Objective:
Looking for a challenging career in your esteemed organization to contribute my knowledge and
experience for organizational and self growth. I am having multiple field experiences and
qualifications in MECHANICAL Engineering, Civil Engineering with Software Engineering
proficiency. So that employer can utilize my services in multi task works.
Experience summary:
Having 20 Years of experience in MECHANICAL Construction field with different Industrial
construction, supervision and modularization works and prepared work schedule plans, Bills
preparation & checking. Planned, supervised and executed enormous works like piping works and
Equipment erections in Chemical, Refinery and LNG plants. Also attended for Refinery and Gas
Plant shutdown works. Having the knowledge of software's. Currently working in Worley parsons
Arabian Industries JV as Sr. Project Engineer for South PDO IMC project based at HO in Muscat,
OMAN. I worked along with GlassPoint in Solar steam generation pilot at Amal, KHPT (Korea),
Cust-O-Fab (USA) and Cooperheat (UK) in Reliance Petroleum Refinery. KO Drum, Flare
(Utilities) area rack piping, TIE-IN’s and continuation lines in CCC for Qatar Gas II Expansion
project and QG I Live plant in QATAR. As a Construction Manager in KCEL I was handling the
project of 3 lac ID piping fabrication and erection, 950 MT of structural and equipment’s erection
independently at site. Trained in HSE & H2S.
Educational Qualifications:
1995 : AMIE (Mechanical Engg. Degree) from Institution of Engineers (India),
Kolkata.
1992 : DCA (Diploma in Computer Applications) from National Center for Computing
Techniques (NCCT), Chennai.
1989 : DCE (Diploma in Civil Engg.) from State board of Technical Education, A.P.
1985 : SSC from State board of secondary school education, A.P.
Other skills:
MS – Office, AUTOCAD-2000, C – Language, Visual Basic, SAP (MM, SD & ABAP/4).
Professional Experience:
Feb2015 – Till Date- Working as Sr. Project Engineer in Worley Parsons Arabian Industries JV
for PDO IMC contract at MUSCAT, OMAN
Jan2012 – Jan 2015 – Worked as Senior Project Engineer in Arabian Industries Projects LLC for
EPC of Gas supply pipeline at Salalah free Zone Area
Oman oil tank repair work at MAF
Fire Water Storage Tank Construction at Rima
GlassPoint - Solar Steam Generation Pilot Project, OMAN.
Sep2008 – Dec2011 – Worked as Project Engineer in Worley Parsons Arabian Industries JV for
PDO EMC contract at MUSCAT, OMAN.
Sep2007 - Aug2008 - Worked as Construction Manager in Kirloskar Constructions and Engineers
Ltd. for NALCO Alumina Refinery Expansion Project at Damanjodi, Orissa.
May2006-July2007 - Worked as Piping Engineer in Consolidated Contractors Intn'l Company for
QATAR GAS II LNG Expansion Project, at QATAR.
2001-2006 - Worked as Construction Engineer in Reliance Industries Ltd. In Jamnagar
Petroleum Refinery, Gujarat.
1997-2001- Worked as Site In charge in Divi's Laboratories Ltd., at Visakhapatnam, A.P.
1995-1997 - Worked as Site Engineer in C. Eswar Reddy &Co. Engineers & contractors at
Hyderabad, A.P.
Personal Details:
Name : Kurupati Ramesh Babu
Father's Name : K. Rangaiah
Date of Birth : 01-06-1970
Marital Status : Married
Passport Details : No. H0070840 Issuid-01/08/2008, Expiry-31/07/2018.
Permanent Address : Kottalapalli(V), Vidapanakal (M),
Anantapur (Dt.), Andhra Pradesh, India - 515870.
Projects Involved: Under my supervision and involvement executed many projects, out of
which some of the projects are listed below,
#1 Worley Parsons Arabian Industries – JV, PDO IMC projects (OMAN)
Job: Project Coordination and Execution from coast (Maintenance & Construction).
Role: Sr. Project Engineer
Responsibilities:
 Responsible for the PDO maintenance works particularly Tanks & Static equipment’s
internal cleaning and refurbishment works in South Oman.
ď‚· Project initiation, preparation of scope, Schedules, material arrangement, preparation of
Estimation s and coordination with client for the various approvals.
ď‚· Preparation of procedures and method statements required for execution of job.
ď‚· Coordinating for arranging the third party vendors for specific works
ď‚· Reporting projects progress and achievements
ď‚· Arranging the resources, executing and completing the works as per schedules
#2 Arabian Industries Projects LLC
Designation: Project Manager for Gas supply pipeline at Salalah Free Zone Area
Sr. Project Engineer for Rima Tank Construction project at Rima, Oman.
Sr. Project Engineer for Oman Oil Tank project at MAF, Muscat.
Sr. Project Engineer for Solar Steam Generation Pilot project, OMAN.
Job Project Planning, Budget preparation, Coordination & Construction
Role Sr. Project Engineer
Responsibilities: Industrial facilities setup, Project modularization and team mobilization,
Project Planning and scheduling the activities with respect to target dates, Reporting,
Manpower and Resources planning, coordinating with other depts for timely support to ensure
continuous progress of the work. Resolving technical and work related issues by discussing
with client and raising the work variations over the scope of work. Arranging the resources
according to the work load and taking the project ownership to complete within time and
budget. Managing and monitoring construction team for execution of work with HSE and
Quality compliance.
#3 Worley Parsons Arabian Industries – JV, PDO EMC projects (OMAN)
Job: Project Coordination from coast (Construction & Maintenance).
Role: Project Engineer
Responsibilities:
To manage, direct and supervise all direct project functions, thus ensuring cost effective and
efficient achievement of all works.
Coordinating the construction works and managing the projects at PDO stations in south Oman.
Prioritisation of designated projects in accordance with available resources.
Liaise with management to ensure the needs of the asset are met as required.
Management of all works relating to the asset from registration to completion.
Overall supervision of individual projects through the designated project engineering team.
Coordinating for the shutdown activities, tie-ins, hook-ups and commissioning.
Managing the repair and maintenance works of the Storage Tanks.
Motivate, manage and develop the projects engineering personnel resources assigned to his
responsibility.
Ensure the Project Team obtains the necessary resources to perform their project objectives.
Reporting projects progress and achievements, to the required level of detail to the Engineering
Manager.
Assisting during the commissioning phase of the project.
Responsible for working within the provisions and guidelines of the Quality Assurance system.
Responsible for personal safety, safe working practices, understand and follow OH&S
procedures.
#4 Kirloskar Constructions and Engineers Limited - Alumina Refinery Expansion Project
NALCO, (Orissa)
Job: Piping, Structural, Equipment and civil works.
Role: Construction Manager
Responsible for all project activities which include piping fabrication, Structural fabrication,
equipment erections and civil works. Interacting with consultant and client for resolving the site
queries, progress review meetings and planning for tie-ins. Ensuring smooth construction
activities and coordination between departments. Forecasting the budget, Equipments and
manpower requirements and reporting to Head office. Allocating the specific works to sub
contractors and reviewing their progress. Ensuring that material availability, progress according
to the plans, safety, project completion within time. Ensuring proper facilities to site staff and
workmen.
#5 Consolidated Contractors International Company - Qatar Gas II LNG Expansion Project
(QATAR)
Job: Piping works - Flare / K O Drum Offsite Area and TIE-IN Works.
Role: Piping Engineer
Responsible for, Job coordination and Construction works.
Ensuring all safety regulations are implementing on site.
Ensuring all quality requirements have been followed on site.
Ensuring that all subordinates aware of the work schedule and daily progress to be monitored in
order to ensure that the work on site is going according to the schedule. Raising T Q’s to the
client for technical mismatches.
Ensuring that every crew producing the planed productivity.
Monitor movement of manpower and equipment according to the site requirements and
progress required.
Maintain integrity between multinational technocrats.
Clearing the test packs with as built measurements of piping and as per drawings.
Ensuring the daily reports updated promptly to monitor the progress and preparing the plans
and schedules.
Approaching all the subordinates by regular meeting daily talk to share the problems in order to
solve on spot and communicating, reporting to the management.
Construction of rack piping (QG II), GRE Firewater lines and TIE-IN works in the live plant
(Qatar Gas I).
#6 Reliance Industries Ltd. – Petroleum Refinery (Jamnagar)
Job: Piping works - Coker plant
Shutdown work – FCCU Plant (Reactor/Regenerator)
Role: Construction Engineer
Responsible for studying the isometric drawings, estimating the quantity of work and routing,
Allotting the daily quantum of work to the workmen, Inspecting the spools and monitoring
spools erection, fit ups, alignment, valves & instrument positions and following the welding
procedures, marking the supports as per drawings with field modifications, preparing the field
joints & lines for NDT tests and Clearing the iso's.
Responsible to complete the work in limited timeframes. Studying the drawings and
inspecting the material. Scaffolding made inside the vessels Regenerator outer cyclone diplegs
are cut in the position using Clamshell cold cutting machine, removed and replaced with 22
new diplegs. Another 22 inner cyclones are cut and repaired for the damages with patch plates
and reinstalled. Valves as per requirement are cut with Colt Hydro cutting machine on the
regenerator shell and fixed new. Hex-mesh fixed and welded in conical portion of cyclone for
refractory lining.
Reactor Baffles removed and replaced with new baffles. Steam distribution nozzles
installed, Spent cat nozzle (A-28) removed by cutting with Robotic plasma cutting machine and
replaced new one. Hex-mesh fixed on the reactor shell and riser. Followed the preheating,
testing of weld joints, post heating, house keeping activities and also taken care of the safety
precautions.
Retail outlets construction, Towers erection, decision taking as per site conditions,
supervising the work execution, construction of Telo's antenna platforms, preparing inspection
reports, bills preparation and checking with stores and returns.
#7 Divi's Laboratories Ltd. - Project Construction (Visakhapatnam)
Job: Plant construction & Commissioning
Role: Site In charge
Responsible for quality of work and reporting the status, following construction of structural
works, Equipments like GLR's, SSR's & FRP tubs erection on platforms and Erection of storage
tanks using cranes. Pipeline supporting structures and pipelines from boiler, DM water plant to
production blocks, pipelines to supply acids from storage tanks to reactors for the process.
Brine storage tanks and supply lines with puff insulation. Fiber glass wool insulations to
pipelines and reactors. Approximately 1 km under ground pipeline laid from Jetty to plant for
sea water pumping.
Incinerator erection and commissioning along with chimney which includes erection of fire
drums with fire nozzles, Quenching tank with water spraying nozzles, water & fuel storage
tanks with piping, ID & FD Fans with required ducting and maintenance.
Purified water system construction with SS pipelines which includes filters and UV treatment
system with pumps and storage tanks. Erection and maintenance of AHU's with HEPA filters
and ducting for supply of clean air to Pharma blocks. Erection of Blowers, hood's, decanters,
Owens, dryers etc. with necessary piping works. And also followed shutdown work for FDA
audit.
#8 C. Eswar Reddy & Co (Contractors)
Job: Construction works
Role: Site Engineer
Worked as site engineer and following the various Mechanical and Civil works for different
clients, Estimating the manpower and supervising the site requirements. Following the clients
requirements and completing the works within time. Following the painting, Insulation and
Aluminium cladding works. Preparing the part and final bills by taking the field measurements.
K. Ramesh Babu.

RAMESH_Resume

  • 1.
    RESUME Kurupati Ramesh Babu Sr.ProjectEngineer Arabian Industries LLC Muscat, OMAN. Mobile: +968-98178191 Email: kkpapa@yahoo.com ramesh_b_k@rediffmail.com --------------------------------------------------------------------------------------------------------------------------- Objective: Looking for a challenging career in your esteemed organization to contribute my knowledge and experience for organizational and self growth. I am having multiple field experiences and qualifications in MECHANICAL Engineering, Civil Engineering with Software Engineering proficiency. So that employer can utilize my services in multi task works. Experience summary: Having 20 Years of experience in MECHANICAL Construction field with different Industrial construction, supervision and modularization works and prepared work schedule plans, Bills preparation & checking. Planned, supervised and executed enormous works like piping works and Equipment erections in Chemical, Refinery and LNG plants. Also attended for Refinery and Gas Plant shutdown works. Having the knowledge of software's. Currently working in Worley parsons Arabian Industries JV as Sr. Project Engineer for South PDO IMC project based at HO in Muscat, OMAN. I worked along with GlassPoint in Solar steam generation pilot at Amal, KHPT (Korea), Cust-O-Fab (USA) and Cooperheat (UK) in Reliance Petroleum Refinery. KO Drum, Flare (Utilities) area rack piping, TIE-IN’s and continuation lines in CCC for Qatar Gas II Expansion project and QG I Live plant in QATAR. As a Construction Manager in KCEL I was handling the project of 3 lac ID piping fabrication and erection, 950 MT of structural and equipment’s erection independently at site. Trained in HSE & H2S. Educational Qualifications: 1995 : AMIE (Mechanical Engg. Degree) from Institution of Engineers (India), Kolkata. 1992 : DCA (Diploma in Computer Applications) from National Center for Computing Techniques (NCCT), Chennai. 1989 : DCE (Diploma in Civil Engg.) from State board of Technical Education, A.P. 1985 : SSC from State board of secondary school education, A.P.
  • 2.
    Other skills: MS –Office, AUTOCAD-2000, C – Language, Visual Basic, SAP (MM, SD & ABAP/4). Professional Experience: Feb2015 – Till Date- Working as Sr. Project Engineer in Worley Parsons Arabian Industries JV for PDO IMC contract at MUSCAT, OMAN Jan2012 – Jan 2015 – Worked as Senior Project Engineer in Arabian Industries Projects LLC for EPC of Gas supply pipeline at Salalah free Zone Area Oman oil tank repair work at MAF Fire Water Storage Tank Construction at Rima GlassPoint - Solar Steam Generation Pilot Project, OMAN. Sep2008 – Dec2011 – Worked as Project Engineer in Worley Parsons Arabian Industries JV for PDO EMC contract at MUSCAT, OMAN. Sep2007 - Aug2008 - Worked as Construction Manager in Kirloskar Constructions and Engineers Ltd. for NALCO Alumina Refinery Expansion Project at Damanjodi, Orissa. May2006-July2007 - Worked as Piping Engineer in Consolidated Contractors Intn'l Company for QATAR GAS II LNG Expansion Project, at QATAR. 2001-2006 - Worked as Construction Engineer in Reliance Industries Ltd. In Jamnagar Petroleum Refinery, Gujarat. 1997-2001- Worked as Site In charge in Divi's Laboratories Ltd., at Visakhapatnam, A.P. 1995-1997 - Worked as Site Engineer in C. Eswar Reddy &Co. Engineers & contractors at Hyderabad, A.P. Personal Details: Name : Kurupati Ramesh Babu Father's Name : K. Rangaiah Date of Birth : 01-06-1970 Marital Status : Married Passport Details : No. H0070840 Issuid-01/08/2008, Expiry-31/07/2018. Permanent Address : Kottalapalli(V), Vidapanakal (M), Anantapur (Dt.), Andhra Pradesh, India - 515870. Projects Involved: Under my supervision and involvement executed many projects, out of which some of the projects are listed below, #1 Worley Parsons Arabian Industries – JV, PDO IMC projects (OMAN) Job: Project Coordination and Execution from coast (Maintenance & Construction). Role: Sr. Project Engineer
  • 3.
    Responsibilities:  Responsible forthe PDO maintenance works particularly Tanks & Static equipment’s internal cleaning and refurbishment works in South Oman.  Project initiation, preparation of scope, Schedules, material arrangement, preparation of Estimation s and coordination with client for the various approvals.  Preparation of procedures and method statements required for execution of job.  Coordinating for arranging the third party vendors for specific works  Reporting projects progress and achievements  Arranging the resources, executing and completing the works as per schedules #2 Arabian Industries Projects LLC Designation: Project Manager for Gas supply pipeline at Salalah Free Zone Area Sr. Project Engineer for Rima Tank Construction project at Rima, Oman. Sr. Project Engineer for Oman Oil Tank project at MAF, Muscat. Sr. Project Engineer for Solar Steam Generation Pilot project, OMAN. Job Project Planning, Budget preparation, Coordination & Construction Role Sr. Project Engineer Responsibilities: Industrial facilities setup, Project modularization and team mobilization, Project Planning and scheduling the activities with respect to target dates, Reporting, Manpower and Resources planning, coordinating with other depts for timely support to ensure continuous progress of the work. Resolving technical and work related issues by discussing with client and raising the work variations over the scope of work. Arranging the resources according to the work load and taking the project ownership to complete within time and budget. Managing and monitoring construction team for execution of work with HSE and Quality compliance. #3 Worley Parsons Arabian Industries – JV, PDO EMC projects (OMAN) Job: Project Coordination from coast (Construction & Maintenance). Role: Project Engineer Responsibilities: To manage, direct and supervise all direct project functions, thus ensuring cost effective and efficient achievement of all works. Coordinating the construction works and managing the projects at PDO stations in south Oman. Prioritisation of designated projects in accordance with available resources. Liaise with management to ensure the needs of the asset are met as required. Management of all works relating to the asset from registration to completion. Overall supervision of individual projects through the designated project engineering team. Coordinating for the shutdown activities, tie-ins, hook-ups and commissioning.
  • 4.
    Managing the repairand maintenance works of the Storage Tanks. Motivate, manage and develop the projects engineering personnel resources assigned to his responsibility. Ensure the Project Team obtains the necessary resources to perform their project objectives. Reporting projects progress and achievements, to the required level of detail to the Engineering Manager. Assisting during the commissioning phase of the project. Responsible for working within the provisions and guidelines of the Quality Assurance system. Responsible for personal safety, safe working practices, understand and follow OH&S procedures. #4 Kirloskar Constructions and Engineers Limited - Alumina Refinery Expansion Project NALCO, (Orissa) Job: Piping, Structural, Equipment and civil works. Role: Construction Manager Responsible for all project activities which include piping fabrication, Structural fabrication, equipment erections and civil works. Interacting with consultant and client for resolving the site queries, progress review meetings and planning for tie-ins. Ensuring smooth construction activities and coordination between departments. Forecasting the budget, Equipments and manpower requirements and reporting to Head office. Allocating the specific works to sub contractors and reviewing their progress. Ensuring that material availability, progress according to the plans, safety, project completion within time. Ensuring proper facilities to site staff and workmen. #5 Consolidated Contractors International Company - Qatar Gas II LNG Expansion Project (QATAR) Job: Piping works - Flare / K O Drum Offsite Area and TIE-IN Works. Role: Piping Engineer Responsible for, Job coordination and Construction works. Ensuring all safety regulations are implementing on site. Ensuring all quality requirements have been followed on site. Ensuring that all subordinates aware of the work schedule and daily progress to be monitored in order to ensure that the work on site is going according to the schedule. Raising T Q’s to the client for technical mismatches. Ensuring that every crew producing the planed productivity. Monitor movement of manpower and equipment according to the site requirements and progress required. Maintain integrity between multinational technocrats. Clearing the test packs with as built measurements of piping and as per drawings.
  • 5.
    Ensuring the dailyreports updated promptly to monitor the progress and preparing the plans and schedules. Approaching all the subordinates by regular meeting daily talk to share the problems in order to solve on spot and communicating, reporting to the management. Construction of rack piping (QG II), GRE Firewater lines and TIE-IN works in the live plant (Qatar Gas I). #6 Reliance Industries Ltd. – Petroleum Refinery (Jamnagar) Job: Piping works - Coker plant Shutdown work – FCCU Plant (Reactor/Regenerator) Role: Construction Engineer Responsible for studying the isometric drawings, estimating the quantity of work and routing, Allotting the daily quantum of work to the workmen, Inspecting the spools and monitoring spools erection, fit ups, alignment, valves & instrument positions and following the welding procedures, marking the supports as per drawings with field modifications, preparing the field joints & lines for NDT tests and Clearing the iso's. Responsible to complete the work in limited timeframes. Studying the drawings and inspecting the material. Scaffolding made inside the vessels Regenerator outer cyclone diplegs are cut in the position using Clamshell cold cutting machine, removed and replaced with 22 new diplegs. Another 22 inner cyclones are cut and repaired for the damages with patch plates and reinstalled. Valves as per requirement are cut with Colt Hydro cutting machine on the regenerator shell and fixed new. Hex-mesh fixed and welded in conical portion of cyclone for refractory lining. Reactor Baffles removed and replaced with new baffles. Steam distribution nozzles installed, Spent cat nozzle (A-28) removed by cutting with Robotic plasma cutting machine and replaced new one. Hex-mesh fixed on the reactor shell and riser. Followed the preheating, testing of weld joints, post heating, house keeping activities and also taken care of the safety precautions. Retail outlets construction, Towers erection, decision taking as per site conditions, supervising the work execution, construction of Telo's antenna platforms, preparing inspection reports, bills preparation and checking with stores and returns. #7 Divi's Laboratories Ltd. - Project Construction (Visakhapatnam) Job: Plant construction & Commissioning Role: Site In charge Responsible for quality of work and reporting the status, following construction of structural works, Equipments like GLR's, SSR's & FRP tubs erection on platforms and Erection of storage
  • 6.
    tanks using cranes.Pipeline supporting structures and pipelines from boiler, DM water plant to production blocks, pipelines to supply acids from storage tanks to reactors for the process. Brine storage tanks and supply lines with puff insulation. Fiber glass wool insulations to pipelines and reactors. Approximately 1 km under ground pipeline laid from Jetty to plant for sea water pumping. Incinerator erection and commissioning along with chimney which includes erection of fire drums with fire nozzles, Quenching tank with water spraying nozzles, water & fuel storage tanks with piping, ID & FD Fans with required ducting and maintenance. Purified water system construction with SS pipelines which includes filters and UV treatment system with pumps and storage tanks. Erection and maintenance of AHU's with HEPA filters and ducting for supply of clean air to Pharma blocks. Erection of Blowers, hood's, decanters, Owens, dryers etc. with necessary piping works. And also followed shutdown work for FDA audit. #8 C. Eswar Reddy & Co (Contractors) Job: Construction works Role: Site Engineer Worked as site engineer and following the various Mechanical and Civil works for different clients, Estimating the manpower and supervising the site requirements. Following the clients requirements and completing the works within time. Following the painting, Insulation and Aluminium cladding works. Preparing the part and final bills by taking the field measurements. K. Ramesh Babu.