ID Task Name Duration Start Finish
1 Maunsell work 222 days? Mon 10/12/07 Tue 28/10/08
2 Key Milestones 118 days Mon 10/12/07 Wed 4/06/08
3 Draft RAP engineering to Estimators 0 days Fri 4/04/08 Fri 4/04/08
4 Final RAP engineering to Estimators 0 days Wed 4/06/08 Wed 4/06/08
5 Issued for Construction Documentation 0 days Mon 10/12/07 Mon 10/12/07
6 GSDA Aligment 1 day Thu 20/03/08 Thu 20/03/08
7 Geotechnical Information 1 day Thu 20/03/08 Thu 20/03/08
8 Survey Crossing 1 day Fri 22/02/08 Fri 22/02/08
9 Water Treatment Plant Location Fix 1 day Mon 10/03/08 Mon 10/03/08
10 Design Reviews with GAWB 123 days? Mon 10/12/07 Wed 11/06/08
11 Intake 30% design review 1 day? Fri 4/04/08 Fri 4/04/08
12 Intake 50% design review 1 day? Wed 11/06/08 Wed 11/06/08
13 Intake 80% design review 1 day? Mon 10/12/07 Mon 10/12/07
14 Intake HAZOP 1 day? Mon 10/12/07 Mon 10/12/07
15 OPTIONEERING 61 days Mon 10/12/07 Mon 17/03/08
16 Intake structure optioneering 41 days Mon 10/12/07 Mon 18/02/08
17 Develop ideas 4 days Mon 10/12/07 Thu 13/12/07
18 Value engineering workshop # 1 1 day Fri 14/12/07 Fri 14/12/07
19 Sunwater information from GAWB 0 days Fri 21/12/07 Fri 21/12/07
20 further preliminary engineering 15 days Mon 17/12/07 Mon 21/01/08
21 costings of ideas 15 days Tue 8/01/08 Mon 28/01/08
22 Value engineering workshop # 2 1 day Tue 29/01/08 Tue 29/01/08
23 Finalise preliminary engineering 3 days Wed 30/01/08 Fri 1/02/08
24 Develop report & recommendation to GAWB 1 day Mon 4/02/08 Mon 4/02/08
25 Issue recommendation to GAWB 0 days Mon 4/02/08 Mon 4/02/08
26 GAWB review 10 days Tue 5/02/08 Mon 18/02/08
27 Approval from GAWB to proceed 0 days Mon 18/02/08 Mon 18/02/08
28 Aldoga resevoir optioneering 45 days Mon 10/12/07 Fri 22/02/08
29 Develop ideas 4 days Mon 10/12/07 Thu 13/12/07
30 Value engineering workshop # 1 1 day Fri 14/12/07 Fri 14/12/07
31 further preliminary engineering 14 days Mon 17/12/07 Fri 18/01/08
32 costings of ideas 15 days Mon 14/01/08 Fri 1/02/08
33 Value engineering workshop # 2 1 day Mon 4/02/08 Mon 4/02/08
34 Finalise preliminary engineering 3 days Tue 5/02/08 Thu 7/02/08
35 Develop report & recommendation to GAWB 1 day Fri 8/02/08 Fri 8/02/08
36 Issue recommendation to GAWB 0 days Fri 8/02/08 Fri 8/02/08
37 GAWB review 10 days Mon 11/02/08 Fri 22/02/08
38 Approval from GAWB to proceed 0 days Fri 22/02/08 Fri 22/02/08
39 Pipe cost analysis 52 days Mon 10/12/07 Tue 4/03/08
40 Develop long sections and profiles 5 days Mon 10/12/07 Fri 14/12/07
41 Surge analysis 25 days Mon 10/12/07 Mon 28/01/08
42 Develop constructability costs for each pipe option 10 days Mon 10/12/07 Fri 21/12/07
43 Issue GAWB a pipe & fitting schedule 0 days Fri 14/12/07 Fri 14/12/07
44 GAWB discussions with DOI 5 days Mon 17/12/07 Fri 21/12/07
45 DOI to supply initial piping costs 0 days Fri 21/12/07 Fri 21/12/07
46 Develop economic analysis 12 days Tue 29/01/08 Wed 13/02/08
47 Value engineering workshop 1 day Thu 14/02/08 Thu 14/02/08
48 Develop report & recommendation to GAWB 3 days Fri 15/02/08 Tue 19/02/08
49 Issue recommendation to GAWB 0 days Tue 19/02/08 Tue 19/02/08
50 GAWB review 10 days Wed 20/02/08 Tue 4/03/08
51 Approval from GAWB to proceed 0 days Tue 4/03/08 Tue 4/03/08
52 Streamlining storage 61 days Mon 10/12/07 Mon 17/03/08
53 Develop ideas 4 days Mon 10/12/07 Thu 13/12/07
54 Value engineering workshop # 1 1 day Fri 14/12/07 Fri 14/12/07
55 Water treatment plant optimisation for storage 5 days Mon 17/12/07 Fri 21/12/07
56 Develop operating philosophy of pipeline 5 days Tue 29/01/08 Mon 4/02/08
57 Internal workshop to idenitfy storage optimisation 1 day Tue 5/02/08 Tue 5/02/08
58 Preliminary engineering of options 10 days Wed 6/02/08 Tue 19/02/08
59 Costing of options 10 days Wed 13/02/08 Tue 26/02/08
60 Value engineering workshop 1 day Wed 27/02/08 Wed 27/02/08
61 Develop report & recommendation to GAWB 3 days Thu 28/02/08 Mon 3/03/08
62 Issue recommendation to GAWB 0 days Mon 3/03/08 Mon 3/03/08
63 GAWB review 10 days Tue 4/03/08 Mon 17/03/08
64 Approval from GAWB to proceed 0 days Mon 17/03/08 Mon 17/03/08
65 Pipeline access 34 days Mon 17/12/07 Thu 14/02/08
66 Identify locations of valves, scour points etc 5 days Mon 17/12/07 Fri 21/12/07
67 Identify access routes along long section 1 day Mon 7/01/08 Mon 7/01/08
68 Develop an access regime 5 days Tue 8/01/08 Mon 14/01/08
69 Costing of options 10 days Tue 15/01/08 Mon 28/01/08
70 Develop prelim report & recommendation to GAWB 3 days Tue 29/01/08 Thu 31/01/08
71 Issue preliminary recommendation to GAWB 0 days Thu 31/01/08 Thu 31/01/08
72 GAWB review 10 days Fri 1/02/08 Thu 14/02/08
73 GAWB comments but will be refined in engineering process 0 days Thu 14/02/08 Thu 14/02/08
74 Special Crossings 27 days Thu 17/01/08 Fri 22/02/08
75 Develop Ideas 14 days Thu 17/01/08 Tue 5/02/08
76 Value engineering workshop 1 day Wed 6/02/08 Wed 6/02/08
77 Develop report & recommendation to GAWB 2 days Thu 7/02/08 Fri 8/02/08
78 Issue recommendation to GAWB 0 days Fri 8/02/08 Fri 8/02/08
79 GAWB review 10 days Mon 11/02/08 Fri 22/02/08
80 Approval from GAWB to proceed 0 days Fri 22/02/08 Fri 22/02/08
81
82 DESIGN 217 days? Mon 17/12/07 Tue 28/10/08
83 Intake Pump Station 26100 187 days? Tue 22/01/08 Wed 8/10/08
84 Generic engineering independent of decision process 20 days Tue 22/01/08 Mon 18/02/08
85 Eng for 30% Design 15 days Tue 19/02/08 Mon 10/03/08
86 Drafting for 30% Design 5 days Tue 4/03/08 Mon 10/03/08
87 Internal 30% design review 1 day? Mon 10/03/08 Mon 10/03/08
88 Information for 30% design review issued to GAWB 0 days Mon 10/03/08 Mon 10/03/08
89 30% engineering info issued to estimators 0 days Mon 10/03/08 Mon 10/03/08
90 GAWB review 10 days Tue 11/03/08 Mon 24/03/08
91 Eng for 50% Design 54 days Tue 11/03/08 Fri 23/05/08
92 Drafting for 50% Design 54 days Tue 11/03/08 Fri 23/05/08
93 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08
94 Internal 50% design review 1 day? Tue 27/05/08 Tue 27/05/08
95 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08
96 Information for 50% design review issued to GAWB 0 days Tue 27/05/08 Tue 27/05/08
97 50% engineering info issued to estimators 0 days Tue 27/05/08 Tue 27/05/08
98 GAWB review 10 days Wed 28/05/08 Tue 10/06/08
99 Eng for 80% Design 54 days Tue 27/05/08 Fri 8/08/08
100 Drafting for 80% Design 54 days Tue 27/05/08 Fri 8/08/08
101 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08
102 Internal 80% design review 1 day? Mon 11/08/08 Mon 11/08/08
103 Information for 80% design review issued to GAWB 0 days Mon 11/08/08 Mon 11/08/08
104 80% engineering info issued to estimators 0 days Mon 11/08/08 Mon 11/08/08
105 GAWB review 10 days Tue 12/08/08 Mon 25/08/08
106 HAZOP 1 day Tue 26/08/08 Tue 26/08/08
107 Package up work as is for FINAL RAP 5 days Tue 12/08/08 Mon 18/08/08
108 Eng to IFC 40 days Mon 11/08/08 Fri 3/10/08
109 Drafting to IFC 40 days Mon 11/08/08 Fri 3/10/08
110 Final review and sign off 3 days Mon 6/10/08 Wed 8/10/08
111 Issue Intake documentation for IFC 0 days Wed 8/10/08 Wed 8/10/08
112
113 WTP Pump Station 26200 118 days? Tue 22/01/08 Thu 3/07/08
114 Generic engineering independent of decision process 20 days Tue 22/01/08 Mon 18/02/08
4/04
4/06
10/12
21/12
4/02
18/02
8/02
22/02
14/12
21/12
19/02
4/03
3/03
17/03
31/01
14/02
8/02
22/02
10/03
10/03
27/05
27/05
11/08
11/08
8/10
22 9 27 15 2 20 7 25 14 1 19 7 25 12 30 18 5 23 10 28 16 3
22 Oct '07 3 Dec '07 14 Jan '08 25 Feb '08 7 Apr '08 19 May '08 30 Jun '08 11 Aug '08 22 Sep '08 3 Nov '08
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
CDUJV Detail Design Schedule (Rev_H) 19-12-07
Page 1
Project: Maunsell example schedule
Date: Sun 15/01/17
ID Task Name Duration Start Finish
115 Eng for 30% Design 15 days Tue 19/02/08 Mon 10/03/08
116 Drafting for 30% Design 5 days Tue 4/03/08 Mon 10/03/08
117 Internal 30% design review 1 day? Mon 10/03/08 Mon 10/03/08
118 Information for 30% design review issued to GAWB 0 days Mon 10/03/08 Mon 10/03/08
119 30% engineering info issued to estimators 0 days Mon 10/03/08 Mon 10/03/08
120 GAWB review 10 days Tue 11/03/08 Mon 24/03/08
121 Eng for 50% Design 30 days Tue 11/03/08 Mon 21/04/08
122 Drafting for 50% Design 30 days Tue 11/03/08 Mon 21/04/08
123 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08
124 Internal 50% design review 1 day? Tue 22/04/08 Tue 22/04/08
125 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08
126 Information for 50% design review issued to GAWB 0 days Tue 22/04/08 Tue 22/04/08
127 50% engineering info issued to estimators 0 days Tue 22/04/08 Tue 22/04/08
128 GAWB review 10 days Wed 23/04/08 Tue 6/05/08
129 Eng for 80% Design 25 days Tue 22/04/08 Mon 26/05/08
130 Drafting for 80% Design 25 days Tue 22/04/08 Mon 26/05/08
131 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08
132 Internal 80% design review 1 day? Tue 27/05/08 Tue 27/05/08
133 Information for 80% design review issued to GAWB 0 days Tue 27/05/08 Tue 27/05/08
134 80% engineering info issued to estimators 0 days Tue 27/05/08 Tue 27/05/08
135 GAWB review 10 days Wed 28/05/08 Tue 10/06/08
136 HAZOP 1 day Wed 11/06/08 Wed 11/06/08
137 Package up work as is for FINAL RAP 5 days Thu 29/05/08 Wed 4/06/08
138 Eng to IFC 25 days Tue 27/05/08 Mon 30/06/08
139 Drafting to IFC 25 days Tue 27/05/08 Mon 30/06/08
140 Final review and sign off 3 days Tue 1/07/08 Thu 3/07/08
141 Issue Intake documentation for IFC 0 days Thu 3/07/08 Thu 3/07/08
142
143 Raglan Creek Pump Station 26300 118 days? Tue 22/01/08 Thu 3/07/08
144 Generic engineering independent of decision process 20 days Tue 22/01/08 Mon 18/02/08
145 Eng for 30% Design 15 days Tue 19/02/08 Mon 10/03/08
146 Drafting for 30% Design 5 days Tue 4/03/08 Mon 10/03/08
147 Internal 30% design review 1 day? Mon 10/03/08 Mon 10/03/08
148 Information for 30% design review issued to GAWB 0 days Mon 10/03/08 Mon 10/03/08
149 30% engineering info issued to estimators 0 days Mon 10/03/08 Mon 10/03/08
150 GAWB review 10 days Tue 11/03/08 Mon 24/03/08
151 Eng for 50% Design 30 days Tue 11/03/08 Mon 21/04/08
152 Drafting for 50% Design 30 days Tue 11/03/08 Mon 21/04/08
153 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08
154 Internal 50% design review 1 day? Tue 22/04/08 Tue 22/04/08
155 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08
156 Information for 50% design review issued to GAWB 0 days Tue 22/04/08 Tue 22/04/08
157 50% engineering info issued to estimators 0 days Tue 22/04/08 Tue 22/04/08
158 GAWB review 10 days Wed 23/04/08 Tue 6/05/08
159 Eng for 80% Design 25 days Tue 22/04/08 Mon 26/05/08
160 Drafting for 80% Design 25 days Tue 22/04/08 Mon 26/05/08
161 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08
162 Internal 80% design review 1 day? Tue 27/05/08 Tue 27/05/08
163 Information for 80% design review issued to GAWB 0 days Tue 27/05/08 Tue 27/05/08
164 80% engineering info issued to estimators 0 days Tue 27/05/08 Tue 27/05/08
165 GAWB review 10 days Wed 28/05/08 Tue 10/06/08
166 HAZOP 1 day Wed 11/06/08 Wed 11/06/08
167 Package up work as is for FINAL RAP 5 days Thu 29/05/08 Wed 4/06/08
168 Eng to IFC 25 days Tue 27/05/08 Mon 30/06/08
169 Drafting to IFC 25 days Tue 27/05/08 Mon 30/06/08
170 Final review and sign off 3 days Tue 1/07/08 Thu 3/07/08
171 Issue Intake documentation for IFC 0 days Thu 3/07/08 Thu 3/07/08
172
173 Aldoga Resevoir 176 days Mon 7/01/08 Mon 8/09/08
174 Generic engineering independent of decision process 20 days Tue 22/01/08 Mon 18/02/08
175 Eng for 30% Design 51 days Mon 7/01/08 Mon 17/03/08
176 Drafting for 30% Design 41 days Mon 21/01/08 Mon 17/03/08
177 Internal 30% design review 1 day Thu 20/03/08 Thu 20/03/08
178 Information for 30% design review issued to GAWB 0 days Thu 20/03/08 Thu 20/03/08
179 30% engineering info issued to estimators 0 days Thu 20/03/08 Thu 20/03/08
180 GAWB review 10 days Fri 21/03/08 Thu 3/04/08
181 Eng for 50% Design 40 days Thu 20/03/08 Wed 14/05/08
182 Drafting for 50% Design 40 days Thu 20/03/08 Wed 14/05/08
183 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08
184 Internal 50% design review 1 day Tue 20/05/08 Tue 20/05/08
185 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08
186 Information for 50% design review issued to GAWB 0 days Tue 20/05/08 Tue 20/05/08
187 50% engineering info issued to estimators 0 days Tue 20/05/08 Tue 20/05/08
188 GAWB review 10 days Wed 21/05/08 Tue 3/06/08
189 Eng for 80% Design 52 days Mon 19/05/08 Tue 29/07/08
190 Drafting for 80% Design 52 days Mon 19/05/08 Tue 29/07/08
191 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08
192 Internal 80% design review 1 day Wed 30/07/08 Wed 30/07/08
193 Information for 80% design review issued to GAWB 0 days Wed 30/07/08 Wed 30/07/08
194 80% engineering info issued to estimators 0 days Wed 30/07/08 Wed 30/07/08
195 GAWB review 10 days Thu 31/07/08 Wed 13/08/08
196 HAZOP 1 day Thu 14/08/08 Thu 14/08/08
197 Package up work as is for FINAL RAP 5 days Thu 29/05/08 Wed 4/06/08
198 Eng to IFC 25 days Thu 31/07/08 Wed 3/09/08
199 Drafting to IFC 25 days Thu 31/07/08 Wed 3/09/08
200 Final review and sign off 3 days Thu 4/09/08 Mon 8/09/08
201 Issue documentation for Construction IFC 0 days Mon 8/09/08 Mon 8/09/08
202
203 Pipeline - WTP to Relift 217 days? Mon 17/12/07 Tue 28/10/08
204 Generic engineering independent of decision process 65 days Mon 17/12/07 Fri 28/03/08
205 Eng for 30% Design 65 days Mon 14/01/08 Fri 11/04/08
206 Drafting for 30% Design 55 days Mon 28/01/08 Fri 11/04/08
207 Internal 30% design review 1 day Wed 16/04/08 Wed 16/04/08
208 Information for 30% design review issued to GAWB 0 days Wed 16/04/08 Wed 16/04/08
209 30% engineering info issued to estimators 0 days Wed 16/04/08 Wed 16/04/08
210 GAWB review 10 days Thu 17/04/08 Wed 30/04/08
211 Eng for 50% Design 50 days Wed 16/04/08 Tue 24/06/08
212 Drafting for 50% Design 50 days Wed 16/04/08 Tue 24/06/08
213 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08
214 Internal 50% design review 1 day Mon 30/06/08 Mon 30/06/08
215 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08
216 Information for 50% design review issued to GAWB 0 days Mon 30/06/08 Mon 30/06/08
217 50% engineering info issued to estimators 0 days Mon 30/06/08 Mon 30/06/08
218 GAWB review 10 days Tue 1/07/08 Mon 14/07/08
219 Eng for 80% Design 46 days Tue 1/07/08 Tue 2/09/08
220 Drafting for 80% Design 46 days Tue 1/07/08 Tue 2/09/08
221 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08
222 Internal 80% design review 1 day? Fri 5/09/08 Fri 5/09/08
223 Information for 80% design review issued to GAWB 0 days Fri 5/09/08 Fri 5/09/08
224 80% engineering info issued to estimators 0 days Fri 5/09/08 Fri 5/09/08
225 GAWB review 10 days Mon 8/09/08 Fri 19/09/08
226 HAZOP 1 day Mon 22/09/08 Mon 22/09/08
227 Package up work as is for FINAL RAP 5 days Thu 29/05/08 Wed 4/06/08
228 Eng to IFC 35 days Fri 5/09/08 Thu 23/10/08
229 Drafting to IFC 35 days Fri 5/09/08 Thu 23/10/08
10/03
10/03
22/04
22/04
27/05
27/05
3/07
10/03
10/03
22/04
22/04
27/05
27/05
3/07
20/03
20/03
20/05
20/05
30/07
30/07
8/09
16/04
16/04
30/06
30/06
5/09
5/09
22 9 27 15 2 20 7 25 14 1 19 7 25 12 30 18 5 23 10 28 16 3
22 Oct '07 3 Dec '07 14 Jan '08 25 Feb '08 7 Apr '08 19 May '08 30 Jun '08 11 Aug '08 22 Sep '08 3 Nov '08
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
CDUJV Detail Design Schedule (Rev_H) 19-12-07
Page 2
Project: Maunsell example schedule
Date: Sun 15/01/17
ID Task Name Duration Start Finish
230 Final review and sign off 3 days Fri 24/10/08 Tue 28/10/08
231 Issue documentation for Construction IFC 0 days Tue 28/10/08 Tue 28/10/08
232
233 Pipeline - Relift to Aldoga 173 days? Mon 17/12/07 Wed 27/08/08
234 Generic engineering independent of decision process 65 days Mon 17/12/07 Fri 28/03/08
235 Eng for 30% Design 55 days Mon 14/01/08 Fri 28/03/08
236 Drafting for 30% Design 45 days Mon 28/01/08 Fri 28/03/08
237 Internal 30% design review 1 day Wed 2/04/08 Wed 2/04/08
238 Information for 30% design review issued to GAWB 0 days Wed 2/04/08 Wed 2/04/08
239 30% engineering info issued to estimators 0 days Wed 2/04/08 Wed 2/04/08
240 GAWB review 10 days Thu 3/04/08 Wed 16/04/08
241 Eng for 50% Design 38 days Fri 4/04/08 Tue 27/05/08
242 Drafting for 50% Design 38 days Fri 4/04/08 Tue 27/05/08
243 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08
244 Internal 50% design review 1 day Wed 28/05/08 Wed 28/05/08
245 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08
246 Information for 50% design review issued to GAWB 0 days Wed 28/05/08 Wed 28/05/08
247 50% engineering info issued to estimators 0 days Wed 28/05/08 Wed 28/05/08
248 GAWB review 10 days Thu 29/05/08 Wed 11/06/08
249 Eng for 80% Design 38 days Wed 28/05/08 Fri 18/07/08
250 Drafting for 80% Design 38 days Wed 28/05/08 Fri 18/07/08
251 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08
252 Internal 80% design review 1 day? Mon 21/07/08 Mon 21/07/08
253 Information for 80% design review issued to GAWB 0 days Mon 21/07/08 Mon 21/07/08
254 80% engineering info issued to estimators 0 days Mon 21/07/08 Mon 21/07/08
255 GAWB review 10 days Tue 22/07/08 Mon 4/08/08
256 HAZOP 1 day Tue 5/08/08 Tue 5/08/08
257 Package up work as is for FINAL RAP 5 days Thu 29/05/08 Wed 4/06/08
258 Eng to IFC 25 days Mon 21/07/08 Fri 22/08/08
259 Drafting to IFC 25 days Mon 21/07/08 Fri 22/08/08
260 Final review and sign off 3 days Mon 25/08/08 Wed 27/08/08
261 Issue documentation for Construction IFC 0 days Wed 27/08/08 Wed 27/08/08
262
263 Pipeline - Aldoga to Mt Miller 173 days? Mon 17/12/07 Wed 27/08/08
264 Generic engineering independent of decision process 65 days Mon 17/12/07 Fri 28/03/08
265 Eng for 30% Design 55 days Mon 14/01/08 Fri 28/03/08
266 Drafting for 30% Design 45 days Mon 28/01/08 Fri 28/03/08
267 Internal 30% design review 1 day Wed 2/04/08 Wed 2/04/08
268 Information for 30% design review issued to GAWB 0 days Wed 2/04/08 Wed 2/04/08
269 30% engineering info issued to estimators 0 days Wed 2/04/08 Wed 2/04/08
270 GAWB review 10 days Thu 3/04/08 Wed 16/04/08
271 Eng for 50% Design 38 days Fri 4/04/08 Tue 27/05/08
272 Drafting for 50% Design 38 days Fri 4/04/08 Tue 27/05/08
273 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08
274 Internal 50% design review 1 day Wed 28/05/08 Wed 28/05/08
275 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08
276 Information for 50% design review issued to GAWB 0 days Wed 28/05/08 Wed 28/05/08
277 50% engineering info issued to estimators 0 days Wed 28/05/08 Wed 28/05/08
278 GAWB review 10 days Thu 29/05/08 Wed 11/06/08
279 Eng for 80% Design 38 days Wed 28/05/08 Fri 18/07/08
280 Drafting for 80% Design 38 days Wed 28/05/08 Fri 18/07/08
281 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08
282 Internal 80% design review 1 day? Mon 21/07/08 Mon 21/07/08
283 Information for 80% design review issued to GAWB 0 days Mon 21/07/08 Mon 21/07/08
284 80% engineering info issued to estimators 0 days Mon 21/07/08 Mon 21/07/08
285 GAWB review 10 days Tue 22/07/08 Mon 4/08/08
286 HAZOP 1 day Tue 5/08/08 Tue 5/08/08
287 Package up work as is for FINAL RAP 5 days Thu 29/05/08 Wed 4/06/08
288 Eng to IFC 25 days Mon 21/07/08 Fri 22/08/08
289 Drafting to IFC 25 days Mon 21/07/08 Fri 22/08/08
290 Final review and sign off 3 days Mon 25/08/08 Wed 27/08/08
291 Issue documentation for Construction IFC 0 days Wed 27/08/08 Wed 27/08/08
28/10
2/04
2/04
28/05
28/05
21/07
21/07
27/08
2/04
2/04
28/05
28/05
21/07
21/07
27/08
22 9 27 15 2 20 7 25 14 1 19 7 25 12 30 18 5 23 10 28 16 3
22 Oct '07 3 Dec '07 14 Jan '08 25 Feb '08 7 Apr '08 19 May '08 30 Jun '08 11 Aug '08 22 Sep '08 3 Nov '08
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
CDUJV Detail Design Schedule (Rev_H) 19-12-07
Page 3
Project: Maunsell example schedule
Date: Sun 15/01/17
3 21 9 27 14 1 19 9 27 14 2 20 7 25 13 31 18 5 23 11 29 16 4 22 9 27 14 4 22
3 Nov '08 15 Dec '08 26 Jan '09 9 Mar '09 20 Apr '09 1 Jun '09 13 Jul '09 24 Aug '09 5 Oct '09 16 Nov '09 28 Dec '09 8 Feb '10 22 Mar '10
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
CDUJV Detail Design Schedule (Rev_H) 19-12-07
Page 4
Project: Maunsell example schedule
Date: Sun 15/01/17
3 21 9 27 14 1 19 9 27 14 2 20 7 25 13 31 18 5 23 11 29 16 4 22 9 27 14 4 22
3 Nov '08 15 Dec '08 26 Jan '09 9 Mar '09 20 Apr '09 1 Jun '09 13 Jul '09 24 Aug '09 5 Oct '09 16 Nov '09 28 Dec '09 8 Feb '10 22 Mar '10
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
CDUJV Detail Design Schedule (Rev_H) 19-12-07
Page 5
Project: Maunsell example schedule
Date: Sun 15/01/17
28/10
3 21 9 27 14 1 19 9 27 14 2 20 7 25 13 31 18 5 23 11 29 16 4 22 9 27 14 4 22
3 Nov '08 15 Dec '08 26 Jan '09 9 Mar '09 20 Apr '09 1 Jun '09 13 Jul '09 24 Aug '09 5 Oct '09 16 Nov '09 28 Dec '09 8 Feb '10 22 Mar '10
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
CDUJV Detail Design Schedule (Rev_H) 19-12-07
Page 6
Project: Maunsell example schedule
Date: Sun 15/01/17

Fitzroy-Gladestone Pipeline EPC Project - Design Schedule

  • 1.
    ID Task NameDuration Start Finish 1 Maunsell work 222 days? Mon 10/12/07 Tue 28/10/08 2 Key Milestones 118 days Mon 10/12/07 Wed 4/06/08 3 Draft RAP engineering to Estimators 0 days Fri 4/04/08 Fri 4/04/08 4 Final RAP engineering to Estimators 0 days Wed 4/06/08 Wed 4/06/08 5 Issued for Construction Documentation 0 days Mon 10/12/07 Mon 10/12/07 6 GSDA Aligment 1 day Thu 20/03/08 Thu 20/03/08 7 Geotechnical Information 1 day Thu 20/03/08 Thu 20/03/08 8 Survey Crossing 1 day Fri 22/02/08 Fri 22/02/08 9 Water Treatment Plant Location Fix 1 day Mon 10/03/08 Mon 10/03/08 10 Design Reviews with GAWB 123 days? Mon 10/12/07 Wed 11/06/08 11 Intake 30% design review 1 day? Fri 4/04/08 Fri 4/04/08 12 Intake 50% design review 1 day? Wed 11/06/08 Wed 11/06/08 13 Intake 80% design review 1 day? Mon 10/12/07 Mon 10/12/07 14 Intake HAZOP 1 day? Mon 10/12/07 Mon 10/12/07 15 OPTIONEERING 61 days Mon 10/12/07 Mon 17/03/08 16 Intake structure optioneering 41 days Mon 10/12/07 Mon 18/02/08 17 Develop ideas 4 days Mon 10/12/07 Thu 13/12/07 18 Value engineering workshop # 1 1 day Fri 14/12/07 Fri 14/12/07 19 Sunwater information from GAWB 0 days Fri 21/12/07 Fri 21/12/07 20 further preliminary engineering 15 days Mon 17/12/07 Mon 21/01/08 21 costings of ideas 15 days Tue 8/01/08 Mon 28/01/08 22 Value engineering workshop # 2 1 day Tue 29/01/08 Tue 29/01/08 23 Finalise preliminary engineering 3 days Wed 30/01/08 Fri 1/02/08 24 Develop report & recommendation to GAWB 1 day Mon 4/02/08 Mon 4/02/08 25 Issue recommendation to GAWB 0 days Mon 4/02/08 Mon 4/02/08 26 GAWB review 10 days Tue 5/02/08 Mon 18/02/08 27 Approval from GAWB to proceed 0 days Mon 18/02/08 Mon 18/02/08 28 Aldoga resevoir optioneering 45 days Mon 10/12/07 Fri 22/02/08 29 Develop ideas 4 days Mon 10/12/07 Thu 13/12/07 30 Value engineering workshop # 1 1 day Fri 14/12/07 Fri 14/12/07 31 further preliminary engineering 14 days Mon 17/12/07 Fri 18/01/08 32 costings of ideas 15 days Mon 14/01/08 Fri 1/02/08 33 Value engineering workshop # 2 1 day Mon 4/02/08 Mon 4/02/08 34 Finalise preliminary engineering 3 days Tue 5/02/08 Thu 7/02/08 35 Develop report & recommendation to GAWB 1 day Fri 8/02/08 Fri 8/02/08 36 Issue recommendation to GAWB 0 days Fri 8/02/08 Fri 8/02/08 37 GAWB review 10 days Mon 11/02/08 Fri 22/02/08 38 Approval from GAWB to proceed 0 days Fri 22/02/08 Fri 22/02/08 39 Pipe cost analysis 52 days Mon 10/12/07 Tue 4/03/08 40 Develop long sections and profiles 5 days Mon 10/12/07 Fri 14/12/07 41 Surge analysis 25 days Mon 10/12/07 Mon 28/01/08 42 Develop constructability costs for each pipe option 10 days Mon 10/12/07 Fri 21/12/07 43 Issue GAWB a pipe & fitting schedule 0 days Fri 14/12/07 Fri 14/12/07 44 GAWB discussions with DOI 5 days Mon 17/12/07 Fri 21/12/07 45 DOI to supply initial piping costs 0 days Fri 21/12/07 Fri 21/12/07 46 Develop economic analysis 12 days Tue 29/01/08 Wed 13/02/08 47 Value engineering workshop 1 day Thu 14/02/08 Thu 14/02/08 48 Develop report & recommendation to GAWB 3 days Fri 15/02/08 Tue 19/02/08 49 Issue recommendation to GAWB 0 days Tue 19/02/08 Tue 19/02/08 50 GAWB review 10 days Wed 20/02/08 Tue 4/03/08 51 Approval from GAWB to proceed 0 days Tue 4/03/08 Tue 4/03/08 52 Streamlining storage 61 days Mon 10/12/07 Mon 17/03/08 53 Develop ideas 4 days Mon 10/12/07 Thu 13/12/07 54 Value engineering workshop # 1 1 day Fri 14/12/07 Fri 14/12/07 55 Water treatment plant optimisation for storage 5 days Mon 17/12/07 Fri 21/12/07 56 Develop operating philosophy of pipeline 5 days Tue 29/01/08 Mon 4/02/08 57 Internal workshop to idenitfy storage optimisation 1 day Tue 5/02/08 Tue 5/02/08 58 Preliminary engineering of options 10 days Wed 6/02/08 Tue 19/02/08 59 Costing of options 10 days Wed 13/02/08 Tue 26/02/08 60 Value engineering workshop 1 day Wed 27/02/08 Wed 27/02/08 61 Develop report & recommendation to GAWB 3 days Thu 28/02/08 Mon 3/03/08 62 Issue recommendation to GAWB 0 days Mon 3/03/08 Mon 3/03/08 63 GAWB review 10 days Tue 4/03/08 Mon 17/03/08 64 Approval from GAWB to proceed 0 days Mon 17/03/08 Mon 17/03/08 65 Pipeline access 34 days Mon 17/12/07 Thu 14/02/08 66 Identify locations of valves, scour points etc 5 days Mon 17/12/07 Fri 21/12/07 67 Identify access routes along long section 1 day Mon 7/01/08 Mon 7/01/08 68 Develop an access regime 5 days Tue 8/01/08 Mon 14/01/08 69 Costing of options 10 days Tue 15/01/08 Mon 28/01/08 70 Develop prelim report & recommendation to GAWB 3 days Tue 29/01/08 Thu 31/01/08 71 Issue preliminary recommendation to GAWB 0 days Thu 31/01/08 Thu 31/01/08 72 GAWB review 10 days Fri 1/02/08 Thu 14/02/08 73 GAWB comments but will be refined in engineering process 0 days Thu 14/02/08 Thu 14/02/08 74 Special Crossings 27 days Thu 17/01/08 Fri 22/02/08 75 Develop Ideas 14 days Thu 17/01/08 Tue 5/02/08 76 Value engineering workshop 1 day Wed 6/02/08 Wed 6/02/08 77 Develop report & recommendation to GAWB 2 days Thu 7/02/08 Fri 8/02/08 78 Issue recommendation to GAWB 0 days Fri 8/02/08 Fri 8/02/08 79 GAWB review 10 days Mon 11/02/08 Fri 22/02/08 80 Approval from GAWB to proceed 0 days Fri 22/02/08 Fri 22/02/08 81 82 DESIGN 217 days? Mon 17/12/07 Tue 28/10/08 83 Intake Pump Station 26100 187 days? Tue 22/01/08 Wed 8/10/08 84 Generic engineering independent of decision process 20 days Tue 22/01/08 Mon 18/02/08 85 Eng for 30% Design 15 days Tue 19/02/08 Mon 10/03/08 86 Drafting for 30% Design 5 days Tue 4/03/08 Mon 10/03/08 87 Internal 30% design review 1 day? Mon 10/03/08 Mon 10/03/08 88 Information for 30% design review issued to GAWB 0 days Mon 10/03/08 Mon 10/03/08 89 30% engineering info issued to estimators 0 days Mon 10/03/08 Mon 10/03/08 90 GAWB review 10 days Tue 11/03/08 Mon 24/03/08 91 Eng for 50% Design 54 days Tue 11/03/08 Fri 23/05/08 92 Drafting for 50% Design 54 days Tue 11/03/08 Fri 23/05/08 93 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08 94 Internal 50% design review 1 day? Tue 27/05/08 Tue 27/05/08 95 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08 96 Information for 50% design review issued to GAWB 0 days Tue 27/05/08 Tue 27/05/08 97 50% engineering info issued to estimators 0 days Tue 27/05/08 Tue 27/05/08 98 GAWB review 10 days Wed 28/05/08 Tue 10/06/08 99 Eng for 80% Design 54 days Tue 27/05/08 Fri 8/08/08 100 Drafting for 80% Design 54 days Tue 27/05/08 Fri 8/08/08 101 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08 102 Internal 80% design review 1 day? Mon 11/08/08 Mon 11/08/08 103 Information for 80% design review issued to GAWB 0 days Mon 11/08/08 Mon 11/08/08 104 80% engineering info issued to estimators 0 days Mon 11/08/08 Mon 11/08/08 105 GAWB review 10 days Tue 12/08/08 Mon 25/08/08 106 HAZOP 1 day Tue 26/08/08 Tue 26/08/08 107 Package up work as is for FINAL RAP 5 days Tue 12/08/08 Mon 18/08/08 108 Eng to IFC 40 days Mon 11/08/08 Fri 3/10/08 109 Drafting to IFC 40 days Mon 11/08/08 Fri 3/10/08 110 Final review and sign off 3 days Mon 6/10/08 Wed 8/10/08 111 Issue Intake documentation for IFC 0 days Wed 8/10/08 Wed 8/10/08 112 113 WTP Pump Station 26200 118 days? Tue 22/01/08 Thu 3/07/08 114 Generic engineering independent of decision process 20 days Tue 22/01/08 Mon 18/02/08 4/04 4/06 10/12 21/12 4/02 18/02 8/02 22/02 14/12 21/12 19/02 4/03 3/03 17/03 31/01 14/02 8/02 22/02 10/03 10/03 27/05 27/05 11/08 11/08 8/10 22 9 27 15 2 20 7 25 14 1 19 7 25 12 30 18 5 23 10 28 16 3 22 Oct '07 3 Dec '07 14 Jan '08 25 Feb '08 7 Apr '08 19 May '08 30 Jun '08 11 Aug '08 22 Sep '08 3 Nov '08 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Progress Deadline CDUJV Detail Design Schedule (Rev_H) 19-12-07 Page 1 Project: Maunsell example schedule Date: Sun 15/01/17
  • 2.
    ID Task NameDuration Start Finish 115 Eng for 30% Design 15 days Tue 19/02/08 Mon 10/03/08 116 Drafting for 30% Design 5 days Tue 4/03/08 Mon 10/03/08 117 Internal 30% design review 1 day? Mon 10/03/08 Mon 10/03/08 118 Information for 30% design review issued to GAWB 0 days Mon 10/03/08 Mon 10/03/08 119 30% engineering info issued to estimators 0 days Mon 10/03/08 Mon 10/03/08 120 GAWB review 10 days Tue 11/03/08 Mon 24/03/08 121 Eng for 50% Design 30 days Tue 11/03/08 Mon 21/04/08 122 Drafting for 50% Design 30 days Tue 11/03/08 Mon 21/04/08 123 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08 124 Internal 50% design review 1 day? Tue 22/04/08 Tue 22/04/08 125 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08 126 Information for 50% design review issued to GAWB 0 days Tue 22/04/08 Tue 22/04/08 127 50% engineering info issued to estimators 0 days Tue 22/04/08 Tue 22/04/08 128 GAWB review 10 days Wed 23/04/08 Tue 6/05/08 129 Eng for 80% Design 25 days Tue 22/04/08 Mon 26/05/08 130 Drafting for 80% Design 25 days Tue 22/04/08 Mon 26/05/08 131 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08 132 Internal 80% design review 1 day? Tue 27/05/08 Tue 27/05/08 133 Information for 80% design review issued to GAWB 0 days Tue 27/05/08 Tue 27/05/08 134 80% engineering info issued to estimators 0 days Tue 27/05/08 Tue 27/05/08 135 GAWB review 10 days Wed 28/05/08 Tue 10/06/08 136 HAZOP 1 day Wed 11/06/08 Wed 11/06/08 137 Package up work as is for FINAL RAP 5 days Thu 29/05/08 Wed 4/06/08 138 Eng to IFC 25 days Tue 27/05/08 Mon 30/06/08 139 Drafting to IFC 25 days Tue 27/05/08 Mon 30/06/08 140 Final review and sign off 3 days Tue 1/07/08 Thu 3/07/08 141 Issue Intake documentation for IFC 0 days Thu 3/07/08 Thu 3/07/08 142 143 Raglan Creek Pump Station 26300 118 days? Tue 22/01/08 Thu 3/07/08 144 Generic engineering independent of decision process 20 days Tue 22/01/08 Mon 18/02/08 145 Eng for 30% Design 15 days Tue 19/02/08 Mon 10/03/08 146 Drafting for 30% Design 5 days Tue 4/03/08 Mon 10/03/08 147 Internal 30% design review 1 day? Mon 10/03/08 Mon 10/03/08 148 Information for 30% design review issued to GAWB 0 days Mon 10/03/08 Mon 10/03/08 149 30% engineering info issued to estimators 0 days Mon 10/03/08 Mon 10/03/08 150 GAWB review 10 days Tue 11/03/08 Mon 24/03/08 151 Eng for 50% Design 30 days Tue 11/03/08 Mon 21/04/08 152 Drafting for 50% Design 30 days Tue 11/03/08 Mon 21/04/08 153 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08 154 Internal 50% design review 1 day? Tue 22/04/08 Tue 22/04/08 155 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08 156 Information for 50% design review issued to GAWB 0 days Tue 22/04/08 Tue 22/04/08 157 50% engineering info issued to estimators 0 days Tue 22/04/08 Tue 22/04/08 158 GAWB review 10 days Wed 23/04/08 Tue 6/05/08 159 Eng for 80% Design 25 days Tue 22/04/08 Mon 26/05/08 160 Drafting for 80% Design 25 days Tue 22/04/08 Mon 26/05/08 161 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08 162 Internal 80% design review 1 day? Tue 27/05/08 Tue 27/05/08 163 Information for 80% design review issued to GAWB 0 days Tue 27/05/08 Tue 27/05/08 164 80% engineering info issued to estimators 0 days Tue 27/05/08 Tue 27/05/08 165 GAWB review 10 days Wed 28/05/08 Tue 10/06/08 166 HAZOP 1 day Wed 11/06/08 Wed 11/06/08 167 Package up work as is for FINAL RAP 5 days Thu 29/05/08 Wed 4/06/08 168 Eng to IFC 25 days Tue 27/05/08 Mon 30/06/08 169 Drafting to IFC 25 days Tue 27/05/08 Mon 30/06/08 170 Final review and sign off 3 days Tue 1/07/08 Thu 3/07/08 171 Issue Intake documentation for IFC 0 days Thu 3/07/08 Thu 3/07/08 172 173 Aldoga Resevoir 176 days Mon 7/01/08 Mon 8/09/08 174 Generic engineering independent of decision process 20 days Tue 22/01/08 Mon 18/02/08 175 Eng for 30% Design 51 days Mon 7/01/08 Mon 17/03/08 176 Drafting for 30% Design 41 days Mon 21/01/08 Mon 17/03/08 177 Internal 30% design review 1 day Thu 20/03/08 Thu 20/03/08 178 Information for 30% design review issued to GAWB 0 days Thu 20/03/08 Thu 20/03/08 179 30% engineering info issued to estimators 0 days Thu 20/03/08 Thu 20/03/08 180 GAWB review 10 days Fri 21/03/08 Thu 3/04/08 181 Eng for 50% Design 40 days Thu 20/03/08 Wed 14/05/08 182 Drafting for 50% Design 40 days Thu 20/03/08 Wed 14/05/08 183 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08 184 Internal 50% design review 1 day Tue 20/05/08 Tue 20/05/08 185 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08 186 Information for 50% design review issued to GAWB 0 days Tue 20/05/08 Tue 20/05/08 187 50% engineering info issued to estimators 0 days Tue 20/05/08 Tue 20/05/08 188 GAWB review 10 days Wed 21/05/08 Tue 3/06/08 189 Eng for 80% Design 52 days Mon 19/05/08 Tue 29/07/08 190 Drafting for 80% Design 52 days Mon 19/05/08 Tue 29/07/08 191 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08 192 Internal 80% design review 1 day Wed 30/07/08 Wed 30/07/08 193 Information for 80% design review issued to GAWB 0 days Wed 30/07/08 Wed 30/07/08 194 80% engineering info issued to estimators 0 days Wed 30/07/08 Wed 30/07/08 195 GAWB review 10 days Thu 31/07/08 Wed 13/08/08 196 HAZOP 1 day Thu 14/08/08 Thu 14/08/08 197 Package up work as is for FINAL RAP 5 days Thu 29/05/08 Wed 4/06/08 198 Eng to IFC 25 days Thu 31/07/08 Wed 3/09/08 199 Drafting to IFC 25 days Thu 31/07/08 Wed 3/09/08 200 Final review and sign off 3 days Thu 4/09/08 Mon 8/09/08 201 Issue documentation for Construction IFC 0 days Mon 8/09/08 Mon 8/09/08 202 203 Pipeline - WTP to Relift 217 days? Mon 17/12/07 Tue 28/10/08 204 Generic engineering independent of decision process 65 days Mon 17/12/07 Fri 28/03/08 205 Eng for 30% Design 65 days Mon 14/01/08 Fri 11/04/08 206 Drafting for 30% Design 55 days Mon 28/01/08 Fri 11/04/08 207 Internal 30% design review 1 day Wed 16/04/08 Wed 16/04/08 208 Information for 30% design review issued to GAWB 0 days Wed 16/04/08 Wed 16/04/08 209 30% engineering info issued to estimators 0 days Wed 16/04/08 Wed 16/04/08 210 GAWB review 10 days Thu 17/04/08 Wed 30/04/08 211 Eng for 50% Design 50 days Wed 16/04/08 Tue 24/06/08 212 Drafting for 50% Design 50 days Wed 16/04/08 Tue 24/06/08 213 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08 214 Internal 50% design review 1 day Mon 30/06/08 Mon 30/06/08 215 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08 216 Information for 50% design review issued to GAWB 0 days Mon 30/06/08 Mon 30/06/08 217 50% engineering info issued to estimators 0 days Mon 30/06/08 Mon 30/06/08 218 GAWB review 10 days Tue 1/07/08 Mon 14/07/08 219 Eng for 80% Design 46 days Tue 1/07/08 Tue 2/09/08 220 Drafting for 80% Design 46 days Tue 1/07/08 Tue 2/09/08 221 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08 222 Internal 80% design review 1 day? Fri 5/09/08 Fri 5/09/08 223 Information for 80% design review issued to GAWB 0 days Fri 5/09/08 Fri 5/09/08 224 80% engineering info issued to estimators 0 days Fri 5/09/08 Fri 5/09/08 225 GAWB review 10 days Mon 8/09/08 Fri 19/09/08 226 HAZOP 1 day Mon 22/09/08 Mon 22/09/08 227 Package up work as is for FINAL RAP 5 days Thu 29/05/08 Wed 4/06/08 228 Eng to IFC 35 days Fri 5/09/08 Thu 23/10/08 229 Drafting to IFC 35 days Fri 5/09/08 Thu 23/10/08 10/03 10/03 22/04 22/04 27/05 27/05 3/07 10/03 10/03 22/04 22/04 27/05 27/05 3/07 20/03 20/03 20/05 20/05 30/07 30/07 8/09 16/04 16/04 30/06 30/06 5/09 5/09 22 9 27 15 2 20 7 25 14 1 19 7 25 12 30 18 5 23 10 28 16 3 22 Oct '07 3 Dec '07 14 Jan '08 25 Feb '08 7 Apr '08 19 May '08 30 Jun '08 11 Aug '08 22 Sep '08 3 Nov '08 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Progress Deadline CDUJV Detail Design Schedule (Rev_H) 19-12-07 Page 2 Project: Maunsell example schedule Date: Sun 15/01/17
  • 3.
    ID Task NameDuration Start Finish 230 Final review and sign off 3 days Fri 24/10/08 Tue 28/10/08 231 Issue documentation for Construction IFC 0 days Tue 28/10/08 Tue 28/10/08 232 233 Pipeline - Relift to Aldoga 173 days? Mon 17/12/07 Wed 27/08/08 234 Generic engineering independent of decision process 65 days Mon 17/12/07 Fri 28/03/08 235 Eng for 30% Design 55 days Mon 14/01/08 Fri 28/03/08 236 Drafting for 30% Design 45 days Mon 28/01/08 Fri 28/03/08 237 Internal 30% design review 1 day Wed 2/04/08 Wed 2/04/08 238 Information for 30% design review issued to GAWB 0 days Wed 2/04/08 Wed 2/04/08 239 30% engineering info issued to estimators 0 days Wed 2/04/08 Wed 2/04/08 240 GAWB review 10 days Thu 3/04/08 Wed 16/04/08 241 Eng for 50% Design 38 days Fri 4/04/08 Tue 27/05/08 242 Drafting for 50% Design 38 days Fri 4/04/08 Tue 27/05/08 243 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08 244 Internal 50% design review 1 day Wed 28/05/08 Wed 28/05/08 245 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08 246 Information for 50% design review issued to GAWB 0 days Wed 28/05/08 Wed 28/05/08 247 50% engineering info issued to estimators 0 days Wed 28/05/08 Wed 28/05/08 248 GAWB review 10 days Thu 29/05/08 Wed 11/06/08 249 Eng for 80% Design 38 days Wed 28/05/08 Fri 18/07/08 250 Drafting for 80% Design 38 days Wed 28/05/08 Fri 18/07/08 251 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08 252 Internal 80% design review 1 day? Mon 21/07/08 Mon 21/07/08 253 Information for 80% design review issued to GAWB 0 days Mon 21/07/08 Mon 21/07/08 254 80% engineering info issued to estimators 0 days Mon 21/07/08 Mon 21/07/08 255 GAWB review 10 days Tue 22/07/08 Mon 4/08/08 256 HAZOP 1 day Tue 5/08/08 Tue 5/08/08 257 Package up work as is for FINAL RAP 5 days Thu 29/05/08 Wed 4/06/08 258 Eng to IFC 25 days Mon 21/07/08 Fri 22/08/08 259 Drafting to IFC 25 days Mon 21/07/08 Fri 22/08/08 260 Final review and sign off 3 days Mon 25/08/08 Wed 27/08/08 261 Issue documentation for Construction IFC 0 days Wed 27/08/08 Wed 27/08/08 262 263 Pipeline - Aldoga to Mt Miller 173 days? Mon 17/12/07 Wed 27/08/08 264 Generic engineering independent of decision process 65 days Mon 17/12/07 Fri 28/03/08 265 Eng for 30% Design 55 days Mon 14/01/08 Fri 28/03/08 266 Drafting for 30% Design 45 days Mon 28/01/08 Fri 28/03/08 267 Internal 30% design review 1 day Wed 2/04/08 Wed 2/04/08 268 Information for 30% design review issued to GAWB 0 days Wed 2/04/08 Wed 2/04/08 269 30% engineering info issued to estimators 0 days Wed 2/04/08 Wed 2/04/08 270 GAWB review 10 days Thu 3/04/08 Wed 16/04/08 271 Eng for 50% Design 38 days Fri 4/04/08 Tue 27/05/08 272 Drafting for 50% Design 38 days Fri 4/04/08 Tue 27/05/08 273 Incorporate GAWB comments into Design 5 days Mon 7/04/08 Fri 11/04/08 274 Internal 50% design review 1 day Wed 28/05/08 Wed 28/05/08 275 Package up work as is for DRAFT RAP 5 days Fri 28/03/08 Thu 3/04/08 276 Information for 50% design review issued to GAWB 0 days Wed 28/05/08 Wed 28/05/08 277 50% engineering info issued to estimators 0 days Wed 28/05/08 Wed 28/05/08 278 GAWB review 10 days Thu 29/05/08 Wed 11/06/08 279 Eng for 80% Design 38 days Wed 28/05/08 Fri 18/07/08 280 Drafting for 80% Design 38 days Wed 28/05/08 Fri 18/07/08 281 Incorporate GAWB comments into Design 5 days Thu 12/06/08 Wed 18/06/08 282 Internal 80% design review 1 day? Mon 21/07/08 Mon 21/07/08 283 Information for 80% design review issued to GAWB 0 days Mon 21/07/08 Mon 21/07/08 284 80% engineering info issued to estimators 0 days Mon 21/07/08 Mon 21/07/08 285 GAWB review 10 days Tue 22/07/08 Mon 4/08/08 286 HAZOP 1 day Tue 5/08/08 Tue 5/08/08 287 Package up work as is for FINAL RAP 5 days Thu 29/05/08 Wed 4/06/08 288 Eng to IFC 25 days Mon 21/07/08 Fri 22/08/08 289 Drafting to IFC 25 days Mon 21/07/08 Fri 22/08/08 290 Final review and sign off 3 days Mon 25/08/08 Wed 27/08/08 291 Issue documentation for Construction IFC 0 days Wed 27/08/08 Wed 27/08/08 28/10 2/04 2/04 28/05 28/05 21/07 21/07 27/08 2/04 2/04 28/05 28/05 21/07 21/07 27/08 22 9 27 15 2 20 7 25 14 1 19 7 25 12 30 18 5 23 10 28 16 3 22 Oct '07 3 Dec '07 14 Jan '08 25 Feb '08 7 Apr '08 19 May '08 30 Jun '08 11 Aug '08 22 Sep '08 3 Nov '08 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Progress Deadline CDUJV Detail Design Schedule (Rev_H) 19-12-07 Page 3 Project: Maunsell example schedule Date: Sun 15/01/17
  • 4.
    3 21 927 14 1 19 9 27 14 2 20 7 25 13 31 18 5 23 11 29 16 4 22 9 27 14 4 22 3 Nov '08 15 Dec '08 26 Jan '09 9 Mar '09 20 Apr '09 1 Jun '09 13 Jul '09 24 Aug '09 5 Oct '09 16 Nov '09 28 Dec '09 8 Feb '10 22 Mar '10 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Progress Deadline CDUJV Detail Design Schedule (Rev_H) 19-12-07 Page 4 Project: Maunsell example schedule Date: Sun 15/01/17
  • 5.
    3 21 927 14 1 19 9 27 14 2 20 7 25 13 31 18 5 23 11 29 16 4 22 9 27 14 4 22 3 Nov '08 15 Dec '08 26 Jan '09 9 Mar '09 20 Apr '09 1 Jun '09 13 Jul '09 24 Aug '09 5 Oct '09 16 Nov '09 28 Dec '09 8 Feb '10 22 Mar '10 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Progress Deadline CDUJV Detail Design Schedule (Rev_H) 19-12-07 Page 5 Project: Maunsell example schedule Date: Sun 15/01/17
  • 6.
    28/10 3 21 927 14 1 19 9 27 14 2 20 7 25 13 31 18 5 23 11 29 16 4 22 9 27 14 4 22 3 Nov '08 15 Dec '08 26 Jan '09 9 Mar '09 20 Apr '09 1 Jun '09 13 Jul '09 24 Aug '09 5 Oct '09 16 Nov '09 28 Dec '09 8 Feb '10 22 Mar '10 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Progress Deadline CDUJV Detail Design Schedule (Rev_H) 19-12-07 Page 6 Project: Maunsell example schedule Date: Sun 15/01/17