SlideShare a Scribd company logo
1 of 16
Earned Value
Management –
Project
Controls
Prepared by: Amr Omar
12-Apr-2021
Agenda
1. Introduction to Project Controls
2. What is Planned Value
3. What is % Complete and what is Earned Value
4. What is Actual Costs
5. Project Performance Metrics
• SPI and Schedule Variance
• CPI and Cost Variance
What is Project Controls?
• Project Controls are an ongoing process which Project Managers
continuously perform through the lifecycle of the project. This process is
aimed to measure project performance and be enable the project
manager to forecast the finish.
• Main Areas of Controls:
1. Scope
2. Schedule
3. Cost
4. Quality
Introduction
to Schedule
Controls
Schedule Phases
• The phases of the schedule development
1. During Estimate Phase : Initial Schedule or Estimate Schedule
• High level estimate to estimate durations based on the understanding of the scope
• Performed by the Estimating Team
2. After Contract Award: Baseline Schedule
• Typically published after 10 business days from contract award and is discussed in the kick-
off meeting with the client.
• Should be more refined than the initial schedule and client buy-in is obtained
• Once Client buys-in it is stored and named as the Baseline Schedule
• Baseline schedule is the playbook of all project schedules and is always referred back to in
all stages of the project.
• All Schedule Controls are performed throughout the project to measure against the baseline
schedule
Baseline Schedule Example:
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
A
B
C
D
E
GANTT CHART presentation for Baseline Schedule
Further Development of Baseline Schedule
Activity Duration Budget
A 5 $20,000
B 3 $15,000
C 4 $20,000
D 2 $4,000
E 3 $18,000
TOTAL BUDGET
(BAC)
$77,000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
A 4k 4k 4k 4k 4k
B 5k 5k 5k
C 5k 5k 5k 5k
D 2k 2k
E 6k 6k 6k
Schedule Example - Continued
Question:
- By day 3, per the baseline,
how much did we PLAN to
spend?
- Answer: PV = $12k
- By day 7, what is our
planned value?
- Answer: PV= $40k
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
A 4k 4k 4k 4k 4k
B 5k 5k 5k
C 5k 5k 5k 5k
D 2k 2k
E 6k 6k 6k
Planned Value - Continued
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
A 4k 4k 4k 4k 4k
B 5k 5k 5k
C 5k 5k 5k 5k
D 2k 2k
E 6k 6k 6k
PV 4k 8k 12k 16k 20k 30k 40k 50k 55k 57k 59k 65k 71k 77k
Earned Value
• Earned value is how much actual progress was completed for any given
activity at a certain point in time (DATA DATE).
• It is a derived as a percentage of the original budget, based on scope
completion
• The % complete is always the percentage completed of SCOPE
Therefore:
EARNED VALUE = % Complete of SCOPE x Budget (BAC)
Earned Value Example
Activity Duration Budget
A 5 $20,000
B 3 $15,000
C 4 $20,000
D 2 $4,000
E 3 $18,000
TOTAL BUDGET
(BAC)
$77,000
Activity % Comp
A 100 %
B 50%
C 100%
D 0%
E 0%
TOTAL EARNED VALUE
(EV)
AFTER 6
days OR
by day 7
DATA
DATE
EV
$20,000
$7,500
$20,000
0
0
$47,500
Earned Value – Schedule Metrics
• At day 7:
• EV =$47,500
• PV = $40,000
Question:
How is our schedule
performance?
Answer:
We’re doing well!
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
A 4k 4k 4k 4k 4k
B 5k 5k 5k
C 5k 5k 5k 5k
D 2k 2k
E 6k 6k 6k
P
V
4k 8k 12
k
16
k
20
k
30
k
40
k
50
k
55
k
57
k
59
k
65
k
71
k
77
k
EV @
day 7
$20,000
$7,500
$20,000
0
0
$47,500
Example Continue- Schedule-wise, How well
are we doing?
• EV = $47,500
• PV = $40,000
• Since we actually earned better than we planned, (EV > PV), then . We’re ahead of schedule
• IF EV< PV, then we’re behind schedule
• Further dissection:
• At day 7 (our data date – when we collected all data), our schedule earnings were how much higher than
planned??? (This is called Schedule Variance)
• Schedule Variance = EV – PV = $7,500 (positive number)
• OR
• At day 7 , how much did we earn compared to planned (just a simple division)
• EV / PV = 47500 / 40000 = 1.1875
• THIS IS CALLED SCHEDULE PERFOMANCE INDEX = SPI
Schedule Controls Summary
• Planned Value = PV = What was planned at the baseline schedule in terms of budget
• Earned Value = EV = How much we earned of what was budgeted for
EV= ACTUAL % COMPLETE OF SCOPE x Budget
• Schedule Variance = SV = Earned Value – Planned Value = EV - PV
IF SV = Positive Number , then we’re ahead of schedule
IF SV = Negative Number, then we’re behind schedule
• Schedule Performance Index = SPI = Earned Value / Planned Value = EV/PV
IF SPI is greater than 1, then we’re ahead of schedule
IF SPI is less than 1, then we’re behind schedule
Exercise for the team
• Question: The total budget at completion for the entire project is $800,000. The
project has a total planned value of $180,000 after 5 days, per the baseline
schedule. After 5 days, the percent complete for the project was calculated at
20%. Please calculate the Schedule Variance, Schedule Performance Index
and determine whether the project is ahead or behind schedule.
• Answer:
• EV = 20%x 800,000 = $160,000
• SV = EV-PV = $160,000 - $180,000 = ($ - 20,000)
• SPI = EV/PV = $160/180 = 0.88
• Therefore, the project is running behind schedule
Exercise for the team
• At a given data date for project XYZ, the SPI was 0.8. The planned value at
the data date was $380,000 and the overall budget at completion is
$800,000. What is the percentage completed of scope at this data date?

More Related Content

Similar to Earned Value Management - Project Controls - Schedule Only.pptx

EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis trainingPaul King
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasAnand Bobade
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisSaqib Raza
 
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN PanigrahiSN Panigrahi, PMP
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentationCDN_Irony
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureJohn Carter
 

Similar to Earned Value Management - Project Controls - Schedule Only.pptx (20)

EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
IT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.pptIT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.ppt
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
S-Curve Presentation- 20130529
S-Curve Presentation- 20130529S-Curve Presentation- 20130529
S-Curve Presentation- 20130529
 
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentation
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
 

Recently uploaded

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 

Recently uploaded (20)

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 

Earned Value Management - Project Controls - Schedule Only.pptx

  • 2. Agenda 1. Introduction to Project Controls 2. What is Planned Value 3. What is % Complete and what is Earned Value 4. What is Actual Costs 5. Project Performance Metrics • SPI and Schedule Variance • CPI and Cost Variance
  • 3. What is Project Controls? • Project Controls are an ongoing process which Project Managers continuously perform through the lifecycle of the project. This process is aimed to measure project performance and be enable the project manager to forecast the finish. • Main Areas of Controls: 1. Scope 2. Schedule 3. Cost 4. Quality
  • 5. Schedule Phases • The phases of the schedule development 1. During Estimate Phase : Initial Schedule or Estimate Schedule • High level estimate to estimate durations based on the understanding of the scope • Performed by the Estimating Team 2. After Contract Award: Baseline Schedule • Typically published after 10 business days from contract award and is discussed in the kick- off meeting with the client. • Should be more refined than the initial schedule and client buy-in is obtained • Once Client buys-in it is stored and named as the Baseline Schedule • Baseline schedule is the playbook of all project schedules and is always referred back to in all stages of the project. • All Schedule Controls are performed throughout the project to measure against the baseline schedule
  • 6. Baseline Schedule Example: 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 A B C D E GANTT CHART presentation for Baseline Schedule
  • 7. Further Development of Baseline Schedule Activity Duration Budget A 5 $20,000 B 3 $15,000 C 4 $20,000 D 2 $4,000 E 3 $18,000 TOTAL BUDGET (BAC) $77,000 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 A 4k 4k 4k 4k 4k B 5k 5k 5k C 5k 5k 5k 5k D 2k 2k E 6k 6k 6k
  • 8. Schedule Example - Continued Question: - By day 3, per the baseline, how much did we PLAN to spend? - Answer: PV = $12k - By day 7, what is our planned value? - Answer: PV= $40k 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 A 4k 4k 4k 4k 4k B 5k 5k 5k C 5k 5k 5k 5k D 2k 2k E 6k 6k 6k
  • 9. Planned Value - Continued 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 A 4k 4k 4k 4k 4k B 5k 5k 5k C 5k 5k 5k 5k D 2k 2k E 6k 6k 6k PV 4k 8k 12k 16k 20k 30k 40k 50k 55k 57k 59k 65k 71k 77k
  • 10. Earned Value • Earned value is how much actual progress was completed for any given activity at a certain point in time (DATA DATE). • It is a derived as a percentage of the original budget, based on scope completion • The % complete is always the percentage completed of SCOPE Therefore: EARNED VALUE = % Complete of SCOPE x Budget (BAC)
  • 11. Earned Value Example Activity Duration Budget A 5 $20,000 B 3 $15,000 C 4 $20,000 D 2 $4,000 E 3 $18,000 TOTAL BUDGET (BAC) $77,000 Activity % Comp A 100 % B 50% C 100% D 0% E 0% TOTAL EARNED VALUE (EV) AFTER 6 days OR by day 7 DATA DATE EV $20,000 $7,500 $20,000 0 0 $47,500
  • 12. Earned Value – Schedule Metrics • At day 7: • EV =$47,500 • PV = $40,000 Question: How is our schedule performance? Answer: We’re doing well! 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 A 4k 4k 4k 4k 4k B 5k 5k 5k C 5k 5k 5k 5k D 2k 2k E 6k 6k 6k P V 4k 8k 12 k 16 k 20 k 30 k 40 k 50 k 55 k 57 k 59 k 65 k 71 k 77 k EV @ day 7 $20,000 $7,500 $20,000 0 0 $47,500
  • 13. Example Continue- Schedule-wise, How well are we doing? • EV = $47,500 • PV = $40,000 • Since we actually earned better than we planned, (EV > PV), then . We’re ahead of schedule • IF EV< PV, then we’re behind schedule • Further dissection: • At day 7 (our data date – when we collected all data), our schedule earnings were how much higher than planned??? (This is called Schedule Variance) • Schedule Variance = EV – PV = $7,500 (positive number) • OR • At day 7 , how much did we earn compared to planned (just a simple division) • EV / PV = 47500 / 40000 = 1.1875 • THIS IS CALLED SCHEDULE PERFOMANCE INDEX = SPI
  • 14. Schedule Controls Summary • Planned Value = PV = What was planned at the baseline schedule in terms of budget • Earned Value = EV = How much we earned of what was budgeted for EV= ACTUAL % COMPLETE OF SCOPE x Budget • Schedule Variance = SV = Earned Value – Planned Value = EV - PV IF SV = Positive Number , then we’re ahead of schedule IF SV = Negative Number, then we’re behind schedule • Schedule Performance Index = SPI = Earned Value / Planned Value = EV/PV IF SPI is greater than 1, then we’re ahead of schedule IF SPI is less than 1, then we’re behind schedule
  • 15. Exercise for the team • Question: The total budget at completion for the entire project is $800,000. The project has a total planned value of $180,000 after 5 days, per the baseline schedule. After 5 days, the percent complete for the project was calculated at 20%. Please calculate the Schedule Variance, Schedule Performance Index and determine whether the project is ahead or behind schedule. • Answer: • EV = 20%x 800,000 = $160,000 • SV = EV-PV = $160,000 - $180,000 = ($ - 20,000) • SPI = EV/PV = $160/180 = 0.88 • Therefore, the project is running behind schedule
  • 16. Exercise for the team • At a given data date for project XYZ, the SPI was 0.8. The planned value at the data date was $380,000 and the overall budget at completion is $800,000. What is the percentage completed of scope at this data date?