SlideShare a Scribd company logo
Implementing Earned Value Management in
             the CxP ESPO




     Project Management Challenge 2010
               Galveston, TX
             February 9-10, 2010


               Les Sorge/SGT, Inc.
          ESPO Project Planning & Control


                Used with Permission
Implementation Goal & Presentation Agenda

♦ The goal of the EVA Systems Project Office (ESPO) Earned Value
  Management (EVM) implementation is to utilize existing products and
  processes where possible or influence them to make them compatible
  with EVM

♦ Agenda
   •   Work Breakdown Structure
   •   Organizational Breakdown Structure
   •   Responsibility Assignment Matrix and Control Accounts
   •   Work Packages / Charge Codes and Planning Packages
   •   Integrated Master Plan
   •   Integrated Master Schedule – Primavera PM Tool Implementation
   •   Deltek Cobra Tool Implementation
   •   Integration / Interfaces to Other Processes / Tools
   •   EVM Integration with Prime Contractor
   •   Future Opportunities for Improvements
   •   Acronyms and Reference Documents
   •   Questions & Answers

                                                                        2
Work Breakdown Structure (WBS)

♦ Summary of WBS requirements defined in NPR 7120.5D, Appendix G
    •    The standard space flight project WBS applies to the entire life cycle of the project
    •    Space flight projects will use the standard Level 1/2 WBS elements with level 1 as the
         Project name
    •    Level 3 and lower WBS elements will be determined by the project
    •    If there is no work to fit into a Level 1/2 WBS element, then an inactive placeholder
         element will be established
    •    A single WBS will be used for both technical / business management and reporting
♦ ESPO Implementation
    •    The technical WBS matches the financial WBS excluding the 6 digit project code
    •    The figure below represents the CxP reporting level and the pre-defined Control Account
         level




  Agency Defined

  Project Defined




                                                                                                   3
Organizational Breakdown Structure (OBS)
♦ Defining the responsible organization versus the performing organization
    •   Ask the question, “How does the Project Manager distribute the budget for control?”
♦ The Responsible Organization
    •   Used to develop the Responsibility Assignment Matrix (RAM) and Cost Performance
        Report (CPR) Format 2
    •   Aligns closely with the Work Breakdown Structure
♦ The Performing Organization
    •   Based on NASA Center, Directorate, and Divisions
          − A budget forecasting requirement does exist for the performing organization for planning purposes


    NASA Performing Organization                                     ESPO Responsible Organization




                                                                                                                4
Responsibility Assignment Matrix (RAM)
                                                  & Control Accounts (CA)
♦ Prime added as an organization in the OBS per ANSI-748 guidance
           •          This structure allows budgets to be segregated between prime and non-prime work while still
                      reinforcing the “integrated project – NASA and Prime” philosophy of ESPO
♦ CA nomenclature used: .29 for historical, .31 for NASA/non-prime, .32 for Prime
           •          .31 used for all NASA/non-prime organizations for easy recognition in SAP financial system
                              − Nomenclature works since multiple organizations don’t support a WBS element
 ESPO RAM Rev #: 001                                        Budget in ($K)                                                                                                            Constellation EVA Systems Project Office
 Date:                     11/3/2009                                                                                                                                                                      $0.0

 PAD #:                    CxP-EV-731384-P1-00                                    OBS            $0.0                 $0.0                 $0.0             $0.0           $0.0           $0.0                $0.0                  $0.0                 $0.0              $0.0              $0.0                 $0.0
 PAD Issue Date:           7/10/2009




                                                                                                                                                                                         Development
                                                                                                                       Project Mgmt
                                                                                                 Historical CA




                                                                                                                                                                                                                                                                                            Operations &
                                                                                                                                                                                                              Suit Element




                                                                                                                                                                                                                                                                                                                  CSSS Prime
                                                                                                                                                                                         Technology




                                                                                                                                                                                                                                                                          Testing and
                                                                                                                                         Planning &




                                                                                                                                                                                                                                 Equipment




                                                                                                                                                                                                                                                                                            Sustaining
                                                                                                                                                                                                                                 Tools and




                                                                                                                                                                                                                                                                          Facilities
                                                                                                                                                                                                                                                      Interface
                                                                                                                                                                                                                                 Element




                                                                                                                                                                                                                                                      Element
                                                                                                                                                                           SR&QA
                                                                                                                                         Control




                                                                                                                                                                                                                                                      Vehicle
                                                                                                                                         Project




                                                                                                                                                            SE&I
                            WBS                                    Description
                           731384.01.01                        Project Management          731384.01.01.29       731384.01.01.31                                                                                                                                                                            731284.01.01.32
           731384.01            $0.0                                                            $0.0                  $0.0                                                                                                                                                                                       $0.0
                           731384.01.02                     Project Planning & Control     731384.01.02.29                            731384.01.02.31                                                                                                                                                       731384.01.02.32
               $0.0             $0.0                                                             $0.0                                      $0.0                                                                                                                                                                   $0.0
               731384.02                                      Systems Engineering &         731384.02.29                                                731384.02.31                                                                                                                                         731384.02.32
               $0.0                                                 Integration                  $0.0                                                       $0.0                                                                                                                                                  $0.0
               731384.03                                       Safety, Reliability and      731384.03.29                                                               731384.03.31                                                                                                                          731384.03.32
               $0.0                                             Quality Assurance                $0.0                                                                      $0.0                                                                                                                                   $0.0
               731384.04                                     Technology Development         731384.04.29                                                                              731384.04.31                                                                                                           731384.04.32
               $0.0                                                                              $0.0                                                                                     $0.0                                                                                                                    $0.0
               731384.05                                            Payload(s)              731384.05.29
               $0.0                                                                              $0.0
                                                          EVA Systems H/W
                           731384.06.01                   Management
                           731384.06.02                   reserved
                           731384.06.03                    EVA Systems Sustaining          731384.06.03.29                                                                                                                                                                              731384.06.03.31     731384.06.03.32
                                $0.0                             Engineering                     $0.0                                                                                                                                                                                        $0.0                 $0.0
                                          731384.06.04.01        Suit Element             731384.06.04.01.29                                                                                           731384.06.04.01.31                                                                                  731384.06.04.01.32
                                                $0.0                                             $0.0                                                                                                         $0.0                                                                                                $0.0
  731384                   731384.06.04 731384.06.04.02       Tools and Equipment                                                                                                                                            731384.06.04.02.31                                                            731384.06.04.02.32
                                                $0.0                  Element                                                                                                                                                       $0.0                                                                          $0.0
                                          731384.06.04.03    Vehicle Interface Element    731384.06.04.03.29                                                                                                                                      731384.06.04.03.31                                       731384.06.04.03.32
           731384.06
                                $0.0            $0.0                                             $0.0                                                                                                                                                    $0.0                                                     $0.0
                                                            Logistics, Processing and                                                                                                                                                                                                   731384.06.05.31
                                                                 Inventory Mgmt                                                                                                                                                                                                              $0.0
                                                               Logistics Planning
                                                                                                                                      Control Accounts identified in the                                                                                                                                   731384.06.05.32.01
                                                                                                                                                                                                                                                                                                                  $0.0
                           731384.06.05                      Flight & Training Hardware                                                                                                                                                                                                                    731384.06.05.32.02
                                                                      Processing                                                      RAM create a natural extension to                                                                                                                                           $0.0
                                                                  Hardware Inventory                                                                                                                                                                                                                       731384.06.05.32.03
                                                                     Management                                                               the project WBS                                                                                                                                                     $0.0
                                                             Procedures Development                                                                                                                                                                                                                        731384.06.05.32.04
               $0.0             $0.0                                  and Control                                                                                                                                                                                                                                 $0.0
               731384.07                                    reserved
               731384.08                                    reserved
               731384.09                                    reserved
               731384.10                                        Integrated Testing and      731384.10.29                                                                                                                                                               731384.10.31                          731384.10.32
               $0.0                                                    Facilities                $0.0                                                                                                                                                                      $0.0                                   $0.0
               731384.11                                         Education and Public       731384.11.29          731384.11.31                                                                                                                                                                               731384.11.32
   $0.0        $0.0                                                    Outreach                  $0.0                 $0.0                                                                                                                                                                                        $0.0
                                                                                                                                                                                                                                                                                                                                5
WBS and CA Levels

  ♦ Although the WBS expanded to a lower level, the summary level was requested as
    the control point
          •    Control points/CAMs identified as the ESPO WBS Leads
          •    The EVM implementation added “subsystem” summary lines between the Control Accounts and
               the Work Packages to match the expanded WBS
                  − Each subsystem has it’s own unique codes
                  − Allows easier summation of performance / costs at the subsystem level
  ♦ The implementation strategy works, but in hindsight, it may have been better to use
    the lowest level of the WBS as the Control Account level
          •    CAMs would have multiple Control Accounts
          •    Budget changes between subsystems would be more closely tracked                            731384.06.04.01
                                                                                                            Suit Element
                                                     Pre-defined
          Excerpt of ESPO WBS                         CA Level
                                                                                            .31 Govt CA               .32 Prime CA
WBS       WBS Title
6.4.1     Suit Element                                                    .06.04.01.31.01 Suit Mgmt
6.4.1.1   Suit Element Management & Administration                         WP / PP
6.4.1.2   Suit Element SE&I                                                .06.04.01.31.01.01 – Suit Mgmt – IOC
6.4.1.3   Suit Element Safety                                              .06.04.01.31.01.a – Suit Mgmt – CxLEOOps
                                                                            Etc.
6.4.1.4   Pressure Garment Subsystem
6.4.1.5   Portable Life Support Subsystem                                 .06.04.01.31.02 Suit SE&I
          Power, Communication, Avionics, and                                  WP / PP
6.4.1.6   Informatics (CAI) Subsystem                                     .06.04.01.31.03 Suit Safety
6.4.1.7   Suit Ground Support Equipment (GSE)
                                                                                 WP / PP
                                                                          Etc.
                                                                                                                                     6
Work Packages (WP) / Charge Codes
                              & Planning Packages (PP)

                                                                              Excerpt of ESPO WP / PP
♦ The financial WBS / charge codes are
  maintained in SAP financial tool                                    WBS Elem ent Long Title                    Project/WBS
                                                                      Extravehicular Activity                    731384
     •   Over 400 charge codes previously existed in SAP              Project Management                         731384.01
         prior to EVM implementation due to multiple re-builds        Project Management                         731384.01.01
         (most codes never used)                                      Project Management and Administration      731384.01.01.01

     •   A “fresh” start was required for EVM                         GRC-Proj Mgt & Admin                       731384.01.01.01.03

           − Several ideas were explored                              LaRC-EVA Project Management                731384.01.01.01.04
                                                                                                                 731384.01.01.01.10
           − Preferred option was an easily recognizable unique       JSC-EVA-Project Mgmt.
                                                                      Project Management Plan                    731384.01.01.02
             numbering for the CA
                                                                      GRC-Proj Mgmt & Admin                      731384.01.01.03
           − All “old” codes collected in the historical CA
                                                                      Internal/External Project Review Support   731384.01.01.04

                                                                      LaRC-Internal/External Proj Review Spt     731384.01.01.04.04

♦ For CxP ESPO a WP equals a            731384.01.01.29               Performance Management and Review s        731384.01.01.05

                                                                      JSC-Proj Mgmt & Amin                       731384.01.01.10
  charge code equals the lowest WBS                                   NASA Project Management                    731384.01.01.31
  level                                                               JSC-EVA Project Mgmt - IOC                 731384.01.01.31.01

♦ Adhere to SAP rule that charge           Work Packages /            JSC-External Review Supt thru KDP C        731384.01.01.31.02
                                           Charge Codes               GRC-EVA Project Mgmt -IOC                  731384.01.01.31.03
  codes cannot cross NASA centers                                     LaRC-External Review Supt thru KDP C       731384.01.01.31.04

♦ PP identified as a letter in the code                               PP - JSC-EVA Project Mgmt - CxLEOOps       731384.01.01.31.a
                                                                                                                 731384.01.01.31.aa
  and are not in the SAP financial tool         Planning              PP - JSC-EVA Project Mgmt - CxLEOOps -2
                                                           Packages   PP - JSC-EVA Project Mgmt - HLR            731384.01.01.31.5a
     •   During rolling wave planning, a request                      PP - GRC-EVA Project Mgmt - HLR            731384.01.01.31.5b
         for a new charge code will be submitted                      JSC-CSSS Project Managment                 731384.01.01.32
         for the next sequential number to be
         opened in SAP
                                                                                                                                      7
Integrated Master Plan (IMP)
♦ NASA Project life cycle defined in NPR
  7120.5D, starting point used to define                                                         Constellation Program

  the ESPO IMP                                                                                 EVA Systems Project Office
                                                                                         Lunar Capability Integrated Master Plan
                                                         IMP                                                            Significant                Accomplishment
♦ CxP ESPO defined as two separate                     L
                                                        Code
                                                                  Lunar Capability
                                                                                        Event                        Accomplishment                    Criteria


  Projects, Initial Capability and Lunar               L.A
                                                       L.B
                                                                  Requirements Development & System Definition
                                                                  Preliminary Design
                                                       L.C        Final Design
  Capability, that are linked                          L.D
                                                       L.E
                                                                  System Assembly, Integration, and Test Constellation Program
                                                                  Operations & Sustainment                 EVA Systems Project Office

♦ IMP needs to capture all work content                L.S
                                                       L.T
                                                                  Manufacturing
                                                                 IMP Systems Tools
                                                                  EVA
                                                                Code                         Event
                                                                                                   Initial Capability Integrated Master Plan
                                                                                                                               Significant
                                                                                                                             Accomplishment       Accomplishment Criteria
                                                       L.U        GSE
  of the entire Project                                L.V
                                                       L.W
                                                             I Facilities and TSE
                                                                         Initial Capability
                                                                         Requirements Development & System Definition
                                                             I.A Management and Integration

    •
                                                             I.B         Preliminary Design
                                                       L.X        Constellation Program Integration
        IMP events added for work content that is      L.F
                                                             I.B.02
                                                                  Decommissioning and Close-out
                                                             I.B.04
                                                                                                                          VIE PDR
                                                                                                                       Suit Element PDR
        not readily defined by the life cycle phases         I.B.05                                                    EVA Systems PDR
                                                                                                                                               EVA Systems PDR Planning

    •
                                                             I.B.05.a                                                                          Complete
        IMP jointly developed with the Prime                 I.B.05.b
                                                                                                                                               EVA Systems PDR Requirements
                                                                                                                                               Analysis Cycle Complete
                                                                                                                                               EVA Systems PDR Design
                                                             I.B.05.c                                                                          Analysis Cycle Complete
                                                                                                                                               EVA Systems PDR Hardware
                                                             I.B.05.d                                                                          Complete
                                                                                                                                               EVA Systems PDR Testing
                                                             I.B.05.e                                                                          Complete
                                                                                                                                               EVA Systems PDR Products
                                                             I.B.05.f                                                                          Complete
                                                                                                                                               EVA Systems PDR Execution
                                                             I.B.05.g                                                                          Complete
                                                                                                                       Phase B Independent
                                                             I.B.06                                                    Reviews
                                                                                                                                               EVA Systems PDR SRB Activities
                                                             I.B.06.a                                                                          Complete
                                                                                                                                               Non-advocate Review (NAR) / KDP
                                                             I.B.06.b                                                                          C Gate Review Complete
                                                             I.C        Final Design
                                                             I.D        System Test and Operational Readiness
                                                             I.E        Operations & Sustainment
                                                             I.S        Manufacturing
                                                             I.T        EVA Systems Tools
                                                             I.U        GSE
                                                             I.V        Facilities and TSE
                                                             I.W        Management and Integration
                                                             I.X        Constellation Program Integration
                                                             I.Y        Award and Transition
                                                             I.F        Decommissioning and Close-out




                                                                                                                                                                                 8
Integrated Master Schedule (IMS)
                    Primavera PM Tool Implementation
♦ The Primavera IMS developed with Resource Loaded (RL) activities linked to
  the budget WP / PP in Deltek Cobra
    •   Activities were originally resource loaded in the Primavera IMS
          − Discovered resource loading easier to customize in Deltek Cobra as compared to Primavera
          − Resources removed from IMS and only the activity dates and % completes are now linked
    •   Additional schedule detail added to the IMS by the rolling wave method
♦ All activities are also tagged with an IMP code for an event-driven view




                                                                                                       9
Deltek Cobra Tool Implementation
    WBS / OBS / CA Structure


          Control Accounts (CA)
               match RAM




     Multiple WP make up
           each CA




           .00 WBS created to
          track budget funding
                 marks




                                   10
Integration / Interface with Other Processes / Tools

                               WP/PP Structure/Tasks
IMP/IMS                        Start/End Dates
Primavera PM
                               Schedule risk estimate                                      Joint Confidence Level (JCL)
                               Time Dependent                                              Primavera PertMaster
Start/End Dates
                               Time Independent                                            JCL analysis
% Completes                                             Risk
                                                        Cx IRMA
                                                        Discrete Risks

                                                                          WP/PP Structure
                                                          Likelihood      BAC                  ETC/EAC
                                          MR estimate
                                                          Cost Impact     Cost risk estimate   Validation




                                               EVMS
                                               Deltek Cobra                                                   Fund Reporting
                                               BAC                                                            CIRR & JSC IBOT
                                                                                                              ETC/EAC
                                               ETC/EAC                                                        Fund variance
                                               MR
             ETC/EAC Updates
             FY Funding Constraints




Fund Planning
CIRR & JSC IBOT
PPBE = Comprehensive ETC/EAC update                                                                         EVM Analysis
PPBE = FY Funding Constraints                                      Financials                               Deltek wInsight
JSC ITA = Routine EAC update (at least quarterly)                  SAP/Business Warehouse                   SPI / CPI
                                                                   Actuals                                  Formats 1-5


                                                                                                                                11
EVM Integration with Prime Contractor
                                                                          Cx PAD
♦ Driving requirement is NOT                                                                              EVA Systems Project
                                                                         TAB
  to replicate Prime EVM                                        AUW     OVERRUN
                                                                                                                     .31 CA budget
  data within Project data                                      NCC      PBB        OTB
                                                                                                                     .32 CA budget
♦ Utilize Deltek wInsight tool
                                                       Mgmt Reserve               PMB
  to integrate Prime EVM
  data with ESPO EVM data                       Undistributed
                                                  Budget
                                                                  Distributed
                                                                   Budget
                                                                                      Summary Level
                                                                                    Planning Packages
♦ Items that must be
                                            Work      Planning         Planning      Planning              Contract Price (Prime)
  addressed to integrate                  Packages    Packages        Packages**    Packages         Total Allocated Budget      Work
                                                                        (IDIQ)      (Prime not                                 Package
  data:                                          Closed                            on contract)
                                                                                                      Planning
                                                                                                     Package
                                                                                                                    PMB
                                                                                                                              (award fee)
    •   Management Reserve (MR)                 Packages                                            (Prime MR)

    •   Undistributed Budget (UB)       **IDIQ budget has
    •   Summary Level Planning          been distributed to                                    Contract Price
                                        the CAMs to manage
        Packages
                                                                                                    TAB                      Award
    •   Prime Award Fee                                                                  AUW       OVERRUN                    Fee
    •   IDIQ content                                                                    NCC        CBB         OTB


    •   Differences between Cx PAD and Prime
                                                                        Mgmt Reserve           PMB                               Prime
        contract periods of performance
    •   Differences between Prime contract value and                    Undistributed      Distributed         Summary Level
                                                                          Budget            Budget           Planning Packages
        Government probable cost
                                                                        Closed            Work           Planning
                                                                       Packages         Packages         Packages




                                                                                                                                            12
Future Opportunities for Improvement

♦ NASA financial systems (SAP) not fully compatible with EVM
    •   SAP set up as a cost collection system, not necessarily a performance measurement system
          − Requires obligation of funds at the lowest level of detail, i.e. the charge code for ESPO
          − System cumbersome on Procurement personnel to de-obligate & re-obligate funds from old to new charge
            codes
          − System sometimes creates situations of lagging actuals due to obligations at the lowest level, i.e. cost over
            obligations
          − System cumbersome with regards to timely creation and inability to close charge codes and does not limit
            access to charge codes
          − These issues have forced the creation of long duration work / planning packages (multiple years)
♦ Continued training for understanding of Earned Value concepts, in particular,
  separation of budget versus funding
    •   Existing NASA processes (PPBE, JSC ITA, etc.) are funding processes that are being used
        synonymously with EVM budget processes
          − They should be linked to EVM funding processes (ETC / EAC)
♦ Not all organization support contracts structured to collect and report data to
  support Cx Project EVM requirements
    •   Contract structure forces organizations to "guess" on the monthly costs collected against charge
        codes by applying estimates since data reported at a summary level
    •   Manual entry process of support contract data into SAP precludes detailed data due to the time
        requirements to enter the data



                                                                                                                            13
Acronyms and Reference Documents

♦   Acronyms                                                      ♦   Reference Documents
     •   CA – Control Account                                          •   NPR 7120.5D – NASA Program and Project
     •   CAM – Control Account Manager                                     Management Processes and Requirements
     •   CIRR - CxP Integrated Resources Report                        •   CxP 72179 – CxP ESPO Project Plan
     •   CPR – Cost Performance Report                                 •   CxP 72179 Anx01 – CxP ESPO EVM
     •   CxP – Constellation Program                                       Implementation Plan
     •   ESPO – EVA Systems Project Office                             •   CxP 72179 Anx03 – CxP ESPO IMP/IMS
                                                                           Implementation Plan
     •   EVA – Extravehicular Activity
                                                                       •   ANSI/EIA-748 – Earned Value Management
     •   EVM – Earned Value Management                                     Systems
     •   EVMS – Earned Value Management System
     •   IBOT - Integrated Budget Office Toolkit
     •   IDIQ – Indefinite Delivery, Indefinite Quantity
     •   IMP – Integrated Master Plan
     •   IMS – Integrated Master Schedule
     •   IRMA – Integrated Risk Management Application
     •   ITA - Internal Task Agreement
     •   JCL - Joint Confidence Level
     •   JSC – Johnson Space Center
     •   NPR - NASA Procedural Requirements
     •   OBS – Organizational Breakdown Structure
     •   PAD – Project Authorization Document
     •   PP – Planning Package
     •   PPBE - Planning, Programming, Budgeting, and Execution
     •   RAM – Responsibility Assignment Matrix
     •   RL – Resource Loaded
     •   SAP – Systems Application and Products
     •   WBS – Work Breakdown Structure
     •   WP – Work Package



                                                                                                                    14
Questions & Answers




                      15

More Related Content

What's hot

Dennehy richard mrozinski
Dennehy richard mrozinskiDennehy richard mrozinski
Dennehy richard mrozinski
NASAPMC
 
Daisy.mueller
Daisy.muellerDaisy.mueller
Daisy.mueller
NASAPMC
 
Armstrong
ArmstrongArmstrong
Armstrong
NASAPMC
 
Carsile.azarbain
Carsile.azarbainCarsile.azarbain
Carsile.azarbain
NASAPMC
 
Bauer.frank
Bauer.frankBauer.frank
Bauer.frank
NASAPMC
 
Nona.cheeks
Nona.cheeksNona.cheeks
Nona.cheeks
NASAPMC
 
Lau.cheevon
Lau.cheevonLau.cheevon
Lau.cheevon
NASAPMC
 
R simpson elee
R simpson eleeR simpson elee
R simpson elee
NASAPMC
 
Keer.beth
Keer.bethKeer.beth
Keer.beth
NASAPMC
 
Ingoldsby.k.lee.y
Ingoldsby.k.lee.yIngoldsby.k.lee.y
Ingoldsby.k.lee.y
NASAPMC
 
Bladwin.kristen
Bladwin.kristenBladwin.kristen
Bladwin.kristen
NASAPMC
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_case
NASAPMC
 
Fayssal.safie
Fayssal.safieFayssal.safie
Fayssal.safie
NASAPMC
 
Solomon.paul
Solomon.paulSolomon.paul
Solomon.paul
NASAPMC
 
Carol.scott
Carol.scottCarol.scott
Carol.scott
NASAPMC
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.james
NASAPMC
 
Harvey elliott
Harvey elliottHarvey elliott
Harvey elliott
NASAPMC
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinal
NASAPMC
 
Graham dave
Graham daveGraham dave
Graham dave
NASAPMC
 
Mullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseMullane stanley-hamilton-wise
Mullane stanley-hamilton-wise
NASAPMC
 

What's hot (20)

Dennehy richard mrozinski
Dennehy richard mrozinskiDennehy richard mrozinski
Dennehy richard mrozinski
 
Daisy.mueller
Daisy.muellerDaisy.mueller
Daisy.mueller
 
Armstrong
ArmstrongArmstrong
Armstrong
 
Carsile.azarbain
Carsile.azarbainCarsile.azarbain
Carsile.azarbain
 
Bauer.frank
Bauer.frankBauer.frank
Bauer.frank
 
Nona.cheeks
Nona.cheeksNona.cheeks
Nona.cheeks
 
Lau.cheevon
Lau.cheevonLau.cheevon
Lau.cheevon
 
R simpson elee
R simpson eleeR simpson elee
R simpson elee
 
Keer.beth
Keer.bethKeer.beth
Keer.beth
 
Ingoldsby.k.lee.y
Ingoldsby.k.lee.yIngoldsby.k.lee.y
Ingoldsby.k.lee.y
 
Bladwin.kristen
Bladwin.kristenBladwin.kristen
Bladwin.kristen
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_case
 
Fayssal.safie
Fayssal.safieFayssal.safie
Fayssal.safie
 
Solomon.paul
Solomon.paulSolomon.paul
Solomon.paul
 
Carol.scott
Carol.scottCarol.scott
Carol.scott
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.james
 
Harvey elliott
Harvey elliottHarvey elliott
Harvey elliott
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinal
 
Graham dave
Graham daveGraham dave
Graham dave
 
Mullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseMullane stanley-hamilton-wise
Mullane stanley-hamilton-wise
 

Viewers also liked

Fuller.david
Fuller.davidFuller.david
Fuller.david
NASAPMC
 
Miller.charles
Miller.charlesMiller.charles
Miller.charles
NASAPMC
 
Sharyl butler
Sharyl butlerSharyl butler
Sharyl butler
NASAPMC
 
Odum.t.averbeck.r
Odum.t.averbeck.rOdum.t.averbeck.r
Odum.t.averbeck.r
NASAPMC
 
Law.richard
Law.richardLaw.richard
Law.richard
NASAPMC
 
Mark wiese
Mark wieseMark wiese
Mark wiese
NASAPMC
 
Inter succes partnerships
Inter succes partnershipsInter succes partnerships
Inter succes partnerships
NASAPMC
 
Daniel.dvorak
Daniel.dvorakDaniel.dvorak
Daniel.dvorak
NASAPMC
 
Ken poole
Ken pooleKen poole
Ken poole
NASAPMC
 
Robert.bayt
Robert.baytRobert.bayt
Robert.bayt
NASAPMC
 
Shinn
ShinnShinn
Shinn
NASAPMC
 
Mc namara.karen
Mc namara.karenMc namara.karen
Mc namara.karen
NASAPMC
 
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pgGeorgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pgNASAPMC
 
Heitzman.askins
Heitzman.askinsHeitzman.askins
Heitzman.askins
NASAPMC
 
Muirhead.brian
Muirhead.brianMuirhead.brian
Muirhead.brian
NASAPMC
 
Gilbert.jonathan
Gilbert.jonathanGilbert.jonathan
Gilbert.jonathan
NASAPMC
 
Brian muirhead v1-27-12
Brian muirhead v1-27-12Brian muirhead v1-27-12
Brian muirhead v1-27-12
NASAPMC
 
Weaver.ed
Weaver.edWeaver.ed
Weaver.ed
NASAPMC
 
Hazen michael
Hazen michaelHazen michael
Hazen michael
NASAPMC
 
Yonce.clayton
Yonce.claytonYonce.clayton
Yonce.clayton
NASAPMC
 

Viewers also liked (20)

Fuller.david
Fuller.davidFuller.david
Fuller.david
 
Miller.charles
Miller.charlesMiller.charles
Miller.charles
 
Sharyl butler
Sharyl butlerSharyl butler
Sharyl butler
 
Odum.t.averbeck.r
Odum.t.averbeck.rOdum.t.averbeck.r
Odum.t.averbeck.r
 
Law.richard
Law.richardLaw.richard
Law.richard
 
Mark wiese
Mark wieseMark wiese
Mark wiese
 
Inter succes partnerships
Inter succes partnershipsInter succes partnerships
Inter succes partnerships
 
Daniel.dvorak
Daniel.dvorakDaniel.dvorak
Daniel.dvorak
 
Ken poole
Ken pooleKen poole
Ken poole
 
Robert.bayt
Robert.baytRobert.bayt
Robert.bayt
 
Shinn
ShinnShinn
Shinn
 
Mc namara.karen
Mc namara.karenMc namara.karen
Mc namara.karen
 
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pgGeorgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
 
Heitzman.askins
Heitzman.askinsHeitzman.askins
Heitzman.askins
 
Muirhead.brian
Muirhead.brianMuirhead.brian
Muirhead.brian
 
Gilbert.jonathan
Gilbert.jonathanGilbert.jonathan
Gilbert.jonathan
 
Brian muirhead v1-27-12
Brian muirhead v1-27-12Brian muirhead v1-27-12
Brian muirhead v1-27-12
 
Weaver.ed
Weaver.edWeaver.ed
Weaver.ed
 
Hazen michael
Hazen michaelHazen michael
Hazen michael
 
Yonce.clayton
Yonce.claytonYonce.clayton
Yonce.clayton
 

Similar to Les.sorge

Dev High Level Process Flow 0.7
Dev High Level Process Flow 0.7Dev High Level Process Flow 0.7
Dev High Level Process Flow 0.7
Mark Bethel
 
SAP PS Intro
SAP PS IntroSAP PS Intro
SAP PS Intro
Naga Venkata K
 
Warren.d.harrison.g
Warren.d.harrison.gWarren.d.harrison.g
Warren.d.harrison.g
NASAPMC
 
Enable Large Scale, High Volume Deployment For Enterprise Applications
Enable Large Scale, High Volume Deployment For Enterprise ApplicationsEnable Large Scale, High Volume Deployment For Enterprise Applications
Enable Large Scale, High Volume Deployment For Enterprise Applications
Clever Moe
 
Nek e am_overview_2010_1f.ppt [compatibility m
Nek e am_overview_2010_1f.ppt [compatibility mNek e am_overview_2010_1f.ppt [compatibility m
Nek e am_overview_2010_1f.ppt [compatibility m
Oracle Hrvatska
 
Ayyadevara Rangadham 1203
Ayyadevara Rangadham 1203Ayyadevara Rangadham 1203
Ayyadevara Rangadham 1203
Rangadham Ayyadevara
 
Byron Pang (LinkedIn- Oct 2014)
Byron Pang (LinkedIn- Oct 2014)Byron Pang (LinkedIn- Oct 2014)
Byron Pang (LinkedIn- Oct 2014)
Byron Pang
 
Semantics to energize the full Services Spectrum: Ontological approach to be...
Semantics to energize  the full Services Spectrum: Ontological approach to be...Semantics to energize  the full Services Spectrum: Ontological approach to be...
Semantics to energize the full Services Spectrum: Ontological approach to be...
Amit Sheth
 
Global automation equipment leader gains scalability through upgrades
Global automation equipment leader gains scalability through upgradesGlobal automation equipment leader gains scalability through upgrades
Global automation equipment leader gains scalability through upgrades
Hazelknight Media & Entertainment Pvt Ltd
 
Riverbed's presentation at SFSE Meetup 2/22
Riverbed's presentation at SFSE Meetup 2/22Riverbed's presentation at SFSE Meetup 2/22
Riverbed's presentation at SFSE Meetup 2/22
Sauce Labs
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
NASAPMC
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
NASAPMC
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
NASAPMC
 
Sap solutions presentation
Sap solutions presentationSap solutions presentation
Sap solutions presentation
Kumar M.
 
IRJET- Analysis of Pre-Engineered Building and Conventional Building usin...
IRJET-  	  Analysis of Pre-Engineered Building and Conventional Building usin...IRJET-  	  Analysis of Pre-Engineered Building and Conventional Building usin...
IRJET- Analysis of Pre-Engineered Building and Conventional Building usin...
IRJET Journal
 
50 Things About Digital
50 Things About Digital50 Things About Digital
50 Things About Digital
John Yuiska
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value Management
Unanet
 
Week 10 - 22W Students.pdf
Week 10 - 22W Students.pdfWeek 10 - 22W Students.pdf
Week 10 - 22W Students.pdf
AnshulAggarwal94
 
SuccessFactors 2H 2021 Sneak Peek by Deloitte Germany
SuccessFactors 2H 2021 Sneak Peek by Deloitte GermanySuccessFactors 2H 2021 Sneak Peek by Deloitte Germany
SuccessFactors 2H 2021 Sneak Peek by Deloitte Germany
Christoph Pohl
 
Messing
MessingMessing
Messing
NASAPMC
 

Similar to Les.sorge (20)

Dev High Level Process Flow 0.7
Dev High Level Process Flow 0.7Dev High Level Process Flow 0.7
Dev High Level Process Flow 0.7
 
SAP PS Intro
SAP PS IntroSAP PS Intro
SAP PS Intro
 
Warren.d.harrison.g
Warren.d.harrison.gWarren.d.harrison.g
Warren.d.harrison.g
 
Enable Large Scale, High Volume Deployment For Enterprise Applications
Enable Large Scale, High Volume Deployment For Enterprise ApplicationsEnable Large Scale, High Volume Deployment For Enterprise Applications
Enable Large Scale, High Volume Deployment For Enterprise Applications
 
Nek e am_overview_2010_1f.ppt [compatibility m
Nek e am_overview_2010_1f.ppt [compatibility mNek e am_overview_2010_1f.ppt [compatibility m
Nek e am_overview_2010_1f.ppt [compatibility m
 
Ayyadevara Rangadham 1203
Ayyadevara Rangadham 1203Ayyadevara Rangadham 1203
Ayyadevara Rangadham 1203
 
Byron Pang (LinkedIn- Oct 2014)
Byron Pang (LinkedIn- Oct 2014)Byron Pang (LinkedIn- Oct 2014)
Byron Pang (LinkedIn- Oct 2014)
 
Semantics to energize the full Services Spectrum: Ontological approach to be...
Semantics to energize  the full Services Spectrum: Ontological approach to be...Semantics to energize  the full Services Spectrum: Ontological approach to be...
Semantics to energize the full Services Spectrum: Ontological approach to be...
 
Global automation equipment leader gains scalability through upgrades
Global automation equipment leader gains scalability through upgradesGlobal automation equipment leader gains scalability through upgrades
Global automation equipment leader gains scalability through upgrades
 
Riverbed's presentation at SFSE Meetup 2/22
Riverbed's presentation at SFSE Meetup 2/22Riverbed's presentation at SFSE Meetup 2/22
Riverbed's presentation at SFSE Meetup 2/22
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
 
Sap solutions presentation
Sap solutions presentationSap solutions presentation
Sap solutions presentation
 
IRJET- Analysis of Pre-Engineered Building and Conventional Building usin...
IRJET-  	  Analysis of Pre-Engineered Building and Conventional Building usin...IRJET-  	  Analysis of Pre-Engineered Building and Conventional Building usin...
IRJET- Analysis of Pre-Engineered Building and Conventional Building usin...
 
50 Things About Digital
50 Things About Digital50 Things About Digital
50 Things About Digital
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value Management
 
Week 10 - 22W Students.pdf
Week 10 - 22W Students.pdfWeek 10 - 22W Students.pdf
Week 10 - 22W Students.pdf
 
SuccessFactors 2H 2021 Sneak Peek by Deloitte Germany
SuccessFactors 2H 2021 Sneak Peek by Deloitte GermanySuccessFactors 2H 2021 Sneak Peek by Deloitte Germany
SuccessFactors 2H 2021 Sneak Peek by Deloitte Germany
 
Messing
MessingMessing
Messing
 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
NASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
NASAPMC
 
Yew manson
Yew mansonYew manson
Yew manson
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
NASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
NASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahm
NASAPMC
 
Snow lee
Snow leeSnow lee
Snow lee
NASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
NASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
NASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
NASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
NASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
NASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
NASAPMC
 
Paradis william
Paradis williamParadis william
Paradis william
NASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
NASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
NASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
NASAPMC
 

More from NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Recently uploaded

GraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracyGraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracy
Tomaz Bratanic
 
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Tatiana Kojar
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
Pixlogix Infotech
 
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing InstancesEnergy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Alpen-Adria-Universität
 
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
saastr
 
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Jeffrey Haguewood
 
Programming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup SlidesProgramming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup Slides
Zilliz
 
System Design Case Study: Building a Scalable E-Commerce Platform - Hiike
System Design Case Study: Building a Scalable E-Commerce Platform - HiikeSystem Design Case Study: Building a Scalable E-Commerce Platform - Hiike
System Design Case Study: Building a Scalable E-Commerce Platform - Hiike
Hiike
 
FREE A4 Cyber Security Awareness Posters-Social Engineering part 3
FREE A4 Cyber Security Awareness  Posters-Social Engineering part 3FREE A4 Cyber Security Awareness  Posters-Social Engineering part 3
FREE A4 Cyber Security Awareness Posters-Social Engineering part 3
Data Hops
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
panagenda
 
Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)
Jakub Marek
 
“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...
“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...
“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...
Edge AI and Vision Alliance
 
Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024
Jason Packer
 
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their MainframeDigital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Precisely
 
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-EfficiencyFreshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
ScyllaDB
 
Astute Business Solutions | Oracle Cloud Partner |
Astute Business Solutions | Oracle Cloud Partner |Astute Business Solutions | Oracle Cloud Partner |
Astute Business Solutions | Oracle Cloud Partner |
AstuteBusiness
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
shyamraj55
 
zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...
zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...
zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...
Alex Pruden
 
Introduction of Cybersecurity with OSS at Code Europe 2024
Introduction of Cybersecurity with OSS  at Code Europe 2024Introduction of Cybersecurity with OSS  at Code Europe 2024
Introduction of Cybersecurity with OSS at Code Europe 2024
Hiroshi SHIBATA
 
Dandelion Hashtable: beyond billion requests per second on a commodity server
Dandelion Hashtable: beyond billion requests per second on a commodity serverDandelion Hashtable: beyond billion requests per second on a commodity server
Dandelion Hashtable: beyond billion requests per second on a commodity server
Antonios Katsarakis
 

Recently uploaded (20)

GraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracyGraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracy
 
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
 
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing InstancesEnergy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
 
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
 
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
 
Programming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup SlidesProgramming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup Slides
 
System Design Case Study: Building a Scalable E-Commerce Platform - Hiike
System Design Case Study: Building a Scalable E-Commerce Platform - HiikeSystem Design Case Study: Building a Scalable E-Commerce Platform - Hiike
System Design Case Study: Building a Scalable E-Commerce Platform - Hiike
 
FREE A4 Cyber Security Awareness Posters-Social Engineering part 3
FREE A4 Cyber Security Awareness  Posters-Social Engineering part 3FREE A4 Cyber Security Awareness  Posters-Social Engineering part 3
FREE A4 Cyber Security Awareness Posters-Social Engineering part 3
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
 
Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)
 
“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...
“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...
“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...
 
Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024
 
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their MainframeDigital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
 
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-EfficiencyFreshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
 
Astute Business Solutions | Oracle Cloud Partner |
Astute Business Solutions | Oracle Cloud Partner |Astute Business Solutions | Oracle Cloud Partner |
Astute Business Solutions | Oracle Cloud Partner |
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
 
zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...
zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...
zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...
 
Introduction of Cybersecurity with OSS at Code Europe 2024
Introduction of Cybersecurity with OSS  at Code Europe 2024Introduction of Cybersecurity with OSS  at Code Europe 2024
Introduction of Cybersecurity with OSS at Code Europe 2024
 
Dandelion Hashtable: beyond billion requests per second on a commodity server
Dandelion Hashtable: beyond billion requests per second on a commodity serverDandelion Hashtable: beyond billion requests per second on a commodity server
Dandelion Hashtable: beyond billion requests per second on a commodity server
 

Les.sorge

  • 1. Implementing Earned Value Management in the CxP ESPO Project Management Challenge 2010 Galveston, TX February 9-10, 2010 Les Sorge/SGT, Inc. ESPO Project Planning & Control Used with Permission
  • 2. Implementation Goal & Presentation Agenda ♦ The goal of the EVA Systems Project Office (ESPO) Earned Value Management (EVM) implementation is to utilize existing products and processes where possible or influence them to make them compatible with EVM ♦ Agenda • Work Breakdown Structure • Organizational Breakdown Structure • Responsibility Assignment Matrix and Control Accounts • Work Packages / Charge Codes and Planning Packages • Integrated Master Plan • Integrated Master Schedule – Primavera PM Tool Implementation • Deltek Cobra Tool Implementation • Integration / Interfaces to Other Processes / Tools • EVM Integration with Prime Contractor • Future Opportunities for Improvements • Acronyms and Reference Documents • Questions & Answers 2
  • 3. Work Breakdown Structure (WBS) ♦ Summary of WBS requirements defined in NPR 7120.5D, Appendix G • The standard space flight project WBS applies to the entire life cycle of the project • Space flight projects will use the standard Level 1/2 WBS elements with level 1 as the Project name • Level 3 and lower WBS elements will be determined by the project • If there is no work to fit into a Level 1/2 WBS element, then an inactive placeholder element will be established • A single WBS will be used for both technical / business management and reporting ♦ ESPO Implementation • The technical WBS matches the financial WBS excluding the 6 digit project code • The figure below represents the CxP reporting level and the pre-defined Control Account level Agency Defined Project Defined 3
  • 4. Organizational Breakdown Structure (OBS) ♦ Defining the responsible organization versus the performing organization • Ask the question, “How does the Project Manager distribute the budget for control?” ♦ The Responsible Organization • Used to develop the Responsibility Assignment Matrix (RAM) and Cost Performance Report (CPR) Format 2 • Aligns closely with the Work Breakdown Structure ♦ The Performing Organization • Based on NASA Center, Directorate, and Divisions − A budget forecasting requirement does exist for the performing organization for planning purposes NASA Performing Organization ESPO Responsible Organization 4
  • 5. Responsibility Assignment Matrix (RAM) & Control Accounts (CA) ♦ Prime added as an organization in the OBS per ANSI-748 guidance • This structure allows budgets to be segregated between prime and non-prime work while still reinforcing the “integrated project – NASA and Prime” philosophy of ESPO ♦ CA nomenclature used: .29 for historical, .31 for NASA/non-prime, .32 for Prime • .31 used for all NASA/non-prime organizations for easy recognition in SAP financial system − Nomenclature works since multiple organizations don’t support a WBS element ESPO RAM Rev #: 001 Budget in ($K) Constellation EVA Systems Project Office Date: 11/3/2009 $0.0 PAD #: CxP-EV-731384-P1-00 OBS $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 PAD Issue Date: 7/10/2009 Development Project Mgmt Historical CA Operations & Suit Element CSSS Prime Technology Testing and Planning & Equipment Sustaining Tools and Facilities Interface Element Element SR&QA Control Vehicle Project SE&I WBS Description 731384.01.01 Project Management 731384.01.01.29 731384.01.01.31 731284.01.01.32 731384.01 $0.0 $0.0 $0.0 $0.0 731384.01.02 Project Planning & Control 731384.01.02.29 731384.01.02.31 731384.01.02.32 $0.0 $0.0 $0.0 $0.0 $0.0 731384.02 Systems Engineering & 731384.02.29 731384.02.31 731384.02.32 $0.0 Integration $0.0 $0.0 $0.0 731384.03 Safety, Reliability and 731384.03.29 731384.03.31 731384.03.32 $0.0 Quality Assurance $0.0 $0.0 $0.0 731384.04 Technology Development 731384.04.29 731384.04.31 731384.04.32 $0.0 $0.0 $0.0 $0.0 731384.05 Payload(s) 731384.05.29 $0.0 $0.0 EVA Systems H/W 731384.06.01 Management 731384.06.02 reserved 731384.06.03 EVA Systems Sustaining 731384.06.03.29 731384.06.03.31 731384.06.03.32 $0.0 Engineering $0.0 $0.0 $0.0 731384.06.04.01 Suit Element 731384.06.04.01.29 731384.06.04.01.31 731384.06.04.01.32 $0.0 $0.0 $0.0 $0.0 731384 731384.06.04 731384.06.04.02 Tools and Equipment 731384.06.04.02.31 731384.06.04.02.32 $0.0 Element $0.0 $0.0 731384.06.04.03 Vehicle Interface Element 731384.06.04.03.29 731384.06.04.03.31 731384.06.04.03.32 731384.06 $0.0 $0.0 $0.0 $0.0 $0.0 Logistics, Processing and 731384.06.05.31 Inventory Mgmt $0.0 Logistics Planning Control Accounts identified in the 731384.06.05.32.01 $0.0 731384.06.05 Flight & Training Hardware 731384.06.05.32.02 Processing RAM create a natural extension to $0.0 Hardware Inventory 731384.06.05.32.03 Management the project WBS $0.0 Procedures Development 731384.06.05.32.04 $0.0 $0.0 and Control $0.0 731384.07 reserved 731384.08 reserved 731384.09 reserved 731384.10 Integrated Testing and 731384.10.29 731384.10.31 731384.10.32 $0.0 Facilities $0.0 $0.0 $0.0 731384.11 Education and Public 731384.11.29 731384.11.31 731384.11.32 $0.0 $0.0 Outreach $0.0 $0.0 $0.0 5
  • 6. WBS and CA Levels ♦ Although the WBS expanded to a lower level, the summary level was requested as the control point • Control points/CAMs identified as the ESPO WBS Leads • The EVM implementation added “subsystem” summary lines between the Control Accounts and the Work Packages to match the expanded WBS − Each subsystem has it’s own unique codes − Allows easier summation of performance / costs at the subsystem level ♦ The implementation strategy works, but in hindsight, it may have been better to use the lowest level of the WBS as the Control Account level • CAMs would have multiple Control Accounts • Budget changes between subsystems would be more closely tracked 731384.06.04.01 Suit Element Pre-defined Excerpt of ESPO WBS CA Level .31 Govt CA .32 Prime CA WBS WBS Title 6.4.1 Suit Element .06.04.01.31.01 Suit Mgmt 6.4.1.1 Suit Element Management & Administration WP / PP 6.4.1.2 Suit Element SE&I .06.04.01.31.01.01 – Suit Mgmt – IOC 6.4.1.3 Suit Element Safety .06.04.01.31.01.a – Suit Mgmt – CxLEOOps Etc. 6.4.1.4 Pressure Garment Subsystem 6.4.1.5 Portable Life Support Subsystem .06.04.01.31.02 Suit SE&I Power, Communication, Avionics, and WP / PP 6.4.1.6 Informatics (CAI) Subsystem .06.04.01.31.03 Suit Safety 6.4.1.7 Suit Ground Support Equipment (GSE) WP / PP Etc. 6
  • 7. Work Packages (WP) / Charge Codes & Planning Packages (PP) Excerpt of ESPO WP / PP ♦ The financial WBS / charge codes are maintained in SAP financial tool WBS Elem ent Long Title Project/WBS Extravehicular Activity 731384 • Over 400 charge codes previously existed in SAP Project Management 731384.01 prior to EVM implementation due to multiple re-builds Project Management 731384.01.01 (most codes never used) Project Management and Administration 731384.01.01.01 • A “fresh” start was required for EVM GRC-Proj Mgt & Admin 731384.01.01.01.03 − Several ideas were explored LaRC-EVA Project Management 731384.01.01.01.04 731384.01.01.01.10 − Preferred option was an easily recognizable unique JSC-EVA-Project Mgmt. Project Management Plan 731384.01.01.02 numbering for the CA GRC-Proj Mgmt & Admin 731384.01.01.03 − All “old” codes collected in the historical CA Internal/External Project Review Support 731384.01.01.04 LaRC-Internal/External Proj Review Spt 731384.01.01.04.04 ♦ For CxP ESPO a WP equals a 731384.01.01.29 Performance Management and Review s 731384.01.01.05 JSC-Proj Mgmt & Amin 731384.01.01.10 charge code equals the lowest WBS NASA Project Management 731384.01.01.31 level JSC-EVA Project Mgmt - IOC 731384.01.01.31.01 ♦ Adhere to SAP rule that charge Work Packages / JSC-External Review Supt thru KDP C 731384.01.01.31.02 Charge Codes GRC-EVA Project Mgmt -IOC 731384.01.01.31.03 codes cannot cross NASA centers LaRC-External Review Supt thru KDP C 731384.01.01.31.04 ♦ PP identified as a letter in the code PP - JSC-EVA Project Mgmt - CxLEOOps 731384.01.01.31.a 731384.01.01.31.aa and are not in the SAP financial tool Planning PP - JSC-EVA Project Mgmt - CxLEOOps -2 Packages PP - JSC-EVA Project Mgmt - HLR 731384.01.01.31.5a • During rolling wave planning, a request PP - GRC-EVA Project Mgmt - HLR 731384.01.01.31.5b for a new charge code will be submitted JSC-CSSS Project Managment 731384.01.01.32 for the next sequential number to be opened in SAP 7
  • 8. Integrated Master Plan (IMP) ♦ NASA Project life cycle defined in NPR 7120.5D, starting point used to define Constellation Program the ESPO IMP EVA Systems Project Office Lunar Capability Integrated Master Plan IMP Significant Accomplishment ♦ CxP ESPO defined as two separate L Code Lunar Capability Event Accomplishment Criteria Projects, Initial Capability and Lunar L.A L.B Requirements Development & System Definition Preliminary Design L.C Final Design Capability, that are linked L.D L.E System Assembly, Integration, and Test Constellation Program Operations & Sustainment EVA Systems Project Office ♦ IMP needs to capture all work content L.S L.T Manufacturing IMP Systems Tools EVA Code Event Initial Capability Integrated Master Plan Significant Accomplishment Accomplishment Criteria L.U GSE of the entire Project L.V L.W I Facilities and TSE Initial Capability Requirements Development & System Definition I.A Management and Integration • I.B Preliminary Design L.X Constellation Program Integration IMP events added for work content that is L.F I.B.02 Decommissioning and Close-out I.B.04 VIE PDR Suit Element PDR not readily defined by the life cycle phases I.B.05 EVA Systems PDR EVA Systems PDR Planning • I.B.05.a Complete IMP jointly developed with the Prime I.B.05.b EVA Systems PDR Requirements Analysis Cycle Complete EVA Systems PDR Design I.B.05.c Analysis Cycle Complete EVA Systems PDR Hardware I.B.05.d Complete EVA Systems PDR Testing I.B.05.e Complete EVA Systems PDR Products I.B.05.f Complete EVA Systems PDR Execution I.B.05.g Complete Phase B Independent I.B.06 Reviews EVA Systems PDR SRB Activities I.B.06.a Complete Non-advocate Review (NAR) / KDP I.B.06.b C Gate Review Complete I.C Final Design I.D System Test and Operational Readiness I.E Operations & Sustainment I.S Manufacturing I.T EVA Systems Tools I.U GSE I.V Facilities and TSE I.W Management and Integration I.X Constellation Program Integration I.Y Award and Transition I.F Decommissioning and Close-out 8
  • 9. Integrated Master Schedule (IMS) Primavera PM Tool Implementation ♦ The Primavera IMS developed with Resource Loaded (RL) activities linked to the budget WP / PP in Deltek Cobra • Activities were originally resource loaded in the Primavera IMS − Discovered resource loading easier to customize in Deltek Cobra as compared to Primavera − Resources removed from IMS and only the activity dates and % completes are now linked • Additional schedule detail added to the IMS by the rolling wave method ♦ All activities are also tagged with an IMP code for an event-driven view 9
  • 10. Deltek Cobra Tool Implementation WBS / OBS / CA Structure Control Accounts (CA) match RAM Multiple WP make up each CA .00 WBS created to track budget funding marks 10
  • 11. Integration / Interface with Other Processes / Tools WP/PP Structure/Tasks IMP/IMS Start/End Dates Primavera PM Schedule risk estimate Joint Confidence Level (JCL) Time Dependent Primavera PertMaster Start/End Dates Time Independent JCL analysis % Completes Risk Cx IRMA Discrete Risks WP/PP Structure Likelihood BAC ETC/EAC MR estimate Cost Impact Cost risk estimate Validation EVMS Deltek Cobra Fund Reporting BAC CIRR & JSC IBOT ETC/EAC ETC/EAC Fund variance MR ETC/EAC Updates FY Funding Constraints Fund Planning CIRR & JSC IBOT PPBE = Comprehensive ETC/EAC update EVM Analysis PPBE = FY Funding Constraints Financials Deltek wInsight JSC ITA = Routine EAC update (at least quarterly) SAP/Business Warehouse SPI / CPI Actuals Formats 1-5 11
  • 12. EVM Integration with Prime Contractor Cx PAD ♦ Driving requirement is NOT EVA Systems Project TAB to replicate Prime EVM AUW OVERRUN .31 CA budget data within Project data NCC PBB OTB .32 CA budget ♦ Utilize Deltek wInsight tool Mgmt Reserve PMB to integrate Prime EVM data with ESPO EVM data Undistributed Budget Distributed Budget Summary Level Planning Packages ♦ Items that must be Work Planning Planning Planning Contract Price (Prime) addressed to integrate Packages Packages Packages** Packages Total Allocated Budget Work (IDIQ) (Prime not Package data: Closed on contract) Planning Package PMB (award fee) • Management Reserve (MR) Packages (Prime MR) • Undistributed Budget (UB) **IDIQ budget has • Summary Level Planning been distributed to Contract Price the CAMs to manage Packages TAB Award • Prime Award Fee AUW OVERRUN Fee • IDIQ content NCC CBB OTB • Differences between Cx PAD and Prime Mgmt Reserve PMB Prime contract periods of performance • Differences between Prime contract value and Undistributed Distributed Summary Level Budget Budget Planning Packages Government probable cost Closed Work Planning Packages Packages Packages 12
  • 13. Future Opportunities for Improvement ♦ NASA financial systems (SAP) not fully compatible with EVM • SAP set up as a cost collection system, not necessarily a performance measurement system − Requires obligation of funds at the lowest level of detail, i.e. the charge code for ESPO − System cumbersome on Procurement personnel to de-obligate & re-obligate funds from old to new charge codes − System sometimes creates situations of lagging actuals due to obligations at the lowest level, i.e. cost over obligations − System cumbersome with regards to timely creation and inability to close charge codes and does not limit access to charge codes − These issues have forced the creation of long duration work / planning packages (multiple years) ♦ Continued training for understanding of Earned Value concepts, in particular, separation of budget versus funding • Existing NASA processes (PPBE, JSC ITA, etc.) are funding processes that are being used synonymously with EVM budget processes − They should be linked to EVM funding processes (ETC / EAC) ♦ Not all organization support contracts structured to collect and report data to support Cx Project EVM requirements • Contract structure forces organizations to "guess" on the monthly costs collected against charge codes by applying estimates since data reported at a summary level • Manual entry process of support contract data into SAP precludes detailed data due to the time requirements to enter the data 13
  • 14. Acronyms and Reference Documents ♦ Acronyms ♦ Reference Documents • CA – Control Account • NPR 7120.5D – NASA Program and Project • CAM – Control Account Manager Management Processes and Requirements • CIRR - CxP Integrated Resources Report • CxP 72179 – CxP ESPO Project Plan • CPR – Cost Performance Report • CxP 72179 Anx01 – CxP ESPO EVM • CxP – Constellation Program Implementation Plan • ESPO – EVA Systems Project Office • CxP 72179 Anx03 – CxP ESPO IMP/IMS Implementation Plan • EVA – Extravehicular Activity • ANSI/EIA-748 – Earned Value Management • EVM – Earned Value Management Systems • EVMS – Earned Value Management System • IBOT - Integrated Budget Office Toolkit • IDIQ – Indefinite Delivery, Indefinite Quantity • IMP – Integrated Master Plan • IMS – Integrated Master Schedule • IRMA – Integrated Risk Management Application • ITA - Internal Task Agreement • JCL - Joint Confidence Level • JSC – Johnson Space Center • NPR - NASA Procedural Requirements • OBS – Organizational Breakdown Structure • PAD – Project Authorization Document • PP – Planning Package • PPBE - Planning, Programming, Budgeting, and Execution • RAM – Responsibility Assignment Matrix • RL – Resource Loaded • SAP – Systems Application and Products • WBS – Work Breakdown Structure • WP – Work Package 14