Khurram Ashfaq Khan CV
Name: Khurram Ashfaq Khan
Date of Birth: October 31, 1983
Qualification: Civil Engineering University of Engineering & Technology, Pakistan, 2007
Contact Details:
Tel: +971-56-7839493
Email: khurram.ashfaq@hotmail.com
Marital status: Married
Additional Training and IT Skills:
• Training on Primavera P6 Project Planning & Scheduling
• Primavera P3 Project Planning, Management, Control and Scheduling Software course
• MS Project, MS Excel, MS Word, MS Power Point
• H2S and BA Training
• Incident, Injury, Free Environment Training (IIF)
• In house Training in Descon Engineering of Daily Progress Systems (DPMS)
Professional Membership: Member, Pakistan Engineering Council (# Civil -27164)
OBJECTIVE
To work at responsible position in such an organization that offers excellent opportunities for
expertise in field work that helps me pursue a well-balanced and satisfying career.
EXPERIENCE: 9 YEARS
OVERVIEW :
I am a Civil Engineer with 9 years of working experience in construction Projects for
Planning / Scheduling and Project Controls. With an experience of working with International
Companies like Al jaber, Arabtec & Descon, & project management / client like
AECOM,GASCO & ADAC & Select properties. I also had had an opportunity to work a joint
venture project of abu dabhi mid field terminal building project (Arabtec ,ccc & Tav). I have
worked on EPC Projects as well and have a good knowledge of MEP and substations including
Uae Authority approvals in addition to civil. I am looking forward to employ more standard
techniques to the projects and add value to the team and to the project.
Company AL JABER ENGINEERING AND CONTRACTING UAE
Designation SENIOR PLANNING ENGINEER
Duration Oct 2014 to Date
Projects Abu dhabi Terminal 1 & 3 Enhancement project,Marina gate Tower 1
programme
Description
Abu Dhabi airport enhancement Project is basically expansion of Terminal 1 & 3
including New Food & beverages area, Expansion of Business and Economy class areas. In addition
to that new Passenger boarding bridges,New Baggage handling system,substations and back up
generators.I prepared and got approval from client on marina gate tower 1 baseline programme
which has 44 storeys +8 podiums (400 apartments and 8 villas).
1
Khurram Ashfaq Khan CV
Company ARABTEC CONSTRUCTION UAE
Designation PLANNING ENGINEER
Duration Sep 2012 to Sep 2014
Project Midfield Terminal Building airport project Abu dhabi
Description:
Abu Dhabi Airports and the joint venture (JV) of TAV, CCC, and Arabtec have signed an
AED 10.8 billion contract in June 2012 for the construction of the Midfield Terminal Building
(MTB) at Abu Dhabi International Airport.. Construction of the 700,000sqm terminal building,
one of the world-class infrastructure projects being undertaken in the capital, commenced in
2012. The building will be constructed using approximately 69,000 tons of steel, more than
680,000 cubic meters of concrete, and nearly 500,000 square meters of steel and glass cladding,
135,000 tons of rebar, 360,000 square meters of suspended ceilings and 325,000 square meters of
natural stone flooring. Piers will accommodate up to 65 aircraft, including the Airbus Check-in is
capable of handling around 8,500 passengers per hour.Check-in will provide 165 conventional
counters and 48 self-service kiosks Baggage system is designed to process over 19,000 bags per
hour with over 22 kilometers of conveying lines and 10 reclaim carousels136 security screening
lanes for passengers, with a further 25 for staff. Passenger facilities and duty-free retail will
include high-end commercial offerings across more than 18,000sqm, including internationally
renowned luxury goods and designer outlets, and almost 10,000sqm of international restaurants
and cafes, offering a wide range of styles and cuisines. Passenger facilities will also include over
27,500sqm of airline hospitality lounges, a transit hotel & office and a heritage and culture
museum.
Current Job Responsibilities
• Assist in the preparation of 120 days preliminary schedule
• Assist in the preparation of Baseline schedule (clause 14.3)
• Preparation of recovery programs and acceleration programmes.
• Review and approval of Subcontractor schedule
• Cost loading ,quantity loading and manpower loading into baseline programmes
• Preparation of detailed schedule with pre-construction works including mock ups and
subcontractor programme should be aligned with Main contractor programme.
• Assiting contract department in raising of variation order & Extension of time.
• Assisting Engineering department in terms of value Engineering & its time impact.
• Analyzing critical path ,monitoring its trend & proactive meaures.
2
Khurram Ashfaq Khan CV
• Prepartion of KPIS,S-curves,Manpower curves and pre-construction trackers
• Progress & monitoring which includes highlighting the possible delays to Planning
Manager and package managers and its effects to the project milestones and completion
dates .
• Attends meetings with subcontractors and monitoring and evaluation of sub contractors
schedule and recommendations to meet the targets,
• Attend internal meetings and CMA meetings.
• Weekly review of planned value as compared to Earned value and taking pro-active
measures to catch the planned value.
• Preparation of Weekly and monthly reports.
• Supervises day to day monitoring of planning team which include planning & junior
planning engineer and assign the work.
• Assist and guide juniors and fellows in the Project Management team, thus maintaining a
friendly and progressive work envirorment
Company DESCON ENGINEERING (PVT) LTD
Designation PLANNING ENGINEER
Duration July 2010 to AUGUST 2012
Project Integrated Gas Plant Habshan 5, Abu Dhabi, UAE
Description:
A large industrial oil and gas project in Habshan, Abu Dhabi comprising complete civil,
mechanical & electrical works. The works include construction of pipe rack foundations, substation
buildings, instrument & electrical buildings, transformer foundations, switchyard, cooling tower,
warehouse, light fuel oil tanks, water storage tank, asphalt roads and hard surfaces, water and waste
water treatment plant, waste water pumping station, water supply pipe line, sewerage & drainage
system, fire fighting pump house, cable channels, external lighting, piping system, piping bridge,
cooling water pipeline, steel structure etc. The Owner is GASCO & the Main Contractor is (JGC-
TECHNIMONT) JV. The estimated cost of the project is 5.5 billion US Dollars. DESCON’s share is
400 million US Dollars.
Current Job Responsibilities
• Planning, monitoring & controlling of construction activities by using Primavera P3/P6 including
through a WBS, creating activity coding and duration selection
• Preparing of detailed construction baseline schedules from BOQ and scope of work
• Monitoring and evaluation of subcontractors according to construction schedules and
recommendations to meet the targets
• Sequencing and linking the required activities with given milestones
• Responsible for recording and reporting actual progress against planned progress
• Set up activities, coding and project calendars
• Utilization of resource allocation, resource loading and resource curves
• Ensure that subcontractors’ programs are in line with site requirements
• Preparation of Latest Forecast (LF) plans
3
Khurram Ashfaq Khan CV
• Preparation of S-Curve in terms of manhours & cost
• Weekly and Monthly Reports
• Checking of invoices against achieved progress
• Preparation of Latest Forecast Budget in coordination with site managers
• Preparation of Manpower and Equipment Deployment Plans with resource curves
• Monitoring of finishing works of building and subcontract programe of building interface
including civil works, HVAC, fire and gas
• Monitoring of underground non pressure piping and pressure piping (fire water)
Company National Highway Authority Pakistan
Designation Planning Engineer
Duration July 2009 to June 2010
Project NHA (Multan Package) Moosa Pak Shaheed Bridge over the Sutlij river
& approach roads, Pakistan
Description:
An important socio-economic road project that will significantly improve transport links to
remote areas of southern Punjab in Pakistan by reducing travel distances by 45km.The project
includes a 0.6 km two lane bridge, 4.5 km of approach roads. The estimated cost of the Project is
15.3 million US Dollars.
Job Responsibilities
• Planning, monitoring & controlling of construction activities by using Primavera P3/P6 including
through a WBS, creating activity coding and duration selection
• Preparing of detailed construction baseline schedules from BOQ and scope of work
• Sequencing and linking the required activities with given milestones
• Responsible for recording and reporting actual progress against planned progress
• Preparation of Latest Forecast (LF) plans
• Preparation of S-Curve in terms of manhours & cost
• Weekly and Monthly Reports
• Utilization of resource allocation, resource loading and resource curves
• Coordination with consultant and client
Company Habib Rafiq Private Limited
Designation Scheduler
Duration July 2008 to May 2009
Project 234 MW Combined Cycle Power Plant, Sheikhupura, Pakistan
DESCRIPTION:
A large industrial project near Sheikhupura, Pakistan. The project comprised complete civil,
mechanical & electrical works. These included construction of steam turbine house, control room, gas
turbine, HRSG and transformer foundations, switchyard, cooling tower, office building, warehouse,
light fuel oil tanks, water storage tank, asphalt road and hard surfaces, water and waste water
treatment plant, waste water pumping station, water supply pipe line, sewerage & drainage system,
fire fighting pump house, gas supply pipe line, gas conditioning & filtration system, cable channels,
external lighting,erection of steam turbine, piping system, piping bridge, cooling water pipe line, steel
structure etc. The Owner is Sapphire Electrical Company & the E&M Contractor is a Czech-based
firm CKD-EXPORT.The estimated cost of the project was 13.24 million US Dollars.
4
Khurram Ashfaq Khan CV
Job Responsibilities
• Preparation of detailed construction baseline schedule
• Responsible for recording and reporting actual progress against planned progress
• Preparation of Latest Forecast (LF) plans
• Preparation of S-Curve in terms of manhours & cost
• Weekly and monthly reports
• Coordination with consultant and client
Company Trident Construction Private Limited
Designation Site Engineer, QA/QC Engineer
Duration July 2007 to June 2008
Project 13-Story Mixed Use Development, including a 5 Star Grand Hyatt Hotel,
Shopping Mall & Luxury Apartments
DESCRIPTION: A landmark project in Lahore, Pakistan spread over a 15,000m2 area and comprised
a 5-star Hyatt Regency Hotel with 300 rooms, Hyatt Serviced Apartments, Pace Circle Apartments
and a Shopping Mall with 4 designated floors of retail area. The project was designed by Smallwood,
Reynolds, Stewart, Stewart and Associates (SRSS) from. The estimated project cost of the Project
was 40 million US Dollars
Job Responsibilities
• Responsible for Quality Control as the assistant to the project’s Quality Control Manager
• Handled material submittals (MS), material inspection requests (MIR), inspection requests (IR),
work procedures (WP) and inspection identification cards (IIC) in the Quality Control Department
• Maintained records of all the site activities
• Checked layouts, levels, rebar fixing and formwork
• Undertook coordination with consultant, client and contractor
• Checked drawings and quantities for accuracy
• Oversaw the selection, requisition of materials and plant for use in construction
• Liaised with site staff
• Supervised construction activities.
• Established Work Procedures (WPs), Inspection Identification Cards (IICs), Inspection requests
(IRs) and all documents through “Quality Assurance and Quality Control Plan”
Company Engineering Design Bureau
Designation Design Engineer
Duration March 2006 to June 2007
Project Warid Phase-V, Pakistan
Job Responsibilities
• Preparation of feasibility reports
• Preparation of bar bending schedules
• Coordination with contractor and client
• Resolving technical issues
LANGUAGES
English
Urdu
5
Khurram Ashfaq Khan CV
6
Khurram Ashfaq Khan CV
6

More Related Content

What's hot (20)

Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
 
Resume Built Using Primavera P6
Resume Built Using Primavera P6Resume Built Using Primavera P6
Resume Built Using Primavera P6
 
Ahmed Elsonbaty Resume Oct_2016
Ahmed Elsonbaty Resume Oct_2016Ahmed Elsonbaty Resume Oct_2016
Ahmed Elsonbaty Resume Oct_2016
 
CV-2015 Rev 0
CV-2015 Rev 0CV-2015 Rev 0
CV-2015 Rev 0
 
CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)
 
Vineet Sharma-CV.DOCX
Vineet Sharma-CV.DOCXVineet Sharma-CV.DOCX
Vineet Sharma-CV.DOCX
 
Amr. 2015....
Amr. 2015....Amr. 2015....
Amr. 2015....
 
Shoaib Resume
Shoaib ResumeShoaib Resume
Shoaib Resume
 
Elamathi Panneerselvam CV
Elamathi Panneerselvam CVElamathi Panneerselvam CV
Elamathi Panneerselvam CV
 
2013 CIP executive summary 131204
2013 CIP executive summary 1312042013 CIP executive summary 131204
2013 CIP executive summary 131204
 
Gangopadhaya Shekhar CV
Gangopadhaya Shekhar CVGangopadhaya Shekhar CV
Gangopadhaya Shekhar CV
 
CV at 2015 Aug
CV at 2015 AugCV at 2015 Aug
CV at 2015 Aug
 
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
 
CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar Behera
 
Abi Ninan Joseph cv 10-01-2016
Abi Ninan Joseph cv  10-01-2016Abi Ninan Joseph cv  10-01-2016
Abi Ninan Joseph cv 10-01-2016
 
K. Srinivas Rao- CV - QS
K. Srinivas Rao- CV - QSK. Srinivas Rao- CV - QS
K. Srinivas Rao- CV - QS
 
Resume
ResumeResume
Resume
 
Subhash CV Dec 2016
Subhash CV Dec 2016Subhash CV Dec 2016
Subhash CV Dec 2016
 
Sagar_cv
Sagar_cv Sagar_cv
Sagar_cv
 
Raja Rama Mohan Roy - 26th May 2016
Raja Rama Mohan Roy - 26th May 2016Raja Rama Mohan Roy - 26th May 2016
Raja Rama Mohan Roy - 26th May 2016
 

Viewers also liked

Cv Asa May 2008 Compl
Cv Asa May 2008 ComplCv Asa May 2008 Compl
Cv Asa May 2008 Complanwarsansari
 
Cv -sabtain haider new. fresh
Cv -sabtain haider new. freshCv -sabtain haider new. fresh
Cv -sabtain haider new. freshSabtain Haider
 
kashif Nazeer Updated CV
kashif Nazeer Updated CVkashif Nazeer Updated CV
kashif Nazeer Updated CVkashif nazeer
 
Resume - Senior Projects Planner / Schedule
Resume - Senior Projects Planner / ScheduleResume - Senior Projects Planner / Schedule
Resume - Senior Projects Planner / Schedulesaieq
 
CV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGER
CV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGERCV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGER
CV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGERAZHAR QAZI
 
Muhammad Raza Hussain_Project Manager
Muhammad Raza Hussain_Project ManagerMuhammad Raza Hussain_Project Manager
Muhammad Raza Hussain_Project ManagerMuhammad Raza Hussain
 

Viewers also liked (11)

Cv Asa May 2008 Compl
Cv Asa May 2008 ComplCv Asa May 2008 Compl
Cv Asa May 2008 Compl
 
CV Asif Rashid
CV Asif Rashid CV Asif Rashid
CV Asif Rashid
 
Cv -sabtain haider new. fresh
Cv -sabtain haider new. freshCv -sabtain haider new. fresh
Cv -sabtain haider new. fresh
 
Senior Planning Engineer.
Senior Planning Engineer.Senior Planning Engineer.
Senior Planning Engineer.
 
kashif Nazeer Updated CV
kashif Nazeer Updated CVkashif Nazeer Updated CV
kashif Nazeer Updated CV
 
ZIA-CV
ZIA-CV ZIA-CV
ZIA-CV
 
RASHID JALAL C V Updat 1411
RASHID JALAL C V  Updat 1411RASHID JALAL C V  Updat 1411
RASHID JALAL C V Updat 1411
 
Resume - Senior Projects Planner / Schedule
Resume - Senior Projects Planner / ScheduleResume - Senior Projects Planner / Schedule
Resume - Senior Projects Planner / Schedule
 
CV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGER
CV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGERCV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGER
CV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGER
 
Resume Shahid
Resume ShahidResume Shahid
Resume Shahid
 
Muhammad Raza Hussain_Project Manager
Muhammad Raza Hussain_Project ManagerMuhammad Raza Hussain_Project Manager
Muhammad Raza Hussain_Project Manager
 

Similar to KHURRAM ASHFAQ KHAN CV updated

Similar to KHURRAM ASHFAQ KHAN CV updated (20)

Updated C.V of water & sewerage
Updated  C.V of water & sewerageUpdated  C.V of water & sewerage
Updated C.V of water & sewerage
 
Planning engineer cv (mehtab)
Planning engineer cv (mehtab)Planning engineer cv (mehtab)
Planning engineer cv (mehtab)
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning Engineer
 
Sheikh Mohammed Muntazer Resume
Sheikh Mohammed Muntazer Resume Sheikh Mohammed Muntazer Resume
Sheikh Mohammed Muntazer Resume
 
Sheikh Mohammed Muntazer- Resume - Final
Sheikh Mohammed Muntazer- Resume - FinalSheikh Mohammed Muntazer- Resume - Final
Sheikh Mohammed Muntazer- Resume - Final
 
CV- Project Control Manager PMP
CV- Project Control Manager PMPCV- Project Control Manager PMP
CV- Project Control Manager PMP
 
Luxman -CV
Luxman -CVLuxman -CV
Luxman -CV
 
Anuraj Panicker
Anuraj PanickerAnuraj Panicker
Anuraj Panicker
 
Anuraj panicker
Anuraj panickerAnuraj panicker
Anuraj panicker
 
Deepak Kumar_Project
Deepak Kumar_ProjectDeepak Kumar_Project
Deepak Kumar_Project
 
Engr. Abo ElSoud CV-2017
Engr.  Abo ElSoud CV-2017Engr.  Abo ElSoud CV-2017
Engr. Abo ElSoud CV-2017
 
Allwyn Leo CV
Allwyn Leo CVAllwyn Leo CV
Allwyn Leo CV
 
Allwyn-PE-CV
Allwyn-PE-CVAllwyn-PE-CV
Allwyn-PE-CV
 
Project Careers Oil&Gas
Project Careers Oil&Gas Project Careers Oil&Gas
Project Careers Oil&Gas
 
Prudhivi__Rushi_CV
Prudhivi__Rushi_CVPrudhivi__Rushi_CV
Prudhivi__Rushi_CV
 
Updated Resume.DOC
Updated Resume.DOCUpdated Resume.DOC
Updated Resume.DOC
 
jafar hussain 07-06-2014
jafar hussain 07-06-2014jafar hussain 07-06-2014
jafar hussain 07-06-2014
 
jafar hussain 07-06-2014
jafar hussain 07-06-2014jafar hussain 07-06-2014
jafar hussain 07-06-2014
 
Adly CV111
Adly CV111Adly CV111
Adly CV111
 
CV-Sounder
CV-SounderCV-Sounder
CV-Sounder
 

KHURRAM ASHFAQ KHAN CV updated

  • 1. Khurram Ashfaq Khan CV Name: Khurram Ashfaq Khan Date of Birth: October 31, 1983 Qualification: Civil Engineering University of Engineering & Technology, Pakistan, 2007 Contact Details: Tel: +971-56-7839493 Email: khurram.ashfaq@hotmail.com Marital status: Married Additional Training and IT Skills: • Training on Primavera P6 Project Planning & Scheduling • Primavera P3 Project Planning, Management, Control and Scheduling Software course • MS Project, MS Excel, MS Word, MS Power Point • H2S and BA Training • Incident, Injury, Free Environment Training (IIF) • In house Training in Descon Engineering of Daily Progress Systems (DPMS) Professional Membership: Member, Pakistan Engineering Council (# Civil -27164) OBJECTIVE To work at responsible position in such an organization that offers excellent opportunities for expertise in field work that helps me pursue a well-balanced and satisfying career. EXPERIENCE: 9 YEARS OVERVIEW : I am a Civil Engineer with 9 years of working experience in construction Projects for Planning / Scheduling and Project Controls. With an experience of working with International Companies like Al jaber, Arabtec & Descon, & project management / client like AECOM,GASCO & ADAC & Select properties. I also had had an opportunity to work a joint venture project of abu dabhi mid field terminal building project (Arabtec ,ccc & Tav). I have worked on EPC Projects as well and have a good knowledge of MEP and substations including Uae Authority approvals in addition to civil. I am looking forward to employ more standard techniques to the projects and add value to the team and to the project. Company AL JABER ENGINEERING AND CONTRACTING UAE Designation SENIOR PLANNING ENGINEER Duration Oct 2014 to Date Projects Abu dhabi Terminal 1 & 3 Enhancement project,Marina gate Tower 1 programme Description Abu Dhabi airport enhancement Project is basically expansion of Terminal 1 & 3 including New Food & beverages area, Expansion of Business and Economy class areas. In addition to that new Passenger boarding bridges,New Baggage handling system,substations and back up generators.I prepared and got approval from client on marina gate tower 1 baseline programme which has 44 storeys +8 podiums (400 apartments and 8 villas). 1
  • 2. Khurram Ashfaq Khan CV Company ARABTEC CONSTRUCTION UAE Designation PLANNING ENGINEER Duration Sep 2012 to Sep 2014 Project Midfield Terminal Building airport project Abu dhabi Description: Abu Dhabi Airports and the joint venture (JV) of TAV, CCC, and Arabtec have signed an AED 10.8 billion contract in June 2012 for the construction of the Midfield Terminal Building (MTB) at Abu Dhabi International Airport.. Construction of the 700,000sqm terminal building, one of the world-class infrastructure projects being undertaken in the capital, commenced in 2012. The building will be constructed using approximately 69,000 tons of steel, more than 680,000 cubic meters of concrete, and nearly 500,000 square meters of steel and glass cladding, 135,000 tons of rebar, 360,000 square meters of suspended ceilings and 325,000 square meters of natural stone flooring. Piers will accommodate up to 65 aircraft, including the Airbus Check-in is capable of handling around 8,500 passengers per hour.Check-in will provide 165 conventional counters and 48 self-service kiosks Baggage system is designed to process over 19,000 bags per hour with over 22 kilometers of conveying lines and 10 reclaim carousels136 security screening lanes for passengers, with a further 25 for staff. Passenger facilities and duty-free retail will include high-end commercial offerings across more than 18,000sqm, including internationally renowned luxury goods and designer outlets, and almost 10,000sqm of international restaurants and cafes, offering a wide range of styles and cuisines. Passenger facilities will also include over 27,500sqm of airline hospitality lounges, a transit hotel & office and a heritage and culture museum. Current Job Responsibilities • Assist in the preparation of 120 days preliminary schedule • Assist in the preparation of Baseline schedule (clause 14.3) • Preparation of recovery programs and acceleration programmes. • Review and approval of Subcontractor schedule • Cost loading ,quantity loading and manpower loading into baseline programmes • Preparation of detailed schedule with pre-construction works including mock ups and subcontractor programme should be aligned with Main contractor programme. • Assiting contract department in raising of variation order & Extension of time. • Assisting Engineering department in terms of value Engineering & its time impact. • Analyzing critical path ,monitoring its trend & proactive meaures. 2
  • 3. Khurram Ashfaq Khan CV • Prepartion of KPIS,S-curves,Manpower curves and pre-construction trackers • Progress & monitoring which includes highlighting the possible delays to Planning Manager and package managers and its effects to the project milestones and completion dates . • Attends meetings with subcontractors and monitoring and evaluation of sub contractors schedule and recommendations to meet the targets, • Attend internal meetings and CMA meetings. • Weekly review of planned value as compared to Earned value and taking pro-active measures to catch the planned value. • Preparation of Weekly and monthly reports. • Supervises day to day monitoring of planning team which include planning & junior planning engineer and assign the work. • Assist and guide juniors and fellows in the Project Management team, thus maintaining a friendly and progressive work envirorment Company DESCON ENGINEERING (PVT) LTD Designation PLANNING ENGINEER Duration July 2010 to AUGUST 2012 Project Integrated Gas Plant Habshan 5, Abu Dhabi, UAE Description: A large industrial oil and gas project in Habshan, Abu Dhabi comprising complete civil, mechanical & electrical works. The works include construction of pipe rack foundations, substation buildings, instrument & electrical buildings, transformer foundations, switchyard, cooling tower, warehouse, light fuel oil tanks, water storage tank, asphalt roads and hard surfaces, water and waste water treatment plant, waste water pumping station, water supply pipe line, sewerage & drainage system, fire fighting pump house, cable channels, external lighting, piping system, piping bridge, cooling water pipeline, steel structure etc. The Owner is GASCO & the Main Contractor is (JGC- TECHNIMONT) JV. The estimated cost of the project is 5.5 billion US Dollars. DESCON’s share is 400 million US Dollars. Current Job Responsibilities • Planning, monitoring & controlling of construction activities by using Primavera P3/P6 including through a WBS, creating activity coding and duration selection • Preparing of detailed construction baseline schedules from BOQ and scope of work • Monitoring and evaluation of subcontractors according to construction schedules and recommendations to meet the targets • Sequencing and linking the required activities with given milestones • Responsible for recording and reporting actual progress against planned progress • Set up activities, coding and project calendars • Utilization of resource allocation, resource loading and resource curves • Ensure that subcontractors’ programs are in line with site requirements • Preparation of Latest Forecast (LF) plans 3
  • 4. Khurram Ashfaq Khan CV • Preparation of S-Curve in terms of manhours & cost • Weekly and Monthly Reports • Checking of invoices against achieved progress • Preparation of Latest Forecast Budget in coordination with site managers • Preparation of Manpower and Equipment Deployment Plans with resource curves • Monitoring of finishing works of building and subcontract programe of building interface including civil works, HVAC, fire and gas • Monitoring of underground non pressure piping and pressure piping (fire water) Company National Highway Authority Pakistan Designation Planning Engineer Duration July 2009 to June 2010 Project NHA (Multan Package) Moosa Pak Shaheed Bridge over the Sutlij river & approach roads, Pakistan Description: An important socio-economic road project that will significantly improve transport links to remote areas of southern Punjab in Pakistan by reducing travel distances by 45km.The project includes a 0.6 km two lane bridge, 4.5 km of approach roads. The estimated cost of the Project is 15.3 million US Dollars. Job Responsibilities • Planning, monitoring & controlling of construction activities by using Primavera P3/P6 including through a WBS, creating activity coding and duration selection • Preparing of detailed construction baseline schedules from BOQ and scope of work • Sequencing and linking the required activities with given milestones • Responsible for recording and reporting actual progress against planned progress • Preparation of Latest Forecast (LF) plans • Preparation of S-Curve in terms of manhours & cost • Weekly and Monthly Reports • Utilization of resource allocation, resource loading and resource curves • Coordination with consultant and client Company Habib Rafiq Private Limited Designation Scheduler Duration July 2008 to May 2009 Project 234 MW Combined Cycle Power Plant, Sheikhupura, Pakistan DESCRIPTION: A large industrial project near Sheikhupura, Pakistan. The project comprised complete civil, mechanical & electrical works. These included construction of steam turbine house, control room, gas turbine, HRSG and transformer foundations, switchyard, cooling tower, office building, warehouse, light fuel oil tanks, water storage tank, asphalt road and hard surfaces, water and waste water treatment plant, waste water pumping station, water supply pipe line, sewerage & drainage system, fire fighting pump house, gas supply pipe line, gas conditioning & filtration system, cable channels, external lighting,erection of steam turbine, piping system, piping bridge, cooling water pipe line, steel structure etc. The Owner is Sapphire Electrical Company & the E&M Contractor is a Czech-based firm CKD-EXPORT.The estimated cost of the project was 13.24 million US Dollars. 4
  • 5. Khurram Ashfaq Khan CV Job Responsibilities • Preparation of detailed construction baseline schedule • Responsible for recording and reporting actual progress against planned progress • Preparation of Latest Forecast (LF) plans • Preparation of S-Curve in terms of manhours & cost • Weekly and monthly reports • Coordination with consultant and client Company Trident Construction Private Limited Designation Site Engineer, QA/QC Engineer Duration July 2007 to June 2008 Project 13-Story Mixed Use Development, including a 5 Star Grand Hyatt Hotel, Shopping Mall & Luxury Apartments DESCRIPTION: A landmark project in Lahore, Pakistan spread over a 15,000m2 area and comprised a 5-star Hyatt Regency Hotel with 300 rooms, Hyatt Serviced Apartments, Pace Circle Apartments and a Shopping Mall with 4 designated floors of retail area. The project was designed by Smallwood, Reynolds, Stewart, Stewart and Associates (SRSS) from. The estimated project cost of the Project was 40 million US Dollars Job Responsibilities • Responsible for Quality Control as the assistant to the project’s Quality Control Manager • Handled material submittals (MS), material inspection requests (MIR), inspection requests (IR), work procedures (WP) and inspection identification cards (IIC) in the Quality Control Department • Maintained records of all the site activities • Checked layouts, levels, rebar fixing and formwork • Undertook coordination with consultant, client and contractor • Checked drawings and quantities for accuracy • Oversaw the selection, requisition of materials and plant for use in construction • Liaised with site staff • Supervised construction activities. • Established Work Procedures (WPs), Inspection Identification Cards (IICs), Inspection requests (IRs) and all documents through “Quality Assurance and Quality Control Plan” Company Engineering Design Bureau Designation Design Engineer Duration March 2006 to June 2007 Project Warid Phase-V, Pakistan Job Responsibilities • Preparation of feasibility reports • Preparation of bar bending schedules • Coordination with contractor and client • Resolving technical issues LANGUAGES English Urdu 5