1. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
3 Project Reinitiated 0 days Thu 1/1/15 Thu 1/1/15 Fri 8/3/18 Fri 8/3/18 2 days 937 days
4 Review technical, sustainability and program changes with
team
5 days Mon 1/5/15 Fri 1/9/15 Fri 8/3/18 Thu 8/9/18 0 days 935 days 3
5 Project reinitiation meeting with client and stakeholders on
any scope changes
1 day Mon 1/12/15 Mon 1/12/15 Fri 8/10/18 Fri 8/10/18 0 days 935 days 4
6 Edit design permit and tender drawings according to
feedback
10 days Mon 1/12/15 Fri 1/23/15 Fri 8/10/18 Thu 8/23/18 0 days 935 days 5SS
7 Review safety by construction with electrical, mechanical,
structural engineers
5 days Mon 1/26/15 Fri 1/30/15 Fri 8/31/18 Thu 9/6/18 0 days 940 days 6
8 Meeting with engineers and operation & mangament staff
on safety by construction designs
1 day Mon 2/2/15 Mon 2/2/15 Fri 9/7/18 Fri 9/7/18 0 days 940 days 7
9 Edit design according to safety by construction review
meeting
10 days Mon 2/2/15 Fri 2/13/15 Fri 9/7/18 Thu 9/20/18 0 days 940 days 8SS
10 Value engineering of design permit and tender drawings 5 days Mon 2/16/15 Fri 2/20/15 Fri 9/21/18 Thu 9/27/18 940 days 940 days 9
11 Meeting with value engineering group and review permit
and tender drawings
1 day Mon 3/23/15 Mon 3/23/15 Fri 8/3/18 Fri 8/3/18 0 days 880 days
12 Edit design permit and tender drawings according to value
engineering
10 days Mon 3/23/15 Fri 4/3/15 Fri 8/3/18 Thu 8/16/18 0 days 880 days 11SS
13 Review meeting with client and stakeholders on design
changes
1 day Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 12
14 Design Complete 0 days Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 13SS
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
1/1
12/7 12/21
December 1
November 2014
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
1/1
4/6
12/21 1/4 1/18 2/1 2/15 3/1 3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13
December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1
November 2014 January 2015 March 2015 May 2015 July 2015 September 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days
17 Develop recommendation report to UBC Board of
Governors
15 days Mon 1/26/15 Fri 2/13/15 Fri 8/24/18 Thu 9/13/18 9 days 935 days 6
18 Submit recommendation to UBC Board of Governors 0 days Fri 2/27/15 Fri 2/27/15 Fri 9/14/18 Fri 9/14/18 1 day 926 days 17
19 UBC Board of Governors review project
recommendations
10 days Mon 3/2/15 Fri 3/13/15 Fri 9/14/18 Thu 9/27/18 0 days 925 days 18
20 Approval from UBC Board of Governors 0 days Mon 3/16/15 Mon 3/16/15 Thu 9/27/18 Thu 9/27/18 925 days 925 days 19
21 Submit construction permits from UBC 0 days Mon 4/6/15 Mon 4/6/15 Fri 9/14/18 Fri 9/14/18 0 days 900 days 14
22 UBC review construction permit 10 days Mon 4/6/15 Fri 4/17/15 Fri 9/14/18 Thu 9/27/18 0 days 900 days 21
23 Approval of construction permit from UBC 0 days Fri 4/17/15 Fri 4/17/15 Thu 9/27/18 Thu 9/27/18 900 days 900 days 22
24 Develop traffic control plans for the delivery of
equipment and supplies for project
15 days Mon 7/13/15 Fri 7/31/15 Thu 5/10/18 Wed 5/30/18 0 days 739 days 47
25 Submit traffic control plans to UBC 0 days Fri 7/31/15 Fri 7/31/15 Thu 5/31/18 Thu 5/31/18 0 days 739 days 24
26 UBC review traffic control plans 10 days Mon 8/3/15 Fri 8/14/15 Thu 5/31/18 Wed 6/13/18 0 days 739 days 25
27 Approval from UBC on traffic control plans 0 days Fri 8/14/15 Fri 8/14/15 Thu 6/14/18 Thu 6/14/18 0 days 739 days 26
28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days
35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days
43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days
56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
12/28 1/18
December 21
September 2014 January 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
2/27
3/16
4/6
4/17
7/31
8/14
1/18 2/8 3/1 3/22 4/12 5/3 5/24 6/14 7/5 7/26 8/16 9/6 9/27 10/18 11/8 11/29 12/20 1/10 1/31 2/21 3/13 4/3 4/24 5/15
December 21 February 11 April 1 May 21 July 11 September 1 October 21 December 11 February 1 March 21 May 11
January 2015 May 2015 September 2015 January 2016 May 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
2. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days
28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days
29 Submit construction permits from the City 0 days Mon 4/6/15 Mon 4/6/15 Fri 8/17/18 Fri 8/17/18 0 days 880 days 14
30 City reviews construction permits 30 days Mon 4/6/15 Fri 5/15/15 Fri 8/17/18 Thu 9/27/18 0 days 880 days 29SS
31 Approval from City on Construction permits 0 days Fri 5/15/15 Fri 5/15/15 Thu 9/27/18 Thu 9/27/18 880 days 880 days 30
32 Submit file grading permit to City 0 days Fri 7/10/15 Fri 7/10/15 Fri 9/7/18 Fri 9/7/18 0 days 825 days 47
33 City reviews file grading permits 15 days Mon 7/13/15 Fri 7/31/15 Fri 9/7/18 Thu 9/27/18 0 days 825 days 32SS
34 Approval from City on file grading permits 0 days Fri 7/31/15 Fri 7/31/15 Thu 9/27/18 Thu 9/27/18 825 days 825 days 33
35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days
36 Issue Bid Proposal for Concrete Services 0 days Thu 4/9/15 Thu 4/9/15 Wed 2/7/18 Wed 2/7/18 0 days 740 days
37 Acquire proposals for concrete services 10 days Thu 4/9/15 Wed 4/22/15 Wed 2/7/18 Tue 2/20/18 0 days 740 days 36
38 Evaluation of proposals for concrete services 5 days Thu 4/23/15 Wed 4/29/15 Wed 2/21/18 Tue 2/27/18 1 day 740 days 37
39 Award concrete services to qualified contractors 0 days Fri 5/1/15 Fri 5/1/15 Wed 2/28/18 Wed 2/28/18 0 days 739 days 38
40 Schedule for Concrete supplies and services 15 days Mon 5/4/15 Fri 5/22/15 Wed 10/10/18 Tue 10/30/18 898 days 898 days
41 Order and schedule for steel rebar 15 days Mon 5/4/15 Fri 5/22/15 Fri 9/7/18 Thu 9/27/18 0 days 875 days 39
42 Order and schedule for concrete 15 days Mon 5/4/15 Fri 5/22/15 Fri 9/7/18 Thu 9/27/18 875 days 875 days 41SS
43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days
56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
3/1
March 1
March 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
4/6
5/15
7/10
7/31
4/9
5/1
3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 11/8 11/22 12/6 12/20 1/3
March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1
March 2015 May 2015 July 2015 September 2015 November 2015 January 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days
28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days
35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days
43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days
44 Acquire quotations from qualified suppliers (equipment,
machinery, elevator, piping, cables, fixtures, duct,
landscaping material)
15 days Fri 5/1/15 Thu 5/21/15 Wed 2/28/18 Tue 3/20/18 0 days 739 days 39
45 Evaluate subcontractor quotations 30 days Mon 5/4/15 Fri 6/12/15 Thu 3/1/18 Wed 4/11/18 0 days 739 days 44SS+1 day
46 Award contract for subcontractors to work on utility and
trades work
5 days Mon 6/15/15 Fri 6/19/15 Thu 4/12/18 Wed 4/18/18 0 days 739 days 45
47 Schedule for subcontractor supplies and services 15 days Mon 6/22/15 Fri 7/10/15 Tue 5/22/18 Mon 6/11/18 0 days 762 days
48 Order and schedule for excavation machinery and
workers
15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
49 Order and schedule for elevator and necessary parts
and workers
15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
50 Order and schedule for HVAC parts and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
51 Order and schedule for plumbing parts and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
52 Order and schedule for electrical and SCADA cables
and parts and workers
15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
53 Order and schedule for drywall and paint and workers 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
54 Order and schedule for carpets, windows, frames,
doors and workers
15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
55 Order and schedule for landscapers and plants 15 days Mon 6/22/15 Fri 7/10/15 Thu 4/19/18 Wed 5/9/18 739 days 739 days 46
3/29
March 1 April 1
March 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
3/29
March 1 April 1
March 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25
April 1 May 1 June 1 July 1 August 1 September 1 October 1
March 2015 May 2015 July 2015 September 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
4/12 4/26 5/10 5/24 6/7 6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25
April 1 May 1 June 1 July 1 August 1 September 1 October 1
March 2015 May 2015 July 2015 September 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
4. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days
28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days
35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days
43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days
56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days
57 Qualify contractors for Project 70 days Mon 6/22/15 Fri 9/25/15 Mon 6/4/18 Mon 8/27/18 762 days 762 days
58 Develop Request for Qualifications (RFQ) Specifications and
Documents
31 days Mon 6/22/15 Mon 8/3/15 Mon 6/4/18 Tue 7/17/18 9 days 771 days
59 Meet with legal team to discuss details on RFQ 1 day Mon 6/22/15 Mon 6/22/15 Wed 5/2/18 Wed 5/2/18 0 days 748 days 47SS
60 Edit RFQ specifications according to legal team details 15 days Tue 6/23/15 Mon 7/13/15 Thu 5/3/18 Wed 5/23/18 0 days 748 days 59
61 Legal team reviews and makes changes to RFQ documents 15 days Tue 7/14/15 Mon 8/3/15 Thu 5/24/18 Wed 6/13/18 0 days 748 days 60
62 RFQ specifications and documents complete 0 days Mon 8/3/15 Mon 8/3/15 Thu 6/14/18 Thu 6/14/18 748 days 748 days 61
63 RFQ Opens 0 days Fri 8/14/15 Fri 8/14/15 Thu 6/14/18 Thu 6/14/18 0 days 739 days 27,58
64 Acquire RFQ 15 days Mon 8/17/15 Fri 9/4/15 Thu 6/14/18 Wed 7/4/18 0 days 739 days 63
65 RFQ Closes 0 days Fri 9/4/15 Fri 9/4/15 Thu 7/5/18 Thu 7/5/18 0 days 739 days 64
66 Evaluation of RFQs 10 days Mon 9/7/15 Fri 9/18/15 Thu 7/5/18 Wed 7/18/18 0 days 739 days 65
67 Create short list of contractors from evaluated RFQs 5 days Mon 9/21/15 Fri 9/25/15 Thu 7/19/18 Wed 7/25/18 0 days 739 days 66
68 Tender/Bid Project 155 days Mon 9/28/15 Mon 5/2/16 Tue 8/28/18 Tue 10/30/18 653 days 653 days
79 Meet with contractors to discuss construction and subcontractor
details
1 day Mon 5/2/16 Mon 5/2/16 Thu 8/16/18 Thu 8/16/18 0 days 599 days 78
6/7
June 1
May 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
80 Review and edit costs, supply list, schedules and subcontractors
and their qualifications
30 days Tue 5/3/16 Mon 6/13/16 Fri 8/17/18 Thu 9/27/18 599 days 599 days 79
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
6/7
June 1
May 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
8/3
8/14
9/4
6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 11/8 11/22 12/6 12/20 1/3 1/17 1/31 2/14
June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1
May 2015 July 2015 September 2015 November 2015 January 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
6/21 7/5 7/19 8/2 8/16 8/30 9/13 9/27 10/11 10/25 11/8 11/22 12/6 12/20 1/3 1/17 1/31 2/14
June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1
May 2015 July 2015 September 2015 November 2015 January 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
5. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
16 Documents/Permits to UBC 145 days Mon 1/26/15 Fri 8/14/15 Tue 6/12/18 Tue 10/30/18 838 days 838 days
28 Documents/Permits to City 85 days Mon 4/6/15 Fri 7/31/15 Wed 9/19/18 Tue 10/30/18 848 days 848 days
35 Concrete Services Acquisition 32 days Thu 4/9/15 Fri 5/22/15 Mon 3/12/18 Tue 10/30/18 763 days 763 days
43 Utility and Trades Services Acquisition 51 days Fri 5/1/15 Fri 7/10/15 Mon 4/2/18 Mon 6/11/18 762 days 762 days
56 Project Construction Services Acquisition 256 days Mon 6/22/15 Mon 6/13/16 Mon 6/4/18 Tue 10/30/18 622 days 622 days
57 Qualify contractors for Project 70 days Mon 6/22/15 Fri 9/25/15 Mon 6/4/18 Mon 8/27/18 762 days 762 days
68 Tender/Bid Project 155 days Mon 9/28/15 Mon 5/2/16 Tue 8/28/18 Tue 10/30/18 653 days 653 days
69 Develop Tender Specifications and Documents 31 days Mon 9/28/15 Mon 11/9/15 Tue 8/28/18 Wed 10/10/18 79 days 762 days
70 Meet with legal team to discuss details on Tender
Specifications
1 day Mon 9/28/15 Mon 9/28/15 Thu 7/26/18 Thu 7/26/18 0 days 739 days 67
71 Edit tender specifications according to legal team details 15 days Tue 9/29/15 Mon 10/19/15 Fri 7/27/18 Thu 8/16/18 0 days 739 days 70
72 Legal team reviews and makes changes to tender
specifications documents
15 days Tue 10/20/15 Mon 11/9/15 Fri 8/17/18 Thu 9/6/18 0 days 739 days 71
73 Tender specifications and documents complete 0 days Mon 11/9/15 Mon 11/9/15 Fri 9/7/18 Fri 9/7/18 739 days 739 days 72
74 Bid Opens on BCBids 0 days Mon 2/29/16 Mon 2/29/16 Fri 9/7/18 Fri 9/7/18 0 days 660 days 27,69,66,76SS-15 days
75 Acquire Request for Proposal (RFP) for project construction 15 days Mon 2/29/16 Fri 3/18/16 Fri 9/7/18 Thu 9/27/18 660 days 660 days 74
76 Bid Closes 0 days Mon 3/21/16 Mon 3/21/16 Fri 8/17/18 Fri 8/17/18 0 days 630 days 78SS-30 days
77 Evaluation of Proposals for project construction 30 days Mon 3/21/16 Fri 4/29/16 Fri 8/17/18 Thu 9/27/18 630 days 630 days 76SS
78 Award project to qualified contractors 0 days Mon 5/2/16 Mon 5/2/16 Thu 8/16/18 Thu 8/16/18 0 days 599 days
79 Meet with contractors to discuss construction and subcontractor
details
1 day Mon 5/2/16 Mon 5/2/16 Thu 8/16/18 Thu 8/16/18 0 days 599 days 78
8/30
July 1 September 1
May 2015 September 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
80 Review and edit costs, supply list, schedules and subcontractors
and their qualifications
30 days Tue 5/3/16 Mon 6/13/16 Fri 8/17/18 Thu 9/27/18 599 days 599 days 79
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
8/30
July 1 September 1
May 2015 September 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
11/9
2/29
3/21
5/2
9/27 10/25 11/22 12/20 1/17 2/14 3/13 4/10 5/8 6/5 7/3 7/31 8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4
September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1 May 1
September 2015 January 2016 May 2016 September 2016 January 2017 May 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
9/27 10/25 11/22 12/20 1/17 2/14 3/13 4/10 5/8 6/5 7/3 7/31 8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4
September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1 May 1
September 2015 January 2016 May 2016 September 2016 January 2017 May 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
6. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days
88 Level Ground 10 days Wed 7/13/16 Tue 7/26/16 Fri 4/22/16 Thu 5/5/16 0 days -59 days 84
89 Bulk Excavate 30 days Wed 7/20/16 Tue 8/30/16 Fri 4/29/16 Thu 6/9/16 0 days -59 days 88FS-5 days
90 Excavate for Elevator 5 days Wed 7/27/16 Tue 8/2/16 Fri 6/3/16 Thu 6/9/16 0 days -39 days 89SS+5 days
91 Install Shoring 47 days Wed 8/31/16 Thu 11/3/16 Fri 6/10/16 Fri 8/12/16 0 days -59 days 89,90
92 Excavate Footings 25 days Fri 11/4/16 Thu 12/8/16 Mon 8/15/16 Fri 9/16/16 0 days -59 days 91
93 Loading of ground work 10 days Fri 12/9/16 Thu 12/22/16 Mon 9/19/16 Fri 9/30/16 0 days -59 days 92
94 Remove loadings 2 days Thu 12/22/16 Fri 12/23/16 Tue 2/7/17 Wed 2/8/17 0 days 33 days 93FS-1 day
95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days
111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days
124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days
137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days
156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF
7/4
6/5
May 11
May 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
6/5
May 11
May 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7/4
6/26 7/17 8/7 8/28 9/18 10/9 10/30 11/20 12/11 1/1 1/22 2/12 3/5 3/26 4/16 5/7 5/28 6/18 7/9 7/30 8/20
May 11 July 1 August 21 October 11 December 1 January 21 March 11 May 1 June 21 August 11
May 2016 September 2016 January 2017 May 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
6/26 7/17 8/7 8/28 9/18 10/9 10/30 11/20 12/11 1/1 1/22 2/12 3/5 3/26 4/16 5/7 5/28 6/18 7/9 7/30 8/20
May 11 July 1 August 21 October 11 December 1 January 21 March 11 May 1 June 21 August 11
May 2016 September 2016 January 2017 May 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days
95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days
96 Foundations (Ground Floor) 127 days Mon 10/3/16 Tue 3/28/17 Mon 10/3/16 Fri 5/12/17 0 days 0 days 93
97 Steel rebars get delivered on site (stored offsite) 10 days Mon 10/3/16 Fri 10/14/16 Wed 7/25/18 Wed 8/8/18 472 days 472 days 92SS
98 Form Footings 35 days Fri 12/23/16 Thu 2/9/17 Wed 2/8/17 Tue 3/28/17 0 days 33 days 94FS-1 day
99 Install Reinforcing Steel Footings 15 days Fri 1/20/17 Thu 2/9/17 Wed 3/8/17 Tue 3/28/17 0 days 33 days 98FF
100 Footing inspections 2 days Fri 2/10/17 Mon 2/13/17 Wed 3/29/17 Thu 3/30/17 0 days 33 days 99
101 Place Concrete Footings 2 days Tue 2/14/17 Wed 2/15/17 Fri 3/31/17 Mon 4/3/17 0 days 33 days 100
102 Strip Forms for Footings 10 days Wed 2/15/17 Tue 2/28/17 Mon 4/3/17 Fri 4/14/17 0 days 33 days 101FS-1 day
103 Backfill footings 10 days Wed 3/1/17 Tue 3/14/17 Mon 4/17/17 Fri 4/28/17 0 days 33 days 102
104 Pour concrete for ground floor 10 days Wed 3/15/17 Tue 3/28/17 Mon 5/1/17 Fri 5/12/17 0 days 33 days 103
105 Interior Supports (Ground Floor) 31 days Wed 3/29/17 Wed 5/10/17 Mon 5/15/17 Mon 6/26/17 33 days 33 days
106 Form Supports 16 days Wed 3/29/17 Wed 4/19/17 Mon 5/15/17 Mon 6/5/17 0 days 33 days 104
107 Install Reinforcing Steel Supports 15 days Thu 3/30/17 Wed 4/19/17 Tue 5/16/17 Mon 6/5/17 0 days 33 days 98,106FF
7/4
7/31
July 1
May 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
108 Support inspection 2 days Fri 4/21/17 Mon 4/24/17 Wed 6/7/17 Thu 6/8/17 0 days 33 days 107FS+1 day,106FS+1 day
109 Place Concrete Supports 2 days Tue 4/25/17 Wed 4/26/17 Fri 6/9/17 Mon 6/12/17 0 days 33 days 108
110 Strip forms for interior supports 10 days Thu 4/27/17 Wed 5/10/17 Tue 6/13/17 Mon 6/26/17 0 days 33 days 109
111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days
124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days
137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days
156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
7/31
July 1
May 2016
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7/4
8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4 7/2 7/30 8/27 9/24 10/22 11/19 12/17 1/14 2/11 3/11 4/8
July 1 September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1
May 2016 September 2016 January 2017 May 2017 September 2017 January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3/2
7/3
8/28 9/25 10/23 11/20 12/18 1/15 2/12 3/12 4/9 5/7 6/4 7/2 7/30 8/27 9/24 10/22 11/19 12/17 1/14 2/11 3/11 4/8
July 1 September 1 November 1 January 1 March 1 May 1 July 1 September 1 November 1 January 1 March 1
May 2016 September 2016 January 2017 May 2017 September 2017 January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
8. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days
95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days
111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days
112 Foundation (Mezzanine) 24 days Wed 5/10/17 Mon 6/12/17 Mon 6/26/17 Thu 7/27/17 33 days 33 days
113 Form Mezzanine Floor 15 days Wed 5/10/17 Tue 5/30/17 Mon 6/26/17 Fri 7/14/17 0 days 33 days 110FS-1 day
114 Install Reinforcing Steel for Mezzanine Floor 7 days Mon 5/22/17 Tue 5/30/17 Thu 7/6/17 Fri 7/14/17 0 days 33 days 110FS-5 days,113FF
115 Mezzanine Floor inspections 1 day Thu 6/1/17 Thu 6/1/17 Tue 7/18/17 Tue 7/18/17 0 days 33 days 114FS+1 day
116 Place Concrete for Mezzanine Floor 2 days Fri 6/2/17 Mon 6/5/17 Wed 7/19/17 Thu 7/20/17 0 days 33 days 115
117 Strip Forms for Mezzanine Floor 5 days Tue 6/6/17 Mon 6/12/17 Fri 7/21/17 Thu 7/27/17 0 days 33 days 116
118 Interior Supports (Mezzanine) 16 days Tue 6/13/17 Tue 7/4/17 Fri 7/28/17 Fri 8/18/17 33 days 33 days
119 Form Supports 7 days Tue 6/13/17 Wed 6/21/17 Fri 7/28/17 Mon 8/7/17 0 days 33 days 117
120 Install Reinforcing Steel Supports 7 days Tue 6/13/17 Wed 6/21/17 Fri 7/28/17 Mon 8/7/17 0 days 33 days 113,119FF
121 Support inspection 1 day Fri 6/23/17 Fri 6/23/17 Wed 8/9/17 Wed 8/9/17 0 days 33 days 120FS+1 day
122 Place Concrete Supports 2 days Mon 6/26/17 Tue 6/27/17 Thu 8/10/17 Fri 8/11/17 0 days 33 days 121
4/23
April
Qtr 2, 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
123 Strip forms for interior supports 5 days Wed 6/28/17 Tue 7/4/17 Mon 8/14/17 Fri 8/18/17 0 days 33 days 122
124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days
137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days
156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
4/23
April
Qtr 2, 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
4/30 5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24
April May June July August September
Qtr 2, 2017 Qtr 3, 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
4/30 5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17 9/24
April May June July August September
Qtr 2, 2017 Qtr 3, 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
9. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days
95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days
111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days
124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days
125 Foundation (Second Floor) 35 days Wed 7/5/17 Tue 8/22/17 Mon 8/21/17 Fri 10/6/17 33 days 33 days
126 Form Second Floor 21 days Wed 7/5/17 Wed 8/2/17 Mon 8/21/17 Mon 9/18/17 0 days 33 days 123
127 Install Reinforcing Steel for Second Floor 15 days Thu 7/13/17 Wed 8/2/17 Tue 8/29/17 Mon 9/18/17 0 days 33 days 123FF-5 days,126FF
128 Second Floor inspections 2 days Thu 8/3/17 Fri 8/4/17 Tue 9/19/17 Wed 9/20/17 0 days 33 days 127,126
129 Place Concrete for Second Floor 2 days Mon 8/7/17 Tue 8/8/17 Thu 9/21/17 Fri 9/22/17 0 days 33 days 128
130 Strip Forms for Second Floor 10 days Wed 8/9/17 Tue 8/22/17 Mon 9/25/17 Fri 10/6/17 0 days 33 days 129
131 Interior Supports (Second) 30 days Wed 8/23/17 Tue 10/3/17 Mon 10/9/17 Fri 11/17/17 33 days 33 days
132 Form Supports 15 days Wed 8/23/17 Tue 9/12/17 Mon 10/9/17 Fri 10/27/17 0 days 33 days 130
133 Install Reinforcing Steel Supports 15 days Wed 8/23/17 Tue 9/12/17 Mon 10/9/17 Fri 10/27/17 0 days 33 days 132FF,126
134 Support inspection 2 days Thu 9/14/17 Fri 9/15/17 Tue 10/31/17 Wed 11/1/17 0 days 33 days 133FS+1 day,132FS+1 day
6/4
June 1
May 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
135 Place Concrete Supports 2 days Mon 9/18/17 Tue 9/19/17 Thu 11/2/17 Fri 11/3/17 0 days 33 days 134
136 Strip forms for interior supports 10 days Wed 9/20/17 Tue 10/3/17 Mon 11/6/17 Fri 11/17/17 0 days 33 days 135
137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days
156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
6/4
June 1
May 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
6/18 7/2 7/16 7/30 8/13 8/27 9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25
June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1
May 2017 July 2017 September 2017 November 2017 January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3/2
6/18 7/2 7/16 7/30 8/13 8/27 9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25
June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1 February 1
May 2017 July 2017 September 2017 November 2017 January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
10. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days
95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days
111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days
124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days
137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
138 Foundation (Third Floor) 35 days Wed 10/4/17 Tue 11/21/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
139 Form Third Floor 21 days Wed 10/4/17 Wed 11/1/17 Mon 11/20/17 Mon 12/18/17 0 days 33 days 136
140 Install Reinforcing Steel for Third Floor 15 days Thu 10/12/17 Wed 11/1/17 Tue 11/28/17 Mon 12/18/17 0 days 33 days 139FF,135FF-5 days
141 Third Floor inspections 2 days Thu 11/2/17 Fri 11/3/17 Tue 12/19/17 Wed 12/20/17 0 days 33 days 140
142 Place Concrete for Third Floor 2 days Mon 11/6/17 Tue 11/7/17 Mon 7/23/18 Tue 7/24/18 0 days 185 days 141
143 Strip Forms for Third Floor 10 days Wed 11/8/17 Tue 11/21/17 Wed 7/25/18 Tue 8/7/18 185 days 185 days 142
144 Interior Supports (Third ) 36 days Mon 11/6/17 Mon 12/25/17 Thu 12/21/17 Tue 1/30/18 26 days 26 days
145 Form Supports 15 days Mon 11/6/17 Fri 11/24/17 Thu 12/21/17 Wed 1/10/18 0 days 33 days 141
146 Install Reinforcing Steel Supports 15 days Mon 11/6/17 Fri 11/24/17 Thu 12/21/17 Wed 1/10/18 0 days 33 days 139,145FF
8/27
August 1
July 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
147 Support inspection 2 days Mon 11/27/17 Tue 11/28/17 Thu 1/11/18 Fri 1/12/18 7 days 33 days 146
148 Place Concrete Supports 2 days Fri 12/8/17 Mon 12/11/17 Wed 12/13/17 Thu 12/14/17 0 days 3 days 147
149 Strip forms for interior supports 10 days Tue 12/12/17 Mon 12/25/17 Wed 1/17/18 Tue 1/30/18 0 days 26 days 148
150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days
156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
8/27
August 1
July 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8
September 1 October 1 November 1 December 1 January 1 February 1 March 1 April 1
September 2017 November 2017 January 2018 March 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3/2
9/10 9/24 10/8 10/22 11/5 11/19 12/3 12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8
September 1 October 1 November 1 December 1 January 1 February 1 March 1 April 1
September 2017 November 2017 January 2018 March 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
11. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
87 Ground Work 118 days Wed 7/13/16 Fri 12/23/16 Fri 4/22/16 Wed 2/8/17 0 days -59 days
95 Ground Floor 158 days Mon 10/3/16 Wed 5/10/17 Mon 10/3/16 Mon 6/26/17 0 days 0 days
111 Mezzanine 40 days Wed 5/10/17 Tue 7/4/17 Mon 6/26/17 Fri 8/18/17 33 days 33 days
124 Second Floor 65 days Wed 7/5/17 Tue 10/3/17 Mon 8/21/17 Fri 11/17/17 33 days 33 days
137 Third Floor 59 days Wed 10/4/17 Mon 12/25/17 Mon 11/20/17 Tue 8/7/18 33 days 33 days
150 Roof 49 days Tue 12/26/17 Fri 3/2/18 Wed 1/31/18 Mon 4/9/18 26 days 26 days
151 Form Roof 35 days Tue 12/26/17 Mon 2/12/18 Wed 1/31/18 Tue 3/20/18 0 days 26 days 149
152 Install Reinforcing Steel for Roof 15 days Tue 1/23/18 Mon 2/12/18 Mon 1/29/18 Fri 2/16/18 0 days 4 days 148FF-5 days,151FF
153 Roof inspections 2 days Tue 2/13/18 Wed 2/14/18 Thu 3/22/18 Fri 3/23/18 0 days 27 days 152,151
154 Place Concrete for Roof 2 days Fri 2/16/18 Mon 2/19/18 Mon 3/26/18 Tue 3/27/18 0 days 26 days 153
155 Strip Forms for Roof 10 days Mon 2/19/18 Fri 3/2/18 Thu 2/22/18 Wed 3/7/18 0 days 3 days 154FS-1 day
156 Structural Construction Complete 0 days Fri 3/2/18 Fri 3/2/18 Wed 8/8/18 Wed 8/8/18 112 days 112 days 155FF
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
12/3
December 1
November 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
12/3
December 1
November 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3/2
12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17
December 1 January 1 February 1 March 1 April 1 May 1 June 1
November 2017 January 2018 March 2018 May 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7/3
12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17
December 1 January 1 February 1 March 1 April 1 May 1 June 1
November 2017 January 2018 March 2018 May 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
12. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days
159 Pipes get delivered to site (stored off site) 14 days Tue 12/26/17 Fri 1/12/18 Wed 3/7/18 Mon 3/26/18 0 days 51 days 149
160 Inspect pipe supplies 15 days Mon 12/25/17 Fri 1/12/18 Thu 2/1/18 Wed 2/21/18 0 days 28 days 159SS-1 day
161 Weld pipes together prior to installation 30 days Mon 1/1/18 Fri 2/9/18 Tue 3/13/18 Mon 4/23/18 25 days 51 days 160SS+5 days
162 Install pipes 18 days Mon 2/12/18 Wed 3/7/18 Tue 3/20/18 Thu 4/12/18 26 days 26 days
163 Install Pipes for Ground Floor 3 days Mon 2/12/18 Wed 2/14/18 Thu 2/15/18 Mon 2/19/18 0 days 3 days 152FS-5 days,151FS-1 day,123,161SS+5 days
164 Install Pipes for Mezzainine Floor 3 days Mon 2/19/18 Wed 2/21/18 Tue 3/27/18 Thu 3/29/18 0 days 26 days 168,136
165 Install Pipes for Second Floor 3 days Mon 2/26/18 Wed 2/28/18 Tue 4/3/18 Thu 4/5/18 0 days 26 days 169,149
166 Install Pipes for Third Floor 3 days Mon 3/5/18 Wed 3/7/18 Tue 4/10/18 Thu 4/12/18 0 days 26 days 170,155
167 Pipe inspections 17 days Thu 2/15/18 Fri 3/9/18 Fri 3/23/18 Mon 4/16/18 26 days 26 days
168 Pipe Inspection for Ground Floor 2 days Thu 2/15/18 Fri 2/16/18 Fri 3/23/18 Mon 3/26/18 0 days 26 days 163
169 Pipe Inspection for Mezzainine Floor 2 days Thu 2/22/18 Fri 2/23/18 Fri 3/30/18 Mon 4/2/18 0 days 26 days 164
170 Pipe Inspection for Second Floor 2 days Thu 3/1/18 Fri 3/2/18 Fri 4/6/18 Mon 4/9/18 0 days 26 days 165
12/3
December 1
November 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
171 Pipe Inspection for Third Floor 2 days Thu 3/8/18 Fri 3/9/18 Fri 4/13/18 Mon 4/16/18 0 days 26 days 166
172 Plumbing fixtures get delivered (toilets, sinks, drains,
handrails, soap and paper towel dispensers)
5 days Mon 2/12/18 Fri 2/16/18 Fri 6/29/18 Thu 7/5/18 0 days 99 days 163SS
173 Inspection of plumbing fixtures 5 days Mon 2/12/18 Fri 2/16/18 Fri 6/29/18 Thu 7/5/18 99 days 99 days 172SS
174 Install plumbing fixtures 3 days Mon 3/12/18 Wed 3/14/18 Wed 8/1/18 Fri 8/3/18 0 days 102 days 171
175 Inspection of servicability of plumbing fixtures 2 days Thu 3/15/18 Fri 3/16/18 Mon 8/6/18 Tue 8/7/18 102 days 102 days 174
176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days
194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days
216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days
224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
12/3
December 1
November 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15
December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1
November 2017 January 2018 March 2018 May 2018 July 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7/3
7/3
12/17 12/31 1/14 1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15
December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1
November 2017 January 2018 March 2018 May 2018 July 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
13. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days
176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days
177 Ducting, air vents, heating and air conditioning units
get delivered on site
5 days Mon 12/25/17 Fri 12/29/17 Fri 6/29/18 Thu 7/5/18 134 days 134 days 178SS
178 Inspection of equipment and parts 30 days Mon 12/25/17 Fri 2/2/18 Fri 5/25/18 Thu 7/5/18 0 days 109 days 179FF-5 days
179 Weld ducting together 30 days Mon 1/1/18 Mon 2/12/18 Fri 5/25/18 Thu 7/5/18 0 days 104 days 181SF-5 days
180 Install ducting and air vents 18 days Mon 2/19/18 Wed 3/14/18 Tue 4/17/18 Thu 4/26/18 31 days 31 days
181 Install ducting and air vents (Ground Floor) 3 days Mon 2/19/18 Wed 2/21/18 Tue 4/17/18 Thu 4/19/18 0 days 41 days 168,123
182 Install ducting and air vents (Mezzainine Floor) 3 days Mon 2/26/18 Wed 2/28/18 Fri 4/20/18 Wed 4/25/18 0 days 39.5 days 169,136
183 Install ducting and air vents (Second Floor) 3 days Mon 3/5/18 Wed 3/7/18 Tue 4/24/18 Thu 4/26/18 0 days 36 days 170,149
184 Install ducting and air vents (Third Floor) 3 days Mon 3/12/18 Wed 3/14/18 Tue 4/17/18 Thu 4/19/18 0 days 26 days 171,155
185 Inspection of completed ducting and air vents 17 days Thu 2/22/18 Fri 3/16/18 Fri 4/20/18 Mon 4/30/18 31 days 31 days
12/3
November 21
September 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
186 HVAC Inspection of Ground Floor 2 days Thu 2/22/18 Fri 2/23/18 Fri 4/20/18 Mon 4/23/18 15 days 41 days 181
187 HVAC Inspection of Mezzainine Floor 2 days Thu 3/1/18 Fri 3/2/18 Wed 4/25/18 Fri 4/27/18 11 days 39.5 days 182
188 HVAC Inspection of Second Floor 2 days Thu 3/8/18 Fri 3/9/18 Fri 4/27/18 Mon 4/30/18 0 days 36 days 183
189 HVAC Inspection of Third Floor 2 days Thu 3/15/18 Fri 3/16/18 Fri 4/20/18 Mon 4/23/18 0 days 26 days 184
190 Heating and air conditioning units get delivered on site 5 days Mon 2/19/18 Fri 2/23/18 Fri 6/29/18 Thu 7/5/18 0 days 94 days 181SS
191 Inspection of heating and air conditioning units 5 days Mon 2/19/18 Fri 2/23/18 Fri 6/29/18 Thu 7/5/18 94 days 94 days 190SS
192 Install heating and air conditioning units (for each
room, elevator)
5 days Tue 4/10/18 Mon 4/16/18 Wed 5/23/18 Tue 5/29/18 0 days 31 days 189,232,240
193 30 day test of HVAC system 30 days Tue 4/17/18 Mon 5/28/18 Wed 6/27/18 Tue 8/7/18 11 days 51 days 192
194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days
216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days
224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
12/3
November 21
September 2017
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
12/24 1/14 2/4 2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12 9/2 9/23 10/14 11/4 11/25 12/16 1/6 1/27
November 21 January 11 March 1 April 21 June 11 August 1 September 21 November 11 January 1
September 2017 January 2018 May 2018 September 2018 January 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
5/28
7/3
7/3
12/24 1/14 2/4 2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12 9/2 9/23 10/14 11/4 11/25 12/16 1/6 1/27
November 21 January 11 March 1 April 21 June 11 August 1 September 21 November 11 January 1
September 2017 January 2018 May 2018 September 2018 January 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
14. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days
176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days
194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days
195 Lighting fixtures, cables, cable trays get delivered on
site
5 days Mon 3/12/18 Fri 3/16/18 Wed 8/1/18 Tue 8/7/18 1 day 102 days 188
196 Inspection of delivered parts 5 days Tue 3/13/18 Mon 3/19/18 Fri 6/29/18 Thu 7/5/18 78 days 78 days 195SS,198FS-5 days
197 Install cable tray 4 days Mon 3/19/18 Thu 3/22/18 Tue 4/24/18 Fri 5/4/18 26 days 26 days
198 Install cable tray on Ground Floor 1 day Mon 3/19/18 Mon 3/19/18 Tue 4/24/18 Tue 4/24/18 0 days 26 days 186,189
199 Install cable tray on Mezzainine 0.5 days Tue 3/20/18 Tue 3/20/18 Fri 4/27/18 Fri 4/27/18 0.5 days 28.5 days 198,187
200 Install cable tray on Second Floor 1 day Wed 3/21/18 Wed 3/21/18 Tue 5/1/18 Tue 5/1/18 0 days 29 days 199,188
201 Install cable tray on Third Floor 1 day Thu 3/22/18 Thu 3/22/18 Fri 5/4/18 Fri 5/4/18 6 days 31 days 200,189
202 Route electrical connections 12 days Tue 3/20/18 Wed 4/4/18 Wed 4/25/18 Wed 5/9/18 25 days 25 days
203 Route connections on Ground Floor 3 days Tue 3/20/18 Thu 3/22/18 Wed 4/25/18 Fri 4/27/18 0 days 26 days 198
2/25
February 1
January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
204 Route connections on Mezzainine 2 days Mon 3/26/18 Tue 3/27/18 Mon 4/30/18 Tue 5/1/18 0 days 25 days 199,203
205 Route connections on Second Floor 3 days Wed 3/28/18 Fri 3/30/18 Wed 5/2/18 Fri 5/4/18 0 days 25 days 200,204
206 Route connections on Third Floor 3 days Mon 4/2/18 Wed 4/4/18 Mon 5/7/18 Wed 5/9/18 0 days 25 days 201,205
207 Label cables with asset tags and input into system 21 days Tue 3/20/18 Tue 4/17/18 Thu 6/7/18 Thu 7/5/18 57 days 57 days 203SS,206FF
208 Install electric boxes 2 days Tue 4/10/18 Wed 4/11/18 Tue 5/15/18 Wed 5/16/18 0 days 25 days 206,232,240
209 Install electric service panel 4 days Thu 4/12/18 Tue 4/17/18 Thu 5/17/18 Tue 5/22/18 0 days 25 days 208,232,240
210 Security cameras, sensors for lights and projectors
delivered on site
1 day Thu 4/12/18 Thu 4/12/18 Fri 5/18/18 Fri 5/18/18 0 days 26 days 208
211 Inspection of security and educational equipment 2 days Fri 4/13/18 Mon 4/16/18 Mon 5/21/18 Tue 5/22/18 1 day 26 days 210
212 Install security cameras, sensors for lights, projectors 5 days Wed 4/18/18 Tue 4/24/18 Wed 5/23/18 Tue 5/29/18 0 days 25 days 209,211
213 Connect electrical and SCADA cables with electric
boxes, lighting fixtures, heating unit, elevator unit
15 days Wed 4/25/18 Tue 5/15/18 Wed 5/30/18 Tue 6/19/18 0 days 25 days 208,209,212,192
214 Inspection of electrical and SCADA connections 5 days Wed 5/16/18 Tue 5/22/18 Wed 6/20/18 Tue 6/26/18 0 days 25 days 213
215 30 day testing of electrical system 30 days Wed 5/23/18 Tue 7/3/18 Wed 6/27/18 Tue 8/7/18 25 days 25 days 214
216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days
224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
2/25
February 1
January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2 12/16 12/30
March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1
March 2018 May 2018 July 2018 September 2018 November 2018 January 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7/3
7/3
7/3
3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2 12/16 12/30
March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1 January 1
March 2018 May 2018 July 2018 September 2018 November 2018 January 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
15. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
158 Piping (plumbing) 60 days Mon 12/25/17 Fri 3/16/18 Tue 3/6/18 Tue 8/7/18 51 days 51 days
176 HVAC (heating, ventilation, air conditioning) 111 days Mon 12/25/17 Mon 5/28/18 Tue 4/17/18 Tue 8/7/18 26 days 51 days
194 Electrical (lighting, SCADA, security, sensors, projectors) 82 days Mon 3/12/18 Tue 7/3/18 Tue 4/24/18 Tue 8/7/18 0 days 25 days
216 Elevator Shaft 84 days Wed 2/14/18 Tue 6/12/18 Thu 5/24/18 Tue 8/7/18 15 days 40 days
217 Elevator equipment and parts delivered to site 0 days Wed 2/14/18 Wed 2/14/18 Mon 4/23/18 Mon 4/23/18 0 days 47 days 153
218 Inspection of equipment and parts 2 days Thu 2/15/18 Fri 2/16/18 Thu 5/24/18 Fri 5/25/18 0 days 70 days 217
219 Assemble and install elevator shaft 15 days Mon 2/19/18 Fri 3/9/18 Mon 5/28/18 Fri 6/15/18 0 days 70 days 218
220 Inspection of elevator shaft assembly 2 days Mon 3/12/18 Tue 3/13/18 Wed 5/16/18 Thu 5/17/18 30 days 47 days 153FF+5 days,219
221 Connect electrical and mechanical parts 3 days Wed 4/25/18 Fri 4/27/18 Fri 5/18/18 Tue 5/22/18 0 days 17 days 220,213SS
222 Inspection of elevator operations 2 days Mon 4/30/18 Tue 5/1/18 Mon 6/25/18 Tue 6/26/18 0 days 40 days 221
223 30 day test of elevators 30 days Wed 5/2/18 Tue 6/12/18 Fri 5/25/18 Thu 7/5/18 17 days 17 days 193FF,222
224 Utlities Complete 0 days Tue 7/3/18 Tue 7/3/18 Fri 7/6/18 Fri 7/6/18 2 days 2 days 158FF,176FF,194FF,216FF
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
1/14
January 1
January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
1/14
January 1
January 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
2/14
6/12
7/3
1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2
January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1
January 2018 March 2018 May 2018 July 2018 September 2018 November 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
7/3
1/28 2/11 2/25 3/11 3/25 4/8 4/22 5/6 5/20 6/3 6/17 7/1 7/15 7/29 8/12 8/26 9/9 9/23 10/7 10/21 11/4 11/18 12/2
January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1 November 1 December 1
January 2018 March 2018 May 2018 July 2018 September 2018 November 2018
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
16. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days 82
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days 83
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
226 Drywall 15 days Mon 3/19/18 Fri 4/6/18 Fri 4/27/18 Fri 5/11/18 25 days 25 days
227 Delivery of drywall 0 days Mon 3/19/18 Mon 3/19/18 Tue 3/27/18 Tue 3/27/18 0 days 6 days 198SS
228 Install drywall 10 days Mon 3/26/18 Fri 4/6/18 Fri 5/4/18 Fri 5/11/18 25 days 25 days
229 Install drywall for Ground Floor 3 days Mon 3/26/18 Wed 3/28/18 Fri 5/4/18 Tue 5/8/18 4 days 29 days 168,186,203,227FS+5 days
230 Install drywall for Mezzainine 3 days Wed 3/28/18 Fri 3/30/18 Mon 5/7/18 Wed 5/9/18 3 days 28 days 169,187,204
231 Install drywall for Second Floor 3 days Mon 4/2/18 Wed 4/4/18 Tue 5/8/18 Thu 5/10/18 1 day 26 days 170,188,205
232 Install drywall for Third Floor 3 days Wed 4/4/18 Fri 4/6/18 Fri 4/6/18 Tue 4/10/18 0 days 2 days 171,189,206FS-1 day
233 Carpentry 16 days Mon 3/19/18 Mon 4/9/18 Wed 5/9/18 Tue 8/7/18 37 days 37 days
234 Windows, doors, cabintry delivered on site 0 days Mon 3/19/18 Mon 3/19/18 Wed 7/4/18 Wed 7/4/18 0 days 77 days 227
235 Inspection of parts 2 days Mon 3/19/18 Tue 3/20/18 Wed 7/4/18 Thu 7/5/18 77 days 77 days 234
236 Install windows, doors and cabintry 4 days Wed 4/4/18 Mon 4/9/18 Wed 5/9/18 Mon 5/14/18 25 days 25 days
237 Install Windows/Doors for Ground Floor 1 day Wed 4/4/18 Wed 4/4/18 Fri 4/6/18 Fri 4/6/18 0 days 2 days 229,232SS
3/19
3/19
T
Mar 11, '18
B
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
238 Install Windows/Doors for Mezzainine 1 day Thu 4/5/18 Thu 4/5/18 Thu 5/10/18 Thu 5/10/18 0 days 25 days 237,230
239 Install Windows/Doors for Second Floor 1 day Fri 4/6/18 Fri 4/6/18 Fri 5/11/18 Fri 5/11/18 0 days 25 days 238,231
240 Install Windows/Doors for Third Floor 1 day Mon 4/9/18 Mon 4/9/18 Mon 5/14/18 Mon 5/14/18 0 days 25 days 239,232
241 Insulation 15 days Mon 4/9/18 Fri 4/27/18 Wed 6/13/18 Tue 7/3/18 25 days 47 days
243 Paint (walls) 13 days Mon 4/30/18 Wed 5/16/18 Wed 7/4/18 Fri 7/20/18 12 days 47 days
247 Floor Finishes 15 days Mon 5/14/18 Fri 6/1/18 Wed 7/25/18 Wed 8/8/18 0 days 47 days
252 Trades Complete 0 days Fri 6/1/18 Fri 6/1/18 Fri 7/6/18 Fri 7/6/18 24 days 24 days 226FF,233FF,241FF,243FF,247FF
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days 85FF,253FF
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
T
Mar 11, '18
B
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
3/19
3/19
S W S T F M T S W S T F M T S W S T F M T
Mar 18, '18 Mar 25, '18 Apr 1, '18 Apr 8, '18 Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18
B E M B
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
S W S T F M T S W S T F M T S W S T F M T
Mar 18, '18 Mar 25, '18 Apr 1, '18 Apr 8, '18 Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18
B E M B
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
17. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
82 Commence Construction 0 days Mon 7/4/16 Mon 7/4/16 Thu 4/14/16 Thu 4/14/16 0 days -59 days
83 Demobilize and remove trailers 3 days Tue 7/5/16 Thu 7/7/16 Thu 4/14/16 Mon 4/18/16 0 days -59 days
84 Mobilize construction crew and project staff trailers 3 days Fri 7/8/16 Tue 7/12/16 Tue 4/19/16 Thu 4/21/16 0 days -59 days
85 Building Construction 515 days Wed 7/13/16 Tue 7/3/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
86 Structural 428 days Wed 7/13/16 Fri 3/2/18 Fri 4/22/16 Wed 8/8/18 0 days -59 days
157 Utilities 137 days Mon 12/25/17 Tue 7/3/18 Tue 3/6/18 Wed 8/8/18 25 days 25 days
225 Trade Finishes 55 days Mon 3/19/18 Fri 6/1/18 Fri 4/27/18 Wed 8/8/18 29 days 29 days
226 Drywall 15 days Mon 3/19/18 Fri 4/6/18 Fri 4/27/18 Fri 5/11/18 25 days 25 days
233 Carpentry 16 days Mon 3/19/18 Mon 4/9/18 Wed 5/9/18 Tue 8/7/18 37 days 37 days
241 Insulation 15 days Mon 4/9/18 Fri 4/27/18 Wed 6/13/18 Tue 7/3/18 25 days 47 days
242 Caulking, air sealing, and draft and fire stop 15 days Mon 4/9/18 Fri 4/27/18 Wed 6/13/18 Tue 7/3/18 0 days 47 days
243 Paint (walls) 13 days Mon 4/30/18 Wed 5/16/18 Wed 7/4/18 Fri 7/20/18 12 days 47 days
244 Prep drywall for prime coat 3 days Mon 4/30/18 Wed 5/2/18 Wed 7/4/18 Fri 7/6/18 0 days 47 days
245 Prime paint drywall 3 days Mon 5/7/18 Wed 5/9/18 Wed 7/11/18 Fri 7/13/18 0 days 47 days
246 Paint wall 3 days Mon 5/14/18 Wed 5/16/18 Wed 7/18/18 Fri 7/20/18 0 days 47 days
247 Floor Finishes 15 days Mon 5/14/18 Fri 6/1/18 Wed 7/25/18 Wed 8/8/18 0 days 47 days
248 Delivery of carpets 0 days Mon 5/14/18 Mon 5/14/18 Fri 7/6/18 Fri 7/6/18 0 days 39 days
249 Cleaning of floors 5 days Mon 5/21/18 Fri 5/25/18 Wed 7/25/18 Tue 7/31/18 0 days 47 days
250 Waxing of floors 2 days Mon 5/28/18 Tue 5/29/18 Wed 8/1/18 Thu 8/2/18 0 days 47 days
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
251 Installing carpets 3 days Wed 5/30/18 Fri 6/1/18 Fri 8/3/18 Tue 8/7/18 47 days 47 days
252 Trades Complete 0 days Fri 6/1/18 Fri 6/1/18 Fri 7/6/18 Fri 7/6/18 24 days 24 days
253 Others 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 22 days 93 days
254 Landscaping 15 days Mon 5/14/18 Fri 6/1/18 Thu 9/20/18 Wed 10/10/18 93 days 93 days
255 Sidewalks, ramps and stairs 10 days Mon 5/14/18 Fri 5/25/18 Mon 8/20/18 Fri 8/31/18 0 days 70 days
256 Handrails 1 day Mon 5/28/18 Mon 5/28/18 Wed 10/10/18 Wed 10/10/18 97 days 97 days
257 Plants 5 days Mon 5/28/18 Fri 6/1/18 Thu 10/4/18 Wed 10/10/18 93 days 93 days
258 Construction Complete 0 days Tue 7/3/18 Tue 7/3/18 Thu 10/11/18 Thu 10/11/18 25 days 71 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
Predecessors
82
83
232
242
244FS+2 days
245FS+2 days
249SS-5 days
246FS+2 days
249
5/14
T W T F S S M T W T F S S M T
Mar 18, '18 Apr 8, '18 Apr 29, '18 May 20, '18 Jun 10, '18 Jul 1, '18
B E M
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
Predecessors
250
226FF,233FF,241FF,243FF,247FF
248SS
255
255
85FF,253FF
6/1
7/3
T W T F S S M T W T F S S M T
Mar 18, '18 Apr 8, '18 Apr 29, '18 May 20, '18 Jun 10, '18 Jul 1, '18
B E M
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
18. ID Task Name Duration Start Finish Late Start Late Finish Free
Slack
Total
Slack
Predecessors
1 EDC Project Post-Economic Recession 1000 days Thu 1/1/15 Tue 10/30/18 Thu 4/14/16 Tue 10/30/18 0 days 0 days
2 Detailed Design Post-Economic Recession 68 days Thu 1/1/15 Mon 4/6/15 Wed 9/5/18 Tue 10/30/18 932 days 932 days
15 Acquisition 361 days Mon 1/26/15 Mon 6/13/16 Mon 3/12/18 Tue 10/30/18 622 days 622 days
81 Construction 521 days Mon 7/4/16 Tue 7/3/18 Thu 4/14/16 Thu 10/11/18 0 days -59 days
259 Comissioning 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
260 Document and Stakeholder Control 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days
261 Biweekly meetings with stakeholders and subcontractors 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 85SS
262 Confirm all documents (transmittals, change orders, shop
drawings, reports, manuals) are complete
600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 85SS
263 Total all change orders and submit to client as a report 600 days Wed 7/13/16 Tue 10/30/18 Wed 7/13/16 Tue 10/30/18 0 days 0 days 85SS
264 Complete all deficiency items 60 days Wed 7/4/18 Tue 9/25/18 Fri 7/6/18 Thu 9/27/18 2 days 2 days 85
265 Cleaning of site and building 3 days Wed 7/4/18 Fri 7/6/18 Thu 9/6/18 Mon 9/10/18 0 days 46 days 85
266 Contractor final inspection of building 1 day Mon 7/9/18 Mon 7/9/18 Tue 9/11/18 Tue 9/11/18 0 days 46 days 265
267 City final inspection of building 1 day Tue 7/17/18 Tue 7/17/18 Wed 9/19/18 Wed 9/19/18 0 days 46 days 266FS+5 days
268 Issue City user and occupancy certificate 0 days Tue 8/7/18 Tue 8/7/18 Thu 10/11/18 Thu 10/11/18 0 days 46 days 267FS+15 days
269 Meet with client to confirm all requirements were tended to 1 day Wed 8/8/18 Wed 8/8/18 Thu 10/11/18 Thu 10/11/18 0 days 46 days 258,268
270 Meet and train operators on the functionality of building 5 days Thu 8/16/18 Wed 8/22/18 Fri 10/19/18 Thu 10/25/18 0 days 46 days 269FS+5 days
271 Demobilize site trailers 3 days Thu 8/23/18 Mon 8/27/18 Fri 10/26/18 Tue 10/30/18 46 days 46 days 270
272 Grand opening of Engineering Design Center 0 days Fri 9/7/18 Fri 9/7/18 Tue 10/30/18 Tue 10/30/18 38 days 38 days 267
3/13
September 1
July 2015
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: EDC Project Final Ver 2
Date: Fri 4/3/15
8/7
9/7
6/19 9/25 1/1 4/9 7/16 10/22 1/28 5/6 8/12 11/18 2/24 6/2 9/8 12/15 3/22 6/28 10/4 1/10 4/18 7/25 10/31 2/6 5/15
March 21 October 11 May 1 November 21 June 11 January 1 July 21 February 11 September 1 March 21 October 11 May 1
July 2015 September 2016 November 2017 January 2019 March 2020 May 2021 July 2022
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: EDC Project Final Ver 2
Date: Fri 4/3/15