Submit bond and nsurance documents
Start: Mon 08-05-23ID: 4
Finish: Tue 09-05-23 Dur: 2 days
Res:
prepare and submit project schedule
Start: Wed 10-05-23ID: 5
Finish: Thu 11-05-23 Dur: 2 days
Res:
prepare and submit schedule of values
Start: Fri 12-05-23 ID: 6
Finish: Mon 15-05-23Dur: 2 days
Res:
obtain building permits
Start: Mon 08-05-23ID: 7
Finish: Thu 11-05-23 Dur: 4 days
Res:
submit preliminary shop drawings
Start: Fri 12-05-23 ID: 8
Finish: Thu 25-05-23 Dur: 2 wks
Res:
submit monthly requests for payment
Start: Mon 08-05-23ID: 9
Finish: Mon 08-05-23Dur: 1 day
Res:
Drawing
Start: Tue 09-05-23ID: 10
Finish: Mon 14-08-23
Dur: 70 days
Comp: 0%
submit shop drawings and order long lead items - Steel
Start: Tue 09-05-23 ID: 11
Finish: Mon 22-05-23Dur: 2 wks
Res:
submit shop drawings and order long lead items - roofing
Start: Fri 26-05-23 ID: 12
Finish: Thu 08-06-23 Dur: 2 wks
Res:
submit shop drawings and order long lead items - elevator
Start: Fri 26-05-23 ID: 13
Finish: Thu 08-06-23 Dur: 2 wks
Res:
submit shop drawings and order long lead items - plumbing
Start: Fri 26-05-23 ID: 14
Finish: Thu 08-06-23 Dur: 2 wks
Res:
submit shop drawings and order long lead items - electrical
Start: Fri 26-05-23 ID: 15
Finish: Thu 08-06-23 Dur: 2 wks
Res:
submit shop drawings and order long lead items - HVAC
Start: Fri 26-05-23 ID: 16
Finish: Thu 08-06-23 Dur: 2 wks
Res:
Detail, fabricate and deliver steel
Start: Tue 23-05-23 ID: 17
Finish: Mon 14-08-23Dur: 12 wks
Res:
Temporary
Start: Mon 08-05-23
ID: 18
Finish: Fri 19-05-23 Dur: 10 days
Comp: 0%
Install temporary power
Start: Mon 08-05-23ID: 19
Finish: Tue 09-05-23 Dur: 2 days
Res:
Install temporary water service
Start: Mon 08-05-23ID: 20
Finish: Tue 09-05-23 Dur: 2 days
Res:
set up site office
Start: Wed 10-05-23ID: 21
Finish: Fri 12-05-23 Dur: 3 days
Res:
set line and grade benchmarks
Start: Mon 15-05-23ID: 22
Finish: Wed 17-05-23Dur: 3 days
Res:
prepare site lay down yard and temporary fencing
Start: Thu 18-05-23 ID: 23
Finish: Fri 19-05-23 Dur: 2 days
Res:
Clean
Start: Mon 22-05-23
ID: 24
Finish: Mon 10-07-23
Dur: 36 days
Comp: 0%
clear and grub site
Start: Mon 22-05-23 ID: 25
Finish: Wed 24-05-23Dur: 3 days
Res:
stone site access and temporary parking area
Start: Thu 25-05-23 ID: 26
Finish: Fri 26-05-23 Dur: 2 days
Res:
Rough grade site (cut and fill)
Start: Mon 29-05-23 ID: 27
Finish: Fri 02-06-23 Dur: 1 wk
Res:
Install storm drainage
Start: Mon 05-06-23 ID: 28
Finish: Fri 16-06-23 Dur: 2 wks
Res:
Install exterior fire line and building fire riser
Start: Mon 05-06-23 ID: 29
Finish: Fri 16-06-23 Dur: 2 wks
Res:
perform site final grading
Start: Tue 20-06-23 ID: 30
Finish: Mon 03-07-23Dur: 2 wks
Res:
erect building batter boards and layout buildig
Start: Tue 04-07-23 ID: 31
Finish: Mon 10-07-23Dur: 1 wk
Res:
Excavation
Start: Tue 04-07-23ID: 32
Finish: Fri 18-08-23 Dur: 34 days
Comp: 0%
excavate foundations
Start: Tue 04-07-23 ID: 33
Finish: Mon 17-07-23Dur: 2 wks
Res:
Excavate elevator pit
Start: Tue 04-07-23 ID: 34
Finish: Wed 05-07-23Dur: 2 days
Res:
Form column piers and srpead foundations
Start: Tue 18-07-23 ID: 35
Finish: Fri 21-07-23 Dur: 4 days
Res:
Rough in electrical and plumbing in elevator
Start: Thu 06-07-23 ID: 36
Finish: Tue 11-07-23 Dur: 4 days
Res:
form elevator pit walls
Start: Wed 12-07-23ID: 37
Finish: Mon 17-07-23Dur: 4 days
Res:
set reinforcing and anchor bolts
Start: Mon 24-07-23ID: 38
Finish: Thu 27-07-23 Dur: 4 days
Res:
pour column piers and foundations
Start: Fri 28-07-23 ID: 39
Finish: Thu 03-08-23 Dur: 5 days
Res:
pour concrete elevator wall
Start: Tue 18-07-23 ID: 40
Finish: Tue 18-07-23 Dur: 1 day
Res:
cure elevator wall concrete
Start: Wed 19-07-23ID: 41
Finish: Thu 27-07-23 Dur: 7 days
Res:
cure piers and foundations
Start: Fri 04-08-23 ID: 42
Finish: Mon 14-08-23Dur: 7 days
Res:
strip wall forms
Start: Fri 28-07-23 ID: 43
Finish: Fri 28-07-23 Dur: 1 day
Res:
strip column piers and foundation forms
Start: Tue 15-08-23 ID: 44
Finish: Thu 17-08-23 Dur: 3 days
Res:
A06
Start: Thu 06-07-23ID: 47
Finish: Mon 28-08-23
Dur: 38 days
Comp: 0%
Erect Steel columns, beams and joist - 3rd and roof
Start: Tue 18-07-23 ID: 49
Finish: Mon 31-07-23Dur: 2 wks
Res:
Install miscellaneous iron and bracing - 1st and 2nd floors
Start: Tue 18-07-23 ID: 50
Finish: Mon 31-07-23Dur: 2 wks
Res:
Install miscellaneous iron and bracing - 3rd floor and roof
Start: Thu 06-07-23 ID: 51
Finish: Wed 19-07-23Dur: 2 wks
Res:
Install stairs and miscellaneous iron railing
Start: Wed 12-07-23ID: 52
Finish: Tue 25-07-23 Dur: 2 wks
Res:
touch-up paint on steel
Start: Tue 18-07-23 ID: 53
Finish: Mon 24-07-23Dur: 1 wk
Res:
A07
Start: Tue 29-08-23ID: 54
Finish: Mon 06-11-23
Dur: 50 days
Comp: 0%
Exterior Sheathing & Misc Works
Start: Tue 18-04-23ID: 77
Finish: Tue 16-05-23
Dur: 20 days
Comp: 0%
Preparatory Works (Toilets, etc)
Start: Tue 18-04-23ID: 79
Finish: Tue 31-10-23
Dur: 140 days
Comp: 0%
Lay masonary at core, mechanical, and toilets
Start: Tue 01-08-23 ID: 81
Finish: Mon 28-08-23Dur: 4 wks
Res:
A10
Start: Tue 02-01-24ID: 87
Finish: Tue 13-02-24
Dur: 31 days
Comp: 0%
A11
Start: Tue 02-01-24ID: 93
Finish: Mon 25-03-24
Dur: 60 days
Comp: 0%
Receive notice to proceed and sign the contratc
Start: Tue 02-05-23 ID: 3
Finish: Fri 05-05-23 Dur: 3 days
Res:
BUILDING
Start: Tue 02-05-23ID: 1
Finish: Fri 21-06-24Dur: 298 days
Comp: 0%
Initiation
Start: Tue 02-05-23ID: 2
Finish: Thu 25-05-23
Dur: 17 days
Comp: 0%
DIVYANSH
Start: Tue 18-04-23ID: 0
Finish: Mon 24-06-24
Dur: 309 days
Comp: 0%
BT20CIV038
Page 1
A12
Start: Tue 06-02-24ID: 98
Finish: Mon 10-06-24
Dur: 90 days
Comp: 0%
A13
Start: Tue 29-08-23ID: 110
Finish: Mon 23-10-23
Dur: 40 days
Comp: 0%
A14
Start: Tue 09-01-24ID: 114
Finish: Mon 27-05-24
Dur: 100 days
Comp: 0%
A15
Start: Wed 18-10-23
ID: 119
Finish: Mon 29-04-24
Dur: 139 days
Comp: 0%
A16
Start: Tue 29-08-23ID: 126
Finish: Mon 13-05-24
Dur: 185 days
Comp: 0%
Set equipment mechanical room
Start: Tue 29-08-23 ID: 127
Finish: Mon 11-09-23Dur: 2 wks
Res:
A17
Start: Tue 12-03-24ID: 132
Finish: Mon 17-06-24
Dur: 70 days
Comp: 0%
A18
Start: Tue 02-05-23ID: 137
Finish: Mon 24-06-24
Dur: 299 days
Comp: 0%
BT20CIV038
Milestone Date: Tue 02-05-23
ID: 144
DIVYANSH
Milestone Date: Tue 02-05-23
ID: 145
KUMAR
Milestone Date: Tue 02-05-23
ID: 146
SINGH
Milestone Date: Tue 02-05-23
ID: 147
BT20CIV038
Page 2
Install pneumatic tube in elevator pit
Start: Mon 31-07-23 ID: 45
Finish: Wed 02-08-23Dur: 3 days
Res:
prepare and pour concrete floor in elevator pit
Start: Fri 18-08-23 ID: 46
Finish: Fri 18-08-23 Dur: 1 day
Res:
Erect stell columns, beams and joist - 1st and 2nd floors
Start: Tue 15-08-23 ID: 48
Finish: Mon 28-08-23Dur: 2 wks
Res:
Form 2nd floor including all floor openings
Start: Tue 29-08-23 ID: 55
Finish: Mon 04-09-23Dur: 5 days
Res:
Install rebar and in-floor utilities (Including mechanical, electrical, plumbing)
Start: Tue 29-08-23 ID: 56
Finish: Mon 04-09-23Dur: 5 days
Res:
Pour 2nd Floor Slab
Start: Tue 05-09-23 ID: 57
Finish: Fri 08-09-23 Dur: 4 days
Res:
Cure 2nd Floor Slab
Start: Mon 11-09-23ID: 58
Finish: Tue 19-09-23 Dur: 7 days
Res:
Srtip forms from 2nd Floor Slab
Start: Wed 20-09-23ID: 59
Finish: Thu 21-09-23 Dur: 2 days
Res:
Form 3rd floor including all floor openings
Start: Wed 20-09-23ID: 60
Finish: Tue 26-09-23 Dur: 5 days
Res:
Install rebar and in-floor utilities (Including mechanical, electrical, plumbing)
Start: Wed 20-09-23ID: 61
Finish: Tue 26-09-23 Dur: 5 days
Res:
Pour 3rd floor slab
Start: Wed 27-09-23ID: 62
Finish: Mon 02-10-23Dur: 4 days
Res:
Cure 3rd floor slab
Start: Tue 03-10-23 ID: 63
Finish: Wed 11-10-23Dur: 7 days
Res:
strip forms from 3rd floor slab
Start: Thu 12-10-23 ID: 64
Finish: Fri 13-10-23 Dur: 2 days
Res:
form roof slab including all floor openings
Start: Thu 12-10-23 ID: 65
Finish: Wed 18-10-23Dur: 5 days
Res:
Install rebar and in-floor utilites (including mechanical, electrical, plumbing)
Start: Thu 12-10-23 ID: 66
Finish: Wed 18-10-23Dur: 5 days
Res:
Pour roof slab
Start: Thu 19-10-23 ID: 67
Finish: Tue 24-10-23 Dur: 4 days
Res:
cure rof slab
Start: Wed 25-10-23 ID: 68
Finish: Thu 02-11-23 Dur: 7 days
Res:
Strip forms form roof slab
Start: Fri 03-11-23 ID: 69
Finish: Mon 06-11-23Dur: 2 days
Res:
form 1st floor
Start: Fri 22-09-23 ID: 70
Finish: Wed 27-09-23Dur: 4 days
Res:
Install electrical underground
Start: Fri 22-09-23 ID: 71
Finish: Thu 28-09-23 Dur: 1 wk
Res:
nstall plumbing underground
Start: Fri 22-09-23 ID: 72
Finish: Thu 28-09-23 Dur: 1 wk
Res:
Install rebar and in-floor utilities
Start: Fri 22-09-23 ID: 73
Finish: Wed 27-09-23Dur: 4 days
Res:
Pour 1st floor slab
Start: Fri 29-09-23 ID: 74
Finish: Wed 04-10-23Dur: 4 days
Res:
cure 1st floor slab
Start: Thu 05-10-23 ID: 75
Finish: Fri 13-10-23 Dur: 7 days
Res:
strip forms from 1st floor slab
Start: Mon 16-10-23 ID: 76
Finish: Tue 17-10-23 Dur: 2 days
Res:
Install exteior sheathing and metal studs
Start: Tue 07-11-23 ID: 78
Finish: Mon 27-11-23Dur: 3 wks
Res:
Rough-in plumbing at toilets and masonary walls
Start: Wed 18-10-23 ID: 80
Finish: Tue 14-11-23 Dur: 4 wks
Res:
Install exterior masonary work
Start: Tue 28-11-23 ID: 82
Finish: Mon 01-01-24Dur: 5 wks
Res:
Install roof drains
Start: Tue 02-01-24 ID: 83
Finish: Wed 03-01-24Dur: 2 days
Res:
Install tile in toilet rooms
Start: Wed 15-11-23 ID: 84
Finish: Tue 28-11-23 Dur: 2 wks
Res:
Clean masonary
Start: Tue 02-01-24 ID: 85
Finish: Mon 08-01-24Dur: 1 wk
Res:
Clean toilets room tile
Start: Wed 29-11-23 ID: 86
Finish: Tue 05-12-23 Dur: 1 wk
Res:
Install flashing at parapet walls
Start: Tue 02-01-24 ID: 88
Finish: Fri 05-01-24 Dur: 4 days
Res:
pour lightweight concrete roof fill
Start: Mon 08-01-24ID: 89
Finish: Tue 09-01-24 Dur: 2 days
Res:
Install seamless roofing material
Start: Wed 10-01-24ID: 90
Finish: Tue 16-01-24 Dur: 5 days
Res:
spread stone ballast on seamless roof
Start: Wed 24-01-24ID: 91
Finish: Tue 30-01-24 Dur: 5 days
Res:
set rooftop equipment
Start: Wed 31-01-24ID: 92
Finish: Tue 13-02-24 Dur: 2 wks
Res:
Install window wall aluminium and glass
Start: Tue 02-01-24 ID: 94
Finish: Mon 05-02-24Dur: 5 wks
Res:
Install interior stud walls and dry walls
Start: Tue 06-02-24 ID: 95
Finish: Mon 11-03-24Dur: 5 wks
Res:
Install interior doors and hardware
Start: Tue 12-03-24 ID: 96
Finish: Mon 25-03-24Dur: 2 wks
Res:
Install store front doors and hardware
Start: Tue 02-01-24 ID: 97
Finish: Mon 22-01-24Dur: 3 wks
Res:
BT20CIV038
Page 3
Install millwork and wood trim
Start: Tue 26-03-24 ID: 99
Finish: Mon 15-04-24Dur: 3 wks
Res:
Paint walls and wood work
Start: Tue 16-04-24 ID: 100
Finish: Mon 13-05-24Dur: 4 wks
Res:
Install conduit at ceiling plenum space
Start: Tue 06-02-24 ID: 101
Finish: Mon 26-02-24Dur: 3 wks
Res:
Install duct in ceiling
Start: Tue 12-03-24 ID: 102
Finish: Mon 01-04-24Dur: 3 wks
Res:
Install ceiling grid
Start: Tue 02-04-24 ID: 103
Finish: Mon 15-04-24Dur: 2 wks
Res:
Install ceiling tile
Start: Tue 16-04-24 ID: 104
Finish: Mon 29-04-24Dur: 2 wks
Res:
hang wallpaper
Start: Tue 16-04-24 ID: 105
Finish: Mon 29-04-24Dur: 2 wks
Res:
set elevator equipment in shafts
Start: Tue 29-08-23 ID: 111
Finish: Mon 25-09-23Dur: 4 wks
Res:
set equipment in mechanical room
Start: Tue 26-09-23 ID: 112
Finish: Mon 09-10-23Dur: 2 wks
Res:
Test and align doors and equipment
Start: Tue 10-10-23 ID: 113
Finish: Mon 23-10-23Dur: 2 wks
Res:
rough-in plumbing in drywall walls
Start: Tue 06-02-24 ID: 115
Finish: Mon 04-03-24Dur: 4 wks
Res:
Tie-in fire line riser and set valves
Start: Tue 09-01-24 ID: 116
Finish: Mon 22-01-24Dur: 2 wks
Res:
Set plumbing fixtures and trim
Start: Tue 05-03-24 ID: 117
Finish: Mon 25-03-24Dur: 3 wks
Res:
Rough-in electrical in masonary walls
Start: Wed 18-10-23 ID: 120
Finish: Tue 14-11-23 Dur: 4 wks
Res:
Rough-in electrical drywalls walls
Start: Tue 06-02-24 ID: 121
Finish: Mon 04-03-24Dur: 4 wks
Res:
Pull wire in conduit and set area transformers
Start: Tue 27-02-24 ID: 122
Finish: Mon 18-03-24Dur: 3 wks
Res:
Install and terminate electrical devices
Start: Tue 19-03-24 ID: 123
Finish: Mon 08-04-24Dur: 3 wks
Res:
Install light fixtures - test and clean
Start: Tue 16-04-24 ID: 125
Finish: Mon 29-04-24Dur: 2 wks
Res:
Rough-in mechanical in masonary walls
Start: Wed 18-10-23 ID: 128
Finish: Tue 14-11-23 Dur: 4 wks
Res:
Rough-in mechanical in drywall walls
Start: Tue 06-02-24 ID: 129
Finish: Mon 19-02-24Dur: 2 wks
Res:
Install duct in building chase
Start: Tue 06-02-24 ID: 130
Finish: Mon 26-02-24Dur: 3 wks
Res:
Install hard tile flooring in common areas
Start: Tue 12-03-24 ID: 133
Finish: Mon 18-03-24Dur: 1 wk
Res:
Clean hard tile floors
Start: Tue 19-03-24 ID: 134
Finish: Fri 22-03-24 Dur: 4 days
Res:
BT20CIV038
Page 4
BT20CIV038
Page 5
Install building carpet
Start: Tue 14-05-24 ID: 106
Finish: Mon 10-06-24Dur: 4 wks
Res:
Install hardware and accessories
Start: Tue 14-05-24 ID: 107
Finish: Mon 03-06-24Dur: 3 wks
Res:
complete interior and exterior sod plantings
Start: Tue 14-05-24 ID: 108
Finish: Mon 27-05-24Dur: 2 wks
Res:
pave, curb and stripe parking lot
Start: Tue 28-05-24 ID: 109
Finish: Mon 10-06-24Dur: 2 wks
Res:
Flush, test and clean piping and fixtures
Start: Tue 14-05-24 ID: 118
Finish: Mon 27-05-24Dur: 2 wks
Res:
Make electrical terminations for HVAC equipment
Start: Tue 19-03-24 ID: 124
Finish: Wed 20-03-24Dur: 2 days
Res:
Set HVAC trim and test and balance system
Start: Tue 16-04-24 ID: 131
Finish: Mon 13-05-24Dur: 4 wks
Res:
Remove debris from building and do final clean up
Start: Tue 11-06-24 ID: 135
Finish: Fri 14-06-24 Dur: 4 days
Res:
Substantial completion date
Start: Mon 17-06-24ID: 136
Finish: Mon 17-06-24Dur: 1 day
Res:
Complete elevator Inspection and certification
Start: Mon 17-06-24ID: 138
Finish: Wed 19-06-24Dur: 3 days
Res:
Perform architect's Inspection
Start: Thu 20-06-24 ID: 139
Finish: Thu 20-06-24 Dur: 1 day
Res:
Perform local building agency inspection
Start: Fri 21-06-24 ID: 140
Finish: Fri 21-06-24 Dur: 1 day
Res:
Perform Fire Marshal's Inspectiom
Start: Mon 24-06-24ID: 141
Finish: Mon 24-06-24Dur: 1 day
Res:
BT20CIV038
Page 6
Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
BT20CIV038
Page 7
Project: DIVYANSH
Date: Tue 18-04-23

Nework digram .pdf

  • 1.
    Submit bond andnsurance documents Start: Mon 08-05-23ID: 4 Finish: Tue 09-05-23 Dur: 2 days Res: prepare and submit project schedule Start: Wed 10-05-23ID: 5 Finish: Thu 11-05-23 Dur: 2 days Res: prepare and submit schedule of values Start: Fri 12-05-23 ID: 6 Finish: Mon 15-05-23Dur: 2 days Res: obtain building permits Start: Mon 08-05-23ID: 7 Finish: Thu 11-05-23 Dur: 4 days Res: submit preliminary shop drawings Start: Fri 12-05-23 ID: 8 Finish: Thu 25-05-23 Dur: 2 wks Res: submit monthly requests for payment Start: Mon 08-05-23ID: 9 Finish: Mon 08-05-23Dur: 1 day Res: Drawing Start: Tue 09-05-23ID: 10 Finish: Mon 14-08-23 Dur: 70 days Comp: 0% submit shop drawings and order long lead items - Steel Start: Tue 09-05-23 ID: 11 Finish: Mon 22-05-23Dur: 2 wks Res: submit shop drawings and order long lead items - roofing Start: Fri 26-05-23 ID: 12 Finish: Thu 08-06-23 Dur: 2 wks Res: submit shop drawings and order long lead items - elevator Start: Fri 26-05-23 ID: 13 Finish: Thu 08-06-23 Dur: 2 wks Res: submit shop drawings and order long lead items - plumbing Start: Fri 26-05-23 ID: 14 Finish: Thu 08-06-23 Dur: 2 wks Res: submit shop drawings and order long lead items - electrical Start: Fri 26-05-23 ID: 15 Finish: Thu 08-06-23 Dur: 2 wks Res: submit shop drawings and order long lead items - HVAC Start: Fri 26-05-23 ID: 16 Finish: Thu 08-06-23 Dur: 2 wks Res: Detail, fabricate and deliver steel Start: Tue 23-05-23 ID: 17 Finish: Mon 14-08-23Dur: 12 wks Res: Temporary Start: Mon 08-05-23 ID: 18 Finish: Fri 19-05-23 Dur: 10 days Comp: 0% Install temporary power Start: Mon 08-05-23ID: 19 Finish: Tue 09-05-23 Dur: 2 days Res: Install temporary water service Start: Mon 08-05-23ID: 20 Finish: Tue 09-05-23 Dur: 2 days Res: set up site office Start: Wed 10-05-23ID: 21 Finish: Fri 12-05-23 Dur: 3 days Res: set line and grade benchmarks Start: Mon 15-05-23ID: 22 Finish: Wed 17-05-23Dur: 3 days Res: prepare site lay down yard and temporary fencing Start: Thu 18-05-23 ID: 23 Finish: Fri 19-05-23 Dur: 2 days Res: Clean Start: Mon 22-05-23 ID: 24 Finish: Mon 10-07-23 Dur: 36 days Comp: 0% clear and grub site Start: Mon 22-05-23 ID: 25 Finish: Wed 24-05-23Dur: 3 days Res: stone site access and temporary parking area Start: Thu 25-05-23 ID: 26 Finish: Fri 26-05-23 Dur: 2 days Res: Rough grade site (cut and fill) Start: Mon 29-05-23 ID: 27 Finish: Fri 02-06-23 Dur: 1 wk Res: Install storm drainage Start: Mon 05-06-23 ID: 28 Finish: Fri 16-06-23 Dur: 2 wks Res: Install exterior fire line and building fire riser Start: Mon 05-06-23 ID: 29 Finish: Fri 16-06-23 Dur: 2 wks Res: perform site final grading Start: Tue 20-06-23 ID: 30 Finish: Mon 03-07-23Dur: 2 wks Res: erect building batter boards and layout buildig Start: Tue 04-07-23 ID: 31 Finish: Mon 10-07-23Dur: 1 wk Res: Excavation Start: Tue 04-07-23ID: 32 Finish: Fri 18-08-23 Dur: 34 days Comp: 0% excavate foundations Start: Tue 04-07-23 ID: 33 Finish: Mon 17-07-23Dur: 2 wks Res: Excavate elevator pit Start: Tue 04-07-23 ID: 34 Finish: Wed 05-07-23Dur: 2 days Res: Form column piers and srpead foundations Start: Tue 18-07-23 ID: 35 Finish: Fri 21-07-23 Dur: 4 days Res: Rough in electrical and plumbing in elevator Start: Thu 06-07-23 ID: 36 Finish: Tue 11-07-23 Dur: 4 days Res: form elevator pit walls Start: Wed 12-07-23ID: 37 Finish: Mon 17-07-23Dur: 4 days Res: set reinforcing and anchor bolts Start: Mon 24-07-23ID: 38 Finish: Thu 27-07-23 Dur: 4 days Res: pour column piers and foundations Start: Fri 28-07-23 ID: 39 Finish: Thu 03-08-23 Dur: 5 days Res: pour concrete elevator wall Start: Tue 18-07-23 ID: 40 Finish: Tue 18-07-23 Dur: 1 day Res: cure elevator wall concrete Start: Wed 19-07-23ID: 41 Finish: Thu 27-07-23 Dur: 7 days Res: cure piers and foundations Start: Fri 04-08-23 ID: 42 Finish: Mon 14-08-23Dur: 7 days Res: strip wall forms Start: Fri 28-07-23 ID: 43 Finish: Fri 28-07-23 Dur: 1 day Res: strip column piers and foundation forms Start: Tue 15-08-23 ID: 44 Finish: Thu 17-08-23 Dur: 3 days Res: A06 Start: Thu 06-07-23ID: 47 Finish: Mon 28-08-23 Dur: 38 days Comp: 0% Erect Steel columns, beams and joist - 3rd and roof Start: Tue 18-07-23 ID: 49 Finish: Mon 31-07-23Dur: 2 wks Res: Install miscellaneous iron and bracing - 1st and 2nd floors Start: Tue 18-07-23 ID: 50 Finish: Mon 31-07-23Dur: 2 wks Res: Install miscellaneous iron and bracing - 3rd floor and roof Start: Thu 06-07-23 ID: 51 Finish: Wed 19-07-23Dur: 2 wks Res: Install stairs and miscellaneous iron railing Start: Wed 12-07-23ID: 52 Finish: Tue 25-07-23 Dur: 2 wks Res: touch-up paint on steel Start: Tue 18-07-23 ID: 53 Finish: Mon 24-07-23Dur: 1 wk Res: A07 Start: Tue 29-08-23ID: 54 Finish: Mon 06-11-23 Dur: 50 days Comp: 0% Exterior Sheathing & Misc Works Start: Tue 18-04-23ID: 77 Finish: Tue 16-05-23 Dur: 20 days Comp: 0% Preparatory Works (Toilets, etc) Start: Tue 18-04-23ID: 79 Finish: Tue 31-10-23 Dur: 140 days Comp: 0% Lay masonary at core, mechanical, and toilets Start: Tue 01-08-23 ID: 81 Finish: Mon 28-08-23Dur: 4 wks Res: A10 Start: Tue 02-01-24ID: 87 Finish: Tue 13-02-24 Dur: 31 days Comp: 0% A11 Start: Tue 02-01-24ID: 93 Finish: Mon 25-03-24 Dur: 60 days Comp: 0% Receive notice to proceed and sign the contratc Start: Tue 02-05-23 ID: 3 Finish: Fri 05-05-23 Dur: 3 days Res: BUILDING Start: Tue 02-05-23ID: 1 Finish: Fri 21-06-24Dur: 298 days Comp: 0% Initiation Start: Tue 02-05-23ID: 2 Finish: Thu 25-05-23 Dur: 17 days Comp: 0% DIVYANSH Start: Tue 18-04-23ID: 0 Finish: Mon 24-06-24 Dur: 309 days Comp: 0% BT20CIV038 Page 1
  • 2.
    A12 Start: Tue 06-02-24ID:98 Finish: Mon 10-06-24 Dur: 90 days Comp: 0% A13 Start: Tue 29-08-23ID: 110 Finish: Mon 23-10-23 Dur: 40 days Comp: 0% A14 Start: Tue 09-01-24ID: 114 Finish: Mon 27-05-24 Dur: 100 days Comp: 0% A15 Start: Wed 18-10-23 ID: 119 Finish: Mon 29-04-24 Dur: 139 days Comp: 0% A16 Start: Tue 29-08-23ID: 126 Finish: Mon 13-05-24 Dur: 185 days Comp: 0% Set equipment mechanical room Start: Tue 29-08-23 ID: 127 Finish: Mon 11-09-23Dur: 2 wks Res: A17 Start: Tue 12-03-24ID: 132 Finish: Mon 17-06-24 Dur: 70 days Comp: 0% A18 Start: Tue 02-05-23ID: 137 Finish: Mon 24-06-24 Dur: 299 days Comp: 0% BT20CIV038 Milestone Date: Tue 02-05-23 ID: 144 DIVYANSH Milestone Date: Tue 02-05-23 ID: 145 KUMAR Milestone Date: Tue 02-05-23 ID: 146 SINGH Milestone Date: Tue 02-05-23 ID: 147 BT20CIV038 Page 2
  • 3.
    Install pneumatic tubein elevator pit Start: Mon 31-07-23 ID: 45 Finish: Wed 02-08-23Dur: 3 days Res: prepare and pour concrete floor in elevator pit Start: Fri 18-08-23 ID: 46 Finish: Fri 18-08-23 Dur: 1 day Res: Erect stell columns, beams and joist - 1st and 2nd floors Start: Tue 15-08-23 ID: 48 Finish: Mon 28-08-23Dur: 2 wks Res: Form 2nd floor including all floor openings Start: Tue 29-08-23 ID: 55 Finish: Mon 04-09-23Dur: 5 days Res: Install rebar and in-floor utilities (Including mechanical, electrical, plumbing) Start: Tue 29-08-23 ID: 56 Finish: Mon 04-09-23Dur: 5 days Res: Pour 2nd Floor Slab Start: Tue 05-09-23 ID: 57 Finish: Fri 08-09-23 Dur: 4 days Res: Cure 2nd Floor Slab Start: Mon 11-09-23ID: 58 Finish: Tue 19-09-23 Dur: 7 days Res: Srtip forms from 2nd Floor Slab Start: Wed 20-09-23ID: 59 Finish: Thu 21-09-23 Dur: 2 days Res: Form 3rd floor including all floor openings Start: Wed 20-09-23ID: 60 Finish: Tue 26-09-23 Dur: 5 days Res: Install rebar and in-floor utilities (Including mechanical, electrical, plumbing) Start: Wed 20-09-23ID: 61 Finish: Tue 26-09-23 Dur: 5 days Res: Pour 3rd floor slab Start: Wed 27-09-23ID: 62 Finish: Mon 02-10-23Dur: 4 days Res: Cure 3rd floor slab Start: Tue 03-10-23 ID: 63 Finish: Wed 11-10-23Dur: 7 days Res: strip forms from 3rd floor slab Start: Thu 12-10-23 ID: 64 Finish: Fri 13-10-23 Dur: 2 days Res: form roof slab including all floor openings Start: Thu 12-10-23 ID: 65 Finish: Wed 18-10-23Dur: 5 days Res: Install rebar and in-floor utilites (including mechanical, electrical, plumbing) Start: Thu 12-10-23 ID: 66 Finish: Wed 18-10-23Dur: 5 days Res: Pour roof slab Start: Thu 19-10-23 ID: 67 Finish: Tue 24-10-23 Dur: 4 days Res: cure rof slab Start: Wed 25-10-23 ID: 68 Finish: Thu 02-11-23 Dur: 7 days Res: Strip forms form roof slab Start: Fri 03-11-23 ID: 69 Finish: Mon 06-11-23Dur: 2 days Res: form 1st floor Start: Fri 22-09-23 ID: 70 Finish: Wed 27-09-23Dur: 4 days Res: Install electrical underground Start: Fri 22-09-23 ID: 71 Finish: Thu 28-09-23 Dur: 1 wk Res: nstall plumbing underground Start: Fri 22-09-23 ID: 72 Finish: Thu 28-09-23 Dur: 1 wk Res: Install rebar and in-floor utilities Start: Fri 22-09-23 ID: 73 Finish: Wed 27-09-23Dur: 4 days Res: Pour 1st floor slab Start: Fri 29-09-23 ID: 74 Finish: Wed 04-10-23Dur: 4 days Res: cure 1st floor slab Start: Thu 05-10-23 ID: 75 Finish: Fri 13-10-23 Dur: 7 days Res: strip forms from 1st floor slab Start: Mon 16-10-23 ID: 76 Finish: Tue 17-10-23 Dur: 2 days Res: Install exteior sheathing and metal studs Start: Tue 07-11-23 ID: 78 Finish: Mon 27-11-23Dur: 3 wks Res: Rough-in plumbing at toilets and masonary walls Start: Wed 18-10-23 ID: 80 Finish: Tue 14-11-23 Dur: 4 wks Res: Install exterior masonary work Start: Tue 28-11-23 ID: 82 Finish: Mon 01-01-24Dur: 5 wks Res: Install roof drains Start: Tue 02-01-24 ID: 83 Finish: Wed 03-01-24Dur: 2 days Res: Install tile in toilet rooms Start: Wed 15-11-23 ID: 84 Finish: Tue 28-11-23 Dur: 2 wks Res: Clean masonary Start: Tue 02-01-24 ID: 85 Finish: Mon 08-01-24Dur: 1 wk Res: Clean toilets room tile Start: Wed 29-11-23 ID: 86 Finish: Tue 05-12-23 Dur: 1 wk Res: Install flashing at parapet walls Start: Tue 02-01-24 ID: 88 Finish: Fri 05-01-24 Dur: 4 days Res: pour lightweight concrete roof fill Start: Mon 08-01-24ID: 89 Finish: Tue 09-01-24 Dur: 2 days Res: Install seamless roofing material Start: Wed 10-01-24ID: 90 Finish: Tue 16-01-24 Dur: 5 days Res: spread stone ballast on seamless roof Start: Wed 24-01-24ID: 91 Finish: Tue 30-01-24 Dur: 5 days Res: set rooftop equipment Start: Wed 31-01-24ID: 92 Finish: Tue 13-02-24 Dur: 2 wks Res: Install window wall aluminium and glass Start: Tue 02-01-24 ID: 94 Finish: Mon 05-02-24Dur: 5 wks Res: Install interior stud walls and dry walls Start: Tue 06-02-24 ID: 95 Finish: Mon 11-03-24Dur: 5 wks Res: Install interior doors and hardware Start: Tue 12-03-24 ID: 96 Finish: Mon 25-03-24Dur: 2 wks Res: Install store front doors and hardware Start: Tue 02-01-24 ID: 97 Finish: Mon 22-01-24Dur: 3 wks Res: BT20CIV038 Page 3
  • 4.
    Install millwork andwood trim Start: Tue 26-03-24 ID: 99 Finish: Mon 15-04-24Dur: 3 wks Res: Paint walls and wood work Start: Tue 16-04-24 ID: 100 Finish: Mon 13-05-24Dur: 4 wks Res: Install conduit at ceiling plenum space Start: Tue 06-02-24 ID: 101 Finish: Mon 26-02-24Dur: 3 wks Res: Install duct in ceiling Start: Tue 12-03-24 ID: 102 Finish: Mon 01-04-24Dur: 3 wks Res: Install ceiling grid Start: Tue 02-04-24 ID: 103 Finish: Mon 15-04-24Dur: 2 wks Res: Install ceiling tile Start: Tue 16-04-24 ID: 104 Finish: Mon 29-04-24Dur: 2 wks Res: hang wallpaper Start: Tue 16-04-24 ID: 105 Finish: Mon 29-04-24Dur: 2 wks Res: set elevator equipment in shafts Start: Tue 29-08-23 ID: 111 Finish: Mon 25-09-23Dur: 4 wks Res: set equipment in mechanical room Start: Tue 26-09-23 ID: 112 Finish: Mon 09-10-23Dur: 2 wks Res: Test and align doors and equipment Start: Tue 10-10-23 ID: 113 Finish: Mon 23-10-23Dur: 2 wks Res: rough-in plumbing in drywall walls Start: Tue 06-02-24 ID: 115 Finish: Mon 04-03-24Dur: 4 wks Res: Tie-in fire line riser and set valves Start: Tue 09-01-24 ID: 116 Finish: Mon 22-01-24Dur: 2 wks Res: Set plumbing fixtures and trim Start: Tue 05-03-24 ID: 117 Finish: Mon 25-03-24Dur: 3 wks Res: Rough-in electrical in masonary walls Start: Wed 18-10-23 ID: 120 Finish: Tue 14-11-23 Dur: 4 wks Res: Rough-in electrical drywalls walls Start: Tue 06-02-24 ID: 121 Finish: Mon 04-03-24Dur: 4 wks Res: Pull wire in conduit and set area transformers Start: Tue 27-02-24 ID: 122 Finish: Mon 18-03-24Dur: 3 wks Res: Install and terminate electrical devices Start: Tue 19-03-24 ID: 123 Finish: Mon 08-04-24Dur: 3 wks Res: Install light fixtures - test and clean Start: Tue 16-04-24 ID: 125 Finish: Mon 29-04-24Dur: 2 wks Res: Rough-in mechanical in masonary walls Start: Wed 18-10-23 ID: 128 Finish: Tue 14-11-23 Dur: 4 wks Res: Rough-in mechanical in drywall walls Start: Tue 06-02-24 ID: 129 Finish: Mon 19-02-24Dur: 2 wks Res: Install duct in building chase Start: Tue 06-02-24 ID: 130 Finish: Mon 26-02-24Dur: 3 wks Res: Install hard tile flooring in common areas Start: Tue 12-03-24 ID: 133 Finish: Mon 18-03-24Dur: 1 wk Res: Clean hard tile floors Start: Tue 19-03-24 ID: 134 Finish: Fri 22-03-24 Dur: 4 days Res: BT20CIV038 Page 4
  • 5.
  • 6.
    Install building carpet Start:Tue 14-05-24 ID: 106 Finish: Mon 10-06-24Dur: 4 wks Res: Install hardware and accessories Start: Tue 14-05-24 ID: 107 Finish: Mon 03-06-24Dur: 3 wks Res: complete interior and exterior sod plantings Start: Tue 14-05-24 ID: 108 Finish: Mon 27-05-24Dur: 2 wks Res: pave, curb and stripe parking lot Start: Tue 28-05-24 ID: 109 Finish: Mon 10-06-24Dur: 2 wks Res: Flush, test and clean piping and fixtures Start: Tue 14-05-24 ID: 118 Finish: Mon 27-05-24Dur: 2 wks Res: Make electrical terminations for HVAC equipment Start: Tue 19-03-24 ID: 124 Finish: Wed 20-03-24Dur: 2 days Res: Set HVAC trim and test and balance system Start: Tue 16-04-24 ID: 131 Finish: Mon 13-05-24Dur: 4 wks Res: Remove debris from building and do final clean up Start: Tue 11-06-24 ID: 135 Finish: Fri 14-06-24 Dur: 4 days Res: Substantial completion date Start: Mon 17-06-24ID: 136 Finish: Mon 17-06-24Dur: 1 day Res: Complete elevator Inspection and certification Start: Mon 17-06-24ID: 138 Finish: Wed 19-06-24Dur: 3 days Res: Perform architect's Inspection Start: Thu 20-06-24 ID: 139 Finish: Thu 20-06-24 Dur: 1 day Res: Perform local building agency inspection Start: Fri 21-06-24 ID: 140 Finish: Fri 21-06-24 Dur: 1 day Res: Perform Fire Marshal's Inspectiom Start: Mon 24-06-24ID: 141 Finish: Mon 24-06-24Dur: 1 day Res: BT20CIV038 Page 6
  • 7.
    Critical Noncritical CriticalMilestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical BT20CIV038 Page 7 Project: DIVYANSH Date: Tue 18-04-23