/16 1/6 1/27 November 21 January 11 March 1 April 21 June 11 August 1 September 21 November 11 January 1 September 2017 January 2018 May 2018 September 2018 January 2019 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 14. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days 83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82 84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83 85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days 158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days 176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days 194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days 195 Lighting fixtures, cables, cable trays get delivered on site 5 days Mon 3/12/18 Fri 3/16/18 Wed 8/1/18 Tue 8/7/18 1 day 102 days 188 196 Inspection of delivered parts 5 days Tue 3/13/18 Mon 3/19/18 Fri 6/29/18 Thu 7/5/18 78 days 78 days 195SS,198FS-5 days 197 Install cable tray 4 days Mon 3/19/18 Thu 3/22/18 Tue 4/24/18 Fri 5/4/18 26 days 26 days 198 Install cable tray on Ground Floor 1 day Mon 3/19/18 Mon 3/19/18 Tue 4/24/18 Tue 4/24/18 0 days 26 days 186,189 199 Install cable tray on Mezzainine 0.5 days Tue 3/20/18 Tue 3/20/18 Fri 4/27/18 Fri 4/27/18 0.5 days 28.5 days 198,187 200 Install cable tray on Second Floor 1 day Wed 3/21/18 Wed 3/21/18 Tue 5/1/18 Tue 5/1/18 0 days 29 days 199,188 201 Install cable tray on Third Floor 1 day Thu 3/22/18 Thu 3/22/18 Fri 5/4/18 Fri 5/4/18 6 days 31 days 200,189 202 Route electrical connections 12 days Tue 3/20/18 Wed 4/4/18 Wed 4/25/18 Wed 5/9/18 25 days 25 days 203 Route connections on Ground Floor 3 days Tue 3/20/18 Thu 3/22/18 Wed 4/25/18 Fri 4/27/18 0 days 26 days 198 2/25 February 1 January 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 204 Route connections on Mezzainine 2 days Mon 3/26/18 Tue 3/27/18 Mon 4/30/18 Tue 5/1/18 0 days 25 days 199,203 205 Route connections on Second Floor 3 days Wed 3/28/18 Fri 3/30/18 Wed 5/2/18 Fri 5/4/18 0 days 25 days 200,204 206 Route connections on Third Floor 3 days Mon 4/2/18 Wed 4/4/18 Mon 5/7/18 Wed 5/9/18 0 days 25 days 201,205 207 Label cables with asset tags and input into system 21 days Tue 3/20/18 Tue 4/17/18 Thu 6/7/18 Thu 7/5/18 57 days 57 days 203SS,206FF 208 Install electric boxes 2 days Tue 4/10/18 Wed 4/11/18 Tue 5/15/18 Wed 5/16/18 0 days 25 days 206,232,240 209 Install electric service panel 4 days Thu 4/12/18 Tue 4/17/18 Thu 5/17/18 Tue 5/22/18 0 days 25 days 208,232,240 210 Security cameras, sensors for lights and projectors delivered on site 1 day Thu 4/12/18 Thu 4/12/18 Fri 5/18/18 Fri 5/18/18 0 days 26 days 208 211 Inspection of security and educational equipment 2 days Fri 4/13/18 Mon 4/16/18 Mon 5/21/18 Tue 5/22/18 1 day 26 days 210 212 Install security cameras, sensors for lights, projectors 5 days Wed 4/18/18 Tue 4/24/18 Wed 5/23/18 Tue 5/29/18 0 days 25 days 209,211 213 Connect electrical and SCADA cables with electric boxes, lighting fixtures, heating unit, elevator unit 15 days Wed 4/25/18 Tue 5/15/18 Wed 5/30/18 Tue 6/19/18 0 days 25 days 208,209,212,192 214 Inspection of electrical and SCADA connections 5 days Wed 5/16/18 Tue 5/22/18 Wed 6/20/18 Tue 6/26/18 0 days 25 days 213 215 30 day testing of electrical system 30 days Wed 5/23/18 Tue 7/3/18 Wed 6/27/18 Tue 8/7/18 25 days 25 days 214 216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days 224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF 225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days 253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days 258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 2/25 February 1 January 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2 12/16 12/30 March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 March 2018 May 2018 July 2018 September 2018 November 2018 January 2019 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 7/3 7/3 7/3 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2 12/16 12/30 March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 March 2018 May 2018 July 2018 September 2018 November 2018 January 2019 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 15. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days 83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82 84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83 85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days 158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days 176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days 194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days 216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days 217 Elevator equipment and parts delivered to site 0 days Wed 2/14/18 Wed 2/14/18 Mon 4/23/18 Mon 4/23/18 0 days 47 days 153 218 Inspection of equipment and parts 2 days Thu 2/15/18 Fri 2/16/18 Thu 5/24/18 Fri 5/25/18 0 days 70 days 217 219 Assemble and install elevator shaft 15 days Mon 2/19/18 Fri 3/9/18 Mon 5/28/18 Fri 6/15/18 0 days 70 days 218 220 Inspection of elevator shaft assembly 2 days Mon 3/12/18 Tue 3/13/18 Wed 5/16/18 Thu 5/17/18 30 days 47 days 153FF+5 days,219 221 Connect electrical and mechanical parts 3 days Wed 4/25/18 Fri 4/27/18 Fri 5/18/18 Tue 5/22/18 0 days 17 days 220,213SS 222 Inspection of elevator operations 2 days Mon 4/30/18 Tue 5/1/18 Mon 6/25/18 Tue 6/26/18 0 days 40 days 221 223 30 day test of elevators 30 days Wed 5/2/18 Tue 6/12/18 Fri 5/25/18 Thu 7/5/18 17 days 17 days 193FF,222 224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF 225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days 1/14 January 1 January 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days 258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 1/14 January 1 January 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 2/14 6/12 7/3 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2 January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 2018 March 2018 May 2018 July 2018 September 2018 November 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 7/3 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2 January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 2018 March 2018 May 2018 July 2018 September 2018 November 2018 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 16. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days 83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82 84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83 85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days 225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days 226 Drywall 15 days Mon 3/19/18 Fri 4/6/18 Fri 4/27/18 Fri 5/11/18 25 days 25 days 227 Delivery of drywall 0 days Mon 3/19/18 Mon 3/19/18 Tue 3/27/18 Tue 3/27/18 0 days 6 days 198SS 228 Install drywall 10 days Mon 3/26/18 Fri 4/6/18 Fri 5/4/18 Fri 5/11/18 25 days 25 days 229 Install drywall for Ground Floor 3 days Mon 3/26/18 Wed 3/28/18 Fri 5/4/18 Tue 5/8/18 4 days 29 days 168,186,203,227FS+5 days 230 Install drywall for Mezzainine 3 days Wed 3/28/18 Fri 3/30/18 Mon 5/7/18 Wed 5/9/18 3 days 28 days 169,187,204 231 Install drywall for Second Floor 3 days Mon 4/2/18 Wed 4/4/18 Tue 5/8/18 Thu 5/10/18 1 day 26 days 170,188,205 232 Install drywall for Third Floor 3 days Wed 4/4/18 Fri 4/6/18 Fri 4/6/18 Tue 4/10/18 0 days 2 days 171,189,206FS-1 day 233 Carpentry 16 days Mon 3/19/18 Mon 4/9/18 Wed 5/9/18 Tue 8/7/18 37 days 37 days 234 Windows, doors, cabintry delivered on site 0 days Mon 3/19/18 Mon 3/19/18 Wed 7/4/18 Wed 7/4/18 0 days 77 days 227 235 Inspection of parts 2 days Mon 3/19/18 Tue 3/20/18 Wed 7/4/18 Thu 7/5/18 77 days 77 days 234 236 Install windows, doors and cabintry 4 days Wed 4/4/18 Mon 4/9/18 Wed 5/9/18 Mon 5/14/18 25 days 25 days 237 Install Windows/Doors for Ground Floor 1 day Wed 4/4/18 Wed 4/4/18 Fri 4/6/18 Fri 4/6/18 0 days 2 days 229,232SS 3/19 3/19 T Mar 11, '18 B Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 238 Install Windows/Doors for Mezzainine 1 day Thu 4/5/18 Thu 4/5/18 Thu 5/10/18 Thu 5/10/18 0 days 25 days 237,230 239 Install Windows/Doors for Second Floor 1 day Fri 4/6/18 Fri 4/6/18 Fri 5/11/18 Fri 5/11/18 0 days 25 days 238,231 240 Install Windows/Doors for Third Floor 1 day Mon 4/9/18 Mon 4/9/18 Mon 5/14/18 Mon 5/14/18 0 days 25 days 239,232 241 Insulation 15 days Mon 4/9/18 Fri 4/27/18 Wed 6/13/18 Tue 7/3/18 25 days 47 days 243 Paint (walls) 13 days Mon 4/30/18 Wed 5/16/18 Wed 7/4/18 Fri 7/20/18 12 days 47 days 247 Floor Finishes 15 days Mon 5/14/18 Fri 6/1/18 Wed 7/25/18 Wed 8/8/18 0 days 47 days 252 Trades Complete 0 days Fri 6/1/18 Fri 6/1/18 Fri 7/6/18 Fri 7/6/18 24 days 24 days 226FF,233FF,241FF,243FF,247FF 253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days 258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days T Mar 11, '18 B Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 3/19 3/19 S W S T F M T S W S T F M T S W S T F M T Mar 18, '18 Mar 25, '18 Apr 1, '18 Apr 8, '18 Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18 B E M B Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 S W S T F M T S W S T F M T S W S T F M T Mar 18, '18 Mar 25, '18 Apr 1, '18 Apr 8, '18 Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18 B E M B Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 17. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days 83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days 157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days 225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days 226 Drywall 15 days Mon 3/19/18 Fri 4/6/18 Fri 4/27/18 Fri 5/11/18 25 days 25 days 233 Carpentry 16 days Mon 3/19/18 Mon 4/9/18 Wed 5/9/18 Tue 8/7/18 37 days 37 days 241 Insulation 15 days Mon 4/9/18 Fri 4/27/18 Wed 6/13/18 Tue 7/3/18 25 days 47 days 242 Caulking, air sealing, and draft and fire stop 15 days Mon 4/9/18 Fri 4/27/18 Wed 6/13/18 Tue 7/3/18 0 days 47 days 243 Paint (walls) 13 days Mon 4/30/18 Wed 5/16/18 Wed 7/4/18 Fri 7/20/18 12 days 47 days 244 Prep drywall for prime coat 3 days Mon 4/30/18 Wed 5/2/18 Wed 7/4/18 Fri 7/6/18 0 days 47 days 245 Prime paint drywall 3 days Mon 5/7/18 Wed 5/9/18 Wed 7/11/18 Fri 7/13/18 0 days 47 days 246 Paint wall 3 days Mon 5/14/18 Wed 5/16/18 Wed 7/18/18 Fri 7/20/18 0 days 47 days 247 Floor Finishes 15 days Mon 5/14/18 Fri 6/1/18 Wed 7/25/18 Wed 8/8/18 0 days 47 days 248 Delivery of carpets 0 days Mon 5/14/18 Mon 5/14/18 Fri 7/6/18 Fri 7/6/18 0 days 39 days 249 Cleaning of floors 5 days Mon 5/21/18 Fri 5/25/18 Wed 7/25/18 Tue 7/31/18 0 days 47 days 250 Waxing of floors 2 days Mon 5/28/18 Tue 5/29/18 Wed 8/1/18 Thu 8/2/18 0 days 47 days Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack 251 Installing carpets 3 days Wed 5/30/18 Fri 6/1/18 Fri 8/3/18 Tue 8/7/18 47 days 47 days 252 Trades Complete 0 days Fri 6/1/18 Fri 6/1/18 Fri 7/6/18 Fri 7/6/18 24 days 24 days 253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days 254 Landscaping 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 93 days 93 days 255 Sidewalks, ramps and stairs 10 days Mon 5/14/18 Fri 5/25/18 Mon 8/20/18 Fri 8/31/18 0 days 70 days 256 Handrails 1 day Mon 5/28/18 Mon 5/28/18 Wed 10/10/18 Wed 10/10/18 97 days 97 days 257 Plants 5 days Mon 5/28/18 Fri 6/1/18 Thu 10/4/18 Wed 10/10/18 93 days 93 days 258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 Predecessors 82 83 232 242 244FS+2 days 245FS+2 days 249SS-5 days 246FS+2 days 249 5/14 T W T F S S M T W T F S S M T Mar 18, '18 Apr 8, '18 Apr 29, '18 May 20, '18 Jun 10, '18 Jul 1, '18 B E M Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 Predecessors 250 226FF,233FF,241FF,243FF,247FF 248SS 255 255 85FF,253FF 6/1 7/3 T W T F S S M T W T F S S M T Mar 18, '18 Apr 8, '18 Apr 29, '18 May 20, '18 Jun 10, '18 Jul 1, '18 B E M Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: EDC Project Final Ver 2 Date: Fri 4/3/15
  • 18. ID Task Name Duration Start Finish Late Start Late Finish Free Slack Total Slack Predecessors 1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days 2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days 15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days 81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days 259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 260 Document and Stakeholder Control 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 261 Biweekly meetings with stakeholders and subcontractors 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 85SS 262 Confirm all documents (transmittals, change orders, shop drawings, reports, manuals) are complete 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 85SS 263 Total all change orders and submit to client as a report 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 85SS 264 Complete all deficiency items 60 days Wed 7/4/18 Tue 9/25/18 Fri 7/6/18 Thu 9/27/18 2 days 2 days 85 265 Cleaning of site and building 3 days Wed 7/4/18 Fri 7/6/18 Thu 9/6/18 Mon 9/10/18 0 days 46 days 85 266 Contractor final inspection of building 1 day Mon 7/9/18 Mon 7/9/18 Tue 9/11/18 Tue 9/11/18 0 days 46 days 265 267 City final inspection of building 1 day Tue 7/17/18 Tue 7/17/18 Wed 9/19/18 Wed 9/19/18 0 days 46 days 266FS+5 days 268 Issue City user and occupancy certificate 0 days Tue 8/7/18 Tue 8/7/18 Thu 10/11/18 Thu 10/11/18 0 days 46 days 267FS+15 days 269 Meet with client to confirm all requirements were tended to 1 day Wed 8/8/18 Wed 8/8/18 Thu 10/11/18 Thu 10/11/18 0 days 46 days 258,268 270 Meet and train operators on the functionality of building 5 days Thu 8/16/18 Wed 8/22/18 Fri 10/19/18 Thu 10/25/18 0 days 46 days 269FS+5 days 271 Demobilize site trailers 3 days Thu 8/23/18 Mon 8/27/18 Fri 10/26/18 Tue 10/30/18 46 days 46 days 270 272 Grand opening of Engineering Design Center 0 days Fri 9/7/18 Fri 9/7/18 Tue 10/30/18 Tue 10/30/18 38 days 38 days 267 3/13 September 1 July 2015 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: EDC Project Final Ver 2 Date: Fri 4/3/15 8/7 9/7 6/19 9/25 1/1 4/9 7/16 10/22 1/28 5/6 8/12 11/18 2/24 6/2 9/8 12/15 3/22 6/28 10/4 1/10 4/18 7/25 10/31 2/6 5/15 March 21 October 11 May 1 November 21 June 11 January 1 July 21 February 11 September 1 March 21 October 11 May 1 July 2015 September 2016 November 2017 January 2019 March 2020 May 2021 July 2022 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: EDC Project Final Ver 2 Date: Fri 4/3/15