SlideShare a Scribd company logo
1 of 32
Download to read offline
LL--44
Wastewater Flow RatesWastewater Flow Rates
Environmental Engineering-II
IntroductionIntroduction
• In order to determine the section of
the sewer, it is essential to know the
total quantity of wastewater or
sewage that would flow through the
sewer.sewer.
• The total wastewater flow can be
divided two components :
(a) Dry weather flow (D.W.F.) and
(b) Storm water flow
The dry weather flow (DWF)The dry weather flow (DWF)
• The dry weather flow is the flow
through the sewers that would
normally be available during non-
rainfall periods.rainfall periods.
It consists mainly of
(i)Domestic sewage and
(ii)Industrial wastewater
DRY WEATHER FLOWDRY WEATHER FLOW
• It is that quantity of wastewater that
flows through a sewer in dry weather
when no storm water is in the sewer.
• The dry weather flow is also• The dry weather flow is also
sometimes called as 'sanitary
sewage', and is obtained from the
following sources :
1. Domestic wastewater from
houses- WCs, Baths, urinals,
wash basins etc
2. Industrial waste water from
industriesindustries
3. Wastewater from public
facilities
4. Ground water infiltration
Wastewater Quantity EstimationWastewater Quantity Estimation
• The flow of sanitary sewage alone in
the absence of storms in dry season
is known as dry weather flow (DWF).
• Quantity= Per capita sewage contributed per
day x Population
FACTORSFACTORS AFFECTING DRYAFFECTING DRY
WEATHER FLOWWEATHER FLOW
(a) Rate of water supply.
(b) Population growth.
(c) Type of area served
(d) Infiltration of ground water
a. Rate of water supplya. Rate of water supply
• The quantity of wastewater produced from
a community would naturally depend upon
the rate of water supply per capita' per
day. The quantity of wastewater entering
the sewers would be less than the totalthe sewers would be less than the total
quantity of water supplied.
• This is because of the fact that water is
lost in domestic consumption (i.e. cooking
etc.), evaporation, lawn sprinkling, fire
fighting, industrial consumption etc.
• In general it is assumed that waste
generation quantity is 80% of rate of
water supplywater supply
b.b. Population GrowthPopulation Growth
• The various methods adopted for
estimating future populations are
given below. The particular method to
be adopted for a particular case or forbe adopted for a particular case or for
a particular city depends largely on
the factors discussed in the methods,
and the selection is left to the the
designer.
• Arithmetic Increase Method
• Geometric Increase Method
• Incremental Increase Method
• Decreasing Rate of Growth Method
• Simple Graphical Method• Simple Graphical Method
• Comparative Graphical Method
• Ratio Method
• Logistic Curve Method
• In case the desired information on
population is not available in the
Master Plan of the town, the densities
given in following Table may be
adopted as suggested by the Manual
on Sewage and Sewage Treatmenton Sewage and Sewage Treatment
prepared by the Public Health and
Environmental Engineering
Organisation
Sizeo/Town (Population)
Density / population per
hectare
l. Upto 5000 75 -150
2. 5000 - 20,000 150-250
3. 20,000 - 50,000 250-300
4. 50,000 to 100,000 300-350
5. Above 100,000 350-1000
Effect of growth of populationEffect of growth of population
Population
Rate of water
supply
Sewage
production
lit./capita/day lit/capita/day
Below 2 lacs 130-160 110-120Below 2 lacs 130-160 110-120
2 to 5 lacs 160-180 130-140
5 to 10 lacs 180-200 150-170
More than 10
lacs
200-250 I80-200
Design period as per CPHEEODesign period as per CPHEEO
manualmanual
1. Branches of sewer – 30 years
2. Pumping stations – 30 years
3. The treatment plant - 30 year
4. Pumping machinery – 15 years4. Pumping machinery – 15 years
5. Effluent disposal and utilisation –
30 years
c. Type of area served.c. Type of area served.
• The quantity of wastewater produced
depends upon whether the area to be
served is
• Residential,• Residential,
• Commercial,
• Industrial.
• The wastewater from the residential
area directly depends upon the rate of
water supply. If there is no infiltration
of water in the sewers, and if there
are no private sources of supply.
• The wastewater produced from the• The wastewater produced from the
residential area may be assumed to
be equal to 70 to 80% of the water
supplied through the public supply
system
• The amount of waste water produced
from the industrial locality depends
upon the types of industries and their
corresponding industrial processes.
• The same is the case with the
commercial un-dertakings. Thecommercial un-dertakings. The
sewage flow rates can be determined
after careful study of the various
process involved.
d. Infiltration of subd. Infiltration of sub--soil watersoil water
• Ground water or subsoil water may infiltrate into
the sewers through the leaky joints. Exfiltration
is the reverse process which indicates the flow
of wastewater from the sewer into the ground.
• While due to the infiltration the quantity of flow• While due to the infiltration the quantity of flow
through sewer increases, exfiltration results in
decrease in the flow and consequent increase
in the pollution of ground water. Both infiltration
as well as exfiltration are undesirable and take
place due to imperfect joints.
VARIATIONS IN RATEVARIATIONS IN RATE
OF SEWAGEOF SEWAGE
Peaking factorsPeaking factors
Contributory
population
Peak factor
Up to 20,000 3.0
20,000 to 50,000 2.5
50,000 to 750,000 2.25
above 750,000 2.0
Objective QuestionsObjective Questions
1. DWF is the flow in sewers available in
___________ periods. (rainy/non rainfall/both
a and b/none of these).
2. Pumping machinery is designed for period
____ years (10/15/20/30). (**)
3. For a town having population 1,00,000 the3. For a town having population 1,00,000 the
density of population considered is _____
people/hectare (50-100/100-150/150-200/200-
250).
4. For population of 5 to 10 lacs the sewage
production is ______ lpcd (110-120/130-
140/150-170/180-200)
5. The design period of branch sewer is ____
years. (15/30/20/25). (**)
6.For town having population 50,000 to 100000
the density of population per hectare is
_____.(50-100/75-100/110-120/120-150).
7.For design of sewers the peak factor for
population above750000 is considered aspopulation above750000 is considered as
___.(2/2.25/2.5/3.5)
8. For town having population 5000 the density of
population per hectare is _____.(50-75/75-
150/100-200/200/300)
9.For population of below 2 lac rate of water
supply is _____lpcd. (100-130/150-170/130-
160/180-200)
10 For population of 2 to 5 lacs the sewage
production is ______ lpcd (110-120/130-
140/150-170/180-200)
11. For population of upto 20000 the peak factor11. For population of upto 20000 the peak factor
is ____. (2.5/3.0/3.5/4.0)
Theory QuestionsTheory Questions
Q1. Explain any two factors affecting
DWF. (Nov 2010, 5 marks)
Q2. What is DWF? Explain any four
factors affecting DWF. (Nov 2010 old,factors affecting DWF. (Nov 2010 old,
8 marks)
L 4 wastewater flow rates
L 4 wastewater flow rates
L 4 wastewater flow rates

More Related Content

What's hot

Water demand and factor affecting water demand
Water demand and factor affecting water demandWater demand and factor affecting water demand
Water demand and factor affecting water demandAnkit Gola
 
Sludge digestor
Sludge digestor Sludge digestor
Sludge digestor MNIT,JAIPUR
 
Recycle and reuse of wastewater
Recycle and reuse of wastewaterRecycle and reuse of wastewater
Recycle and reuse of wastewaterPulkit Shukla
 
Sewage Conveyance and Pumping
Sewage Conveyance and PumpingSewage Conveyance and Pumping
Sewage Conveyance and PumpingGAURAV. H .TANDON
 
DESIGN OF A SEWAGE TREATMENT PLANT
DESIGN OF A SEWAGE TREATMENT PLANTDESIGN OF A SEWAGE TREATMENT PLANT
DESIGN OF A SEWAGE TREATMENT PLANTRatnesh Kushwaha
 
Estimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage dischargeEstimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage dischargeAnkit Gola
 
Introduction, water demand
Introduction, water demandIntroduction, water demand
Introduction, water demandGARRE RAVI KUMAR
 
Physical Unit Operation- Screening, Grit Removal, Equalization
Physical Unit Operation-Screening, Grit Removal,EqualizationPhysical Unit Operation-Screening, Grit Removal,Equalization
Physical Unit Operation- Screening, Grit Removal, EqualizationYash Patel
 
2. screen chamber
 2. screen chamber 2. screen chamber
2. screen chambervvsasane
 
Ev5002 Solid and hazardous waste management-previous year question paper
Ev5002 Solid and hazardous waste management-previous year question paperEv5002 Solid and hazardous waste management-previous year question paper
Ev5002 Solid and hazardous waste management-previous year question paperRaj Kumar
 

What's hot (20)

Water demand and factor affecting water demand
Water demand and factor affecting water demandWater demand and factor affecting water demand
Water demand and factor affecting water demand
 
L 13 grit chamber
L 13 grit chamberL 13 grit chamber
L 13 grit chamber
 
Sludge digestor
Sludge digestor Sludge digestor
Sludge digestor
 
Design of sewers
Design of sewersDesign of sewers
Design of sewers
 
Recycle and reuse of wastewater
Recycle and reuse of wastewaterRecycle and reuse of wastewater
Recycle and reuse of wastewater
 
Physical Unit Operations
Physical Unit OperationsPhysical Unit Operations
Physical Unit Operations
 
Sewage Conveyance and Pumping
Sewage Conveyance and PumpingSewage Conveyance and Pumping
Sewage Conveyance and Pumping
 
L 8 equalization and proportioning
L  8 equalization and proportioningL  8 equalization and proportioning
L 8 equalization and proportioning
 
DESIGN OF A SEWAGE TREATMENT PLANT
DESIGN OF A SEWAGE TREATMENT PLANTDESIGN OF A SEWAGE TREATMENT PLANT
DESIGN OF A SEWAGE TREATMENT PLANT
 
Estimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage dischargeEstimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage discharge
 
Introduction, water demand
Introduction, water demandIntroduction, water demand
Introduction, water demand
 
02 water demand
02 water demand02 water demand
02 water demand
 
Dry weather flow
Dry weather flowDry weather flow
Dry weather flow
 
Physical Unit Operation- Screening, Grit Removal, Equalization
Physical Unit Operation-Screening, Grit Removal,EqualizationPhysical Unit Operation-Screening, Grit Removal,Equalization
Physical Unit Operation- Screening, Grit Removal, Equalization
 
Sewerage System
Sewerage SystemSewerage System
Sewerage System
 
2. screen chamber
 2. screen chamber 2. screen chamber
2. screen chamber
 
Septic tank
Septic tankSeptic tank
Septic tank
 
Ev5002 Solid and hazardous waste management-previous year question paper
Ev5002 Solid and hazardous waste management-previous year question paperEv5002 Solid and hazardous waste management-previous year question paper
Ev5002 Solid and hazardous waste management-previous year question paper
 
Grit chambers
Grit chambersGrit chambers
Grit chambers
 
L 8 stormwater sewr design
L 8 stormwater sewr designL 8 stormwater sewr design
L 8 stormwater sewr design
 

Viewers also liked

Waste water treatment processes
Waste water treatment processesWaste water treatment processes
Waste water treatment processesAshish Agarwal
 
Environmental Engineering -II Unit I
Environmental Engineering -II Unit IEnvironmental Engineering -II Unit I
Environmental Engineering -II Unit IGAURAV. H .TANDON
 
Sewage treatment plant design calculation
Sewage treatment plant design calculationSewage treatment plant design calculation
Sewage treatment plant design calculationSharifah Ain
 
Industrial wastewater treatment
Industrial wastewater treatmentIndustrial wastewater treatment
Industrial wastewater treatmentMohamed Ramzy
 
Dr. mahmoud nasr (env 2)
Dr. mahmoud nasr (env 2)Dr. mahmoud nasr (env 2)
Dr. mahmoud nasr (env 2)Mahmoud Nasr
 
Pipe stress engineering
Pipe stress engineeringPipe stress engineering
Pipe stress engineeringRicardo Soares
 
Lec 1 (wastewater collection system)
Lec 1 (wastewater collection system)Lec 1 (wastewater collection system)
Lec 1 (wastewater collection system)5032683
 
L 4 characterization of industrial waste and sampling
L 4 characterization of industrial waste and samplingL 4 characterization of industrial waste and sampling
L 4 characterization of industrial waste and samplingDr. shrikant jahagirdar
 
What is the difference between sewage and drainage
What is the difference between sewage and drainageWhat is the difference between sewage and drainage
What is the difference between sewage and drainageNaresh Kuruba
 
L 21 developement of treatment processes
L 21 developement of treatment processesL 21 developement of treatment processes
L 21 developement of treatment processesDr. shrikant jahagirdar
 

Viewers also liked (20)

L 3 collection and conveyance
L 3 collection and conveyanceL 3 collection and conveyance
L 3 collection and conveyance
 
L 5and l-6 sewer design
L 5and l-6 sewer designL 5and l-6 sewer design
L 5and l-6 sewer design
 
Waste water treatment processes
Waste water treatment processesWaste water treatment processes
Waste water treatment processes
 
Sewerage design
Sewerage designSewerage design
Sewerage design
 
Hydraulic design of sewer
Hydraulic design of sewerHydraulic design of sewer
Hydraulic design of sewer
 
Environmental Engineering -II Unit I
Environmental Engineering -II Unit IEnvironmental Engineering -II Unit I
Environmental Engineering -II Unit I
 
L 1 and 2 introductio and definitions
L 1 and 2 introductio and definitionsL 1 and 2 introductio and definitions
L 1 and 2 introductio and definitions
 
Sewage treatment plant design calculation
Sewage treatment plant design calculationSewage treatment plant design calculation
Sewage treatment plant design calculation
 
Water distribution system
Water distribution systemWater distribution system
Water distribution system
 
Industrial wastewater treatment
Industrial wastewater treatmentIndustrial wastewater treatment
Industrial wastewater treatment
 
Design flow
Design flowDesign flow
Design flow
 
Bod sizing
Bod sizingBod sizing
Bod sizing
 
Dr. mahmoud nasr (env 2)
Dr. mahmoud nasr (env 2)Dr. mahmoud nasr (env 2)
Dr. mahmoud nasr (env 2)
 
Pipe stress engineering
Pipe stress engineeringPipe stress engineering
Pipe stress engineering
 
L 5 characterization part-ii
L 5 characterization part-iiL 5 characterization part-ii
L 5 characterization part-ii
 
Lec 1 (wastewater collection system)
Lec 1 (wastewater collection system)Lec 1 (wastewater collection system)
Lec 1 (wastewater collection system)
 
L 4 characterization of industrial waste and sampling
L 4 characterization of industrial waste and samplingL 4 characterization of industrial waste and sampling
L 4 characterization of industrial waste and sampling
 
What is the difference between sewage and drainage
What is the difference between sewage and drainageWhat is the difference between sewage and drainage
What is the difference between sewage and drainage
 
L 21 developement of treatment processes
L 21 developement of treatment processesL 21 developement of treatment processes
L 21 developement of treatment processes
 
L 19
L 19L 19
L 19
 

Similar to L 4 wastewater flow rates

sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenanceManish Goyal
 
Water demand/Waterrequirements
Water demand/Waterrequirements Water demand/Waterrequirements
Water demand/Waterrequirements dhavalsshah
 
Sources, intake structures and water demand in Water Supply Schemes
  Sources, intake structures and water demand in Water Supply Schemes   Sources, intake structures and water demand in Water Supply Schemes
Sources, intake structures and water demand in Water Supply Schemes Vaibhav Kambale
 
Quality & quantity of water
Quality & quantity of waterQuality & quantity of water
Quality & quantity of waterdhara dattani
 
water quality, water demands
water quality, water demandswater quality, water demands
water quality, water demandsMir Zafarullah
 
Water demand
Water demandWater demand
Water demandMood Naik
 
Quantity of water-1.pdf
Quantity of water-1.pdfQuantity of water-1.pdf
Quantity of water-1.pdfSunilJangra29
 
Ee ii ce(pc)505- module 1_2_3
Ee ii ce(pc)505- module 1_2_3Ee ii ce(pc)505- module 1_2_3
Ee ii ce(pc)505- module 1_2_3SamirDas66
 
Water Supply & Urban Drainage.pptx
Water Supply & Urban Drainage.pptxWater Supply & Urban Drainage.pptx
Water Supply & Urban Drainage.pptxYalelet Abera
 
Chapter 1..Water Demand (1) examples.pptx
Chapter 1..Water Demand (1) examples.pptxChapter 1..Water Demand (1) examples.pptx
Chapter 1..Water Demand (1) examples.pptxHeniyit
 
Quality and quantity of water m1
Quality and quantity of water m1Quality and quantity of water m1
Quality and quantity of water m1Bibhabasu Mohanty
 
L5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptxL5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptxPRACHI DESSAI
 
UNIT -I Introduction to water supply scheme.ppt
UNIT -I Introduction to water supply scheme.pptUNIT -I Introduction to water supply scheme.ppt
UNIT -I Introduction to water supply scheme.pptmadhukarjadhav10
 
Water Supply and Treatment Engineering- Module 1
Water Supply and Treatment Engineering- Module 1Water Supply and Treatment Engineering- Module 1
Water Supply and Treatment Engineering- Module 1Mujeeb Muji
 

Similar to L 4 wastewater flow rates (20)

sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenance
 
Lec 2.pptx
Lec 2.pptxLec 2.pptx
Lec 2.pptx
 
Water Requirements
Water RequirementsWater Requirements
Water Requirements
 
Water demand/Waterrequirements
Water demand/Waterrequirements Water demand/Waterrequirements
Water demand/Waterrequirements
 
Sources, intake structures and water demand in Water Supply Schemes
  Sources, intake structures and water demand in Water Supply Schemes   Sources, intake structures and water demand in Water Supply Schemes
Sources, intake structures and water demand in Water Supply Schemes
 
Quality & quantity of water
Quality & quantity of waterQuality & quantity of water
Quality & quantity of water
 
water quality, water demands
water quality, water demandswater quality, water demands
water quality, water demands
 
Water demand
Water demandWater demand
Water demand
 
Quantity of water-1.pdf
Quantity of water-1.pdfQuantity of water-1.pdf
Quantity of water-1.pdf
 
Project report
Project reportProject report
Project report
 
Ee ii ce(pc)505- module 1_2_3
Ee ii ce(pc)505- module 1_2_3Ee ii ce(pc)505- module 1_2_3
Ee ii ce(pc)505- module 1_2_3
 
Water requirements
Water requirementsWater requirements
Water requirements
 
L 3 and l-4 water demand
L 3  and l-4 water demandL 3  and l-4 water demand
L 3 and l-4 water demand
 
Uthaan
UthaanUthaan
Uthaan
 
Water Supply & Urban Drainage.pptx
Water Supply & Urban Drainage.pptxWater Supply & Urban Drainage.pptx
Water Supply & Urban Drainage.pptx
 
Chapter 1..Water Demand (1) examples.pptx
Chapter 1..Water Demand (1) examples.pptxChapter 1..Water Demand (1) examples.pptx
Chapter 1..Water Demand (1) examples.pptx
 
Quality and quantity of water m1
Quality and quantity of water m1Quality and quantity of water m1
Quality and quantity of water m1
 
L5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptxL5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptx
 
UNIT -I Introduction to water supply scheme.ppt
UNIT -I Introduction to water supply scheme.pptUNIT -I Introduction to water supply scheme.ppt
UNIT -I Introduction to water supply scheme.ppt
 
Water Supply and Treatment Engineering- Module 1
Water Supply and Treatment Engineering- Module 1Water Supply and Treatment Engineering- Module 1
Water Supply and Treatment Engineering- Module 1
 

More from Dr. shrikant jahagirdar (20)

Indoor Air Pollution .......................
Indoor Air Pollution .......................Indoor Air Pollution .......................
Indoor Air Pollution .......................
 
06 Filtration.ppt
06 Filtration.ppt06 Filtration.ppt
06 Filtration.ppt
 
Oxidation pond problem
Oxidation pond problemOxidation pond problem
Oxidation pond problem
 
Module v Environmental Sanitation
Module v Environmental SanitationModule v Environmental Sanitation
Module v Environmental Sanitation
 
Module VI Rural Sanitation
Module VI Rural SanitationModule VI Rural Sanitation
Module VI Rural Sanitation
 
Module IV Wastewater treatment methods
Module IV Wastewater treatment methodsModule IV Wastewater treatment methods
Module IV Wastewater treatment methods
 
Hw2 do sag curve
Hw2 do sag curveHw2 do sag curve
Hw2 do sag curve
 
Do sag problems
Do sag problemsDo sag problems
Do sag problems
 
Do sag curve
Do sag curveDo sag curve
Do sag curve
 
Module iii
Module iiiModule iii
Module iii
 
Unit viii
Unit viiiUnit viii
Unit viii
 
Unit vii
Unit viiUnit vii
Unit vii
 
L tannery industry
L tannery industryL tannery industry
L tannery industry
 
L sugar industry
L sugar industryL sugar industry
L sugar industry
 
L distillery industry
L distillery industryL distillery industry
L distillery industry
 
L dairy industry
L dairy industryL dairy industry
L dairy industry
 
L 31 Water Pollution act and other topics
L 31 Water Pollution act and other topicsL 31 Water Pollution act and other topics
L 31 Water Pollution act and other topics
 
L 30 fertilizer industry
L 30 fertilizer industryL 30 fertilizer industry
L 30 fertilizer industry
 
L 29 steel industry
L 29 steel industryL 29 steel industry
L 29 steel industry
 
L 20
L 20L 20
L 20
 

Recently uploaded

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

L 4 wastewater flow rates

  • 1. LL--44 Wastewater Flow RatesWastewater Flow Rates Environmental Engineering-II
  • 2. IntroductionIntroduction • In order to determine the section of the sewer, it is essential to know the total quantity of wastewater or sewage that would flow through the sewer.sewer. • The total wastewater flow can be divided two components : (a) Dry weather flow (D.W.F.) and (b) Storm water flow
  • 3. The dry weather flow (DWF)The dry weather flow (DWF) • The dry weather flow is the flow through the sewers that would normally be available during non- rainfall periods.rainfall periods. It consists mainly of (i)Domestic sewage and (ii)Industrial wastewater
  • 4. DRY WEATHER FLOWDRY WEATHER FLOW • It is that quantity of wastewater that flows through a sewer in dry weather when no storm water is in the sewer. • The dry weather flow is also• The dry weather flow is also sometimes called as 'sanitary sewage', and is obtained from the following sources :
  • 5. 1. Domestic wastewater from houses- WCs, Baths, urinals, wash basins etc 2. Industrial waste water from industriesindustries 3. Wastewater from public facilities 4. Ground water infiltration
  • 6. Wastewater Quantity EstimationWastewater Quantity Estimation • The flow of sanitary sewage alone in the absence of storms in dry season is known as dry weather flow (DWF). • Quantity= Per capita sewage contributed per day x Population
  • 7. FACTORSFACTORS AFFECTING DRYAFFECTING DRY WEATHER FLOWWEATHER FLOW (a) Rate of water supply. (b) Population growth. (c) Type of area served (d) Infiltration of ground water
  • 8. a. Rate of water supplya. Rate of water supply • The quantity of wastewater produced from a community would naturally depend upon the rate of water supply per capita' per day. The quantity of wastewater entering the sewers would be less than the totalthe sewers would be less than the total quantity of water supplied. • This is because of the fact that water is lost in domestic consumption (i.e. cooking etc.), evaporation, lawn sprinkling, fire fighting, industrial consumption etc.
  • 9. • In general it is assumed that waste generation quantity is 80% of rate of water supplywater supply
  • 10. b.b. Population GrowthPopulation Growth • The various methods adopted for estimating future populations are given below. The particular method to be adopted for a particular case or forbe adopted for a particular case or for a particular city depends largely on the factors discussed in the methods, and the selection is left to the the designer.
  • 11. • Arithmetic Increase Method • Geometric Increase Method • Incremental Increase Method • Decreasing Rate of Growth Method • Simple Graphical Method• Simple Graphical Method • Comparative Graphical Method • Ratio Method • Logistic Curve Method
  • 12. • In case the desired information on population is not available in the Master Plan of the town, the densities given in following Table may be adopted as suggested by the Manual on Sewage and Sewage Treatmenton Sewage and Sewage Treatment prepared by the Public Health and Environmental Engineering Organisation
  • 13. Sizeo/Town (Population) Density / population per hectare l. Upto 5000 75 -150 2. 5000 - 20,000 150-250 3. 20,000 - 50,000 250-300 4. 50,000 to 100,000 300-350 5. Above 100,000 350-1000
  • 14. Effect of growth of populationEffect of growth of population Population Rate of water supply Sewage production lit./capita/day lit/capita/day Below 2 lacs 130-160 110-120Below 2 lacs 130-160 110-120 2 to 5 lacs 160-180 130-140 5 to 10 lacs 180-200 150-170 More than 10 lacs 200-250 I80-200
  • 15. Design period as per CPHEEODesign period as per CPHEEO manualmanual 1. Branches of sewer – 30 years 2. Pumping stations – 30 years 3. The treatment plant - 30 year 4. Pumping machinery – 15 years4. Pumping machinery – 15 years 5. Effluent disposal and utilisation – 30 years
  • 16. c. Type of area served.c. Type of area served. • The quantity of wastewater produced depends upon whether the area to be served is • Residential,• Residential, • Commercial, • Industrial.
  • 17. • The wastewater from the residential area directly depends upon the rate of water supply. If there is no infiltration of water in the sewers, and if there are no private sources of supply. • The wastewater produced from the• The wastewater produced from the residential area may be assumed to be equal to 70 to 80% of the water supplied through the public supply system
  • 18. • The amount of waste water produced from the industrial locality depends upon the types of industries and their corresponding industrial processes. • The same is the case with the commercial un-dertakings. Thecommercial un-dertakings. The sewage flow rates can be determined after careful study of the various process involved.
  • 19. d. Infiltration of subd. Infiltration of sub--soil watersoil water • Ground water or subsoil water may infiltrate into the sewers through the leaky joints. Exfiltration is the reverse process which indicates the flow of wastewater from the sewer into the ground. • While due to the infiltration the quantity of flow• While due to the infiltration the quantity of flow through sewer increases, exfiltration results in decrease in the flow and consequent increase in the pollution of ground water. Both infiltration as well as exfiltration are undesirable and take place due to imperfect joints.
  • 20. VARIATIONS IN RATEVARIATIONS IN RATE OF SEWAGEOF SEWAGE
  • 21.
  • 22.
  • 23.
  • 24. Peaking factorsPeaking factors Contributory population Peak factor Up to 20,000 3.0 20,000 to 50,000 2.5 50,000 to 750,000 2.25 above 750,000 2.0
  • 25.
  • 26. Objective QuestionsObjective Questions 1. DWF is the flow in sewers available in ___________ periods. (rainy/non rainfall/both a and b/none of these). 2. Pumping machinery is designed for period ____ years (10/15/20/30). (**) 3. For a town having population 1,00,000 the3. For a town having population 1,00,000 the density of population considered is _____ people/hectare (50-100/100-150/150-200/200- 250). 4. For population of 5 to 10 lacs the sewage production is ______ lpcd (110-120/130- 140/150-170/180-200)
  • 27. 5. The design period of branch sewer is ____ years. (15/30/20/25). (**) 6.For town having population 50,000 to 100000 the density of population per hectare is _____.(50-100/75-100/110-120/120-150). 7.For design of sewers the peak factor for population above750000 is considered aspopulation above750000 is considered as ___.(2/2.25/2.5/3.5) 8. For town having population 5000 the density of population per hectare is _____.(50-75/75- 150/100-200/200/300)
  • 28. 9.For population of below 2 lac rate of water supply is _____lpcd. (100-130/150-170/130- 160/180-200) 10 For population of 2 to 5 lacs the sewage production is ______ lpcd (110-120/130- 140/150-170/180-200) 11. For population of upto 20000 the peak factor11. For population of upto 20000 the peak factor is ____. (2.5/3.0/3.5/4.0)
  • 29. Theory QuestionsTheory Questions Q1. Explain any two factors affecting DWF. (Nov 2010, 5 marks) Q2. What is DWF? Explain any four factors affecting DWF. (Nov 2010 old,factors affecting DWF. (Nov 2010 old, 8 marks)