SlideShare a Scribd company logo
1 of 79
INDUSTRIALISED ofINDUSTRIALISED of
CONSTRUCTION SECTORCONSTRUCTION SECTOR
THROUGHTHROUGH
IBS ROADMAP 2003-2010IBS ROADMAP 2003-2010
11 JULY 200611 JULY 2006
Construction Industry Development Board Malaysia (CIDB)Construction Industry Development Board Malaysia (CIDB)
Rozaiman HassanRozaiman Hassan
MMCMMC
Modern MethodModern Method
ConstructionConstruction
OFFSITEOFFSITE
IBSIBS
Industrialised Building SystemIndustrialised Building System
Part 3 :
The Way Forward
Part 1 :
The Current Scenario of
Malaysian Construction Industry
Part 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
Conclusion
Introduction
Part 4 :
Case Study
IBS ROADMAP 2003-2010
• On the 29th Oct 2003, the
Cabinet has endorsed a
document – IBS
RoadMap 2003-2010
Introduction
 IBS Roadmap 2003-2010 endorsed by the
Cabinet on 29th
. October 2003
 the blueprint document towards achieving the
Industrialisation of the construction sector and
the longer term objective of Open Building
Concept.
IBS ROADMAP 2003-2010
Introduction
IntroductionPart 1 :
Implementing the Roadmap
Cabinet
Ministry of Works
[Inter-Ministry coordination committee]
[Chaired by : KSU KKR]
Ministries Agencies
CIDB
Implementation
Coordinator/secretariat IBS Steering Com.
Stakeholders
Policy
Poor Site ConditionPart 1 :
The Current Scenario of
Malaysian Construction Industry
 Messy sites
 Poor S & H
 High wastage
 Labour intensive
 Low quality
 Delays
SO WHAT IS
CONSTRUCTION
ACTUALLY??
DIRTYDIRTY
DIFFICULTDIFFICULT
DANGEROUSDANGEROUS
“Construction techniques in which components are
manufactured in a factory, on or off site, positioned
and assembled into a structure with minimal
additional site works”
DefinitionPart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
Processing
of steel
Assembly
of floor frame
Assembly of
ceiling frame
Assembly of
sidewall frames
Assembly of
structural unit
Attachment of
exterior walls
Application
of insulators
Attachment of
interior walls
Incorporation of
kitchen facilities
Incorporation of
bath and sanitary
facilities
Final inspection
Packing
Shipment
Delivery
Installation
Major production process
- Manufactured house (Sekisui)
ConceptsPart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
ConceptsPart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
UsagePart 2 :
Promoting Industrialized Building Systems (IBS) – Simplifying
Construction
FIGURE 4.3 - Knowledge in Industrialised Building
Systems (IBS)
34%
66%
% GOOD % POOR
“IBS Survey 2005 – Survey on the Malaysian
Architects’ Experience in IBS Construction”.
UsagePart 2 :
Promoting Industrialized Building Systems (IBS) – Simplifying
Construction
“IBS Survey 2005 – Survey on the Malaysian
Architects’ Experience in IBS Construction”.
FIGURE 4.5 - Experience in Using IBS Components in
Building Projects
30%
70%
YES NO
CharacteristicsPart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
5. Systematic Quality Control (ISO 9000 QMS)
2. Labour reduction
3. Modular Coordination - Open building concept
4. Modern design / manufacturing
(ex.CAD/CAM)
1. Industrial production of components (prefab,
precast under controlled environment) or highly
mechanised in-situ processes (slip forms, etc.)
1. Precast Concrete framing, panel,
box systems
TypesPart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
PC columns, beams, slabs, 3d-components (balconies,
staircases, toilets, lift chambers, box girders, etc)
2. Steel formworks systems
TypesPart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
Tunnel forms, beams and column moulding forms,
permanent steel formworks (metal decks), etc
3. Steel frame systems
TypesPart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
Steel beams and columns, portal frames, roof trusses, etc
4. Prefab timber frame systems
TypesPart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
Timber frames, roof trusses, etc
5. Block work systems
TypesPart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
Interlocking concrete masonry unit, lightweight concrete
blocks, etc
1. Reduction of site labour
2. Minimal wastage
3. Less site materials
4. Cleaner environment
5. Controlled quality
6. Neater and safer sites
7. Faster project completion
8. Lower total construction costs due to the above
BenefitsPart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
Shorter construction period; if there is consistently large
number of apartments to be constructed.
Time Scale (Months)
Precast System 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Production
Foundation Concurrently done ( with 2 week lead time)
Erection
Finishing
Mechanical & Electrical
Infrastructure
Testing & commisioning
Handing Over
Overall completion Period
Conventional System 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Foundation
Construction- superstructure
Finishing
Mechanical & Electrical
Infrastructure
Testing & commisioning
Handing Over
Overall completion Period
18 Month Completion
24 Month Completion
Sumber :Setia Precast
Sdn Bhd

Labour efficient through mechanisation, reduces 30%
labour
Sumber :Setia Precast
Sdn Bhd
IBS – Not A New Concept
Concept of prefabrication started
from the panellised timber houses
(circa, 1624) shipped form England
to the new settlements in America
Ref: Salahuddin, 2001
HistoryPart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
CIDB’s efforts in promoting IBS
started since 1998
Earlier, concentrated on
Awareness/Promotion/Training
Early EffortsPart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
However, usage of IBS in construction of
buildings is still relatively very low if compared to
infra works (bridges, tunnels, etc)
Only 15% IBS in building (Ref: IBS Survey, 2003)
Main Reason : Relatively cheap and abundant
supply of foreign labour for Malaysian industry
c.f. Labour cost in developed economies such
as Finland - 10 times the rates in Malaysia
(Ref: Gardiner & Theobald, 2002)
UsagePart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
Labour is cheap, so why IBS?
• Because labour is not going to stay cheap and
abundant forever and disruption to supply is
catastrophic
• Industry needs better productivity, quality and
safety to be globally competitive
• Move towards k-economy
UsagePart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
UsagePart 2 :
Promoting Industrialized Building
Systems – Simplifying Construction
IBS components are expensive, so why IBS?
• True. The components cost higher than
conventional, but in-situ construction has
hidden costs that usually lead to higher
expenditure; due to rectifications, wastages, etc
• IBS components currently cost higher because:
Low demand
Low standardisation of components (moulds need to
custom made or adjusted to suit orders)
Part 3 :
The Way Forward- The IBS
RoadMap 2003-2010
THE WAY FORWARD
IS TO INDUSTRIALISE CONSTRUCTION INDUSTRY
THROUGH COMPONENTS INDUSTRY
BUILT-IN
COMPONENTS
STRUCTURAL
COMPONENTS
RAILING
COMPONENTS
DOOR
COMPONENTS
WINDOW
COMPONENTS
Ref: JKR, 2003
Standardisation/ CoordinationPart 3 :
The Way Forward
To facilitate open
industrialization,
coordination is
needed in terms
of :
Dimensions
Tolerance
Joints and details
Technical
compatibility
Vendors,
manufacturer
IBS - HOLLISTIC APPROACH
Contractor, assemblers, fabricators
Designers,
(architects, engineers)
Client/Asset
manager
IBS Component
Catalogues
Design Guides
Standardisation/ CoordinationPart 3 :
The Way Forward
MS 1064 : 2001 :GUIDE TO MODULAR
COORDINATION IN BUILDINGS
PART 1: General Principles
PART 2: Storey and Room Heights
PART 3: Coordinating Sizes and Preferred Dimensions for Stairs and Stairs
Opening
PART 4: Coordinating Sizes and Preferred Dimensions for Doorsets
PART 5: Coordinating Sizes and Preferred Dimensions for Windowsets
PART 6: Coordinating Sizes and Preferred Dimensions for Rigid Flat Sheet
PART 7: Coordinating Sizes and Preferred Dimensions for Tiles
PART 8: Coordinating Sizes and Preferred Dimensions for Masonry Bricks and
Blocks
PART 9: Coordinating Sizes and Preferred Dimensions for Cabinets
PART 10: Coordinating Sizes and Preferred Dimensions for RC Components
Gazetted oct. 2002Gazetted oct. 2002
Publication Materials
Based on MS1064, MC
coordinates the positions,
dimensions of components
and spaces in building designs
Base module :
M = 100mm
Modular Coordination (MC)Part 3 :
The Way Forward
Modularisation
MS 1064
New Strategies
New Strategies on IBS & MC needed to promote
industrialisation; Enforcement & Incentives in
addition to Awareness/Promotion/Training
Main target – housing sector (repetitive, high
volume)
Part 3 :
The Way Forward
“Closed System”
mass - production
one end product
etc.
Mula-mula:
Projek
Kemudian:
Sistem
Bekalan:
Syarikat tertentu
First a project Then a system
Always third
party supply
Current ScenarioPart 3 :
The Way Forward
“Open System”
DESIGN GUIDE
CATALOGUE
etc.
?
?
First a system
Then many
projects
Open supply
Future ScenarioPart 3 :
The Way Forward
IBS Roadmap 2003-2010Part 3 :
The Way Forward
5. Marketing/Promotion
2. Materials/Components/Machines
1. Manpower
3. Management/Process/Methods
4. Monetary/Economic/Financial
Formulation of Roadmap based on FIVE main
elements
• To have a labour policy that gradually reduces
PERCENTAGE OF FOREIGN WORKERS from the
current 75% to 55% in 2005, 25% in 2007 and
15% in 2009.
• To incorporate IBS in CPD courses for
architects, engineers and others.
• To incorporate SYLLABUS ON IBS in
architecture, engineering, building courses in
IPTs.
Key Elements of RoadmapThe Way Forward
(MANPOWER)
• Continue efforts to develop NOSS ( National
Occupational Skill Standards).
• Continue Workers training and certification
programme to include all types of IBS.
• Commence the training programme on mould
making for IBS components.
• Commence the industrial expertise awareness
programme together with IBS manufacture
through on-job training for trainees.
Key Elements of RoadmapThe Way Forward
(MANPOWER)
• Commence the site supervisory training and
certification programme which includes
knowledge on IBS
• To start BUMIPUTERA IBS MANUFACTURERS
AND SPECIALISED CONTRACTORS training
and financial aid
Key Elements of RoadmapThe Way Forward
(MANPOWER)
• Enforce the use of Modular Coordination
based on MS 1064 through Uniformed Building
By Laws (UBBL) by local authorities.
• Continue publishing reference books and case
study reports regarding IBS.
• Continue writing new Malaysian Standards
(MS) covering all types of IBS.
• Continue writing new Construction Industry
Standards (CIS).
Key Elements of Roadmap
The Way Forward
(MATERIALS)
• Develop software for MC components and
dimensioning.
• Include the IBS/MC knowledge into the
standards of practice and training modules for
the training and certification of Project
Manager.
Key Elements of Roadmap
The Way Forward
(MANAGEMENT)
• Offer specialised contractors training and
certification programmes to cater for IBS
related registration codes.
• Continually update the website to disseminate
information on IBS, MC and OBS.
Key Elements of Roadmap
The Way Forward
(MANAGEMENT)
• Enforce IBS usage in government (building)
projects in phases (from 30% in 2004 to 70% in 2008).
• Offer levy exemptions from 2004 for low cost, low
medium cost and medium cost housing projects.
• Offer training schemes and financial loans for
manufacture and contractors.
Key Elements of Roadmap
The Way Forward
(MONETARY)
• Introduce Buildability Programme beginning
2006 for private (building) projects and
enforcing it through the local Authorities in
2008.
• Use IBS construct 30% of the 150,000 units of
houses proposed to be built by Syarikat
Perumahan Negara Berhad under the 2003
Economy Stimulus Packages.
Key Elements of Roadmap
The Way Forward
(MONETARY)
• Publish IBS product catalogues.
• Continue IBS/MC road show programmes at
the national and international levels.
• Establish IBS as the main criteria for Malaysian
Construction Industry Excellence Awards.
• Introduce concept of Open building Systems
to the industry.
Key Elements of Roadmap
The Way Forward
(MARKETING)
2005 Budget:2005 Budget:
1. Directives:1. Directives:
- Govt building projects- Govt building projects ≥≥ 50% IBS Score50% IBS Score
- 100,000 affordable houses using IBS- 100,000 affordable houses using IBS
2. Incentive:2. Incentive:
- Zero levy for residential projects- Zero levy for residential projects ≥≥ 50% IBS50% IBS
ScoreScore
Budget 2005Part 3 :
The Way Forward
IBS ScoringPart 3 :
The Way Forward
• Part 1 – Structural
Element (50%)
• Part 2 – Wall
Element (30%)
• Part 3 – Other
Simplified Solution
(20%)
Case StudiesCase StudiesPart 4 :
Case StudiesCase Studies
SJK(C) DAMANSARA
PETALING JAYA
SELANGOR DARUL EHSAN
Case StudiesCase StudiesPart 4 :
Sumber : JKR
PROJECT DETAILS
Cabinet’s directive - 31Januari 2001
school to be completed in 2001 – 8 months
•project site : 2 .1 hectares
•possession of site : 1 February 2001
•completion : 31 July 2001
•construction period : 5 1/2 months
FEB 2001
Earth worksFEB - MAC 2001 Piling works
Case StudyPart 4:
Ground level
MAC 2001
MAC 2001
Level 1
•Fast track project using prefabricated
components
•Beams, floor slabs (half slabs with
concrete topping) and staircases were
prefabricated in the factory, wall panel are
hollow blocks
•Columns and toilets were cast in-situ
Roof level
APR - MEI 2001
External works
MAC - APRIL 2001
Level 2
APRIL - MEI 2001
Level 3
Back
elevation
Front elevation
Case StudiesCase StudiesPart 4:
Case StudiesPart 4 :
 IBS STRUCTURE:
“HOLLOWCORE” SLABS;
PRECAST CONCRETE
COLUMNS & BEAMS
 9,900 m2, 4 FLOORS
 COMPLETION IN 8 MONTHS
CASE STUDY 8 : SCHOOL
SEK. KEB. BRICKFIELDS 1, KUALA LUMPUR
PROJECT DETAILS
a compact design to house two schools in
a total site area of 48,220 sq.ft.
•start of project : 6 February 2003
•completion : 17 Sept. 2003
•construction period : 7 1/2 months
• project constraints – limited site, busy
access, short construction period
• 75 % of building components were
prefabricated
• Prefab components used – columns,
beams, hollow core floor slabs,
staircases, wall panels (Acotech
panels)
• Architectural features – bright façade,
cascading roofs with large overhangs,
internal pockets of large and small
courtyards
installation of precast column
installation of first floor slab on 02.05.03
installation of 3rd floor slab on 28.05.03
installation of precast staircases
fixing of wall panel
completion of external wall on 16.07.03
in 2001 – new design alternatives for all categories of government
quarters were initiated
NEW DESIGN FOR GOVERNMENT
QUARTERS
•application of modular coordination
• use of building components
• flexibility and creativity in design and the concept of sustainable design
• standardised components for interchangeability between designs
Projek Akademi Audit Negara, Nilai, NS
Krtrs kelas F & G – load bearing design, precast wall,
slab, column & beam
Projek Akademi Audit Negara, Nilai, NS
Projek Balai Polis, Senawang, NS
frame system : cast-in-situ
column & beam, precast infill
wall & slab
Krtrs kelas F
Krtrs kelas G
Projek Balai Polis, Senawang, NS
Projek Balai Polis, Senawang, NS
Case StudiesPart 4 :
 KEDAH STATE GOVERNMENT
 IBS STRUCTURE:
“HOLLOWCORE” SLABS;
PRECAST CONCRETE
COLUMNS & BEAMS
 25,500 m2, 3 FLOORS
 STRUCTURAL
CONSTRUCTION: 4 MONTHS
CASE STUDY 1 : COMMUNITY COMPLEX
DEWAN WAWASAN, KUBANG PASU, KEDAH
Case StudiesPart 4 :
 PENANG STATE
GOVERNMENT
 IBS STRUCTURE:
“HOLLOWCORE” SLABS;
PRECAST CONCRETE
COLUMNS & BEAMS
 7,500 m2, 4 FLOORS
 STRUCTURAL
CONSTRUCTION: 2 MONTHS
CASE STUDY 2 : COMMUNITY COMPLEX
DEWAN MILENIUM, KEPALA BATAS, PULAU PINANG
Case StudiesPart 4:
 MAJLIS PERBANDARAN
PPINANG
 IBS STRUCTURE:
“HOLLOWCORE” SLABS;
PRECAST CONCRETE
COLUMNS, BEAMS &
BLEACHERS
 6,000 m2, 3 FLOORS
 STRUCTURAL
CONSTRUCTION: 2 MONTHS
CASE STUDY 3: STADIUM
BALIK PULAU INDOOR STADIUM, PULAU PINANG
Case StudiesPart 4 :
 IBS STRUCTURE: METAL
FORMWORKS FOR WALLS,
SLABS, BEAMS & COLUMNS
 TWO 26-30 STOREY TOWERS
(APARTMENTS & OFFICES)
 STRUCTURAL
CONSTRUCTION: 6 MONTHS
CASE STUDY 4 : RESIDENTIAL & OFFICE
NORTHAM CITY, PULAU PINANG
Case StudiesPart 4:
 IBS STRUCTURE:
LIGHTWEIGHT BLOCKS &
PRECAST CONCRETE WALLS;
PRECAST CONCRETE SLABS
 10,000 UNITS, 4-5 STOREY
 109 LOCATIONS IN 9 STATES
 COMPLETION IN 3 YEARS
CASE STUDY 6 : QUARTERS
TEACHERS QUARTERS, ALL OVER MALAYSIA
Case StudiesPart 4 :
 CIDB MALAYSIA
 IBS STRUCTURE: PRECAST
CONCRETE SLABS, BEAMS,
COLUMNS & WALLS
 9,600 m2, 6 WORKSHOP
BLOCKS
 STRUCTURAL
CONSTRUCTION: 3 MONTHS
CASE STUDY 7 : TRAINING CENTRE
AKADEMI BINAAN MALAYSIA, SINTOK, KEDAH
Case StudiesPart 4 :
 MINISTRY OF HEALTH
 620-BED HOSPITAL
 HYBRID IBS STRUCTURE OF
STEEL FRAMES; PRECAST
CONCRETE SLABS;
LIGHTWEIGHT CONCRETE
BLOCKS FOR WALLS
 130,000 m2, 9 FLOORS
 STRUCTURAL CONSTRUCTION:
4 MONTHS
CASE STUDY 9 : MEDICAL CENTRE
HOSPITAL SERDANG, SELANGOR
Case StudiesPart 4 :
 IBS STRUCTURE: “SOLID” &
“HOLLOWCORE” SLABS;
PRECAST CONCRETE WALLS,
STAIRCASES, GUTTERS,
BEAMS & COLUMNS
 121,000 m2, 4 FLOORS, 2
BASEMENTS
 STRUCTURAL
CONSTRUCTION: 4 MONTHS
CASE STUDY 10 : SHOPPING COMPLEX
IKEA MUTIARA DAMANSARA, SELANGOR
Case StudiesPart 4 :
 IBS STRUCTURE: PRECAST
CONCRETE SLABS, WALLS &
STAIRCASES
 756 UNITS, 6 BLOCKS, 8-16
FLOORS
 CONSTRUCTION: 18 MONTHS
CASE STUDY 11 : RESIDENTIAL
APARTMENTS, PRECINCT 9, WP PUTRAJAYA
IBS ROADMAP 2003-2010:
towards labour reduction and
better productivity,quality, safety &
environment; reducing total
industry costs
THUS INCREASING THE
INDUSTRY COMPETITIVENESS
Conclusion
Thank you

More Related Content

What's hot

Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Nekumi Kida
 
Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]JerotichMaswan
 
IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartmentJy Chong
 
Building Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSBuilding Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSJing Fan Koh
 
industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achahAisyah Asyikin
 
Btech report final
Btech report finalBtech report final
Btech report finalSarah Esa
 
Project 1 - Industrialised Building System
Project 1 - Industrialised Building SystemProject 1 - Industrialised Building System
Project 1 - Industrialised Building Systemhilmanaqil1
 
Blockwork system
Blockwork systemBlockwork system
Blockwork systemWen Crystal
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Soh Shing
 
Building Technology Project 1 Report
Building Technology Project 1 ReportBuilding Technology Project 1 Report
Building Technology Project 1 ReportBolin Loong
 
Prefabricated timber framing systems
Prefabricated timber framing  systemsPrefabricated timber framing  systems
Prefabricated timber framing systemsFarah Sham
 
Structural systems and aerodynamic in multi stoery buildings
Structural systems and aerodynamic in multi stoery buildingsStructural systems and aerodynamic in multi stoery buildings
Structural systems and aerodynamic in multi stoery buildingsManoj Kumar
 
Parliament building
Parliament buildingParliament building
Parliament buildingWeng Chuan
 
Ctblockworksystem. report
Ctblockworksystem. reportCtblockworksystem. report
Ctblockworksystem. reportlohwenjun
 

What's hot (20)

Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)
 
Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]
 
IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartment
 
Building Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSBuilding Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBS
 
Ibs part1
Ibs part1Ibs part1
Ibs part1
 
industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achah
 
Building Technology II Project 1
Building Technology II Project 1Building Technology II Project 1
Building Technology II Project 1
 
Btech report final
Btech report finalBtech report final
Btech report final
 
Project 1 - Industrialised Building System
Project 1 - Industrialised Building SystemProject 1 - Industrialised Building System
Project 1 - Industrialised Building System
 
Blockwork system
Blockwork systemBlockwork system
Blockwork system
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Building Technology 1 (Project 1)
Building Technology 1 (Project 1)
 
Building Technology Project 1 Report
Building Technology Project 1 ReportBuilding Technology Project 1 Report
Building Technology Project 1 Report
 
Refurbishment
RefurbishmentRefurbishment
Refurbishment
 
Building Services Case Study
Building Services Case StudyBuilding Services Case Study
Building Services Case Study
 
Prefabricated timber framing systems
Prefabricated timber framing  systemsPrefabricated timber framing  systems
Prefabricated timber framing systems
 
Structural systems and aerodynamic in multi stoery buildings
Structural systems and aerodynamic in multi stoery buildingsStructural systems and aerodynamic in multi stoery buildings
Structural systems and aerodynamic in multi stoery buildings
 
Parliament building
Parliament buildingParliament building
Parliament building
 
Ctblockworksystem. report
Ctblockworksystem. reportCtblockworksystem. report
Ctblockworksystem. report
 
ibs 304
ibs 304ibs 304
ibs 304
 

Similar to IBS Roadmap 2003-2010: Promoting Industrialized Building Systems in Malaysia

230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).pptMohd Zulhairi Mohd Noor
 
MS Ibs in malaysia
MS Ibs in malaysiaMS Ibs in malaysia
MS Ibs in malaysiaEst
 
CSCM Ibs in malaysia
CSCM Ibs in malaysiaCSCM Ibs in malaysia
CSCM Ibs in malaysiaEst
 
Modular Coordination in buildings and construction.pptx
Modular Coordination in buildings and construction.pptxModular Coordination in buildings and construction.pptx
Modular Coordination in buildings and construction.pptxAtulBhagwat6
 
Chap 2-literature-review (3)
Chap 2-literature-review (3)Chap 2-literature-review (3)
Chap 2-literature-review (3)Jessyca Than
 
Off-site and on -site modern method of construction
Off-site and on -site modern method of constructionOff-site and on -site modern method of construction
Off-site and on -site modern method of constructionANNA REBECCA PRASAD
 
Analysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional ConstructionAnalysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional ConstructionIRJET Journal
 
Industrialised Building System in Malaysia.pdf
Industrialised Building System in Malaysia.pdfIndustrialised Building System in Malaysia.pdf
Industrialised Building System in Malaysia.pdfKamalGhazali2
 
Motorcycle Pallet Rack Project Report
Motorcycle Pallet Rack Project ReportMotorcycle Pallet Rack Project Report
Motorcycle Pallet Rack Project ReportOlusegun. B Adekoya
 
Mivan Formwork in Construction
Mivan Formwork in ConstructionMivan Formwork in Construction
Mivan Formwork in ConstructionIRJET Journal
 
Building Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyBuilding Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyQuinn Liew
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3 Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3 Yee Len Wan
 
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...Haziq1511
 
Mmcrevisionnotes 100523035236-phpapp02
Mmcrevisionnotes 100523035236-phpapp02Mmcrevisionnotes 100523035236-phpapp02
Mmcrevisionnotes 100523035236-phpapp02Gopinan
 
IRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate Developers
IRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate DevelopersIRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate Developers
IRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate DevelopersIRJET Journal
 
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”IRJET Journal
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsIRJET Journal
 

Similar to IBS Roadmap 2003-2010: Promoting Industrialized Building Systems in Malaysia (20)

230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt
 
MS Ibs in malaysia
MS Ibs in malaysiaMS Ibs in malaysia
MS Ibs in malaysia
 
CSCM Ibs in malaysia
CSCM Ibs in malaysiaCSCM Ibs in malaysia
CSCM Ibs in malaysia
 
Modular Coordination in buildings and construction.pptx
Modular Coordination in buildings and construction.pptxModular Coordination in buildings and construction.pptx
Modular Coordination in buildings and construction.pptx
 
Chap 2-literature-review (3)
Chap 2-literature-review (3)Chap 2-literature-review (3)
Chap 2-literature-review (3)
 
Off-site and on -site modern method of construction
Off-site and on -site modern method of constructionOff-site and on -site modern method of construction
Off-site and on -site modern method of construction
 
Analysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional ConstructionAnalysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional Construction
 
Industrialised Building System in Malaysia.pdf
Industrialised Building System in Malaysia.pdfIndustrialised Building System in Malaysia.pdf
Industrialised Building System in Malaysia.pdf
 
Motorcycle Pallet Rack Project Report
Motorcycle Pallet Rack Project ReportMotorcycle Pallet Rack Project Report
Motorcycle Pallet Rack Project Report
 
Mivan Formwork in Construction
Mivan Formwork in ConstructionMivan Formwork in Construction
Mivan Formwork in Construction
 
Building Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyBuilding Technology : Industrialize Building Technology
Building Technology : Industrialize Building Technology
 
Btech report
Btech reportBtech report
Btech report
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3 Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3
 
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
 
Mmcrevisionnotes 100523035236-phpapp02
Mmcrevisionnotes 100523035236-phpapp02Mmcrevisionnotes 100523035236-phpapp02
Mmcrevisionnotes 100523035236-phpapp02
 
MMC Revision Notes
MMC Revision NotesMMC Revision Notes
MMC Revision Notes
 
IRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate Developers
IRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate DevelopersIRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate Developers
IRJET- Adoption of Pre-Fabricated Bathroom Units by Real Estate Developers
 
Ct3
Ct3Ct3
Ct3
 
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast Buildings
 

More from UTHM

2014 sistem pengangkutan_dalam_bangunan
2014 sistem pengangkutan_dalam_bangunan2014 sistem pengangkutan_dalam_bangunan
2014 sistem pengangkutan_dalam_bangunanUTHM
 
Ukur aras-levelling
Ukur aras-levellingUkur aras-levelling
Ukur aras-levellingUTHM
 
Sistem pencegah kebakaran
Sistem pencegah kebakaranSistem pencegah kebakaran
Sistem pencegah kebakaranUTHM
 
Bab 11 (b) meminimakan sampah
Bab 11 (b)   meminimakan sampahBab 11 (b)   meminimakan sampah
Bab 11 (b) meminimakan sampahUTHM
 
K4 banjir
K4 banjirK4 banjir
K4 banjirUTHM
 
The strategy formulation_framework_10
The strategy formulation_framework_10The strategy formulation_framework_10
The strategy formulation_framework_10UTHM
 
Sistem bekalan air
Sistem bekalan air Sistem bekalan air
Sistem bekalan air UTHM
 
Teknologi alam sekitar
Teknologi alam sekitar Teknologi alam sekitar
Teknologi alam sekitar UTHM
 
Meminimumkan sisa bahan
Meminimumkan sisa bahanMeminimumkan sisa bahan
Meminimumkan sisa bahanUTHM
 
Kod Etika Kontraktor
Kod Etika Kontraktor Kod Etika Kontraktor
Kod Etika Kontraktor UTHM
 
Brochure BIM
Brochure BIM Brochure BIM
Brochure BIM UTHM
 
Drn bm
Drn bmDrn bm
Drn bmUTHM
 
Planning standard
Planning standardPlanning standard
Planning standardUTHM
 
Construction materialsconcrete
Construction materialsconcreteConstruction materialsconcrete
Construction materialsconcreteUTHM
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
Applications of high performance lightweight concrete in a floating barge gate
Applications of high performance lightweight concrete in a floating barge gateApplications of high performance lightweight concrete in a floating barge gate
Applications of high performance lightweight concrete in a floating barge gateUTHM
 
Pembinaanjalan w12
Pembinaanjalan w12Pembinaanjalan w12
Pembinaanjalan w12UTHM
 
Lesson 1-Learning Mandarin Class
Lesson 1-Learning Mandarin ClassLesson 1-Learning Mandarin Class
Lesson 1-Learning Mandarin ClassUTHM
 
Topik 7 kaedah penilaian projek
Topik 7      kaedah penilaian projekTopik 7      kaedah penilaian projek
Topik 7 kaedah penilaian projekUTHM
 
Tembok penahan
Tembok penahanTembok penahan
Tembok penahanUTHM
 

More from UTHM (20)

2014 sistem pengangkutan_dalam_bangunan
2014 sistem pengangkutan_dalam_bangunan2014 sistem pengangkutan_dalam_bangunan
2014 sistem pengangkutan_dalam_bangunan
 
Ukur aras-levelling
Ukur aras-levellingUkur aras-levelling
Ukur aras-levelling
 
Sistem pencegah kebakaran
Sistem pencegah kebakaranSistem pencegah kebakaran
Sistem pencegah kebakaran
 
Bab 11 (b) meminimakan sampah
Bab 11 (b)   meminimakan sampahBab 11 (b)   meminimakan sampah
Bab 11 (b) meminimakan sampah
 
K4 banjir
K4 banjirK4 banjir
K4 banjir
 
The strategy formulation_framework_10
The strategy formulation_framework_10The strategy formulation_framework_10
The strategy formulation_framework_10
 
Sistem bekalan air
Sistem bekalan air Sistem bekalan air
Sistem bekalan air
 
Teknologi alam sekitar
Teknologi alam sekitar Teknologi alam sekitar
Teknologi alam sekitar
 
Meminimumkan sisa bahan
Meminimumkan sisa bahanMeminimumkan sisa bahan
Meminimumkan sisa bahan
 
Kod Etika Kontraktor
Kod Etika Kontraktor Kod Etika Kontraktor
Kod Etika Kontraktor
 
Brochure BIM
Brochure BIM Brochure BIM
Brochure BIM
 
Drn bm
Drn bmDrn bm
Drn bm
 
Planning standard
Planning standardPlanning standard
Planning standard
 
Construction materialsconcrete
Construction materialsconcreteConstruction materialsconcrete
Construction materialsconcrete
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
Applications of high performance lightweight concrete in a floating barge gate
Applications of high performance lightweight concrete in a floating barge gateApplications of high performance lightweight concrete in a floating barge gate
Applications of high performance lightweight concrete in a floating barge gate
 
Pembinaanjalan w12
Pembinaanjalan w12Pembinaanjalan w12
Pembinaanjalan w12
 
Lesson 1-Learning Mandarin Class
Lesson 1-Learning Mandarin ClassLesson 1-Learning Mandarin Class
Lesson 1-Learning Mandarin Class
 
Topik 7 kaedah penilaian projek
Topik 7      kaedah penilaian projekTopik 7      kaedah penilaian projek
Topik 7 kaedah penilaian projek
 
Tembok penahan
Tembok penahanTembok penahan
Tembok penahan
 

Recently uploaded

Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxChelloAnnAsuncion2
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........LeaCamillePacle
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 

Recently uploaded (20)

Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 

IBS Roadmap 2003-2010: Promoting Industrialized Building Systems in Malaysia

  • 1. INDUSTRIALISED ofINDUSTRIALISED of CONSTRUCTION SECTORCONSTRUCTION SECTOR THROUGHTHROUGH IBS ROADMAP 2003-2010IBS ROADMAP 2003-2010 11 JULY 200611 JULY 2006 Construction Industry Development Board Malaysia (CIDB)Construction Industry Development Board Malaysia (CIDB) Rozaiman HassanRozaiman Hassan
  • 3.
  • 4. Part 3 : The Way Forward Part 1 : The Current Scenario of Malaysian Construction Industry Part 2 : Promoting Industrialized Building Systems – Simplifying Construction Conclusion Introduction Part 4 : Case Study
  • 5. IBS ROADMAP 2003-2010 • On the 29th Oct 2003, the Cabinet has endorsed a document – IBS RoadMap 2003-2010 Introduction
  • 6.  IBS Roadmap 2003-2010 endorsed by the Cabinet on 29th . October 2003  the blueprint document towards achieving the Industrialisation of the construction sector and the longer term objective of Open Building Concept. IBS ROADMAP 2003-2010 Introduction
  • 7. IntroductionPart 1 : Implementing the Roadmap Cabinet Ministry of Works [Inter-Ministry coordination committee] [Chaired by : KSU KKR] Ministries Agencies CIDB Implementation Coordinator/secretariat IBS Steering Com. Stakeholders Policy
  • 8. Poor Site ConditionPart 1 : The Current Scenario of Malaysian Construction Industry  Messy sites  Poor S & H  High wastage  Labour intensive  Low quality  Delays
  • 9.
  • 10.
  • 12. “Construction techniques in which components are manufactured in a factory, on or off site, positioned and assembled into a structure with minimal additional site works” DefinitionPart 2 : Promoting Industrialized Building Systems – Simplifying Construction
  • 13. Processing of steel Assembly of floor frame Assembly of ceiling frame Assembly of sidewall frames Assembly of structural unit Attachment of exterior walls Application of insulators Attachment of interior walls Incorporation of kitchen facilities Incorporation of bath and sanitary facilities Final inspection Packing Shipment Delivery Installation Major production process - Manufactured house (Sekisui)
  • 14. ConceptsPart 2 : Promoting Industrialized Building Systems – Simplifying Construction
  • 15. ConceptsPart 2 : Promoting Industrialized Building Systems – Simplifying Construction
  • 16. UsagePart 2 : Promoting Industrialized Building Systems (IBS) – Simplifying Construction FIGURE 4.3 - Knowledge in Industrialised Building Systems (IBS) 34% 66% % GOOD % POOR “IBS Survey 2005 – Survey on the Malaysian Architects’ Experience in IBS Construction”.
  • 17. UsagePart 2 : Promoting Industrialized Building Systems (IBS) – Simplifying Construction “IBS Survey 2005 – Survey on the Malaysian Architects’ Experience in IBS Construction”. FIGURE 4.5 - Experience in Using IBS Components in Building Projects 30% 70% YES NO
  • 18. CharacteristicsPart 2 : Promoting Industrialized Building Systems – Simplifying Construction 5. Systematic Quality Control (ISO 9000 QMS) 2. Labour reduction 3. Modular Coordination - Open building concept 4. Modern design / manufacturing (ex.CAD/CAM) 1. Industrial production of components (prefab, precast under controlled environment) or highly mechanised in-situ processes (slip forms, etc.)
  • 19. 1. Precast Concrete framing, panel, box systems TypesPart 2 : Promoting Industrialized Building Systems – Simplifying Construction PC columns, beams, slabs, 3d-components (balconies, staircases, toilets, lift chambers, box girders, etc)
  • 20. 2. Steel formworks systems TypesPart 2 : Promoting Industrialized Building Systems – Simplifying Construction Tunnel forms, beams and column moulding forms, permanent steel formworks (metal decks), etc
  • 21. 3. Steel frame systems TypesPart 2 : Promoting Industrialized Building Systems – Simplifying Construction Steel beams and columns, portal frames, roof trusses, etc
  • 22. 4. Prefab timber frame systems TypesPart 2 : Promoting Industrialized Building Systems – Simplifying Construction Timber frames, roof trusses, etc
  • 23. 5. Block work systems TypesPart 2 : Promoting Industrialized Building Systems – Simplifying Construction Interlocking concrete masonry unit, lightweight concrete blocks, etc
  • 24. 1. Reduction of site labour 2. Minimal wastage 3. Less site materials 4. Cleaner environment 5. Controlled quality 6. Neater and safer sites 7. Faster project completion 8. Lower total construction costs due to the above BenefitsPart 2 : Promoting Industrialized Building Systems – Simplifying Construction
  • 25. Shorter construction period; if there is consistently large number of apartments to be constructed. Time Scale (Months) Precast System 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Production Foundation Concurrently done ( with 2 week lead time) Erection Finishing Mechanical & Electrical Infrastructure Testing & commisioning Handing Over Overall completion Period Conventional System 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Foundation Construction- superstructure Finishing Mechanical & Electrical Infrastructure Testing & commisioning Handing Over Overall completion Period 18 Month Completion 24 Month Completion Sumber :Setia Precast Sdn Bhd
  • 26.  Labour efficient through mechanisation, reduces 30% labour Sumber :Setia Precast Sdn Bhd
  • 27. IBS – Not A New Concept Concept of prefabrication started from the panellised timber houses (circa, 1624) shipped form England to the new settlements in America Ref: Salahuddin, 2001 HistoryPart 2 : Promoting Industrialized Building Systems – Simplifying Construction
  • 28. CIDB’s efforts in promoting IBS started since 1998 Earlier, concentrated on Awareness/Promotion/Training Early EffortsPart 2 : Promoting Industrialized Building Systems – Simplifying Construction
  • 29. However, usage of IBS in construction of buildings is still relatively very low if compared to infra works (bridges, tunnels, etc) Only 15% IBS in building (Ref: IBS Survey, 2003) Main Reason : Relatively cheap and abundant supply of foreign labour for Malaysian industry c.f. Labour cost in developed economies such as Finland - 10 times the rates in Malaysia (Ref: Gardiner & Theobald, 2002) UsagePart 2 : Promoting Industrialized Building Systems – Simplifying Construction
  • 30. Labour is cheap, so why IBS? • Because labour is not going to stay cheap and abundant forever and disruption to supply is catastrophic • Industry needs better productivity, quality and safety to be globally competitive • Move towards k-economy UsagePart 2 : Promoting Industrialized Building Systems – Simplifying Construction
  • 31. UsagePart 2 : Promoting Industrialized Building Systems – Simplifying Construction IBS components are expensive, so why IBS? • True. The components cost higher than conventional, but in-situ construction has hidden costs that usually lead to higher expenditure; due to rectifications, wastages, etc • IBS components currently cost higher because: Low demand Low standardisation of components (moulds need to custom made or adjusted to suit orders)
  • 32. Part 3 : The Way Forward- The IBS RoadMap 2003-2010
  • 33. THE WAY FORWARD IS TO INDUSTRIALISE CONSTRUCTION INDUSTRY THROUGH COMPONENTS INDUSTRY BUILT-IN COMPONENTS STRUCTURAL COMPONENTS RAILING COMPONENTS DOOR COMPONENTS WINDOW COMPONENTS Ref: JKR, 2003
  • 34. Standardisation/ CoordinationPart 3 : The Way Forward To facilitate open industrialization, coordination is needed in terms of : Dimensions Tolerance Joints and details Technical compatibility
  • 35. Vendors, manufacturer IBS - HOLLISTIC APPROACH Contractor, assemblers, fabricators Designers, (architects, engineers) Client/Asset manager IBS Component Catalogues Design Guides Standardisation/ CoordinationPart 3 : The Way Forward
  • 36. MS 1064 : 2001 :GUIDE TO MODULAR COORDINATION IN BUILDINGS PART 1: General Principles PART 2: Storey and Room Heights PART 3: Coordinating Sizes and Preferred Dimensions for Stairs and Stairs Opening PART 4: Coordinating Sizes and Preferred Dimensions for Doorsets PART 5: Coordinating Sizes and Preferred Dimensions for Windowsets PART 6: Coordinating Sizes and Preferred Dimensions for Rigid Flat Sheet PART 7: Coordinating Sizes and Preferred Dimensions for Tiles PART 8: Coordinating Sizes and Preferred Dimensions for Masonry Bricks and Blocks PART 9: Coordinating Sizes and Preferred Dimensions for Cabinets PART 10: Coordinating Sizes and Preferred Dimensions for RC Components Gazetted oct. 2002Gazetted oct. 2002 Publication Materials
  • 37. Based on MS1064, MC coordinates the positions, dimensions of components and spaces in building designs Base module : M = 100mm Modular Coordination (MC)Part 3 : The Way Forward Modularisation MS 1064
  • 38. New Strategies New Strategies on IBS & MC needed to promote industrialisation; Enforcement & Incentives in addition to Awareness/Promotion/Training Main target – housing sector (repetitive, high volume) Part 3 : The Way Forward
  • 39. “Closed System” mass - production one end product etc. Mula-mula: Projek Kemudian: Sistem Bekalan: Syarikat tertentu First a project Then a system Always third party supply Current ScenarioPart 3 : The Way Forward
  • 40. “Open System” DESIGN GUIDE CATALOGUE etc. ? ? First a system Then many projects Open supply Future ScenarioPart 3 : The Way Forward
  • 41. IBS Roadmap 2003-2010Part 3 : The Way Forward 5. Marketing/Promotion 2. Materials/Components/Machines 1. Manpower 3. Management/Process/Methods 4. Monetary/Economic/Financial Formulation of Roadmap based on FIVE main elements
  • 42. • To have a labour policy that gradually reduces PERCENTAGE OF FOREIGN WORKERS from the current 75% to 55% in 2005, 25% in 2007 and 15% in 2009. • To incorporate IBS in CPD courses for architects, engineers and others. • To incorporate SYLLABUS ON IBS in architecture, engineering, building courses in IPTs. Key Elements of RoadmapThe Way Forward (MANPOWER)
  • 43. • Continue efforts to develop NOSS ( National Occupational Skill Standards). • Continue Workers training and certification programme to include all types of IBS. • Commence the training programme on mould making for IBS components. • Commence the industrial expertise awareness programme together with IBS manufacture through on-job training for trainees. Key Elements of RoadmapThe Way Forward (MANPOWER)
  • 44. • Commence the site supervisory training and certification programme which includes knowledge on IBS • To start BUMIPUTERA IBS MANUFACTURERS AND SPECIALISED CONTRACTORS training and financial aid Key Elements of RoadmapThe Way Forward (MANPOWER)
  • 45. • Enforce the use of Modular Coordination based on MS 1064 through Uniformed Building By Laws (UBBL) by local authorities. • Continue publishing reference books and case study reports regarding IBS. • Continue writing new Malaysian Standards (MS) covering all types of IBS. • Continue writing new Construction Industry Standards (CIS). Key Elements of Roadmap The Way Forward (MATERIALS)
  • 46. • Develop software for MC components and dimensioning. • Include the IBS/MC knowledge into the standards of practice and training modules for the training and certification of Project Manager. Key Elements of Roadmap The Way Forward (MANAGEMENT)
  • 47. • Offer specialised contractors training and certification programmes to cater for IBS related registration codes. • Continually update the website to disseminate information on IBS, MC and OBS. Key Elements of Roadmap The Way Forward (MANAGEMENT)
  • 48. • Enforce IBS usage in government (building) projects in phases (from 30% in 2004 to 70% in 2008). • Offer levy exemptions from 2004 for low cost, low medium cost and medium cost housing projects. • Offer training schemes and financial loans for manufacture and contractors. Key Elements of Roadmap The Way Forward (MONETARY)
  • 49. • Introduce Buildability Programme beginning 2006 for private (building) projects and enforcing it through the local Authorities in 2008. • Use IBS construct 30% of the 150,000 units of houses proposed to be built by Syarikat Perumahan Negara Berhad under the 2003 Economy Stimulus Packages. Key Elements of Roadmap The Way Forward (MONETARY)
  • 50. • Publish IBS product catalogues. • Continue IBS/MC road show programmes at the national and international levels. • Establish IBS as the main criteria for Malaysian Construction Industry Excellence Awards. • Introduce concept of Open building Systems to the industry. Key Elements of Roadmap The Way Forward (MARKETING)
  • 51. 2005 Budget:2005 Budget: 1. Directives:1. Directives: - Govt building projects- Govt building projects ≥≥ 50% IBS Score50% IBS Score - 100,000 affordable houses using IBS- 100,000 affordable houses using IBS 2. Incentive:2. Incentive: - Zero levy for residential projects- Zero levy for residential projects ≥≥ 50% IBS50% IBS ScoreScore Budget 2005Part 3 : The Way Forward
  • 52. IBS ScoringPart 3 : The Way Forward • Part 1 – Structural Element (50%) • Part 2 – Wall Element (30%) • Part 3 – Other Simplified Solution (20%)
  • 53. Case StudiesCase StudiesPart 4 : Case StudiesCase Studies
  • 54. SJK(C) DAMANSARA PETALING JAYA SELANGOR DARUL EHSAN Case StudiesCase StudiesPart 4 : Sumber : JKR
  • 55. PROJECT DETAILS Cabinet’s directive - 31Januari 2001 school to be completed in 2001 – 8 months •project site : 2 .1 hectares •possession of site : 1 February 2001 •completion : 31 July 2001 •construction period : 5 1/2 months FEB 2001 Earth worksFEB - MAC 2001 Piling works Case StudyPart 4:
  • 56. Ground level MAC 2001 MAC 2001 Level 1 •Fast track project using prefabricated components •Beams, floor slabs (half slabs with concrete topping) and staircases were prefabricated in the factory, wall panel are hollow blocks •Columns and toilets were cast in-situ
  • 57. Roof level APR - MEI 2001 External works MAC - APRIL 2001 Level 2 APRIL - MEI 2001 Level 3
  • 59. Case StudiesPart 4 :  IBS STRUCTURE: “HOLLOWCORE” SLABS; PRECAST CONCRETE COLUMNS & BEAMS  9,900 m2, 4 FLOORS  COMPLETION IN 8 MONTHS CASE STUDY 8 : SCHOOL SEK. KEB. BRICKFIELDS 1, KUALA LUMPUR
  • 60. PROJECT DETAILS a compact design to house two schools in a total site area of 48,220 sq.ft. •start of project : 6 February 2003 •completion : 17 Sept. 2003 •construction period : 7 1/2 months
  • 61. • project constraints – limited site, busy access, short construction period • 75 % of building components were prefabricated • Prefab components used – columns, beams, hollow core floor slabs, staircases, wall panels (Acotech panels) • Architectural features – bright façade, cascading roofs with large overhangs, internal pockets of large and small courtyards installation of precast column installation of first floor slab on 02.05.03
  • 62. installation of 3rd floor slab on 28.05.03 installation of precast staircases fixing of wall panel completion of external wall on 16.07.03
  • 63. in 2001 – new design alternatives for all categories of government quarters were initiated NEW DESIGN FOR GOVERNMENT QUARTERS •application of modular coordination • use of building components • flexibility and creativity in design and the concept of sustainable design • standardised components for interchangeability between designs
  • 64. Projek Akademi Audit Negara, Nilai, NS Krtrs kelas F & G – load bearing design, precast wall, slab, column & beam
  • 65. Projek Akademi Audit Negara, Nilai, NS
  • 66. Projek Balai Polis, Senawang, NS frame system : cast-in-situ column & beam, precast infill wall & slab Krtrs kelas F Krtrs kelas G
  • 67. Projek Balai Polis, Senawang, NS
  • 68. Projek Balai Polis, Senawang, NS
  • 69. Case StudiesPart 4 :  KEDAH STATE GOVERNMENT  IBS STRUCTURE: “HOLLOWCORE” SLABS; PRECAST CONCRETE COLUMNS & BEAMS  25,500 m2, 3 FLOORS  STRUCTURAL CONSTRUCTION: 4 MONTHS CASE STUDY 1 : COMMUNITY COMPLEX DEWAN WAWASAN, KUBANG PASU, KEDAH
  • 70. Case StudiesPart 4 :  PENANG STATE GOVERNMENT  IBS STRUCTURE: “HOLLOWCORE” SLABS; PRECAST CONCRETE COLUMNS & BEAMS  7,500 m2, 4 FLOORS  STRUCTURAL CONSTRUCTION: 2 MONTHS CASE STUDY 2 : COMMUNITY COMPLEX DEWAN MILENIUM, KEPALA BATAS, PULAU PINANG
  • 71. Case StudiesPart 4:  MAJLIS PERBANDARAN PPINANG  IBS STRUCTURE: “HOLLOWCORE” SLABS; PRECAST CONCRETE COLUMNS, BEAMS & BLEACHERS  6,000 m2, 3 FLOORS  STRUCTURAL CONSTRUCTION: 2 MONTHS CASE STUDY 3: STADIUM BALIK PULAU INDOOR STADIUM, PULAU PINANG
  • 72. Case StudiesPart 4 :  IBS STRUCTURE: METAL FORMWORKS FOR WALLS, SLABS, BEAMS & COLUMNS  TWO 26-30 STOREY TOWERS (APARTMENTS & OFFICES)  STRUCTURAL CONSTRUCTION: 6 MONTHS CASE STUDY 4 : RESIDENTIAL & OFFICE NORTHAM CITY, PULAU PINANG
  • 73. Case StudiesPart 4:  IBS STRUCTURE: LIGHTWEIGHT BLOCKS & PRECAST CONCRETE WALLS; PRECAST CONCRETE SLABS  10,000 UNITS, 4-5 STOREY  109 LOCATIONS IN 9 STATES  COMPLETION IN 3 YEARS CASE STUDY 6 : QUARTERS TEACHERS QUARTERS, ALL OVER MALAYSIA
  • 74. Case StudiesPart 4 :  CIDB MALAYSIA  IBS STRUCTURE: PRECAST CONCRETE SLABS, BEAMS, COLUMNS & WALLS  9,600 m2, 6 WORKSHOP BLOCKS  STRUCTURAL CONSTRUCTION: 3 MONTHS CASE STUDY 7 : TRAINING CENTRE AKADEMI BINAAN MALAYSIA, SINTOK, KEDAH
  • 75. Case StudiesPart 4 :  MINISTRY OF HEALTH  620-BED HOSPITAL  HYBRID IBS STRUCTURE OF STEEL FRAMES; PRECAST CONCRETE SLABS; LIGHTWEIGHT CONCRETE BLOCKS FOR WALLS  130,000 m2, 9 FLOORS  STRUCTURAL CONSTRUCTION: 4 MONTHS CASE STUDY 9 : MEDICAL CENTRE HOSPITAL SERDANG, SELANGOR
  • 76. Case StudiesPart 4 :  IBS STRUCTURE: “SOLID” & “HOLLOWCORE” SLABS; PRECAST CONCRETE WALLS, STAIRCASES, GUTTERS, BEAMS & COLUMNS  121,000 m2, 4 FLOORS, 2 BASEMENTS  STRUCTURAL CONSTRUCTION: 4 MONTHS CASE STUDY 10 : SHOPPING COMPLEX IKEA MUTIARA DAMANSARA, SELANGOR
  • 77. Case StudiesPart 4 :  IBS STRUCTURE: PRECAST CONCRETE SLABS, WALLS & STAIRCASES  756 UNITS, 6 BLOCKS, 8-16 FLOORS  CONSTRUCTION: 18 MONTHS CASE STUDY 11 : RESIDENTIAL APARTMENTS, PRECINCT 9, WP PUTRAJAYA
  • 78. IBS ROADMAP 2003-2010: towards labour reduction and better productivity,quality, safety & environment; reducing total industry costs THUS INCREASING THE INDUSTRY COMPETITIVENESS Conclusion