SlideShare a Scribd company logo
Jason Douglas
Earned Value Basics and Application
Jason Douglas– PM, Senior PM and Portfolio Lead
The Road Ahead
• Earn Value Defined
• Reasons why Earned Value is not used
• What causes Earned Value not to be Accurate
• Earned Value Pre-requisites
• Simple Scenario
• Formula Basics
• Question 1
• Question 1 Answers
• Other Earned Factors to Consider
• Summary and Next Steps
Earned ValueDefined
Earned value management (EVM) is used to assess and grade a PM and
their project based on the schedule and cost performance of a project.
A PM needs to demonstrate control and one key areas is EVM:
• Ahead of / on / behind schedule
• Under / on / over budget
• Earned value management (EVM) is based on the concept that
• i) work completed will deliver value and
• ii) the value delivered equals the budget put into the work.
Reasons Why Earned Value is NOT used
• Too hard and expensive too
• Not enough budget or time
• Programme Management has not allocated enough time for
development or standardisation
• Plans are not mature enough
• Internal or External charge out rates will be exposed to customer or
other resources
• No documented requirements
• Incomplete requirements
• Just because requirements are
baselined does no make them
complete
• SMART* approach needs to be
used
• WBS* not used or not accepted;
(Plan the Plan)
• WBS incomplete;
• Plan not integrated (WBS-Schedule-
Budget)
• Schedule and/or budget incorrect
• Change management not used or
ineffective;
• Cost collection system inadequate;
• Incorrect progress recorded
• When is a task 0,20,80,100% complete
• management influence and/or
control.
• Contingencies added in to the project
Earned Value Pre-Requisites
• The project must have an agreed
‘Baseline Budget’
• Implications Include
• Project Outlook (budget from
Account) aligned to
• Cost Model
• Schedule (Effort, Duration and
Deliverables).
• AS IS model to be agreed/baselined
• If there is no contingency then
project slippages or additional
meetings need Change Requests
(CR) for money and time.
• Decision is needed on CR triggers
• Raw Financial Reports need to be
timely and align with reported
progress
• Requirements, deliverables,
governance approach and processes
need to be agreed up front.
• Good will
Simple Scenario
• Build a Fence with 10 Panels, each panel takes a day.
• It is day 4, 4 panels should have been built
• Each panel has a value of £100
Formulas Basics
Planned Value (PV) At end of day 4, 4 panels
should be complete
4 panels x £100 =£400
The budgeted value of the
work completed so far at a
specific date
Earned Value (EV) By end of day 4 only 3
panels have been built
hence the EV is £300
The actual value of the
work completed so far at a
specific date
Actual Cost (AC) By end of day 4 actual cost
is £400
The total expenditure for
the work so far at a
specific date
Budget At Completion
(BAC)
10 Panels at £100 each =
£1000
The total budget for the
project
Formula Basics Continued
Schedule Variance (SV) At end of day 4,
SV= £300-£400
-£100
Minus is behind schedule
Plus is in front
Is the projects work ahead
or behind schedule
SV=EV-PV
Schedule Performance
Index (SPI)
By end of day 4
SPI= £300/£400
0.75
Minus now becomes below
one
Plus becomes higher than
one
Represents schedule
variance as a ratio
SPI=EV/PV
Formula Basics Continued
Cost Variance (CV) At end of day 4,
CV= £300-£400
-£100
Minus is behind budget
Plus is in front
Is the projects costs ahead
or behind budget
CV=EV-AC
Cost Performance Index
(CPI)
By end of day 4
CPI= £300/£400
0.75
Minus is achieved less than
is planned
Plus achieved more than is
planned
Represents schedule
variance as a ratio
CPI=EV/AC
SPI and CPI Interpretation
• CPI above 1 – for every £ spent, obtaining more value that is expected
• SPI - how close the actual work is to the schedule – above 1 ahead of
schedule
• Interesting when combining 2 ratios together
CPI 0.75 / SPI 0.90 Spending too much money and behind time. Investigate
CPI 0.90 / SPI 1.5 Spending too much money getting ahead of schedule
CPI 1.5 / SPI 0.90 Adding lots of value but slower than planned
CPI 1.5 / SPI 1.5 Adding lots of value / faster than planned. CR required
and replan.
Question 1
• Bid Budget of £15,000 which includes uplifts. £10,000 is the Labour Cost. The Project Lasts 5
weeks and the money should be spent evenly
• By end of week 2 The following deliverables are completed, Project Start Up, Set up in corporate
system for reporting, request for labour and requests for getting labour reports done. The project
has been created a project sharepoint, Cost Model, CR Templates, DAIR Log Created, Projects
Meetings Set Up, Requirements are Baselined, Capacity Sheet Submitted, Bid Charter Baselined,
Pricing sheet submitted, Network Diagram created. The Cost registered in labour systems is
£4500. However 3 weeks work is Completed.
• What is the BAC, EV, PV, AC
• What is SV, SPI
• What is the CV, CPI
• Interpret the data what does it mean
PTO to see answers
Answers
• What is the BAC, EV, PV, AC
• BAC = £10,000
• EV = £6,000 (3 Weeks effort)
• PV = £4,000 (2 weeks effort)
• AC =£4,500 what has been spent
• What is SV, SPI
• SV = EV-PV £6,000 - £4,000 SV = £2000
• SPI = EV/PV £6,000/£4000 SPI = 1.5
• What is the CV, CPI
• CV = EV-AC £6,000-£4,500 = £1,500
• CPI = EV/AC =1.33
• Interpret the data what does it mean
• Ahead of schedule and ahead of budget at end of week 2.
EV Considerations
• Physical Measurement — directly transform the physical measurement of the amount of
work completed into EV
• example: building 10 Panels each has a value of £100 expected to be completed in 10 days in
proportion, earned value of 3 panel built is £300
• Percentage Complete — directly transform the percentage of the amount of work
completed into EV
• example: building 10 panel each has a value of £100 expected to be completed in 10 days in
proportion, earned value of 30% complete is £300
• Weighted Milestone — a EV is assigned to the 100% completion of each milestone of the
work packages with prior agreement with stakeholders
• Fixed Formula — a specific percentage of the overall PV is assigned to the start of a work
package and the remaining assigned upon completion; these must be agreed upon in the
project management plan
• 0/100 rule: 0% EV at the activity begins; 100% EV upon completion
• 20/80 rule: 20% EV at the activity begins; 80% EV upon completion.
• 50/50 rule: 50% EV at the activity begins; 50% EV upon completion
Summary and Next Steps
• Basic 101 of what is earned value
• Why we use it
• Covered of simple example and had a practise question
• Next Lesson on Earned value
• Applying Earned Value to projects and programmes
• More complex formula such as budget at completion
Thank you
Any questions to Jason Douglas
Jasondouglas1105@outlook.com
Mobile 07496002461
16

More Related Content

What's hot

Earned value management
Earned value managementEarned value management
Earned value management
Ashif AR
 
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
HARDIK PARIKH
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Vivek Prakash
 

What's hot (20)

Earned value
Earned valueEarned value
Earned value
 
Earned value management
Earned value managementEarned value management
Earned value management
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned value management
Earned value managementEarned value management
Earned value management
 
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Earned Value
Earned ValueEarned Value
Earned Value
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 

Viewers also liked

Art is not the Enemy_Writing Sample from Exhibition Catalogue
Art is not the Enemy_Writing Sample from Exhibition CatalogueArt is not the Enemy_Writing Sample from Exhibition Catalogue
Art is not the Enemy_Writing Sample from Exhibition Catalogue
Joelle Rebeiz
 
CVofAndrewMichaelBlairworkhistory
CVofAndrewMichaelBlairworkhistoryCVofAndrewMichaelBlairworkhistory
CVofAndrewMichaelBlairworkhistory
Andrew Blair
 
Realty Connection - Fidelity - Broker Presentation
Realty Connection - Fidelity - Broker PresentationRealty Connection - Fidelity - Broker Presentation
Realty Connection - Fidelity - Broker Presentation
Jami Robertson
 
Curriculum Vitae of MD. ENAMUL HAQUE
Curriculum Vitae of MD. ENAMUL HAQUECurriculum Vitae of MD. ENAMUL HAQUE
Curriculum Vitae of MD. ENAMUL HAQUE
Md. Enamul Haque
 
A Presentation On Summer Internship Project Done At
A Presentation On Summer Internship Project Done AtA Presentation On Summer Internship Project Done At
A Presentation On Summer Internship Project Done At
sumanta kumar das
 

Viewers also liked (10)

Art is not the Enemy_Writing Sample from Exhibition Catalogue
Art is not the Enemy_Writing Sample from Exhibition CatalogueArt is not the Enemy_Writing Sample from Exhibition Catalogue
Art is not the Enemy_Writing Sample from Exhibition Catalogue
 
CVofAndrewMichaelBlairworkhistory
CVofAndrewMichaelBlairworkhistoryCVofAndrewMichaelBlairworkhistory
CVofAndrewMichaelBlairworkhistory
 
MOHAMMED. ABED CV
MOHAMMED. ABED CVMOHAMMED. ABED CV
MOHAMMED. ABED CV
 
Verity About us e-brochure
Verity About us e-brochureVerity About us e-brochure
Verity About us e-brochure
 
Realty Connection - Fidelity - Broker Presentation
Realty Connection - Fidelity - Broker PresentationRealty Connection - Fidelity - Broker Presentation
Realty Connection - Fidelity - Broker Presentation
 
Curriculum Vitae of MD. ENAMUL HAQUE
Curriculum Vitae of MD. ENAMUL HAQUECurriculum Vitae of MD. ENAMUL HAQUE
Curriculum Vitae of MD. ENAMUL HAQUE
 
Thesis Final Version
Thesis Final VersionThesis Final Version
Thesis Final Version
 
A Presentation On Summer Internship Project Done At
A Presentation On Summer Internship Project Done AtA Presentation On Summer Internship Project Done At
A Presentation On Summer Internship Project Done At
 
Project Report on e banking
Project Report on e bankingProject Report on e banking
Project Report on e banking
 
Verity About us e-brochure
Verity About us e-brochureVerity About us e-brochure
Verity About us e-brochure
 

Similar to Jason douglas earned value 1 0

Earned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxEarned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptx
ssuser5fc1e7
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
AsBali1
 
Cost unit 2013 part 2. 24 jan
Cost unit 2013 part 2. 24 janCost unit 2013 part 2. 24 jan
Cost unit 2013 part 2. 24 jan
Skript
 
Scanning Solution Final Ver2.1
Scanning Solution Final Ver2.1Scanning Solution Final Ver2.1
Scanning Solution Final Ver2.1
Pavithra Sampath
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
ssusercf695b
 

Similar to Jason douglas earned value 1 0 (20)

6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
 
Earned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxEarned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptx
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
Cost management
Cost managementCost management
Cost management
 
4.Cost management
4.Cost management4.Cost management
4.Cost management
 
Cost unit 2013 part 2. 24 jan
Cost unit 2013 part 2. 24 janCost unit 2013 part 2. 24 jan
Cost unit 2013 part 2. 24 jan
 
The Benefits Of An In House Energy Engineer
The Benefits Of An In House Energy EngineerThe Benefits Of An In House Energy Engineer
The Benefits Of An In House Energy Engineer
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
 
Cost management
Cost managementCost management
Cost management
 
Scanning Solution Final Ver2.1
Scanning Solution Final Ver2.1Scanning Solution Final Ver2.1
Scanning Solution Final Ver2.1
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
204720 unifier at xcel energy
204720 unifier at xcel energy204720 unifier at xcel energy
204720 unifier at xcel energy
 
Group g
Group gGroup g
Group g
 
Following the-EXEED-methodology: data centre design
Following the-EXEED-methodology: data centre designFollowing the-EXEED-methodology: data centre design
Following the-EXEED-methodology: data centre design
 
DominicMcHalecv171
DominicMcHalecv171DominicMcHalecv171
DominicMcHalecv171
 

Recently uploaded

Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
Khaled Al Awadi
 

Recently uploaded (20)

5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Special Purpose Vehicle (Purpose, Formation & examples)
Special Purpose Vehicle (Purpose, Formation & examples)Special Purpose Vehicle (Purpose, Formation & examples)
Special Purpose Vehicle (Purpose, Formation & examples)
 
Luxury Artificial Plants Dubai | Plants in KSA, UAE | Shajara
Luxury Artificial Plants Dubai | Plants in KSA, UAE | ShajaraLuxury Artificial Plants Dubai | Plants in KSA, UAE | Shajara
Luxury Artificial Plants Dubai | Plants in KSA, UAE | Shajara
 
Equinox Gold Corporate Deck May 24th 2024
Equinox Gold Corporate Deck May 24th 2024Equinox Gold Corporate Deck May 24th 2024
Equinox Gold Corporate Deck May 24th 2024
 
India’s Recommended Women Surgeons to Watch in 2024.pdf
India’s Recommended Women Surgeons to Watch in 2024.pdfIndia’s Recommended Women Surgeons to Watch in 2024.pdf
India’s Recommended Women Surgeons to Watch in 2024.pdf
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
USA classified ads posting – best classified sites in usa.pdf
USA classified ads posting – best classified sites in usa.pdfUSA classified ads posting – best classified sites in usa.pdf
USA classified ads posting – best classified sites in usa.pdf
 
Transforming Max Life Insurance with PMaps Job-Fit Assessments- Case Study
Transforming Max Life Insurance with PMaps Job-Fit Assessments- Case StudyTransforming Max Life Insurance with PMaps Job-Fit Assessments- Case Study
Transforming Max Life Insurance with PMaps Job-Fit Assessments- Case Study
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
 
Hyundai capital 2024 1quarter Earnings release
Hyundai capital 2024 1quarter Earnings releaseHyundai capital 2024 1quarter Earnings release
Hyundai capital 2024 1quarter Earnings release
 
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
 
How to Maintain Healthy Life style.pptx
How to Maintain  Healthy Life style.pptxHow to Maintain  Healthy Life style.pptx
How to Maintain Healthy Life style.pptx
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
LinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptxLinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptx
 
Understanding UAE Labour Law: Key Points for Employers and Employees
Understanding UAE Labour Law: Key Points for Employers and EmployeesUnderstanding UAE Labour Law: Key Points for Employers and Employees
Understanding UAE Labour Law: Key Points for Employers and Employees
 
Byrd & Chen’s Canadian Tax Principles 2023-2024 Edition 1st edition Volumes I...
Byrd & Chen’s Canadian Tax Principles 2023-2024 Edition 1st edition Volumes I...Byrd & Chen’s Canadian Tax Principles 2023-2024 Edition 1st edition Volumes I...
Byrd & Chen’s Canadian Tax Principles 2023-2024 Edition 1st edition Volumes I...
 

Jason douglas earned value 1 0

  • 1. Jason Douglas Earned Value Basics and Application Jason Douglas– PM, Senior PM and Portfolio Lead
  • 2. The Road Ahead • Earn Value Defined • Reasons why Earned Value is not used • What causes Earned Value not to be Accurate • Earned Value Pre-requisites • Simple Scenario • Formula Basics • Question 1 • Question 1 Answers • Other Earned Factors to Consider • Summary and Next Steps
  • 3. Earned ValueDefined Earned value management (EVM) is used to assess and grade a PM and their project based on the schedule and cost performance of a project. A PM needs to demonstrate control and one key areas is EVM: • Ahead of / on / behind schedule • Under / on / over budget • Earned value management (EVM) is based on the concept that • i) work completed will deliver value and • ii) the value delivered equals the budget put into the work.
  • 4. Reasons Why Earned Value is NOT used • Too hard and expensive too • Not enough budget or time • Programme Management has not allocated enough time for development or standardisation • Plans are not mature enough • Internal or External charge out rates will be exposed to customer or other resources
  • 5. • No documented requirements • Incomplete requirements • Just because requirements are baselined does no make them complete • SMART* approach needs to be used • WBS* not used or not accepted; (Plan the Plan) • WBS incomplete; • Plan not integrated (WBS-Schedule- Budget) • Schedule and/or budget incorrect • Change management not used or ineffective; • Cost collection system inadequate; • Incorrect progress recorded • When is a task 0,20,80,100% complete • management influence and/or control. • Contingencies added in to the project
  • 6. Earned Value Pre-Requisites • The project must have an agreed ‘Baseline Budget’ • Implications Include • Project Outlook (budget from Account) aligned to • Cost Model • Schedule (Effort, Duration and Deliverables). • AS IS model to be agreed/baselined • If there is no contingency then project slippages or additional meetings need Change Requests (CR) for money and time. • Decision is needed on CR triggers • Raw Financial Reports need to be timely and align with reported progress • Requirements, deliverables, governance approach and processes need to be agreed up front. • Good will
  • 7. Simple Scenario • Build a Fence with 10 Panels, each panel takes a day. • It is day 4, 4 panels should have been built • Each panel has a value of £100
  • 8. Formulas Basics Planned Value (PV) At end of day 4, 4 panels should be complete 4 panels x £100 =£400 The budgeted value of the work completed so far at a specific date Earned Value (EV) By end of day 4 only 3 panels have been built hence the EV is £300 The actual value of the work completed so far at a specific date Actual Cost (AC) By end of day 4 actual cost is £400 The total expenditure for the work so far at a specific date Budget At Completion (BAC) 10 Panels at £100 each = £1000 The total budget for the project
  • 9. Formula Basics Continued Schedule Variance (SV) At end of day 4, SV= £300-£400 -£100 Minus is behind schedule Plus is in front Is the projects work ahead or behind schedule SV=EV-PV Schedule Performance Index (SPI) By end of day 4 SPI= £300/£400 0.75 Minus now becomes below one Plus becomes higher than one Represents schedule variance as a ratio SPI=EV/PV
  • 10. Formula Basics Continued Cost Variance (CV) At end of day 4, CV= £300-£400 -£100 Minus is behind budget Plus is in front Is the projects costs ahead or behind budget CV=EV-AC Cost Performance Index (CPI) By end of day 4 CPI= £300/£400 0.75 Minus is achieved less than is planned Plus achieved more than is planned Represents schedule variance as a ratio CPI=EV/AC
  • 11. SPI and CPI Interpretation • CPI above 1 – for every £ spent, obtaining more value that is expected • SPI - how close the actual work is to the schedule – above 1 ahead of schedule • Interesting when combining 2 ratios together CPI 0.75 / SPI 0.90 Spending too much money and behind time. Investigate CPI 0.90 / SPI 1.5 Spending too much money getting ahead of schedule CPI 1.5 / SPI 0.90 Adding lots of value but slower than planned CPI 1.5 / SPI 1.5 Adding lots of value / faster than planned. CR required and replan.
  • 12. Question 1 • Bid Budget of £15,000 which includes uplifts. £10,000 is the Labour Cost. The Project Lasts 5 weeks and the money should be spent evenly • By end of week 2 The following deliverables are completed, Project Start Up, Set up in corporate system for reporting, request for labour and requests for getting labour reports done. The project has been created a project sharepoint, Cost Model, CR Templates, DAIR Log Created, Projects Meetings Set Up, Requirements are Baselined, Capacity Sheet Submitted, Bid Charter Baselined, Pricing sheet submitted, Network Diagram created. The Cost registered in labour systems is £4500. However 3 weeks work is Completed. • What is the BAC, EV, PV, AC • What is SV, SPI • What is the CV, CPI • Interpret the data what does it mean PTO to see answers
  • 13. Answers • What is the BAC, EV, PV, AC • BAC = £10,000 • EV = £6,000 (3 Weeks effort) • PV = £4,000 (2 weeks effort) • AC =£4,500 what has been spent • What is SV, SPI • SV = EV-PV £6,000 - £4,000 SV = £2000 • SPI = EV/PV £6,000/£4000 SPI = 1.5 • What is the CV, CPI • CV = EV-AC £6,000-£4,500 = £1,500 • CPI = EV/AC =1.33 • Interpret the data what does it mean • Ahead of schedule and ahead of budget at end of week 2.
  • 14. EV Considerations • Physical Measurement — directly transform the physical measurement of the amount of work completed into EV • example: building 10 Panels each has a value of £100 expected to be completed in 10 days in proportion, earned value of 3 panel built is £300 • Percentage Complete — directly transform the percentage of the amount of work completed into EV • example: building 10 panel each has a value of £100 expected to be completed in 10 days in proportion, earned value of 30% complete is £300 • Weighted Milestone — a EV is assigned to the 100% completion of each milestone of the work packages with prior agreement with stakeholders • Fixed Formula — a specific percentage of the overall PV is assigned to the start of a work package and the remaining assigned upon completion; these must be agreed upon in the project management plan • 0/100 rule: 0% EV at the activity begins; 100% EV upon completion • 20/80 rule: 20% EV at the activity begins; 80% EV upon completion. • 50/50 rule: 50% EV at the activity begins; 50% EV upon completion
  • 15. Summary and Next Steps • Basic 101 of what is earned value • Why we use it • Covered of simple example and had a practise question • Next Lesson on Earned value • Applying Earned Value to projects and programmes • More complex formula such as budget at completion
  • 16. Thank you Any questions to Jason Douglas Jasondouglas1105@outlook.com Mobile 07496002461 16

Editor's Notes

  1. Specific Measurable Attainable Realistic Timely – SMART (Framework for writing requirements) Workbreak down structure. – once the project has asked the questions, what do you want (requirements), and the project team has responded with what we need to do (Scope), the How WBS is how we do it, break down the scope into segments called decomposition.
  2. AS IS – is the current mode of operation or model. In Contrast there there to the To Be – end point. CR – Change Requests, these are used to change requirements, scope, time or quality from an agreed point.
  3. Planned Value (PV) The budgeted value of the work completed so far at a specific date Earned Value (EV) The actual value of the work completed so far at a specific date  Actual Cost (AC) The total expenditure for the work so far at a specific date
  4. BAC – budget at completion Earned Value Planned Value Actual Value Schedule Variance Scheduled Variance Index Cost Variance Cost Performance Index