SlideShare a Scribd company logo
Lecture 4
Transformer on Load
Fig. 32. 17(a) Transformer without load
It has already seen that at no load condition only current I0 flows in
the circuit as shown in Fig. 32.17(a). This current sets up the flux .
When the secondary is loaded, the secondary current I2 is set up.
The magnitude and phase of I2 with respect to V2 determined by the
characteristics of the load.
• The secondary current sets
up its own mmf (=N2I2) and
hence its on flux 2 which is
in opposition to the main
primary flux  which is due
to I0 as shown in Fig.
32.17(b).
• The secondary ampere-
turns N2I2 are known as
demagnetizing amp-turns.
• The opposing secondary
flux 2 weakens the primary
flux , hence primary back
emf E1 tends to be reduced.
Fig. 32.17 (b) Transformer on load
For a moment V1 gains upper hand over E1 and hence causes more
current to flow in primary.
Let the additional primary current be I2
’ as shown in Fig. 32.17(c).
Fig. 32.17(c)
It is known as load component of primary current. This current is anti-
phase with I2 .
The additional primary mmf N1I2’ sets up its own flux 2
’, which is in
opposition to 2 (but is in the same direction as ) and is equal to it in
magnitude.
Hence the two cancel each other out as shown in Fig. 32.17(d).
• So, we find that the magnetic effects of secondary current I2
are immediately neutralized by the additional primary current
I2
’, which is brought into existence exactly at the same instant
as I2.
• Hence, whatever the load conditions, the net flux passing
through the core is approximately the same as at no-load.
Fig. 32.17(d)
Fig. 32.17
An important deduction is that
due to the constancy of core
flux at all loads; the core loss is
also practically the same under
all load conditions.
When transformer is on load,
the primary winding has two
currents in it; one is I0 and the
other I2
’ is which is anti-phase
with I2 and K times in
magnitude (i.e. I2
’ = I2K).
The total primary current is the
vector sum of I0 and I2
’.
Quick Quiz
1.
2. In a transformer
(a) All turns are equally insulated
(b) The end turns are more strongly insulated
(c) The end turns are closely wound
(d) The end turns are widely separated
3. Select the correct statement:
(a) emf per turn of both the windings are equal
(b) emf per turn in HV winding is more than the emf per turn in LV
winding
(c) emf per turn in HV winding is less than the emf per turn in LV
winding
4. The flux involved in the emf equation of a transformer has
(a) rms value
(b) Average value
(c) Total value
(d) Maximum value
5. Transformer changes the value of
(a) Power
(b) Frequency
(c) Voltage
(d) Current
6. Draw the vector diagram of no load condition.
In Fig. 32.8 are shown the vector diagrams for a load transformer when load is non-
inductive and when it is inductive.
Voltage transformation ratio of unity is assumed so that primary vectors are equal to
the secondary vectors.
With reference to Fig. 30.18(a), I2 is secondary current in phase with E2.
It causes primary current I2
’ which is anti-phase with it and equal to it in magnitude.
Total primary current I1 is the vector sum of I0 and I2
’ and lags behind V1 by an angle
1.
Here, I2 lags E2 (actually V2) by 2.
Current I2
’ is again in anti-phase with I2
and equal to it in magnitude.
As before, I1 is the vector sum of I2
’ and
I0 and lags behind V1 by 1.
In Fig. 30.18(b) vectors are drawn for an
inductive load.
In Fig. 32.8 are shown the vector diagrams for a load transformer when load is non-
inductive and when it is inductive.
Voltage transformation ratio of unity is assumed so that primary vectors are equal to
the secondary vectors.
With reference to Fig. 30.18(a), I2 is secondary current in phase with E2.
It causes primary current I2
’ which is anti-phase with it and equal to it in magnitude.
Total primary current I1 is the vector sum of I0 and I2
’ and lags behind V1 by an angle
1.
Here, I2 lags E2 (actually V2) by 2.
Current I2
’ is again in anti-phase with I2
and equal to it in magnitude.
As before, I1 is the vector sum of I2
’ and
I0 and lags behind V1 by 1.
In Fig. 30.18(b) vectors are drawn for an
inductive load.
Lecture 4
Lecture 4

More Related Content

What's hot

Class 12th Solids and semiconductor devices part 2 ppt
Class 12th Solids and semiconductor devices part 2 pptClass 12th Solids and semiconductor devices part 2 ppt
Class 12th Solids and semiconductor devices part 2 ppt
Arpit Meena
 
Diode v i characteristic
Diode v i characteristicDiode v i characteristic
Diode v i characteristic
Unsa Shakir
 
7.3 series and parallel circuits
7.3 series and parallel circuits7.3 series and parallel circuits
7.3 series and parallel circuits
Adlishah Risal Bili
 
Module1 ppt
Module1 pptModule1 ppt
Module1 ppt
Nirupama Rayee
 
P-N junction
P-N junction P-N junction
P-N junction
Ashvani Shukla
 
Electrical and Electronics Engineering
Electrical and Electronics EngineeringElectrical and Electronics Engineering
Electrical and Electronics Engineering
Ekeeda
 
Transformer
TransformerTransformer
Transformer
Latif Hyder Wadho
 
Ete411 Lec11
Ete411 Lec11Ete411 Lec11
Ete411 Lec11
mashiur
 
D.C. Circuits
D.C. CircuitsD.C. Circuits
D.C. Circuits
Shafie Sofian
 
Ankit singh
Ankit singhAnkit singh
Ankit singh
Vipul Pratap Singh
 
Electronics lecture 3
Electronics lecture 3Electronics lecture 3
Electronics lecture 3avocado1111
 
D2.1 basic laws
D2.1 basic lawsD2.1 basic laws
D2.1 basic laws
Rekha Patel
 
Zener diode voltage regulator (ALIV - Bangladesh)
Zener diode voltage regulator (ALIV - Bangladesh)Zener diode voltage regulator (ALIV - Bangladesh)
Zener diode voltage regulator (ALIV - Bangladesh)
Md Abu Jauad Khan Aliv
 
Diodes vi characteries
Diodes vi characteriesDiodes vi characteries
Diodes vi characteries
Manikandan Chinnadurai
 

What's hot (15)

Class 12th Solids and semiconductor devices part 2 ppt
Class 12th Solids and semiconductor devices part 2 pptClass 12th Solids and semiconductor devices part 2 ppt
Class 12th Solids and semiconductor devices part 2 ppt
 
Diode v i characteristic
Diode v i characteristicDiode v i characteristic
Diode v i characteristic
 
7.3 series and parallel circuits
7.3 series and parallel circuits7.3 series and parallel circuits
7.3 series and parallel circuits
 
Binary signal, Uni-polar,
Binary signal, Uni-polar, Binary signal, Uni-polar,
Binary signal, Uni-polar,
 
Module1 ppt
Module1 pptModule1 ppt
Module1 ppt
 
P-N junction
P-N junction P-N junction
P-N junction
 
Electrical and Electronics Engineering
Electrical and Electronics EngineeringElectrical and Electronics Engineering
Electrical and Electronics Engineering
 
Transformer
TransformerTransformer
Transformer
 
Ete411 Lec11
Ete411 Lec11Ete411 Lec11
Ete411 Lec11
 
D.C. Circuits
D.C. CircuitsD.C. Circuits
D.C. Circuits
 
Ankit singh
Ankit singhAnkit singh
Ankit singh
 
Electronics lecture 3
Electronics lecture 3Electronics lecture 3
Electronics lecture 3
 
D2.1 basic laws
D2.1 basic lawsD2.1 basic laws
D2.1 basic laws
 
Zener diode voltage regulator (ALIV - Bangladesh)
Zener diode voltage regulator (ALIV - Bangladesh)Zener diode voltage regulator (ALIV - Bangladesh)
Zener diode voltage regulator (ALIV - Bangladesh)
 
Diodes vi characteries
Diodes vi characteriesDiodes vi characteries
Diodes vi characteries
 

Similar to Lecture 4

bee ppt - lokesh (73).pptx
bee ppt - lokesh (73).pptxbee ppt - lokesh (73).pptx
bee ppt - lokesh (73).pptx
DanyDany88
 
Unit5-Transformers.ppt
Unit5-Transformers.pptUnit5-Transformers.ppt
Unit5-Transformers.ppt
MdSazibMollik
 
Unit1-Transformers.ppt
Unit1-Transformers.pptUnit1-Transformers.ppt
Unit1-Transformers.ppt
MdSazibMollik
 
TRANSFORMER_PHASORS.pptx
TRANSFORMER_PHASORS.pptxTRANSFORMER_PHASORS.pptx
TRANSFORMER_PHASORS.pptx
VivekPrakash828628
 
Single phase transformer
Single phase transformerSingle phase transformer
Single phase transformer
Aniruddh Joshi
 
Diode Applications & Transistor Basics
Diode Applications & Transistor BasicsDiode Applications & Transistor Basics
Diode Applications & Transistor Basics
A B Shinde
 
transformer working principle
transformer working principletransformer working principle
transformer working principle
md akkas ali
 
Transformers 25.02.2020.pptx
Transformers 25.02.2020.pptxTransformers 25.02.2020.pptx
Transformers 25.02.2020.pptx
PraveenKumarB30
 
Calculations of a.c distributions methods & 3 phase unbalanced loads &amp...
Calculations of a.c distributions methods & 3 phase unbalanced loads &amp...Calculations of a.c distributions methods & 3 phase unbalanced loads &amp...
Calculations of a.c distributions methods & 3 phase unbalanced loads &amp...
vishalgohel12195
 
04 Cap 3 - harmonic-generation1-2015.pdf
04 Cap 3 - harmonic-generation1-2015.pdf04 Cap 3 - harmonic-generation1-2015.pdf
04 Cap 3 - harmonic-generation1-2015.pdf
ROCIOMAMANIALATA1
 
Transformers 31.03.2020.pptx
Transformers 31.03.2020.pptxTransformers 31.03.2020.pptx
Transformers 31.03.2020.pptx
PraveenKumarB30
 
questions on diode analysis: Assignment6
questions on diode analysis: Assignment6questions on diode analysis: Assignment6
questions on diode analysis: Assignment6Akash Kumar Verma
 
fall2010-28 (1).pdf
fall2010-28 (1).pdffall2010-28 (1).pdf
fall2010-28 (1).pdf
SarthakShukla45
 
Snubbing Methods
Snubbing MethodsSnubbing Methods
Snubbing MethodsRic Barline
 
Chapter02
Chapter02Chapter02
Chapter02
vikram anand
 
Lecture 07 transistor re model
Lecture 07 transistor re modelLecture 07 transistor re model
Lecture 07 transistor re model
Ismael Cayo Apaza
 
Unit 3
Unit 3Unit 3

Similar to Lecture 4 (20)

bee ppt - lokesh (73).pptx
bee ppt - lokesh (73).pptxbee ppt - lokesh (73).pptx
bee ppt - lokesh (73).pptx
 
Unit5-Transformers.ppt
Unit5-Transformers.pptUnit5-Transformers.ppt
Unit5-Transformers.ppt
 
Unit1-Transformers.ppt
Unit1-Transformers.pptUnit1-Transformers.ppt
Unit1-Transformers.ppt
 
Power Sharing
Power SharingPower Sharing
Power Sharing
 
TRANSFORMER_PHASORS.pptx
TRANSFORMER_PHASORS.pptxTRANSFORMER_PHASORS.pptx
TRANSFORMER_PHASORS.pptx
 
Single phase transformer
Single phase transformerSingle phase transformer
Single phase transformer
 
Choppers
ChoppersChoppers
Choppers
 
Diode Applications & Transistor Basics
Diode Applications & Transistor BasicsDiode Applications & Transistor Basics
Diode Applications & Transistor Basics
 
transformer working principle
transformer working principletransformer working principle
transformer working principle
 
Lecture 6
Lecture 6Lecture 6
Lecture 6
 
Transformers 25.02.2020.pptx
Transformers 25.02.2020.pptxTransformers 25.02.2020.pptx
Transformers 25.02.2020.pptx
 
Calculations of a.c distributions methods & 3 phase unbalanced loads &amp...
Calculations of a.c distributions methods & 3 phase unbalanced loads &amp...Calculations of a.c distributions methods & 3 phase unbalanced loads &amp...
Calculations of a.c distributions methods & 3 phase unbalanced loads &amp...
 
04 Cap 3 - harmonic-generation1-2015.pdf
04 Cap 3 - harmonic-generation1-2015.pdf04 Cap 3 - harmonic-generation1-2015.pdf
04 Cap 3 - harmonic-generation1-2015.pdf
 
Transformers 31.03.2020.pptx
Transformers 31.03.2020.pptxTransformers 31.03.2020.pptx
Transformers 31.03.2020.pptx
 
questions on diode analysis: Assignment6
questions on diode analysis: Assignment6questions on diode analysis: Assignment6
questions on diode analysis: Assignment6
 
fall2010-28 (1).pdf
fall2010-28 (1).pdffall2010-28 (1).pdf
fall2010-28 (1).pdf
 
Snubbing Methods
Snubbing MethodsSnubbing Methods
Snubbing Methods
 
Chapter02
Chapter02Chapter02
Chapter02
 
Lecture 07 transistor re model
Lecture 07 transistor re modelLecture 07 transistor re model
Lecture 07 transistor re model
 
Unit 3
Unit 3Unit 3
Unit 3
 

More from avocado1111

Lecture 1
Lecture 1Lecture 1
Lecture 1
avocado1111
 
Grammar in brief
Grammar in briefGrammar in brief
Grammar in brief
avocado1111
 
Lecture 8
Lecture 8Lecture 8
Lecture 8
avocado1111
 
Self and mutual inductance
Self and mutual inductanceSelf and mutual inductance
Self and mutual inductance
avocado1111
 
Electrostatics
ElectrostaticsElectrostatics
Electrostatics
avocado1111
 
Lecture 1 electromagnetism
Lecture 1 electromagnetismLecture 1 electromagnetism
Lecture 1 electromagnetism
avocado1111
 
Lecture 5 energy bands and charge carriers
Lecture 5 energy bands and charge carriersLecture 5 energy bands and charge carriers
Lecture 5 energy bands and charge carriersavocado1111
 
Instant Power Supply ( IPS) System with Load Priority
Instant Power Supply ( IPS) System with Load Priority Instant Power Supply ( IPS) System with Load Priority
Instant Power Supply ( IPS) System with Load Priority avocado1111
 
Presentation of single axis solar tracker
Presentation of single axis solar trackerPresentation of single axis solar tracker
Presentation of single axis solar trackeravocado1111
 
Introduction to motors
Introduction to motorsIntroduction to motors
Introduction to motorsavocado1111
 
Single and 3 phase transformer
Single and 3 phase transformerSingle and 3 phase transformer
Single and 3 phase transformeravocado1111
 
Transmission impairments
Transmission impairmentsTransmission impairments
Transmission impairmentsavocado1111
 
Digital modulation
Digital modulationDigital modulation
Digital modulationavocado1111
 
Pulse modulation
Pulse modulationPulse modulation
Pulse modulationavocado1111
 
Phase modulation
Phase modulationPhase modulation
Phase modulationavocado1111
 
Angle modulation
Angle modulationAngle modulation
Angle modulationavocado1111
 
Amplitude modulation
Amplitude modulationAmplitude modulation
Amplitude modulationavocado1111
 

More from avocado1111 (20)

Lecture 1
Lecture 1Lecture 1
Lecture 1
 
Grammar in brief
Grammar in briefGrammar in brief
Grammar in brief
 
Lecture 8
Lecture 8Lecture 8
Lecture 8
 
Self and mutual inductance
Self and mutual inductanceSelf and mutual inductance
Self and mutual inductance
 
Electrostatics
ElectrostaticsElectrostatics
Electrostatics
 
Lecture 1 electromagnetism
Lecture 1 electromagnetismLecture 1 electromagnetism
Lecture 1 electromagnetism
 
Lecture 6
Lecture 6Lecture 6
Lecture 6
 
Mics. print
Mics. printMics. print
Mics. print
 
Lecture 5 energy bands and charge carriers
Lecture 5 energy bands and charge carriersLecture 5 energy bands and charge carriers
Lecture 5 energy bands and charge carriers
 
Experiment 2 AM
Experiment 2 AMExperiment 2 AM
Experiment 2 AM
 
Instant Power Supply ( IPS) System with Load Priority
Instant Power Supply ( IPS) System with Load Priority Instant Power Supply ( IPS) System with Load Priority
Instant Power Supply ( IPS) System with Load Priority
 
Presentation of single axis solar tracker
Presentation of single axis solar trackerPresentation of single axis solar tracker
Presentation of single axis solar tracker
 
Introduction to motors
Introduction to motorsIntroduction to motors
Introduction to motors
 
Single and 3 phase transformer
Single and 3 phase transformerSingle and 3 phase transformer
Single and 3 phase transformer
 
Transmission impairments
Transmission impairmentsTransmission impairments
Transmission impairments
 
Digital modulation
Digital modulationDigital modulation
Digital modulation
 
Pulse modulation
Pulse modulationPulse modulation
Pulse modulation
 
Phase modulation
Phase modulationPhase modulation
Phase modulation
 
Angle modulation
Angle modulationAngle modulation
Angle modulation
 
Amplitude modulation
Amplitude modulationAmplitude modulation
Amplitude modulation
 

Recently uploaded

WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 

Recently uploaded (20)

WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 

Lecture 4

  • 2. Transformer on Load Fig. 32. 17(a) Transformer without load It has already seen that at no load condition only current I0 flows in the circuit as shown in Fig. 32.17(a). This current sets up the flux . When the secondary is loaded, the secondary current I2 is set up. The magnitude and phase of I2 with respect to V2 determined by the characteristics of the load.
  • 3. • The secondary current sets up its own mmf (=N2I2) and hence its on flux 2 which is in opposition to the main primary flux  which is due to I0 as shown in Fig. 32.17(b). • The secondary ampere- turns N2I2 are known as demagnetizing amp-turns. • The opposing secondary flux 2 weakens the primary flux , hence primary back emf E1 tends to be reduced. Fig. 32.17 (b) Transformer on load
  • 4. For a moment V1 gains upper hand over E1 and hence causes more current to flow in primary. Let the additional primary current be I2 ’ as shown in Fig. 32.17(c). Fig. 32.17(c) It is known as load component of primary current. This current is anti- phase with I2 . The additional primary mmf N1I2’ sets up its own flux 2 ’, which is in opposition to 2 (but is in the same direction as ) and is equal to it in magnitude. Hence the two cancel each other out as shown in Fig. 32.17(d).
  • 5. • So, we find that the magnetic effects of secondary current I2 are immediately neutralized by the additional primary current I2 ’, which is brought into existence exactly at the same instant as I2. • Hence, whatever the load conditions, the net flux passing through the core is approximately the same as at no-load. Fig. 32.17(d)
  • 6. Fig. 32.17 An important deduction is that due to the constancy of core flux at all loads; the core loss is also practically the same under all load conditions. When transformer is on load, the primary winding has two currents in it; one is I0 and the other I2 ’ is which is anti-phase with I2 and K times in magnitude (i.e. I2 ’ = I2K). The total primary current is the vector sum of I0 and I2 ’.
  • 8. 2. In a transformer (a) All turns are equally insulated (b) The end turns are more strongly insulated (c) The end turns are closely wound (d) The end turns are widely separated 3. Select the correct statement: (a) emf per turn of both the windings are equal (b) emf per turn in HV winding is more than the emf per turn in LV winding (c) emf per turn in HV winding is less than the emf per turn in LV winding 4. The flux involved in the emf equation of a transformer has (a) rms value (b) Average value (c) Total value (d) Maximum value
  • 9. 5. Transformer changes the value of (a) Power (b) Frequency (c) Voltage (d) Current 6. Draw the vector diagram of no load condition.
  • 10. In Fig. 32.8 are shown the vector diagrams for a load transformer when load is non- inductive and when it is inductive. Voltage transformation ratio of unity is assumed so that primary vectors are equal to the secondary vectors. With reference to Fig. 30.18(a), I2 is secondary current in phase with E2. It causes primary current I2 ’ which is anti-phase with it and equal to it in magnitude. Total primary current I1 is the vector sum of I0 and I2 ’ and lags behind V1 by an angle 1. Here, I2 lags E2 (actually V2) by 2. Current I2 ’ is again in anti-phase with I2 and equal to it in magnitude. As before, I1 is the vector sum of I2 ’ and I0 and lags behind V1 by 1. In Fig. 30.18(b) vectors are drawn for an inductive load.
  • 11. In Fig. 32.8 are shown the vector diagrams for a load transformer when load is non- inductive and when it is inductive. Voltage transformation ratio of unity is assumed so that primary vectors are equal to the secondary vectors. With reference to Fig. 30.18(a), I2 is secondary current in phase with E2. It causes primary current I2 ’ which is anti-phase with it and equal to it in magnitude. Total primary current I1 is the vector sum of I0 and I2 ’ and lags behind V1 by an angle 1. Here, I2 lags E2 (actually V2) by 2. Current I2 ’ is again in anti-phase with I2 and equal to it in magnitude. As before, I1 is the vector sum of I2 ’ and I0 and lags behind V1 by 1. In Fig. 30.18(b) vectors are drawn for an inductive load.