SlideShare a Scribd company logo
DEFINITELY A SUCCESS STORY! 2016
1 CASE STUDY
Project Title:
EPCL Condensate Refinery
Turnaround & Inspection – 2016
Refinery Capacity:
120,000 barrels per day
Location:
Jabel Ali Free Zone, United
Arab Emirates
Client:
ENOC Processing Company
L.L.C (EPCL)
Shutdown Contractor:
DESCON Engineering, United
Arab Emirates
Shutdown Duration:
2-Feb-16 to 6-Mar-16
(35 Days) – Oil Out/Oil In
Project Value:
54,000,000 AED Approx.
Peak Manpower:
2,000 Personnel Approx.
Safe Man-hours:
800,000 Approx.
WRITTEN BY:
MUJAHID AKHTAR
Planning & Control
Manager
CASE STUDY: JABEL ALI REFINERY SHUTDOWN
INTRODUCTION:
Jabel Ali Refinery is a gas condensate refinery with a planned output of 120,000 barrels per
day (bpd) and was erected in the United Arab Emirates in 1999. The Jebel Ali Oil Refinery
is the UAE's fourth refinery. The refinery is operated by the Emirates National Oil Co, which
is owned by the Dubai Government. The Jebel Ali Refinery took two and a half years to
complete and covers 500,000 m2 of area.
In September 2010, an $850m upgrade was completed at the Jebel Ali Refinery. It was
aimed at increasing the operational capacity from 70,000 bpd to 120,000 bpd. The plant
converts condensates from Qatar, Iran and Australia into LPG, naphtha, jet fuel, diesel and
fuel oil. The naphtha, a total of about 66,000 bpd, is exported for petrochemical use in
South East Asia, and the rest of the liquids are sold to the domestic market.
The Jebel Ali plant has a pipeline link to the fuel tank farm at Dubai International Airport to
provide a constant supply service. The plant is centered on two 60,000 barrels per stream
day condensate distillation units and five merox sweetening units. Its storage capacity is in
excess of four million barrels of condensate feedstock and petroleum products. Feedstock
is acquired from a number of different suppliers within the gulf region and comes to the
plant by pipeline or by ships with a capacity of up to 120,000 dwt. To minimize sulphur
emissions, the sulphur recovery unit processes the streams, which are rich in hydrogen
sulphide from amine treating and sour water stripping.
The plant operates to the highest international standards and every effort is made to ensure
reduction of its environmental impact through the use of state-of-the art technologies and
best engineering practices.
THE CHALLENGE:
EPCL planned this major shutdown to maintain refinery’s integrity and operational utilization
after major shutdown in 2012. EPCL floated the Expression of Interest followed by Request
for Quotations to selected renowned plant maintenance and shutdown services companies
including DESCON Engineering. A comprehensive tender package was prepared and sent
to bidders by EPCL with Scope of Work (SOW) incl. thousands of drawings, specifications
and data sheets in April, 2015.
The bidders submitted the technical proposals in June, 2015 while commercial proposals
were submitted in July, 2015. After through and detailed technical, commercial bids
evaluation and clarifications, EPCL selected DESCON Engineering to take this challenge
considering its past performance, strengths and capabilities. DESCON Engineering was not
the lowest bidder however EPCL used its discretion to award the shutdown contract to
DESCON in September, 2015 after tough commercial negotiations. DESCON Engineering
took the challenge after giving considerable discounts (approx. 10% of commercial bid), as
EPCL has bestowed firm confidence and trust in its world class plant maintenance services,
which was proved correct later.
This shutdown project was also of strategic importance for DESCON Engineering to
strengthen relations with EPCL and to be present in Dubai region specially after losing
couple of long term shutdown and maintenance contracts in Abu Dhabi’s region with
ADNOC Group. Right after award, DESCON Engineering, started shutdown preparations to
demonstrate that it always deliver the projects within schedule and budget while maintaining
the highest Quality and Safety Standards.
This shutdown involved the maintenance, testing, inspection, replacement or repair of
hundreds of static equipment, valves, and cut/weld jobs as EPCL preventive maintenance
analyses indicated that there was a high likelihood of failure that would lead to significant
downtime and production loss if problems were not attended. Stopping production, no
matter the duration, results in decreased revenue for operator. Also additional resources
and other costs associated with the shutdown make it a very expensive endeavor. Most
shutdowns are highly complex and carry inherent safety risks. And as compared to other
projects, shutdowns are more un-predictable since there are many opportunities to discover or
DEFINITELY A SUCCESS STORY! 2016
2 CASE STUDY
create problems involving expensive equipment and machinery. However, planned shutdowns like DESCON does are always
undertaken because ultimately they are good for refinery. These maintenance lead to improvements in the performance of equipment,
processes and some time enable modifications.
The DESCON shutdown Scope of Work (SOW) involved a large number of such “Challenges”, in old plant and new plant but not
limited to following;
 Maintenance/Inspection of over 200 Nos. Vessels, Columns, Tanks and Filters
 Maintenance/Inspection of approx. 98 Nos. Fin Fan Air Coolers
 Maintenance/Inspection of 147 Nos. Heat Exchangers
 Removal/Shifting/Installation of 300+ Nos. PSV’s, MOV’s and Control Valves
 Piping Erection Works of approx. 2,000 Dia Inch of CS, SS, Haste Alloy Materials
 Maintenance/Inspection of 2 Nos. Cooling Towers
 Erection/Dismantling of over 100,000 CuM internal/external Scaffolding
 High Pressure Hydro-jetting (20,000 psi) of over 120,000 Nos. of tubes
 Hydro-testing of over 245 Nos. of Heat Exchanger and Air Coolers
 Catalyst Replacement Works of over 260 CuM in Reactors/Regenerators
 Hot/Cold Insulation Removal/Installation of Approx. 1,500 SqM
 Sand Blasting/Painting/Coating of Approx. 2,700 SqM
 Refractory Repair works of approx. 170 CuM in Furnaces/Boilers etc.
 Maintenance of 100M, 75M & 50M high Flares in 5 Days using 500T/250T Crane
 122 Nos. of Heat Exchanger Bundle Pulling using 45T, 40T Bundle Extractors
 Other Miscellaneous Works incl. Re-tubing of Air Coolers, Furnaces, and Trays Replacement of Columns, and
Maintenance/Inspection of Sumps, Pits, Electric Heaters and UT of Piping Locations etc.
The schedule with major milestones was provided by EPCL, as part of tender documents. The schedule includes 5 days of Safe
Making, 28 days of New & Old Plant Shutdown, and 3 days for Start-up of both Plants. Utilities shutdown period was 7 Days.
The timeline of major milestones was as below;
Jabel Ali Refinery is divided into two plants (terminology wise) i.e. New Plant & Old Plant as detailed below;
OLD Plant constitutes of following major Units;
 Unit 02, 12 - Condensate Distillation Units
 Unit 03, 05, 06, 07, 09 - Kerosene Merox Units
 Unit 20 – Utilities Unit
 Unit 21 – Flares
 Unit 22 - Effluent Treatment Unit
 Unit 23 - LPG Storage Unit
NEW Plant constitutes of following major Units;
 Unit 08 - Naptha Hydro-treater Unit
 Unit 10 - CCR Reformer Unit
 Unit 15 - LPG Fractionation Unit
 Unit 16 - Amine Treating Unit
 Unit 17- Sulphur Recovery Unit
 Unit 31 - HC Flare Unit
 Unit 32 - Effluent Treatment Unit
DEFINITELY A SUCCESS STORY! 2016
3 CASE STUDY
THE SOLUTION:
Right after award in September, 2015; Descon Engineering geared up for the recruitment, selection and mobilization of Shutdown
Core Team as well as other direct and in-direct resources. Descon Engineering has challenge to source, select and mobilize over
1,600 shutdown professionals in a short duration of 2~3 months. The process was started as earliest as possible considering in mind
the time required for UAE government formalities incl. but not limited to visa quota approvals, visa applications, documentation and
immigration’s security clearance etc. Descon Engineering maintains the huge database of Shutdown’s direct and in-direct personnel
who have worked in the past on similar projects in UAE, Qatar, Saudi Arabia, Oman or Pakistan. The HR database was searched;
people were reached by phone, email or by advertisement in major newspapers and social networking media i.e. LinkedIn.
In October, 2015; an effective recruitment campaign was launched in UAE, India, and Pakistan which lasted for couple of weeks.
Descon Engineering shortlisted and selected 25% more personnel than plan to have contingency in case of visa rejections, or last
moment regrets by potential employees. The strategy well paid off, even though numerous visa applications were rejected, and many
personnel were backed-off before hiring. In parallel, in-house resources were spared who were working in Emirates on different
projects and were mobilized early at site to start the preparation works.
A Core Shutdown Team consisting of season professionals was formed in early
November, 2015 which incl. but not limited to Shutdown Manager, Planning
Manager, Deputy Shutdown Managers, HSE Manager, QA/QC Manager,
Material/Store In-charges, Discipline Engineers and Administration In-charge etc. As
soon as Core Shutdown Team got approval from EPCL, they were mobilized at
Refinery and establishment of temporary site facilities (Shutdown Village) was
started. The shutdown village plot plan was drafted, presented to EPCL for review
and later submitted to Jabel Ali Free Zone Authority (JAFZA) for approval. All QHSE
requirements of Dubai Civil Defense (DCD), JAFZA and EPCL were fulfilled before
temporary site facilities establishment. After shutdown village plot plan approval, the area was leveled, and graded for easy placement
of office, material and store containers. The shutdown village consists of the following facilities;
 06 Nos. of Free Issue Materials Containers; 10 Nos. of Tools Containers
 03 Nos. of Consumables Containers; 08 Nos. of Office Containers
 Pre-Fabrication Shop; Sand Blasting/Painting Shop
 A Mosque as well as 06 Nos. (40’) Ablution Containers
 Air Conditioned Messing Hall to accommodate 1,600 people at same time
 Scaffolding Materials Lay-down Area
 And Sub-contractor’s Office, Tools, and Materials Container
 Parking Area for Fleet of Buses, Vehicles and Other Heavy Equipment
During the shutdown village establishment, a detailed schedule (using Oracle Primavera Project Management) was developed for
resources mobilization incl. sub-contracting, direct materials and consumables procurement, heavy equipment and plant hiring.
Dedicated Sub-contracting Engineer, Procurement Engineer, Human Resource Coordinator, E & P Coordinator, Material Coordinator
and Planners were engaged to follow the schedule and deliver resources as per requirement.
In meanwhile, Descon Engineering FEDC & Planning Department took the lead for Free Issue Materials identification and verification
consisting of thousands of spades, blinds, gaskets, spares, pipes and fittings, nuts/bolts and valves etc. Detailed site surveys, visits
were conducted to prepare and submit the final Free Issue Materials lists to EPCL for order placement. The detailed planning was
started in mid November, 2015 when preparation of work/job packages was started. Descon’s Planning Department rigorously
collected information from archives of EPCL, contract documents and developed over five hundred work packages with name wise
supervisor’s allocation to execute the works successfully without struggling to find scope of work. The 75% of work was planned
during the Day shift, while 25% work was scheduled during Night shift. During night shift, no heavy rigging/lifting was allowed by
EPCL, hence only hydro-jetting, hydro-testing, welding, radiography, and equipment man-way, exchangers covers opening and
cleaning etc. were planning during night shift.
The work packages were prepared, submitted for approval to EPCL with the following contents as minimum;
 Scope of Work incl. P & ID’s, GA Drawings, and Isometrics etc.
 Level-IV Schedule
 Blinds Lists and Free Issue Materials List
 Method Statement or Execution Methodology
 Task Risk Assessments
DEFINITELY A SUCCESS STORY! 2016
4 CASE STUDY
 Inspection Test Plans; Rigging Studies
 Box-up Certificates etc.
Descon has a long‐standing HSE commitment to international and local standards for the health and safety of their employees,
clients, and sub-contractors; as well as to the protection of the environment. Descon HSE dedication is demonstrated in a continued
basis such as, promoting a healthy lifestyle, continued HSE Trainings, employing a qualified HSE staff, encouraging positive and safe
behavior practices, and implementation of safety regulations. At Descon, we are committed to following;
 To develop and supply products and services that best meet the needs of our client, are safe, and have minimal impacts on
health and the environment throughout their life cycle
 To run our plants and transport our products safely, protecting our neighbors and employees, and minimizing the impact of
our activities on our environment
 To encourage our subcontractors, suppliers and clients to adopt a policy on health, safety and environment equivalent to our
own
Descon’s HSE slogan was “Zero Lost Time Injury (LTI)” for the
shutdown and achieved over 800,000 safe man-hours with zero LTI. At
Descon, we believe that responsible health, safety, and environmental
practices go hand in hand with the growth of the company and that they
are essential to long-term success. By maintaining Zero LTI’s, Descon
has proven -and will continue to prove– its commitment and dedication
to the belief that employees are the single most valuable asset of the
company.
Considering in mind its core values, Descon HSE Department, prepared
the HSE Plan, Training Matrix, Permit to Work System and Task Risk
Assessment for EPCL shutdown. A comprehensive HSE organization
chart was developed, and approved by EPCL based on which, experienced and certified (NEBOSH/IOSH) HSE Engineers, Safety
Officers, Environmental Officer, Safety Assistance, Fire Watcher and Hole Watcher were selected and deployed at site. Descon strictly
complied with the EPCL, JAZFA and international oil/gas plants safety standards from award to completion of shutdown works.
Every individual who was mobilized at site was given Descon’s as well as EPCL Safety Orientations. Job specific HSE awareness
sessions were also conducted routinely to further improve the safety awareness and to indentify the risks associated with each task.
Descon prepared detailed Task Risk Assessment (TRA) in joint hazard assessment session with EPCL, for following activities so that
each craft working on these activities can understand risks involved;
 Scaffolding Erection, Dismantling and Modification; Rigging and Lifting activities
 Hot Bolting, Bolt Torquing / Tensioning (Hydraulic & Manual) activities
 Hydro Jetting activity; Grit Blasting and Painting activities
 Blinding / De-blinding activities; Insulation and Cladding activities
 Confined Space / Internal activities; Refractory works
 Pressure (hydro / pneumatic) Testing and Air blowing activity
 Hot Work (Cutting, Grinding, Welding, Pre Heat and PWHT) activities
 Removal and re-inserting of Heat Exchanger Tube Bundle using Bundle Puller & Crane, Fork lifter etc.
 Flare Tip inspection, repair and other replacement activities by using Man-basket and Crane
 Radiography; Catalyst unloading / loading activity; Chemical Cleaning Activity etc.
In addition, some specialized crafts were third party certified to meet the EPCL and JAFZA regulations. All riggers, scaffolders, fire
fighters, hole watcher (confined space), and first aid personnel etc, were third party certified and qualified.
A few key HSE statistics are as follows;
Medical Treatment Case (MTC) 1
Near Misses 13
No. of Observations 267
No. of Audits 101
No. of Tool Box Meetings conducted 1627
DEFINITELY A SUCCESS STORY! 2016
5 CASE STUDY
No. of HSE violation warning issued 5
Training Hours (Induction, As per Training Matrix, Third Party etc.) 8484
PTW Trainings (No. of participants) 62
Confined Space Attendant / Hole Watcher (No. of participants) 117
Fire Watcher (No. of participants) 104
All the requirements for managing and controlling the waste management systems were applied during the Shutdown as an ongoing
commitment to safety and to protect human health and the environment by applying waste management principles and incorporating a
hierarchy of waste management practices. Disposal of the following Non-hazardous and Hazardous Wastes were carried out safely as
per EPCL and JAFZA procedure;
 Hydrocarbon sludge; Pyrophoric scales / substance
 Waste Insulation material; Refectory wastes
 Catalyst; Neutralized Chemical Solution
 Waste Sulfur; Used Gaskets
 Used Grit MaterialGeneral waste
 Food Waste; Sewerage Water
Also a “Blanket Permit System” was developed by EPCL and was executed during shutdown to improve productivity of the contractor
and ensured work progressed in a safe and orderly manner. A “Blanket Permit” may be defined as a permit issued to carry out activity
on equipment which is positively isolated by means of blinds and as defined by scope of work in the work packages for the duration of
contractor shutdown window subject to permit conditions being adhered to at all times by the receiver and conducting gas testing at
regular intervals. Descon deployed six dedicated permit initiators and coordinators in day and night shift to comply with blanket permit
system of EPCL which helped to perform all shutdown tasks in productive and safe manner.
In the other hand, Descon’s Quality Control & Assurance Department was busy preparing the QA/QC Plan, Test Packages, PQR,
WPS and Welder’s Qualifications in coordination with EPCL Inspection Department. Being an ISO-9001 certified company, Descon
always strive to achieve client’s satisfaction by:
 Recognizing that quality is the direct responsibility of every individual
 Fulfilling all the specified and implied needs of the clients
 Fully meeting all our commitments on time, every time
 Continuously enhancing skills and know-how through trainings
 Following the quality management system, national/international standards and regulatory requirements
 Continually improving the effectiveness of the quality management system
As soon as the Shutdown Core Team was mobilized at site, QA/QC Department
took the lead and started establishing the quality control procedures. A
comprehensive organization chart was prepared and approved by EPCL which incl.
the QA/QC Manager, QC Engineers, QC Inspectors, NDT Technicians and Welding
Engineer etc. As approx. 1,500 dia inch piping pre-fabrication was involved during
the pre shutdown phase, Descon selected and pre-qualified the welders for CS, SS
and Haste Alloy materials during recruitment phase in India and Pakistan so that no
surprises can affect the critical welding works during the execution of works.
The QA/QC team identified all the equipment inspections, welding and NDT works
incl. sub-contracting activities i.e. IRIS, DPT, RT, MPI, UT, PWHT etc. The
preparation tasks were completed well in advance to comply with schedule, and
EPCL inspection department guidelines. Inspection and Test Plans (ITP) were
prepared for all the scope, and submitted to EPCL for approval. Later, these ITPs
form the part of work packages.
While in parallel, Descon’s Subcontracting Department was active in reaching agreements with EPCL approved subcontractors. EPCL
subcontracting was an imperative part of the project and accounted for 40% appox. of the project. Dedicated subcontracting engineer
was deployed at site to exactly know the scope, coordinate the site survey and scope clarification meetings for subcontractors. After
through technical and commercial evaluation process, following activities was decided to be subcontracted;
 Scaffolding Activities
DEFINITELY A SUCCESS STORY! 2016
6 CASE STUDY
 Painting, Insulation and Refractory activities
 Bolt Torquing, Tensioning and Machining
 Hydro-jetting, Chemical Cleaning
 Catalyst Handling; Re-tubing of Tube Bundles
 Non-destructive Testing (NDT), Post Weld Heat Treatment (PHWT)
Descon adopted a cost saving subcontracting strategy while keeping in mind the quality and schedule aspects of the critical works.
For example, scaffolding quantities were huge (100,000 CuM approx.) and it may not be a good deal to single source the scaffolding
erection works which were scheduled to complete in approx. one month. The scaffolding works were divided into Old Plant and New
Plant of refinery and two scaffolding subcontractors were hired to start the scaffolding erections works. In addition, Descon also
arranged its own scaffolder and scaffolding material as contingency so that no slips occur for this critical activity. The strategy was
fruitful and no issues were faced during timely erection and dismantling of scaffolding.
Similarly, the bolt torquing and tensioning activities were divided between two
different subcontractors which resulted in considerable cost saving and timely
completion of works. However, initially hydro-jetting was single sourced due to
unavailability of any EPCL approved subcontractor which somehow put Descon in
troubled waters. As hydro-jetting was a critical path activity and was very important
for the success of shutdown, Descon built-in the three days float in schedule while
awarding the subcontract to cover any surprises. The hydro-jetting subcontractor
was confident to meet the deadlines, however it proved wrong later. Descon was
not in position to take any risk and forced subcontractor to mobilize additional
manpower and machines and closely watched the productivity. As a back-up plan,
Descon also arranged couple of hydro-jetting machines with crew from third party
and mobilized them to site. This strategy also paid well as pressure was built on
hydro-jetting subcontractor and they complete the hydro-jetting within schedule
however consuming the three days of float.
A considerable cost saving were achieved due to strategies conceived by Descon and due to tight progress monitoring, controls and
in-time deployment and demobilization of subcontractors.
The heavy equipment, tools and plants resources e.g. cranes, forklifts, man-lifts, bundle pullers, trailers, diesel tanker, water/sewage
tanker, compressors, generators, diesel welding machines etc. were planned, identified, and sourced right after award to meet the
target mobilization dates. Descon’s Equipment and Plant (E & P) Department along with Planning Department played a vital role in
successful completion of shutdown. The heavy equipment and plants were hired from multiple suppliers to meet the requirement at
site. Also, Descon’s own heavy equipment were arranged and deployed for shutdown to save the cost.
A fleet of over 150 Nos. of heavy equipment and plant was planned to keep running during the day and night shift which was achieved
successfully without a single equipment breakdown. Another challenge was the uninterrupted diesel supply to all these equipment and
plants, which Descon executed very well by deploying two E & P coordinators in each shift to monitor and fulfill the requirements.
Approx. 100,000 Gallons of Diesel and Petrol was consumed during the shutdown for these equipment and plant.
Another challenge which Descon overcome was supply of direct materials and consumables incl. but not limited to pipes/fittings,
air/water/steam/nitrogen hoses, small bore valves, test assembles, manifolds, welding electrodes, PPE’s, industrial gases, and other
consumables. Descon’s Supply Chain Department sourced, purchased and delivered thousands of line items at site as per schedule
with few exceptions. The direct materials and consumables were calculated and indentified by Planning Department with help of
execution team after careful study of drawings and site surveys. The materials resource plan (MRP) prepared and given to Supply
Chain Department for procurement ahead of start of pre-shutdown activities. A dedicated Project Buyer was deployed at site as well to
follow-up the deliveries and to purchase the petty cash items to keep the supplies uninterrupted for such a critical shutdown. Descon
hasn’t faced any major issues due to direct materials or consumables availability during the project lifecycle.
Yet another important role was played by Descon’s Administration Department who were responsible for manpower visas, JAFZA
passes, vehicles/buses, catering facilities, attendance, plant access cards, pick and drop, temporary site facilities utilities, pantry and
daily transportation of manpower from camps to site without a miss. The challenge was huge, as managing over 2,000 personnel
without fail was near impossible to achieve. A fleet of over 50 nos. of buses, cars, coasters, and double cabins was managed well by
administration department with assistance of Planning Department. More than 135,000 meals approx. were served in Messing Hall at
temporary site facilities during the project duration as well as over 5,000 JAFZA passes were applied and secured online for time
mobilization of manpower inside the plant. Timely arrangement of visas, JAFZA and site passes and implementation of Biometric
attendance system saved a considerable cost and helped Descon to maintain its reputation as world class shutdown service provider.
Once, other department completed their preparations; the Site Execution Team came into spotlight. The preparations were thoroughly
checked, daily internal meetings were conducted to identify any short falls. The work packages prepared by Planning Department
were handover to execution team after approval from EPCL. A strategy was proposed by Descon’s Planning Team to divide the
DEFINITELY A SUCCESS STORY! 2016
7 CASE STUDY
resources between New Plant, Old Plant and Utilities shutdown execution teams. The organization chart was revised to inline the
execution teams as per new strategy which directly in-line with EPCL shutdown organization chart and hierarchy. This strategy to
develop separate execution teams for each plant shutdown proved successful as a healthy competition was created in between teams
to complete the tasks on or ahead of schedule.
Several challenges or fears were existed during the twenty eight days of New/Old Plant shutdown and seven days of Utilities Plant
shutdown which include following but not limited to;
 Descon Shutdown Core Team comprised of seasoned professional of diverse nationalities and backgrounds who haven’t
worked together in the past. This situation created a most likelihood of lack of integration or understanding; however,
surprising the new team overcame their differences and integrated to share their diverse knowledge in a very short time
which led to success of shutdown.
 The first five days of shutdown which were termed as “Safe Making” were the most critical part of project. During the safe
making, both new and old pant were shutting down and all product draining, steaming, purging, equipment man-way
opening and ventilations were planned. 100% resources were going to be utilized day and night during the safe making. A
separate organization chart and strategy was streamlined after consultation with EPCL Process and Operations Department.
Over 11,000 meters of air, water, steam and nitrogen hoses were laid down inside the both plants and approx. 150
manifolds/headers were fabricated and used during safe making. Also, all plant sewers were completely isolated either by
safety blanket with sand bags or by plugging using sand followed by safety blanket.0 Over 3,000 blinds were inserted during
the safe making, 200 static equipment man-way opened, ventilated by using 200+ ejectors and blowers without a single
near miss and within schedule. The EPCL applauded the Descon for completing this challenging task exceeding their
expectations.
 The shutdown schedule was prepared using Oracle Primavera Project
Management consisting of approx. 35,000 activities divided into three phase of
shutdown which incl. Safe Making, Shutdown and Start-up. Work Breakdown
Structure (WBS) was prepared such that we covers the each Plant Shutdown,
Utilities Shutdown, and Equipment Category e.g. Exchangers, Air Coolers, Tanks,
Columns, Vessels etc. The challenge was to capture the accurate progress from
all supervisors and prepare the report for internal and EPCL submission before
9:00 am every morning. Planning team organization chart was prepared and
Planning Engineers, Planners, Scheduler, and Expeditors were mobilized at site.
The reporting structure was very complex, as scope of work consists of thousands
of Level-IV activities. The Earned Value Management (EVM) was implemented,
and reports along with any slippages were daily submitted to EPCL. The issues,
risks and opportunities were clearly highlighted and preventive, corrective actions were taken without falling behind the
schedule. The Descon subcontractors schedule and reporting was also made in line with Descon as well as EPCL reporting
format. EPCL also assisted Descon in developing the interference schedule as other Engineering Contractor were also
doing the modification works on Compressors, Heat Recovery System, and Piping works. Critical activities incl. hydro-jetting,
hydro-testing, re-tubing inside furnaces, refractory repairs, catalyst unloading/loading, valve replacements, and welding
works were separately monitoring and reported. The shutdown was successfully completed ahead of schedule due to
implementation of these monitoring and control measures with assistant of Descon as well as EPCL Teams.
 EPCL identified several additional works to perform during the shutdown which were not anticipated at bidding stage and
requested Descon to provide estimate based on Unit Rates given in agreement. Descon considered to assist EPCL without
hesitation and secured additional works worth over 10% of contract value. Descon took the challenge, optimized the
resources, brought subcontractors onboard and also completed these additional jobs within the shutdown schedule. EPCL
recognized the efforts made and appreciated the team for the job well done. This exercise again proved that Descon has
capabilities, strengths and teams to deliver exceptional results in time, while meeting the quality and safety expectations.
 Heat exchanger are considered the most common and important equipment of any oil and gas plant. Maintenance and
inspection of heat exchanger is not only about opening of heat exchanger, pulling bundles or cleaning, testing and box up.
Geographical location of any heat exchanger can easily decide its maintenance methodology, duration and other
requirements. During pre-shutdown and Level-IV schedule preparation, exchangers were identified that will be handled
through manual, bundle puller or with crane operation. Identification of heat exchangers on ground level and elevated level
along with weight of bundle decided the total number of cranes and tube pullers required to execute the job. Descon has
challenge to handle approx. 145 Nos. of Heat Exchangers in strict compliance with safety and quality standards.
After detailed site survey and reading drawings, Descon identified the type of exchanger and compared it with TEMA
configuration (AKU, AES etc). These results in clearly identifying the total number of bundles that are extractable from shell,
U-tube heat exchanger, plate type heat exchanger etc. Shell and tube exchangers were further divided into following:
 Fixed tube bundle heat exchanger
 Removable bundle heat exchanger
DEFINITELY A SUCCESS STORY! 2016
8 CASE STUDY
 Removable bundle with floating head heat exchanger
In addition, all heat exchanger tube bundle size, weights were tabulated to identify size of crane and type of bundle puller as
well calculated the size of “eye bolt” that were required for pulling bundling from shell. Similarly test rings for all exchanger
as per requirement were checked during the pre-shutdown to avoid any surprises during execution. However, following heat
exchangers were identified as critical ones;
 10E-207 (Regenerator Loop Trim Cooler), a vertical heat exchanger that was initially planned to be removed
through crane was later identified as potential high risk element because it was installed in between three
structural platforms. To remove its bundle, piping nozzle must be de-attached from shell and bonnet,
structural grating must be removed, one structural member must be cut and one piping network must be
isolated via removing spool for easy bundle removal. Keeping in consideration that this exchanger has
bellow, execution team finally removed complete exchanger from location, performed its maintenance and
later reinstall back to its original location without any hitch.
 08E-101 J/K (NHK Reactor Feed/Effluent Exchanger) there was shell nozzle to shell nozzle leakage which
was studied by EPCL as flange misalignment and detailed studies were done during last 2~3 years to rectify.
Even proposal was made that to cut the subject flange (stub-in joint). However Descon during execution of
job identified that a wrong gasket was installed at location. Shell nozzle to nozzle connection gaskets
provided by supplier were not as per original specification resulting in leakage. This earned Descon Team an
applaud and appreciation from EPCL.
 Another critical task was the maintenance, refractory repairs and re-tubing of 02/12-F-101 (Condensate Furnaces), which
Descon executed as per EPCL expectations. The scope incl. huge ship size external scaffolding, opening the fire boxes,
cutting, removing and storing the existing convection and super heater tubes, repairing refractory lining, removal of tubes/
tube supports/ tube sheets and re-installation of the tubes, including the fabrication, Welding, PWHT, NDT and hydro-testing
and final box-up. As pigging of tube passes was also planned by other contractor for four days, Descon has to prepared
schedule in such a way that it can carry the activities parallel without disturbing the other contractor. The challenge was
completed as per schedule, and with desired safety and quality results.
THE RESULT:
The structured, project approach to the shutdown had immediate benefits. Planning
eliminated schedule conflicts that would have caused delays. During implementation,
schedules were tightly managed. When projects slipped or execution team struggled to
perform, immediate actions were taken to bring them back on track. Rapid decision-making
based on good information, sustained project momentum. Contingency plans maintained
order and control. When problems arose, they were dealt with swiftly.
It was obvious that some of the issues that arose made life very difficult for the project team
and if they had not been resolved quickly, with ingenuity and hard work, significant delays
and therefore substantial production loss would have occurred. Despite the costs incurred, if the intended work had not been
completed, then the future availability of such shutdowns and the revenue that depends on its continued operation would have been at
risk.
The careful planning and tightly managed implementation achieved its goals, reducing the shutdown from twenty eight day to twenty
six days, and saving the equivalent of two days of production loss. Enhanced communication reduced interdepartmental conflicts,
improved project team cooperation, and built better relations by clarifying responsibilities. Another valuable outcome was that
improved project documentation provided a useful road map for future shutdowns and exposed new areas for improvement. Detailed
lesson learnt were circulated to all departments for information and to avoid the same issues in next shutdown.
Most of all, Descon secured the appreciation and confidence of EPCL, while EPCL recognized the Descon efforts to complete the
shutdown as per schedule, with high standard of Quality and Safety in following words;
“We have started our refinery after successful turnaround/shutdown works, in a gesture to thank our team
members; we are pleased to confirm that Descon Engineering, UAE has performed the maintenance works at
EPCL Refinery T & I Shutdown-2016 to our complete satisfaction.
Descon Engineering worked round the clock to meet our tight schedule while maintaining high standard of
Quality and Safety. The job was performed in a professional manner by achieving the milestones given by us
which were result of good planning, execution and team work.”

More Related Content

What's hot

Cv mechanical supervisor
Cv mechanical supervisorCv mechanical supervisor
Cv mechanical supervisor
James Ct
 
Design and Operation of NHT Strippers to Protect Catalytic Reformers
Design and Operation of NHT Strippers to Protect Catalytic Reformers Design and Operation of NHT Strippers to Protect Catalytic Reformers
Design and Operation of NHT Strippers to Protect Catalytic Reformers
Gerard B. Hawkins
 
Resume for Plant Maintenance-Management position
Resume for Plant Maintenance-Management positionResume for Plant Maintenance-Management position
Resume for Plant Maintenance-Management positionSohail Hassan Rana
 
00 resume of site supervisor (Pipeline & welding)
00 resume of site supervisor (Pipeline & welding)00 resume of site supervisor (Pipeline & welding)
00 resume of site supervisor (Pipeline & welding)
Mohammad Khan
 
SANJAY KUMAR RESUME
SANJAY KUMAR RESUMESANJAY KUMAR RESUME
SANJAY KUMAR RESUMESanjay Kumar
 
MECHANICAL MAINTENANCE ENGINEER (1)
MECHANICAL MAINTENANCE ENGINEER (1)MECHANICAL MAINTENANCE ENGINEER (1)
MECHANICAL MAINTENANCE ENGINEER (1)Pramodbhai More
 
ONGC HAZIRA PROJECT REPORT
ONGC HAZIRA PROJECT REPORTONGC HAZIRA PROJECT REPORT
ONGC HAZIRA PROJECT REPORT
Nikhil Chavda
 
CV -(Technical Office structural Engineer)
CV -(Technical Office structural Engineer)CV -(Technical Office structural Engineer)
CV -(Technical Office structural Engineer)MAHMOUD SAYED
 
Mohamed Azaad - Estimation Engineer CV
Mohamed Azaad - Estimation Engineer CVMohamed Azaad - Estimation Engineer CV
Mohamed Azaad - Estimation Engineer CVMohamed Azaad
 
Resume of John Prince (Rotating Equipment Technician)
Resume of John Prince (Rotating Equipment Technician)Resume of John Prince (Rotating Equipment Technician)
Resume of John Prince (Rotating Equipment Technician)JOHN PRINCE
 
Mark Crame Lead Instrument Engineer CV
Mark Crame Lead Instrument Engineer CVMark Crame Lead Instrument Engineer CV
Mark Crame Lead Instrument Engineer CVMark Crame
 
Control room operator
Control room operatorControl room operator
Control room operator
alalawi123
 
Mechanical Technician
Mechanical TechnicianMechanical Technician
Mechanical Technician
subbu manian
 
Nasheem CV- Commissioning Technician
Nasheem CV- Commissioning TechnicianNasheem CV- Commissioning Technician
Nasheem CV- Commissioning TechnicianNaseem Ansari
 

What's hot (20)

Cv mechanical supervisor
Cv mechanical supervisorCv mechanical supervisor
Cv mechanical supervisor
 
Design and Operation of NHT Strippers to Protect Catalytic Reformers
Design and Operation of NHT Strippers to Protect Catalytic Reformers Design and Operation of NHT Strippers to Protect Catalytic Reformers
Design and Operation of NHT Strippers to Protect Catalytic Reformers
 
Resume for Plant Maintenance-Management position
Resume for Plant Maintenance-Management positionResume for Plant Maintenance-Management position
Resume for Plant Maintenance-Management position
 
00 resume of site supervisor (Pipeline & welding)
00 resume of site supervisor (Pipeline & welding)00 resume of site supervisor (Pipeline & welding)
00 resume of site supervisor (Pipeline & welding)
 
SENTHIL PANDIAN CV
SENTHIL PANDIAN CVSENTHIL PANDIAN CV
SENTHIL PANDIAN CV
 
SANJAY KUMAR RESUME
SANJAY KUMAR RESUMESANJAY KUMAR RESUME
SANJAY KUMAR RESUME
 
Ram resume
Ram resumeRam resume
Ram resume
 
MECHANICAL MAINTENANCE ENGINEER (1)
MECHANICAL MAINTENANCE ENGINEER (1)MECHANICAL MAINTENANCE ENGINEER (1)
MECHANICAL MAINTENANCE ENGINEER (1)
 
ONGC HAZIRA PROJECT REPORT
ONGC HAZIRA PROJECT REPORTONGC HAZIRA PROJECT REPORT
ONGC HAZIRA PROJECT REPORT
 
CV -(Technical Office structural Engineer)
CV -(Technical Office structural Engineer)CV -(Technical Office structural Engineer)
CV -(Technical Office structural Engineer)
 
Mohamed Azaad - Estimation Engineer CV
Mohamed Azaad - Estimation Engineer CVMohamed Azaad - Estimation Engineer CV
Mohamed Azaad - Estimation Engineer CV
 
YGL Commissioning ORG CHART
YGL Commissioning ORG CHARTYGL Commissioning ORG CHART
YGL Commissioning ORG CHART
 
Resume of John Prince (Rotating Equipment Technician)
Resume of John Prince (Rotating Equipment Technician)Resume of John Prince (Rotating Equipment Technician)
Resume of John Prince (Rotating Equipment Technician)
 
Mark Crame Lead Instrument Engineer CV
Mark Crame Lead Instrument Engineer CVMark Crame Lead Instrument Engineer CV
Mark Crame Lead Instrument Engineer CV
 
Control room operator
Control room operatorControl room operator
Control room operator
 
Mechanical Technician
Mechanical TechnicianMechanical Technician
Mechanical Technician
 
Nasheem CV- Commissioning Technician
Nasheem CV- Commissioning TechnicianNasheem CV- Commissioning Technician
Nasheem CV- Commissioning Technician
 
Nizami_CV
Nizami_CVNizami_CV
Nizami_CV
 
rakesh resume_10.03.2016
rakesh resume_10.03.2016rakesh resume_10.03.2016
rakesh resume_10.03.2016
 
RAMESH_Resume
RAMESH_ResumeRAMESH_Resume
RAMESH_Resume
 

Viewers also liked

Tables Presentation Refinery Overhauling
Tables Presentation Refinery OverhaulingTables Presentation Refinery Overhauling
Tables Presentation Refinery Overhauling
Ashar Ahmed
 
Service quality-bank-case-study-vg
Service quality-bank-case-study-vgService quality-bank-case-study-vg
Service quality-bank-case-study-vgiipmff2
 
Yeucau ve giamsat nhamay
Yeucau ve giamsat nhamayYeucau ve giamsat nhamay
Yeucau ve giamsat nhamay
Hai Nguyen
 
QA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding InspectorQA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding Inspector
Asad Ahsan
 
Cswip plant inspector course level i week 2
Cswip plant inspector course level i week 2Cswip plant inspector course level i week 2
Cswip plant inspector course level i week 2ram111eg
 
Cswip 11-01 - plant inspection- Week 2 cours
Cswip 11-01 - plant inspection- Week 2 coursCswip 11-01 - plant inspection- Week 2 cours
Cswip 11-01 - plant inspection- Week 2 cours
Rafik Guerbous
 
Cswip plant inspector course level i week 1
Cswip plant inspector course level i week 1Cswip plant inspector course level i week 1
Cswip plant inspector course level i week 1ram111eg
 
Cswip 11-01 - plant inspection- Week 1 cours
Cswip 11-01 - plant inspection- Week 1 coursCswip 11-01 - plant inspection- Week 1 cours
Cswip 11-01 - plant inspection- Week 1 cours
Rafik Guerbous
 
Welded steel tanks for storage oil
Welded steel tanks for storage oilWelded steel tanks for storage oil
Welded steel tanks for storage oilYahya Haggag
 
143137557 storage-tanks
143137557 storage-tanks143137557 storage-tanks
143137557 storage-tanks
bernard347
 
Chris brooks storage tanks inspection, maintenance and failure
Chris brooks   storage tanks inspection, maintenance and failureChris brooks   storage tanks inspection, maintenance and failure
Chris brooks storage tanks inspection, maintenance and failure
Sreekumar K S
 
Introduction to Storage Tanks
Introduction to Storage TanksIntroduction to Storage Tanks
Introduction to Storage Tanks
Ankur Sharma
 
Avon Cosmetics Inc.
Avon Cosmetics Inc. Avon Cosmetics Inc.
Avon Cosmetics Inc. Mark Bulahan
 
Tank design - powerpoint slides
Tank design - powerpoint slidesTank design - powerpoint slides
Tank design - powerpoint slides
moamen mohamed
 
Piping basics knowledge
Piping basics knowledgePiping basics knowledge
Piping basics knowledge
ARINDAM BANERJEE
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Varun Patel
 

Viewers also liked (20)

Tables Presentation Refinery Overhauling
Tables Presentation Refinery OverhaulingTables Presentation Refinery Overhauling
Tables Presentation Refinery Overhauling
 
Service quality-bank-case-study-vg
Service quality-bank-case-study-vgService quality-bank-case-study-vg
Service quality-bank-case-study-vg
 
Yeucau ve giamsat nhamay
Yeucau ve giamsat nhamayYeucau ve giamsat nhamay
Yeucau ve giamsat nhamay
 
QA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding InspectorQA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding Inspector
 
Acute Left Ventricular Failure
Acute Left Ventricular FailureAcute Left Ventricular Failure
Acute Left Ventricular Failure
 
Cswip plant inspector course level i week 2
Cswip plant inspector course level i week 2Cswip plant inspector course level i week 2
Cswip plant inspector course level i week 2
 
Cswip 11-01 - plant inspection- Week 2 cours
Cswip 11-01 - plant inspection- Week 2 coursCswip 11-01 - plant inspection- Week 2 cours
Cswip 11-01 - plant inspection- Week 2 cours
 
Tank Training
Tank TrainingTank Training
Tank Training
 
Cswip plant inspector course level i week 1
Cswip plant inspector course level i week 1Cswip plant inspector course level i week 1
Cswip plant inspector course level i week 1
 
Cswip 11-01 - plant inspection- Week 1 cours
Cswip 11-01 - plant inspection- Week 1 coursCswip 11-01 - plant inspection- Week 1 cours
Cswip 11-01 - plant inspection- Week 1 cours
 
Ppt
PptPpt
Ppt
 
Welded steel tanks for storage oil
Welded steel tanks for storage oilWelded steel tanks for storage oil
Welded steel tanks for storage oil
 
143137557 storage-tanks
143137557 storage-tanks143137557 storage-tanks
143137557 storage-tanks
 
Chris brooks storage tanks inspection, maintenance and failure
Chris brooks   storage tanks inspection, maintenance and failureChris brooks   storage tanks inspection, maintenance and failure
Chris brooks storage tanks inspection, maintenance and failure
 
Introduction to Storage Tanks
Introduction to Storage TanksIntroduction to Storage Tanks
Introduction to Storage Tanks
 
Avon Cosmetics Inc.
Avon Cosmetics Inc. Avon Cosmetics Inc.
Avon Cosmetics Inc.
 
Tank design - powerpoint slides
Tank design - powerpoint slidesTank design - powerpoint slides
Tank design - powerpoint slides
 
Piping basics knowledge
Piping basics knowledgePiping basics knowledge
Piping basics knowledge
 
Question bank
Question bankQuestion bank
Question bank
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
 

Similar to CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016

JESEDLOPECCV042017
JESEDLOPECCV042017JESEDLOPECCV042017
JESEDLOPECCV042017
Jesus Eduardo Lopez
 
Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016ehsan nazeer
 
Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016ehsan nazeer
 
Process Engr_Rashid CV
Process Engr_Rashid CVProcess Engr_Rashid CV
Process Engr_Rashid CVRashid Iqbal
 
A1 Company Profile Secure Supplies 1.pdf
A1 Company Profile Secure Supplies 1.pdfA1 Company Profile Secure Supplies 1.pdf
A1 Company Profile Secure Supplies 1.pdf
Daniel Donatelli
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
Comit Projects Ltd
 
Mec Brief 2009
Mec Brief 2009Mec Brief 2009
Mec Brief 2009
Ahmed
 
Jorge luis sousa escandon cv february 2020
Jorge luis sousa escandon cv february 2020Jorge luis sousa escandon cv february 2020
Jorge luis sousa escandon cv february 2020
Jorge Luis Sousa Escandòn
 
AZMET-Newsletter 2016-17
AZMET-Newsletter 2016-17AZMET-Newsletter 2016-17
AZMET-Newsletter 2016-17Charl Du Preez
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARSAQIB MANIAR
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
MichaelUberti
 
RCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcreeRCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcree
RCREEE
 
Sr Cost Estimator-Resume (July 2016)-Pankaj Kisnadwala
Sr Cost Estimator-Resume (July 2016)-Pankaj KisnadwalaSr Cost Estimator-Resume (July 2016)-Pankaj Kisnadwala
Sr Cost Estimator-Resume (July 2016)-Pankaj KisnadwalaPankaj Kisnadwala
 

Similar to CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016 (20)

01_HVAC-R5_Tecni
01_HVAC-R5_Tecni01_HVAC-R5_Tecni
01_HVAC-R5_Tecni
 
SISCO - Presentation SABIC
SISCO - Presentation SABICSISCO - Presentation SABIC
SISCO - Presentation SABIC
 
JESEDLOPECCV042017
JESEDLOPECCV042017JESEDLOPECCV042017
JESEDLOPECCV042017
 
Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016
 
Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016
 
Process Engr_Rashid CV
Process Engr_Rashid CVProcess Engr_Rashid CV
Process Engr_Rashid CV
 
OGP Awards 2011
OGP Awards 2011OGP Awards 2011
OGP Awards 2011
 
A1 Company Profile Secure Supplies 1.pdf
A1 Company Profile Secure Supplies 1.pdfA1 Company Profile Secure Supplies 1.pdf
A1 Company Profile Secure Supplies 1.pdf
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
 
Mec Brief 2009
Mec Brief 2009Mec Brief 2009
Mec Brief 2009
 
Jorge luis sousa escandon cv february 2020
Jorge luis sousa escandon cv february 2020Jorge luis sousa escandon cv february 2020
Jorge luis sousa escandon cv february 2020
 
Yaqoob Resume.docx 15-4-2015
Yaqoob Resume.docx 15-4-2015Yaqoob Resume.docx 15-4-2015
Yaqoob Resume.docx 15-4-2015
 
Khursaniyah Project Brochure
Khursaniyah Project BrochureKhursaniyah Project Brochure
Khursaniyah Project Brochure
 
V.GUHAN-CV 01 link
V.GUHAN-CV 01 linkV.GUHAN-CV 01 link
V.GUHAN-CV 01 link
 
Clough Enercore Brochure
Clough Enercore BrochureClough Enercore Brochure
Clough Enercore Brochure
 
AZMET-Newsletter 2016-17
AZMET-Newsletter 2016-17AZMET-Newsletter 2016-17
AZMET-Newsletter 2016-17
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIAR
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
 
RCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcreeRCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcree
 
Sr Cost Estimator-Resume (July 2016)-Pankaj Kisnadwala
Sr Cost Estimator-Resume (July 2016)-Pankaj KisnadwalaSr Cost Estimator-Resume (July 2016)-Pankaj Kisnadwala
Sr Cost Estimator-Resume (July 2016)-Pankaj Kisnadwala
 

Recently uploaded

Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 

Recently uploaded (20)

Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 

CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016

  • 1. DEFINITELY A SUCCESS STORY! 2016 1 CASE STUDY Project Title: EPCL Condensate Refinery Turnaround & Inspection – 2016 Refinery Capacity: 120,000 barrels per day Location: Jabel Ali Free Zone, United Arab Emirates Client: ENOC Processing Company L.L.C (EPCL) Shutdown Contractor: DESCON Engineering, United Arab Emirates Shutdown Duration: 2-Feb-16 to 6-Mar-16 (35 Days) – Oil Out/Oil In Project Value: 54,000,000 AED Approx. Peak Manpower: 2,000 Personnel Approx. Safe Man-hours: 800,000 Approx. WRITTEN BY: MUJAHID AKHTAR Planning & Control Manager CASE STUDY: JABEL ALI REFINERY SHUTDOWN INTRODUCTION: Jabel Ali Refinery is a gas condensate refinery with a planned output of 120,000 barrels per day (bpd) and was erected in the United Arab Emirates in 1999. The Jebel Ali Oil Refinery is the UAE's fourth refinery. The refinery is operated by the Emirates National Oil Co, which is owned by the Dubai Government. The Jebel Ali Refinery took two and a half years to complete and covers 500,000 m2 of area. In September 2010, an $850m upgrade was completed at the Jebel Ali Refinery. It was aimed at increasing the operational capacity from 70,000 bpd to 120,000 bpd. The plant converts condensates from Qatar, Iran and Australia into LPG, naphtha, jet fuel, diesel and fuel oil. The naphtha, a total of about 66,000 bpd, is exported for petrochemical use in South East Asia, and the rest of the liquids are sold to the domestic market. The Jebel Ali plant has a pipeline link to the fuel tank farm at Dubai International Airport to provide a constant supply service. The plant is centered on two 60,000 barrels per stream day condensate distillation units and five merox sweetening units. Its storage capacity is in excess of four million barrels of condensate feedstock and petroleum products. Feedstock is acquired from a number of different suppliers within the gulf region and comes to the plant by pipeline or by ships with a capacity of up to 120,000 dwt. To minimize sulphur emissions, the sulphur recovery unit processes the streams, which are rich in hydrogen sulphide from amine treating and sour water stripping. The plant operates to the highest international standards and every effort is made to ensure reduction of its environmental impact through the use of state-of-the art technologies and best engineering practices. THE CHALLENGE: EPCL planned this major shutdown to maintain refinery’s integrity and operational utilization after major shutdown in 2012. EPCL floated the Expression of Interest followed by Request for Quotations to selected renowned plant maintenance and shutdown services companies including DESCON Engineering. A comprehensive tender package was prepared and sent to bidders by EPCL with Scope of Work (SOW) incl. thousands of drawings, specifications and data sheets in April, 2015. The bidders submitted the technical proposals in June, 2015 while commercial proposals were submitted in July, 2015. After through and detailed technical, commercial bids evaluation and clarifications, EPCL selected DESCON Engineering to take this challenge considering its past performance, strengths and capabilities. DESCON Engineering was not the lowest bidder however EPCL used its discretion to award the shutdown contract to DESCON in September, 2015 after tough commercial negotiations. DESCON Engineering took the challenge after giving considerable discounts (approx. 10% of commercial bid), as EPCL has bestowed firm confidence and trust in its world class plant maintenance services, which was proved correct later. This shutdown project was also of strategic importance for DESCON Engineering to strengthen relations with EPCL and to be present in Dubai region specially after losing couple of long term shutdown and maintenance contracts in Abu Dhabi’s region with ADNOC Group. Right after award, DESCON Engineering, started shutdown preparations to demonstrate that it always deliver the projects within schedule and budget while maintaining the highest Quality and Safety Standards. This shutdown involved the maintenance, testing, inspection, replacement or repair of hundreds of static equipment, valves, and cut/weld jobs as EPCL preventive maintenance analyses indicated that there was a high likelihood of failure that would lead to significant downtime and production loss if problems were not attended. Stopping production, no matter the duration, results in decreased revenue for operator. Also additional resources and other costs associated with the shutdown make it a very expensive endeavor. Most shutdowns are highly complex and carry inherent safety risks. And as compared to other projects, shutdowns are more un-predictable since there are many opportunities to discover or
  • 2. DEFINITELY A SUCCESS STORY! 2016 2 CASE STUDY create problems involving expensive equipment and machinery. However, planned shutdowns like DESCON does are always undertaken because ultimately they are good for refinery. These maintenance lead to improvements in the performance of equipment, processes and some time enable modifications. The DESCON shutdown Scope of Work (SOW) involved a large number of such “Challenges”, in old plant and new plant but not limited to following;  Maintenance/Inspection of over 200 Nos. Vessels, Columns, Tanks and Filters  Maintenance/Inspection of approx. 98 Nos. Fin Fan Air Coolers  Maintenance/Inspection of 147 Nos. Heat Exchangers  Removal/Shifting/Installation of 300+ Nos. PSV’s, MOV’s and Control Valves  Piping Erection Works of approx. 2,000 Dia Inch of CS, SS, Haste Alloy Materials  Maintenance/Inspection of 2 Nos. Cooling Towers  Erection/Dismantling of over 100,000 CuM internal/external Scaffolding  High Pressure Hydro-jetting (20,000 psi) of over 120,000 Nos. of tubes  Hydro-testing of over 245 Nos. of Heat Exchanger and Air Coolers  Catalyst Replacement Works of over 260 CuM in Reactors/Regenerators  Hot/Cold Insulation Removal/Installation of Approx. 1,500 SqM  Sand Blasting/Painting/Coating of Approx. 2,700 SqM  Refractory Repair works of approx. 170 CuM in Furnaces/Boilers etc.  Maintenance of 100M, 75M & 50M high Flares in 5 Days using 500T/250T Crane  122 Nos. of Heat Exchanger Bundle Pulling using 45T, 40T Bundle Extractors  Other Miscellaneous Works incl. Re-tubing of Air Coolers, Furnaces, and Trays Replacement of Columns, and Maintenance/Inspection of Sumps, Pits, Electric Heaters and UT of Piping Locations etc. The schedule with major milestones was provided by EPCL, as part of tender documents. The schedule includes 5 days of Safe Making, 28 days of New & Old Plant Shutdown, and 3 days for Start-up of both Plants. Utilities shutdown period was 7 Days. The timeline of major milestones was as below; Jabel Ali Refinery is divided into two plants (terminology wise) i.e. New Plant & Old Plant as detailed below; OLD Plant constitutes of following major Units;  Unit 02, 12 - Condensate Distillation Units  Unit 03, 05, 06, 07, 09 - Kerosene Merox Units  Unit 20 – Utilities Unit  Unit 21 – Flares  Unit 22 - Effluent Treatment Unit  Unit 23 - LPG Storage Unit NEW Plant constitutes of following major Units;  Unit 08 - Naptha Hydro-treater Unit  Unit 10 - CCR Reformer Unit  Unit 15 - LPG Fractionation Unit  Unit 16 - Amine Treating Unit  Unit 17- Sulphur Recovery Unit  Unit 31 - HC Flare Unit  Unit 32 - Effluent Treatment Unit
  • 3. DEFINITELY A SUCCESS STORY! 2016 3 CASE STUDY THE SOLUTION: Right after award in September, 2015; Descon Engineering geared up for the recruitment, selection and mobilization of Shutdown Core Team as well as other direct and in-direct resources. Descon Engineering has challenge to source, select and mobilize over 1,600 shutdown professionals in a short duration of 2~3 months. The process was started as earliest as possible considering in mind the time required for UAE government formalities incl. but not limited to visa quota approvals, visa applications, documentation and immigration’s security clearance etc. Descon Engineering maintains the huge database of Shutdown’s direct and in-direct personnel who have worked in the past on similar projects in UAE, Qatar, Saudi Arabia, Oman or Pakistan. The HR database was searched; people were reached by phone, email or by advertisement in major newspapers and social networking media i.e. LinkedIn. In October, 2015; an effective recruitment campaign was launched in UAE, India, and Pakistan which lasted for couple of weeks. Descon Engineering shortlisted and selected 25% more personnel than plan to have contingency in case of visa rejections, or last moment regrets by potential employees. The strategy well paid off, even though numerous visa applications were rejected, and many personnel were backed-off before hiring. In parallel, in-house resources were spared who were working in Emirates on different projects and were mobilized early at site to start the preparation works. A Core Shutdown Team consisting of season professionals was formed in early November, 2015 which incl. but not limited to Shutdown Manager, Planning Manager, Deputy Shutdown Managers, HSE Manager, QA/QC Manager, Material/Store In-charges, Discipline Engineers and Administration In-charge etc. As soon as Core Shutdown Team got approval from EPCL, they were mobilized at Refinery and establishment of temporary site facilities (Shutdown Village) was started. The shutdown village plot plan was drafted, presented to EPCL for review and later submitted to Jabel Ali Free Zone Authority (JAFZA) for approval. All QHSE requirements of Dubai Civil Defense (DCD), JAFZA and EPCL were fulfilled before temporary site facilities establishment. After shutdown village plot plan approval, the area was leveled, and graded for easy placement of office, material and store containers. The shutdown village consists of the following facilities;  06 Nos. of Free Issue Materials Containers; 10 Nos. of Tools Containers  03 Nos. of Consumables Containers; 08 Nos. of Office Containers  Pre-Fabrication Shop; Sand Blasting/Painting Shop  A Mosque as well as 06 Nos. (40’) Ablution Containers  Air Conditioned Messing Hall to accommodate 1,600 people at same time  Scaffolding Materials Lay-down Area  And Sub-contractor’s Office, Tools, and Materials Container  Parking Area for Fleet of Buses, Vehicles and Other Heavy Equipment During the shutdown village establishment, a detailed schedule (using Oracle Primavera Project Management) was developed for resources mobilization incl. sub-contracting, direct materials and consumables procurement, heavy equipment and plant hiring. Dedicated Sub-contracting Engineer, Procurement Engineer, Human Resource Coordinator, E & P Coordinator, Material Coordinator and Planners were engaged to follow the schedule and deliver resources as per requirement. In meanwhile, Descon Engineering FEDC & Planning Department took the lead for Free Issue Materials identification and verification consisting of thousands of spades, blinds, gaskets, spares, pipes and fittings, nuts/bolts and valves etc. Detailed site surveys, visits were conducted to prepare and submit the final Free Issue Materials lists to EPCL for order placement. The detailed planning was started in mid November, 2015 when preparation of work/job packages was started. Descon’s Planning Department rigorously collected information from archives of EPCL, contract documents and developed over five hundred work packages with name wise supervisor’s allocation to execute the works successfully without struggling to find scope of work. The 75% of work was planned during the Day shift, while 25% work was scheduled during Night shift. During night shift, no heavy rigging/lifting was allowed by EPCL, hence only hydro-jetting, hydro-testing, welding, radiography, and equipment man-way, exchangers covers opening and cleaning etc. were planning during night shift. The work packages were prepared, submitted for approval to EPCL with the following contents as minimum;  Scope of Work incl. P & ID’s, GA Drawings, and Isometrics etc.  Level-IV Schedule  Blinds Lists and Free Issue Materials List  Method Statement or Execution Methodology  Task Risk Assessments
  • 4. DEFINITELY A SUCCESS STORY! 2016 4 CASE STUDY  Inspection Test Plans; Rigging Studies  Box-up Certificates etc. Descon has a long‐standing HSE commitment to international and local standards for the health and safety of their employees, clients, and sub-contractors; as well as to the protection of the environment. Descon HSE dedication is demonstrated in a continued basis such as, promoting a healthy lifestyle, continued HSE Trainings, employing a qualified HSE staff, encouraging positive and safe behavior practices, and implementation of safety regulations. At Descon, we are committed to following;  To develop and supply products and services that best meet the needs of our client, are safe, and have minimal impacts on health and the environment throughout their life cycle  To run our plants and transport our products safely, protecting our neighbors and employees, and minimizing the impact of our activities on our environment  To encourage our subcontractors, suppliers and clients to adopt a policy on health, safety and environment equivalent to our own Descon’s HSE slogan was “Zero Lost Time Injury (LTI)” for the shutdown and achieved over 800,000 safe man-hours with zero LTI. At Descon, we believe that responsible health, safety, and environmental practices go hand in hand with the growth of the company and that they are essential to long-term success. By maintaining Zero LTI’s, Descon has proven -and will continue to prove– its commitment and dedication to the belief that employees are the single most valuable asset of the company. Considering in mind its core values, Descon HSE Department, prepared the HSE Plan, Training Matrix, Permit to Work System and Task Risk Assessment for EPCL shutdown. A comprehensive HSE organization chart was developed, and approved by EPCL based on which, experienced and certified (NEBOSH/IOSH) HSE Engineers, Safety Officers, Environmental Officer, Safety Assistance, Fire Watcher and Hole Watcher were selected and deployed at site. Descon strictly complied with the EPCL, JAZFA and international oil/gas plants safety standards from award to completion of shutdown works. Every individual who was mobilized at site was given Descon’s as well as EPCL Safety Orientations. Job specific HSE awareness sessions were also conducted routinely to further improve the safety awareness and to indentify the risks associated with each task. Descon prepared detailed Task Risk Assessment (TRA) in joint hazard assessment session with EPCL, for following activities so that each craft working on these activities can understand risks involved;  Scaffolding Erection, Dismantling and Modification; Rigging and Lifting activities  Hot Bolting, Bolt Torquing / Tensioning (Hydraulic & Manual) activities  Hydro Jetting activity; Grit Blasting and Painting activities  Blinding / De-blinding activities; Insulation and Cladding activities  Confined Space / Internal activities; Refractory works  Pressure (hydro / pneumatic) Testing and Air blowing activity  Hot Work (Cutting, Grinding, Welding, Pre Heat and PWHT) activities  Removal and re-inserting of Heat Exchanger Tube Bundle using Bundle Puller & Crane, Fork lifter etc.  Flare Tip inspection, repair and other replacement activities by using Man-basket and Crane  Radiography; Catalyst unloading / loading activity; Chemical Cleaning Activity etc. In addition, some specialized crafts were third party certified to meet the EPCL and JAFZA regulations. All riggers, scaffolders, fire fighters, hole watcher (confined space), and first aid personnel etc, were third party certified and qualified. A few key HSE statistics are as follows; Medical Treatment Case (MTC) 1 Near Misses 13 No. of Observations 267 No. of Audits 101 No. of Tool Box Meetings conducted 1627
  • 5. DEFINITELY A SUCCESS STORY! 2016 5 CASE STUDY No. of HSE violation warning issued 5 Training Hours (Induction, As per Training Matrix, Third Party etc.) 8484 PTW Trainings (No. of participants) 62 Confined Space Attendant / Hole Watcher (No. of participants) 117 Fire Watcher (No. of participants) 104 All the requirements for managing and controlling the waste management systems were applied during the Shutdown as an ongoing commitment to safety and to protect human health and the environment by applying waste management principles and incorporating a hierarchy of waste management practices. Disposal of the following Non-hazardous and Hazardous Wastes were carried out safely as per EPCL and JAFZA procedure;  Hydrocarbon sludge; Pyrophoric scales / substance  Waste Insulation material; Refectory wastes  Catalyst; Neutralized Chemical Solution  Waste Sulfur; Used Gaskets  Used Grit MaterialGeneral waste  Food Waste; Sewerage Water Also a “Blanket Permit System” was developed by EPCL and was executed during shutdown to improve productivity of the contractor and ensured work progressed in a safe and orderly manner. A “Blanket Permit” may be defined as a permit issued to carry out activity on equipment which is positively isolated by means of blinds and as defined by scope of work in the work packages for the duration of contractor shutdown window subject to permit conditions being adhered to at all times by the receiver and conducting gas testing at regular intervals. Descon deployed six dedicated permit initiators and coordinators in day and night shift to comply with blanket permit system of EPCL which helped to perform all shutdown tasks in productive and safe manner. In the other hand, Descon’s Quality Control & Assurance Department was busy preparing the QA/QC Plan, Test Packages, PQR, WPS and Welder’s Qualifications in coordination with EPCL Inspection Department. Being an ISO-9001 certified company, Descon always strive to achieve client’s satisfaction by:  Recognizing that quality is the direct responsibility of every individual  Fulfilling all the specified and implied needs of the clients  Fully meeting all our commitments on time, every time  Continuously enhancing skills and know-how through trainings  Following the quality management system, national/international standards and regulatory requirements  Continually improving the effectiveness of the quality management system As soon as the Shutdown Core Team was mobilized at site, QA/QC Department took the lead and started establishing the quality control procedures. A comprehensive organization chart was prepared and approved by EPCL which incl. the QA/QC Manager, QC Engineers, QC Inspectors, NDT Technicians and Welding Engineer etc. As approx. 1,500 dia inch piping pre-fabrication was involved during the pre shutdown phase, Descon selected and pre-qualified the welders for CS, SS and Haste Alloy materials during recruitment phase in India and Pakistan so that no surprises can affect the critical welding works during the execution of works. The QA/QC team identified all the equipment inspections, welding and NDT works incl. sub-contracting activities i.e. IRIS, DPT, RT, MPI, UT, PWHT etc. The preparation tasks were completed well in advance to comply with schedule, and EPCL inspection department guidelines. Inspection and Test Plans (ITP) were prepared for all the scope, and submitted to EPCL for approval. Later, these ITPs form the part of work packages. While in parallel, Descon’s Subcontracting Department was active in reaching agreements with EPCL approved subcontractors. EPCL subcontracting was an imperative part of the project and accounted for 40% appox. of the project. Dedicated subcontracting engineer was deployed at site to exactly know the scope, coordinate the site survey and scope clarification meetings for subcontractors. After through technical and commercial evaluation process, following activities was decided to be subcontracted;  Scaffolding Activities
  • 6. DEFINITELY A SUCCESS STORY! 2016 6 CASE STUDY  Painting, Insulation and Refractory activities  Bolt Torquing, Tensioning and Machining  Hydro-jetting, Chemical Cleaning  Catalyst Handling; Re-tubing of Tube Bundles  Non-destructive Testing (NDT), Post Weld Heat Treatment (PHWT) Descon adopted a cost saving subcontracting strategy while keeping in mind the quality and schedule aspects of the critical works. For example, scaffolding quantities were huge (100,000 CuM approx.) and it may not be a good deal to single source the scaffolding erection works which were scheduled to complete in approx. one month. The scaffolding works were divided into Old Plant and New Plant of refinery and two scaffolding subcontractors were hired to start the scaffolding erections works. In addition, Descon also arranged its own scaffolder and scaffolding material as contingency so that no slips occur for this critical activity. The strategy was fruitful and no issues were faced during timely erection and dismantling of scaffolding. Similarly, the bolt torquing and tensioning activities were divided between two different subcontractors which resulted in considerable cost saving and timely completion of works. However, initially hydro-jetting was single sourced due to unavailability of any EPCL approved subcontractor which somehow put Descon in troubled waters. As hydro-jetting was a critical path activity and was very important for the success of shutdown, Descon built-in the three days float in schedule while awarding the subcontract to cover any surprises. The hydro-jetting subcontractor was confident to meet the deadlines, however it proved wrong later. Descon was not in position to take any risk and forced subcontractor to mobilize additional manpower and machines and closely watched the productivity. As a back-up plan, Descon also arranged couple of hydro-jetting machines with crew from third party and mobilized them to site. This strategy also paid well as pressure was built on hydro-jetting subcontractor and they complete the hydro-jetting within schedule however consuming the three days of float. A considerable cost saving were achieved due to strategies conceived by Descon and due to tight progress monitoring, controls and in-time deployment and demobilization of subcontractors. The heavy equipment, tools and plants resources e.g. cranes, forklifts, man-lifts, bundle pullers, trailers, diesel tanker, water/sewage tanker, compressors, generators, diesel welding machines etc. were planned, identified, and sourced right after award to meet the target mobilization dates. Descon’s Equipment and Plant (E & P) Department along with Planning Department played a vital role in successful completion of shutdown. The heavy equipment and plants were hired from multiple suppliers to meet the requirement at site. Also, Descon’s own heavy equipment were arranged and deployed for shutdown to save the cost. A fleet of over 150 Nos. of heavy equipment and plant was planned to keep running during the day and night shift which was achieved successfully without a single equipment breakdown. Another challenge was the uninterrupted diesel supply to all these equipment and plants, which Descon executed very well by deploying two E & P coordinators in each shift to monitor and fulfill the requirements. Approx. 100,000 Gallons of Diesel and Petrol was consumed during the shutdown for these equipment and plant. Another challenge which Descon overcome was supply of direct materials and consumables incl. but not limited to pipes/fittings, air/water/steam/nitrogen hoses, small bore valves, test assembles, manifolds, welding electrodes, PPE’s, industrial gases, and other consumables. Descon’s Supply Chain Department sourced, purchased and delivered thousands of line items at site as per schedule with few exceptions. The direct materials and consumables were calculated and indentified by Planning Department with help of execution team after careful study of drawings and site surveys. The materials resource plan (MRP) prepared and given to Supply Chain Department for procurement ahead of start of pre-shutdown activities. A dedicated Project Buyer was deployed at site as well to follow-up the deliveries and to purchase the petty cash items to keep the supplies uninterrupted for such a critical shutdown. Descon hasn’t faced any major issues due to direct materials or consumables availability during the project lifecycle. Yet another important role was played by Descon’s Administration Department who were responsible for manpower visas, JAFZA passes, vehicles/buses, catering facilities, attendance, plant access cards, pick and drop, temporary site facilities utilities, pantry and daily transportation of manpower from camps to site without a miss. The challenge was huge, as managing over 2,000 personnel without fail was near impossible to achieve. A fleet of over 50 nos. of buses, cars, coasters, and double cabins was managed well by administration department with assistance of Planning Department. More than 135,000 meals approx. were served in Messing Hall at temporary site facilities during the project duration as well as over 5,000 JAFZA passes were applied and secured online for time mobilization of manpower inside the plant. Timely arrangement of visas, JAFZA and site passes and implementation of Biometric attendance system saved a considerable cost and helped Descon to maintain its reputation as world class shutdown service provider. Once, other department completed their preparations; the Site Execution Team came into spotlight. The preparations were thoroughly checked, daily internal meetings were conducted to identify any short falls. The work packages prepared by Planning Department were handover to execution team after approval from EPCL. A strategy was proposed by Descon’s Planning Team to divide the
  • 7. DEFINITELY A SUCCESS STORY! 2016 7 CASE STUDY resources between New Plant, Old Plant and Utilities shutdown execution teams. The organization chart was revised to inline the execution teams as per new strategy which directly in-line with EPCL shutdown organization chart and hierarchy. This strategy to develop separate execution teams for each plant shutdown proved successful as a healthy competition was created in between teams to complete the tasks on or ahead of schedule. Several challenges or fears were existed during the twenty eight days of New/Old Plant shutdown and seven days of Utilities Plant shutdown which include following but not limited to;  Descon Shutdown Core Team comprised of seasoned professional of diverse nationalities and backgrounds who haven’t worked together in the past. This situation created a most likelihood of lack of integration or understanding; however, surprising the new team overcame their differences and integrated to share their diverse knowledge in a very short time which led to success of shutdown.  The first five days of shutdown which were termed as “Safe Making” were the most critical part of project. During the safe making, both new and old pant were shutting down and all product draining, steaming, purging, equipment man-way opening and ventilations were planned. 100% resources were going to be utilized day and night during the safe making. A separate organization chart and strategy was streamlined after consultation with EPCL Process and Operations Department. Over 11,000 meters of air, water, steam and nitrogen hoses were laid down inside the both plants and approx. 150 manifolds/headers were fabricated and used during safe making. Also, all plant sewers were completely isolated either by safety blanket with sand bags or by plugging using sand followed by safety blanket.0 Over 3,000 blinds were inserted during the safe making, 200 static equipment man-way opened, ventilated by using 200+ ejectors and blowers without a single near miss and within schedule. The EPCL applauded the Descon for completing this challenging task exceeding their expectations.  The shutdown schedule was prepared using Oracle Primavera Project Management consisting of approx. 35,000 activities divided into three phase of shutdown which incl. Safe Making, Shutdown and Start-up. Work Breakdown Structure (WBS) was prepared such that we covers the each Plant Shutdown, Utilities Shutdown, and Equipment Category e.g. Exchangers, Air Coolers, Tanks, Columns, Vessels etc. The challenge was to capture the accurate progress from all supervisors and prepare the report for internal and EPCL submission before 9:00 am every morning. Planning team organization chart was prepared and Planning Engineers, Planners, Scheduler, and Expeditors were mobilized at site. The reporting structure was very complex, as scope of work consists of thousands of Level-IV activities. The Earned Value Management (EVM) was implemented, and reports along with any slippages were daily submitted to EPCL. The issues, risks and opportunities were clearly highlighted and preventive, corrective actions were taken without falling behind the schedule. The Descon subcontractors schedule and reporting was also made in line with Descon as well as EPCL reporting format. EPCL also assisted Descon in developing the interference schedule as other Engineering Contractor were also doing the modification works on Compressors, Heat Recovery System, and Piping works. Critical activities incl. hydro-jetting, hydro-testing, re-tubing inside furnaces, refractory repairs, catalyst unloading/loading, valve replacements, and welding works were separately monitoring and reported. The shutdown was successfully completed ahead of schedule due to implementation of these monitoring and control measures with assistant of Descon as well as EPCL Teams.  EPCL identified several additional works to perform during the shutdown which were not anticipated at bidding stage and requested Descon to provide estimate based on Unit Rates given in agreement. Descon considered to assist EPCL without hesitation and secured additional works worth over 10% of contract value. Descon took the challenge, optimized the resources, brought subcontractors onboard and also completed these additional jobs within the shutdown schedule. EPCL recognized the efforts made and appreciated the team for the job well done. This exercise again proved that Descon has capabilities, strengths and teams to deliver exceptional results in time, while meeting the quality and safety expectations.  Heat exchanger are considered the most common and important equipment of any oil and gas plant. Maintenance and inspection of heat exchanger is not only about opening of heat exchanger, pulling bundles or cleaning, testing and box up. Geographical location of any heat exchanger can easily decide its maintenance methodology, duration and other requirements. During pre-shutdown and Level-IV schedule preparation, exchangers were identified that will be handled through manual, bundle puller or with crane operation. Identification of heat exchangers on ground level and elevated level along with weight of bundle decided the total number of cranes and tube pullers required to execute the job. Descon has challenge to handle approx. 145 Nos. of Heat Exchangers in strict compliance with safety and quality standards. After detailed site survey and reading drawings, Descon identified the type of exchanger and compared it with TEMA configuration (AKU, AES etc). These results in clearly identifying the total number of bundles that are extractable from shell, U-tube heat exchanger, plate type heat exchanger etc. Shell and tube exchangers were further divided into following:  Fixed tube bundle heat exchanger  Removable bundle heat exchanger
  • 8. DEFINITELY A SUCCESS STORY! 2016 8 CASE STUDY  Removable bundle with floating head heat exchanger In addition, all heat exchanger tube bundle size, weights were tabulated to identify size of crane and type of bundle puller as well calculated the size of “eye bolt” that were required for pulling bundling from shell. Similarly test rings for all exchanger as per requirement were checked during the pre-shutdown to avoid any surprises during execution. However, following heat exchangers were identified as critical ones;  10E-207 (Regenerator Loop Trim Cooler), a vertical heat exchanger that was initially planned to be removed through crane was later identified as potential high risk element because it was installed in between three structural platforms. To remove its bundle, piping nozzle must be de-attached from shell and bonnet, structural grating must be removed, one structural member must be cut and one piping network must be isolated via removing spool for easy bundle removal. Keeping in consideration that this exchanger has bellow, execution team finally removed complete exchanger from location, performed its maintenance and later reinstall back to its original location without any hitch.  08E-101 J/K (NHK Reactor Feed/Effluent Exchanger) there was shell nozzle to shell nozzle leakage which was studied by EPCL as flange misalignment and detailed studies were done during last 2~3 years to rectify. Even proposal was made that to cut the subject flange (stub-in joint). However Descon during execution of job identified that a wrong gasket was installed at location. Shell nozzle to nozzle connection gaskets provided by supplier were not as per original specification resulting in leakage. This earned Descon Team an applaud and appreciation from EPCL.  Another critical task was the maintenance, refractory repairs and re-tubing of 02/12-F-101 (Condensate Furnaces), which Descon executed as per EPCL expectations. The scope incl. huge ship size external scaffolding, opening the fire boxes, cutting, removing and storing the existing convection and super heater tubes, repairing refractory lining, removal of tubes/ tube supports/ tube sheets and re-installation of the tubes, including the fabrication, Welding, PWHT, NDT and hydro-testing and final box-up. As pigging of tube passes was also planned by other contractor for four days, Descon has to prepared schedule in such a way that it can carry the activities parallel without disturbing the other contractor. The challenge was completed as per schedule, and with desired safety and quality results. THE RESULT: The structured, project approach to the shutdown had immediate benefits. Planning eliminated schedule conflicts that would have caused delays. During implementation, schedules were tightly managed. When projects slipped or execution team struggled to perform, immediate actions were taken to bring them back on track. Rapid decision-making based on good information, sustained project momentum. Contingency plans maintained order and control. When problems arose, they were dealt with swiftly. It was obvious that some of the issues that arose made life very difficult for the project team and if they had not been resolved quickly, with ingenuity and hard work, significant delays and therefore substantial production loss would have occurred. Despite the costs incurred, if the intended work had not been completed, then the future availability of such shutdowns and the revenue that depends on its continued operation would have been at risk. The careful planning and tightly managed implementation achieved its goals, reducing the shutdown from twenty eight day to twenty six days, and saving the equivalent of two days of production loss. Enhanced communication reduced interdepartmental conflicts, improved project team cooperation, and built better relations by clarifying responsibilities. Another valuable outcome was that improved project documentation provided a useful road map for future shutdowns and exposed new areas for improvement. Detailed lesson learnt were circulated to all departments for information and to avoid the same issues in next shutdown. Most of all, Descon secured the appreciation and confidence of EPCL, while EPCL recognized the Descon efforts to complete the shutdown as per schedule, with high standard of Quality and Safety in following words; “We have started our refinery after successful turnaround/shutdown works, in a gesture to thank our team members; we are pleased to confirm that Descon Engineering, UAE has performed the maintenance works at EPCL Refinery T & I Shutdown-2016 to our complete satisfaction. Descon Engineering worked round the clock to meet our tight schedule while maintaining high standard of Quality and Safety. The job was performed in a professional manner by achieving the milestones given by us which were result of good planning, execution and team work.”