SlideShare a Scribd company logo
The adoption of Industrialised Building System (IBS)
construction in Malaysia: The history, policies,
experiences and lesson learned
Mohd Idrus Din, Noraini Bahri, Mohd Azmi Dzulkifly, Mohd Rizal Norman, Kamarul
Anuar Mohamad Kamar *, and Zuhairi Abd Hamid
Construction Industry Development Board (CIDB) Malaysia
* Corresponding author (kamarul2411@gmail.com)
Purpose Industry and government in Malaysia coined the term industrialised building system (IBS) to describe the
adoption of construction industrialisation, mechanisation, and the use of prefabrication of components in building
construction. IBS consists of precast component systems, fabricated steel structures, innovative mould systems, modular
block systems, and prefabricated timber structures as construction components. Parts of the building that are repetitive
but difficult – and too time consuming and labour intensive to be casted onsite – are designed and detailed as
standardised components at the factory and are then brought to the site to be assembled. The construction industry in
Malaysia has started to embrace IBS as a method of attaining better construction quality and productivity, reducing risks
related to occupational safety and health, alleviating issues for skilled workers and dependency on manual foreign
labour, and achieving the ultimate goal of reducing the overall cost of construction. The chronology of IBS-adoption in
Malaysia goes back a long way, reaching back to the 1960s, when precast elements were adopted in the building
industry to address the problem of an acute housing shortage. However, the introduction of IBS was never sustained
beyond this period. As a result of the failure of early closed-fabricated systems, the industry is now avoiding changing its
construction method to IBS. Some of the foreign systems that were introduced during the late 1960s and 1970s were
also found to be unsuitable in Malaysia’s climate and not very compatible with social practices. IBS has regained its
popularity presently due to problems with construction workforces where the industry has been relying for a long time on
unskilled workers from neighbouring countries. Method In 1999, the IBS Strategic Plan was launched to promote the
system’s usage in the industry. This was followed by the IBS Roadmap 2003-2010 and IBS Roadmap 2011-2015; these
are blueprints for industrialised construction by 2015. The roadmaps have been developed by the government to chart
progress and guide the awareness programmes, incentives, vendor scheme development, training, quality control and
research and development programmes. The government also took the lead in 2008, by mandating that all public-sector
projects must attain no less than 70% IBS-content under the Treasury Circular SPP 07/2008. This policy aims to build up
momentum and to establish demand for IBScomponents, thus bringing the cost down. Results & Discussion At
present, IBS-construction is widely used as a mainstream method and the implementation has moved from prefabrication
towards mechanisation, automation, and robotics applications. This paper highlights some of the history, policies,
experiences, and lesson learned in adopting IBS in Malaysia. The outlook for IBS-implementation in Malaysia is bright,
but much work is still needed from the government to convince the contractors, manufacturers, and suppliers to adopt
IBS-construction.
Keywords: construction, industrialized building systems, Malaysia
INTRODUCTION
Industrialised Building System (IBS) is the term
coined by the industry and government in Malaysia
to represent the adoption of construction
industrialisation and the use of prefabrication of
components in building construction. IBS is defined
as a construction technique in which components
are manufactured in a controlled environment (on or
off site), transported, positioned and assembled into
a structure with minimal additional site work (Hamid
et al., 2008; CIDB, 2007; CIDB, 2005 and CIDB,
2003). It consists of precast component systems,
fabricated steel structures, innovative mould
systems, modular block systems and prefabricated
timber structures as construction components (CIDB,
2003). Parts of the building that are repetitive but
difficult – and too time consuming and labour
intensive to be casted onsite – are designed and
detailed as standardised components at the factory
and are then brought to the site to be assembled
(CIDB, 2003). The onsite casting activities in IBS
utilise innovative and clean mould technologies
(CIDB, 2007; CIDB, 2005 and CIDB, 2003). In the
Malaysian context, the classification by the CIDB is
widely used and well understood by scholars and
practitioners. CIDB has classified the IBS systems
into five categories as depicted in Table 1 (CIDB,
2003).
Table 1: IBS classification (CIDB, 2003)
Classification Descriptions
Precast concrete
framed buildings
The most common group of IBS products is the precast concrete elements; precast
concrete columns, beams, slabs, walls, 3-D components (e.g. balconies, staircases,
toilets, lift chambers, refuse chambers), lightweight precast concrete, as well as
permanent concrete formworks.
Formwork System Considered as one of the low-level or the least prefabricated IBS, as the system
generally involves site casting and is therefore subject to structural quality control, the
products offer high-quality finishes, and fast construction with less site labour and
material requirement.
Steel Framing System Commonly used with precast concrete slabs, steel columns and beams, steel framing
systems have always been the popular choice and used extensively in the fast-track
construction of skyscrapers. Recent developments in this type of IBS include the
increased usage of light steel trusses consisting of cost-effective profiled cold-formed
channels and steel portal frame systems as alternatives to the heavier traditional hot-
rolled sections.
Prefabricated Timber
Framing System
The system consists of timber building frames and timber roof trusses. While the latter
are more popular, timber building frame systems also have their own niche market,
offering interesting designs from simple dwelling units to buildings requiring high
aesthetical values such as chalets for resorts.
Blockwork System The construction method of using conventional bricks has been revolutionised by the
development and usage of interlocking concrete masonry units (CMU) and lightweight
concrete blocks. The tedious and time-consuming traditional brick-laying tasks are
greatly simplified by the usage of these effective alternative solutions.
The construction industry has started to embrace
IBS as a method of attaining better construction
quality and productivity, reducing risks related to
occupational safety and health, alleviating issues for
skilled workers and dependency on manual foreign
labour, and achieving the ultimate goal of reducing
the overall cost of construction. Apart from this, it
offers minimal wastage, fewer site materials, a
cleaner and neater environment, controlled quality,
and lower total construction costs (Pan et al. 2008,
Hamid et al. 2008 and Pan et al. 2007). Already
utilized in Malaysia since 1960s, IBS is the way
forward for the industry stakeholders to make leaps
and bounds progress in the Malaysian construction
industry. Sufficient exposure and incentives are
pouring in to encourage industry players to make a
paradigm move – from conventional to IBS
construction.
THE CHRONOLOGY OF IBS ADOPTION IN MALAYSIA
1. Development of IBS in post-independent
Malaysia:
IBS has been introduced in Malaysia since early
1960s when Public Work Department (PWD) and
Ministry of Housing and Local Government (MHLG)
of Malaysia visited several European countries and
evaluate their housing development program
(Thanoon et al. 2003). In 1963, the
government sent a group of architect from PWD to
learn industrialised building in some of European
countries. The following year, another group of
architect from the Federal Capital Commission was
sent to France for about 6 month for exposure in
industrialised buildings (Sumadi et al. 2001). In the
same year, Ministry of Housing and Local
Government (MHLG) was being set up by the
government to concentrate to development of
housing. The ministry officers and representatives
visited West Germany, Denmark and France to
gather more information on industrialised building
later that year (Sumadi et al. 2001).
2. Development in 1964 to 1970s:
After their successful visit in 1964, the government
had started its first IBS project aims to speed up the
delivery time and built affordable and quality houses
as stipulated under the 2nd
Malayan Plan 1960-1965
and the 1st
Malaysian Plan 1966 – 1970. About 22.7
acres of land along Jalan Pekeliling, Kuala Lumpur
was dedicated to the project comprising 7 blocks of
17 stories flat consists of 3000 units of low-cost flat
and 40 shops lot. This project was awarded to JV
Gammon and Larsen and Nielsen using Danish
System of large panel pre-cast concrete wall and
plank slabs. The project was completed within 27
months from 1966 to 1968 including the time taken
in the construction of the RM 2.5 million casting yard
at Jalan Damansara. In 1965, the second housing
project initiated by the government comprising 6
blocks of 17 stories flats and 3 block of 18 stories
flats at Jalan Rifle Range, Penang. The project was
awarded to Hochtief and Chee Seng using French
Estoit System (CIDB, 2006 and CIDB, 2003). Both
projects utilised the large panel system which
required large concrete panel cast in the factory and
transported to site on trailers for assembly. The
speed of construction is much faster although the
tendered price was slightly higher by 5% to 8%
(Sarja, 1998). Another earliest IBS project was at
Taman Tun Sardon in Penang (consists of 1,000
units five-storey walk up flat). IBS pre-cast
component and system in the project was designed
by British Research Establishment (BRE) for low
cost housing (BRECAST system). A similar system
was constructed almost at the same time at
Edmonton, North London and about 20,000
BRECAST dwellings were constructed throughout
UK from 1964 to 1974 (CIDB, 2006). Nonetheless,
the building design was very basic and not
considering the aspect of serviceability such as the
local needs to have wet toilet and bathroom
(Rahman and Omar, 2006).
3. Development in 1970s to early 1980s:
In 1978, the Penang State Government launched
another 1200 units of housing using prefabrication
technology. Two years later, the Ministry of Defense
(MOD) adopted large prefabricated panel
construction system to build 2800 unit of living
quarters at Lumut Naval Base. As one can observed,
IBS was engage at first place in the construction of
low-cost high-rise residential building to overcome
the increasing demand for housing needs. Many
construction in at this time utilised precast wall panel
system. Nonetheless, the industrialisation of
construction was never sustained in this period.
Failure of early closed fabricated systems had
resultant the industry to avoid of changing their
construction method to IBS. Some of the foreign
systems that were introduced during the late 60s and
70s were also found not to be suitable with Malaysia
climate and social practices. Newer and better
technologies were constantly being introduced than
in the market since wet joint systems were identified
to be more suitable to be used in our tropical climate
and it was also better to utilised the bathroom types
which were relatively wetter than those in the Europe
(CIDB, 2005). At the same time recent innovation the
form of precast concrete sandwich wall panels
developed in Europe, has received wide
acceptability in countries having hot temperature
climates due to better insulating properties resulting
in a cooler in door environment and has been send
in several pilot projects in Malaysia through 1970s to
1980s period (Trikha and Ali, 2004).
4. Development in 1980s to 1990s:
During the period of early 80s up to 90s the use of
structural steel components took place particularly in
high rise buildings in Kuala Lumpur. The usage of
steel structure gained much attention with the
construction of 36-storey Dayabumi complex that
was completed in 1984 by Takenaka Corporation of
Japan (CIDB, 2003 and CIDB, 2006). In the 90s,
demand for the new township has seen the increase
in the use of precast concrete system in residential
buildings. Between 1981 and 1993, Perbadanan
Kemajuan Negeri Selangor (PKNS) a state
government development agency acquired pre-cast
concrete technology from Praton Haus International
based on Germany to build low cost houses and
high cost bungalows for the new townships in
Selangor (CIDB, 2003 and Hassim et al. 2009). It
was recorded then, around 52,000 housing units was
constructed using Praton Haus system (Trikha and
Ali, 2004) and the state of art pre-cast factory was
set up in Shah Alam (Sarja, 1998). Other than the
use of Praton House technology from Germany,
PKNS was also embarked in other IBS systems at
the same period; Taisei Marubumi - large panel are
cast in factory using tilt-up system where one panel
forms the base for next panel cast (1,237 housing
units and 11 shop lots at PJS), Hazama system
(3,222 flat units and 1,112 housing units at Bandar
Baru Bangi), Ingeback system which is Swedish
system using large panels in vertical battery mould
and tilt-up table mould (3,694 flat units) All the
project were constructed by local contractor with
international technical support from established
international firms in joint venture partnership
(Hashim et al. 2009 and Sarja, 1998).In that period
IBS used in Malaysia are large panel system
(housing project in Shah Alam and Taman Brown),
metal form system in Wangsa Maju, Pandan Jaya
and Taman Maluri and modular systems which are
heavily promoted by CIDB in government project.
Although the system originated overseas, local
contractors has made modification to suit local
requirement. Instead of steel, high quality film coated
plywood shuttering is used in an innovative mould
system. The form can be easily dismantled and
handled by small crane and can be adjusted to suit
architectural requirement (Sarja, 1998). Other
systems are framing system, modular system and
partially pre-cast system (the Cemlock Built System
which is originate in Australia and used by the
National Housing Department in Pekan Selama
housing project) (Sarja, 1998).
5. Development in 1990s to 1998s
In this booming period of Malaysian construction
1994 -1997, hybrid IBS application used in many
national iconic landmarks such as Kuala Lumpur
Convention Centre (steel beam and roof trusses and
precast concrete slab: Victor Buyck Steel
Construction), Lightweight Railway Train (LRT), KL
Sentral Station (steel roof structure and precast
hollow core: RSPA – Bovis), KL Tower (steel beams
and columns for tower head: Wayss and Freytag),
Kuala Lumpur International Airport (steel roof
structure: KLIAB – Eversendai) and Petronas Twin
Towers (steel beams and steel decking for the floor
system – Mayjus JV and SKJ JV). The booming
period of construction during that time includes the
development and construction of new administration
capital of Malaysia; Putrajaya and Cyberjaya. Both
cities are the massive development areas consist of
new government buildings, business boulevard and
residential area, and most of them were built in IBS
or a hybrid IBS, combination between IBS and
conventional construction.
6. Development in 1998 – 2008
At this state, the use of IBS as a method of
construction in Malaysia is evolving. Many private
companies in Malaysia have teamed up with foreign
expert to offer solutions to their IBS projects (Eastern
Pretech, BPB Malaysian Gypsum, Lafarge and
Duralite). Many had acquired enough knowledge
through technology transfer to build up own capacity
in IBS technologies (PKNS Engineering, Setia
Precast and Global Globe). Setia Precast and Global
Globe using technologies first adopted by Taisei
Corporation of Japan. In fact, Malaysian was also
developed their own IBS technologies (Zenbes,
CSR, IJM Formwork, Pryda, Baktian and HC
Precast). The local IBS manufacturers are
mushrooming, although the facilities yet to operate in
full capacity. The IBS system is largely used for
private residential projects in Shah Alam, Wangsa
Maju and Pandan, Dua Residency, Taman Mount
Austin and Tongkang Pecah, Johor. It used in public
residential projects in Putrajaya Prescient 17 and
Prescient 9, PPR Sungai Besi, Sungai Bedaun, and
Telipok, Sabah. The new generation of building that
utilised IBS is better in term of quality, and
architectural appearance compared to the earlier
generation. IBS is also widely used to construct
government’s schools and teachers housing
complexes (Kuala Kangsar, Yan and Sungai Petani),
hospitals (Serdang Hospital and UKM Hospital),
collages and universities (Penang Matriculation
Collage, UiTM, Kuching and University PETRONAS
and University of Malaysia Sabah), custom and
immigration complexes (Kelana Jaya and Johor
Bahru), private buildings (Weld Tower, Maju
Perdana, Traders Hotel, City Square and Olympia
Tower, Jaya Jusco, IKEA) and police quarters
(Senawang). The IBS agenda was further boosted
with the 2004, 2005 and 2006 Malaysia Budget
announcements. In 2004, new government building
projects had been strongly encouraged to have at
least 50% of IBS content in their construction
elements which had been calculated using IBS
Score Manual developed by CIDB. Furthermore, in
2005, the government had pledged to construct
100,000 units of affordable houses using IBS (Hamid
et al. 2008). Finally, in 2006, a tax incentive was
offered through Acceleration Capital Allowance
(ACA). IBS manufacturers would be given ACA for
expenses incurred in the purchase of steel moulds
used for production of precast concrete components
to be claimed within three years (CIDB, 2005 and
Shaari, 2006).
7. 2008 – Present
One of the most important milestones of IBS policy is
regulation on the use of IBS in the construction of
public buildings. In November 2008, the Treasury
Malaysia issued a Treasury Circular Letter, now
referred to as SPP 7/2008, to all Malaysian
government agencies directing them to increase the
IBS contents of their building development projects
to a level not less than 70 points of the IBS score
and in that sense IBS must be incorporated as part
of the contract document for tender (Hamid et al.
2008). The circular letter took effect immediately and
the Implementation and Coordination Unit (ICU) of
the Prime Minister’s Department has been given the
task of monitoring the level of compliance to this
directive by the respective agencies. The decision
was to create sufficient momentum for the demand
for IBS components and to create a spill-out effect
throughout the nation. To monitor the
implementation, the government established the
National IBS Secretariat. It involves coordination
between inter-ministry levels to make sure the policy
is successfully implemented. During a period from
October 2008 and May 2010, about 331 projects
under 17 ministries were awarded and constructed
using IBS (CIDB, 2010). The majority of the projects
were construction of public schools, hospitals, higher
learning institutions and government offices
throughout Malaysia. The total cost of the projects
was about RM 9.6 billion (CIDB, 2010).
EXPERIENCES AND LESSONS LEARNED ON IBS
CONSTRUCTION IN MALAYSIA
1. There is a change in paradigm regarding
IBS in Malaysia in the past few years. In the past,
the majority of contractors and industry stakeholders
still divided either to use IBS or conventional method
although the benefits of IBS are clear and eminent.
But this is not the case now, the industry, nowadays
has to think of a system to be implemented in their
project (weather it conventional or IBS) due to the
increase need of quality end-product and speed of
construction, and coping with the issue of foreign
workers. In the case of public building projects, the
industry is instructed to use IBS system. So, the
industry both in the private and public construction
projects has no other choice but to be involved in
IBS and adopt industrialisation in construction. (In
November 2008, the Treasury Malaysia issued a
Treasury Circular Letter, now referred to as SPP
7/2008, to all Malaysian government agencies
directing them to increase the IBS contents of their
building development projects to a level not less than
70 points of the IBS score and IBS must be
incorporated as part of the contract document for
tender. The decision was to create sufficient
momentum for the demand for IBS components and
to create a spill-out effect throughout the nation).
Due to this policy, the cost of constructing in IBS has
reduced significantly. The adoption in the past was
normally based on wanting rather than by viability.
IBS system in Malaysia is now, mostly competitive if
not cheaper if one compare it to the conventional
practices depending on type of projects, type of
systems and volume.
2. The IBS in Malaysia promotes open
system or hybrid system and encourages full
industry participation compared to the prefab closed
system where only limited industry companies can
participate. IBS supply chain should comprises of
modular component-based products that can be
produce and interchangeable between any project
thus promote mass customisation at the customers
end. Therefore, a company that can utilize the IBS
supply chain will enable it to sell systems rather than
selling single products. Standardising the
construction industry is a critical factor in
establishing an Open System in Malaysia. The
concept of the OBS is similar to what has happened
in the ICT industry whereby through standardization
of jointing parts such as USB ports, consumers can
buy computer equipment such as mouse or scanner
anywhere in the world. The equipment can then be
easily installed by the users as the connection from
the equipment to the computer has been
internationally standardized.
3. One of the important milestones in IBS
Roadmap 2003-2010 was the introduction of
Modular Coordination (MC). MC is a concept of
coordination of dimensions and space where
buildings and components are dimensioned and
positioned in a basic unit or module known as 1M
which is equivalent to 100 mm, as stipulated in MS
1064, and developed in 2000. The concept allows
standardisation in design and building components.
It encourages participation from manufactures and
assemblers to enter the market, thus reducing the
price of IBS components. Modular need to be
adopted to cut down the waste in IBS. However the
implementation of modular coordination requires
better design planning.
4. Malaysian construction industry is very
good in modifying and adopting IBS technologies
captured from oversea practices. Many private
companies in Malaysia in present day have teamed
up with foreign expert to offer solutions to their IBS
projects. Many had acquired enough knowledge
through technology transfer to build up own capacity
in IBS technologies. Many world-class Malaysian
developers have chosen IBS over the conventional
methods for important projects such as the Petronas
Twin Towers, Putrajaya, KL Sentral and KLIA. There
is ample evidence that the failures of past
construction systems are due to blind acceptance of
foreign products that were not open (flexible) and
were unsuitable to our climate and culture.
5. Successful IBS contractors as observed
are not a user of technology or limit its role as project
manager and assembler. Most successful IBS
contractors have an in-house manufacturing and
design capacity. They also invest in and sometimes
invent systems, and so do not just depend on
existing manufacturers. The also partner with
oversea partners to acquire the technologies.
6. One of the major issues of IBS is on
changing users’ perception. Users tend to think that
IBS buildings is easy to leak and can not be
renovated. However, through the advancement of
technologies and better planning and design, IBS
buildings/housings in the present days have
improved in term of performance and can be
renovated by users.
7. Some of the foreign systems that were
introduced during the late 60s and 70s were also
found not to be suitable with Malaysia climate and
social practices. Newer and better technologies were
constantly being introduced than in the market since
wet joint systems were identified to be more suitable
to be used in our tropical climate and it was also
better to utilised the bathroom types which were
relatively wetter than those in the Europe.
8. IBS in Malaysia is seen as a threat to
traditional methods but in reality many IBS
technologies like block works is exist together with
conventional practices. The failure of IBS to
penetrate the market is due to a misconception that
it will eventually replace the traditional sector, while it
actually should work closely in tandem to promote
best practice in construction. The sharing of best
practice between the two approaches is essential for
the continued successful development of both
construction sectors. IBS should be looked by the
industry as easy, simple and cost effective solutions
to the players.
9. Each IBS system has its own advantages
and limitations. The selection and implementation of
correct technology in IBS projects is perhaps the key
to IBS success. There is a need to realise that
precast concrete IBS is not suitable for every project.
If more people were aware of its capabilities and
available technology, they could identify particular
system that suited the project. The advantages of
IBS systems in Malaysia are as follows:
BARRIERS TO IBS ADOPTION IN MALAYSIA
1. Currently, the incentives for IBS are not
sufficient. IBS adoption requires more pull and push
factors from the government. Due to the small profit
margin, the change from conventional to IBS was not
feasible, unless, more attractive incentive systems
and benefits which can lure the conventionalist to
IBS are in place.
2. The availability of cheap foreign labour which
offsets the cost benefit of using IBS is a root cause
of the slow adoption in the past. As long as it is easy
for the industry to find foreign workers, labour rates
will remain low and builders will find it unattractive to
change into simplified solutions such as IBS.
3. The limited take up also relates to sheer cost of
investment and the inadequacy of market size. Since
the Asian financial crisis in 1997 and global
recession in 2008, it becomes apparent that large
investments in central production plants are
uneconomical.
4. To use a higher level of IBS, the adopters
require a huge volume of works to break even on the
investment. Although it creates more value to
construction, it is literally a more expensive option
due to the paid up capitals and maintenance of
machineries. Inconsistency of volume over time and
lack of business continuity resulted in the investment
in latest innovation not being commercially
sustainable.
5. Low standardisation of components also
hinders successful use of IBS. The tailor-made
components which do not fit into another project will
increase initial costs due to the cost of the mould
and design. Lack of standardisation was due to a
lack of a certification and accreditation scheme on
IBS and the lukewarm response to Modular
Coordination (MC) promotion under MS 1064.
6. There is a general consensus among
practitioners that IBS needs mass production to
achieve economic viability, but currently, in Malaysia,
there is no assurance of continuity of production,
thus limiting interest in IBS.
7. Supply Chain Management (SCM) and
partnering concept has not been fully understood by
the industry. Currently, the cooperation between
contractors, manufacturers and suppliers is weak in
many cases. Improving the procurement system and
supply chain is the key to achieving IBS success for
contracting companies.
THE WAY FORWARD
The lesson learnt on IBS construction in Malaysia
has led to the following recommendations towards
the future improvement of IBS adoption in Malaysia:
1. The rising sustainability awareness around the
globe has put the construction industry under
immense pressure to improve project efficiency and
deliverables. Industrialised Building System (IBS)
has the potential to promote sustainability
development and green construction. This may be
achieved from a controlled production
environment, minimization of construction waste,
extensive usage of energy efficient building
material, a safer and more stable work
environment, and possibly better investment for long
term project economy. The industry need to seize
this opportunity and use IBS as their competitive
advantages in promoting sustainable construction.
2. The mass construction workforce, especially
the locals, needs to upgrade their skills to be
involved in IBS. The policy on labour focuses on
encouraging personnel to acquire skills in more than
single trade. This would add more value by providing
a more skilled workforce which would ultimately
enhance the competitive advantage of the industry in
facing the issue of adoption from conventional to the
IBS. They must be equipped in design, installation
and project management skills which are critical to
IBS. A comprehensive preliminary study should be
conducted by the government to identify the skill
gaps in the IBS sector in order to create a
comprehensive and systematic training programme.
The preliminary study will ensure that the training fits
the needs of IBS organisations and accommodates
current skill shortages in the market, particularly
specialist skills such as design and installation,
based on information from real practice.
3. A vendor development programme modeled
along the lines of the development of the national car
industry should be established to target delivery of
building components for the construction. The
vendor program is to be accredited by existing
government agencies which can provide a vetting
process not only to guarantee consistent quality but
also the achievement of structural capacity, fire
rating and other requirements. The selected vendor
are to be provided training, seed capital,
components design, and selected private sector
consultant to start up production factories. The
location of this vendor’s manufacturing plant has to
be located in the areas with available labour. Based
on educated assumption, the expected investment
requirement of RM 1.25 million is considered within
the reach of SMEs and small contractors displaced
by the new technology. A system is to be developed
such that building component accredited will be
given green lane approval such that technical and
non-technical legislation that hinders implementation
of the new technology will be removed. The
government can help by conducting market research
to ascertain market opportunities to the vendors. The
vendors also need inventory management
consultancy and advice and development of better
tools and infrastructures required for location of
manufacturing plant.
4. Manufacturers and all players of IBS sectors
need to create highest value for IBS to serve the
clients best interest, as we know clients in a private
sector are more demanding in term of design
esthetic value. With this regards, we need to move
from mass production of components to mass
customisation of buildings where the building design
can be tailor-made to specific customer needs. The
industry shall need to encourage automation and
robotic to be really reduce the use of workers in
construction and prefabrication. The government
also perhaps needs to encourage manufacturers to
produce ‘modular housing’ which move all the work
trade at site to the manufacturing floor. We need to
move up the level of industrialisation and encourage
innovation, whilst low innovative systems which do
contained enough value like mould systems will be
discouraged. Proper incentive and tax holiday need
to introduce to cater the production of innovative
IBS.
5. Malaysian IBS contractors need to benchmark
IBS technologies, lesson learnt and best practices
from other countries. Construction industrialisation is
a worldwide agenda. IBS is already successful
adopted in Finland, Sweden, Japan, Germany and
Singapore where offsite technologies had eventually
modernised and improved the industry. This
research recommended the industry players to find
ways to capture and disseminate technologies,
lesson learned, and best practices from successful
countries and companies to expedite our learning
curve on IBS and to guide the way forward. The
government should launch a forum on a regular
basis of academics and associated practitioners
active in IBS for exchange of information and
experience, development of new techniques and
advice on promotion and implementation of IBS. An
online portal was also suggested to disseminate
international trends, products and processes
associated with the IBS.
References
1. CIDB, “CIDB News”, Construction Industry
Development Board (CIDB) Publication, first
quarters 2010, 2010
2. CIDB, “Malaysian construction industry outlook”,
presentation by Business Development Sector of
CIDB, August 2009
3. CIDB, “Malaysian construction industry outlook”,
presentation by Business Development Sector of
CIDB, August 2008
4. CIDB, “IBS Implementation in Malaysia”,
Construction Industry Development Board (CIDB),
Kuala Lumpur, 2008
5. CIDB, “IBS Digest at Malbex”, IBS Digest, Special
Issues on 24th Malaysian International Building
Exposition, pp. 19-22, Malbex, september 2007.
6. CIDB, “Report of quality assessment for project in
Cambodia and Thailand constructed by Malaysian
contractor”, Construction Industry Development
Board (CIDB), Kuala Lumpur, 2007.
7. CIDB, “Implementing IBS Roadmap: Mid-term
review of IBS Roadmap 2003-2010”, Construction
Industry Development Board (CIDB), Kuala Lumpur,
2007.
8. CIDB, “IBS Survey 2005: Survey on Malaysian
Architects”, Construction Industry Development
Board (CIDB), Kuala Lumpur, 2005 .
9. CIDB, “Industrialised Building System (IBS)
Roadmap 2003-2010”, Construction Industry
Development Board (CIDB), Kuala Lumpur, 2003.
10. CIDB, “IBS Survey 2003 - A Survey on the Usage of
Industrialised Building System in Malaysian
Construction Industry”, Construction Industry
Development Board, Kuala Lumpur, 2003.
11. CIDB, “IBS Roadmap 2003-2010”, Construction
Industry Development Board (CIDB), Kuala Lumpur,
2003.
12. Hamid, Z., Kamar, K.A.M., Zain, M., Ghani, K.,
Rahim, A.H.A., “Industrialized Building System (IBS)
in Malaysia: The Current State and R&D Initiatives”,
Malaysia Construction Research Journal (MCRJ),
Vol. 2 (1), pp 1-13, 2008.
13. Hassim, S., Jaafar, M.S., Sazali, S.A.A.H., “The
Contractor Perception Towards Industrialised
Building System Risk in Construction Projects in
Malaysia”, American Journal of Applied Sciences,
vol. 6 (5), pp. 937-942, 2009.
14. Pan, W., Gibb, , F.A.G., Dainty, A.R.J., “Leading UK
Housebuilders' Utilization of Offsite Construction
Methods”, Building Research & Information, vol. 36
(1), pp. 56 - 67, 2008.
15. Pan, W., Gibb, A.G.F., Dainty, A.R.J., “Perspectives
of UK housebuilders on the use of offsite modern
methods of construction”, Construction
Management and Economics, vol. 25 (2), pp. 183-
194, 2007.
16. Rahman, A.B.A., Omar, W. “Issues and Challenge
in the Implementation of IBS in Malaysia”,
Proceeding of the 6th Asia Pacific Structural
Engineering and Construction Conference
(ASPEC), Kuala Lumpur, Malaysia, 5 & 6
september, 2006.
17. Sarja, A., “Open and Industrialised Building”,
International Council for Building Research, E&FN
Spoon, London, 1998.
18. Shaari, S. N., Ismail, E., “Promoting the Usage of
Industrialised Building System (IBS) and Modular
Coordination (MC) in Malaysia”, Construction
Industry in Engineers (Board of Engineer Malaysia),
March 2003.
19. Sumadi, S. R., “Promotion strategy and future
research and development on IBS”, National
Seminar on Industrialised Building System,
Construction Industry development Board (CIDB),
Kuala Lumpur, 2001 .
20. Thanoon, W.A., Peng, L.W., Kadir, M.R.A., Jaafar,
M.S., Salit, M.S., “The Essential Characteristics of
Industrialised Building System”, International
Conference on Industrialised Building Systems
Construction Industry Development Board (CIDB),
Kuala Lumpur, Malaysia, 10-11 september 2003.
21. Trikha, D.N., Ali A.A.A., “Industrialised Building
System (Fist ed.)”, Universiti Putra Malaysia Press,
Kuala Lumpur, 2004

More Related Content

What's hot

IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
Haziq1511
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3 Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3
Yee Len Wan
 
ibs 304
ibs 304ibs 304
Ct iii presentation
Ct iii presentationCt iii presentation
Ct iii presentation
Pui Chun Shian
 
Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)
Nekumi Kida
 
Modular construction for_low_cost_housing_in_india
Modular construction for_low_cost_housing_in_indiaModular construction for_low_cost_housing_in_india
Modular construction for_low_cost_housing_in_india
Nikhil Gadkar
 
Prefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed ImpetusPrefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed Impetus
IEI GSC
 
#6a modular construction (1)
#6a    modular construction (1)#6a    modular construction (1)
#6a modular construction (1)
Eveana Crystle
 
Modular construction
Modular constructionModular construction
Modular construction
DRM Investments LTD
 
PREFABRICATION AND MODULAR COORDINATION
PREFABRICATION AND MODULAR COORDINATIONPREFABRICATION AND MODULAR COORDINATION
PREFABRICATION AND MODULAR COORDINATION
sreestr18
 
Introduction of Prefabricated structures
Introduction  of Prefabricated structuresIntroduction  of Prefabricated structures
Introduction of Prefabricated structures
Yogi Yogesh
 
Prefabricated structure
Prefabricated structurePrefabricated structure
Prefabricated structure
Vishvendu pandey
 
A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES
VEMANA INSTITUTE OF TECHNOLOGY, VTU
 
Chap 2-literature-review (3)
Chap 2-literature-review (3)Chap 2-literature-review (3)
Chap 2-literature-review (3)
Jessyca Than
 
Building Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing ConstructionBuilding Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing Construction
jisunfoo
 
Seminar on modular building
Seminar on modular buildingSeminar on modular building
Seminar on modular building
UNIVERSAL ENGINEERING COLLEGE
 
modular construction
modular construction modular construction
modular construction
sandeeprao112
 
CREAM report
CREAM reportCREAM report
CREAM report
Zull-kefle Ismail
 
Modular construction
Modular constructionModular construction
Modular construction
Kiran Gill
 

What's hot (19)

IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3 Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3
 
ibs 304
ibs 304ibs 304
ibs 304
 
Ct iii presentation
Ct iii presentationCt iii presentation
Ct iii presentation
 
Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)
 
Modular construction for_low_cost_housing_in_india
Modular construction for_low_cost_housing_in_indiaModular construction for_low_cost_housing_in_india
Modular construction for_low_cost_housing_in_india
 
Prefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed ImpetusPrefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed Impetus
 
#6a modular construction (1)
#6a    modular construction (1)#6a    modular construction (1)
#6a modular construction (1)
 
Modular construction
Modular constructionModular construction
Modular construction
 
PREFABRICATION AND MODULAR COORDINATION
PREFABRICATION AND MODULAR COORDINATIONPREFABRICATION AND MODULAR COORDINATION
PREFABRICATION AND MODULAR COORDINATION
 
Introduction of Prefabricated structures
Introduction  of Prefabricated structuresIntroduction  of Prefabricated structures
Introduction of Prefabricated structures
 
Prefabricated structure
Prefabricated structurePrefabricated structure
Prefabricated structure
 
A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES
 
Chap 2-literature-review (3)
Chap 2-literature-review (3)Chap 2-literature-review (3)
Chap 2-literature-review (3)
 
Building Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing ConstructionBuilding Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing Construction
 
Seminar on modular building
Seminar on modular buildingSeminar on modular building
Seminar on modular building
 
modular construction
modular construction modular construction
modular construction
 
CREAM report
CREAM reportCREAM report
CREAM report
 
Modular construction
Modular constructionModular construction
Modular construction
 

Viewers also liked

Industrialised Building System report,
Industrialised Building System report, Industrialised Building System report,
Industrialised Building System report,
Eraz
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
Construction Tech. and Mgmt., VNIT Nagpur
 
Jim Stertz: Automation and Robotic Arm: Maximizing Throughput and Capacity
Jim Stertz: Automation and Robotic Arm: Maximizing Throughput and CapacityJim Stertz: Automation and Robotic Arm: Maximizing Throughput and Capacity
Jim Stertz: Automation and Robotic Arm: Maximizing Throughput and Capacity
360mnbsu
 
Konkrit siap tuang dan teknologi pasang siap
Konkrit siap tuang dan teknologi pasang siapKonkrit siap tuang dan teknologi pasang siap
Konkrit siap tuang dan teknologi pasang siap
Arduni Ahmad
 
Chapter 12 law and class robot
Chapter 12  law and class robotChapter 12  law and class robot
Chapter 12 law and class robot
Siti Sofia
 
review of soil mechanics
review of soil mechanicsreview of soil mechanics
review of soil mechanics
fayaz jatoi
 
Class 2 Grain Size Analysis ( Geotechnical Engineering )
Class 2   Grain Size Analysis ( Geotechnical Engineering )Class 2   Grain Size Analysis ( Geotechnical Engineering )
Class 2 Grain Size Analysis ( Geotechnical Engineering )
Hossam Shafiq I
 
Soil Compaction - Civil Engineering
Soil Compaction - Civil EngineeringSoil Compaction - Civil Engineering
Soil Compaction - Civil Engineering
Latif Hyder Wadho
 
Proktor compaction
Proktor compactionProktor compaction
Proktor compaction
Natalie Ulza
 
Proctor Compaction Test: A Basic Guide
Proctor Compaction Test: A Basic GuideProctor Compaction Test: A Basic Guide
Proctor Compaction Test: A Basic Guide
Catie Ewen
 
Class 1 Moisture Content - Specific Gravity ( Geotechnical Engineering )
Class 1  Moisture Content - Specific Gravity ( Geotechnical Engineering )Class 1  Moisture Content - Specific Gravity ( Geotechnical Engineering )
Class 1 Moisture Content - Specific Gravity ( Geotechnical Engineering )
Hossam Shafiq I
 
Class 3 (b) Soil Classification ( Geotechnical Engineering )
Class 3 (b)    Soil Classification ( Geotechnical Engineering )Class 3 (b)    Soil Classification ( Geotechnical Engineering )
Class 3 (b) Soil Classification ( Geotechnical Engineering )
Hossam Shafiq I
 
Class 4 Soil Compaction ( Geotechnical Engineering )
Class 4    Soil Compaction ( Geotechnical Engineering )Class 4    Soil Compaction ( Geotechnical Engineering )
Class 4 Soil Compaction ( Geotechnical Engineering )
Hossam Shafiq I
 
IBS Training
IBS TrainingIBS Training
IBS Training
Tempus Telcosys
 
Highway And traffic Engineering
Highway And traffic EngineeringHighway And traffic Engineering
Highway And traffic Engineering
Latif Hyder Wadho
 
Pestle analysis on malaysia
Pestle analysis on malaysiaPestle analysis on malaysia
Pestle analysis on malaysia
Alisa Buravytska
 
Robotic Process Automation: A Cohesive View
Robotic Process Automation: A Cohesive ViewRobotic Process Automation: A Cohesive View
Robotic Process Automation: A Cohesive View
Christopher Manfredi
 
IBS Presentation
IBS PresentationIBS Presentation
IBS Presentation
Pk Doctors
 

Viewers also liked (18)

Industrialised Building System report,
Industrialised Building System report, Industrialised Building System report,
Industrialised Building System report,
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
 
Jim Stertz: Automation and Robotic Arm: Maximizing Throughput and Capacity
Jim Stertz: Automation and Robotic Arm: Maximizing Throughput and CapacityJim Stertz: Automation and Robotic Arm: Maximizing Throughput and Capacity
Jim Stertz: Automation and Robotic Arm: Maximizing Throughput and Capacity
 
Konkrit siap tuang dan teknologi pasang siap
Konkrit siap tuang dan teknologi pasang siapKonkrit siap tuang dan teknologi pasang siap
Konkrit siap tuang dan teknologi pasang siap
 
Chapter 12 law and class robot
Chapter 12  law and class robotChapter 12  law and class robot
Chapter 12 law and class robot
 
review of soil mechanics
review of soil mechanicsreview of soil mechanics
review of soil mechanics
 
Class 2 Grain Size Analysis ( Geotechnical Engineering )
Class 2   Grain Size Analysis ( Geotechnical Engineering )Class 2   Grain Size Analysis ( Geotechnical Engineering )
Class 2 Grain Size Analysis ( Geotechnical Engineering )
 
Soil Compaction - Civil Engineering
Soil Compaction - Civil EngineeringSoil Compaction - Civil Engineering
Soil Compaction - Civil Engineering
 
Proktor compaction
Proktor compactionProktor compaction
Proktor compaction
 
Proctor Compaction Test: A Basic Guide
Proctor Compaction Test: A Basic GuideProctor Compaction Test: A Basic Guide
Proctor Compaction Test: A Basic Guide
 
Class 1 Moisture Content - Specific Gravity ( Geotechnical Engineering )
Class 1  Moisture Content - Specific Gravity ( Geotechnical Engineering )Class 1  Moisture Content - Specific Gravity ( Geotechnical Engineering )
Class 1 Moisture Content - Specific Gravity ( Geotechnical Engineering )
 
Class 3 (b) Soil Classification ( Geotechnical Engineering )
Class 3 (b)    Soil Classification ( Geotechnical Engineering )Class 3 (b)    Soil Classification ( Geotechnical Engineering )
Class 3 (b) Soil Classification ( Geotechnical Engineering )
 
Class 4 Soil Compaction ( Geotechnical Engineering )
Class 4    Soil Compaction ( Geotechnical Engineering )Class 4    Soil Compaction ( Geotechnical Engineering )
Class 4 Soil Compaction ( Geotechnical Engineering )
 
IBS Training
IBS TrainingIBS Training
IBS Training
 
Highway And traffic Engineering
Highway And traffic EngineeringHighway And traffic Engineering
Highway And traffic Engineering
 
Pestle analysis on malaysia
Pestle analysis on malaysiaPestle analysis on malaysia
Pestle analysis on malaysia
 
Robotic Process Automation: A Cohesive View
Robotic Process Automation: A Cohesive ViewRobotic Process Automation: A Cohesive View
Robotic Process Automation: A Cohesive View
 
IBS Presentation
IBS PresentationIBS Presentation
IBS Presentation
 

Similar to MS Ibs in malaysia

Industrialised Building System in Malaysia.pdf
Industrialised Building System in Malaysia.pdfIndustrialised Building System in Malaysia.pdf
Industrialised Building System in Malaysia.pdf
KamalGhazali2
 
230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt
Mohd Zulhairi Mohd Noor
 
IBS Roadmap.pdf
IBS Roadmap.pdfIBS Roadmap.pdf
IBS Roadmap.pdf
Azhari Puteh
 
Mivan Formwork in Construction
Mivan Formwork in ConstructionMivan Formwork in Construction
Mivan Formwork in Construction
IRJET Journal
 
Building Technology Project 1
Building Technology Project 1Building Technology Project 1
Building Technology Project 1
zerospaces_
 
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET Journal
 
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET Journal
 
Modular Coordination in buildings and construction.pptx
Modular Coordination in buildings and construction.pptxModular Coordination in buildings and construction.pptx
Modular Coordination in buildings and construction.pptx
AtulBhagwat6
 
Btech report
Btech reportBtech report
Btech report
Chong Chin Pin
 
Building Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyBuilding Technology : Industrialize Building Technology
Building Technology : Industrialize Building Technology
Quinn Liew
 
Building Technology Project 1 Report
Building Technology Project 1 ReportBuilding Technology Project 1 Report
Building Technology Project 1 Report
Bolin Loong
 
ace cover pg 2829
ace cover pg  2829ace cover pg  2829
ace cover pg 2829
Jayanta Chakraborty
 
Building Technology PJT 1 Report
Building Technology PJT 1 Report Building Technology PJT 1 Report
Building Technology PJT 1 Report
ForestedTiger
 
Prefabrication structures in construction
Prefabrication structures in constructionPrefabrication structures in construction
Prefabrication structures in construction
RajalekshmiSivaram
 
Btech i compressed
Btech i compressedBtech i compressed
Btech i compressed
Weng Chuan
 
Off-site and on -site modern method of construction
Off-site and on -site modern method of constructionOff-site and on -site modern method of construction
Off-site and on -site modern method of construction
ANNA REBECCA PRASAD
 
Project Management Individual Assignment
Project Management Individual AssignmentProject Management Individual Assignment
Project Management Individual Assignment
Arissa Loh
 
SHD Individual Report
SHD Individual ReportSHD Individual Report
SHD Individual Report
Kellyann Hiew
 
IBS group 5 material assignment.pptx
IBS group 5 material assignment.pptxIBS group 5 material assignment.pptx
IBS group 5 material assignment.pptx
AndualemDamtew
 
Modular buildings in_modern_construction
Modular buildings in_modern_constructionModular buildings in_modern_construction
Modular buildings in_modern_construction
ANTONYYONIANCCOHUACC
 

Similar to MS Ibs in malaysia (20)

Industrialised Building System in Malaysia.pdf
Industrialised Building System in Malaysia.pdfIndustrialised Building System in Malaysia.pdf
Industrialised Building System in Malaysia.pdf
 
230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt
 
IBS Roadmap.pdf
IBS Roadmap.pdfIBS Roadmap.pdf
IBS Roadmap.pdf
 
Mivan Formwork in Construction
Mivan Formwork in ConstructionMivan Formwork in Construction
Mivan Formwork in Construction
 
Building Technology Project 1
Building Technology Project 1Building Technology Project 1
Building Technology Project 1
 
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
 
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
 
Modular Coordination in buildings and construction.pptx
Modular Coordination in buildings and construction.pptxModular Coordination in buildings and construction.pptx
Modular Coordination in buildings and construction.pptx
 
Btech report
Btech reportBtech report
Btech report
 
Building Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyBuilding Technology : Industrialize Building Technology
Building Technology : Industrialize Building Technology
 
Building Technology Project 1 Report
Building Technology Project 1 ReportBuilding Technology Project 1 Report
Building Technology Project 1 Report
 
ace cover pg 2829
ace cover pg  2829ace cover pg  2829
ace cover pg 2829
 
Building Technology PJT 1 Report
Building Technology PJT 1 Report Building Technology PJT 1 Report
Building Technology PJT 1 Report
 
Prefabrication structures in construction
Prefabrication structures in constructionPrefabrication structures in construction
Prefabrication structures in construction
 
Btech i compressed
Btech i compressedBtech i compressed
Btech i compressed
 
Off-site and on -site modern method of construction
Off-site and on -site modern method of constructionOff-site and on -site modern method of construction
Off-site and on -site modern method of construction
 
Project Management Individual Assignment
Project Management Individual AssignmentProject Management Individual Assignment
Project Management Individual Assignment
 
SHD Individual Report
SHD Individual ReportSHD Individual Report
SHD Individual Report
 
IBS group 5 material assignment.pptx
IBS group 5 material assignment.pptxIBS group 5 material assignment.pptx
IBS group 5 material assignment.pptx
 
Modular buildings in_modern_construction
Modular buildings in_modern_constructionModular buildings in_modern_construction
Modular buildings in_modern_construction
 

More from Est

SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017
Est
 
Sabd undergraduate pg draft v3
Sabd undergraduate pg draft   v3Sabd undergraduate pg draft   v3
Sabd undergraduate pg draft v3
Est
 
BS 2 Fire protection 4
BS 2 Fire protection 4BS 2 Fire protection 4
BS 2 Fire protection 4
Est
 
CSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscmCSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscm
Est
 
CSCM Partnering
CSCM PartneringCSCM Partnering
CSCM Partnering
Est
 
CSCM Communication in construction
CSCM Communication in constructionCSCM Communication in construction
CSCM Communication in construction
Est
 
CSCM Material delivery problems cscm
CSCM Material delivery problems cscmCSCM Material delivery problems cscm
CSCM Material delivery problems cscm
Est
 
BS 2 Escalators arrangement
BS 2 Escalators arrangementBS 2 Escalators arrangement
BS 2 Escalators arrangement
Est
 
BS 2 Escalators 1of 2
BS 2 Escalators 1of 2BS 2 Escalators 1of 2
BS 2 Escalators 1of 2
Est
 
BS 2 Group assignment brief question august 2016
BS 2 Group assignment brief  question august 2016BS 2 Group assignment brief  question august 2016
BS 2 Group assignment brief question august 2016
Est
 
BS 2 Variable air volume systems
BS 2 Variable air volume systemsBS 2 Variable air volume systems
BS 2 Variable air volume systems
Est
 
CSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscmCSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscm
Est
 
CSCM Bim group assignment.docx
CSCM Bim group assignment.docxCSCM Bim group assignment.docx
CSCM Bim group assignment.docx
Est
 
CSCM individual assignment
CSCM individual assignmentCSCM individual assignment
CSCM individual assignment
Est
 
Management science group assignment MS
Management science group assignment MSManagement science group assignment MS
Management science group assignment MS
Est
 
MS Tutorial 12 hrm
MS Tutorial 12 hrmMS Tutorial 12 hrm
MS Tutorial 12 hrm
Est
 
MS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerbergMS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerberg
Est
 
MS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivationMS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivation
Est
 
MS Lecture 8 communication
MS Lecture 8 communicationMS Lecture 8 communication
MS Lecture 8 communication
Est
 
MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016
Est
 

More from Est (20)

SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017
 
Sabd undergraduate pg draft v3
Sabd undergraduate pg draft   v3Sabd undergraduate pg draft   v3
Sabd undergraduate pg draft v3
 
BS 2 Fire protection 4
BS 2 Fire protection 4BS 2 Fire protection 4
BS 2 Fire protection 4
 
CSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscmCSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscm
 
CSCM Partnering
CSCM PartneringCSCM Partnering
CSCM Partnering
 
CSCM Communication in construction
CSCM Communication in constructionCSCM Communication in construction
CSCM Communication in construction
 
CSCM Material delivery problems cscm
CSCM Material delivery problems cscmCSCM Material delivery problems cscm
CSCM Material delivery problems cscm
 
BS 2 Escalators arrangement
BS 2 Escalators arrangementBS 2 Escalators arrangement
BS 2 Escalators arrangement
 
BS 2 Escalators 1of 2
BS 2 Escalators 1of 2BS 2 Escalators 1of 2
BS 2 Escalators 1of 2
 
BS 2 Group assignment brief question august 2016
BS 2 Group assignment brief  question august 2016BS 2 Group assignment brief  question august 2016
BS 2 Group assignment brief question august 2016
 
BS 2 Variable air volume systems
BS 2 Variable air volume systemsBS 2 Variable air volume systems
BS 2 Variable air volume systems
 
CSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscmCSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscm
 
CSCM Bim group assignment.docx
CSCM Bim group assignment.docxCSCM Bim group assignment.docx
CSCM Bim group assignment.docx
 
CSCM individual assignment
CSCM individual assignmentCSCM individual assignment
CSCM individual assignment
 
Management science group assignment MS
Management science group assignment MSManagement science group assignment MS
Management science group assignment MS
 
MS Tutorial 12 hrm
MS Tutorial 12 hrmMS Tutorial 12 hrm
MS Tutorial 12 hrm
 
MS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerbergMS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerberg
 
MS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivationMS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivation
 
MS Lecture 8 communication
MS Lecture 8 communicationMS Lecture 8 communication
MS Lecture 8 communication
 
MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016
 

Recently uploaded

Challenges of Nation Building-1.pptx with more important
Challenges of Nation Building-1.pptx with more importantChallenges of Nation Building-1.pptx with more important
Challenges of Nation Building-1.pptx with more important
Sm321
 
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
hyfjgavov
 
The Ipsos - AI - Monitor 2024 Report.pdf
The  Ipsos - AI - Monitor 2024 Report.pdfThe  Ipsos - AI - Monitor 2024 Report.pdf
The Ipsos - AI - Monitor 2024 Report.pdf
Social Samosa
 
Build applications with generative AI on Google Cloud
Build applications with generative AI on Google CloudBuild applications with generative AI on Google Cloud
Build applications with generative AI on Google Cloud
Márton Kodok
 
一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理
一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理
一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理
xclpvhuk
 
原版一比一利兹贝克特大学毕业证(LeedsBeckett毕业证书)如何办理
原版一比一利兹贝克特大学毕业证(LeedsBeckett毕业证书)如何办理原版一比一利兹贝克特大学毕业证(LeedsBeckett毕业证书)如何办理
原版一比一利兹贝克特大学毕业证(LeedsBeckett毕业证书)如何办理
wyddcwye1
 
Open Source Contributions to Postgres: The Basics POSETTE 2024
Open Source Contributions to Postgres: The Basics POSETTE 2024Open Source Contributions to Postgres: The Basics POSETTE 2024
Open Source Contributions to Postgres: The Basics POSETTE 2024
ElizabethGarrettChri
 
4th Modern Marketing Reckoner by MMA Global India & Group M: 60+ experts on W...
4th Modern Marketing Reckoner by MMA Global India & Group M: 60+ experts on W...4th Modern Marketing Reckoner by MMA Global India & Group M: 60+ experts on W...
4th Modern Marketing Reckoner by MMA Global India & Group M: 60+ experts on W...
Social Samosa
 
Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...
Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...
Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...
Kaxil Naik
 
ViewShift: Hassle-free Dynamic Policy Enforcement for Every Data Lake
ViewShift: Hassle-free Dynamic Policy Enforcement for Every Data LakeViewShift: Hassle-free Dynamic Policy Enforcement for Every Data Lake
ViewShift: Hassle-free Dynamic Policy Enforcement for Every Data Lake
Walaa Eldin Moustafa
 
一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
aqzctr7x
 
一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
bmucuha
 
writing report business partner b1+ .pdf
writing report business partner b1+ .pdfwriting report business partner b1+ .pdf
writing report business partner b1+ .pdf
VyNguyen709676
 
Module 1 ppt BIG DATA ANALYTICS_NOTES FOR MCA
Module 1 ppt BIG DATA ANALYTICS_NOTES FOR MCAModule 1 ppt BIG DATA ANALYTICS_NOTES FOR MCA
Module 1 ppt BIG DATA ANALYTICS_NOTES FOR MCA
yuvarajkumar334
 
"Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens"
"Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens""Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens"
"Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens"
sameer shah
 
Predictably Improve Your B2B Tech Company's Performance by Leveraging Data
Predictably Improve Your B2B Tech Company's Performance by Leveraging DataPredictably Improve Your B2B Tech Company's Performance by Leveraging Data
Predictably Improve Your B2B Tech Company's Performance by Leveraging Data
Kiwi Creative
 
DSSML24_tspann_CodelessGenerativeAIPipelines
DSSML24_tspann_CodelessGenerativeAIPipelinesDSSML24_tspann_CodelessGenerativeAIPipelines
DSSML24_tspann_CodelessGenerativeAIPipelines
Timothy Spann
 
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
mkkikqvo
 
University of New South Wales degree offer diploma Transcript
University of New South Wales degree offer diploma TranscriptUniversity of New South Wales degree offer diploma Transcript
University of New South Wales degree offer diploma Transcript
soxrziqu
 
A presentation that explain the Power BI Licensing
A presentation that explain the Power BI LicensingA presentation that explain the Power BI Licensing
A presentation that explain the Power BI Licensing
AlessioFois2
 

Recently uploaded (20)

Challenges of Nation Building-1.pptx with more important
Challenges of Nation Building-1.pptx with more importantChallenges of Nation Building-1.pptx with more important
Challenges of Nation Building-1.pptx with more important
 
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
 
The Ipsos - AI - Monitor 2024 Report.pdf
The  Ipsos - AI - Monitor 2024 Report.pdfThe  Ipsos - AI - Monitor 2024 Report.pdf
The Ipsos - AI - Monitor 2024 Report.pdf
 
Build applications with generative AI on Google Cloud
Build applications with generative AI on Google CloudBuild applications with generative AI on Google Cloud
Build applications with generative AI on Google Cloud
 
一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理
一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理
一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理
 
原版一比一利兹贝克特大学毕业证(LeedsBeckett毕业证书)如何办理
原版一比一利兹贝克特大学毕业证(LeedsBeckett毕业证书)如何办理原版一比一利兹贝克特大学毕业证(LeedsBeckett毕业证书)如何办理
原版一比一利兹贝克特大学毕业证(LeedsBeckett毕业证书)如何办理
 
Open Source Contributions to Postgres: The Basics POSETTE 2024
Open Source Contributions to Postgres: The Basics POSETTE 2024Open Source Contributions to Postgres: The Basics POSETTE 2024
Open Source Contributions to Postgres: The Basics POSETTE 2024
 
4th Modern Marketing Reckoner by MMA Global India & Group M: 60+ experts on W...
4th Modern Marketing Reckoner by MMA Global India & Group M: 60+ experts on W...4th Modern Marketing Reckoner by MMA Global India & Group M: 60+ experts on W...
4th Modern Marketing Reckoner by MMA Global India & Group M: 60+ experts on W...
 
Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...
Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...
Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...
 
ViewShift: Hassle-free Dynamic Policy Enforcement for Every Data Lake
ViewShift: Hassle-free Dynamic Policy Enforcement for Every Data LakeViewShift: Hassle-free Dynamic Policy Enforcement for Every Data Lake
ViewShift: Hassle-free Dynamic Policy Enforcement for Every Data Lake
 
一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
 
一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
 
writing report business partner b1+ .pdf
writing report business partner b1+ .pdfwriting report business partner b1+ .pdf
writing report business partner b1+ .pdf
 
Module 1 ppt BIG DATA ANALYTICS_NOTES FOR MCA
Module 1 ppt BIG DATA ANALYTICS_NOTES FOR MCAModule 1 ppt BIG DATA ANALYTICS_NOTES FOR MCA
Module 1 ppt BIG DATA ANALYTICS_NOTES FOR MCA
 
"Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens"
"Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens""Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens"
"Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens"
 
Predictably Improve Your B2B Tech Company's Performance by Leveraging Data
Predictably Improve Your B2B Tech Company's Performance by Leveraging DataPredictably Improve Your B2B Tech Company's Performance by Leveraging Data
Predictably Improve Your B2B Tech Company's Performance by Leveraging Data
 
DSSML24_tspann_CodelessGenerativeAIPipelines
DSSML24_tspann_CodelessGenerativeAIPipelinesDSSML24_tspann_CodelessGenerativeAIPipelines
DSSML24_tspann_CodelessGenerativeAIPipelines
 
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
 
University of New South Wales degree offer diploma Transcript
University of New South Wales degree offer diploma TranscriptUniversity of New South Wales degree offer diploma Transcript
University of New South Wales degree offer diploma Transcript
 
A presentation that explain the Power BI Licensing
A presentation that explain the Power BI LicensingA presentation that explain the Power BI Licensing
A presentation that explain the Power BI Licensing
 

MS Ibs in malaysia

  • 1. The adoption of Industrialised Building System (IBS) construction in Malaysia: The history, policies, experiences and lesson learned Mohd Idrus Din, Noraini Bahri, Mohd Azmi Dzulkifly, Mohd Rizal Norman, Kamarul Anuar Mohamad Kamar *, and Zuhairi Abd Hamid Construction Industry Development Board (CIDB) Malaysia * Corresponding author (kamarul2411@gmail.com) Purpose Industry and government in Malaysia coined the term industrialised building system (IBS) to describe the adoption of construction industrialisation, mechanisation, and the use of prefabrication of components in building construction. IBS consists of precast component systems, fabricated steel structures, innovative mould systems, modular block systems, and prefabricated timber structures as construction components. Parts of the building that are repetitive but difficult – and too time consuming and labour intensive to be casted onsite – are designed and detailed as standardised components at the factory and are then brought to the site to be assembled. The construction industry in Malaysia has started to embrace IBS as a method of attaining better construction quality and productivity, reducing risks related to occupational safety and health, alleviating issues for skilled workers and dependency on manual foreign labour, and achieving the ultimate goal of reducing the overall cost of construction. The chronology of IBS-adoption in Malaysia goes back a long way, reaching back to the 1960s, when precast elements were adopted in the building industry to address the problem of an acute housing shortage. However, the introduction of IBS was never sustained beyond this period. As a result of the failure of early closed-fabricated systems, the industry is now avoiding changing its construction method to IBS. Some of the foreign systems that were introduced during the late 1960s and 1970s were also found to be unsuitable in Malaysia’s climate and not very compatible with social practices. IBS has regained its popularity presently due to problems with construction workforces where the industry has been relying for a long time on unskilled workers from neighbouring countries. Method In 1999, the IBS Strategic Plan was launched to promote the system’s usage in the industry. This was followed by the IBS Roadmap 2003-2010 and IBS Roadmap 2011-2015; these are blueprints for industrialised construction by 2015. The roadmaps have been developed by the government to chart progress and guide the awareness programmes, incentives, vendor scheme development, training, quality control and research and development programmes. The government also took the lead in 2008, by mandating that all public-sector projects must attain no less than 70% IBS-content under the Treasury Circular SPP 07/2008. This policy aims to build up momentum and to establish demand for IBScomponents, thus bringing the cost down. Results & Discussion At present, IBS-construction is widely used as a mainstream method and the implementation has moved from prefabrication towards mechanisation, automation, and robotics applications. This paper highlights some of the history, policies, experiences, and lesson learned in adopting IBS in Malaysia. The outlook for IBS-implementation in Malaysia is bright, but much work is still needed from the government to convince the contractors, manufacturers, and suppliers to adopt IBS-construction. Keywords: construction, industrialized building systems, Malaysia INTRODUCTION Industrialised Building System (IBS) is the term coined by the industry and government in Malaysia to represent the adoption of construction industrialisation and the use of prefabrication of components in building construction. IBS is defined as a construction technique in which components are manufactured in a controlled environment (on or off site), transported, positioned and assembled into a structure with minimal additional site work (Hamid et al., 2008; CIDB, 2007; CIDB, 2005 and CIDB, 2003). It consists of precast component systems, fabricated steel structures, innovative mould systems, modular block systems and prefabricated timber structures as construction components (CIDB, 2003). Parts of the building that are repetitive but difficult – and too time consuming and labour intensive to be casted onsite – are designed and detailed as standardised components at the factory and are then brought to the site to be assembled (CIDB, 2003). The onsite casting activities in IBS utilise innovative and clean mould technologies (CIDB, 2007; CIDB, 2005 and CIDB, 2003). In the Malaysian context, the classification by the CIDB is widely used and well understood by scholars and practitioners. CIDB has classified the IBS systems into five categories as depicted in Table 1 (CIDB, 2003).
  • 2. Table 1: IBS classification (CIDB, 2003) Classification Descriptions Precast concrete framed buildings The most common group of IBS products is the precast concrete elements; precast concrete columns, beams, slabs, walls, 3-D components (e.g. balconies, staircases, toilets, lift chambers, refuse chambers), lightweight precast concrete, as well as permanent concrete formworks. Formwork System Considered as one of the low-level or the least prefabricated IBS, as the system generally involves site casting and is therefore subject to structural quality control, the products offer high-quality finishes, and fast construction with less site labour and material requirement. Steel Framing System Commonly used with precast concrete slabs, steel columns and beams, steel framing systems have always been the popular choice and used extensively in the fast-track construction of skyscrapers. Recent developments in this type of IBS include the increased usage of light steel trusses consisting of cost-effective profiled cold-formed channels and steel portal frame systems as alternatives to the heavier traditional hot- rolled sections. Prefabricated Timber Framing System The system consists of timber building frames and timber roof trusses. While the latter are more popular, timber building frame systems also have their own niche market, offering interesting designs from simple dwelling units to buildings requiring high aesthetical values such as chalets for resorts. Blockwork System The construction method of using conventional bricks has been revolutionised by the development and usage of interlocking concrete masonry units (CMU) and lightweight concrete blocks. The tedious and time-consuming traditional brick-laying tasks are greatly simplified by the usage of these effective alternative solutions. The construction industry has started to embrace IBS as a method of attaining better construction quality and productivity, reducing risks related to occupational safety and health, alleviating issues for skilled workers and dependency on manual foreign labour, and achieving the ultimate goal of reducing the overall cost of construction. Apart from this, it offers minimal wastage, fewer site materials, a cleaner and neater environment, controlled quality, and lower total construction costs (Pan et al. 2008, Hamid et al. 2008 and Pan et al. 2007). Already utilized in Malaysia since 1960s, IBS is the way forward for the industry stakeholders to make leaps and bounds progress in the Malaysian construction industry. Sufficient exposure and incentives are pouring in to encourage industry players to make a paradigm move – from conventional to IBS construction. THE CHRONOLOGY OF IBS ADOPTION IN MALAYSIA 1. Development of IBS in post-independent Malaysia: IBS has been introduced in Malaysia since early 1960s when Public Work Department (PWD) and Ministry of Housing and Local Government (MHLG) of Malaysia visited several European countries and evaluate their housing development program (Thanoon et al. 2003). In 1963, the government sent a group of architect from PWD to learn industrialised building in some of European countries. The following year, another group of architect from the Federal Capital Commission was sent to France for about 6 month for exposure in industrialised buildings (Sumadi et al. 2001). In the same year, Ministry of Housing and Local Government (MHLG) was being set up by the government to concentrate to development of housing. The ministry officers and representatives visited West Germany, Denmark and France to gather more information on industrialised building later that year (Sumadi et al. 2001). 2. Development in 1964 to 1970s: After their successful visit in 1964, the government had started its first IBS project aims to speed up the delivery time and built affordable and quality houses as stipulated under the 2nd Malayan Plan 1960-1965 and the 1st Malaysian Plan 1966 – 1970. About 22.7 acres of land along Jalan Pekeliling, Kuala Lumpur was dedicated to the project comprising 7 blocks of 17 stories flat consists of 3000 units of low-cost flat and 40 shops lot. This project was awarded to JV Gammon and Larsen and Nielsen using Danish System of large panel pre-cast concrete wall and plank slabs. The project was completed within 27 months from 1966 to 1968 including the time taken in the construction of the RM 2.5 million casting yard at Jalan Damansara. In 1965, the second housing project initiated by the government comprising 6 blocks of 17 stories flats and 3 block of 18 stories flats at Jalan Rifle Range, Penang. The project was awarded to Hochtief and Chee Seng using French
  • 3. Estoit System (CIDB, 2006 and CIDB, 2003). Both projects utilised the large panel system which required large concrete panel cast in the factory and transported to site on trailers for assembly. The speed of construction is much faster although the tendered price was slightly higher by 5% to 8% (Sarja, 1998). Another earliest IBS project was at Taman Tun Sardon in Penang (consists of 1,000 units five-storey walk up flat). IBS pre-cast component and system in the project was designed by British Research Establishment (BRE) for low cost housing (BRECAST system). A similar system was constructed almost at the same time at Edmonton, North London and about 20,000 BRECAST dwellings were constructed throughout UK from 1964 to 1974 (CIDB, 2006). Nonetheless, the building design was very basic and not considering the aspect of serviceability such as the local needs to have wet toilet and bathroom (Rahman and Omar, 2006). 3. Development in 1970s to early 1980s: In 1978, the Penang State Government launched another 1200 units of housing using prefabrication technology. Two years later, the Ministry of Defense (MOD) adopted large prefabricated panel construction system to build 2800 unit of living quarters at Lumut Naval Base. As one can observed, IBS was engage at first place in the construction of low-cost high-rise residential building to overcome the increasing demand for housing needs. Many construction in at this time utilised precast wall panel system. Nonetheless, the industrialisation of construction was never sustained in this period. Failure of early closed fabricated systems had resultant the industry to avoid of changing their construction method to IBS. Some of the foreign systems that were introduced during the late 60s and 70s were also found not to be suitable with Malaysia climate and social practices. Newer and better technologies were constantly being introduced than in the market since wet joint systems were identified to be more suitable to be used in our tropical climate and it was also better to utilised the bathroom types which were relatively wetter than those in the Europe (CIDB, 2005). At the same time recent innovation the form of precast concrete sandwich wall panels developed in Europe, has received wide acceptability in countries having hot temperature climates due to better insulating properties resulting in a cooler in door environment and has been send in several pilot projects in Malaysia through 1970s to 1980s period (Trikha and Ali, 2004). 4. Development in 1980s to 1990s: During the period of early 80s up to 90s the use of structural steel components took place particularly in high rise buildings in Kuala Lumpur. The usage of steel structure gained much attention with the construction of 36-storey Dayabumi complex that was completed in 1984 by Takenaka Corporation of Japan (CIDB, 2003 and CIDB, 2006). In the 90s, demand for the new township has seen the increase in the use of precast concrete system in residential buildings. Between 1981 and 1993, Perbadanan Kemajuan Negeri Selangor (PKNS) a state government development agency acquired pre-cast concrete technology from Praton Haus International based on Germany to build low cost houses and high cost bungalows for the new townships in Selangor (CIDB, 2003 and Hassim et al. 2009). It was recorded then, around 52,000 housing units was constructed using Praton Haus system (Trikha and Ali, 2004) and the state of art pre-cast factory was set up in Shah Alam (Sarja, 1998). Other than the use of Praton House technology from Germany, PKNS was also embarked in other IBS systems at the same period; Taisei Marubumi - large panel are cast in factory using tilt-up system where one panel forms the base for next panel cast (1,237 housing units and 11 shop lots at PJS), Hazama system (3,222 flat units and 1,112 housing units at Bandar Baru Bangi), Ingeback system which is Swedish system using large panels in vertical battery mould and tilt-up table mould (3,694 flat units) All the project were constructed by local contractor with international technical support from established international firms in joint venture partnership (Hashim et al. 2009 and Sarja, 1998).In that period IBS used in Malaysia are large panel system (housing project in Shah Alam and Taman Brown), metal form system in Wangsa Maju, Pandan Jaya and Taman Maluri and modular systems which are heavily promoted by CIDB in government project. Although the system originated overseas, local contractors has made modification to suit local requirement. Instead of steel, high quality film coated plywood shuttering is used in an innovative mould system. The form can be easily dismantled and handled by small crane and can be adjusted to suit architectural requirement (Sarja, 1998). Other systems are framing system, modular system and partially pre-cast system (the Cemlock Built System which is originate in Australia and used by the National Housing Department in Pekan Selama housing project) (Sarja, 1998). 5. Development in 1990s to 1998s In this booming period of Malaysian construction 1994 -1997, hybrid IBS application used in many national iconic landmarks such as Kuala Lumpur Convention Centre (steel beam and roof trusses and precast concrete slab: Victor Buyck Steel Construction), Lightweight Railway Train (LRT), KL Sentral Station (steel roof structure and precast hollow core: RSPA – Bovis), KL Tower (steel beams
  • 4. and columns for tower head: Wayss and Freytag), Kuala Lumpur International Airport (steel roof structure: KLIAB – Eversendai) and Petronas Twin Towers (steel beams and steel decking for the floor system – Mayjus JV and SKJ JV). The booming period of construction during that time includes the development and construction of new administration capital of Malaysia; Putrajaya and Cyberjaya. Both cities are the massive development areas consist of new government buildings, business boulevard and residential area, and most of them were built in IBS or a hybrid IBS, combination between IBS and conventional construction. 6. Development in 1998 – 2008 At this state, the use of IBS as a method of construction in Malaysia is evolving. Many private companies in Malaysia have teamed up with foreign expert to offer solutions to their IBS projects (Eastern Pretech, BPB Malaysian Gypsum, Lafarge and Duralite). Many had acquired enough knowledge through technology transfer to build up own capacity in IBS technologies (PKNS Engineering, Setia Precast and Global Globe). Setia Precast and Global Globe using technologies first adopted by Taisei Corporation of Japan. In fact, Malaysian was also developed their own IBS technologies (Zenbes, CSR, IJM Formwork, Pryda, Baktian and HC Precast). The local IBS manufacturers are mushrooming, although the facilities yet to operate in full capacity. The IBS system is largely used for private residential projects in Shah Alam, Wangsa Maju and Pandan, Dua Residency, Taman Mount Austin and Tongkang Pecah, Johor. It used in public residential projects in Putrajaya Prescient 17 and Prescient 9, PPR Sungai Besi, Sungai Bedaun, and Telipok, Sabah. The new generation of building that utilised IBS is better in term of quality, and architectural appearance compared to the earlier generation. IBS is also widely used to construct government’s schools and teachers housing complexes (Kuala Kangsar, Yan and Sungai Petani), hospitals (Serdang Hospital and UKM Hospital), collages and universities (Penang Matriculation Collage, UiTM, Kuching and University PETRONAS and University of Malaysia Sabah), custom and immigration complexes (Kelana Jaya and Johor Bahru), private buildings (Weld Tower, Maju Perdana, Traders Hotel, City Square and Olympia Tower, Jaya Jusco, IKEA) and police quarters (Senawang). The IBS agenda was further boosted with the 2004, 2005 and 2006 Malaysia Budget announcements. In 2004, new government building projects had been strongly encouraged to have at least 50% of IBS content in their construction elements which had been calculated using IBS Score Manual developed by CIDB. Furthermore, in 2005, the government had pledged to construct 100,000 units of affordable houses using IBS (Hamid et al. 2008). Finally, in 2006, a tax incentive was offered through Acceleration Capital Allowance (ACA). IBS manufacturers would be given ACA for expenses incurred in the purchase of steel moulds used for production of precast concrete components to be claimed within three years (CIDB, 2005 and Shaari, 2006). 7. 2008 – Present One of the most important milestones of IBS policy is regulation on the use of IBS in the construction of public buildings. In November 2008, the Treasury Malaysia issued a Treasury Circular Letter, now referred to as SPP 7/2008, to all Malaysian government agencies directing them to increase the IBS contents of their building development projects to a level not less than 70 points of the IBS score and in that sense IBS must be incorporated as part of the contract document for tender (Hamid et al. 2008). The circular letter took effect immediately and the Implementation and Coordination Unit (ICU) of the Prime Minister’s Department has been given the task of monitoring the level of compliance to this directive by the respective agencies. The decision was to create sufficient momentum for the demand for IBS components and to create a spill-out effect throughout the nation. To monitor the implementation, the government established the National IBS Secretariat. It involves coordination between inter-ministry levels to make sure the policy is successfully implemented. During a period from October 2008 and May 2010, about 331 projects under 17 ministries were awarded and constructed using IBS (CIDB, 2010). The majority of the projects were construction of public schools, hospitals, higher learning institutions and government offices throughout Malaysia. The total cost of the projects was about RM 9.6 billion (CIDB, 2010). EXPERIENCES AND LESSONS LEARNED ON IBS CONSTRUCTION IN MALAYSIA 1. There is a change in paradigm regarding IBS in Malaysia in the past few years. In the past, the majority of contractors and industry stakeholders still divided either to use IBS or conventional method although the benefits of IBS are clear and eminent. But this is not the case now, the industry, nowadays has to think of a system to be implemented in their project (weather it conventional or IBS) due to the increase need of quality end-product and speed of construction, and coping with the issue of foreign workers. In the case of public building projects, the industry is instructed to use IBS system. So, the industry both in the private and public construction projects has no other choice but to be involved in IBS and adopt industrialisation in construction. (In November 2008, the Treasury Malaysia issued a
  • 5. Treasury Circular Letter, now referred to as SPP 7/2008, to all Malaysian government agencies directing them to increase the IBS contents of their building development projects to a level not less than 70 points of the IBS score and IBS must be incorporated as part of the contract document for tender. The decision was to create sufficient momentum for the demand for IBS components and to create a spill-out effect throughout the nation). Due to this policy, the cost of constructing in IBS has reduced significantly. The adoption in the past was normally based on wanting rather than by viability. IBS system in Malaysia is now, mostly competitive if not cheaper if one compare it to the conventional practices depending on type of projects, type of systems and volume. 2. The IBS in Malaysia promotes open system or hybrid system and encourages full industry participation compared to the prefab closed system where only limited industry companies can participate. IBS supply chain should comprises of modular component-based products that can be produce and interchangeable between any project thus promote mass customisation at the customers end. Therefore, a company that can utilize the IBS supply chain will enable it to sell systems rather than selling single products. Standardising the construction industry is a critical factor in establishing an Open System in Malaysia. The concept of the OBS is similar to what has happened in the ICT industry whereby through standardization of jointing parts such as USB ports, consumers can buy computer equipment such as mouse or scanner anywhere in the world. The equipment can then be easily installed by the users as the connection from the equipment to the computer has been internationally standardized. 3. One of the important milestones in IBS Roadmap 2003-2010 was the introduction of Modular Coordination (MC). MC is a concept of coordination of dimensions and space where buildings and components are dimensioned and positioned in a basic unit or module known as 1M which is equivalent to 100 mm, as stipulated in MS 1064, and developed in 2000. The concept allows standardisation in design and building components. It encourages participation from manufactures and assemblers to enter the market, thus reducing the price of IBS components. Modular need to be adopted to cut down the waste in IBS. However the implementation of modular coordination requires better design planning. 4. Malaysian construction industry is very good in modifying and adopting IBS technologies captured from oversea practices. Many private companies in Malaysia in present day have teamed up with foreign expert to offer solutions to their IBS projects. Many had acquired enough knowledge through technology transfer to build up own capacity in IBS technologies. Many world-class Malaysian developers have chosen IBS over the conventional methods for important projects such as the Petronas Twin Towers, Putrajaya, KL Sentral and KLIA. There is ample evidence that the failures of past construction systems are due to blind acceptance of foreign products that were not open (flexible) and were unsuitable to our climate and culture. 5. Successful IBS contractors as observed are not a user of technology or limit its role as project manager and assembler. Most successful IBS contractors have an in-house manufacturing and design capacity. They also invest in and sometimes invent systems, and so do not just depend on existing manufacturers. The also partner with oversea partners to acquire the technologies. 6. One of the major issues of IBS is on changing users’ perception. Users tend to think that IBS buildings is easy to leak and can not be renovated. However, through the advancement of technologies and better planning and design, IBS buildings/housings in the present days have improved in term of performance and can be renovated by users. 7. Some of the foreign systems that were introduced during the late 60s and 70s were also found not to be suitable with Malaysia climate and social practices. Newer and better technologies were constantly being introduced than in the market since wet joint systems were identified to be more suitable to be used in our tropical climate and it was also better to utilised the bathroom types which were relatively wetter than those in the Europe. 8. IBS in Malaysia is seen as a threat to traditional methods but in reality many IBS technologies like block works is exist together with conventional practices. The failure of IBS to penetrate the market is due to a misconception that it will eventually replace the traditional sector, while it actually should work closely in tandem to promote best practice in construction. The sharing of best practice between the two approaches is essential for the continued successful development of both construction sectors. IBS should be looked by the industry as easy, simple and cost effective solutions to the players. 9. Each IBS system has its own advantages and limitations. The selection and implementation of correct technology in IBS projects is perhaps the key to IBS success. There is a need to realise that precast concrete IBS is not suitable for every project. If more people were aware of its capabilities and available technology, they could identify particular system that suited the project. The advantages of IBS systems in Malaysia are as follows: BARRIERS TO IBS ADOPTION IN MALAYSIA
  • 6. 1. Currently, the incentives for IBS are not sufficient. IBS adoption requires more pull and push factors from the government. Due to the small profit margin, the change from conventional to IBS was not feasible, unless, more attractive incentive systems and benefits which can lure the conventionalist to IBS are in place. 2. The availability of cheap foreign labour which offsets the cost benefit of using IBS is a root cause of the slow adoption in the past. As long as it is easy for the industry to find foreign workers, labour rates will remain low and builders will find it unattractive to change into simplified solutions such as IBS. 3. The limited take up also relates to sheer cost of investment and the inadequacy of market size. Since the Asian financial crisis in 1997 and global recession in 2008, it becomes apparent that large investments in central production plants are uneconomical. 4. To use a higher level of IBS, the adopters require a huge volume of works to break even on the investment. Although it creates more value to construction, it is literally a more expensive option due to the paid up capitals and maintenance of machineries. Inconsistency of volume over time and lack of business continuity resulted in the investment in latest innovation not being commercially sustainable. 5. Low standardisation of components also hinders successful use of IBS. The tailor-made components which do not fit into another project will increase initial costs due to the cost of the mould and design. Lack of standardisation was due to a lack of a certification and accreditation scheme on IBS and the lukewarm response to Modular Coordination (MC) promotion under MS 1064. 6. There is a general consensus among practitioners that IBS needs mass production to achieve economic viability, but currently, in Malaysia, there is no assurance of continuity of production, thus limiting interest in IBS. 7. Supply Chain Management (SCM) and partnering concept has not been fully understood by the industry. Currently, the cooperation between contractors, manufacturers and suppliers is weak in many cases. Improving the procurement system and supply chain is the key to achieving IBS success for contracting companies. THE WAY FORWARD The lesson learnt on IBS construction in Malaysia has led to the following recommendations towards the future improvement of IBS adoption in Malaysia: 1. The rising sustainability awareness around the globe has put the construction industry under immense pressure to improve project efficiency and deliverables. Industrialised Building System (IBS) has the potential to promote sustainability development and green construction. This may be achieved from a controlled production environment, minimization of construction waste, extensive usage of energy efficient building material, a safer and more stable work environment, and possibly better investment for long term project economy. The industry need to seize this opportunity and use IBS as their competitive advantages in promoting sustainable construction. 2. The mass construction workforce, especially the locals, needs to upgrade their skills to be involved in IBS. The policy on labour focuses on encouraging personnel to acquire skills in more than single trade. This would add more value by providing a more skilled workforce which would ultimately enhance the competitive advantage of the industry in facing the issue of adoption from conventional to the IBS. They must be equipped in design, installation and project management skills which are critical to IBS. A comprehensive preliminary study should be conducted by the government to identify the skill gaps in the IBS sector in order to create a comprehensive and systematic training programme. The preliminary study will ensure that the training fits the needs of IBS organisations and accommodates current skill shortages in the market, particularly specialist skills such as design and installation, based on information from real practice. 3. A vendor development programme modeled along the lines of the development of the national car industry should be established to target delivery of building components for the construction. The vendor program is to be accredited by existing government agencies which can provide a vetting process not only to guarantee consistent quality but also the achievement of structural capacity, fire rating and other requirements. The selected vendor are to be provided training, seed capital, components design, and selected private sector consultant to start up production factories. The location of this vendor’s manufacturing plant has to be located in the areas with available labour. Based on educated assumption, the expected investment requirement of RM 1.25 million is considered within the reach of SMEs and small contractors displaced by the new technology. A system is to be developed such that building component accredited will be given green lane approval such that technical and non-technical legislation that hinders implementation of the new technology will be removed. The government can help by conducting market research to ascertain market opportunities to the vendors. The vendors also need inventory management consultancy and advice and development of better tools and infrastructures required for location of manufacturing plant. 4. Manufacturers and all players of IBS sectors need to create highest value for IBS to serve the
  • 7. clients best interest, as we know clients in a private sector are more demanding in term of design esthetic value. With this regards, we need to move from mass production of components to mass customisation of buildings where the building design can be tailor-made to specific customer needs. The industry shall need to encourage automation and robotic to be really reduce the use of workers in construction and prefabrication. The government also perhaps needs to encourage manufacturers to produce ‘modular housing’ which move all the work trade at site to the manufacturing floor. We need to move up the level of industrialisation and encourage innovation, whilst low innovative systems which do contained enough value like mould systems will be discouraged. Proper incentive and tax holiday need to introduce to cater the production of innovative IBS. 5. Malaysian IBS contractors need to benchmark IBS technologies, lesson learnt and best practices from other countries. Construction industrialisation is a worldwide agenda. IBS is already successful adopted in Finland, Sweden, Japan, Germany and Singapore where offsite technologies had eventually modernised and improved the industry. This research recommended the industry players to find ways to capture and disseminate technologies, lesson learned, and best practices from successful countries and companies to expedite our learning curve on IBS and to guide the way forward. The government should launch a forum on a regular basis of academics and associated practitioners active in IBS for exchange of information and experience, development of new techniques and advice on promotion and implementation of IBS. An online portal was also suggested to disseminate international trends, products and processes associated with the IBS. References 1. CIDB, “CIDB News”, Construction Industry Development Board (CIDB) Publication, first quarters 2010, 2010 2. CIDB, “Malaysian construction industry outlook”, presentation by Business Development Sector of CIDB, August 2009 3. CIDB, “Malaysian construction industry outlook”, presentation by Business Development Sector of CIDB, August 2008 4. CIDB, “IBS Implementation in Malaysia”, Construction Industry Development Board (CIDB), Kuala Lumpur, 2008 5. CIDB, “IBS Digest at Malbex”, IBS Digest, Special Issues on 24th Malaysian International Building Exposition, pp. 19-22, Malbex, september 2007. 6. CIDB, “Report of quality assessment for project in Cambodia and Thailand constructed by Malaysian contractor”, Construction Industry Development Board (CIDB), Kuala Lumpur, 2007. 7. CIDB, “Implementing IBS Roadmap: Mid-term review of IBS Roadmap 2003-2010”, Construction Industry Development Board (CIDB), Kuala Lumpur, 2007. 8. CIDB, “IBS Survey 2005: Survey on Malaysian Architects”, Construction Industry Development Board (CIDB), Kuala Lumpur, 2005 . 9. CIDB, “Industrialised Building System (IBS) Roadmap 2003-2010”, Construction Industry Development Board (CIDB), Kuala Lumpur, 2003. 10. CIDB, “IBS Survey 2003 - A Survey on the Usage of Industrialised Building System in Malaysian Construction Industry”, Construction Industry Development Board, Kuala Lumpur, 2003. 11. CIDB, “IBS Roadmap 2003-2010”, Construction Industry Development Board (CIDB), Kuala Lumpur, 2003. 12. Hamid, Z., Kamar, K.A.M., Zain, M., Ghani, K., Rahim, A.H.A., “Industrialized Building System (IBS) in Malaysia: The Current State and R&D Initiatives”, Malaysia Construction Research Journal (MCRJ), Vol. 2 (1), pp 1-13, 2008. 13. Hassim, S., Jaafar, M.S., Sazali, S.A.A.H., “The Contractor Perception Towards Industrialised Building System Risk in Construction Projects in Malaysia”, American Journal of Applied Sciences, vol. 6 (5), pp. 937-942, 2009. 14. Pan, W., Gibb, , F.A.G., Dainty, A.R.J., “Leading UK Housebuilders' Utilization of Offsite Construction Methods”, Building Research & Information, vol. 36 (1), pp. 56 - 67, 2008. 15. Pan, W., Gibb, A.G.F., Dainty, A.R.J., “Perspectives of UK housebuilders on the use of offsite modern methods of construction”, Construction Management and Economics, vol. 25 (2), pp. 183- 194, 2007. 16. Rahman, A.B.A., Omar, W. “Issues and Challenge in the Implementation of IBS in Malaysia”, Proceeding of the 6th Asia Pacific Structural Engineering and Construction Conference (ASPEC), Kuala Lumpur, Malaysia, 5 & 6 september, 2006. 17. Sarja, A., “Open and Industrialised Building”, International Council for Building Research, E&FN Spoon, London, 1998. 18. Shaari, S. N., Ismail, E., “Promoting the Usage of Industrialised Building System (IBS) and Modular Coordination (MC) in Malaysia”, Construction Industry in Engineers (Board of Engineer Malaysia), March 2003. 19. Sumadi, S. R., “Promotion strategy and future research and development on IBS”, National Seminar on Industrialised Building System, Construction Industry development Board (CIDB), Kuala Lumpur, 2001 . 20. Thanoon, W.A., Peng, L.W., Kadir, M.R.A., Jaafar, M.S., Salit, M.S., “The Essential Characteristics of Industrialised Building System”, International Conference on Industrialised Building Systems Construction Industry Development Board (CIDB), Kuala Lumpur, Malaysia, 10-11 september 2003.
  • 8. 21. Trikha, D.N., Ali A.A.A., “Industrialised Building System (Fist ed.)”, Universiti Putra Malaysia Press, Kuala Lumpur, 2004