ID Task
Mode
% Work
Complete
Task Name Duration Start Finish
1 81% Nexen Process Build -
WC-14-NXE-007-00
230 days Mon 03/11/14 Fri 18/09/15
2 97% VBX-650-W Modules - WC-14-NXE-007-02 173 days Mon 03/11/14 Wed 01/07/15
3 100% Design 105 days Mon 03/11/14 Fri 27/03/15
4 100% Review Current Build Drawings 5 days Mon 03/11/14 Fri 07/11/14
5 100% Develop P&ID 3 days Mon 10/11/14 Wed 12/11/14
6 100% Confirm Build Requirements and Specifications 5 days Mon 10/11/14 Fri 14/11/14
7 100% Component Selection 81 days Mon 17/11/14 Mon 09/03/15
8 100% Valves & Fittings 25 days Mon 05/01/15 Fri 06/02/15
9 100% Coriolis Meter 2 days Mon 17/11/14 Tue 18/11/14
10 100% Mag Meter 2 days Mon 17/11/14 Tue 18/11/14
11 100% OCF 7000 Centrifuge 10 days Mon 17/11/14 Fri 28/11/14
12 100% Heat Exchanger 3 days Mon 17/11/14 Wed 19/11/14
13 100% Electrical Panels 46 days Mon 05/01/15 Mon 09/03/15
14 100% Centrifuge Feed Pump 3 days Mon 17/11/14 Wed 19/11/14
15 100% Solids Auger 5 days Mon 17/11/14 Fri 21/11/14
16 100% Polymer Tank 10 days Mon 19/01/15 Fri 30/01/15
17 100% Heaters (Steam Ruffnecks) 10 days Mon 05/01/15 Fri 16/01/15
18 100% Temperature Control Valve 2 days Mon 17/11/14 Tue 18/11/14
19 100% Spinner and Heater 2 days Mon 17/11/14 Tue 18/11/14
20 100% Polymer Water Supply Pump 2 days Mon 17/11/14 Tue 18/11/14
21 100% Polymer Injection Pump 2 days Mon 17/11/14 Tue 18/11/14
22 100% Oil Centrate Pump 2 days Mon 17/11/14 Tue 18/11/14
23 100% Water Centrate Pump 2 days Mon 17/11/14 Tue 18/11/14
24 100% Model Development 60 days Mon 29/12/14 Fri 20/03/15
25 100% Structural Model Development/Approval 30 days Mon 29/12/14 Fri 06/02/15
26 100% Process Model Development/Approval 30 days Mon 19/01/15 Fri 27/02/15
27 100% Structural Fabrication Drawings 35 days Mon 12/01/15 Fri 27/02/15
28 100% Piping Fabrication Drawings 35 days Mon 02/02/15 Fri 20/03/15
29 100% Component Fabrication Drawings 80 days Mon 10/11/14 Fri 27/02/15
30 100% Work Bench 2 days Mon 10/11/14 Tue 11/11/14
31 100% Varsol Tank 2 days Mon 10/11/14 Tue 11/11/14
32 100% Sink 2 days Mon 10/11/14 Tue 11/11/14
33 100% Centrate Tank 2 days Tue 06/01/15 Wed 07/01/15
34 100% Centrate Tank Flanges 1 day Fri 27/02/15 Fri 27/02/15
35 100% Catwalks & Stairways 2 days Sun 08/02/15 Mon 09/02/15
36 100% Electrical/Instrumentation Design 60 days Mon 05/01/15 Fri 27/03/15
37 100% Electrical/Inst. Design 60 days Mon 05/01/15 Fri 27/03/15
38 99% Procurement 144 days Wed 19/11/14 Mon 08/06/15
39 100% Piping, Valves & Fittings 20 days Mon 02/02/15 Fri 27/02/15
40 100% Coriolis Meter 45 days Mon 01/12/14 Fri 30/01/15
41 100% Mag Meter 72 days Wed 19/11/14 Thu 26/02/15
42 100% OCF 7000 Centrifuge 100 days Mon 01/12/14 Fri 17/04/15
43 100% Heat Exchanger 72 days Thu 20/11/14 Fri 27/02/15
44 100% Electrical Panels 55 days Mon 19/01/15 Fri 03/04/15
45 100% Centrifuge Feed Pump 72 days Thu 20/11/14 Fri 27/02/15
46 100% Solids Auger 55 days Mon 24/11/14 Fri 06/02/15
47 100% Polymer Tank 14 days Tue 20/01/15 Fri 06/02/15
48 100% Heaters (Steam Ruffnecks) 10 days Mon 19/01/15 Fri 30/01/15
49 100% Temperature Control Valve 57 days Wed 19/11/14 Thu 05/02/15
T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S
28 Sep '14 26 Oct '14 23 Nov '14 21 Dec '14 18 Jan '15 15 Feb '15 15 Mar '15 12 Apr '15 10 May '15 07 Jun '15 05 Jul '15 02 Aug '15 30 Aug '15 27 Sep '15
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Late
Progress
Deadline
WC-14-NXE-007-01 Schedule
WC-14-NXE-007-01 Sch Rev 0 Page 1 Fri 29/05/15 12:59 PM
ID Task
Mode
% Work
Complete
Task Name Duration Start Finish
50 100% Spinner and Heater 85 days Wed 19/11/14 Tue 17/03/15
51 100% Polymer Water Supply Pump 73 days Wed 19/11/14 Fri 27/02/15
52 100% Polymer Injection Pump 73 days Wed 19/11/14 Fri 27/02/15
53 100% Oil Centrate Pump 73 days Wed 19/11/14 Fri 27/02/15
54 100% Water Centrate Pump 73 days Wed 19/11/14 Fri 27/02/15
55 90% Electrical Material 60 days Tue 17/03/15 Mon 08/06/15
56 97% Fabrication 99 days Mon 26/01/15 Thu 11/06/15
57 100% Level 1 Container Modifications 20 days Mon 26/01/15 Mon 02/03/15
58 100% Level 2 Container Modifications 25 days Mon 16/02/15 Mon 06/04/15
59 100% Work Bench 8 days Tue 17/03/15 Thu 26/03/15
60 100% Varsol Tank 8 days Tue 17/03/15 Thu 26/03/15
61 100% Sink 3 days Tue 31/03/15 Thu 02/04/15
62 100% Centrate Tank 18 days Mon 02/02/15 Wed 25/02/15
63 100% Process Piping 50 days Tue 03/02/15 Mon 13/04/15
64 100% Piping/Electrical Supports 30 days Tue 24/03/15 Mon 11/05/15
65 80% Catwalks & Stairways 30 days Fri 01/05/15 Thu 11/06/15
66 100% Piping Testing 40 days Tue 17/02/15 Mon 13/04/15
67 100% NDE Piping Testing 35 days Tue 17/02/15 Mon 06/04/15
68 100% Spool String Testing - Hydrostatic 3 days Thu 09/04/15 Mon 13/04/15
69 100% Pre-Assembly & Installation 17 days Tue 28/04/15 Wed 20/05/15
70 100% Level 1 Component Installation 5 days Tue 28/04/15 Mon 04/05/15
71 100% Level 2 Comonent Installation 5 days Tue 05/05/15 Mon 11/05/15
72 100% Piping Installation 5 days Tue 12/05/15 Mon 18/05/15
73 100% Disassemble for Painting 2 days Tue 19/05/15 Wed 20/05/15
74 82% Painting 23 days Thu 07/05/15 Mon 08/06/15
75 100% Level 1 Container 5 days Thu 07/05/15 Wed 13/05/15
76 100% Level 2 Container 5 days Thu 14/05/15 Wed 20/05/15
77 100% Tanks & Components 2 days Thu 21/05/15 Fri 22/05/15
78 40% Piping 10 days Tue 26/05/15 Mon 08/06/15
79 18% Final Assembly 28 days Thu 21/05/15 Mon 29/06/15
80 88% Component Installation 8 days Thu 21/05/15 Mon 01/06/15
81 0% Piping Installation 5 days Tue 09/06/15 Mon 15/06/15
82 0% Electrical Installation 20 days Tue 02/06/15 Mon 29/06/15
83 0% FAT 2 days Tue 30/06/15 Wed 01/07/15
84 0% Final Acceptance Testing 2 days Tue 30/06/15 Wed 01/07/15
85 36% Pre-Process 53' HC - WC-14-NXE-007-05 152 days Mon 05/01/15 Tue 04/08/15
86 100% Design 110 days Mon 05/01/15 Fri 05/06/15
87 100% GO-ON Approval 0 days Mon 05/01/15 Mon 05/01/15
88 100% Structural/Mechanical Design Work 30 days Mon 02/03/15 Fri 10/04/15
89 100% Electrical Design Work 30 days Mon 02/03/15 Fri 10/04/15
90 100% Model Development 40 days Mon 13/04/15 Fri 05/06/15
91 100% Structural Model Development/Approval 10 days Mon 13/04/15 Fri 24/04/15
92 100% Process Model Development/Approval 10 days Mon 27/04/15 Fri 08/05/15
93 100% Structural Fabrication Drawings 5 days Mon 27/04/15 Fri 01/05/15
94 100% Piping Fabrication Drawings 15 days Mon 27/04/15 Fri 29/05/15
95 0% Component Fabrication Drawings 5 days Mon 01/06/15 Fri 05/06/15
96 35% Procurement 60 days Mon 04/05/15 Fri 24/07/15
97 67% Pumps, Piping, Valves & Fittings 30 days Mon 04/05/15 Fri 12/06/15
98 11% Electrical Panels - Items 45 days Mon 25/05/15 Fri 24/07/15
99 76% Fabrication 20 days Mon 11/05/15 Fri 05/06/15
05/01
T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S
28 Sep '14 26 Oct '14 23 Nov '14 21 Dec '14 18 Jan '15 15 Feb '15 15 Mar '15 12 Apr '15 10 May '15 07 Jun '15 05 Jul '15 02 Aug '15 30 Aug '15 27 Sep '15
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Late
Progress
Deadline
WC-14-NXE-007-01 Schedule
WC-14-NXE-007-01 Sch Rev 0 Page 2 Fri 29/05/15 12:59 PM
ID Task
Mode
% Work
Complete
Task Name Duration Start Finish
100 100% Container Modifications 10 days Mon 18/05/15 Fri 29/05/15
101 50% Components- Manifolds..etc. 4 days Thu 28/05/15 Tue 02/06/15
102 75% Process Piping 20 days Mon 11/05/15 Fri 05/06/15
103 28% Pre-Assembly & Installation 17 days Wed 27/05/15 Thu 18/06/15
104 60% Component Installation 5 days Wed 27/05/15 Tue 02/06/15
105 0% Piping Installation 5 days Mon 08/06/15 Fri 12/06/15
106 0% Piping/Electrical Supports 2 days Mon 15/06/15 Tue 16/06/15
107 0% Disassemble for Painting 2 days Wed 17/06/15 Thu 18/06/15
108 0% Piping Testing 6 days Fri 19/06/15 Fri 26/06/15
109 0% NDE Piping Testing 3 days Fri 19/06/15 Tue 23/06/15
110 0% Spool String Testing - Hydrostatic 3 days Wed 24/06/15 Fri 26/06/15
111 0% Painting 13 days Fri 19/06/15 Tue 07/07/15
112 0% Container 3 days Fri 19/06/15 Tue 23/06/15
113 0% Components 2 days Mon 29/06/15 Tue 30/06/15
114 0% Piping 5 days Wed 01/07/15 Tue 07/07/15
115 0% Final Assembly 22 days Thu 02/07/15 Fri 31/07/15
116 0% Component Installation 3 days Thu 02/07/15 Mon 06/07/15
117 0% Piping Installation 3 days Wed 08/07/15 Fri 10/07/15
118 0% Electrical Installation 5 days Mon 27/07/15 Fri 31/07/15
119 0% FAT 2 days Mon 03/08/15 Tue 04/08/15
120 0% Final Acceptance Testing 2 days Mon 03/08/15 Tue 04/08/15
121 56% Vapor Recovery Unit VRU -
WC-14-NXE-007-07
178 days Mon 10/11/14 Wed 15/07/15
122 100% Design 115 days Mon 10/11/14 Fri 17/04/15
123 100% GO-ON Approval 0 days Mon 10/11/14 Mon 10/11/14
124 100% Structural/Mechanical Design Work 30 days Mon 05/01/15 Fri 13/02/15
125 100% Electrical Design Work 60 days Mon 26/01/15 Fri 17/04/15
126 100% Model Development 45 days Mon 16/02/15 Fri 17/04/15
127 100% Structural Model Development/Approval 10 days Mon 16/02/15 Fri 27/02/15
128 100% Process Model Development/Approval 20 days Mon 02/03/15 Fri 27/03/15
129 100% Structural Fabrication Drawings 10 days Mon 02/03/15 Fri 13/03/15
130 100% Piping Fabrication Drawings 15 days Mon 30/03/15 Fri 17/04/15
131 91% Procurement 50 days Mon 06/04/15 Fri 12/06/15
132 80% Pumps, Piping, Valves & Fittings 50 days Mon 06/04/15 Fri 12/06/15
133 100% Electrical Panels - Items 25 days Mon 20/04/15 Fri 22/05/15
134 100% Fabrication 30 days Mon 30/03/15 Fri 08/05/15
135 100% Container Modifications 15 days Mon 30/03/15 Fri 17/04/15
136 100% Carbon - Clay Partitions 8 days Mon 20/04/15 Wed 29/04/15
137 100% Process Piping 20 days Mon 13/04/15 Fri 08/05/15
138 0% Pre-Assembly & Installation 14 days Mon 01/06/15 Thu 18/06/15
139 0% Component / Mesh Installation 5 days Mon 01/06/15 Fri 05/06/15
140 0% Piping Installation 5 days Mon 08/06/15 Fri 12/06/15
141 0% Piping/Electrical Supports 2 days Mon 15/06/15 Tue 16/06/15
142 0% Disassemble for Painting 2 days Wed 17/06/15 Thu 18/06/15
143 0% Piping Testing 6 days Fri 19/06/15 Fri 26/06/15
144 0% NDE Piping Testing 3 days Fri 19/06/15 Tue 23/06/15
145 0% Spool String Testing - Hydrostatic 3 days Wed 24/06/15 Fri 26/06/15
146 0% Painting 13 days Fri 19/06/15 Tue 07/07/15
147 0% Container 3 days Fri 19/06/15 Tue 23/06/15
148 0% Components 2 days Mon 29/06/15 Tue 30/06/15
10/11
T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S
28 Sep '14 26 Oct '14 23 Nov '14 21 Dec '14 18 Jan '15 15 Feb '15 15 Mar '15 12 Apr '15 10 May '15 07 Jun '15 05 Jul '15 02 Aug '15 30 Aug '15 27 Sep '15
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Late
Progress
Deadline
WC-14-NXE-007-01 Schedule
WC-14-NXE-007-01 Sch Rev 0 Page 3 Fri 29/05/15 12:59 PM
ID Task
Mode
% Work
Complete
Task Name Duration Start Finish
149 0% Piping 5 days Wed 01/07/15 Tue 07/07/15
150 0% Final Assembly 8 days Thu 02/07/15 Mon 13/07/15
151 0% Component Installation 3 days Thu 02/07/15 Mon 06/07/15
152 0% Piping Installation 3 days Wed 08/07/15 Fri 10/07/15
153 0% Electrical Installation 5 days Tue 07/07/15 Mon 13/07/15
154 0% FAT 2 days Tue 14/07/15 Wed 15/07/15
155 0% Final Acceptance Testing 2 days Tue 14/07/15 Wed 15/07/15
156 8% Solids Auger Removal Bin-
WC-14-NXE-007-06
222 days Thu 13/11/14 Fri 18/09/15
157 35% Design 85 days Wed 01/04/15 Tue 28/07/15
158 100% GO-ON Approval 0 days Wed 01/04/15 Wed 01/04/15
159 100% Structural/Mechanical Design Work 30 days Wed 01/04/15 Tue 12/05/15
160 96% Electrical Design Work 45 days Wed 01/04/15 Tue 02/06/15
161 30% Model Development 55 days Wed 13/05/15 Tue 28/07/15
162 65% Structural Model Development/Approval 20 days Wed 13/05/15 Tue 09/06/15
163 0% Process Model Development/Approval 20 days Wed 10/06/15 Tue 07/07/15
164 0% Structural Fabrication Drawings 10 days Wed 10/06/15 Tue 23/06/15
165 0% Process Fabrication Drawings 15 days Wed 08/07/15 Tue 28/07/15
166 0% Procurement 56 days Wed 03/06/15 Wed 19/08/15
167 0% Pumps, Skids, Agur, Piping, Valves & Fittings 20 days Wed 15/07/15 Tue 11/08/15
168 0% Electrical Panels - Items 56 days Wed 03/06/15 Wed 19/08/15
169 0% Fabrication 15 days Wed 05/08/15 Tue 25/08/15
170 0% Assembly 15 days Wed 26/08/15 Tue 15/09/15
171 0% Final Acceptance Testing 3 days Thu 13/11/14 Fri 18/09/15
172 73% Power Distribution 20' HC -
WC-14-NXE-007-03
149.5 days Mon 05/01/15 Fri 31/07/15
173 100% Engineering & Procurement Phase 50 days Mon 05/01/15 Fri 13/03/15
174 100% GO-ON Approval 0 days Mon 05/01/15 Mon 05/01/15
175 100% Structural/Mechanical Design Work 20 days Mon 05/01/15 Fri 30/01/15
176 100% Electrical Design Work 20 days Mon 05/01/15 Fri 30/01/15
177 100% Long Lead Procurement Items ( Electrical ) 30 days Mon 02/02/15 Fri 13/03/15
178 29% Construction Phase 99.5 days Mon 16/03/15 Fri 31/07/15
179 100% Container Preperation 2 days Mon 16/03/15 Tue 17/03/15
180 100% Door Opening 1 day Wed 18/03/15 Wed 18/03/15
181 100% Door Framing installation 1 day Thu 19/03/15 Thu 19/03/15
182 0% Penetrations 1 day Mon 01/06/15 Mon 01/06/15
183 0% Cord Box Welding 4 days Tue 23/06/15 Fri 26/06/15
184 100% Door Installation 1 day Mon 29/06/15 Mon 29/06/15
185 0% Required Welding Complete and NDT 2 days Tue 30/06/15 Wed 01/07/15
186 0% Exterior sand blasting 1 day Thu 02/07/15 Thu 02/07/15
187 0% Primer and Painting 2 days Fri 03/07/15 Mon 06/07/15
188 0% Electrical Finish 15 days Tue 07/07/15 Mon 27/07/15
189 0% Caulking Completion 1 day Tue 28/07/15 Tue 28/07/15
190 0% Testing 2 days Wed 29/07/15 Thu 30/07/15
191 0% Cleaning 0.5 days Fri 31/07/15 Fri 31/07/15
192 0% Misc. Fabrication 15 days Tue 02/06/15 Mon 22/06/15
193 0% Cord Box Fabrication/Welding 15 days Tue 02/06/15 Mon 22/06/15
194 0% Closing Out 0 days Fri 31/07/15 Fri 31/07/15
195 0% shipping Unit 0 days Fri 31/07/15 Fri 31/07/15
196 0% Utilities Module 40' HC - WC-14-NXE-007-04 75 days Mon 01/06/15 Fri 11/09/15
01/04
05/01
31/07
31/07
T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S
28 Sep '14 26 Oct '14 23 Nov '14 21 Dec '14 18 Jan '15 15 Feb '15 15 Mar '15 12 Apr '15 10 May '15 07 Jun '15 05 Jul '15 02 Aug '15 30 Aug '15 27 Sep '15
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Late
Progress
Deadline
WC-14-NXE-007-01 Schedule
WC-14-NXE-007-01 Sch Rev 0 Page 4 Fri 29/05/15 12:59 PM
ID Task
Mode
% Work
Complete
Task Name Duration Start Finish
197 0% Engineering & Procurement Phase 75 days Mon 01/06/15 Fri 11/09/15
198 0% GO-ON Approval 0 days Mon 01/06/15 Mon 01/06/15
199 0% Structural/Mechanical Design Work 15 days Mon 01/06/15 Fri 19/06/15
200 0% Electrical Design Work 15 days Mon 01/06/15 Fri 19/06/15
201 0% Long Lead Procurement Items ( Electrical ) 60 days Mon 22/06/15 Fri 11/09/15
202 0% Construction Phase 39.5 days Mon 22/06/15 Fri 14/08/15
203 0% Container Preperation 2 days Mon 22/06/15 Tue 23/06/15
204 0% Door Opening 2 days Wed 24/06/15 Thu 25/06/15
205 0% Door Framing installation 1 day Fri 26/06/15 Fri 26/06/15
206 0% Penetrations 1 day Mon 29/06/15 Mon 29/06/15
207 0% Cord Box Welding 3 days Wed 08/07/15 Fri 10/07/15
208 0% Door Installation 1 day Mon 13/07/15 Mon 13/07/15
209 0% Required Welding Complete and NDT 2 days Tue 14/07/15 Wed 15/07/15
210 0% Exterior sand blasting 1 day Thu 16/07/15 Thu 16/07/15
211 0% Primer and Painting 2 days Fri 17/07/15 Mon 20/07/15
212 0% Electrical Finish 15 days Tue 21/07/15 Mon 10/08/15
213 0% Caulking Completion 1 day Tue 11/08/15 Tue 11/08/15
214 0% Testing 2 days Wed 12/08/15 Thu 13/08/15
215 0% Cleaning 0.5 days Fri 14/08/15 Fri 14/08/15
216 0% Misc. Fabrication 10 days Wed 24/06/15 Tue 07/07/15
217 0% Cord Box Fabrication/Welding 10 days Wed 24/06/15 Tue 07/07/15
218 0% Closing Out 0 days Fri 14/08/15 Fri 14/08/15
219 0% shipping Unit 0 days Fri 14/08/15 Fri 14/08/15
220 100% Office 1 day Mon 24/11/14 Mon 24/11/14
221 100% Office 1 day Mon 24/11/14 Mon 24/11/14
222 100% Critical Spares 67 days Mon 02/02/15 Tue 05/05/15
223 100% Selection 20 days Mon 02/02/15 Fri 27/02/15
224 100% Procurement 40 days Wed 04/03/15 Tue 28/04/15
225 100% Packaging & Identification 5 days Wed 29/04/15 Tue 05/05/15
01/06
14/08
14/08
T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S
28 Sep '14 26 Oct '14 23 Nov '14 21 Dec '14 18 Jan '15 15 Feb '15 15 Mar '15 12 Apr '15 10 May '15 07 Jun '15 05 Jul '15 02 Aug '15 30 Aug '15 27 Sep '15
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Late
Progress
Deadline
WC-14-NXE-007-01 Schedule
WC-14-NXE-007-01 Sch Rev 0 Page 5 Fri 29/05/15 12:59 PM

More Related Content

Similar to WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)

Proposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdfProposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdfMarkGeraldCuadra1
 
Engineering Design Center Project Schedule
Engineering Design Center Project ScheduleEngineering Design Center Project Schedule
Engineering Design Center Project ScheduleVirginia Kam
 
WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25Tofik Nazirov, B.Sc., PhD
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0Ahmed Khaled
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Ayon Pal
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis ayonpal
 
Northwestern AU+Automation Timeline REV6 6-15-12
Northwestern AU+Automation Timeline REV6  6-15-12Northwestern AU+Automation Timeline REV6  6-15-12
Northwestern AU+Automation Timeline REV6 6-15-12Bin Kallan
 
Northwestern AU+Automation Timeline REV6 6-15-12
Northwestern AU+Automation Timeline REV6  6-15-12Northwestern AU+Automation Timeline REV6  6-15-12
Northwestern AU+Automation Timeline REV6 6-15-12Bin Kallan
 
Jadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfJadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfGaluhWulandari10
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisDeborah Obasogie
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoignitetribes
 

Similar to WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015) (20)

Popop
PopopPopop
Popop
 
program
programprogram
program
 
MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation Schedule
 
CPM
CPMCPM
CPM
 
Proposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdfProposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdf
 
MS project Sample gantt chart
MS project Sample  gantt chartMS project Sample  gantt chart
MS project Sample gantt chart
 
Engineering Design Center Project Schedule
Engineering Design Center Project ScheduleEngineering Design Center Project Schedule
Engineering Design Center Project Schedule
 
Slide4 mp psht1of6
Slide4 mp psht1of6Slide4 mp psht1of6
Slide4 mp psht1of6
 
WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis
 
Northwestern AU+Automation Timeline REV6 6-15-12
Northwestern AU+Automation Timeline REV6  6-15-12Northwestern AU+Automation Timeline REV6  6-15-12
Northwestern AU+Automation Timeline REV6 6-15-12
 
Northwestern AU+Automation Timeline REV6 6-15-12
Northwestern AU+Automation Timeline REV6  6-15-12Northwestern AU+Automation Timeline REV6  6-15-12
Northwestern AU+Automation Timeline REV6 6-15-12
 
Projec
ProjecProjec
Projec
 
Jadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfJadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdf
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 
ScheduleRev- 6
ScheduleRev- 6ScheduleRev- 6
ScheduleRev- 6
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 

WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)

  • 1. ID Task Mode % Work Complete Task Name Duration Start Finish 1 81% Nexen Process Build - WC-14-NXE-007-00 230 days Mon 03/11/14 Fri 18/09/15 2 97% VBX-650-W Modules - WC-14-NXE-007-02 173 days Mon 03/11/14 Wed 01/07/15 3 100% Design 105 days Mon 03/11/14 Fri 27/03/15 4 100% Review Current Build Drawings 5 days Mon 03/11/14 Fri 07/11/14 5 100% Develop P&ID 3 days Mon 10/11/14 Wed 12/11/14 6 100% Confirm Build Requirements and Specifications 5 days Mon 10/11/14 Fri 14/11/14 7 100% Component Selection 81 days Mon 17/11/14 Mon 09/03/15 8 100% Valves & Fittings 25 days Mon 05/01/15 Fri 06/02/15 9 100% Coriolis Meter 2 days Mon 17/11/14 Tue 18/11/14 10 100% Mag Meter 2 days Mon 17/11/14 Tue 18/11/14 11 100% OCF 7000 Centrifuge 10 days Mon 17/11/14 Fri 28/11/14 12 100% Heat Exchanger 3 days Mon 17/11/14 Wed 19/11/14 13 100% Electrical Panels 46 days Mon 05/01/15 Mon 09/03/15 14 100% Centrifuge Feed Pump 3 days Mon 17/11/14 Wed 19/11/14 15 100% Solids Auger 5 days Mon 17/11/14 Fri 21/11/14 16 100% Polymer Tank 10 days Mon 19/01/15 Fri 30/01/15 17 100% Heaters (Steam Ruffnecks) 10 days Mon 05/01/15 Fri 16/01/15 18 100% Temperature Control Valve 2 days Mon 17/11/14 Tue 18/11/14 19 100% Spinner and Heater 2 days Mon 17/11/14 Tue 18/11/14 20 100% Polymer Water Supply Pump 2 days Mon 17/11/14 Tue 18/11/14 21 100% Polymer Injection Pump 2 days Mon 17/11/14 Tue 18/11/14 22 100% Oil Centrate Pump 2 days Mon 17/11/14 Tue 18/11/14 23 100% Water Centrate Pump 2 days Mon 17/11/14 Tue 18/11/14 24 100% Model Development 60 days Mon 29/12/14 Fri 20/03/15 25 100% Structural Model Development/Approval 30 days Mon 29/12/14 Fri 06/02/15 26 100% Process Model Development/Approval 30 days Mon 19/01/15 Fri 27/02/15 27 100% Structural Fabrication Drawings 35 days Mon 12/01/15 Fri 27/02/15 28 100% Piping Fabrication Drawings 35 days Mon 02/02/15 Fri 20/03/15 29 100% Component Fabrication Drawings 80 days Mon 10/11/14 Fri 27/02/15 30 100% Work Bench 2 days Mon 10/11/14 Tue 11/11/14 31 100% Varsol Tank 2 days Mon 10/11/14 Tue 11/11/14 32 100% Sink 2 days Mon 10/11/14 Tue 11/11/14 33 100% Centrate Tank 2 days Tue 06/01/15 Wed 07/01/15 34 100% Centrate Tank Flanges 1 day Fri 27/02/15 Fri 27/02/15 35 100% Catwalks & Stairways 2 days Sun 08/02/15 Mon 09/02/15 36 100% Electrical/Instrumentation Design 60 days Mon 05/01/15 Fri 27/03/15 37 100% Electrical/Inst. Design 60 days Mon 05/01/15 Fri 27/03/15 38 99% Procurement 144 days Wed 19/11/14 Mon 08/06/15 39 100% Piping, Valves & Fittings 20 days Mon 02/02/15 Fri 27/02/15 40 100% Coriolis Meter 45 days Mon 01/12/14 Fri 30/01/15 41 100% Mag Meter 72 days Wed 19/11/14 Thu 26/02/15 42 100% OCF 7000 Centrifuge 100 days Mon 01/12/14 Fri 17/04/15 43 100% Heat Exchanger 72 days Thu 20/11/14 Fri 27/02/15 44 100% Electrical Panels 55 days Mon 19/01/15 Fri 03/04/15 45 100% Centrifuge Feed Pump 72 days Thu 20/11/14 Fri 27/02/15 46 100% Solids Auger 55 days Mon 24/11/14 Fri 06/02/15 47 100% Polymer Tank 14 days Tue 20/01/15 Fri 06/02/15 48 100% Heaters (Steam Ruffnecks) 10 days Mon 19/01/15 Fri 30/01/15 49 100% Temperature Control Valve 57 days Wed 19/11/14 Thu 05/02/15 T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S 28 Sep '14 26 Oct '14 23 Nov '14 21 Dec '14 18 Jan '15 15 Feb '15 15 Mar '15 12 Apr '15 10 May '15 07 Jun '15 05 Jul '15 02 Aug '15 30 Aug '15 27 Sep '15 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Late Progress Deadline WC-14-NXE-007-01 Schedule WC-14-NXE-007-01 Sch Rev 0 Page 1 Fri 29/05/15 12:59 PM
  • 2. ID Task Mode % Work Complete Task Name Duration Start Finish 50 100% Spinner and Heater 85 days Wed 19/11/14 Tue 17/03/15 51 100% Polymer Water Supply Pump 73 days Wed 19/11/14 Fri 27/02/15 52 100% Polymer Injection Pump 73 days Wed 19/11/14 Fri 27/02/15 53 100% Oil Centrate Pump 73 days Wed 19/11/14 Fri 27/02/15 54 100% Water Centrate Pump 73 days Wed 19/11/14 Fri 27/02/15 55 90% Electrical Material 60 days Tue 17/03/15 Mon 08/06/15 56 97% Fabrication 99 days Mon 26/01/15 Thu 11/06/15 57 100% Level 1 Container Modifications 20 days Mon 26/01/15 Mon 02/03/15 58 100% Level 2 Container Modifications 25 days Mon 16/02/15 Mon 06/04/15 59 100% Work Bench 8 days Tue 17/03/15 Thu 26/03/15 60 100% Varsol Tank 8 days Tue 17/03/15 Thu 26/03/15 61 100% Sink 3 days Tue 31/03/15 Thu 02/04/15 62 100% Centrate Tank 18 days Mon 02/02/15 Wed 25/02/15 63 100% Process Piping 50 days Tue 03/02/15 Mon 13/04/15 64 100% Piping/Electrical Supports 30 days Tue 24/03/15 Mon 11/05/15 65 80% Catwalks & Stairways 30 days Fri 01/05/15 Thu 11/06/15 66 100% Piping Testing 40 days Tue 17/02/15 Mon 13/04/15 67 100% NDE Piping Testing 35 days Tue 17/02/15 Mon 06/04/15 68 100% Spool String Testing - Hydrostatic 3 days Thu 09/04/15 Mon 13/04/15 69 100% Pre-Assembly & Installation 17 days Tue 28/04/15 Wed 20/05/15 70 100% Level 1 Component Installation 5 days Tue 28/04/15 Mon 04/05/15 71 100% Level 2 Comonent Installation 5 days Tue 05/05/15 Mon 11/05/15 72 100% Piping Installation 5 days Tue 12/05/15 Mon 18/05/15 73 100% Disassemble for Painting 2 days Tue 19/05/15 Wed 20/05/15 74 82% Painting 23 days Thu 07/05/15 Mon 08/06/15 75 100% Level 1 Container 5 days Thu 07/05/15 Wed 13/05/15 76 100% Level 2 Container 5 days Thu 14/05/15 Wed 20/05/15 77 100% Tanks & Components 2 days Thu 21/05/15 Fri 22/05/15 78 40% Piping 10 days Tue 26/05/15 Mon 08/06/15 79 18% Final Assembly 28 days Thu 21/05/15 Mon 29/06/15 80 88% Component Installation 8 days Thu 21/05/15 Mon 01/06/15 81 0% Piping Installation 5 days Tue 09/06/15 Mon 15/06/15 82 0% Electrical Installation 20 days Tue 02/06/15 Mon 29/06/15 83 0% FAT 2 days Tue 30/06/15 Wed 01/07/15 84 0% Final Acceptance Testing 2 days Tue 30/06/15 Wed 01/07/15 85 36% Pre-Process 53' HC - WC-14-NXE-007-05 152 days Mon 05/01/15 Tue 04/08/15 86 100% Design 110 days Mon 05/01/15 Fri 05/06/15 87 100% GO-ON Approval 0 days Mon 05/01/15 Mon 05/01/15 88 100% Structural/Mechanical Design Work 30 days Mon 02/03/15 Fri 10/04/15 89 100% Electrical Design Work 30 days Mon 02/03/15 Fri 10/04/15 90 100% Model Development 40 days Mon 13/04/15 Fri 05/06/15 91 100% Structural Model Development/Approval 10 days Mon 13/04/15 Fri 24/04/15 92 100% Process Model Development/Approval 10 days Mon 27/04/15 Fri 08/05/15 93 100% Structural Fabrication Drawings 5 days Mon 27/04/15 Fri 01/05/15 94 100% Piping Fabrication Drawings 15 days Mon 27/04/15 Fri 29/05/15 95 0% Component Fabrication Drawings 5 days Mon 01/06/15 Fri 05/06/15 96 35% Procurement 60 days Mon 04/05/15 Fri 24/07/15 97 67% Pumps, Piping, Valves & Fittings 30 days Mon 04/05/15 Fri 12/06/15 98 11% Electrical Panels - Items 45 days Mon 25/05/15 Fri 24/07/15 99 76% Fabrication 20 days Mon 11/05/15 Fri 05/06/15 05/01 T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S 28 Sep '14 26 Oct '14 23 Nov '14 21 Dec '14 18 Jan '15 15 Feb '15 15 Mar '15 12 Apr '15 10 May '15 07 Jun '15 05 Jul '15 02 Aug '15 30 Aug '15 27 Sep '15 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Late Progress Deadline WC-14-NXE-007-01 Schedule WC-14-NXE-007-01 Sch Rev 0 Page 2 Fri 29/05/15 12:59 PM
  • 3. ID Task Mode % Work Complete Task Name Duration Start Finish 100 100% Container Modifications 10 days Mon 18/05/15 Fri 29/05/15 101 50% Components- Manifolds..etc. 4 days Thu 28/05/15 Tue 02/06/15 102 75% Process Piping 20 days Mon 11/05/15 Fri 05/06/15 103 28% Pre-Assembly & Installation 17 days Wed 27/05/15 Thu 18/06/15 104 60% Component Installation 5 days Wed 27/05/15 Tue 02/06/15 105 0% Piping Installation 5 days Mon 08/06/15 Fri 12/06/15 106 0% Piping/Electrical Supports 2 days Mon 15/06/15 Tue 16/06/15 107 0% Disassemble for Painting 2 days Wed 17/06/15 Thu 18/06/15 108 0% Piping Testing 6 days Fri 19/06/15 Fri 26/06/15 109 0% NDE Piping Testing 3 days Fri 19/06/15 Tue 23/06/15 110 0% Spool String Testing - Hydrostatic 3 days Wed 24/06/15 Fri 26/06/15 111 0% Painting 13 days Fri 19/06/15 Tue 07/07/15 112 0% Container 3 days Fri 19/06/15 Tue 23/06/15 113 0% Components 2 days Mon 29/06/15 Tue 30/06/15 114 0% Piping 5 days Wed 01/07/15 Tue 07/07/15 115 0% Final Assembly 22 days Thu 02/07/15 Fri 31/07/15 116 0% Component Installation 3 days Thu 02/07/15 Mon 06/07/15 117 0% Piping Installation 3 days Wed 08/07/15 Fri 10/07/15 118 0% Electrical Installation 5 days Mon 27/07/15 Fri 31/07/15 119 0% FAT 2 days Mon 03/08/15 Tue 04/08/15 120 0% Final Acceptance Testing 2 days Mon 03/08/15 Tue 04/08/15 121 56% Vapor Recovery Unit VRU - WC-14-NXE-007-07 178 days Mon 10/11/14 Wed 15/07/15 122 100% Design 115 days Mon 10/11/14 Fri 17/04/15 123 100% GO-ON Approval 0 days Mon 10/11/14 Mon 10/11/14 124 100% Structural/Mechanical Design Work 30 days Mon 05/01/15 Fri 13/02/15 125 100% Electrical Design Work 60 days Mon 26/01/15 Fri 17/04/15 126 100% Model Development 45 days Mon 16/02/15 Fri 17/04/15 127 100% Structural Model Development/Approval 10 days Mon 16/02/15 Fri 27/02/15 128 100% Process Model Development/Approval 20 days Mon 02/03/15 Fri 27/03/15 129 100% Structural Fabrication Drawings 10 days Mon 02/03/15 Fri 13/03/15 130 100% Piping Fabrication Drawings 15 days Mon 30/03/15 Fri 17/04/15 131 91% Procurement 50 days Mon 06/04/15 Fri 12/06/15 132 80% Pumps, Piping, Valves & Fittings 50 days Mon 06/04/15 Fri 12/06/15 133 100% Electrical Panels - Items 25 days Mon 20/04/15 Fri 22/05/15 134 100% Fabrication 30 days Mon 30/03/15 Fri 08/05/15 135 100% Container Modifications 15 days Mon 30/03/15 Fri 17/04/15 136 100% Carbon - Clay Partitions 8 days Mon 20/04/15 Wed 29/04/15 137 100% Process Piping 20 days Mon 13/04/15 Fri 08/05/15 138 0% Pre-Assembly & Installation 14 days Mon 01/06/15 Thu 18/06/15 139 0% Component / Mesh Installation 5 days Mon 01/06/15 Fri 05/06/15 140 0% Piping Installation 5 days Mon 08/06/15 Fri 12/06/15 141 0% Piping/Electrical Supports 2 days Mon 15/06/15 Tue 16/06/15 142 0% Disassemble for Painting 2 days Wed 17/06/15 Thu 18/06/15 143 0% Piping Testing 6 days Fri 19/06/15 Fri 26/06/15 144 0% NDE Piping Testing 3 days Fri 19/06/15 Tue 23/06/15 145 0% Spool String Testing - Hydrostatic 3 days Wed 24/06/15 Fri 26/06/15 146 0% Painting 13 days Fri 19/06/15 Tue 07/07/15 147 0% Container 3 days Fri 19/06/15 Tue 23/06/15 148 0% Components 2 days Mon 29/06/15 Tue 30/06/15 10/11 T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S 28 Sep '14 26 Oct '14 23 Nov '14 21 Dec '14 18 Jan '15 15 Feb '15 15 Mar '15 12 Apr '15 10 May '15 07 Jun '15 05 Jul '15 02 Aug '15 30 Aug '15 27 Sep '15 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Late Progress Deadline WC-14-NXE-007-01 Schedule WC-14-NXE-007-01 Sch Rev 0 Page 3 Fri 29/05/15 12:59 PM
  • 4. ID Task Mode % Work Complete Task Name Duration Start Finish 149 0% Piping 5 days Wed 01/07/15 Tue 07/07/15 150 0% Final Assembly 8 days Thu 02/07/15 Mon 13/07/15 151 0% Component Installation 3 days Thu 02/07/15 Mon 06/07/15 152 0% Piping Installation 3 days Wed 08/07/15 Fri 10/07/15 153 0% Electrical Installation 5 days Tue 07/07/15 Mon 13/07/15 154 0% FAT 2 days Tue 14/07/15 Wed 15/07/15 155 0% Final Acceptance Testing 2 days Tue 14/07/15 Wed 15/07/15 156 8% Solids Auger Removal Bin- WC-14-NXE-007-06 222 days Thu 13/11/14 Fri 18/09/15 157 35% Design 85 days Wed 01/04/15 Tue 28/07/15 158 100% GO-ON Approval 0 days Wed 01/04/15 Wed 01/04/15 159 100% Structural/Mechanical Design Work 30 days Wed 01/04/15 Tue 12/05/15 160 96% Electrical Design Work 45 days Wed 01/04/15 Tue 02/06/15 161 30% Model Development 55 days Wed 13/05/15 Tue 28/07/15 162 65% Structural Model Development/Approval 20 days Wed 13/05/15 Tue 09/06/15 163 0% Process Model Development/Approval 20 days Wed 10/06/15 Tue 07/07/15 164 0% Structural Fabrication Drawings 10 days Wed 10/06/15 Tue 23/06/15 165 0% Process Fabrication Drawings 15 days Wed 08/07/15 Tue 28/07/15 166 0% Procurement 56 days Wed 03/06/15 Wed 19/08/15 167 0% Pumps, Skids, Agur, Piping, Valves & Fittings 20 days Wed 15/07/15 Tue 11/08/15 168 0% Electrical Panels - Items 56 days Wed 03/06/15 Wed 19/08/15 169 0% Fabrication 15 days Wed 05/08/15 Tue 25/08/15 170 0% Assembly 15 days Wed 26/08/15 Tue 15/09/15 171 0% Final Acceptance Testing 3 days Thu 13/11/14 Fri 18/09/15 172 73% Power Distribution 20' HC - WC-14-NXE-007-03 149.5 days Mon 05/01/15 Fri 31/07/15 173 100% Engineering & Procurement Phase 50 days Mon 05/01/15 Fri 13/03/15 174 100% GO-ON Approval 0 days Mon 05/01/15 Mon 05/01/15 175 100% Structural/Mechanical Design Work 20 days Mon 05/01/15 Fri 30/01/15 176 100% Electrical Design Work 20 days Mon 05/01/15 Fri 30/01/15 177 100% Long Lead Procurement Items ( Electrical ) 30 days Mon 02/02/15 Fri 13/03/15 178 29% Construction Phase 99.5 days Mon 16/03/15 Fri 31/07/15 179 100% Container Preperation 2 days Mon 16/03/15 Tue 17/03/15 180 100% Door Opening 1 day Wed 18/03/15 Wed 18/03/15 181 100% Door Framing installation 1 day Thu 19/03/15 Thu 19/03/15 182 0% Penetrations 1 day Mon 01/06/15 Mon 01/06/15 183 0% Cord Box Welding 4 days Tue 23/06/15 Fri 26/06/15 184 100% Door Installation 1 day Mon 29/06/15 Mon 29/06/15 185 0% Required Welding Complete and NDT 2 days Tue 30/06/15 Wed 01/07/15 186 0% Exterior sand blasting 1 day Thu 02/07/15 Thu 02/07/15 187 0% Primer and Painting 2 days Fri 03/07/15 Mon 06/07/15 188 0% Electrical Finish 15 days Tue 07/07/15 Mon 27/07/15 189 0% Caulking Completion 1 day Tue 28/07/15 Tue 28/07/15 190 0% Testing 2 days Wed 29/07/15 Thu 30/07/15 191 0% Cleaning 0.5 days Fri 31/07/15 Fri 31/07/15 192 0% Misc. Fabrication 15 days Tue 02/06/15 Mon 22/06/15 193 0% Cord Box Fabrication/Welding 15 days Tue 02/06/15 Mon 22/06/15 194 0% Closing Out 0 days Fri 31/07/15 Fri 31/07/15 195 0% shipping Unit 0 days Fri 31/07/15 Fri 31/07/15 196 0% Utilities Module 40' HC - WC-14-NXE-007-04 75 days Mon 01/06/15 Fri 11/09/15 01/04 05/01 31/07 31/07 T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S 28 Sep '14 26 Oct '14 23 Nov '14 21 Dec '14 18 Jan '15 15 Feb '15 15 Mar '15 12 Apr '15 10 May '15 07 Jun '15 05 Jul '15 02 Aug '15 30 Aug '15 27 Sep '15 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Late Progress Deadline WC-14-NXE-007-01 Schedule WC-14-NXE-007-01 Sch Rev 0 Page 4 Fri 29/05/15 12:59 PM
  • 5. ID Task Mode % Work Complete Task Name Duration Start Finish 197 0% Engineering & Procurement Phase 75 days Mon 01/06/15 Fri 11/09/15 198 0% GO-ON Approval 0 days Mon 01/06/15 Mon 01/06/15 199 0% Structural/Mechanical Design Work 15 days Mon 01/06/15 Fri 19/06/15 200 0% Electrical Design Work 15 days Mon 01/06/15 Fri 19/06/15 201 0% Long Lead Procurement Items ( Electrical ) 60 days Mon 22/06/15 Fri 11/09/15 202 0% Construction Phase 39.5 days Mon 22/06/15 Fri 14/08/15 203 0% Container Preperation 2 days Mon 22/06/15 Tue 23/06/15 204 0% Door Opening 2 days Wed 24/06/15 Thu 25/06/15 205 0% Door Framing installation 1 day Fri 26/06/15 Fri 26/06/15 206 0% Penetrations 1 day Mon 29/06/15 Mon 29/06/15 207 0% Cord Box Welding 3 days Wed 08/07/15 Fri 10/07/15 208 0% Door Installation 1 day Mon 13/07/15 Mon 13/07/15 209 0% Required Welding Complete and NDT 2 days Tue 14/07/15 Wed 15/07/15 210 0% Exterior sand blasting 1 day Thu 16/07/15 Thu 16/07/15 211 0% Primer and Painting 2 days Fri 17/07/15 Mon 20/07/15 212 0% Electrical Finish 15 days Tue 21/07/15 Mon 10/08/15 213 0% Caulking Completion 1 day Tue 11/08/15 Tue 11/08/15 214 0% Testing 2 days Wed 12/08/15 Thu 13/08/15 215 0% Cleaning 0.5 days Fri 14/08/15 Fri 14/08/15 216 0% Misc. Fabrication 10 days Wed 24/06/15 Tue 07/07/15 217 0% Cord Box Fabrication/Welding 10 days Wed 24/06/15 Tue 07/07/15 218 0% Closing Out 0 days Fri 14/08/15 Fri 14/08/15 219 0% shipping Unit 0 days Fri 14/08/15 Fri 14/08/15 220 100% Office 1 day Mon 24/11/14 Mon 24/11/14 221 100% Office 1 day Mon 24/11/14 Mon 24/11/14 222 100% Critical Spares 67 days Mon 02/02/15 Tue 05/05/15 223 100% Selection 20 days Mon 02/02/15 Fri 27/02/15 224 100% Procurement 40 days Wed 04/03/15 Tue 28/04/15 225 100% Packaging & Identification 5 days Wed 29/04/15 Tue 05/05/15 01/06 14/08 14/08 T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S 28 Sep '14 26 Oct '14 23 Nov '14 21 Dec '14 18 Jan '15 15 Feb '15 15 Mar '15 12 Apr '15 10 May '15 07 Jun '15 05 Jul '15 02 Aug '15 30 Aug '15 27 Sep '15 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Late Progress Deadline WC-14-NXE-007-01 Schedule WC-14-NXE-007-01 Sch Rev 0 Page 5 Fri 29/05/15 12:59 PM