Submit bond and nsurance documents
Start: Mon 08-05-23ID: 4
Finish: Tue 09-05-23 Dur: 2 days
Res:
prepare and submit project schedule
Start: Wed 10-05-23ID: 5
Finish: Thu 11-05-23 Dur: 2 days
Res:
prepare and submit schedule of values
Start: Fri 12-05-23 ID: 6
Finish: Mon 15-05-23Dur: 2 days
Res:
obtain building permits
Start: Mon 08-05-23ID: 7
Finish: Thu 11-05-23 Dur: 4 days
Res:
submit preliminary shop drawings
Start: Fri 12-05-23 ID: 8
Finish: Thu 25-05-23 Dur: 2 wks
Res:
submit monthly requests for payment
Start: Mon 08-05-23ID: 9
Finish: Mon 08-05-23Dur: 1 day
Res:
Drawing
Start: Tue 09-05-23ID: 10
Finish: Mon 14-08-23
Dur: 70 days
Comp: 0%
submit shop drawings and order long lead items - Steel
Start: Tue 09-05-23 ID: 11
Finish: Mon 22-05-23Dur: 2 wks
Res:
submit shop drawings and order long lead items - roofing
Start: Fri 26-05-23 ID: 12
Finish: Thu 08-06-23 Dur: 2 wks
Res:
submit shop drawings and order long lead items - elevator
Start: Fri 26-05-23 ID: 13
Finish: Thu 08-06-23 Dur: 2 wks
Res:
submit shop drawings and order long lead items - plumbing
Start: Fri 26-05-23 ID: 14
Finish: Thu 08-06-23 Dur: 2 wks
Res:
submit shop drawings and order long lead items - electrical
Start: Fri 26-05-23 ID: 15
Finish: Thu 08-06-23 Dur: 2 wks
Res:
submit shop drawings and order long lead items - HVAC
Start: Fri 26-05-23 ID: 16
Finish: Thu 08-06-23 Dur: 2 wks
Res:
Detail, fabricate and deliver steel
Start: Tue 23-05-23 ID: 17
Finish: Mon 14-08-23Dur: 12 wks
Res:
Temporary
Start: Mon 08-05-23
ID: 18
Finish: Fri 19-05-23 Dur: 10 days
Comp: 0%
Install temporary power
Start: Mon 08-05-23ID: 19
Finish: Tue 09-05-23 Dur: 2 days
Res:
Install temporary water service
Start: Mon 08-05-23ID: 20
Finish: Tue 09-05-23 Dur: 2 days
Res:
set up site office
Start: Wed 10-05-23ID: 21
Finish: Fri 12-05-23 Dur: 3 days
Res:
set line and grade benchmarks
Start: Mon 15-05-23ID: 22
Finish: Wed 17-05-23Dur: 3 days
Res:
prepare site lay down yard and temporary fencing
Start: Thu 18-05-23 ID: 23
Finish: Fri 19-05-23 Dur: 2 days
Res:
Clean
Start: Mon 22-05-23
ID: 24
Finish: Mon 10-07-23
Dur: 36 days
Comp: 0%
clear and grub site
Start: Mon 22-05-23 ID: 25
Finish: Wed 24-05-23Dur: 3 days
Res:
stone site access and temporary parking area
Start: Thu 25-05-23 ID: 26
Finish: Fri 26-05-23 Dur: 2 days
Res:
Rough grade site (cut and fill)
Start: Mon 29-05-23 ID: 27
Finish: Fri 02-06-23 Dur: 1 wk
Res:
Install storm drainage
Start: Mon 05-06-23 ID: 28
Finish: Fri 16-06-23 Dur: 2 wks
Res:
Install exterior fire line and building fire riser
Start: Mon 05-06-23 ID: 29
Finish: Fri 16-06-23 Dur: 2 wks
Res:
perform site final grading
Start: Tue 20-06-23 ID: 30
Finish: Mon 03-07-23Dur: 2 wks
Res:
erect building batter boards and layout buildig
Start: Tue 04-07-23 ID: 31
Finish: Mon 10-07-23Dur: 1 wk
Res:
Excavation
Start: Tue 04-07-23ID: 32
Finish: Fri 18-08-23 Dur: 34 days
Comp: 0%
excavate foundations
Start: Tue 04-07-23 ID: 33
Finish: Mon 17-07-23Dur: 2 wks
Res:
Excavate elevator pit
Start: Tue 04-07-23 ID: 34
Finish: Wed 05-07-23Dur: 2 days
Res:
Form column piers and srpead foundations
Start: Tue 18-07-23 ID: 35
Finish: Fri 21-07-23 Dur: 4 days
Res:
Rough in electrical and plumbing in elevator
Start: Thu 06-07-23 ID: 36
Finish: Tue 11-07-23 Dur: 4 days
Res:
form elevator pit walls
Start: Wed 12-07-23ID: 37
Finish: Mon 17-07-23Dur: 4 days
Res:
set reinforcing and anchor bolts
Start: Mon 24-07-23ID: 38
Finish: Thu 27-07-23 Dur: 4 days
Res:
pour column piers and foundations
Start: Fri 28-07-23 ID: 39
Finish: Thu 03-08-23 Dur: 5 days
Res:
pour concrete elevator wall
Start: Tue 18-07-23 ID: 40
Finish: Tue 18-07-23 Dur: 1 day
Res:
cure elevator wall concrete
Start: Wed 19-07-23ID: 41
Finish: Thu 27-07-23 Dur: 7 days
Res:
cure piers and foundations
Start: Fri 04-08-23 ID: 42
Finish: Mon 14-08-23Dur: 7 days
Res:
strip wall forms
Start: Fri 28-07-23 ID: 43
Finish: Fri 28-07-23 Dur: 1 day
Res:
strip column piers and foundation forms
Start: Tue 15-08-23 ID: 44
Finish: Thu 17-08-23 Dur: 3 days
Res:
A06
Start: Thu 06-07-23ID: 47
Finish: Mon 28-08-23
Dur: 38 days
Comp: 0%
Erect Steel columns, beams and joist - 3rd and roof
Start: Tue 18-07-23 ID: 49
Finish: Mon 31-07-23Dur: 2 wks
Res:
Install miscellaneous iron and bracing - 1st and 2nd floors
Start: Tue 18-07-23 ID: 50
Finish: Mon 31-07-23Dur: 2 wks
Res:
Install miscellaneous iron and bracing - 3rd floor and roof
Start: Thu 06-07-23 ID: 51
Finish: Wed 19-07-23Dur: 2 wks
Res:
Install stairs and miscellaneous iron railing
Start: Wed 12-07-23ID: 52
Finish: Tue 25-07-23 Dur: 2 wks
Res:
touch-up paint on steel
Start: Tue 18-07-23 ID: 53
Finish: Mon 24-07-23Dur: 1 wk
Res:
A07
Start: Tue 29-08-23ID: 54
Finish: Mon 06-11-23
Dur: 50 days
Comp: 0%
Exterior Sheathing & Misc Works
Start: Tue 18-04-23ID: 77
Finish: Tue 16-05-23
Dur: 20 days
Comp: 0%
Preparatory Works (Toilets, etc)
Start: Tue 18-04-23ID: 79
Finish: Tue 31-10-23
Dur: 140 days
Comp: 0%
Lay masonary at core, mechanical, and toilets
Start: Tue 01-08-23 ID: 81
Finish: Mon 28-08-23Dur: 4 wks
Res:
A10
Start: Tue 02-01-24ID: 87
Finish: Tue 13-02-24
Dur: 31 days
Comp: 0%
A11
Start: Tue 02-01-24ID: 93
Finish: Mon 25-03-24
Dur: 60 days
Comp: 0%
Receive notice to proceed and sign the contratc
Start: Tue 02-05-23 ID: 3
Finish: Fri 05-05-23 Dur: 3 days
Res:
BUILDING
Start: Tue 02-05-23ID: 1
Finish: Fri 21-06-24Dur: 298 days
Comp: 0%
Initiation
Start: Tue 02-05-23ID: 2
Finish: Thu 25-05-23
Dur: 17 days
Comp: 0%
DIVYANSH
Start: Tue 18-04-23ID: 0
Finish: Mon 24-06-24
Dur: 309 days
Comp: 0%
BT20CIV038
Page 1
A12
Start: Tue 06-02-24ID: 98
Finish: Mon 10-06-24
Dur: 90 days
Comp: 0%
A13
Start: Tue 29-08-23ID: 110
Finish: Mon 23-10-23
Dur: 40 days
Comp: 0%
A14
Start: Tue 09-01-24ID: 114
Finish: Mon 27-05-24
Dur: 100 days
Comp: 0%
A15
Start: Wed 18-10-23
ID: 119
Finish: Mon 29-04-24
Dur: 139 days
Comp: 0%
A16
Start: Tue 29-08-23ID: 126
Finish: Mon 13-05-24
Dur: 185 days
Comp: 0%
Set equipment mechanical room
Start: Tue 29-08-23 ID: 127
Finish: Mon 11-09-23Dur: 2 wks
Res:
A17
Start: Tue 12-03-24ID: 132
Finish: Mon 17-06-24
Dur: 70 days
Comp: 0%
A18
Start: Tue 02-05-23ID: 137
Finish: Mon 24-06-24
Dur: 299 days
Comp: 0%
BT20CIV038
Milestone Date: Tue 02-05-23
ID: 144
DIVYANSH
Milestone Date: Tue 02-05-23
ID: 145
KUMAR
Milestone Date: Tue 02-05-23
ID: 146
SINGH
Milestone Date: Tue 02-05-23
ID: 147
BT20CIV038
Page 2
Install pneumatic tube in elevator pit
Start: Mon 31-07-23 ID: 45
Finish: Wed 02-08-23Dur: 3 days
Res:
prepare and pour concrete floor in elevator pit
Start: Fri 18-08-23 ID: 46
Finish: Fri 18-08-23 Dur: 1 day
Res:
Erect stell columns, beams and joist - 1st and 2nd floors
Start: Tue 15-08-23 ID: 48
Finish: Mon 28-08-23Dur: 2 wks
Res:
Form 2nd floor including all floor openings
Start: Tue 29-08-23 ID: 55
Finish: Mon 04-09-23Dur: 5 days
Res:
Install rebar and in-floor utilities (Including mechanical, electrical, plumbing)
Start: Tue 29-08-23 ID: 56
Finish: Mon 04-09-23Dur: 5 days
Res:
Pour 2nd Floor Slab
Start: Tue 05-09-23 ID: 57
Finish: Fri 08-09-23 Dur: 4 days
Res:
Cure 2nd Floor Slab
Start: Mon 11-09-23ID: 58
Finish: Tue 19-09-23 Dur: 7 days
Res:
Srtip forms from 2nd Floor Slab
Start: Wed 20-09-23ID: 59
Finish: Thu 21-09-23 Dur: 2 days
Res:
Form 3rd floor including all floor openings
Start: Wed 20-09-23ID: 60
Finish: Tue 26-09-23 Dur: 5 days
Res:
Install rebar and in-floor utilities (Including mechanical, electrical, plumbing)
Start: Wed 20-09-23ID: 61
Finish: Tue 26-09-23 Dur: 5 days
Res:
Pour 3rd floor slab
Start: Wed 27-09-23ID: 62
Finish: Mon 02-10-23Dur: 4 days
Res:
Cure 3rd floor slab
Start: Tue 03-10-23 ID: 63
Finish: Wed 11-10-23Dur: 7 days
Res:
strip forms from 3rd floor slab
Start: Thu 12-10-23 ID: 64
Finish: Fri 13-10-23 Dur: 2 days
Res:
form roof slab including all floor openings
Start: Thu 12-10-23 ID: 65
Finish: Wed 18-10-23Dur: 5 days
Res:
Install rebar and in-floor utilites (including mechanical, electrical, plumbing)
Start: Thu 12-10-23 ID: 66
Finish: Wed 18-10-23Dur: 5 days
Res:
Pour roof slab
Start: Thu 19-10-23 ID: 67
Finish: Tue 24-10-23 Dur: 4 days
Res:
cure rof slab
Start: Wed 25-10-23 ID: 68
Finish: Thu 02-11-23 Dur: 7 days
Res:
Strip forms form roof slab
Start: Fri 03-11-23 ID: 69
Finish: Mon 06-11-23Dur: 2 days
Res:
form 1st floor
Start: Fri 22-09-23 ID: 70
Finish: Wed 27-09-23Dur: 4 days
Res:
Install electrical underground
Start: Fri 22-09-23 ID: 71
Finish: Thu 28-09-23 Dur: 1 wk
Res:
nstall plumbing underground
Start: Fri 22-09-23 ID: 72
Finish: Thu 28-09-23 Dur: 1 wk
Res:
Install rebar and in-floor utilities
Start: Fri 22-09-23 ID: 73
Finish: Wed 27-09-23Dur: 4 days
Res:
Pour 1st floor slab
Start: Fri 29-09-23 ID: 74
Finish: Wed 04-10-23Dur: 4 days
Res:
cure 1st floor slab
Start: Thu 05-10-23 ID: 75
Finish: Fri 13-10-23 Dur: 7 days
Res:
strip forms from 1st floor slab
Start: Mon 16-10-23 ID: 76
Finish: Tue 17-10-23 Dur: 2 days
Res:
Install exteior sheathing and metal studs
Start: Tue 07-11-23 ID: 78
Finish: Mon 27-11-23Dur: 3 wks
Res:
Rough-in plumbing at toilets and masonary walls
Start: Wed 18-10-23 ID: 80
Finish: Tue 14-11-23 Dur: 4 wks
Res:
Install exterior masonary work
Start: Tue 28-11-23 ID: 82
Finish: Mon 01-01-24Dur: 5 wks
Res:
Install roof drains
Start: Tue 02-01-24 ID: 83
Finish: Wed 03-01-24Dur: 2 days
Res:
Install tile in toilet rooms
Start: Wed 15-11-23 ID: 84
Finish: Tue 28-11-23 Dur: 2 wks
Res:
Clean masonary
Start: Tue 02-01-24 ID: 85
Finish: Mon 08-01-24Dur: 1 wk
Res:
Clean toilets room tile
Start: Wed 29-11-23 ID: 86
Finish: Tue 05-12-23 Dur: 1 wk
Res:
Install flashing at parapet walls
Start: Tue 02-01-24 ID: 88
Finish: Fri 05-01-24 Dur: 4 days
Res:
pour lightweight concrete roof fill
Start: Mon 08-01-24ID: 89
Finish: Tue 09-01-24 Dur: 2 days
Res:
Install seamless roofing material
Start: Wed 10-01-24ID: 90
Finish: Tue 16-01-24 Dur: 5 days
Res:
spread stone ballast on seamless roof
Start: Wed 24-01-24ID: 91
Finish: Tue 30-01-24 Dur: 5 days
Res:
set rooftop equipment
Start: Wed 31-01-24ID: 92
Finish: Tue 13-02-24 Dur: 2 wks
Res:
Install window wall aluminium and glass
Start: Tue 02-01-24 ID: 94
Finish: Mon 05-02-24Dur: 5 wks
Res:
Install interior stud walls and dry walls
Start: Tue 06-02-24 ID: 95
Finish: Mon 11-03-24Dur: 5 wks
Res:
Install interior doors and hardware
Start: Tue 12-03-24 ID: 96
Finish: Mon 25-03-24Dur: 2 wks
Res:
Install store front doors and hardware
Start: Tue 02-01-24 ID: 97
Finish: Mon 22-01-24Dur: 3 wks
Res:
BT20CIV038
Page 3
Install millwork and wood trim
Start: Tue 26-03-24 ID: 99
Finish: Mon 15-04-24Dur: 3 wks
Res:
Paint walls and wood work
Start: Tue 16-04-24 ID: 100
Finish: Mon 13-05-24Dur: 4 wks
Res:
Install conduit at ceiling plenum space
Start: Tue 06-02-24 ID: 101
Finish: Mon 26-02-24Dur: 3 wks
Res:
Install duct in ceiling
Start: Tue 12-03-24 ID: 102
Finish: Mon 01-04-24Dur: 3 wks
Res:
Install ceiling grid
Start: Tue 02-04-24 ID: 103
Finish: Mon 15-04-24Dur: 2 wks
Res:
Install ceiling tile
Start: Tue 16-04-24 ID: 104
Finish: Mon 29-04-24Dur: 2 wks
Res:
hang wallpaper
Start: Tue 16-04-24 ID: 105
Finish: Mon 29-04-24Dur: 2 wks
Res:
set elevator equipment in shafts
Start: Tue 29-08-23 ID: 111
Finish: Mon 25-09-23Dur: 4 wks
Res:
set equipment in mechanical room
Start: Tue 26-09-23 ID: 112
Finish: Mon 09-10-23Dur: 2 wks
Res:
Test and align doors and equipment
Start: Tue 10-10-23 ID: 113
Finish: Mon 23-10-23Dur: 2 wks
Res:
rough-in plumbing in drywall walls
Start: Tue 06-02-24 ID: 115
Finish: Mon 04-03-24Dur: 4 wks
Res:
Tie-in fire line riser and set valves
Start: Tue 09-01-24 ID: 116
Finish: Mon 22-01-24Dur: 2 wks
Res:
Set plumbing fixtures and trim
Start: Tue 05-03-24 ID: 117
Finish: Mon 25-03-24Dur: 3 wks
Res:
Rough-in electrical in masonary walls
Start: Wed 18-10-23 ID: 120
Finish: Tue 14-11-23 Dur: 4 wks
Res:
Rough-in electrical drywalls walls
Start: Tue 06-02-24 ID: 121
Finish: Mon 04-03-24Dur: 4 wks
Res:
Pull wire in conduit and set area transformers
Start: Tue 27-02-24 ID: 122
Finish: Mon 18-03-24Dur: 3 wks
Res:
Install and terminate electrical devices
Start: Tue 19-03-24 ID: 123
Finish: Mon 08-04-24Dur: 3 wks
Res:
Install light fixtures - test and clean
Start: Tue 16-04-24 ID: 125
Finish: Mon 29-04-24Dur: 2 wks
Res:
Rough-in mechanical in masonary walls
Start: Wed 18-10-23 ID: 128
Finish: Tue 14-11-23 Dur: 4 wks
Res:
Rough-in mechanical in drywall walls
Start: Tue 06-02-24 ID: 129
Finish: Mon 19-02-24Dur: 2 wks
Res:
Install duct in building chase
Start: Tue 06-02-24 ID: 130
Finish: Mon 26-02-24Dur: 3 wks
Res:
Install hard tile flooring in common areas
Start: Tue 12-03-24 ID: 133
Finish: Mon 18-03-24Dur: 1 wk
Res:
Clean hard tile floors
Start: Tue 19-03-24 ID: 134
Finish: Fri 22-03-24 Dur: 4 days
Res:
BT20CIV038
Page 4
BT20CIV038
Page 5
Install building carpet
Start: Tue 14-05-24 ID: 106
Finish: Mon 10-06-24Dur: 4 wks
Res:
Install hardware and accessories
Start: Tue 14-05-24 ID: 107
Finish: Mon 03-06-24Dur: 3 wks
Res:
complete interior and exterior sod plantings
Start: Tue 14-05-24 ID: 108
Finish: Mon 27-05-24Dur: 2 wks
Res:
pave, curb and stripe parking lot
Start: Tue 28-05-24 ID: 109
Finish: Mon 10-06-24Dur: 2 wks
Res:
Flush, test and clean piping and fixtures
Start: Tue 14-05-24 ID: 118
Finish: Mon 27-05-24Dur: 2 wks
Res:
Make electrical terminations for HVAC equipment
Start: Tue 19-03-24 ID: 124
Finish: Wed 20-03-24Dur: 2 days
Res:
Set HVAC trim and test and balance system
Start: Tue 16-04-24 ID: 131
Finish: Mon 13-05-24Dur: 4 wks
Res:
Remove debris from building and do final clean up
Start: Tue 11-06-24 ID: 135
Finish: Fri 14-06-24 Dur: 4 days
Res:
Substantial completion date
Start: Mon 17-06-24ID: 136
Finish: Mon 17-06-24Dur: 1 day
Res:
Complete elevator Inspection and certification
Start: Mon 17-06-24ID: 138
Finish: Wed 19-06-24Dur: 3 days
Res:
Perform architect's Inspection
Start: Thu 20-06-24 ID: 139
Finish: Thu 20-06-24 Dur: 1 day
Res:
Perform local building agency inspection
Start: Fri 21-06-24 ID: 140
Finish: Fri 21-06-24 Dur: 1 day
Res:
Perform Fire Marshal's Inspectiom
Start: Mon 24-06-24ID: 141
Finish: Mon 24-06-24Dur: 1 day
Res:
BT20CIV038
Page 6
Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
BT20CIV038
Page 7
Project: DIVYANSH
Date: Tue 18-04-23

More Related Content

Similar to Nework digram .pdf

Gantt chart of Minor bridge
Gantt chart of Minor bridge Gantt chart of Minor bridge
Gantt chart of Minor bridge
Kundan Sanap
 
Project master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plantProject master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plant
PT. ANSI MEGA INSTRUMENINDO, Gunawan Widihardjo
 
Project Planning And Control Club house design with MSP
Project Planning And Control Club house design with MSPProject Planning And Control Club house design with MSP
Project Planning And Control Club house design with MSP
Ayush khandelwal
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis
Ayon Pal
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis
ayonpal
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
JaiminTandel1
 

Similar to Nework digram .pdf (6)

Gantt chart of Minor bridge
Gantt chart of Minor bridge Gantt chart of Minor bridge
Gantt chart of Minor bridge
 
Project master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plantProject master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plant
 
Project Planning And Control Club house design with MSP
Project Planning And Control Club house design with MSPProject Planning And Control Club house design with MSP
Project Planning And Control Club house design with MSP
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
 

Recently uploaded

KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 

Recently uploaded (20)

KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 

Nework digram .pdf

  • 1. Submit bond and nsurance documents Start: Mon 08-05-23ID: 4 Finish: Tue 09-05-23 Dur: 2 days Res: prepare and submit project schedule Start: Wed 10-05-23ID: 5 Finish: Thu 11-05-23 Dur: 2 days Res: prepare and submit schedule of values Start: Fri 12-05-23 ID: 6 Finish: Mon 15-05-23Dur: 2 days Res: obtain building permits Start: Mon 08-05-23ID: 7 Finish: Thu 11-05-23 Dur: 4 days Res: submit preliminary shop drawings Start: Fri 12-05-23 ID: 8 Finish: Thu 25-05-23 Dur: 2 wks Res: submit monthly requests for payment Start: Mon 08-05-23ID: 9 Finish: Mon 08-05-23Dur: 1 day Res: Drawing Start: Tue 09-05-23ID: 10 Finish: Mon 14-08-23 Dur: 70 days Comp: 0% submit shop drawings and order long lead items - Steel Start: Tue 09-05-23 ID: 11 Finish: Mon 22-05-23Dur: 2 wks Res: submit shop drawings and order long lead items - roofing Start: Fri 26-05-23 ID: 12 Finish: Thu 08-06-23 Dur: 2 wks Res: submit shop drawings and order long lead items - elevator Start: Fri 26-05-23 ID: 13 Finish: Thu 08-06-23 Dur: 2 wks Res: submit shop drawings and order long lead items - plumbing Start: Fri 26-05-23 ID: 14 Finish: Thu 08-06-23 Dur: 2 wks Res: submit shop drawings and order long lead items - electrical Start: Fri 26-05-23 ID: 15 Finish: Thu 08-06-23 Dur: 2 wks Res: submit shop drawings and order long lead items - HVAC Start: Fri 26-05-23 ID: 16 Finish: Thu 08-06-23 Dur: 2 wks Res: Detail, fabricate and deliver steel Start: Tue 23-05-23 ID: 17 Finish: Mon 14-08-23Dur: 12 wks Res: Temporary Start: Mon 08-05-23 ID: 18 Finish: Fri 19-05-23 Dur: 10 days Comp: 0% Install temporary power Start: Mon 08-05-23ID: 19 Finish: Tue 09-05-23 Dur: 2 days Res: Install temporary water service Start: Mon 08-05-23ID: 20 Finish: Tue 09-05-23 Dur: 2 days Res: set up site office Start: Wed 10-05-23ID: 21 Finish: Fri 12-05-23 Dur: 3 days Res: set line and grade benchmarks Start: Mon 15-05-23ID: 22 Finish: Wed 17-05-23Dur: 3 days Res: prepare site lay down yard and temporary fencing Start: Thu 18-05-23 ID: 23 Finish: Fri 19-05-23 Dur: 2 days Res: Clean Start: Mon 22-05-23 ID: 24 Finish: Mon 10-07-23 Dur: 36 days Comp: 0% clear and grub site Start: Mon 22-05-23 ID: 25 Finish: Wed 24-05-23Dur: 3 days Res: stone site access and temporary parking area Start: Thu 25-05-23 ID: 26 Finish: Fri 26-05-23 Dur: 2 days Res: Rough grade site (cut and fill) Start: Mon 29-05-23 ID: 27 Finish: Fri 02-06-23 Dur: 1 wk Res: Install storm drainage Start: Mon 05-06-23 ID: 28 Finish: Fri 16-06-23 Dur: 2 wks Res: Install exterior fire line and building fire riser Start: Mon 05-06-23 ID: 29 Finish: Fri 16-06-23 Dur: 2 wks Res: perform site final grading Start: Tue 20-06-23 ID: 30 Finish: Mon 03-07-23Dur: 2 wks Res: erect building batter boards and layout buildig Start: Tue 04-07-23 ID: 31 Finish: Mon 10-07-23Dur: 1 wk Res: Excavation Start: Tue 04-07-23ID: 32 Finish: Fri 18-08-23 Dur: 34 days Comp: 0% excavate foundations Start: Tue 04-07-23 ID: 33 Finish: Mon 17-07-23Dur: 2 wks Res: Excavate elevator pit Start: Tue 04-07-23 ID: 34 Finish: Wed 05-07-23Dur: 2 days Res: Form column piers and srpead foundations Start: Tue 18-07-23 ID: 35 Finish: Fri 21-07-23 Dur: 4 days Res: Rough in electrical and plumbing in elevator Start: Thu 06-07-23 ID: 36 Finish: Tue 11-07-23 Dur: 4 days Res: form elevator pit walls Start: Wed 12-07-23ID: 37 Finish: Mon 17-07-23Dur: 4 days Res: set reinforcing and anchor bolts Start: Mon 24-07-23ID: 38 Finish: Thu 27-07-23 Dur: 4 days Res: pour column piers and foundations Start: Fri 28-07-23 ID: 39 Finish: Thu 03-08-23 Dur: 5 days Res: pour concrete elevator wall Start: Tue 18-07-23 ID: 40 Finish: Tue 18-07-23 Dur: 1 day Res: cure elevator wall concrete Start: Wed 19-07-23ID: 41 Finish: Thu 27-07-23 Dur: 7 days Res: cure piers and foundations Start: Fri 04-08-23 ID: 42 Finish: Mon 14-08-23Dur: 7 days Res: strip wall forms Start: Fri 28-07-23 ID: 43 Finish: Fri 28-07-23 Dur: 1 day Res: strip column piers and foundation forms Start: Tue 15-08-23 ID: 44 Finish: Thu 17-08-23 Dur: 3 days Res: A06 Start: Thu 06-07-23ID: 47 Finish: Mon 28-08-23 Dur: 38 days Comp: 0% Erect Steel columns, beams and joist - 3rd and roof Start: Tue 18-07-23 ID: 49 Finish: Mon 31-07-23Dur: 2 wks Res: Install miscellaneous iron and bracing - 1st and 2nd floors Start: Tue 18-07-23 ID: 50 Finish: Mon 31-07-23Dur: 2 wks Res: Install miscellaneous iron and bracing - 3rd floor and roof Start: Thu 06-07-23 ID: 51 Finish: Wed 19-07-23Dur: 2 wks Res: Install stairs and miscellaneous iron railing Start: Wed 12-07-23ID: 52 Finish: Tue 25-07-23 Dur: 2 wks Res: touch-up paint on steel Start: Tue 18-07-23 ID: 53 Finish: Mon 24-07-23Dur: 1 wk Res: A07 Start: Tue 29-08-23ID: 54 Finish: Mon 06-11-23 Dur: 50 days Comp: 0% Exterior Sheathing & Misc Works Start: Tue 18-04-23ID: 77 Finish: Tue 16-05-23 Dur: 20 days Comp: 0% Preparatory Works (Toilets, etc) Start: Tue 18-04-23ID: 79 Finish: Tue 31-10-23 Dur: 140 days Comp: 0% Lay masonary at core, mechanical, and toilets Start: Tue 01-08-23 ID: 81 Finish: Mon 28-08-23Dur: 4 wks Res: A10 Start: Tue 02-01-24ID: 87 Finish: Tue 13-02-24 Dur: 31 days Comp: 0% A11 Start: Tue 02-01-24ID: 93 Finish: Mon 25-03-24 Dur: 60 days Comp: 0% Receive notice to proceed and sign the contratc Start: Tue 02-05-23 ID: 3 Finish: Fri 05-05-23 Dur: 3 days Res: BUILDING Start: Tue 02-05-23ID: 1 Finish: Fri 21-06-24Dur: 298 days Comp: 0% Initiation Start: Tue 02-05-23ID: 2 Finish: Thu 25-05-23 Dur: 17 days Comp: 0% DIVYANSH Start: Tue 18-04-23ID: 0 Finish: Mon 24-06-24 Dur: 309 days Comp: 0% BT20CIV038 Page 1
  • 2. A12 Start: Tue 06-02-24ID: 98 Finish: Mon 10-06-24 Dur: 90 days Comp: 0% A13 Start: Tue 29-08-23ID: 110 Finish: Mon 23-10-23 Dur: 40 days Comp: 0% A14 Start: Tue 09-01-24ID: 114 Finish: Mon 27-05-24 Dur: 100 days Comp: 0% A15 Start: Wed 18-10-23 ID: 119 Finish: Mon 29-04-24 Dur: 139 days Comp: 0% A16 Start: Tue 29-08-23ID: 126 Finish: Mon 13-05-24 Dur: 185 days Comp: 0% Set equipment mechanical room Start: Tue 29-08-23 ID: 127 Finish: Mon 11-09-23Dur: 2 wks Res: A17 Start: Tue 12-03-24ID: 132 Finish: Mon 17-06-24 Dur: 70 days Comp: 0% A18 Start: Tue 02-05-23ID: 137 Finish: Mon 24-06-24 Dur: 299 days Comp: 0% BT20CIV038 Milestone Date: Tue 02-05-23 ID: 144 DIVYANSH Milestone Date: Tue 02-05-23 ID: 145 KUMAR Milestone Date: Tue 02-05-23 ID: 146 SINGH Milestone Date: Tue 02-05-23 ID: 147 BT20CIV038 Page 2
  • 3. Install pneumatic tube in elevator pit Start: Mon 31-07-23 ID: 45 Finish: Wed 02-08-23Dur: 3 days Res: prepare and pour concrete floor in elevator pit Start: Fri 18-08-23 ID: 46 Finish: Fri 18-08-23 Dur: 1 day Res: Erect stell columns, beams and joist - 1st and 2nd floors Start: Tue 15-08-23 ID: 48 Finish: Mon 28-08-23Dur: 2 wks Res: Form 2nd floor including all floor openings Start: Tue 29-08-23 ID: 55 Finish: Mon 04-09-23Dur: 5 days Res: Install rebar and in-floor utilities (Including mechanical, electrical, plumbing) Start: Tue 29-08-23 ID: 56 Finish: Mon 04-09-23Dur: 5 days Res: Pour 2nd Floor Slab Start: Tue 05-09-23 ID: 57 Finish: Fri 08-09-23 Dur: 4 days Res: Cure 2nd Floor Slab Start: Mon 11-09-23ID: 58 Finish: Tue 19-09-23 Dur: 7 days Res: Srtip forms from 2nd Floor Slab Start: Wed 20-09-23ID: 59 Finish: Thu 21-09-23 Dur: 2 days Res: Form 3rd floor including all floor openings Start: Wed 20-09-23ID: 60 Finish: Tue 26-09-23 Dur: 5 days Res: Install rebar and in-floor utilities (Including mechanical, electrical, plumbing) Start: Wed 20-09-23ID: 61 Finish: Tue 26-09-23 Dur: 5 days Res: Pour 3rd floor slab Start: Wed 27-09-23ID: 62 Finish: Mon 02-10-23Dur: 4 days Res: Cure 3rd floor slab Start: Tue 03-10-23 ID: 63 Finish: Wed 11-10-23Dur: 7 days Res: strip forms from 3rd floor slab Start: Thu 12-10-23 ID: 64 Finish: Fri 13-10-23 Dur: 2 days Res: form roof slab including all floor openings Start: Thu 12-10-23 ID: 65 Finish: Wed 18-10-23Dur: 5 days Res: Install rebar and in-floor utilites (including mechanical, electrical, plumbing) Start: Thu 12-10-23 ID: 66 Finish: Wed 18-10-23Dur: 5 days Res: Pour roof slab Start: Thu 19-10-23 ID: 67 Finish: Tue 24-10-23 Dur: 4 days Res: cure rof slab Start: Wed 25-10-23 ID: 68 Finish: Thu 02-11-23 Dur: 7 days Res: Strip forms form roof slab Start: Fri 03-11-23 ID: 69 Finish: Mon 06-11-23Dur: 2 days Res: form 1st floor Start: Fri 22-09-23 ID: 70 Finish: Wed 27-09-23Dur: 4 days Res: Install electrical underground Start: Fri 22-09-23 ID: 71 Finish: Thu 28-09-23 Dur: 1 wk Res: nstall plumbing underground Start: Fri 22-09-23 ID: 72 Finish: Thu 28-09-23 Dur: 1 wk Res: Install rebar and in-floor utilities Start: Fri 22-09-23 ID: 73 Finish: Wed 27-09-23Dur: 4 days Res: Pour 1st floor slab Start: Fri 29-09-23 ID: 74 Finish: Wed 04-10-23Dur: 4 days Res: cure 1st floor slab Start: Thu 05-10-23 ID: 75 Finish: Fri 13-10-23 Dur: 7 days Res: strip forms from 1st floor slab Start: Mon 16-10-23 ID: 76 Finish: Tue 17-10-23 Dur: 2 days Res: Install exteior sheathing and metal studs Start: Tue 07-11-23 ID: 78 Finish: Mon 27-11-23Dur: 3 wks Res: Rough-in plumbing at toilets and masonary walls Start: Wed 18-10-23 ID: 80 Finish: Tue 14-11-23 Dur: 4 wks Res: Install exterior masonary work Start: Tue 28-11-23 ID: 82 Finish: Mon 01-01-24Dur: 5 wks Res: Install roof drains Start: Tue 02-01-24 ID: 83 Finish: Wed 03-01-24Dur: 2 days Res: Install tile in toilet rooms Start: Wed 15-11-23 ID: 84 Finish: Tue 28-11-23 Dur: 2 wks Res: Clean masonary Start: Tue 02-01-24 ID: 85 Finish: Mon 08-01-24Dur: 1 wk Res: Clean toilets room tile Start: Wed 29-11-23 ID: 86 Finish: Tue 05-12-23 Dur: 1 wk Res: Install flashing at parapet walls Start: Tue 02-01-24 ID: 88 Finish: Fri 05-01-24 Dur: 4 days Res: pour lightweight concrete roof fill Start: Mon 08-01-24ID: 89 Finish: Tue 09-01-24 Dur: 2 days Res: Install seamless roofing material Start: Wed 10-01-24ID: 90 Finish: Tue 16-01-24 Dur: 5 days Res: spread stone ballast on seamless roof Start: Wed 24-01-24ID: 91 Finish: Tue 30-01-24 Dur: 5 days Res: set rooftop equipment Start: Wed 31-01-24ID: 92 Finish: Tue 13-02-24 Dur: 2 wks Res: Install window wall aluminium and glass Start: Tue 02-01-24 ID: 94 Finish: Mon 05-02-24Dur: 5 wks Res: Install interior stud walls and dry walls Start: Tue 06-02-24 ID: 95 Finish: Mon 11-03-24Dur: 5 wks Res: Install interior doors and hardware Start: Tue 12-03-24 ID: 96 Finish: Mon 25-03-24Dur: 2 wks Res: Install store front doors and hardware Start: Tue 02-01-24 ID: 97 Finish: Mon 22-01-24Dur: 3 wks Res: BT20CIV038 Page 3
  • 4. Install millwork and wood trim Start: Tue 26-03-24 ID: 99 Finish: Mon 15-04-24Dur: 3 wks Res: Paint walls and wood work Start: Tue 16-04-24 ID: 100 Finish: Mon 13-05-24Dur: 4 wks Res: Install conduit at ceiling plenum space Start: Tue 06-02-24 ID: 101 Finish: Mon 26-02-24Dur: 3 wks Res: Install duct in ceiling Start: Tue 12-03-24 ID: 102 Finish: Mon 01-04-24Dur: 3 wks Res: Install ceiling grid Start: Tue 02-04-24 ID: 103 Finish: Mon 15-04-24Dur: 2 wks Res: Install ceiling tile Start: Tue 16-04-24 ID: 104 Finish: Mon 29-04-24Dur: 2 wks Res: hang wallpaper Start: Tue 16-04-24 ID: 105 Finish: Mon 29-04-24Dur: 2 wks Res: set elevator equipment in shafts Start: Tue 29-08-23 ID: 111 Finish: Mon 25-09-23Dur: 4 wks Res: set equipment in mechanical room Start: Tue 26-09-23 ID: 112 Finish: Mon 09-10-23Dur: 2 wks Res: Test and align doors and equipment Start: Tue 10-10-23 ID: 113 Finish: Mon 23-10-23Dur: 2 wks Res: rough-in plumbing in drywall walls Start: Tue 06-02-24 ID: 115 Finish: Mon 04-03-24Dur: 4 wks Res: Tie-in fire line riser and set valves Start: Tue 09-01-24 ID: 116 Finish: Mon 22-01-24Dur: 2 wks Res: Set plumbing fixtures and trim Start: Tue 05-03-24 ID: 117 Finish: Mon 25-03-24Dur: 3 wks Res: Rough-in electrical in masonary walls Start: Wed 18-10-23 ID: 120 Finish: Tue 14-11-23 Dur: 4 wks Res: Rough-in electrical drywalls walls Start: Tue 06-02-24 ID: 121 Finish: Mon 04-03-24Dur: 4 wks Res: Pull wire in conduit and set area transformers Start: Tue 27-02-24 ID: 122 Finish: Mon 18-03-24Dur: 3 wks Res: Install and terminate electrical devices Start: Tue 19-03-24 ID: 123 Finish: Mon 08-04-24Dur: 3 wks Res: Install light fixtures - test and clean Start: Tue 16-04-24 ID: 125 Finish: Mon 29-04-24Dur: 2 wks Res: Rough-in mechanical in masonary walls Start: Wed 18-10-23 ID: 128 Finish: Tue 14-11-23 Dur: 4 wks Res: Rough-in mechanical in drywall walls Start: Tue 06-02-24 ID: 129 Finish: Mon 19-02-24Dur: 2 wks Res: Install duct in building chase Start: Tue 06-02-24 ID: 130 Finish: Mon 26-02-24Dur: 3 wks Res: Install hard tile flooring in common areas Start: Tue 12-03-24 ID: 133 Finish: Mon 18-03-24Dur: 1 wk Res: Clean hard tile floors Start: Tue 19-03-24 ID: 134 Finish: Fri 22-03-24 Dur: 4 days Res: BT20CIV038 Page 4
  • 6. Install building carpet Start: Tue 14-05-24 ID: 106 Finish: Mon 10-06-24Dur: 4 wks Res: Install hardware and accessories Start: Tue 14-05-24 ID: 107 Finish: Mon 03-06-24Dur: 3 wks Res: complete interior and exterior sod plantings Start: Tue 14-05-24 ID: 108 Finish: Mon 27-05-24Dur: 2 wks Res: pave, curb and stripe parking lot Start: Tue 28-05-24 ID: 109 Finish: Mon 10-06-24Dur: 2 wks Res: Flush, test and clean piping and fixtures Start: Tue 14-05-24 ID: 118 Finish: Mon 27-05-24Dur: 2 wks Res: Make electrical terminations for HVAC equipment Start: Tue 19-03-24 ID: 124 Finish: Wed 20-03-24Dur: 2 days Res: Set HVAC trim and test and balance system Start: Tue 16-04-24 ID: 131 Finish: Mon 13-05-24Dur: 4 wks Res: Remove debris from building and do final clean up Start: Tue 11-06-24 ID: 135 Finish: Fri 14-06-24 Dur: 4 days Res: Substantial completion date Start: Mon 17-06-24ID: 136 Finish: Mon 17-06-24Dur: 1 day Res: Complete elevator Inspection and certification Start: Mon 17-06-24ID: 138 Finish: Wed 19-06-24Dur: 3 days Res: Perform architect's Inspection Start: Thu 20-06-24 ID: 139 Finish: Thu 20-06-24 Dur: 1 day Res: Perform local building agency inspection Start: Fri 21-06-24 ID: 140 Finish: Fri 21-06-24 Dur: 1 day Res: Perform Fire Marshal's Inspectiom Start: Mon 24-06-24ID: 141 Finish: Mon 24-06-24Dur: 1 day Res: BT20CIV038 Page 6
  • 7. Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical BT20CIV038 Page 7 Project: DIVYANSH Date: Tue 18-04-23