SlideShare a Scribd company logo
1 of 53
Download to read offline
B L O C K W O R K
B U I L D I N G T E C H N O L O G Y
C O N T E N T S
I N T R O D U C T I O N
1.1 Introduction to IBS system
1.2 Types of IBS in Malaysia
1.3 Standard Workflow IBS System
1.4 Malaysia Blockwork System
1.5 Case Study
C O N C E P T O F F R A M E W O R K
2.1 Propose IBS System
2.2 Construction Sequences
T E C H N I C A L D R A W I N G S
3.1 Foundation
3.2 Slab
3.3 Plans
3.4 Block Work Plans
3.5 Roof Plans
3.6 Elevations
3.7 Sections
3.8 Axonometric
S C H E D U L E O F I B S C O M P O N E N T S
4.1 Door
4.2 Windows
4.3 Block Components
4.4 Slab
4.5 Roof Truss Components
4.6 Staircase Components
C O N S T R U C T I O N D E T A I L
& P R O C E S S
5.1 Strip Footing
5.2 Blockwork System
5.3 Slab System
5.4 Staircase System
5.5 Roof truss System
5.6 Windows System
I B S C A L C U L A T I O N
C O N C L U S I O N S
R E F E R E N C E S
I N T R O D U C T I O N
1.1 Introduction to IBS system
Industrialized Building System (IBS) is a construction technique whereby building components are manufactured in factories then transported and assembled into a structure
with limited on site work. The benefits of IBS are clear and eminent as it allows for building to be constructed in a shorter time span and with greatly reduced activities at the con-
struction site, which in turn provides tremendous cost savings to the builders. Furthermore, The IBS construction method can reduce wastage of resources besides providing
good quality results for consumers.
The use of IBS in Malaysia started in 1963. However, although it has been four decades since the introduction of IBS in Malaysia, the application and adoption of this method in
the local construction industry, particularly in the private sector, is still relatively low compared to the developed countries. This was despite the perennial problems besetting
traditional construction methods which include: time delay, Â cost overrun, and waste generation.
the government started major projects using the IBS system in 1964. Their main objective was to accelerate the completion of the projects on time besides being able to con-
struct affordable housing units of substantial quality. Projects along the Jalan Pekeliling (figure 1.1a) high rise apartment, Kuala Lumpur which were as wide as 22.7 acres includ-
ed the construction of 7 blocks of flats of 17-storeys each encompassing 3,000 low-cost flats and 40 shop lots.Other megastructure projects that involved using industrialised
building system such as Petronas Twin Tower( figure 1.1.b) and Bukit Jalil Sport Complex(figure 1.1.c)
01
I N T R O D U C T I O N
1.2 Types of IBS in Malaysia
Precast Concrete System
Precast concrete system is the group that is most
widely used in the IBS system. The form of the con-
crete usually prepared, cast and cured off-site Pre-
cast concrete elements can be joined to other ele-
ments to form a complete structure.
Timber Framing System
This system involves prefabricated timber truss
beams and columns. Most of the products listed in
this category are wooden building frames and roof
trusses. It is quite popular and widely applicable as
it provides attractive designs and has high aesthetic
values.
Block work System
Blocks work system exists as one of the type of IBS
because of the revolutionary of construction method
of using conventional bricks with the usage of inter-
locking concrete masonry units (CMU) and light-
weight concrete blocks.
Innovative System
This is the latest IBS type which incorporates vari-
ous “green” elements, which are considered innova-
tive in the industry. An example of the innovation is
the mixture of two elements such as polystyrene
and concrete, to produce IBS components for use in
the construction of a wall which has better heat
insulation properties.
Steel Framing System
Steel Framing System consists of load-bearing and
non-load bearing wall system, composite floor slab
construction that built with a series of high tensile
galvanised cold formed c-sections as well as portal
frame system.
Steel Formwork System
Identified as one of the least prefabricated types of
the IBS, it generally involves concrete at the con-
struction site and high quality control. This includes
the "tunnel form", the"lilt-up" beam system, "mould-
ing form" columns and a permanent steel mould.
02
I N T R O D U C T I O N
1.3 Standard Workflow IBS System
Design Consideration
The important components that needs to
be given consideration in the process of
production and assembly of any buildings
using IBS. Its components are initially
design according to Malaysia stan-
dards(1064) to reduce customising cost
and time.
Production Line
Building Materials are manufactured and
produced in specification or standardise
dimension with proper quality control in
factories. It minimises waste of materials
of product on site.
Transportation Materials
IBS manufacture components are prefab-
ricated and deliver to the site according to
the amount and specification needed.
The time efficient of labour work reduce
due to the manufacturing and delivering
period.
Assembling and Completion
The materials and components are direct-
ly assemble and position onto the struc-
ture building with guidance from profes-
sionals. The completion of the building is
then plastered and coated according to
specification of the schedule.
03
I N T R O D U C T I O N
1.4 Malaysia Blockwork System
Type of Blockwork System in Malaysia Manufacturing Process
The construction method of using conventional bricks has been revolutionised by the development and usage of interlocking concrete masonry units (CMU) and lightweight con-
crete blocks. The blocks are commonly produced by hydraulic machinery which presses them in the steel moulds with the presence of vibration to compact the blocks. The Pres-
ent of Blockwork methods are greatly simplified with reinforcement methods such as steel rods that are embedded inside the block and with the use of steel plate, bolts and nuts
placed on the top of the blocks to make the blocks fixed in position.
Advantages
- The casting of concrete can be done in the working site which makes it economi-
cal.
-The presence of dead air trapped in the cavities of CMU provides natural thermal
insulation.
-CMU makes a building fire-safe due to its noncombustible nature.
-Ingredients of Blockwork materials are easily available in most places.
Advantages Disadvantages
- Compared to other binding materials, the tensile strength of concrete is relatively
low.
- Rise in labour cost work with the increase workforce due to the construction meth-
ods.
- Does not has high compressive strength and weak without reinforcement or rebar
install.
- Concrete may contains soluble salts. Soluble salts cause efflorescence.
Concrete Block Unit
A concrete block is
sometimes known as
concrete masonry
unit (CMU), they can
be solid or hollow and
is available in many
shapes and sizes.
Concrete Blocks are
used for engineering
and architectural
purposes.
Lightweight Block
A lightweight con-
crete block is an
engineering control
that may help reduce
heavy lifting and
carrying. The light-
weight concrete
block is a concrete
masonry unit (CMU)
made of expanded
aggregate to reduce
the density and
weight
Interlocking Block
Interlocking brick is
more convenient for
builders without
experience and skill
set is not a constraint
for this material,
many developing
countries in south-
east asia (SEA) such
as Cambodia, Viet-
nam are popular due
to its workability and
low cost.
Ventilation Block
Ventilation Blocks
promote natural light-
ing and ventilation at
any commercial or
residential project. It
is often used for the
construction of wall
features, screen
walls, partitions for
building facades,
stairwells and
multi-level car parks.
Mixing
After the materials
are measured, they
are dumped into the
mixer to process.
Molding
Then batch of materi-
als are pour into the
molding machine and
compress to its
shape.
Curing
The pallets are then
moved to carts which
travel into a low-pres-
sure steam kiln which
are then to be
heated.
Cubing and Storing
When curing is com-
plete, They move on
to our cubing system
which stacks the
blocks on a wood
pallet.
04
I N T R O D U C T I O N
1.5 Case Study : Sekolah Kafa Integrasi Al-mubarak
Sekolah Kafa Integrasi Al-mubarak is an islamic primary school built by Aras Reka Arkitek and completed in year
2010. The school has funded by government PKNS, it has three stories with six classroom including, one faculty office,
multi-purpose room and a canteen. The building materials are all comprises of concrete masonry blocks, which are
also part of the erection of columns and walls. The blockworks from this building, which have more lighter weight and
designed to be a high quality alternative to conventional construction methods by replacing common bricks & cast in-si-
tu reinforced concrete structure.
Construction Methods
Firstly, site construction begins with concrete infill with reinforcement, then the curing method is apply on the concrete slab after the concrete foundation is dry, concrete
bearing wall and columns blocks started to erect. After the blockwork structure was erected the Prefabricated roof system was installed, other components such as
doors, walls and ceilings are place in.
Case study: Institution (Sekolah Kafa Integrasi
Al-mubarak)
Architect: Aras Reka Arkitek
IBS system: Load-bearing Blockwork System
IBS Supplier: Zenbes sdn.bhd
Main Components: Concrete Masonry Unit
(CMU)
Other Components: Precast Concrete foun-
dation
Blockwork components:
-Load-bearing CMU wall
-Concrete Masonry Unit bond beam
-Concrete Masonry Unit stiffener
Structural Components:
-Reinforcement Concrete foundation
-Precast concrete slab( precast off-site)
Other components:
-Prefabricated roof truss
-Door and windows
05
I N T R O D U C T I O N
1.5 Case Study : Permata Pintar Auditorium
Permata pintar Auditorium and Sports Park are located on 20.15 acres in the University Kebangsaan Malaysia
campus in Bangi, Selangor. The main feature of the auditorium is the capability to include 600 person in the auditorium
hall, primarily catering to lectures, convocations, and the school’s musical theatre programmes. The back of house
serves as a dressing room and rehearsal area, with VIP seating located at the second tier. The extended auditorium
foyer generates a new public space, linking the plaza with visible meeting points.
Construction Methods:
Firstly, site excavation begins on the area along with landscaping construction. Foundation is infill with reinforcement and concrete. After rafter foundation, steel struc-
ture framing was created on the outside, follow-up by installing blockwork system interior of the building. Aluminium cladding were added along the skin of the building.
Precast structure were installed together with landscaping work.
Case study: Permata Pintar auditorium, UKM
Architect: GDP Architect
IBS system: Load-bearing Blockwork System
IBS Supplier: Zenbes sdn.bhd
Main components: Concrete Masonry Unit(C-
MU)
Other components: Aluminium cladding, Steel
structure,
Precast concrete Foundation
Blockwork Components:
-Concrete Masonry Unit block Hollow
-Concrete Ventilation block
-Concrete Masonry Unit bond beam
-Concrete Masonry Unit stiffener
Structural Components
-precast concrete foundation
-precast concrete staircase
Other components:
-aluminium cladding
-metal roof structure
06
C O N C E P T O F F R A M E W O R K
2.1 Propose IBS System
07
The following structure and materials that have been selected based on the of IBS system that are used in the design of the three stories apartment. This components comprises
prefabricated structure, blockwork system, cast-in situ (concrete) and precast concrete components. The main components comprises of blockwork CMU and accommodated
with structure components, which form a hybrid system.
01 Foundation
Cast-in SITU concrete
-Concrete foundation
Precast components 02
Precast concrete Components
-Hollow core slab(Custom Size)
-Precast concrete staircase
Blockwork 04
Blockwork Components
-Blockwork concrete (CMU)
03 Prefabricated components
Cast-in SITU concrete
-steel roof trusses
-Windows and doors
-railing
C O N C E P T O F F R A M E W O R K
2.2 Construction Process
08
01 Foundation
The strip foundation stage is cast in
place by pouring concrete foundation
on the excavate trench till the ground
level. Blockworks is partially built verti-
cally till the ground level.
Concrete Slab 02
After the strip foundation is done in
place, concrete is poured on the
ground floor to form concrete slab.
Cement is screed throughout the area
and leave it to dry.
Continuation of Blockwork 04
The continuation of blockworks are
then being lay out vertically through-
out the ground area until window level.
Windows are installed and the pro-
cess continues.
03 Door and Walls
The built up of concrete blockwork
around the apron is set together with
door frame. As the concrete block
build vertically mortar is infill along the
concrete block.
C O N C E P T O F F R A M E W O R K
2.2 Construction Process
09
05 Lintel and Staircase
Blockworks are continue to built to the
lintel level. Precast lintels are placed
on top of windows and doors. Precast
concrete staircases are installed
throughout the ground floor.
Beam 06
Bond Beams are layered and connect
on top of the wall’s infill with cement
and reinforce with reinforcement bars.
Slabs will be place on top of the
beams afterwards.
Assembling First Floor 08
The construction steps of first floor
begin from no. 4 to no. 7. These steps
are the repeat process from ground
floor.
07 Hollowcore Slabs
After the placement of the beam.
which is the last component to be
assemble on ground floor, hollowcore
slabs are installed on top of the beams
covering the whole first floor.
C O N C E P T O F F R A M E W O R K
2.2 Construction Process
10
09 Assemble Second Floor
The construction steps of second floor
begin from no. 5 to no. 7. Gypsum ceil-
ings are place after the installation of
the roof truss.
Installation Roof Truss 10
Prefabricated roof trusses are
installed on top of the second floor
wall. Purlins are horizontally place on
the roof trusses.
11 Completion
Pitch roof is place on top of the roof
trusses as final construction process.
Interior and exterior work are execut-
ed with mechanical and electrical
work, lighting tiles layering and wall
coating.
T E C H N I C A L D R A W I N G S
3.1 Foundation | Strip Foundation | 1:75
11
A B C D E F G H I
1234
20800
6000 3000
6005 1500 1500
2800
1500 1500
9000
3000 3000 2800
9000
2400
30001200
42002400
T E C H N I C A L D R A W I N G S
3.2 Slab | Ground Floor Plan | 1:75
12
A B C D E F G H I
1234
20800
6000 3000
6005 1500 1500
2800
1500 1500
9000
3000 3000 2800
9000
2400
30001200
42002400
T E C H N I C A L D R A W I N G S
3.2 Slab | First & Second Floor Plan | 1:75
13
A B C D E F G H I
1234
20800
6000 3000
6005 1500 1500
2800
1500 1500
9000
3000 3000 2800
9000
2400
30001200
42002400
T E C H N I C A L D R A W I N G S
3.3 Plans | Ground Floor Plan | 1:75
14
UP
MASTER
BEDROOM
A B C D E F G H I
1234
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
9000
2400
30001200
41982400
YARD
DINING AREA
BEDROOM 1
LIVING ROOMBEDROOM 2
LAUNDRY
FFL+0.20 FFL+0.25 FFL+0.25
FFL+0.25FFL+0.25
FFL+0.25FFL+0.25
FFL+0.20
FFL+0.20
BATH
BATH
7.2SQM 7.2SQM
9.0SQM9.0SQM
7.2SQM 7.2SQM 7.2SQM
KITCHEN
50dp
3.6SQM
50dp 50dp
100dp
50dp
GF
T E C H N I C A L D R A W I N G S
3.3 Plans | First Floor Plan | 1:75
15
DNUP
A B C D E F G H I
1234
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
9000
2400
30001200
41982400
MASTER
BEDROOM
YARD
DINING AREA
BEDROOM 1
LIVING ROOMBEDROOM 2
LAUNDRY
FFL+0.20 FFL+0.25 FFL+0.25
FFL+0.25FFL+0.25
FFL+0.25FFL+0.25
FFL+0.20
FFL+0.20
BATH
BATH
7.2SQM 7.2SQM
9.0SQM9.0SQM
7.2SQM 7.2SQM 7.2SQM
KITCHEN
50dp
50dp 50dp
3.6SQM
50dp
1F
T E C H N I C A L D R A W I N G S
3.3 Plans | Second Floor Plan | 1:75
16
DN
A B C D E F G H I
1234
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
9000
2400
30001200
41982400
MASTER
BEDROOM
YARD
DINING AREA
BEDROOM 1
LIVING ROOMBEDROOM 2
LAUNDRY
FFL+0.20 FFL+0.25 FFL+0.25
FFL+0.25FFL+0.25
FFL+0.25FFL+0.25
FFL+0.20
FFL+0.20
BATH
BATH
7.2SQM 7.2SQM
9.0SQM9.0SQM
7.2SQM 7.2SQM 7.2SQM
KITCHEN
50dp
50dp 50dp
50dp
2F
3.3 Plans | Second Floor Plan | 1:75
T E C H N I C A L D R A W I N G S
3.4 Blockwork Plans | Ground Floor Plan | 1:75
17
A B C D E F G H I
1234
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
9000
2400
30001200
41982400
UP
T E C H N I C A L D R A W I N G S
3.4 Blockwork Plans | First Floor Plan | 1:75
18
A B C D E F G H I
1234
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
9000
2400
30001200
41982400
DNUP
T E C H N I C A L D R A W I N G S
3.4 Blockwork Plans | Second Floor Plan | 1:75
19
A B C D E F G H I
1234
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
9000
2400
30001200
41982400
DN
T E C H N I C A L D R A W I N G S
3.5 Roof Plans | Structure Plan | 1:75
20
A B C D E F G H I
1234
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
9000
2400
30001200
42002400
T E C H N I C A L D R A W I N G S
3.5 Roof Plans | Structure with Batten Plan | 1:75
21
A B C D E F G H I
1234
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
9000
2400
30001200
42002400
T E C H N I C A L D R A W I N G S
3.5 Roof Plans | 1:75
22
A B C D E F G H I
1234
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
9000
2400
30001200
42002400
T E C H N I C A L D R A W I N G S
3.6 Elevations | Front | 1:75
23
A B C D E F G H I
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
►(FFL -200) STRIP FOOTING
►(FFL +0) GROUND LEVEL
►(FFL +9.6) ROOF LEVEL
►(FFL +6.4) SECOND FLOOR
►(FFL +3.2) FIRST FLOOR
T E C H N I C A L D R A W I N G S
3.6 Elevations | Front with Finishing | 1:75
24
A B C D E F G H I
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
►(FFL -200) STRIP FOOTING
►(FFL +0) GROUND LEVEL
►(FFL +9.6) ROOF LEVEL
►(FFL +6.4) SECOND FLOOR
►(FFL +3.2) FIRST FLOOR
T E C H N I C A L D R A W I N G S
3.6 Elevations | Back | 1:75
25
A B C D E F G H I
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
►(FFL -200) STRIP FOOTING
►(FFL +0) GROUND LEVEL
►(FFL +9.6) ROOF LEVEL
►(FFL +6.4) SECOND FLOOR
►(FFL +3.2) FIRST FLOOR
T E C H N I C A L D R A W I N G S
3.6 Elevations | Back with Finishing | 1:75
26
A B C D E F G H I
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
►(FFL -200) STRIP FOOTING
►(FFL +0) GROUND LEVEL
►(FFL +9.6) ROOF LEVEL
►(FFL +6.4) SECOND FLOOR
►(FFL +3.2) FIRST FLOOR
3.6 Elevations
T E C H N I C A L D R A W I N G S
3.6 Elevations | Side & Side with Finishing | 1:75
27
1234
9000
240041982400
1234
9000
240041982400
►(FFL -200) STRIP FOOTING
►(FFL +0) GROUND LEVEL
►(FFL +9.6) ROOF LEVEL
►(FFL +6.4) SECOND FLOOR
►(FFL +3.2) FIRST FLOOR
T E C H N I C A L D R A W I N G S
3.7 Sections | A-A & B-B | 1:75
28
1234
9000
240042002400
1234
9000
240042002400
►(FFL -200) STRIP FOOTING
►(FFL +0) GROUND LEVEL
►(FFL +9.6) ROOF LEVEL
►(FFL +6.4) SECOND FLOOR
►(FFL +3.2) FIRST FLOOR
T E C H N I C A L D R A W I N G S
3.7 Sections | C-C | 1:75
29
A B C D E F G H I
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
►(FFL -200) STRIP FOOTING
►(FFL +0) GROUND LEVEL
►(FFL +9.6) ROOF LEVEL
►(FFL +6.4) SECOND FLOOR
►(FFL +3.2) FIRST FLOOR
T E C H N I C A L D R A W I N G S
3.7 Sections | D-D | 1:75
30
A B C D E F G H I
20800
6000 3000
6000 1500 1500
2800
1500 1500
9000
3000 3000 2800
►(FFL -200) STRIP FOOTING
►(FFL +0) GROUND LEVEL
►(FFL +9.6) ROOF LEVEL
►(FFL +6.4) SECOND FLOOR
►(FFL +3.2) FIRST FLOOR
T E C H N I C A L D R A W I N G S
3.8 Axonometric
31
S C H E D U L E O F I B S C O M P O N E N T S
4.1 Door
32
900 800
2100
2100
D3 D2TYPE
SIZE
DESCRIPTION
LOCATION
TOTAL NO. REQ
TOTAL NO. REQ
900mm (W) x 2100mm (H) 800mm (W) x 2100mm (H)
BATHROOMDINING, LIVING ROOM, BEDROOM 1, MASTER BEDROOM
BATHROOM
BATHROOM
DINING, LIVING ROOM, BEDROOM 1, MASTER BEDROOM
DINING, LIVING ROOM, BEDROOM 1, MASTER BEDROOM
Grd. Flr.
1st. Flr.
2nd. Flr.
SOLID TIMBER H.W. WITH VENEER AND VARNISH TO MANUF'S
DETAIL
SOLID TIMBER H.W. WITH VENEER AND VARNISH TO MANUF'S
DETAIL
S C H E D U L E O F I B S C O M P O N E N T S
4.2 Windows
33
600 2400 1200
1800
1800
600
1800
2400
600
2400
600
2400
W1 W2 W3TYPE
SIZE
DESCRIPTION
LOCATION
600mm (W) x 600mm (H) 2400mm (W) x 1800mm (H) 1200mm (W) x 1800mm (H)
Grd. Flr.
1st. Flr.
2nd. Flr.
BATHROOM DINING, LIVING ROOM, BEDROOM 1, MASTER BEDROOM
BATHROOM
BATHROOM
DINING, LIVING ROOM, BEDROOM 1, MASTER BEDROOM
DINING, LIVING ROOM, BEDROOM 1, MASTER BEDROOM
BEDROOM 2
BEDROOM 2
BEDROOM 2
DARK BROWN POWDER COAL WITH ALUM. FRAME TOP HUNG
STAINED GREY, FROSTED WINDOW ABOVE FIXED WITH GREY
FROSTED STAINED GLASS BELOW TO MANUF'S DETAIL
DARK BROWN POWDER COAL WITH ALUM. FRAME TOP HUNG
STAINED GREY, FROSTED WINDOW ABOVE FIXED WITH GREY
FROSTED STAINED GLASS BELOW TO MANUF'S DETAIL
DARK BROWN POWDER COAL WITH ALUM. FRAME TOP HUNG
STAINED GREY, FROSTED WINDOW ABOVE FIXED WITH GREY
FROSTED STAINED GLASS BELOW TO MANUF'S DETAIL
LOCATION
S C H E D U L E O F I B S C O M P O N E N T S
4.3 Block components
34
TYPE OF BLOCK
SIZE
STRETCHER BOND BEAM EDGE BLOCK
200mm (W) x 200mm (H) x 400mm (L) 100mm (W) x 200mm (H) x 400mm (L) 200mm (W) x 200mm (H) x 400mm (L)
S C H E D U L E O F I B S C O M P O N E N T S
4.4 Slab
35
SLAB 1 SLAB 2 SLAB 3TYPE OF SLAB
LOCATION
Grd. Flr.
1st. Flr.
2nd. Flr.
SIZE 1500mm (W) x 200mm (H) x 2400mm (L) 1500mm (W) x 250mm (H) x 4200mm (L) 1400mm (W) x 250mm (H) x 3000mm (L)
BATHROOM, YARD, LAUNDRY DINING, LIVING ROOM, MASTER BEDROOM, BEDROOM 1,2
BATHROOM, YARD, LAUNDRY
BATHROOM, YARD, LAUNDRY
1500mm (W) x 250mm (H) x 2400mm (L)
DINING, LIVING ROOM, MASTER BEDROOM, BEDROOM 1,2
DINING, LIVING ROOM, MASTER BEDROOM, BEDROOM 1,2
BALCONY (STAIRCASE)
BALCONY (STAIRCASE)
BALCONY (STAIRCASE)
S C H E D U L E O F I B S C O M P O N E N T S
4.5 Roof Truss Components
36
TYPE OF ROOF TRUSS TRUSS 3 TRUSS 5TRUSS 4 TRUSS 6
TYPE OF ROOF TRUSS TRUSS 1 TRUSS 2
S C H E D U L E O F I B S C O M P O N E N T S
4.6 Staircase Components
37
STAIRCASE COMP. ST 1 ST 2 ST 3
RISER : 200 x THREAD : 250 4239mm x 1000mm 2600mm x 4250mm
C O N S T R U C T I O N D E T A I L & P R O C E S S
5.1 Strip Footing
38
Construction Methods: Cast-in SITU
Construction Components: Strip Foundation(concrete)
Installation Process
Cast-in SITU
It refers to work which is carried out on the construction site itself, often in the finished position. The purpose components are to be cast on site using concrete materials such
as piles or footing.
Strip Foundation
Strip foundation are a type of shallow foundation that are used to provide a continuous, level (or sometimes stepped) strip of support to a linear structure such as a wall or close-
ly-spaced rows of columns built centrally above them.
1.The process involves digging out trenches
around the perimeter of the build-up area.
3.Concrete is then poured in until it reaches just
below ground level.
3.Concrete is then poured in until it reaches just
below ground level.
2.Formwork and rebars are produced before the
concrete is poured into it to form the strip footing.
The footings are installed around the foundation
level.
C O N S T R U C T I O N D E T A I L & P R O C E S S
5.1 Strip Footing | Detail Drawings
39
WATERROOFING
TO SPECS
Screed
Blockwork
Skin Coat
OUTDOOR SELECTED FLOOR TILES
TO SPECS. W/ APPROVED
POINTING & ADHESIVE
Concrete Slab
FALL
TO
FT/
FW
BULL NOSED TILES
THRESHOLD TO MATCH
BATHROOM FLOORING
WALL TILES TO SPECS.REFER
DOOR
&
FRAME
TO
SCHEDULE
5 MM THK. X 50MM
L-BRASS DIVIDING STRIP
SELECTED TILES
TO SPECS
BATHROOM
AREA
BEDROOM
AREA
Load - bearing- wall
Row of columnsWide striptee
Inverted tee
C O N S T R U C T I O N D E T A I L & P R O C E S S
5.2 Propose Blockwork System
40
Construction Methods: Blockwork System
Construction Components: Concrete Masonry Unit(CMU) Hollow
Installation Process
Blockwork System
The blockwork system is varied in types of shapes and sizeS, it is more reliable com-
pared to other systems. The proposed blockwork component such as Concrete Mason-
ry Unit (CMU) is used as the main component for structure of a building.
CMU(hollow)
The main use of CMU block components are to build the column and load bearing walls
throughout the entire building. The main blocks are stretcher, bond beam and edge
block.
1. Reference lines are placed with thread or chalk and
a test is performed without mortar. Then, mix the
mortar and spread it onto the strip footing over the
width of a block.
3. At the end of each row, blocks are align vertically
and horizontally, and hit at the side to adjust them if
necessary.
2. The blocks are then placed from the corner and
mortar is applied to their vertical joints.
4. Reinforcement rebars are then added on to the
beam and bearing block to strengthen the tension.
C O N S T R U C T I O N D E T A I L & P R O C E S S
5.2 Propose Blockwork System | Components Location
41
C O N S T R U C T I O N D E T A I L & P R O C E S S
5.2 Propose Blockwork System | Components Location
42
Rebar spacing per
design
Horizontal joint rein-
forcement as
required.
Reinforced masonry
lintel per design
Grout filled cells
Tornado resistant
door / window / frame
Compressible filler
Sealant and backer
rod
Anchor transfer trans-
verse loads and
allows independent
movement
Masonry
H O R I Z O N T A L S P A N H E A D D E T A I L
C O N T R O L J O I N T
Top of wall to accom-
modate floor roof
deflection
Reinforced bond
beam as required.
Reinforced bond
beam as required.
Horizontal joint rein-
forcement as
required.
C O N S T R U C T I O N D E T A I L & P R O C E S S
5.2 Propose Blockwork System | Components Location
43
Solid backing
Waterproofing mem-
brane
Mesh
Mortar bed/lath
Dry set or latex
cement
Grout and reinforce-
ment where required
Terminate horizontal
joint reinforcement
Chalk and backer rod
Building papert
Tile
J A M B D E T A I L
M A S O N R Y F I R E W A L L
W A L L T I L E
C O N T R O L J O I N T
Rebar spacing per
design
16 galvanised mason-
ry T anchor
Grout filled cells
Tornado resistant
door / window / frame
Mineral wall to
forestop insulation
Fireproof sealant as
required
Solid cmu at top
course
Grout and reinforce-
ment as required
Clip angle
Masonry
C O N S T R U C T I O N D E T A I L & P R O C E S S
5.3 Propose Hollow Core Slab
44
Construction Methods: Precast System
Construction Components: Hollow Core Slabs(Custom)
Precast Concrete System
Malaysia commonly use the precast concrete system as the main construction based on IBS. For the build-
ing proposal precast system is used as floor slabs for first and second floor.
Hollow core Slabs
Hollow core system is one of the most widely and popularly used precast concrete flooring system in the
building industry. Fast assembly at site, a self-supporting system, excellent lower surface finish and facto-
ry-assured quality.
Installation Process
1.The hollow core slabs are measured and moulded through machines
according to the specified size.
2.The manufactured slabs are transported to the site. Then HCS(hollow
core slabs) are hoisted with a crane and travel to the building area.
3.The crane are then carefully place the HCS(hollow core slab) at the right
angle of the position on the beam.
4.After the hollow core slabs are rested on the beams. Concrete are pour
between the joints and the slabs once is harden the steps are continue by
another slabs
C O N S T R U C T I O N D E T A I L & P R O C E S S
5.4 Propose Staircase System
45
Prefabricated staircase consists of two individual components which is landing and step. Both of these components are manufactured in the factories and will be transport to the
site for assembling process. The steps and the landing will be attached together by pouring the concrete into the formwork. In order to strengthen the structure, rebar will be
used to support the cured concrete.
Advantages
1.Easy to be assembled
2.Immediate functioning after assembled
3.Quality preserved
4.Speed up construction process as immediate access gained
5.Save time and cost
6.Reduce construction site cost
Installation Process
1.Steel brackets are bolted to the foundation using concrete anchors. These will be
used to catch the legs located behind the stairs
2.Small concrete pads are set under each side of the steps toward the front of the unit.
These pads are set slightly lower than the brackets so that the stairs are pitched
forward for water flow off
3.The precast stairs are then will be placed on the brackets and pads using a boom
truck.
4.If your stairs require railings, they would be installed at this time. The railings are
installed in the precast unit and held in place with anchoring cement.
C O N S T R U C T I O N D E T A I L & P R O C E S S
5.5 Propose Roof Truss System
46
This building use a prefabricated roof trusses which are made from steel framing system. Few components are involved which is the trusses, purlins and rafter
1.Flexible design can be applied
2.Longer life span
3.Easy to be assembled
4.High durability
5.Lightweight structure
Installation Process
1.Lift first individual truss and place in their right position . Long trusses will require a
spreader bar to lift it
2.Secure truss to bearing support with metal bracket
3.Screw gun can install hardware at the bearing support and bracing material to hold
the trusses in the position
4.For first truss, the truss is restrained with bracing to the ground or building interior.
C O N S T R U C T I O N D E T A I L & P R O C E S S
5.6 Propose Windows System
47
I B S C A L C U L A T I O N
48
Part 1: Structural systems (Maximum score is 50 points)
Points are awarded for various types of structural system that are used in the building, e.g. combination of precast concrete beams, columns and slabs, combination of load bear-
ing blocks and in situ concrete using reusable formwork; and other combinations Points are also given based on the usage of Roof’s Structural Systems
Part 2: Wall systems (Maximum score is 20 points)
Points are awarded based on various types of wall systems that are utilised, e.g. precast concrete panel, dry wall system, blockwork system and other wall systems
Part 3: Other simplified construction solutions (Maximum score is 30 points)
Points are awarded based on usage of other simplified construction solutions, e.g. standardised components based on MS 1064, repetition of structural layout and other produc-
tivity enhancing solutions such as volumetric modular units, BIM and Modular gridlines.
C O N C L U S I O N
49
This apartment is three stories height and manage to score up to 78% of IBS score. This proof that by using blockwork as the main IBS components are achievable due to the
low IBS factor and also one of the lowest among other IBS components.
By understanding the main components in each of the IBS components, we as a group manage to come out with the proposal that proposed each part with different type of IBS
components. This proposal are based on the installation method, advantage and disadvantage and its suitability to make sure that the building are well structured. Besides, we
manage to analyse on the IBS construction method and each process that need to be taken into consideration before come out with the IBS calculation score.
We also produced a physical model that shows all the detail in IBS component starting from its foundation until the roof. From the physical model we manage to understand how
the IBS components works and function.
As a group, we agreed that the implementation of IBS system can greatly reduced total construction time. The efficiency of the IBS system also proves that it is suitable to be
used in our country as it can enhanced quality of building, minimising solid waste, reducing number of workers at site and decreasing air pollution at construction site.
R E F E R E N C E S
50
Rullktter, J. (2004). Of Mud Flats, Mixed Mud Flats and Sand Flats. German Research, 26(2-3), 8-12. doi:10.1002/germ.200490024
Barghchi, M., Omar, D. B., Aman, M. S., & Kazemian, S. (2011). The Intangible Impacts of Sports Facilities Development: Case Study of the Bukit Jalil National Sports Complex
in Malaysia. Modern Methods and Advances in Structural Engineering and Construction(ISEC-6). doi:10.3850/978-981-08-7920-4_s1-f04-cd
Permata Pintar Negara. (n.d.). Retrieved from http://www.mmces.com.my/our-business/civil-infrastructure/permata-pintar-negara
Http://www.brenwood.com.my/wp-content/uploads/2012/07/Taiping-Hospital-640x295.jpg. (n.d.).
DUO System Formwork. (n.d.). Retrieved from https://www.perimalaysia.com/products/formwork/column-formwork/duo-formwork.html#&gid=1&pid=4
Https://www.star2.com/wp-content/uploads/2017/01/str2_gamudaF_cb_1~1.jpg. (n.d.).
(n.d.). Retrieved from https://ame-engi.com.my/wp-content/uploads/2016/04/IMG-20150804-WA0004-1024x768.jpg
Https://www.nitterhousemasonry.com/wp-content/uploads/2014/01/Nitterhouse150-5672-1024x682.jpg. (n.d.).
PERMATApintar Auditorium. (n.d.). Retrieved from http://gdparchitects.com/2015/?project=permatapintar-auditor ium-sports-park
https://selfbuild.ie/wp-content/uploads/2017/11/100-0005_IMG-1.jpg (n.d)
https://www.nairaland.com/attachments/4942548_img20170222181447_jpegd0255845d4020cd8769d693ca8141447 (n.d)
D. (n.d.). MALAYSIAN STANDARD MS 1064:PART 10:2001
GUIDE TO MODULAR COORDINATION IN BUILDINGS: PART 10: COORDINATING SIZES AND PREFERRED SIZES FOR REINFORCED CONCRETE COMPONENT
(CONFIRMED:2009) (Copyright 2009).
D. (n.d.). MALAYSIAN STANDARD MS 1064 PART 5:2001 GUIDE TO MODULAR COORDINATION IN BUILDINGS : PART 5 : COORDINATING SIZES AND PREFERRED
SIZES FOR WINDOWSET (CONFIRMED:2009)
(CONFIRMED:2009) (Copyright 2009).
(n.d.). MALAYSIAN STANDARD MS 1064: PART 3:2003 GUIDE TO MODULAR COORDINATION IN BUILDINGS: Â PART 3: COORDINATING SIZES AND PREFERRED
SIZES FOR STAIRS AND STAIR OPENINGS (FIRST REVISION) © Copyright 2003
STANDARD INDUSTRI PEMBINAAN. (n.d.). Retrieved from http://www.cidb.gov.my/images/content/pdf/cis/CIS-18-2018-Final-Draft-6-Dec-2017-1.pdf
Grega Palang R. Gampilok, Abdul Kadir Marsono,2016,Hydrodynamic Test on IBS Block Work Structure[PDF File].Retrieved from http://engineering.utm.my/civil/wp-content/up-
loads/sites/29/2016/11/3.-Hydrodynamic-Test-on-IBS-Block-Work-Structure.pdf(Accessed on 16, may, 2019).
INDUSTRIALIZED BUILDING SYSTEM (IBS),2017, april 05.Retrieved from https://www.aathaworld.com/industrialized-building-system-ibs (Accessed on 16, may, 2019).
MIDF Research,2014,CONSTRUCTION IBS Practical solution to rising costs[PDF file].Retrieved from http://www.midf.com.my/images/Downloads/Research/EqStrate-
gy/SpecialReports/Construction-IBS_MIDF_140214.pdf (Accessed on 16, may, 2019).
Construction Solutions,Solution: Lightweight Concrete Block,2019, may 11. Retrieved from http://www.cpwrconstructionsolutions.org/masonry/solution/48/-
lightweight-concrete-block.html (Accessed on 16, may, 2019).
PERMATApintar Auditorium,2015, april 14.Retrieved from http://gdparchitects.com/2015/?project=permatapintar-auditorium-sports-park (Accessed on 16, may, 2019)
BAKAR.A. SHAFIE,(2012, JUN, 19), Perasmian Sekolah KAFA Integrasi Al-Mubarak, Seksyen 8, Kota Damansara[Blog pos ]. Retrieved from http://drshafie.blog-
spot.com/2012/06/perasmian-sekolah-kafa-integrasi-al.html (Accessed on 16, may, 2019).
Design Building Wiki,Cast-in-place concrete,2019,Feb 26. Retrieved from https://www.designingbuildings.co.uk/wiki/Cast-in-place_concrete (Accessed on 16, may, 2019).
Driven Cast In-Situ Concrete Piles Construction Process,2019, july 09. Retrieved from https://theconstructor.org/geotechnical/driven-cast-in-si-
tu-concrete-piles-construction-process/7088/ Â Â (Accessed on 16, may, 2019).
Franco.T. Jose, 2018, march 12,Concrete Blocks in Architecture: How to Build With This Modular and Low-Cost Material. Retrieved from https://www.archdaily.com/889657/con-
crete-blocks-in-architecture-how-to-build-with-this-modular-and-low-cost-material (Accessed on 16, may, 2019).
Zenbes Sdn. Bhd, CONCRETE BLOCKS (CMU) IBS BLOCKWORK SYSTEM,2018 may 15, Retrieved from https://zenbes.com.my/index.php/products/concrete-block-cmu/ Â
(Accessed on 16, may, 2019).
Consolis Bentonika,2008,INSTALLATION OF HOLLOW CORE FLOOR SLABS[PDF File]. Retrieved from http://betonika.lt/files/parsisiust/montavimo_instrukci-
jos/montavimo_rekomendacijos_en/installation_of_hollow_core_floor_slabs_en.pdf(Accessed on 16, may, 2019).
A N D I K A S E T I A B U D I
A K I F Z O L K E P L E E
I S Y R A Q N A S I R
A I Z Z A T H A K I M
P O H W E N G C H U A N
0326483
0322927
0322177
0324396
0319951

More Related Content

What's hot

B.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsB.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsCarmen Chan
 
Building Technology I
Building Technology IBuilding Technology I
Building Technology IOng Shi Hui
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1Gertrude Lee
 
Industrialised Building Solution
Industrialised Building SolutionIndustrialised Building Solution
Industrialised Building SolutionLee Wan Xuan
 
Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Nekumi Kida
 
Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]JerotichMaswan
 
Blockwork system
Blockwork systemBlockwork system
Blockwork systemWen Crystal
 
Project 1 - Industrialised Building System
Project 1 - Industrialised Building SystemProject 1 - Industrialised Building System
Project 1 - Industrialised Building Systemhilmanaqil1
 
Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Soh Shing
 
Industrialised Building System report,
Industrialised Building System report, Industrialised Building System report,
Industrialised Building System report, Eraz
 
Building Technology I Project 1
Building Technology I Project 1Building Technology I Project 1
Building Technology I Project 1DavidJPCChai
 
New materials and technologies used in NISM Mumbai
New materials and technologies used in NISM MumbaiNew materials and technologies used in NISM Mumbai
New materials and technologies used in NISM MumbaiDr K M SONI
 
Building technology report
Building technology reportBuilding technology report
Building technology reportChong Yi Hui
 
New materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in MumbaiNew materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in MumbaiDr K M SONI
 
Insulated concrete formwork
Insulated concrete formworkInsulated concrete formwork
Insulated concrete formworkSafaSheriff
 

What's hot (18)

B.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsB.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building Systems
 
Building Technology I
Building Technology IBuilding Technology I
Building Technology I
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1
 
Industrialised Building Solution
Industrialised Building SolutionIndustrialised Building Solution
Industrialised Building Solution
 
Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)
 
Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]
 
Blockwork system
Blockwork systemBlockwork system
Blockwork system
 
PROJECT 2: CONSTRUCTION SOLUTIONS
PROJECT 2: CONSTRUCTION SOLUTIONSPROJECT 2: CONSTRUCTION SOLUTIONS
PROJECT 2: CONSTRUCTION SOLUTIONS
 
Project 1 - Industrialised Building System
Project 1 - Industrialised Building SystemProject 1 - Industrialised Building System
Project 1 - Industrialised Building System
 
Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Building Technology 1 (Project 1)
Building Technology 1 (Project 1)
 
Industrialised Building System report,
Industrialised Building System report, Industrialised Building System report,
Industrialised Building System report,
 
Modern Method
Modern MethodModern Method
Modern Method
 
Building Technology I Project 1
Building Technology I Project 1Building Technology I Project 1
Building Technology I Project 1
 
New materials and technologies used in NISM Mumbai
New materials and technologies used in NISM MumbaiNew materials and technologies used in NISM Mumbai
New materials and technologies used in NISM Mumbai
 
Building technology report
Building technology reportBuilding technology report
Building technology report
 
New materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in MumbaiNew materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in Mumbai
 
Ct iii presentation
Ct iii presentationCt iii presentation
Ct iii presentation
 
Insulated concrete formwork
Insulated concrete formworkInsulated concrete formwork
Insulated concrete formwork
 

Similar to Btech i compressed

Building Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyBuilding Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyQuinn Liew
 
Building Technology Project 1 Report
Building Technology Project 1 ReportBuilding Technology Project 1 Report
Building Technology Project 1 ReportBolin Loong
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System마 이환
 
Btech report final
Btech report finalBtech report final
Btech report finalSarah Esa
 
IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartmentJy Chong
 
B tech final report pdf
 B tech final report pdf B tech final report pdf
B tech final report pdfyenweizheng
 
Building Technology 1 (P1)
Building Technology 1 (P1)Building Technology 1 (P1)
Building Technology 1 (P1)Nicole Foo
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Developmentijsrd.com
 
MODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSMODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSShourya Puri
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1chongyih2
 
Building Technology 1 Construction Solutions Report
Building Technology 1 Construction Solutions ReportBuilding Technology 1 Construction Solutions Report
Building Technology 1 Construction Solutions Reportdouglasloon
 
434773055-INDUSTRIALIZED-BUILDING-SYSTEM-IBS-pptx.pptx
434773055-INDUSTRIALIZED-BUILDING-SYSTEM-IBS-pptx.pptx434773055-INDUSTRIALIZED-BUILDING-SYSTEM-IBS-pptx.pptx
434773055-INDUSTRIALIZED-BUILDING-SYSTEM-IBS-pptx.pptxra1508
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written ReportYap Xin
 
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...Haziq1511
 
96382022 pre-engineered-buildings
96382022 pre-engineered-buildings96382022 pre-engineered-buildings
96382022 pre-engineered-buildingshlksd
 

Similar to Btech i compressed (20)

Building Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyBuilding Technology : Industrialize Building Technology
Building Technology : Industrialize Building Technology
 
Building Technology Project 1 Report
Building Technology Project 1 ReportBuilding Technology Project 1 Report
Building Technology Project 1 Report
 
Btech report
Btech reportBtech report
Btech report
 
Ct3
Ct3Ct3
Ct3
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 
Btech report final
Btech report finalBtech report final
Btech report final
 
IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartment
 
Btech
BtechBtech
Btech
 
B tech final report pdf
 B tech final report pdf B tech final report pdf
B tech final report pdf
 
Building Technology 1 (P1)
Building Technology 1 (P1)Building Technology 1 (P1)
Building Technology 1 (P1)
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Development
 
MODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSMODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODS
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1
 
CREAM report
CREAM reportCREAM report
CREAM report
 
Building Technology 1 Construction Solutions Report
Building Technology 1 Construction Solutions ReportBuilding Technology 1 Construction Solutions Report
Building Technology 1 Construction Solutions Report
 
434773055-INDUSTRIALIZED-BUILDING-SYSTEM-IBS-pptx.pptx
434773055-INDUSTRIALIZED-BUILDING-SYSTEM-IBS-pptx.pptx434773055-INDUSTRIALIZED-BUILDING-SYSTEM-IBS-pptx.pptx
434773055-INDUSTRIALIZED-BUILDING-SYSTEM-IBS-pptx.pptx
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written Report
 
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
 
96382022 pre-engineered-buildings
96382022 pre-engineered-buildings96382022 pre-engineered-buildings
96382022 pre-engineered-buildings
 
Pre-engineered bldg.pptx
Pre-engineered bldg.pptxPre-engineered bldg.pptx
Pre-engineered bldg.pptx
 

More from Weng Chuan

Jake r esythesize board 2
Jake r esythesize board 2Jake r esythesize board 2
Jake r esythesize board 2Weng Chuan
 
Poh weng chuan project 1a & 1b
Poh weng chuan project 1a & 1bPoh weng chuan project 1a & 1b
Poh weng chuan project 1a & 1bWeng Chuan
 
the home environment affect work from home
 the home environment affect work from home the home environment affect work from home
the home environment affect work from homeWeng Chuan
 
Comprehensive design report 2 To create a Social Hub Center that reflect the ...
Comprehensive design report 2 To create a Social Hub Center that reflect the ...Comprehensive design report 2 To create a Social Hub Center that reflect the ...
Comprehensive design report 2 To create a Social Hub Center that reflect the ...Weng Chuan
 
Project management report document a medium size project.
Project management report document a medium size project. Project management report document a medium size project.
Project management report document a medium size project. Weng Chuan
 
Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1 Weng Chuan
 
Report b tech correct compressed
Report b tech correct compressedReport b tech correct compressed
Report b tech correct compressedWeng Chuan
 
Urban theories
Urban theoriesUrban theories
Urban theoriesWeng Chuan
 
Building science ii presentation slide
Building science ii   presentation slideBuilding science ii   presentation slide
Building science ii presentation slideWeng Chuan
 
Building science ii report
Building science ii reportBuilding science ii report
Building science ii reportWeng Chuan
 
structure analysis
structure analysisstructure analysis
structure analysisWeng Chuan
 
Topic & issue proposal 2018 template (2)
Topic & issue proposal 2018 template (2)Topic & issue proposal 2018 template (2)
Topic & issue proposal 2018 template (2)Weng Chuan
 
building cons report
building cons report building cons report
building cons report Weng Chuan
 
Parliament building
Parliament buildingParliament building
Parliament buildingWeng Chuan
 

More from Weng Chuan (20)

Jake r esythesize board 2
Jake r esythesize board 2Jake r esythesize board 2
Jake r esythesize board 2
 
Poh weng chuan project 1a & 1b
Poh weng chuan project 1a & 1bPoh weng chuan project 1a & 1b
Poh weng chuan project 1a & 1b
 
the home environment affect work from home
 the home environment affect work from home the home environment affect work from home
the home environment affect work from home
 
Comprehensive design report 2 To create a Social Hub Center that reflect the ...
Comprehensive design report 2 To create a Social Hub Center that reflect the ...Comprehensive design report 2 To create a Social Hub Center that reflect the ...
Comprehensive design report 2 To create a Social Hub Center that reflect the ...
 
Project management report document a medium size project.
Project management report document a medium size project. Project management report document a medium size project.
Project management report document a medium size project.
 
Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1
 
Report b tech correct compressed
Report b tech correct compressedReport b tech correct compressed
Report b tech correct compressed
 
Urban theories
Urban theoriesUrban theories
Urban theories
 
Synopsis 3
Synopsis 3Synopsis 3
Synopsis 3
 
Synopsis 2
Synopsis 2Synopsis 2
Synopsis 2
 
Synopsis 1
Synopsis 1Synopsis 1
Synopsis 1
 
Building science ii presentation slide
Building science ii   presentation slideBuilding science ii   presentation slide
Building science ii presentation slide
 
Building science ii report
Building science ii reportBuilding science ii report
Building science ii report
 
structure analysis
structure analysisstructure analysis
structure analysis
 
Topic & issue proposal 2018 template (2)
Topic & issue proposal 2018 template (2)Topic & issue proposal 2018 template (2)
Topic & issue proposal 2018 template (2)
 
building cons report
building cons report building cons report
building cons report
 
Timeline
TimelineTimeline
Timeline
 
Parliament building
Parliament buildingParliament building
Parliament building
 
New model
New modelNew model
New model
 
New model
New modelNew model
New model
 

Recently uploaded

如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证ugzga
 
Gamestore case study UI UX by Amgad Ibrahim
Gamestore case study UI UX by Amgad IbrahimGamestore case study UI UX by Amgad Ibrahim
Gamestore case study UI UX by Amgad Ibrahimamgadibrahim92
 
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证wpkuukw
 
如何办理(Columbia College毕业证书)纽约市哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(Columbia College毕业证书)纽约市哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证如何办理(Columbia College毕业证书)纽约市哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(Columbia College毕业证书)纽约市哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证ugzga
 
Resume all my skills and educations and achievement
Resume all my skills and educations and  achievement Resume all my skills and educations and  achievement
Resume all my skills and educations and achievement 210303105569
 
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样yhavx
 
Academic Portfolio (2017-2021) .pdf
Academic Portfolio (2017-2021)      .pdfAcademic Portfolio (2017-2021)      .pdf
Academic Portfolio (2017-2021) .pdfM. A. Architects
 
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...samsungultra782445
 
Essential UI/UX Design Principles: A Comprehensive Guide
Essential UI/UX Design Principles: A Comprehensive GuideEssential UI/UX Design Principles: A Comprehensive Guide
Essential UI/UX Design Principles: A Comprehensive GuideDesign Studio UI UX
 
怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证
怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证
怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证eeanqy
 
Furniture & Joinery Details_Designs.pptx
Furniture & Joinery Details_Designs.pptxFurniture & Joinery Details_Designs.pptx
Furniture & Joinery Details_Designs.pptxNikhil Raut
 
Design-System - FinTech - Isadora Agency
Design-System - FinTech - Isadora AgencyDesign-System - FinTech - Isadora Agency
Design-System - FinTech - Isadora AgencyIsadora Agency
 
Morgenbooster: Storytelling in Identity Design
Morgenbooster: Storytelling in Identity DesignMorgenbooster: Storytelling in Identity Design
Morgenbooster: Storytelling in Identity Design1508 A/S
 
定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制
定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制
定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制eqaqen
 
Abortion pills in Kuwait 🚚+966505195917 but home delivery available in Kuwait...
Abortion pills in Kuwait 🚚+966505195917 but home delivery available in Kuwait...Abortion pills in Kuwait 🚚+966505195917 but home delivery available in Kuwait...
Abortion pills in Kuwait 🚚+966505195917 but home delivery available in Kuwait...drmarathore
 
Branding in the Psychedelic Landscape Report.pdf
Branding in the Psychedelic Landscape Report.pdfBranding in the Psychedelic Landscape Report.pdf
Branding in the Psychedelic Landscape Report.pdfAlexandra Plesner
 
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...samsungultra782445
 
How to Build a Simple Shopify Website
How to Build a Simple Shopify WebsiteHow to Build a Simple Shopify Website
How to Build a Simple Shopify Websitemark11275
 
Edward Boginsky's Trailblazing Contributions to Printing
Edward Boginsky's Trailblazing Contributions to PrintingEdward Boginsky's Trailblazing Contributions to Printing
Edward Boginsky's Trailblazing Contributions to PrintingEdward Boginsky
 
一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证
一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证
一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证wpkuukw
 

Recently uploaded (20)

如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
 
Gamestore case study UI UX by Amgad Ibrahim
Gamestore case study UI UX by Amgad IbrahimGamestore case study UI UX by Amgad Ibrahim
Gamestore case study UI UX by Amgad Ibrahim
 
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
 
如何办理(Columbia College毕业证书)纽约市哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(Columbia College毕业证书)纽约市哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证如何办理(Columbia College毕业证书)纽约市哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(Columbia College毕业证书)纽约市哥伦比亚大学毕业证成绩单本科硕士学位证留信学历认证
 
Resume all my skills and educations and achievement
Resume all my skills and educations and  achievement Resume all my skills and educations and  achievement
Resume all my skills and educations and achievement
 
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
 
Academic Portfolio (2017-2021) .pdf
Academic Portfolio (2017-2021)      .pdfAcademic Portfolio (2017-2021)      .pdf
Academic Portfolio (2017-2021) .pdf
 
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
 
Essential UI/UX Design Principles: A Comprehensive Guide
Essential UI/UX Design Principles: A Comprehensive GuideEssential UI/UX Design Principles: A Comprehensive Guide
Essential UI/UX Design Principles: A Comprehensive Guide
 
怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证
怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证
怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证
 
Furniture & Joinery Details_Designs.pptx
Furniture & Joinery Details_Designs.pptxFurniture & Joinery Details_Designs.pptx
Furniture & Joinery Details_Designs.pptx
 
Design-System - FinTech - Isadora Agency
Design-System - FinTech - Isadora AgencyDesign-System - FinTech - Isadora Agency
Design-System - FinTech - Isadora Agency
 
Morgenbooster: Storytelling in Identity Design
Morgenbooster: Storytelling in Identity DesignMorgenbooster: Storytelling in Identity Design
Morgenbooster: Storytelling in Identity Design
 
定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制
定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制
定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制
 
Abortion pills in Kuwait 🚚+966505195917 but home delivery available in Kuwait...
Abortion pills in Kuwait 🚚+966505195917 but home delivery available in Kuwait...Abortion pills in Kuwait 🚚+966505195917 but home delivery available in Kuwait...
Abortion pills in Kuwait 🚚+966505195917 but home delivery available in Kuwait...
 
Branding in the Psychedelic Landscape Report.pdf
Branding in the Psychedelic Landscape Report.pdfBranding in the Psychedelic Landscape Report.pdf
Branding in the Psychedelic Landscape Report.pdf
 
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
 
How to Build a Simple Shopify Website
How to Build a Simple Shopify WebsiteHow to Build a Simple Shopify Website
How to Build a Simple Shopify Website
 
Edward Boginsky's Trailblazing Contributions to Printing
Edward Boginsky's Trailblazing Contributions to PrintingEdward Boginsky's Trailblazing Contributions to Printing
Edward Boginsky's Trailblazing Contributions to Printing
 
一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证
一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证
一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证
 

Btech i compressed

  • 1. B L O C K W O R K B U I L D I N G T E C H N O L O G Y
  • 2. C O N T E N T S I N T R O D U C T I O N 1.1 Introduction to IBS system 1.2 Types of IBS in Malaysia 1.3 Standard Workflow IBS System 1.4 Malaysia Blockwork System 1.5 Case Study C O N C E P T O F F R A M E W O R K 2.1 Propose IBS System 2.2 Construction Sequences T E C H N I C A L D R A W I N G S 3.1 Foundation 3.2 Slab 3.3 Plans 3.4 Block Work Plans 3.5 Roof Plans 3.6 Elevations 3.7 Sections 3.8 Axonometric S C H E D U L E O F I B S C O M P O N E N T S 4.1 Door 4.2 Windows 4.3 Block Components 4.4 Slab 4.5 Roof Truss Components 4.6 Staircase Components C O N S T R U C T I O N D E T A I L & P R O C E S S 5.1 Strip Footing 5.2 Blockwork System 5.3 Slab System 5.4 Staircase System 5.5 Roof truss System 5.6 Windows System I B S C A L C U L A T I O N C O N C L U S I O N S R E F E R E N C E S
  • 3. I N T R O D U C T I O N 1.1 Introduction to IBS system Industrialized Building System (IBS) is a construction technique whereby building components are manufactured in factories then transported and assembled into a structure with limited on site work. The benefits of IBS are clear and eminent as it allows for building to be constructed in a shorter time span and with greatly reduced activities at the con- struction site, which in turn provides tremendous cost savings to the builders. Furthermore, The IBS construction method can reduce wastage of resources besides providing good quality results for consumers. The use of IBS in Malaysia started in 1963. However, although it has been four decades since the introduction of IBS in Malaysia, the application and adoption of this method in the local construction industry, particularly in the private sector, is still relatively low compared to the developed countries. This was despite the perennial problems besetting traditional construction methods which include: time delay, Â cost overrun, and waste generation. the government started major projects using the IBS system in 1964. Their main objective was to accelerate the completion of the projects on time besides being able to con- struct affordable housing units of substantial quality. Projects along the Jalan Pekeliling (figure 1.1a) high rise apartment, Kuala Lumpur which were as wide as 22.7 acres includ- ed the construction of 7 blocks of flats of 17-storeys each encompassing 3,000 low-cost flats and 40 shop lots.Other megastructure projects that involved using industrialised building system such as Petronas Twin Tower( figure 1.1.b) and Bukit Jalil Sport Complex(figure 1.1.c) 01
  • 4. I N T R O D U C T I O N 1.2 Types of IBS in Malaysia Precast Concrete System Precast concrete system is the group that is most widely used in the IBS system. The form of the con- crete usually prepared, cast and cured off-site Pre- cast concrete elements can be joined to other ele- ments to form a complete structure. Timber Framing System This system involves prefabricated timber truss beams and columns. Most of the products listed in this category are wooden building frames and roof trusses. It is quite popular and widely applicable as it provides attractive designs and has high aesthetic values. Block work System Blocks work system exists as one of the type of IBS because of the revolutionary of construction method of using conventional bricks with the usage of inter- locking concrete masonry units (CMU) and light- weight concrete blocks. Innovative System This is the latest IBS type which incorporates vari- ous “green” elements, which are considered innova- tive in the industry. An example of the innovation is the mixture of two elements such as polystyrene and concrete, to produce IBS components for use in the construction of a wall which has better heat insulation properties. Steel Framing System Steel Framing System consists of load-bearing and non-load bearing wall system, composite floor slab construction that built with a series of high tensile galvanised cold formed c-sections as well as portal frame system. Steel Formwork System Identified as one of the least prefabricated types of the IBS, it generally involves concrete at the con- struction site and high quality control. This includes the "tunnel form", the"lilt-up" beam system, "mould- ing form" columns and a permanent steel mould. 02
  • 5. I N T R O D U C T I O N 1.3 Standard Workflow IBS System Design Consideration The important components that needs to be given consideration in the process of production and assembly of any buildings using IBS. Its components are initially design according to Malaysia stan- dards(1064) to reduce customising cost and time. Production Line Building Materials are manufactured and produced in specification or standardise dimension with proper quality control in factories. It minimises waste of materials of product on site. Transportation Materials IBS manufacture components are prefab- ricated and deliver to the site according to the amount and specification needed. The time efficient of labour work reduce due to the manufacturing and delivering period. Assembling and Completion The materials and components are direct- ly assemble and position onto the struc- ture building with guidance from profes- sionals. The completion of the building is then plastered and coated according to specification of the schedule. 03
  • 6. I N T R O D U C T I O N 1.4 Malaysia Blockwork System Type of Blockwork System in Malaysia Manufacturing Process The construction method of using conventional bricks has been revolutionised by the development and usage of interlocking concrete masonry units (CMU) and lightweight con- crete blocks. The blocks are commonly produced by hydraulic machinery which presses them in the steel moulds with the presence of vibration to compact the blocks. The Pres- ent of Blockwork methods are greatly simplified with reinforcement methods such as steel rods that are embedded inside the block and with the use of steel plate, bolts and nuts placed on the top of the blocks to make the blocks fixed in position. Advantages - The casting of concrete can be done in the working site which makes it economi- cal. -The presence of dead air trapped in the cavities of CMU provides natural thermal insulation. -CMU makes a building fire-safe due to its noncombustible nature. -Ingredients of Blockwork materials are easily available in most places. Advantages Disadvantages - Compared to other binding materials, the tensile strength of concrete is relatively low. - Rise in labour cost work with the increase workforce due to the construction meth- ods. - Does not has high compressive strength and weak without reinforcement or rebar install. - Concrete may contains soluble salts. Soluble salts cause efflorescence. Concrete Block Unit A concrete block is sometimes known as concrete masonry unit (CMU), they can be solid or hollow and is available in many shapes and sizes. Concrete Blocks are used for engineering and architectural purposes. Lightweight Block A lightweight con- crete block is an engineering control that may help reduce heavy lifting and carrying. The light- weight concrete block is a concrete masonry unit (CMU) made of expanded aggregate to reduce the density and weight Interlocking Block Interlocking brick is more convenient for builders without experience and skill set is not a constraint for this material, many developing countries in south- east asia (SEA) such as Cambodia, Viet- nam are popular due to its workability and low cost. Ventilation Block Ventilation Blocks promote natural light- ing and ventilation at any commercial or residential project. It is often used for the construction of wall features, screen walls, partitions for building facades, stairwells and multi-level car parks. Mixing After the materials are measured, they are dumped into the mixer to process. Molding Then batch of materi- als are pour into the molding machine and compress to its shape. Curing The pallets are then moved to carts which travel into a low-pres- sure steam kiln which are then to be heated. Cubing and Storing When curing is com- plete, They move on to our cubing system which stacks the blocks on a wood pallet. 04
  • 7. I N T R O D U C T I O N 1.5 Case Study : Sekolah Kafa Integrasi Al-mubarak Sekolah Kafa Integrasi Al-mubarak is an islamic primary school built by Aras Reka Arkitek and completed in year 2010. The school has funded by government PKNS, it has three stories with six classroom including, one faculty office, multi-purpose room and a canteen. The building materials are all comprises of concrete masonry blocks, which are also part of the erection of columns and walls. The blockworks from this building, which have more lighter weight and designed to be a high quality alternative to conventional construction methods by replacing common bricks & cast in-si- tu reinforced concrete structure. Construction Methods Firstly, site construction begins with concrete infill with reinforcement, then the curing method is apply on the concrete slab after the concrete foundation is dry, concrete bearing wall and columns blocks started to erect. After the blockwork structure was erected the Prefabricated roof system was installed, other components such as doors, walls and ceilings are place in. Case study: Institution (Sekolah Kafa Integrasi Al-mubarak) Architect: Aras Reka Arkitek IBS system: Load-bearing Blockwork System IBS Supplier: Zenbes sdn.bhd Main Components: Concrete Masonry Unit (CMU) Other Components: Precast Concrete foun- dation Blockwork components: -Load-bearing CMU wall -Concrete Masonry Unit bond beam -Concrete Masonry Unit stiffener Structural Components: -Reinforcement Concrete foundation -Precast concrete slab( precast off-site) Other components: -Prefabricated roof truss -Door and windows 05
  • 8. I N T R O D U C T I O N 1.5 Case Study : Permata Pintar Auditorium Permata pintar Auditorium and Sports Park are located on 20.15 acres in the University Kebangsaan Malaysia campus in Bangi, Selangor. The main feature of the auditorium is the capability to include 600 person in the auditorium hall, primarily catering to lectures, convocations, and the school’s musical theatre programmes. The back of house serves as a dressing room and rehearsal area, with VIP seating located at the second tier. The extended auditorium foyer generates a new public space, linking the plaza with visible meeting points. Construction Methods: Firstly, site excavation begins on the area along with landscaping construction. Foundation is infill with reinforcement and concrete. After rafter foundation, steel struc- ture framing was created on the outside, follow-up by installing blockwork system interior of the building. Aluminium cladding were added along the skin of the building. Precast structure were installed together with landscaping work. Case study: Permata Pintar auditorium, UKM Architect: GDP Architect IBS system: Load-bearing Blockwork System IBS Supplier: Zenbes sdn.bhd Main components: Concrete Masonry Unit(C- MU) Other components: Aluminium cladding, Steel structure, Precast concrete Foundation Blockwork Components: -Concrete Masonry Unit block Hollow -Concrete Ventilation block -Concrete Masonry Unit bond beam -Concrete Masonry Unit stiffener Structural Components -precast concrete foundation -precast concrete staircase Other components: -aluminium cladding -metal roof structure 06
  • 9. C O N C E P T O F F R A M E W O R K 2.1 Propose IBS System 07 The following structure and materials that have been selected based on the of IBS system that are used in the design of the three stories apartment. This components comprises prefabricated structure, blockwork system, cast-in situ (concrete) and precast concrete components. The main components comprises of blockwork CMU and accommodated with structure components, which form a hybrid system. 01 Foundation Cast-in SITU concrete -Concrete foundation Precast components 02 Precast concrete Components -Hollow core slab(Custom Size) -Precast concrete staircase Blockwork 04 Blockwork Components -Blockwork concrete (CMU) 03 Prefabricated components Cast-in SITU concrete -steel roof trusses -Windows and doors -railing
  • 10. C O N C E P T O F F R A M E W O R K 2.2 Construction Process 08 01 Foundation The strip foundation stage is cast in place by pouring concrete foundation on the excavate trench till the ground level. Blockworks is partially built verti- cally till the ground level. Concrete Slab 02 After the strip foundation is done in place, concrete is poured on the ground floor to form concrete slab. Cement is screed throughout the area and leave it to dry. Continuation of Blockwork 04 The continuation of blockworks are then being lay out vertically through- out the ground area until window level. Windows are installed and the pro- cess continues. 03 Door and Walls The built up of concrete blockwork around the apron is set together with door frame. As the concrete block build vertically mortar is infill along the concrete block.
  • 11. C O N C E P T O F F R A M E W O R K 2.2 Construction Process 09 05 Lintel and Staircase Blockworks are continue to built to the lintel level. Precast lintels are placed on top of windows and doors. Precast concrete staircases are installed throughout the ground floor. Beam 06 Bond Beams are layered and connect on top of the wall’s infill with cement and reinforce with reinforcement bars. Slabs will be place on top of the beams afterwards. Assembling First Floor 08 The construction steps of first floor begin from no. 4 to no. 7. These steps are the repeat process from ground floor. 07 Hollowcore Slabs After the placement of the beam. which is the last component to be assemble on ground floor, hollowcore slabs are installed on top of the beams covering the whole first floor.
  • 12. C O N C E P T O F F R A M E W O R K 2.2 Construction Process 10 09 Assemble Second Floor The construction steps of second floor begin from no. 5 to no. 7. Gypsum ceil- ings are place after the installation of the roof truss. Installation Roof Truss 10 Prefabricated roof trusses are installed on top of the second floor wall. Purlins are horizontally place on the roof trusses. 11 Completion Pitch roof is place on top of the roof trusses as final construction process. Interior and exterior work are execut- ed with mechanical and electrical work, lighting tiles layering and wall coating.
  • 13. T E C H N I C A L D R A W I N G S 3.1 Foundation | Strip Foundation | 1:75 11 A B C D E F G H I 1234 20800 6000 3000 6005 1500 1500 2800 1500 1500 9000 3000 3000 2800 9000 2400 30001200 42002400
  • 14. T E C H N I C A L D R A W I N G S 3.2 Slab | Ground Floor Plan | 1:75 12 A B C D E F G H I 1234 20800 6000 3000 6005 1500 1500 2800 1500 1500 9000 3000 3000 2800 9000 2400 30001200 42002400
  • 15. T E C H N I C A L D R A W I N G S 3.2 Slab | First & Second Floor Plan | 1:75 13 A B C D E F G H I 1234 20800 6000 3000 6005 1500 1500 2800 1500 1500 9000 3000 3000 2800 9000 2400 30001200 42002400
  • 16. T E C H N I C A L D R A W I N G S 3.3 Plans | Ground Floor Plan | 1:75 14 UP MASTER BEDROOM A B C D E F G H I 1234 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 9000 2400 30001200 41982400 YARD DINING AREA BEDROOM 1 LIVING ROOMBEDROOM 2 LAUNDRY FFL+0.20 FFL+0.25 FFL+0.25 FFL+0.25FFL+0.25 FFL+0.25FFL+0.25 FFL+0.20 FFL+0.20 BATH BATH 7.2SQM 7.2SQM 9.0SQM9.0SQM 7.2SQM 7.2SQM 7.2SQM KITCHEN 50dp 3.6SQM 50dp 50dp 100dp 50dp GF
  • 17. T E C H N I C A L D R A W I N G S 3.3 Plans | First Floor Plan | 1:75 15 DNUP A B C D E F G H I 1234 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 9000 2400 30001200 41982400 MASTER BEDROOM YARD DINING AREA BEDROOM 1 LIVING ROOMBEDROOM 2 LAUNDRY FFL+0.20 FFL+0.25 FFL+0.25 FFL+0.25FFL+0.25 FFL+0.25FFL+0.25 FFL+0.20 FFL+0.20 BATH BATH 7.2SQM 7.2SQM 9.0SQM9.0SQM 7.2SQM 7.2SQM 7.2SQM KITCHEN 50dp 50dp 50dp 3.6SQM 50dp 1F
  • 18. T E C H N I C A L D R A W I N G S 3.3 Plans | Second Floor Plan | 1:75 16 DN A B C D E F G H I 1234 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 9000 2400 30001200 41982400 MASTER BEDROOM YARD DINING AREA BEDROOM 1 LIVING ROOMBEDROOM 2 LAUNDRY FFL+0.20 FFL+0.25 FFL+0.25 FFL+0.25FFL+0.25 FFL+0.25FFL+0.25 FFL+0.20 FFL+0.20 BATH BATH 7.2SQM 7.2SQM 9.0SQM9.0SQM 7.2SQM 7.2SQM 7.2SQM KITCHEN 50dp 50dp 50dp 50dp 2F 3.3 Plans | Second Floor Plan | 1:75
  • 19. T E C H N I C A L D R A W I N G S 3.4 Blockwork Plans | Ground Floor Plan | 1:75 17 A B C D E F G H I 1234 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 9000 2400 30001200 41982400 UP
  • 20. T E C H N I C A L D R A W I N G S 3.4 Blockwork Plans | First Floor Plan | 1:75 18 A B C D E F G H I 1234 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 9000 2400 30001200 41982400 DNUP
  • 21. T E C H N I C A L D R A W I N G S 3.4 Blockwork Plans | Second Floor Plan | 1:75 19 A B C D E F G H I 1234 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 9000 2400 30001200 41982400 DN
  • 22. T E C H N I C A L D R A W I N G S 3.5 Roof Plans | Structure Plan | 1:75 20 A B C D E F G H I 1234 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 9000 2400 30001200 42002400
  • 23. T E C H N I C A L D R A W I N G S 3.5 Roof Plans | Structure with Batten Plan | 1:75 21 A B C D E F G H I 1234 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 9000 2400 30001200 42002400
  • 24. T E C H N I C A L D R A W I N G S 3.5 Roof Plans | 1:75 22 A B C D E F G H I 1234 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 9000 2400 30001200 42002400
  • 25. T E C H N I C A L D R A W I N G S 3.6 Elevations | Front | 1:75 23 A B C D E F G H I 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 ►(FFL -200) STRIP FOOTING ►(FFL +0) GROUND LEVEL ►(FFL +9.6) ROOF LEVEL ►(FFL +6.4) SECOND FLOOR ►(FFL +3.2) FIRST FLOOR
  • 26. T E C H N I C A L D R A W I N G S 3.6 Elevations | Front with Finishing | 1:75 24 A B C D E F G H I 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 ►(FFL -200) STRIP FOOTING ►(FFL +0) GROUND LEVEL ►(FFL +9.6) ROOF LEVEL ►(FFL +6.4) SECOND FLOOR ►(FFL +3.2) FIRST FLOOR
  • 27. T E C H N I C A L D R A W I N G S 3.6 Elevations | Back | 1:75 25 A B C D E F G H I 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 ►(FFL -200) STRIP FOOTING ►(FFL +0) GROUND LEVEL ►(FFL +9.6) ROOF LEVEL ►(FFL +6.4) SECOND FLOOR ►(FFL +3.2) FIRST FLOOR
  • 28. T E C H N I C A L D R A W I N G S 3.6 Elevations | Back with Finishing | 1:75 26 A B C D E F G H I 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 ►(FFL -200) STRIP FOOTING ►(FFL +0) GROUND LEVEL ►(FFL +9.6) ROOF LEVEL ►(FFL +6.4) SECOND FLOOR ►(FFL +3.2) FIRST FLOOR 3.6 Elevations
  • 29. T E C H N I C A L D R A W I N G S 3.6 Elevations | Side & Side with Finishing | 1:75 27 1234 9000 240041982400 1234 9000 240041982400 ►(FFL -200) STRIP FOOTING ►(FFL +0) GROUND LEVEL ►(FFL +9.6) ROOF LEVEL ►(FFL +6.4) SECOND FLOOR ►(FFL +3.2) FIRST FLOOR
  • 30. T E C H N I C A L D R A W I N G S 3.7 Sections | A-A & B-B | 1:75 28 1234 9000 240042002400 1234 9000 240042002400 ►(FFL -200) STRIP FOOTING ►(FFL +0) GROUND LEVEL ►(FFL +9.6) ROOF LEVEL ►(FFL +6.4) SECOND FLOOR ►(FFL +3.2) FIRST FLOOR
  • 31. T E C H N I C A L D R A W I N G S 3.7 Sections | C-C | 1:75 29 A B C D E F G H I 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 ►(FFL -200) STRIP FOOTING ►(FFL +0) GROUND LEVEL ►(FFL +9.6) ROOF LEVEL ►(FFL +6.4) SECOND FLOOR ►(FFL +3.2) FIRST FLOOR
  • 32. T E C H N I C A L D R A W I N G S 3.7 Sections | D-D | 1:75 30 A B C D E F G H I 20800 6000 3000 6000 1500 1500 2800 1500 1500 9000 3000 3000 2800 ►(FFL -200) STRIP FOOTING ►(FFL +0) GROUND LEVEL ►(FFL +9.6) ROOF LEVEL ►(FFL +6.4) SECOND FLOOR ►(FFL +3.2) FIRST FLOOR
  • 33. T E C H N I C A L D R A W I N G S 3.8 Axonometric 31
  • 34. S C H E D U L E O F I B S C O M P O N E N T S 4.1 Door 32 900 800 2100 2100 D3 D2TYPE SIZE DESCRIPTION LOCATION TOTAL NO. REQ TOTAL NO. REQ 900mm (W) x 2100mm (H) 800mm (W) x 2100mm (H) BATHROOMDINING, LIVING ROOM, BEDROOM 1, MASTER BEDROOM BATHROOM BATHROOM DINING, LIVING ROOM, BEDROOM 1, MASTER BEDROOM DINING, LIVING ROOM, BEDROOM 1, MASTER BEDROOM Grd. Flr. 1st. Flr. 2nd. Flr. SOLID TIMBER H.W. WITH VENEER AND VARNISH TO MANUF'S DETAIL SOLID TIMBER H.W. WITH VENEER AND VARNISH TO MANUF'S DETAIL
  • 35. S C H E D U L E O F I B S C O M P O N E N T S 4.2 Windows 33 600 2400 1200 1800 1800 600 1800 2400 600 2400 600 2400 W1 W2 W3TYPE SIZE DESCRIPTION LOCATION 600mm (W) x 600mm (H) 2400mm (W) x 1800mm (H) 1200mm (W) x 1800mm (H) Grd. Flr. 1st. Flr. 2nd. Flr. BATHROOM DINING, LIVING ROOM, BEDROOM 1, MASTER BEDROOM BATHROOM BATHROOM DINING, LIVING ROOM, BEDROOM 1, MASTER BEDROOM DINING, LIVING ROOM, BEDROOM 1, MASTER BEDROOM BEDROOM 2 BEDROOM 2 BEDROOM 2 DARK BROWN POWDER COAL WITH ALUM. FRAME TOP HUNG STAINED GREY, FROSTED WINDOW ABOVE FIXED WITH GREY FROSTED STAINED GLASS BELOW TO MANUF'S DETAIL DARK BROWN POWDER COAL WITH ALUM. FRAME TOP HUNG STAINED GREY, FROSTED WINDOW ABOVE FIXED WITH GREY FROSTED STAINED GLASS BELOW TO MANUF'S DETAIL DARK BROWN POWDER COAL WITH ALUM. FRAME TOP HUNG STAINED GREY, FROSTED WINDOW ABOVE FIXED WITH GREY FROSTED STAINED GLASS BELOW TO MANUF'S DETAIL LOCATION
  • 36. S C H E D U L E O F I B S C O M P O N E N T S 4.3 Block components 34 TYPE OF BLOCK SIZE STRETCHER BOND BEAM EDGE BLOCK 200mm (W) x 200mm (H) x 400mm (L) 100mm (W) x 200mm (H) x 400mm (L) 200mm (W) x 200mm (H) x 400mm (L)
  • 37. S C H E D U L E O F I B S C O M P O N E N T S 4.4 Slab 35 SLAB 1 SLAB 2 SLAB 3TYPE OF SLAB LOCATION Grd. Flr. 1st. Flr. 2nd. Flr. SIZE 1500mm (W) x 200mm (H) x 2400mm (L) 1500mm (W) x 250mm (H) x 4200mm (L) 1400mm (W) x 250mm (H) x 3000mm (L) BATHROOM, YARD, LAUNDRY DINING, LIVING ROOM, MASTER BEDROOM, BEDROOM 1,2 BATHROOM, YARD, LAUNDRY BATHROOM, YARD, LAUNDRY 1500mm (W) x 250mm (H) x 2400mm (L) DINING, LIVING ROOM, MASTER BEDROOM, BEDROOM 1,2 DINING, LIVING ROOM, MASTER BEDROOM, BEDROOM 1,2 BALCONY (STAIRCASE) BALCONY (STAIRCASE) BALCONY (STAIRCASE)
  • 38. S C H E D U L E O F I B S C O M P O N E N T S 4.5 Roof Truss Components 36 TYPE OF ROOF TRUSS TRUSS 3 TRUSS 5TRUSS 4 TRUSS 6 TYPE OF ROOF TRUSS TRUSS 1 TRUSS 2
  • 39. S C H E D U L E O F I B S C O M P O N E N T S 4.6 Staircase Components 37 STAIRCASE COMP. ST 1 ST 2 ST 3 RISER : 200 x THREAD : 250 4239mm x 1000mm 2600mm x 4250mm
  • 40. C O N S T R U C T I O N D E T A I L & P R O C E S S 5.1 Strip Footing 38 Construction Methods: Cast-in SITU Construction Components: Strip Foundation(concrete) Installation Process Cast-in SITU It refers to work which is carried out on the construction site itself, often in the finished position. The purpose components are to be cast on site using concrete materials such as piles or footing. Strip Foundation Strip foundation are a type of shallow foundation that are used to provide a continuous, level (or sometimes stepped) strip of support to a linear structure such as a wall or close- ly-spaced rows of columns built centrally above them. 1.The process involves digging out trenches around the perimeter of the build-up area. 3.Concrete is then poured in until it reaches just below ground level. 3.Concrete is then poured in until it reaches just below ground level. 2.Formwork and rebars are produced before the concrete is poured into it to form the strip footing. The footings are installed around the foundation level.
  • 41. C O N S T R U C T I O N D E T A I L & P R O C E S S 5.1 Strip Footing | Detail Drawings 39 WATERROOFING TO SPECS Screed Blockwork Skin Coat OUTDOOR SELECTED FLOOR TILES TO SPECS. W/ APPROVED POINTING & ADHESIVE Concrete Slab FALL TO FT/ FW BULL NOSED TILES THRESHOLD TO MATCH BATHROOM FLOORING WALL TILES TO SPECS.REFER DOOR & FRAME TO SCHEDULE 5 MM THK. X 50MM L-BRASS DIVIDING STRIP SELECTED TILES TO SPECS BATHROOM AREA BEDROOM AREA Load - bearing- wall Row of columnsWide striptee Inverted tee
  • 42. C O N S T R U C T I O N D E T A I L & P R O C E S S 5.2 Propose Blockwork System 40 Construction Methods: Blockwork System Construction Components: Concrete Masonry Unit(CMU) Hollow Installation Process Blockwork System The blockwork system is varied in types of shapes and sizeS, it is more reliable com- pared to other systems. The proposed blockwork component such as Concrete Mason- ry Unit (CMU) is used as the main component for structure of a building. CMU(hollow) The main use of CMU block components are to build the column and load bearing walls throughout the entire building. The main blocks are stretcher, bond beam and edge block. 1. Reference lines are placed with thread or chalk and a test is performed without mortar. Then, mix the mortar and spread it onto the strip footing over the width of a block. 3. At the end of each row, blocks are align vertically and horizontally, and hit at the side to adjust them if necessary. 2. The blocks are then placed from the corner and mortar is applied to their vertical joints. 4. Reinforcement rebars are then added on to the beam and bearing block to strengthen the tension.
  • 43. C O N S T R U C T I O N D E T A I L & P R O C E S S 5.2 Propose Blockwork System | Components Location 41
  • 44. C O N S T R U C T I O N D E T A I L & P R O C E S S 5.2 Propose Blockwork System | Components Location 42 Rebar spacing per design Horizontal joint rein- forcement as required. Reinforced masonry lintel per design Grout filled cells Tornado resistant door / window / frame Compressible filler Sealant and backer rod Anchor transfer trans- verse loads and allows independent movement Masonry H O R I Z O N T A L S P A N H E A D D E T A I L C O N T R O L J O I N T Top of wall to accom- modate floor roof deflection Reinforced bond beam as required. Reinforced bond beam as required. Horizontal joint rein- forcement as required.
  • 45. C O N S T R U C T I O N D E T A I L & P R O C E S S 5.2 Propose Blockwork System | Components Location 43 Solid backing Waterproofing mem- brane Mesh Mortar bed/lath Dry set or latex cement Grout and reinforce- ment where required Terminate horizontal joint reinforcement Chalk and backer rod Building papert Tile J A M B D E T A I L M A S O N R Y F I R E W A L L W A L L T I L E C O N T R O L J O I N T Rebar spacing per design 16 galvanised mason- ry T anchor Grout filled cells Tornado resistant door / window / frame Mineral wall to forestop insulation Fireproof sealant as required Solid cmu at top course Grout and reinforce- ment as required Clip angle Masonry
  • 46. C O N S T R U C T I O N D E T A I L & P R O C E S S 5.3 Propose Hollow Core Slab 44 Construction Methods: Precast System Construction Components: Hollow Core Slabs(Custom) Precast Concrete System Malaysia commonly use the precast concrete system as the main construction based on IBS. For the build- ing proposal precast system is used as floor slabs for first and second floor. Hollow core Slabs Hollow core system is one of the most widely and popularly used precast concrete flooring system in the building industry. Fast assembly at site, a self-supporting system, excellent lower surface finish and facto- ry-assured quality. Installation Process 1.The hollow core slabs are measured and moulded through machines according to the specified size. 2.The manufactured slabs are transported to the site. Then HCS(hollow core slabs) are hoisted with a crane and travel to the building area. 3.The crane are then carefully place the HCS(hollow core slab) at the right angle of the position on the beam. 4.After the hollow core slabs are rested on the beams. Concrete are pour between the joints and the slabs once is harden the steps are continue by another slabs
  • 47. C O N S T R U C T I O N D E T A I L & P R O C E S S 5.4 Propose Staircase System 45 Prefabricated staircase consists of two individual components which is landing and step. Both of these components are manufactured in the factories and will be transport to the site for assembling process. The steps and the landing will be attached together by pouring the concrete into the formwork. In order to strengthen the structure, rebar will be used to support the cured concrete. Advantages 1.Easy to be assembled 2.Immediate functioning after assembled 3.Quality preserved 4.Speed up construction process as immediate access gained 5.Save time and cost 6.Reduce construction site cost Installation Process 1.Steel brackets are bolted to the foundation using concrete anchors. These will be used to catch the legs located behind the stairs 2.Small concrete pads are set under each side of the steps toward the front of the unit. These pads are set slightly lower than the brackets so that the stairs are pitched forward for water flow off 3.The precast stairs are then will be placed on the brackets and pads using a boom truck. 4.If your stairs require railings, they would be installed at this time. The railings are installed in the precast unit and held in place with anchoring cement.
  • 48. C O N S T R U C T I O N D E T A I L & P R O C E S S 5.5 Propose Roof Truss System 46 This building use a prefabricated roof trusses which are made from steel framing system. Few components are involved which is the trusses, purlins and rafter 1.Flexible design can be applied 2.Longer life span 3.Easy to be assembled 4.High durability 5.Lightweight structure Installation Process 1.Lift first individual truss and place in their right position . Long trusses will require a spreader bar to lift it 2.Secure truss to bearing support with metal bracket 3.Screw gun can install hardware at the bearing support and bracing material to hold the trusses in the position 4.For first truss, the truss is restrained with bracing to the ground or building interior.
  • 49. C O N S T R U C T I O N D E T A I L & P R O C E S S 5.6 Propose Windows System 47
  • 50. I B S C A L C U L A T I O N 48 Part 1: Structural systems (Maximum score is 50 points) Points are awarded for various types of structural system that are used in the building, e.g. combination of precast concrete beams, columns and slabs, combination of load bear- ing blocks and in situ concrete using reusable formwork; and other combinations Points are also given based on the usage of Roof’s Structural Systems Part 2: Wall systems (Maximum score is 20 points) Points are awarded based on various types of wall systems that are utilised, e.g. precast concrete panel, dry wall system, blockwork system and other wall systems Part 3: Other simplified construction solutions (Maximum score is 30 points) Points are awarded based on usage of other simplified construction solutions, e.g. standardised components based on MS 1064, repetition of structural layout and other produc- tivity enhancing solutions such as volumetric modular units, BIM and Modular gridlines.
  • 51. C O N C L U S I O N 49 This apartment is three stories height and manage to score up to 78% of IBS score. This proof that by using blockwork as the main IBS components are achievable due to the low IBS factor and also one of the lowest among other IBS components. By understanding the main components in each of the IBS components, we as a group manage to come out with the proposal that proposed each part with different type of IBS components. This proposal are based on the installation method, advantage and disadvantage and its suitability to make sure that the building are well structured. Besides, we manage to analyse on the IBS construction method and each process that need to be taken into consideration before come out with the IBS calculation score. We also produced a physical model that shows all the detail in IBS component starting from its foundation until the roof. From the physical model we manage to understand how the IBS components works and function. As a group, we agreed that the implementation of IBS system can greatly reduced total construction time. The efficiency of the IBS system also proves that it is suitable to be used in our country as it can enhanced quality of building, minimising solid waste, reducing number of workers at site and decreasing air pollution at construction site.
  • 52. R E F E R E N C E S 50 Rullktter, J. (2004). Of Mud Flats, Mixed Mud Flats and Sand Flats. German Research, 26(2-3), 8-12. doi:10.1002/germ.200490024 Barghchi, M., Omar, D. B., Aman, M. S., & Kazemian, S. (2011). The Intangible Impacts of Sports Facilities Development: Case Study of the Bukit Jalil National Sports Complex in Malaysia. Modern Methods and Advances in Structural Engineering and Construction(ISEC-6). doi:10.3850/978-981-08-7920-4_s1-f04-cd Permata Pintar Negara. (n.d.). Retrieved from http://www.mmces.com.my/our-business/civil-infrastructure/permata-pintar-negara Http://www.brenwood.com.my/wp-content/uploads/2012/07/Taiping-Hospital-640x295.jpg. (n.d.). DUO System Formwork. (n.d.). Retrieved from https://www.perimalaysia.com/products/formwork/column-formwork/duo-formwork.html#&gid=1&pid=4 Https://www.star2.com/wp-content/uploads/2017/01/str2_gamudaF_cb_1~1.jpg. (n.d.). (n.d.). Retrieved from https://ame-engi.com.my/wp-content/uploads/2016/04/IMG-20150804-WA0004-1024x768.jpg Https://www.nitterhousemasonry.com/wp-content/uploads/2014/01/Nitterhouse150-5672-1024x682.jpg. (n.d.). PERMATApintar Auditorium. (n.d.). Retrieved from http://gdparchitects.com/2015/?project=permatapintar-auditor ium-sports-park https://selfbuild.ie/wp-content/uploads/2017/11/100-0005_IMG-1.jpg (n.d) https://www.nairaland.com/attachments/4942548_img20170222181447_jpegd0255845d4020cd8769d693ca8141447 (n.d) D. (n.d.). MALAYSIAN STANDARD MS 1064:PART 10:2001 GUIDE TO MODULAR COORDINATION IN BUILDINGS: PART 10: COORDINATING SIZES AND PREFERRED SIZES FOR REINFORCED CONCRETE COMPONENT (CONFIRMED:2009) (Copyright 2009). D. (n.d.). MALAYSIAN STANDARD MS 1064 PART 5:2001 GUIDE TO MODULAR COORDINATION IN BUILDINGS : PART 5 : COORDINATING SIZES AND PREFERRED SIZES FOR WINDOWSET (CONFIRMED:2009) (CONFIRMED:2009) (Copyright 2009). (n.d.). MALAYSIAN STANDARD MS 1064: PART 3:2003 GUIDE TO MODULAR COORDINATION IN BUILDINGS:  PART 3: COORDINATING SIZES AND PREFERRED SIZES FOR STAIRS AND STAIR OPENINGS (FIRST REVISION) © Copyright 2003 STANDARD INDUSTRI PEMBINAAN. (n.d.). Retrieved from http://www.cidb.gov.my/images/content/pdf/cis/CIS-18-2018-Final-Draft-6-Dec-2017-1.pdf Grega Palang R. Gampilok, Abdul Kadir Marsono,2016,Hydrodynamic Test on IBS Block Work Structure[PDF File].Retrieved from http://engineering.utm.my/civil/wp-content/up- loads/sites/29/2016/11/3.-Hydrodynamic-Test-on-IBS-Block-Work-Structure.pdf(Accessed on 16, may, 2019). INDUSTRIALIZED BUILDING SYSTEM (IBS),2017, april 05.Retrieved from https://www.aathaworld.com/industrialized-building-system-ibs (Accessed on 16, may, 2019). MIDF Research,2014,CONSTRUCTION IBS Practical solution to rising costs[PDF file].Retrieved from http://www.midf.com.my/images/Downloads/Research/EqStrate- gy/SpecialReports/Construction-IBS_MIDF_140214.pdf (Accessed on 16, may, 2019). Construction Solutions,Solution: Lightweight Concrete Block,2019, may 11. Retrieved from http://www.cpwrconstructionsolutions.org/masonry/solution/48/- lightweight-concrete-block.html (Accessed on 16, may, 2019). PERMATApintar Auditorium,2015, april 14.Retrieved from http://gdparchitects.com/2015/?project=permatapintar-auditorium-sports-park (Accessed on 16, may, 2019) BAKAR.A. SHAFIE,(2012, JUN, 19), Perasmian Sekolah KAFA Integrasi Al-Mubarak, Seksyen 8, Kota Damansara[Blog pos ]. Retrieved from http://drshafie.blog- spot.com/2012/06/perasmian-sekolah-kafa-integrasi-al.html (Accessed on 16, may, 2019). Design Building Wiki,Cast-in-place concrete,2019,Feb 26. Retrieved from https://www.designingbuildings.co.uk/wiki/Cast-in-place_concrete (Accessed on 16, may, 2019). Driven Cast In-Situ Concrete Piles Construction Process,2019, july 09. Retrieved from https://theconstructor.org/geotechnical/driven-cast-in-si- tu-concrete-piles-construction-process/7088/   (Accessed on 16, may, 2019). Franco.T. Jose, 2018, march 12,Concrete Blocks in Architecture: How to Build With This Modular and Low-Cost Material. Retrieved from https://www.archdaily.com/889657/con- crete-blocks-in-architecture-how-to-build-with-this-modular-and-low-cost-material (Accessed on 16, may, 2019). Zenbes Sdn. Bhd, CONCRETE BLOCKS (CMU) IBS BLOCKWORK SYSTEM,2018 may 15, Retrieved from https://zenbes.com.my/index.php/products/concrete-block-cmu/  (Accessed on 16, may, 2019). Consolis Bentonika,2008,INSTALLATION OF HOLLOW CORE FLOOR SLABS[PDF File]. Retrieved from http://betonika.lt/files/parsisiust/montavimo_instrukci- jos/montavimo_rekomendacijos_en/installation_of_hollow_core_floor_slabs_en.pdf(Accessed on 16, may, 2019).
  • 53. A N D I K A S E T I A B U D I A K I F Z O L K E P L E E I S Y R A Q N A S I R A I Z Z A T H A K I M P O H W E N G C H U A N 0326483 0322927 0322177 0324396 0319951