This document provides an overview of Industrialized Building Systems (IBS) with a focus on precast concrete systems. It defines IBS and discusses the key types, including precast concrete, steel framing, formwork, blockwork, timber framing, and innovative systems. The advantages of IBS are faster construction, higher quality, and lower cost. Potential defects in precast concrete like water leakage and cracking are also outlined. The document presents the standard design and construction workflows for IBS and provides case studies of two apartment buildings in Singapore that utilized precast concrete systems.
Project 1: Industrialised Building System [ IBS ]JerotichMaswan
Ā
Project 1 of Advanced Architectural Construction.
Requirement: Design a 3 storey apartment building using Precast Concrete System. Other IBS systems are allowed. Create a report on IBS and the building detailing.
Project 1: Industrialised Building System [ IBS ]JerotichMaswan
Ā
Project 1 of Advanced Architectural Construction.
Requirement: Design a 3 storey apartment building using Precast Concrete System. Other IBS systems are allowed. Create a report on IBS and the building detailing.
Passive Fire Protection According to UBBL MalaysiaZhao Wei Kim
Ā
Design and Application of passive fire protection stated in Uniform Building By-Laws of Malaysia. It contains graphical guidance to make the law items easier to comprehend and apply.
Credit to: UTM alumni
Passive Fire Protection According to UBBL MalaysiaZhao Wei Kim
Ā
Design and Application of passive fire protection stated in Uniform Building By-Laws of Malaysia. It contains graphical guidance to make the law items easier to comprehend and apply.
Credit to: UTM alumni
Building Technology 1 Construction Solutions Reportdouglasloon
Ā
Taylor's University Lakeside Campus
School of Architecture, Building & Design
Bachelor of Science (Hons) in Architecture
Building Technology (BLD 61403)
Pre-Cast Technology: An Initial Step to Sustainable Developmentijsrd.com
Ā
Erection of precast construction unit is a complex mechanized process for continuous assembly of buildings and installation of prefabricated elements and components. Precast construction provides advantages over conventional practice by costing the pre definite size of the members (penal, walls, beams, columns) in the factory. In this technique the structural members specially made of concrete that has been cast into form prior being transported to its construction location for the final installation work. Precast construction technique is the first step to satisfy the demand of sustainable housing for the population in developing country. It is also one of faster construction process which also provides high quality. This Paper cover different types of precast construction system, its main features, equipment required for the construction work and its installation process for different type of components.
Adjusting primitives for graph : SHORT REPORT / NOTESSubhajit Sahu
Ā
Graph algorithms, like PageRank Compressed Sparse Row (CSR) is an adjacency-list based graph representation that is
Multiply with different modes (map)
1. Performance of sequential execution based vs OpenMP based vector multiply.
2. Comparing various launch configs for CUDA based vector multiply.
Sum with different storage types (reduce)
1. Performance of vector element sum using float vs bfloat16 as the storage type.
Sum with different modes (reduce)
1. Performance of sequential execution based vs OpenMP based vector element sum.
2. Performance of memcpy vs in-place based CUDA based vector element sum.
3. Comparing various launch configs for CUDA based vector element sum (memcpy).
4. Comparing various launch configs for CUDA based vector element sum (in-place).
Sum with in-place strategies of CUDA mode (reduce)
1. Comparing various launch configs for CUDA based vector element sum (in-place).
Opendatabay - Open Data Marketplace.pptxOpendatabay
Ā
Opendatabay.com unlocks the power of data for everyone. Open Data Marketplace fosters a collaborative hub for data enthusiasts to explore, share, and contribute to a vast collection of datasets.
First ever open hub for data enthusiasts to collaborate and innovate. A platform to explore, share, and contribute to a vast collection of datasets. Through robust quality control and innovative technologies like blockchain verification, opendatabay ensures the authenticity and reliability of datasets, empowering users to make data-driven decisions with confidence. Leverage cutting-edge AI technologies to enhance the data exploration, analysis, and discovery experience.
From intelligent search and recommendations to automated data productisation and quotation, Opendatabay AI-driven features streamline the data workflow. Finding the data you need shouldn't be a complex. Opendatabay simplifies the data acquisition process with an intuitive interface and robust search tools. Effortlessly explore, discover, and access the data you need, allowing you to focus on extracting valuable insights. Opendatabay breaks new ground with a dedicated, AI-generated, synthetic datasets.
Leverage these privacy-preserving datasets for training and testing AI models without compromising sensitive information. Opendatabay prioritizes transparency by providing detailed metadata, provenance information, and usage guidelines for each dataset, ensuring users have a comprehensive understanding of the data they're working with. By leveraging a powerful combination of distributed ledger technology and rigorous third-party audits Opendatabay ensures the authenticity and reliability of every dataset. Security is at the core of Opendatabay. Marketplace implements stringent security measures, including encryption, access controls, and regular vulnerability assessments, to safeguard your data and protect your privacy.
1. Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Bachelor of Science (Honours) in ArchitectureĀ Ā
Ā
BUILDING TECHNOLOGY I (BLD 61403)Ā
Ā Ā
Project 1Ā Ā
Industrialised Building SystemĀ Ā
Ā
Group Members :Ā
Alexandra GoĀ
How Seng GuanĀ
Jacky Ting Sim MingĀ
Lee Suk FangĀ
Lee Wan XuanĀ
Tan Chin YinĀ
0325342Ā
1007P73021Ā
0325286Ā
0323293Ā
0325273Ā
0320080Ā
Ā
Tutor : Mr. RizalĀ
1
2. Table of Contents PageĀ
Ā
1.Introduction Ā Ā
1.1 Aims and objectives 1Ā
1.2 Introduction of IBS 1Ā
1.3 Types of IBS 3-4Ā Ā
1.4 Concept and Framework Ā
1.4.1 Advantages of using IBS 5Ā
1.4.2 Defects of Precast Concrete Building 5Ā
1.4.3 Standard Design WorkflowĀ 6Ā
1.4.4 Structural Construction Process 6Ā
1.5 Case StudyĀ
1.5.1 The Bayron, Devonshire Road, Singapore 7-8Ā
1.5.2 Seri Jati Apartment, Setia Alam 9 Ā
Ā
2.Technical DrawingsĀ
2.1 Architectural Plans 10-11Ā
2.2 Structural Plan 12Ā
2.3 Elevations 13-14Ā
2.4 Section 15Ā
2.5 Axonometric 16Ā
2.6 Sectional PerspectiveĀ 17Ā
2.7 Construction Details 18Ā
Ā
3.Study of Proposed IBS categories and detail of componentsĀ
3.1 Precast Concrete Frame 19Ā
3.2 Precast Concrete Column 20Ā
3.3 Precast Concrete Beam 21Ā
3.4 Precast Concrete Floor Slab 22Ā
3.5 Precast Concrete Wall 22Ā
3.6 Precast Concrete Staircase 23Ā
3.7 Prefabricated Steel Framing Roof Truss 23Ā
Ā
4. Construction sequence 24-26Ā
5. Schedule of IBS ComponentsĀ
5.1 Column Schedule 27-28Ā
5.2 Column and Beam Schedule 29Ā
5.3 Wall Schedule 30-33 Ā
5.4 Door and Window Schedule 34Ā
6. IBS Score Calculation 35-36Ā
7. Conclusion 36Ā
8. Reference List 37Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā Ā
2
3. 1.IntroductionĀ
Ā
1.1 Aims and ObjectivesĀ
Ā
This project is to provide a in depth and well-documented analysis about the topic ofĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
different types and methods of Industrialised Building System (IBS).For this report, we needĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
to proposed a 3-storey apartment block which using mainly IBS components. Done so over theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
course of six to seven weeks,our learning outcome as the following:Ā
Ā
(i) To study and identify the research data about types of IBS and construction methods.Ā
Ā
(ii) Able to explain and apply the relevant knowledge through a set of architectural andĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
structural documentation.Ā
Ā
(iii) Able to relate the basic structural elements and structural principles inĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
construction.Further analyse and document construction methods and materials.Ā
Ā
(iv) To be able to produce a well-documented report that surmises our findings and analysisĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
of our case study - which can then serve as an example of our accumulated knowledge of theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
relationship between construction and building.Ā
Ā
By analysing the types of IBS applied in the apartment building, we are then able to developĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
a better understanding on the characteristics of each structural components and how itĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
affects the IBS score. It is also important to know how different types of components andĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
their construction method influence the construction efficiency and the overall aestheticĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
appearance.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
1.2 Introduction of IBSĀ
Ā
What is IBS?Ā
Ā
Industrialised building system (IBS) also known as Pre-fabricated Construction and Off-siteĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
Construction, is a method of construction where the structural of building components areĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
fabricated under a controlled environment. They are produced off-site later transported andĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
assembled into construction site.Ā
Ā
They are divided into two systems which are open system and close system:Ā
Open system refers to the IBS components are fabricated by different manufacturersĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
while;Ā
Close system is the IBS components are fabricated from one manufacturer.Ā
Ā
There are several building components using IBS, which are columns, beams, floor slabs,Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
walls, portal frame, steel roof truss and 3-D components such as balconies, staircases,Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
toilets, etc.Ā
Ā
The content of IBS (IBS Score) is determined based on the Construction Industry Standard 18Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
(CIS 18: 2010); either manually, web application or fully automated CAD-based IBS ScoreĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
calculator.Ā
Ā
In Malaysia, the implementation of IBS concept by using pre-cast concrete building wereĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
introduced in Malaysia 1966 when the government launched two pilot projects for pre-castĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
housing which involves the construction of Tuanku Abdul Rahman Flats in Kuala Lumpur andĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
the Rifle Range Road Flats in Penang.Ā Ā
Ā
Since 1980ās there are intensive marketing strategies launched by the Malaysian GovernmentĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
to introduce modular coordination, its acceptance has received poor responses for theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
building industry. As a result even partial introduction of IBS such as lintels and staircase hasĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
not been possibleĀ Ā
Ā
In the 90s, demand for the new township has seen to increase in the use of precast concreteĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
system in high rise residential buildings. In the booming period of Malaysian constructionĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
1994 to 1997, hybrid IBS application used in many national iconic landmarks such as KualaĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
Lumpur Convention Center, Bukit Jalil Sport Complex constructed using steel beam and roofĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
trusses and precast concrete. Other than that, Lightweight Railway Train (LRT) and KLĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
Sentral was constructed by using steel roof structure and precast hollow core.Ā Ā
Ā
Ā
3
4. 1.3 Types of IBSĀ
Ā
The Malaysian construction industry is undergoing a transitional change from anĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
industry employing to one which is more systematic and mechanised. Based onĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
Construction Industry Development Berhad ( CIDB ), IBS is structurally classified intoĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
six main groups, which are:Ā
Ā
i. Precast systemĀ
ii. Steel Framing systemĀ
iii. Formwork systemĀ
iv. Block work systemĀ
v. Prefabricated timber framingĀ
vi. Innovative systemĀ
Ā
i. Precast systemĀ
This system consist of precasting concrete columns, beams, slabs, walls and ā 3-D āĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
components which as balconies , staircases, toilets, lift chambers, refuse chambers asĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
well as lightweight precast concrete and permanent concrete formworks. This is theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
most popular and widely used IBS in Malaysia. Besides, it is produced by using steel orĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
fiberglass formwork. Mainly used in schools, apartments, infrastructure projects andĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā
etc.Ā
Ā
Figure 1.1 Precast walls Figure 1.2 Precast staircasesĀ
Ā
Ā
Ā
ii. Steel framing systemĀ
This system is commonly used with precast concrete slabs, steel columns/ beams andĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
steel framing systems, and is used extensively in fast-track construction of skyscrapersĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
and also in construction of large factories and exhibition halls that require wide areas.Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
Apart from that, it is extensively used for light steel trusses consisting ofĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
cost-effective profiled cold-formed channels and steel portal frame system asĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā
alternatives to the heavier traditional hot-rolled sections.Ā Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 1.3 Steel roof trusses Figure 1.4 Pre-cast steel floor deckingĀ
Ā
iii. Formwork systemĀ
This system is made up of tunnel forms, beams and columns moulding forms, andĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
permanent steel formworks. It is the least prefabricated among all the IBS, as itĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
normally involves site casting. Therefore, it is subject to structural quality control,Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
high quality finishes and fast construction with less site labour and materialĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
requirement. The temporary formwork usually used not less than 20 times. It usesĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
expanded polystyrene (EPS) as based forms.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 1.5 Formwork of column Figure 1.6 Formwork of wall panelsĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
4
5. iv. Block work systemĀ
It includes of interlocking concrete masonry units (CMU) and lightweight concreteĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
blocks. It is mainly used for non-structural wall as an alternative to conventional brickĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
and plaster. They may include a hollow core to make them lighter and to improveĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
insulation properties. It has the lowest IBS score in the IBS scoring system.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 1.7 Interlocking block work Figure 1.8 Installation of blocksĀ
Ā
Ā
v. Prefabricated- timber framing systemĀ
It consists of timber building frames and timber roof trusses. Although the latter isĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
more common, timber building frame systems also offer attractive designs and highĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
aesthetic value from simple dwelling units to buildings such as chalets for resorts.Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
Examples of choice of timber are Bakau, Chengal, Kekatong, Keranji and Resak.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā Ā
Figure 1.9 Timber roof trusses Figure 1.10 Timber framingĀ Ā
Ā
Ā
Ā
Ā
Ā
vi. Innovative systemĀ
This is the latest IBS which incorporates various āgreenā elements, which areĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
considered innovative in the industry. An example of the innovation is the mixture ofĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
two elements such as polystyrene and concrete, to produce IBS components for use inĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
the construction of a wall which has better heat insulation properties. Indeed, withĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
the advancement in technology and innovation, new materials are being introduced atĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
the fabrication stage. Some of the new materials introduced in IBS include gypsum,Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
wood wool, polymer, fiberglass and aluminium-based IBS components.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 1.11 Installation of drywallĀ Ā
Ā
Ā
Ā Ā
5
6. 1.4 Concept and FrameworkĀ
Ā
1.4.1 What is the advantages of using IBS:Ā
ā Results in high-quality products and minimum waste, due to a factory workĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
environment that is easier to control.Ā
ā Results in elimination of conventional timber props and an obvious decrease ofĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
supporting materials, through the use of complete assembly elements or prop systemĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
for the onsite casting process.Ā
ā Results in a stronger and safer work platform, produced through a complete assemblyĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
element.Ā
ā Results in faster completion, due to the introduction of prefabricated components toĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
replace onsite fabrication.Ā
ā Results in a safer, cleaner and more organized site, due to the reduction ofĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
construction waste, site workers and prefabricated construction materials; andĀ
ā Results in a cheaper total construction cost, resulting from the above factors.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
1.4.2 Defects of Precast Concrete BuildingĀ
Ā
Ā
Figure 1.12 Steel reinforcement is exposed Figure 1.13 Water damage on concreteĀ
Ā
Without proper building maintenance, precast concrete building under IBS will beĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
facing a few very common problems, such as below:Ā
Ā
1.Water leakageĀ Ā
Water leakage is the most crucial defect in precast concrete building.This problemĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
normally happen due to poor joint connection of the components.Ā
Ā
2.CrackingĀ Ā
This problem is most commonly related to the improper use of raw material withĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
specification or there is lacking of skills and careless mistakes during the procedureĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
for quality control. Cracking may occur any part of the precast component eitherĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
panel, beam or even slab.Ā Ā
Ā
3. Poor humidity controlĀ Ā
When there is water leakage into the building such as from piping system, it willĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
caused the interior of the building to have high level of humidity. This can cause theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
M&E services inside the building became rusted and same time will affect theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
effectiveness of M&E services.Ā
Ā
4. Poor finishingĀ
Poor finishing could cause by the human factors like workers experiences or theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
material issues.Ā Ā
Ā
Ā
Ā
Ā
Ā
6
7. 1.4.3 Standard Design Workflow of IBSĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
The first stage is design phase, where the design of IBS components are carried outĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
according to the specification stated in MS 1064. Then, the components are precastĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
off site, which is at the manufacturing plant according to the specified dimension andĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
details. Quality-controlled of the end products was ensured through the processes ofĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
controlled prefabrication stage. The IBS components are then transported to the siteĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
from the manufacturing plant to the construction site for assembling stage. When theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
components reached the site, they will be assembled with the assistance of a craneĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
tower. Because of the precast process for components, there is less in-site work, thusĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
reduces the wastage and provide a cleaner site. Finally, the final unit is doneĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
assembling and is ready to serve the users or client.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
1.4.4 Structural Construction ProcessĀ
Ā
Before any proper planning, the construction shouldnāt been carried out because itĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
might caused a lot of mistakes in installation of components which will causeĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
structural failure. So to ensure high efficiency and quality of installation, things likeĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
method or sequence of assembly, handling method of rigging system, temporaryĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
support, joint detail method and etc. should be taken into consideration. FollowingĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
are some steps to be considered during the phase of preparation:Ā
Ā
Ā
Ā
1. Check for site accessibility for the delivery ofĀ Ā Ā Ā Ā Ā Ā Ā
precast elements.Ā
2. Check delivery checklist for correct type,Ā Ā Ā Ā Ā Ā
quantity and panel specification.Ā
3. Conduct sample measurement to confirm onĀ Ā Ā Ā Ā Ā
the accuracy of the dimension of components.Ā
4. Check the locations and conditions for lifting.Ā
Ā
Next phase will be the installation of vertical precastĀ Ā Ā Ā Ā Ā Ā Ā Ā
components. Firstly:Ā
Ā
1. Check the positions and alignment of starterĀ Ā Ā Ā Ā Ā Ā
bars before installing it.Ā
2. During installation, check the stability of theĀ Ā Ā Ā Ā Ā Ā
erected props before releasing hoisting cable.Ā
3. When carrying out grouting work, make sureĀ Ā Ā Ā Ā Ā Ā
the joint width between panels are withinĀ Ā Ā Ā Ā Ā Ā
allowances designed.Ā
4. The joint gaps should be consistent to allow forĀ Ā Ā Ā Ā Ā Ā Ā Ā
proper installation of sealant or grout toĀ Ā Ā Ā Ā Ā Ā
achieve high level of watertightness which canĀ Ā Ā Ā Ā Ā Ā
prevent water leakage.Ā
Ā
The last phase is the installation of horizontal precastĀ Ā Ā Ā Ā Ā Ā Ā Ā
components. Checklists that need to be done are such as:Ā
Ā
1. Lifting of beam should be supported minimum at two ends.Ā
2. Secure the formwork during casting.Ā
3. Check the levelness between each component before sealing them.Ā
4. Other will be mostly the same as vertical components casting.Ā
7
8. 1.5 Case StudiesĀ
Ā
1.5.1 The Bayron, Devonshire Road, SingaporeĀ
Ā
Located in Devonshire Road, Singapore, The Bayron is a private residential completedĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
in 1999. It is a part 12 storey, part 15 storey apartment with a total of 96 units. 19Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
months were taken to complete the construction of this apartment.Ā Ā
Ā
An existing layout plan that uses conventional in-situ reinforced concrete structureĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
with brickwall and plastering was modified to use precast concrete instead as on-siteĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
precasting was not possible due to site constraints.Ā Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 1.14 Entrance of the Bayron ApartmentĀ
Ā
The Bayron uses precast concrete components such as precast 2-tiered columns,Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
precast beams, prefabricated bathroom, precast wall panel, precast staircase andĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā
precast refuse chute. The buildability score of this apartment using precast concreteĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
is 85 while the buildability score of the existing design is only 48.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
FIgure 1.15 Plan indicating precast concrete components in The BayronĀ
Ā
8
10. 1.5.2 Seri Jati Apartment, Setia AlamĀ
Ā
Seri Jati is a low cost apartment located in the vicinity of Shah Alam, Selangor. ThisĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
residence was developed for the lower and medium income citizens by the renownedĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
SP Setia. Launched in the year 2012, this high density residence was completed onĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
2014. This residence offers 6 blocks in total, whereby 3 blocks are 10 storeys high andĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
the remaining 3 blocks are 11 storeys high. It has a total of 948 units.Ā
Ā
Ā
Ā
Figure 1.22 View of Seri Jati Apartment from the poolĀ
Ā
Seri Jati Apartment uses precast concrete system with components such as precastĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
load bearing walls,precast non-bearing walls, precast staircases and landing slabs,Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
precast lift core walls, precast bathroom slabs and precast air-cond ledges. It alsoĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
uses prefabricated steel trusses for the roof.Ā Ā
Ā
Floor slabs of this apartment are cast in-situ slabs. It has a total of 81.9 IBS score. TheĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
use of IBS in this apartment has reduced construction time, number of constructionĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
workers and also cost.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 1.23 Image showing the construction of Setia Jati ApartmentĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 1.24 Precast load bearing walls of Setia Jati ApartmentĀ
Ā
Ā
Ā
10
20. 3. Study of Proposed IBS categories and detail of componentsĀ
3.1 Precast Concrete FrameĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.1 Precast concrete frames are installed during constructionĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.2 Precast concrete frame during constructionĀ
Ā
Precast concrete-framed building has become one of the most commonly used IBS inĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
large structure such as industrial and institutional buildings. There are many reasonsĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
why the architects and engineering nowadays preferred this method instead of theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
conventional construction system.The advantage of the frame system is mainly theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
interior flexibility, as large space can be used for different functions and can be easilyĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
changed or modified according to the use. The frame system on its own, forms onlyĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
the skeleton of the building and do not enclose the space. Therefore, infill elementsĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
such as prefabricated panels or building the infill elements on site or both need to beĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
put up to complete the system. The components included column, beam, slab andĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
wall.Ā Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.3 Components of precast concrete frameĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.4 Image showing the substructure and superstructure of a 3 storey buildingĀ
Ā
The components are cast and cured in factories, transported to the construction jobĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
site, and erected as rigid components. Precasting offers many potential advantagesĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
over site casting of concrete. One of the main reason is precast concrete framesĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
provide a high strength, stable, durable and robust solution for any multi-storeyĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
structure. Control of the quality of materials and workmanship is generally betterĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
than on the construction job site. The erection of whole process does not only saveĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
times further more it also can take place under adverse weather conditions, whichĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
would not permit the site casting of concrete.Ā
Ā
Ā Ā
20
21. 3.2 Precast Concrete ColumnĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā Ā
Figure 3.5 Image above shows the corbel on the column supporting floor slabs.Ā
Ā
Precast concrete column is one of the load bearing element in the structuralĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
component of a building. To minimize the number of precast elements the columnsĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
have up to 3 stories height. The columns provide with single or multiple corbels toĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
support floor or roof beams.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.6 Connection of the column to the foundationĀ
Ā
A simple base detail for precast concrete columns. Four anchor bolts project from theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
top of the sitecast foundation. Nuts and washers are placed on these bolts to supportĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
the column temporarily. The column, which was cast around steel dowels welded to aĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
baseplate, is lowered by crane. Workers guide the column so that the anchor boltsĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
come through the holes in the baseplate. Washers and nuts are added to the anchorĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
bolts on top of the baseplate. The eight nuts are used to adjust the height of theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
column and to make it plumb. When this has been accomplished, the nuts areĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
tightened and stiff grout is dry packed under the baseplate.Ā
Ā
Ā
Typical Connection of Precast Concrete ElementsĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.7 Connection of column to columnĀ
Ā
1. Column-to-column connectionĀ Ā
-Metal bearing plates and embedded anchor bolts are cast into the ends of theĀ Ā
columns.Ā
-After the columns are mechanically joined, the connection is grouted to provide fullĀ Ā
bearing between elements and protect the metal components from fire andĀ Ā
corrosion.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.8 Connection of column to beamĀ
Ā
2. Column-to-beam connectionĀ
-Beams are set on bearing pads on the column corbels.Ā
-Steel angles are welded to metal plates cast into the beams and columns and theĀ Ā
joint is grouted solid.Ā
Ā
Ā
Ā
Ā
Ā Ā
21
22. 3.3 Precast Concrete BeamĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.9 Drawing of L shaped beam and inverted tee beamĀ
Ā
As for our project, the beam design chosen is L-shape beam and inverted tee beam.Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
The reason of selecting the type of beams is because they provide direct support forĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
precast slab elements. They conserve headroom in a building by supporting slabs nearĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
the bottoms of the beams, compared to rectangular beams without ledgers,where slabĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
elements must rest on top.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.10 Image showing the beam being supported by the columnĀ
Ā
Above is the indication of a cross section beams. The larger dots represent mild steelĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
reinforcing bars, and the smaller dots represent high-strength pressing strands. TheĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
broken lines show mild steel stirrups. Stirrups usually project above the top of theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
beam, to bond to a sitecast concrete topping for composite structural action.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Beam-to-Slab ConnectionĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.11 Connection of floor slab to beamĀ
Ā
The hollow core slabs are placed on the bearing pads on top of each beam. Grout isĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
poured into the gap between the ends of the planks to unite loops of reinforcing thatĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
project from the tops of the beams,reinforcing bars are inserted. The end results is aĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
tightly connected assembly that supports an untopped precast concrete floor or roof.Ā
Ā
Ā
Ā Ā
22
23. 3.4 Precast Concrete Floor SlabĀ
Ā
There are few types of slabs in the precast floor slab. We had chosen hollow core slabĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
as it could support a larger spans, deeper elements and it have internal longitudinalĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
voids replace much of the nonworking concrete.Ā Ā
Ā
Ā
Figure 3.12 Different types of floor slabĀ
Ā
Ā
Ā
Connections between hollow-core slabs and supporting members are made usingĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā
site-cast concrete fill and reinforcing steel. In addition to the concrete fill used forĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
connections, a site-cast concrete topping is generally used over the slabs. The toppingĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
provides structural integration of slab units and increases the floorās fire resistanceĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
and sound insulation. It also functions as a leveling bed, particularly with units withĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
uneven camber. Topping, when used , is generally about 2 inches thick and reinforcedĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
with welded wire reinforcement.Ā
Ā
Ā
Figure 3.13 Types of floor slab - Hollow core floor slabsĀ Ā
Ā
Ā
Ā
Ā
3.5 Precast Concrete WallĀ
Ā
Precast concrete walls provide an economical solution when compared to theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
conventional column / beam/ infill wall system. The primary advantages are speed ofĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
construction and elimination of wet trades.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.14 The installation of precast concrete wallsĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.15 Wall panels lined the side of the construction siteĀ
Ā
Typically, the wall panels for the front and rear elevations are non-load bearing facadeĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
elements. Support of these panels is achieved by the columns. The wall panels areĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
typically be designed for vertical loads due to self weight and an allowance for floorĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
loads, if applicable, in addition to horizontal loads due to external wind pressures.Ā Ā
Ā
Precast concrete wall manufactured in factory has smooth surfaces on both sides. ThusĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
the wall finished such as painting or other desired textured surfaces are easily applied.Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
Wall panels can be easily designed to undertake both structural requirements forĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
strength and safety, as well as aesthetic and sound attenuation qualities are desired.Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
Speed construction and durability of finished structures are hallmarks of precast wallĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
panels.Ā
23
24. Ā
3.6 Pre-cast Concrete StaircasesĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.16 Prefabricated staircase are transported to the construction siteĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Figure 3.17 Staircase is installed using the craneĀ
Ā
Ā
By using precast staircase,it will shorten the construction duration and allowsĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
operational access instantly to all floor areas, also has a high quality finish gives anĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
excellent acoustic properties such as sound transfer issues that associated with steelĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
and wooden staircases. It offers significant benefits during the construction phaseĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
providing rapid installation and early access for residential users.Ā
Ā
The joint of the staircases use the dry joint construction. The precast staircase will beĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
manufactured in the factory before it is brought over to site for installation. BeforeĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
that, the special casting system ensures the concrete steps are produced from steelĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
mould face giving a uniform, smooth surface finish. Adjustable casting moulds enableĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
concrete stairs to be precast with rising and going profiles to suit each application.Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
Rapid steel mould adjustment without costly timber shuttering minimizes downtimeĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā
and maximizing production.Ā
Ā
Ā
3.7 Prefabricated Steel Framing Roof TrussĀ
Ā
Prefabricated steel framing roof truss are flexible to work with any design. It is usually moreĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
expensive than wooden trusses, but they do last a lot longer than timber and require veryĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
little maintenance. Steel trusses deliver multiple benefits to construction project: ForĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
instance, they donāt need chemical treatments to maintain the frame; are not subject toĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
insect infestations; light weight, allowing easy and quick installation on site . Beside that,Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
steel framing can also be recycled easily. However, steel frame roof trusses require more skillĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
on the installation.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā Ā
24
25. 4. Model Construction SequenceĀ
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
1. Pad footings are constructed as the foundation of the apartment.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
2. Ground beams are placed and are supported by the pad footings.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
3. Precast hollow core concrete floor slabs are laid on top of the ground beamĀ
to act as the floor for ground level.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
4. Precast concrete columns are installed in the apartment.Ā
Ā
Ā
Ā
Ā
25
26. Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
5. Precast concrete wall panels of different sizes are placed into the apartmentĀ
according to the plan.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
6. Precast concrete staircase and landing are installed into the apartment.Ā Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
7. First floor precast concrete beams are placed on the columns.Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
8. First floor columns are installed on top of the first floor columns. Step 3 to step 7 areĀ
repeated for first floor and second floor.Ā
Ā
Ā
Ā
Ā
Ā
26
34. 6. IBS Score CalculationĀ
Ā
1) Construction areaĀ
Ā Ā
(i) Ground floor areaĀ Ā = 94 m2Ā
(ii) First floor areaĀ = 94 m2Ā
(iii) Second floor areaĀ Ā = 94 m2Ā
(iv) Roof areaĀ = 94 m2Ā
Ā Ā
Total Construction areaĀ = 376 m2Ā
Ā Ā
2) Structural SystemsĀ
Ā Ā
(i) Beams:Ā Precast concrete beamsĀ
(ii) Columns:Ā Precast concrete columnĀ
(iii) Floor slab:Ā Precast concrete floor slabĀ
(iv) Roof truss:Ā Ā Prefabricated steel roof trussĀ
Ā Ā
3) Wall SystemĀ
Ā Ā
(i) Internal wall:Ā Precast concrete panelĀ
(ii) External wall:Ā Precast concrete panelĀ
Ā Ā
4) Other simplified construction solutionsĀ
Ā Ā
(i) Beams: Less than 50% complies with MS 1064 Part 10: 2001Ā
Columns: 84.6% complies with MS 1064 Part 10: 2001Ā
Walls: Less than 50% complies with MS 1064 Part 10: 2001Ā
Floor Slabs: Less than 50% complies with MS 1064 Part 10: 2001Ā
Doors: 100% complies with MS 1064 Part 4: 2001Ā
Windows: 100% complies with MS 1064 Part 5: 2001Ā
Ā Ā
(ii) Repetition of floor to floor height = 100%Ā
Horizontal repetition of structure = 100%Ā
Vertical repetition of structure = 100%Ā
Ā
Ā
Ā
Ā
Ā
Ā Ā
ELEMENTSĀ
AREA(m2
) orĀ
Length(m)Ā
Ā Ā
COVERAGEĀ
IBSĀ
FACTOR(1)Ā
Ā Ā
IBS SCOREĀ
Part 1: StructureĀ
ElementsĀ
Ā Ā Ā Ā Ā Ā Ā Ā
Precast beams + PrecastĀ
columns + PrecastĀ
concrete slab - GroundĀ
floor areaĀ
Ā Ā
94 m2Ā
(94/376)Ā
= 0.25Ā
Ā Ā
1.0Ā
0.25 x 1.0 x 50Ā
= 12.5Ā
Precast beams + PrecastĀ
columns + PrecastĀ
concrete slab - FirstĀ
floor areaĀ
Ā Ā
94 m2Ā
(94/376)Ā
= 0.25Ā
Ā Ā
Ā Ā
1.0Ā
0.25 x 1.0 x 50Ā
= 12.5Ā
Precast beams + PrecastĀ
columns + PrecastĀ
concrete slab - SecondĀ
floor areaĀ
Ā Ā
94 m2Ā
(94/376)Ā
= 0.25Ā
Ā Ā
Ā Ā
1.0Ā
0.25 x 1.0 x 50Ā
= 12.5Ā
Roof truss using prefabĀ
metal roof truss - RoofĀ
areaĀ
Ā Ā
94 m2Ā
(94/376)Ā
= 0.25Ā
Ā Ā
1.0Ā
0.25 x 1.0 x 50Ā
= 12.5Ā
Total Part 1Ā 376 m2Ā
1.0Ā Ā Ā 50Ā
Ā
Ā
Ā Ā
ELEMENTSĀ
AREA(m2
)Ā
orĀ
Length(m)Ā
Ā Ā
COVERAGEĀ
IBSĀ
FACTOR(1)Ā
Ā Ā
IBS SCOREĀ
Part 2: Wall SystemĀ Ā Ā Ā Ā Ā Ā Ā Ā
External wall usingĀ
precast concrete panelĀ
425.1 m2Ā
(425.1/1019.7)Ā
= 0.42Ā
1.0Ā 0.42 x 1.0 x 20Ā
= 8.4Ā
Internal wall usingĀ
precast concrete panelĀ
594.6 m2Ā
(594.6/1019.7)Ā
= 0.58Ā
1.0Ā 0.58 x 1.0 x 20Ā
= 11.6Ā
Total Part 2Ā 1019.7 m2Ā
1.0Ā Ā Ā 20Ā
32
35. Ā
Ā Ā
ELEMENTSĀ
AREA(m2
) orĀ
Length(m)Ā
Ā Ā
COVERAGEĀ
IBSĀ
FACTOR(1)Ā
Ā Ā
IBS SCOREĀ
Part 3: Other simplifiedĀ
construction solutionsĀ
Ā Ā Ā Ā Ā Ā Ā Ā
Column sizes followĀ
MS1064 Part 10: 2001Ā
Ā Ā 84.6%Ā Ā Ā 4Ā
Door sizes follow MS1064Ā
Part 4: 2001Ā
Ā Ā 100%Ā Ā Ā 4Ā
Window sizes followĀ
MS1064 Part 4: 2001Ā
Ā Ā 100%Ā Ā Ā 4Ā
Repetition of floor toĀ
floor heightĀ
Ā Ā 100%Ā Ā Ā 2Ā
Horizontal repetition ofĀ
structural floor layout (>Ā
2 storeys)Ā
Ā Ā 100%Ā Ā Ā 2Ā
Vertical repetition ofĀ
structural floor layout (>Ā
2 storeys)Ā
Ā Ā 100%Ā Ā Ā 2Ā
Total Part 3Ā Ā Ā Ā Ā Ā Ā 18Ā
Ā
Ā
IBS CONTENTS SCORE OF PROJECĀ
Total Part 1 + Total Part 2 + Total Part 3Ā
= 50 + 20 + 18Ā
= 88Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Conclusion:Ā
Ā
In conclusion, the IBS score we calculated is 88% which is considering high, which reflectsĀ
that the construction if carried out effectively and it achieved most of the features of IBS.Ā
Ā
In IBS, precast concrete building is a very efficient construction method but without properĀ
management and planning since the stage of designing until the sealing and grouting of gaps,Ā
many defects might happen in future such as water leakage and cracking of some part of theĀ
components.Ā
Ā
After analysing the types of IBS applied in the apartment building, we are able to develop aĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
better understanding on the characteristics of each structural components and how it affectsĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
the IBS score.Ā Ā
Ā
We are then able to understand that IBS actually brings a lot of advantages to theĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
construction process such as a cleaner construction site, less wastage, faster completion ofĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
work and etc. which resulted a lower total construction cost.Ā Ā
Ā
Thanks to this project, we learnt that IBS is a very good method to carry out a constructionĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
and it has become a commonly used method for construction in Malaysia due to the limitedĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
boundary of site condition and limited time to finish a project. But we have to be alert ofĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
every single details in the process of construction and must always remember that, donāt letĀ Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā Ā
this system restrict our mind from exploring the designs of a building.Ā
Ā
Ā Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
Ā
33
36. Reference list:
1. Industrialised building system (IBS). (2017, September 27). Retrieved October 08, 2017, from
https://en.wikipedia.org/wiki/Industrialised_building_system_(IBS)
2. ė§ ģ“ķ Follow. (2014, July 04). Group Assignmentļ¼IBS System. Retrieved October 08, 2017,
from https://www.slideshare.net/x3HwaN/group-assignmentibs-system
3. Concrete masonry unit. (2017, September 30). Retrieved October 08, 2017, from
https://en.wikipedia.org/wiki/Concrete_masonry_unit
4. Ibs Complete. (n.d.). Retrieved October 08, 2017, from
https://www.scribd.com/doc/21794505/Ibs-Complete
5. Concrete Frame Construction | Concrete Frame Structures. (n.d.). Retrieved October 08, 2017,
from http://www.understandconstruction.com/concrete-frame-structures.html
6. History Of Ibs In Malaysia Construction Essay. (n.d.). Retrieved October 08, 2017, from
https://essays.pw/essay/history-of-ibs-in-malaysia-construction-essay-68039
7. Bhd, I. M. (1970, January 01). IBS Modular. Retrieved October 08, 2017, from
http://ibsmodular.blogspot.my/
8. Abhishek Gupta, Working Follow. (2015, April 03). PreCast Construction. Retrieved October 08,
2017, from https://www.slideshare.net/shekhu001/precast-construction
9. Precast Concrete Frame Buildings Design Guide. (n.d.). Retrieved October 08, 2017, from
https://www.scribd.com/doc/51059215/Precast-Concrete-Frame-Buildings-Design-Guide
10. Experimental study of a new beam-to-column connection for precast concrete frames under
reversal cyclic loading. (n.d.). Retrieved October 08, 2017, from
http://journals.sagepub.com/doi/abs/10.1177/1369433216630122
11. Precast Wall Connections, Precast Walls, Precast Frames. (n.d.). Retrieved October 08, 2017,
from
http://www.oreillyconcrete.com/products/precast-walls/precast-wall-connection-details/#prettyPh
oto[postimages]/5/
12. (n.d.). Retrieved October 08, 2017, from http://www.swiftseal.com/construction%20joints.html
13. Industrialised building systems in Malaysia. (2006). Malaysia: CIDB.
34