SlideShare a Scribd company logo
Investigations of the effects of supplying Jenin’s power distribution
network by a PV generator with respect to voltage level, power
losses, P.F and harmonics
By: Ibrahim Anwar Ibrahim
Ihsan Abd Alfattah Omareya
The supervisor: Dr. Maher Khammash
Outline:
Introduction
Problem Statement
Objectives
Scope
Methodology
Results and Analysis
Conclusion
Constraints
Recommendation
Introduction:
Due to the global trend toward the clean energy resources, it is very important to make our projects
and researches related with it. Moreover, we need to find the best solutions for improving our
power networks taking into consideration the best possible price which represented in the almost
free sources such as solar energy, especially that we are under the occupation and we don't have
control on our networks or the electricity generation.
The share of grid-connected photovoltaic (PV) power sources in power distribution systems is expected
to rise due to increasing costs of traditional fossil-fuel sources and continuous reduction of PV
generators worldwide. This project will present the schematic diagram of a complete PV generator with
control system (design with detailed specifications) to be connected safely with the electric network in
Jenin.
Problem Statement:
We will investigate what is the possibility of using PV generators in order to improve the action of
the system was selected from one part of Jenin’s power distribution network that contains 25 bus in the
same voltage level that consume 10.076 MW, 3.075 MVAR and total power losses 0.136 MW, 0.096
MVAR at Maximum load and consume 1.878 MW, 0.859 MVAR and total power losses 0.00538 MW,
0.00377 MVAR at Minimum load taking in consideration the voltage levels, power losses, P.F and
harmonics.
Objectives:
 Find the optimal placement and sizing of distribution generation PV units in the network.
 Study the impact of the added PV DG units by conducting a new power flow study and
harmonic distortion analysis.
 Economic evaluation of the added PV DG units.
Methodology:
This study will be carried out on – Jenin's power distribution network-West Bank – Palestine. Some
information about the network and it's component specifications (like cables, transformers, loads, ...
etc) will be used. Also some specialized simulation software such as MATLAB, ETAP, and GIS are used to
analyze and study the above mentioned effects.
After analyzing the targeted network, we will review relevant research work in order to layout and
design an appropriate PV generator to be connected with the busses of Jenin network. After that we will
use simulation models to investigate the effect s of connecting PV generator with the outlined grid.
Through simulation technique, the effects of this PV on P.F, power losses, voltage level, harmonics and
reactive power flow in the network will be investigated. We expect that our work will yield an
improvement of power quality and distribution reliability of Jenin network by connecting of PV
generators.
Part 1:
From the literature reviews we found that the more suitable methodology to have optimal location and
sizing of DG in the system is one of Artificial Intelligent techniques called “Particle Swarm Optimization
(PSO)” because it is fast and accurate to find the optimum location and sizing of the photovoltaic
distributed generators that we can add to the system was selected from one part of Jenin’s distribution
network.
No
Yes
No
Yes
Yes No
BEGIN
Set System Parameters
Run Power Flow at Base Case
Set x=1: N
(x=bus no. DG is added; N=total bus number)
X>N
Add DG to bus X, 𝑃 𝐷𝐺 from 0% to 15% in ratio 0.5% of total load power
𝑃 𝐷𝐺 = ∑ 𝑃𝑖−1
𝑖=𝑗
𝑖=0
+ 𝑃𝑖
(𝑃 𝐷𝐺: 𝑝𝑜𝑤𝑒𝑟 𝑜𝑓 𝑃𝑉 𝑎𝑑𝑑, 𝑃𝑖−1: 𝑝𝑟𝑒𝑣𝑖𝑜𝑢𝑠 𝑝𝑜𝑤𝑒𝑟 𝑜𝑓 𝑃𝑉, 𝑃𝑖: 0.5% 𝑜𝑓
𝑡𝑜𝑡𝑎𝑙 𝑙𝑜𝑎𝑑 𝑝𝑜𝑤𝑒𝑟, 𝑗: 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑖𝑛𝑐𝑟𝑒𝑚𝑒𝑛𝑡 = 0 𝑎𝑠 𝑖𝑛𝑖𝑡𝑖𝑎𝑙 𝑣𝑎𝑙𝑢𝑒)
Calculate the total power losses
Are the voltages in
acceptable range?
0.95 𝑝𝑢 ≤ 𝑉 ≤ 1.05 𝑝𝑢
Chose the optimum bus
number by using PSO
J>30
X=x+1
J=j+1
Part 2:
After finding the optimal location and sizing of DG that will add to the system, we will study the effects
of PV DG added on the system such as; the voltage drop, total power losses, power losses between the
branches, P.F, buses voltages and harmonics.
Part 3:
This part for economic evaluation of the added DG PV on the system, it will contains the capital
cost of PV and the other equipment need, the saving money after reduce the total power losses
and power generation, total annual saving, the saving money while 20 years (PV life cycle) and
the payback period.
Results and Analysis:
Part 1:
As the first results in our methodology to investigate what is the possibility of using PV
generators in order to improve the action of the system was selected from one part of Jenin’s power
distribution network that contains 25 bus in the same voltage level taking in consideration the
voltage levels, power losses, P.F and harmonics is make run of load flow in maximum and
minimum loads for the system.
End
The system that contains 25 bus at the same Voltage levels
Load Flow by using MATLAB (Newton Raphson Method):
Month Power Factor Q Generation (MVAR) P Generation (MW) P loss (MW) Q loss (MVAR)
Jan 0.909 0.859 1.878 0.0054 0.0038
Feb 0.909 0.859 1.878 0.0054 0.0038
Mar 0.909 0.859 1.878 0.0054 0.0038
Apr 0.96 3.075 10.076 0.136 0.096
May 0.96 3.075 10.076 0.136 0.096
Jun 0.96 3.075 10.076 0.136 0.096
Jul 0.96 3.075 10.076 0.136 0.096
Aug 0.96 3.075 10.076 0.136 0.096
Sep 0.96 3.075 10.076 0.136 0.096
Oct 0.909 0.859 1.878 0.0054 0.0038
Nov 0.909 0.859 1.878 0.0054 0.0038
Dec 0.909 0.859 1.878 0.0054 0.0038
The yearly load curve for the Main Feeder
From this yearly load curve we found that the Average Power=5.977 MW, Max. Power=10.076 MW and
Load Factor= 59.32%
As we mentioned before the total DG PV added must not exceed 15% of the total load in both situation
(min. and max. load) for the main feeder. We saw that the max. load for this feeder in (April., May., Jun.,
Jul., Aug. and Sep.) months and the min. load for this feeder in (Jan., Feb., Mar., Oct., Nov. and Dec.)
months.
Solar Energy Parameters for Jenin:
The monthly average solar radiation that recorded by Energy Research Center in 2012 in Jenin
city as the following table:
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
G(W/m2
) 208.3 263.6 362.8 464.2 552.6 598.7 585.6 528.8 449.6 335.1 242.1 191.4
T (°C) 11.3 12.7 16.7 23.1 27.9 31.3 34.0 34.2 31.5 25.7 18.7 13.2
Tilt Angle 47 45 35 29 20 15 18 25 32.5 44 55 58.5
Table 6.1 Average monthly solar radiation for Jenin City [7].
Monthly Average Solar Radiation at Jenin City:
0
2
4
6
8
10
12
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
PGeneration(MW)
Month
P Generation (MW)
Average monthly solar radiation for Jenin City
Peak Sun Shine Hour 5.4 H.
The solar radiation and the temperature are changed during the year in Jenin City. So that mean the
energy that generated from the PV array depends on these terms, so to have the maximum efficiency
we will use tracking solar system by MPPT algorithm device to change the tilt angle 12 times per year.
The maximum demand in these months (April., May., Jun., Jul., Aug. and Sep.) is 10.076 MW and the
maximum demand in these months (Jan., Feb., Mar., Oct., Nov. and Dec.) is 1.878 MW, so if we said that
the DG PV will be 15% of the total load, we can see that the PV power needed in (April., May., Jun., Jul.,
Aug. and Sep.) is 1.5 MW from PV and the PV power needed in (Jan., Feb., Mar., Oct., Nov. and Dec.) is
0.2817 MW from PV.
However, we use PV module from SUNTECH com. Called (SuperPoly STP300 – 24/Vd) at STP (1000
(w/m²), 25 (⁰C) ) to have maximum efficiency, but the average yearly solar radiation about 400 (W/m²)
so we will use 3 MW PV when we need 1.5 MW, and 800 KW PV when we need 218.7 KW by using the
previous equations, we have the following that describe the power that generate from the DG PV field
during the year and the suitable tilt angle needed to achieve the max. efficiency for this field :
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
G(W/m2
) 208.3 263.6 362.8 464.2 552.6 598.7 585.6 528.8 449.6 335.1 242.1 191.4
T (°C) 11.3 12.7 16.7 23.1 27.9 31.3 34.0 34.2 31.5 25.7 18.7 13.2
208.3
263.6
362.8
464.2
552.6
598.7 585.6
528.8
449.6
335.1
242.1
191.4
0
100
200
300
400
500
600
700
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
G(W/M²)
MONTH
Monthly Average Solar Radiation (W/m²)
Tilt Angle 47 45 35 29 20 15 18 25 32.5 44 55 58.5
P generation-
Max.(MW)
0.591 0.746 1.010 1.253 1.456 1.550 1.495 1.349 1.163 0.892 0.665 0.537
P generation-
Min. (MW)
0.158 0.199 0.269 0.334 0.388 0.413 0.399 0.360 0.310 0.238 0.177 0.143
PV Power
generation -
Used (MW)
0.158 0.199 0.269 1.253 1.456 1.550 1.495 1.349 1.163 0.238 0.177 0.143
The Real Power generated yearly from the Solar Field.
After we found the optimum sizing that will add to Ayash Feeder we will find the optimum location for
this DG PV field by using PSO algorithm. Firstly, we implement this size in the all buses in the feeder.
The PSO algorithm takes for each bus 6 values as an initial values for voltage profile, power factor, total
real power losses and total reactive power losses by using the following equations:
𝑉 𝑘+1
= 𝜔 ∗ 𝑉 𝑘
+ 𝐶1 ∗ 𝑟2 ∗ (𝑃𝑏𝑒𝑠𝑡 − 𝑆 𝑘
) + 𝐶2 ∗ 𝑟1 ∗ (𝐺 𝑏𝑒𝑠𝑡 − 𝑆 𝑘
)
𝑆 𝑘+1
= 𝑉 𝑘+1
+ 𝑆 𝑘
Where:
 𝜔 is the weighting function is usually used as follows:
𝜔 = 𝜔 𝑚𝑎𝑥 −
𝜔 𝑚𝑎𝑥 − 𝜔 𝑚𝑖𝑛
𝐼𝑡𝑟𝑒 𝑚𝑎𝑥
𝐼𝑡𝑟𝑒
𝜔 𝑚𝑎𝑥 𝑎𝑛𝑑 𝜔 𝑚𝑖𝑛 ∶ Are the maximum and minimum weights, respectively.
Appropriate values for 𝜔 𝑚𝑎𝑥 𝑎𝑛𝑑 𝜔 𝑚𝑖𝑛 are 0.4 and 0.9 [3].
The weights for each factor as the following:
Voltage profile: 50%
Power factor: 30%
Total real power losses: 10%
Total reactive power losses: 10%
The results as the following for maximum and minimum loads as the following:
Maximum load case:
# Bus Voltages P.F Total P loss Total Q loss
12 25 3 0.09417 0.066817
16 20 2 0.094383 0.066646
18 20 2 0.0944 0.066655
13 15 3 0.09431 0.066902
15 16 2 0.094709 0.06683
11 13 4 0.094734
PSO Bus selection in max. load.
As the above table shown the optimum location in max. load is bus #12.
Minimum load case:
# Bus Voltages P.F Total P loss Total Q loss
12 24 8 0.003887656 0.002744823
13 14 7 0.00388864 0.002745419
14 13 6 0.003911429 0.0027532
15 12 5 0.00391135 0.002751781
16 18 15 0.003910106 0.002745546
18 18 7 0.003908988 0.002744918
PSO Bus selection in min. load.
As the above table shown the optimum location in min. load is bus #12.
To sum up, we can notice that bus #12 is the optimum location in the both situation.
Part 2:
Discussion:
As we mentioned in the previous chapter that the optimum sizing was 1.5 MW in max. load and
218.7 KW in min. load and the optimum location was bus #12, the effects for this adding on the main
feeder as the following:
Month
Solar
Radiation
(W/m²)
Voltage
Profile
(P.U)
Total
Power
Factor
P
Generation
(MW)
P PV
(MW)
Q Generation
(MVAR)
Total P Loss
(MW)
Total Q
Loss(MW)
Jan 208.3 0.9965 0.895 1.72 0.158 0.859 0.005 0.003
Feb 263.6 0.9966 0.89 1.678 0.199 0.859 0.004 0.003
Mar 362.8 0.9968 0.882 1.608 0.269 0.858 0.004 0.003
Apr 464.2 0.9848 0.945 10.04 1.253 3.049 0.1001 0.071
May 552.6 0.9853 0.942 10.035 1.456 3.045 0.095 0.068
Jun 598.7 0.9856 0.941 10.033 1.55 3.044 0.093 0.066
Jul 585.6 0.9854 0.942 10.034 1.495 3.045 0.094 0.067
Aug 528.8 0.985 0.944 10.038 1.349 3.047 0.098 0.069
Table 8.1 The effects of add DG PV on bus 12
The power factor at the main feeder (Ayash Feeder) after add DG PV as the following fig. 8.1:
Fig 8.1 The power factor at the main feeder after add DG PV on bus 12
The total real power feed the all over main feeder (Ayash Feeder) after add DG PV as the following fig.
8.2:
0.895
0.89
0.882
0.945 0.942 0.941 0.942 0.944 0.946
0.886
0.893 0.896
0.84
0.86
0.88
0.9
0.92
0.94
0.96
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
P.F
MONTH
Ayash Feeder Power Factor
Sep 449.6 0.9845 0.946 10.042 1.163 3.05 0.102 0.073
Oct 335.1 0.9967 0.886 1.639 0.238 0.858 0.004 0.003
Nov 242.1 0.9966 0.893 1.7 0.177 0.859 0.004 0.003
Dec 191.4 0.9965 0.896 1.734 0.143 0.859 0.005 0.003
Fig 8.2 The total real power feed the all over main feeder after add DG PV on bus 12
Average Power=6.6459 MW, Max. Power=10.042 MW, Load Factor=66.18 %
The total Reactive power feed the all over main feeder (Ayash Feeder) after add DG PV as the following
fig. 8.3:
Fig 8.3 The total reactive power feed the all over main feeder after add DG PV on bus 12
The total real power and reactive power loss for the all over main feeder (Ayash Feeder) after add DG PV
as the following fig. 8.4:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
P PV (MW) 0.158 0.199 0.269 1.253 1.456 1.55 1.495 1.349 1.163 0.238 0.177 0.143
P Generation (MW) 1.72 1.678 1.608 10.04 10.035 10.033 10.034 10.038 10.042 1.639 1.7 1.734
0
2
4
6
8
10
12
14
PGeneration(MW)
Total Real Power Generation (MW)
P Generation (MW) P PV (MW)
0.859 0.859 0.858
3.049 3.045 3.044 3.045 3.047 3.05
0.858 0.859 0.859
0
0.5
1
1.5
2
2.5
3
3.5
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
QGENERATION(MVAR)
MONTH
Total Reacive Power Generation (MVAR)
Fig 8.4 The total real power and reactive power loss for all over main feeder after add DG PV on bus 12
We can notice from the previous results that:
 The power factor at the main feeder sharp decrease
 The voltage profile at the main feeder gradual increase
 The reactive power generation constant
 The real power came from connection point steady decrease
 The total real and reactive power losses within the system decrease
 The load factor increase to become 66.18% from 59.32%
But, the effects on bus #12 as the following figures, we can noticed that the power factor
become unity and steady at 1, on the other hand the voltage profile sharp increased during the
year:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Total P Loss (MW) 0.005 0.004 0.004 0.1001 0.095 0.093 0.094 0.098 0.102 0.004 0.004 0.005
Total Q Loss(MW) 0.003 0.003 0.003 0.071 0.068 0.066 0.067 0.069 0.073 0.003 0.003 0.003
0
0.02
0.04
0.06
0.08
0.1
0.12
Total Losses
Total P Loss (MW) Total Q Loss(MW)
The voltage profile for bus #12 after add DG PV as the following fig. 8.5:
Fig 8.5 The voltage profile for bus #12 after add DG PV
The power factor at bus #12 after add DG PV as the following fig. 8.6:
Fig 8.6 The power factor at bus #12 after add DG PV
Although, we studied the effects that appear in the all buses when we add DG PV on bus #12,
the effects was the following figures and tables:
0.99650.99660.9968
0.98480.98530.98560.9854 0.985 0.9845
0.99670.99660.9965
0.978
0.98
0.982
0.984
0.986
0.988
0.99
0.992
0.994
0.996
0.998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
V(P.U)
MONTH
Voltage Profile (P.U)
1 1 1 1 1 1 1 1 1 1 1 1
0
0.2
0.4
0.6
0.8
1
1.2
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
P.F
MONTH
Power Factor bus #12
The following table 8. 2 shows the power factor in each bus before and after added DG PV:
# Bus PF Original PF After PV
1 0.909 0.885867
2 0.8917 0.408423
3 0.911 0.654792
4 0.853 0.7676
5 0.934 0.7532
6 0.889 0.64617
7 0.93 0.7979
8 0.912 0.80946
9 0.767 0.643
10 0.707106 0.589
11 0.952 0.6696
12 0.891 1
13 0.879 0.699784
14 0.878 0.607558
15 0.926 0.7217
16 0.855 0.74
17 0.879 0.621
18 0.891 0.6313
19 0.899 0.75
20 0.939 0.617
21 0.903 0.76238
22 0.857 0.6685
23 0.953 0.7402
24 0.908 0.646
25 0.866 0.6159
Table 8.2 The power factor in each bus before and after added DG PV
The affects for added DG PV on bus #12 on the power factor for each bus as the following:
Fig 8.7 The affects for added DG PV on bus #12 on the power factor for each bus
The following table shows the Voltage profile in each bus before and after added DG PV:
# Bus V original V after PV
1 1 1
2 0.98889624 0.989987
3 0.98886 0.989765
4 0.98575 0.9872
5 0.98597 0.9875
6 0.985 0.98703
7 0.9848 0.986571
8 0.9835532 0.98567
9 0.9827 0.985091
10 0.9819987 0.98459
11 0.981849 0.984533
12 0.98122843 0.984512
13 0.98099 0.984278
14 0.98093 0.984217
15 0.98177123 0.984363
16 0.98127757 0.98387
17 0.98117745 0.98377
18 0.9811353 0.983728
19 0.98093 0.983524
20 0.9887876 0.9899
21 0.9885 0.98964
22 0.988 0.98957
23 0.9883 0.989393
0
0.2
0.4
0.6
0.8
1
1.2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
PowerFactor
Buses
Power Factor For Each Bus
PF Original PF After PV
24 0.9821263 0.989304
25 0.98820786 0.989299665
Table 8.3 The Voltage profile in each bus before and after added DG PV
The affects for added DG PV on bus #12 on the voltage profile for each bus as the following:
Fig 8.8 The affects for added DG PV on bus #12 on the voltage profile for each bus
The following table shows the total harmonic distortion (THD) in each bus before and after added DG PV
to bus #12:
0.97
0.975
0.98
0.985
0.99
0.995
1
1.005
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
V(P.U)
Bus Number
Voltage Profile For Each Bus
V original V after PV
Bus
Num.
Voltage harmonic
Before (%)
Voltage harmonic
After (%)
Current harmonic
Before (%)
Current harmonic
After (%)
1 5.42 2.6 11.94 6.32
2 5.32 2.45 11.67 6.8
3 6.85 4.2 8.66 4.6
4 5.26 3.2 11.65 6.3
5 6.35 3.85 7.43 3.5
6 6.22 3.8 10.68 5.02
7 6.96 4.3 7.35 3.4
8 5.62 2.55 10.67 5.01
9 5.36 2.35 9.85 4.8
10 5.68 2.45 10.67 5.1
11 6.52 1.98 7.45 3.6
12 6.35 2.7 7.41 3.8
13 5.59 2.89 10.68 4.89
14 4.99 2.12 11.94 4.52
Table 8.4 The total harmonic distortion (THD) in each bus before and after added DG PV to bus #12
The Voltage Harmonic emission in the network after add DG PV to the bus #12 and how it effects on the
THD as the following:
Fig. 8.9 The Voltage Harmonic emission in the network after add DG PV to the bus #12
The Current Harmonic emission in the network after add DG PV to the bus #12 and how it effects on the
THD as the following:
0
1
2
3
4
5
6
7
8
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
VTHD(%)
Bus Number
Voltage Harmonic
Voltage harmonic Before (%) Voltage harmonic After (%)
15 5.26 3.2 9.54 4.98
16 6.53 2 8.56 4.6
17 5.33 2.3 9.53 4.88
18 6.43 2.82 7.42 3.89
19 6.42 2.86 8.52 4.99
20 5.95 2.15 9.53 4.62
21 5.69 2.23 10.69 5.08
22 5.2 3.1 11.68 6.2
23 5.36 3.21 10.66 5.6
24 4.98 2.5 9.53 4.9
25 5.96 2.3 10.68 5.6
Fig. 8.10 The Current Harmonic emission in the network after add DG PV to the bus #12
We can notice from the previous results:
 The power factor at each bus sharp decrease
 The Voltage profile increase
 The total losses decrease
 The THD decrease for voltage and current signal
Part 3:
the one line diagram for An-Najah solar field that will feed Ayash feeder:
0
2
4
6
8
10
12
14
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
ITHD(%)
Bus Number
Current Harmonic
Current harmonic Before (%) Current harmonic After (%)
Fig. 7.3 An-Najah Solar Field.
Non Labor:
DC Components V line (KV)
Nominal
Current (A)
Breaking
Capacity (A) Unit Price ($)/unit Price ($)
Fuse 0.4 30 300 150 111 16650
Switch 0.4 30 - 150 64 9600
Contactor 0.4 3000 - 1 1400 1400
DC Wire, 10 mm² 0.4 30 - 5000 4 20000
Total 47650
AC Components V line (KV)
Nominal
Current (KA)
Breaking
Capacity (KA) Unit Price ($)/Unit Price ($)
Fuse 0.4 5 35 1 14395 14395
Table 7.15 DC Components, properties, units and price [12]
Table 7.16 AC Components, properties, units and price [12]
Table 7.17 other Components, properties, units and price [8,11,12,13]
Assets Area $/Year Year Price ($)
Site 20 Dunam 75000 20 1500000
Table 7.18 Assets, properties, duration and price
DC Components 47650 $
AC Components 229605 $
Other Components 2788852 $
Site 1500000 $
Switch 0.4 5 - 1 7500 7500
C.B, SF6 0.4 5 35 1 18710 18710
C.B, SF6 33 0.05 3 1 29000 29000
Fuse 33 0.05 3 2 23000 46000
Switch 33 0.05 - 2 24500 49000
C.B, SF6 33 0.05 6 2 30000 60000
Bas Bur 33 0.1 - 1 5000 5000
Total 229605
Other Components Properties Unit Price ($)/Unit Price ($)
PV Module_SUNTECH 300W/24Vd 10013 250 2503250
Transformer_Schneider 0.4/33 KV , 3MVA 1 30000 30000
DC/DC Converter_ SMA (300-400)V =400 V, 20000 W 150 500 75000
DC/AC Inverter _SMA 400 V = 400 V,50 Hz, 20000 W 150 1000 150000
Capacitor Banks_ABB 20KVAR, 400V 2 185 370
Capacitor Banks_ABB 25KVAR, 400V 9 200 1800
Capacitor Banks_ABB 30KVAR, 400V 13 264 3432
MPPT_SMA 150 100 15000
Motor 3 ph, 400 V, 10 Khp 1 10000 10000
Rotary UPS 400 V, 9 KAH 1 65000 65000
Total 2853852
Total ($) 4541107 $
Table 7.19 Total Non-labor resource Cost.
Labor:
Person Num. $/Hour Hours/ 18 Months Price ($)
Engineers 7 45 4320 194400
Technicians 20 23 4320 99360
Others 10 15 5000 75000
Total ($) 368760 $
Table 7.20 Total labor resource Cost.
Labor 368760 ($)
Non Labor 4631107 ($)
Currency Diffusion 133 ($)
Total Budget ($) 5000000 ($)
Table 7.21 Total Capital Cost.
The annual saving for Ayash Feeder:
Original:
The annual max demand:
Pmax= 10.076 MW
Since the load factor (L.F) = 59.32 %
𝑃𝑎𝑣𝑔 = 𝐿. 𝐹 ∗ 𝑃𝑚𝑎𝑥
𝑃𝑎𝑣𝑔 = 0.5932 ∗ 10.076 ∗ 103
= 5977 𝐾𝑊
𝐸𝑛𝑒𝑟𝑔𝑦 (𝐸) = 𝑃𝑎𝑣𝑔 ∗ 8760 = 52359249 𝐾𝑊𝐻 𝑦𝑒𝑎𝑟𝑙𝑦
The cost per KWH is 0.62 NIS/KWH:
𝑇𝑜𝑡𝑎𝑙 𝑏𝑖𝑙𝑙 = 𝐸 ∗ 0.62 𝑁𝐼𝑆 𝐾𝑊𝐻⁄ = 32462734 𝑁𝐼𝑆 𝑝𝑒𝑟 𝑦𝑒𝑎𝑟
Since the power factor during the minimum load period less than 0.92 so the company is paying a
penalty as explained below:
𝐸𝑛𝑒𝑟𝑔𝑦/𝑚𝑜𝑛𝑡ℎ = 𝑃𝑎𝑣𝑔 ∗ 8760/12 = 4363271 𝐾𝑊𝐻 𝑚𝑜𝑛𝑡ℎ𝑙𝑦
𝑐𝑜𝑠𝑡 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ = 2705228 𝑁𝐼𝑆 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ
During the six month of minimum load the power factor =0.909
In Palestine the penalty for 0.8 ≤ 𝑝. 𝑓 ≤ 0.92 is 1% at total bill for each 0.1 under 0.92
0.92-0.909=0.011
𝑃𝑒𝑛𝑎𝑙𝑡𝑦 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ = 0.011 ∗ 𝑇𝑜𝑡𝑎𝑙 𝑚𝑜𝑛𝑡ℎ𝑙𝑦 𝐵𝑖𝑙𝑙
𝑃𝑒𝑛𝑎𝑙𝑡𝑦 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ = 0.011 ∗ 2705228
= 29758 𝑁𝐼𝑆 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ
For the six months:
𝑇𝑜𝑡𝑎𝑙 𝑃𝑒𝑛𝑎𝑙𝑡𝑦 = 6 ∗ 29758 = 178548 𝑁𝐼𝑆
The total cost:
𝑇𝑜𝑡𝑎𝑙 𝑎𝑛𝑛𝑢𝑎𝑙 𝑐𝑜𝑠𝑡 = 𝐸𝑛𝑒𝑟𝑔𝑦 𝑐𝑜𝑠𝑡 + 𝑡𝑜𝑡𝑎𝑙 𝑝𝑒𝑛𝑎𝑙𝑡𝑦
= 32462734 + 178548
= 32641282 𝑁𝐼𝑆
= 𝟗𝟒𝟎𝟔𝟕𝟏𝟎 $ .
After using DG PV:
The annual max demand:
Pmax= 8.879 MW
Since the load factor (L.F) = 66.18 %
𝑃𝑎𝑣𝑔 = 𝐿. 𝐹 ∗ 𝑃𝑚𝑎𝑥
𝑃𝑎𝑣𝑔 = 0.6618 ∗ 8.879 ∗ 103
= 5070.92 𝐾𝑊
𝑃𝑎𝑣𝑔 = 5070.92 𝐾𝑊
𝐸𝑛𝑒𝑟𝑔𝑦 (𝐸) = 𝑃𝑎𝑣𝑔 ∗ 8760 = 44421259 𝐾𝑊𝐻 𝑦𝑒𝑎𝑟𝑙𝑦
The cost per KWH is 0.62 NIS/KWH
𝑇𝑜𝑡𝑎𝑙 𝑏𝑖𝑙𝑙 = 𝐸 ∗ 0.62 𝑁𝐼𝑆 𝐾𝑊𝐻⁄ = 27541181 𝑁𝐼𝑆 𝑝𝑒𝑟 𝑦𝑒𝑎𝑟
Before using PV After using PV
Total annual cost 32641282 NIS 27541181 NIS
Cost in $ (1$=3.47 NIS) 9406710 $ 7936940 $
Table 7.22 Total annual Cost before and after add DG PV.
𝑇ℎ𝑒 𝑦𝑒𝑎𝑟𝑙𝑦 𝑠𝑎𝑣𝑖𝑛𝑔 = 9406710 − 7936940
= 𝟏𝟒𝟔𝟗𝟕𝟕𝟎 $
The Payback Period:
𝑃. 𝐵. 𝑃 =
𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡
𝑆𝑎𝑣𝑖𝑛𝑔
𝑃. 𝐵. 𝑃 =
5000000 $
1469770 $
𝑃. 𝐵. 𝑃 = 3.5 𝑌𝑒𝑎𝑟
By the way the life cycle of the equipment in the solar field is about 20 Year and the payback
period is 3.5 Year, so the total saving after 3.5 years of implemented this project will be
𝑆𝑎𝑣𝑖𝑛𝑔 𝑎𝑓𝑡𝑒𝑟 3.5 𝑌𝑒𝑎𝑟 = (20 − 3.5) ∗ 𝑌𝑒𝑎𝑟𝑙𝑦 𝑆𝑎𝑣𝑖𝑛𝑔
𝑆𝑎𝑣𝑖𝑛𝑔 𝑎𝑓𝑡𝑒𝑟 3.5 𝑌𝑒𝑎𝑟 = 16.5 ∗ 1469770
𝑆𝑎𝑣𝑖𝑛𝑔 𝑎𝑓𝑡𝑒𝑟 3.5 𝑌𝑒𝑎𝑟 = 𝟐𝟒𝟐𝟓𝟏𝟐𝟎𝟓 $
To sum up, one can show that the project is feasible to implement.
Conclusions and Recommendation:
In general, we can conclude that this project will be a strong solution for this problem due to
the improvement that happened after add DG PV on this feeder in Jenin City, especially in bus
#12.
To sum up, the all effects on the system after add DG PV as the following:
 The voltage profile increase within the range (1.05≤ V ≤ 0.95) that can increase the
efficiency of the supply from one hand, so the current in the system will decrease that
mean the total losses will decrease, so the total bill will decrease, from the other hand
we can use the same feeder to add new load within range that did not let the voltage be
less than 0.95 P.U, so we can make a long term control without need new transformers.
 The total harmonic distortion in the system will decrease it can be seen that only the
12th, 15th, 18th, 21st and 24th harmonics exceeded the threshold limits. However, total
voltage harmonics distortion for all of the studied cases is within the Australian
regulatory standard limit as stated in AS 4777 [10], total Harmonic Distortion gives us
the information about the harmonic content in a signal w.r.t. fundamental component,
so that mean increase the power quality for the supply.
 The total real and reactive power losses decrease sharply, due to increase the voltage
profile and decrease the currents in the system in the same time.
 The total saving in the total bill will be about 24 Million $.
 The only bad effect for this solution was decrease the power factor in the system, so
that mean the penalty will be huge, so we recommend to use capacitor banks to
increase the power factor to be equal or more than 92%.
The recommendation to improve power factor is to use capacitor banks as the following:
# Bus PF Original PF After PV Capacitor Bank (KVAR)
1 0.909 0.885867 20
2 0.8917 0.408423 30
3 0.911 0.654792 30
4 0.853 0.7676 25
5 0.934 0.7532 30
6 0.889 0.64617 25
7 0.93 0.7979 25
8 0.912 0.80946 20
9 0.767 0.643 30
10 0.707106 0.589 30
11 0.952 0.6696 25
12 0.891 1 0
13 0.879 0.699784 25
14 0.878 0.607558 30
15 0.926 0.7217 25
16 0.855 0.74 25
17 0.879 0.621 30
18 0.891 0.6313 30
19 0.899 0.75 25
20 0.939 0.617 30
21 0.903 0.76238 25
22 0.857 0.6685 30
23 0.953 0.7402 25
24 0.908 0.646 30
25 0.866 0.6159 30
Table 9.1 Improve power factor and the value of capacitor banks
By using the above values of capacitor banks that will increase the power factor to be at least
92%, on the other hand will increase the voltage at the bus but within the voltage rang.
Constraints:
As any problem in our life we will find the suitable solution for it in many terms to solve it from one side
and to have the stability for this solution during a long term period, so in this case we will use SMART
method to solve it.
SMART method means that the solution will be specific, measurable, achievable, realistic and have time
frame to have long term solution for any problem.
So to satisfy this method we faced many constraints and the constraints in our project can be divided
into four parts:
1. Leakage in Data base from the supplier.
2. Unrealistic solution for this problem.
3. No Palestinian Standers to assist our work
4. Suitable software that can help us.
We find the suitable solution for this constraints as the following:
1. Leakage in Data base from the supplier:
The leakage in data base was in the some loads data, cables used, records for some factors and the
vision for solving this problem.
The solution was that we took the records for some these loads by ourselves under the supervision of
supplier and we calculated the parameters for the cables used in the system.
2. Unrealistic solution for this problem:
The solution for the problem from the supplier is unrealistic that the solution was to increase the
connection points that to feed the increasing in demand for this system.
3. No Palestinian Standers to assist our work:
There is no standers for this work from Palestinian government to assist our solution, so we used the
Australian standers.
4. Suitable software that can help us:
Due to the huge budget needed for this solution, we can’t implement samples as a test sample in the
ground, so the software can help us to find the suitable solution, so to solve this problem we built
MATLAB codes to simulate the reality for this solution.

More Related Content

What's hot

Publications_Photovoltaics_Tianhao_Li
Publications_Photovoltaics_Tianhao_LiPublications_Photovoltaics_Tianhao_Li
Publications_Photovoltaics_Tianhao_Li
Tianhao Li
 
134 logeswaran
134 logeswaran134 logeswaran
A hybrid maximum power point tracking for partially shaded photovoltaic syste...
A hybrid maximum power point tracking for partially shaded photovoltaic syste...A hybrid maximum power point tracking for partially shaded photovoltaic syste...
A hybrid maximum power point tracking for partially shaded photovoltaic syste...
nizhonglian
 
Simulation and analysis of perturb and observe mppt algorithm for array using...
Simulation and analysis of perturb and observe mppt algorithm for array using...Simulation and analysis of perturb and observe mppt algorithm for array using...
Simulation and analysis of perturb and observe mppt algorithm for array using...
Asoka Technologies
 
Matlab based comparative studies on selected mppt
Matlab based comparative studies on selected mpptMatlab based comparative studies on selected mppt
Matlab based comparative studies on selected mppt
eSAT Publishing House
 
MPPT-Based Control Algorithm for PV System Using iteration-PSO under Irregula...
MPPT-Based Control Algorithm for PV System Using iteration-PSO under Irregula...MPPT-Based Control Algorithm for PV System Using iteration-PSO under Irregula...
MPPT-Based Control Algorithm for PV System Using iteration-PSO under Irregula...
AZOJETE UNIMAID
 
Simplified PV Module Simulator With MPPT
Simplified PV Module Simulator With MPPTSimplified PV Module Simulator With MPPT
Simplified PV Module Simulator With MPPT
IJMTST Journal
 
IJER_2013_308
IJER_2013_308IJER_2013_308
IJER_2013_308
Shobana Gunasekaran
 
Energy Harvesting Using Adaptive Duty-Cycling Algorithm - Wireless Sensor Net...
Energy Harvesting Using Adaptive Duty-Cycling Algorithm - Wireless Sensor Net...Energy Harvesting Using Adaptive Duty-Cycling Algorithm - Wireless Sensor Net...
Energy Harvesting Using Adaptive Duty-Cycling Algorithm - Wireless Sensor Net...
IJERDJOURNAL
 
Site Acceptance Test for Solar PV System of Bronzeville Community Microgrid
Site Acceptance Test for Solar PV System of Bronzeville Community MicrogridSite Acceptance Test for Solar PV System of Bronzeville Community Microgrid
Site Acceptance Test for Solar PV System of Bronzeville Community Microgrid
Power System Operation
 
Incremental Conductance MPPT Algorithm for PV System Implemented Using DC-DC ...
Incremental Conductance MPPT Algorithm for PV System Implemented Using DC-DC ...Incremental Conductance MPPT Algorithm for PV System Implemented Using DC-DC ...
Incremental Conductance MPPT Algorithm for PV System Implemented Using DC-DC ...
IJERA Editor
 
Maximum Power Point Tracking Method for Single Phase Grid Connected PV System...
Maximum Power Point Tracking Method for Single Phase Grid Connected PV System...Maximum Power Point Tracking Method for Single Phase Grid Connected PV System...
Maximum Power Point Tracking Method for Single Phase Grid Connected PV System...
Ali Mahmood
 
H41015660
H41015660H41015660
H41015660
IJERA Editor
 
Maximum Power Point Tracking of PV Arrays using Different Techniques
Maximum Power Point Tracking of PV Arrays using Different TechniquesMaximum Power Point Tracking of PV Arrays using Different Techniques
Maximum Power Point Tracking of PV Arrays using Different Techniques
IJERA Editor
 
Mppt of solar enrgy
Mppt of solar enrgyMppt of solar enrgy
Mppt of solar enrgy
hassan ali
 
MLPE performance modeling
MLPE performance modelingMLPE performance modeling
MLPE performance modeling
chaudharichetan
 
A MATLAB /Simulink Modal of Triple-Junction Solar Cell and MPPT Based on Incr...
A MATLAB /Simulink Modal of Triple-Junction Solar Cell and MPPT Based on Incr...A MATLAB /Simulink Modal of Triple-Junction Solar Cell and MPPT Based on Incr...
A MATLAB /Simulink Modal of Triple-Junction Solar Cell and MPPT Based on Incr...
IJERA Editor
 
Improving efficiency of Photovoltaic System with Neural Network Based MPPT Co...
Improving efficiency of Photovoltaic System with Neural Network Based MPPT Co...Improving efficiency of Photovoltaic System with Neural Network Based MPPT Co...
Improving efficiency of Photovoltaic System with Neural Network Based MPPT Co...
IJMER
 
Dual Mode Control of Grid Connected Photovoltaic System
Dual Mode Control of Grid Connected Photovoltaic SystemDual Mode Control of Grid Connected Photovoltaic System
Dual Mode Control of Grid Connected Photovoltaic System
Ravindra Kuhada
 
A Case Study of Economic Load Dispatch for a Thermal Power Plant using Partic...
A Case Study of Economic Load Dispatch for a Thermal Power Plant using Partic...A Case Study of Economic Load Dispatch for a Thermal Power Plant using Partic...
A Case Study of Economic Load Dispatch for a Thermal Power Plant using Partic...
International Journal of Science and Research (IJSR)
 

What's hot (20)

Publications_Photovoltaics_Tianhao_Li
Publications_Photovoltaics_Tianhao_LiPublications_Photovoltaics_Tianhao_Li
Publications_Photovoltaics_Tianhao_Li
 
134 logeswaran
134 logeswaran134 logeswaran
134 logeswaran
 
A hybrid maximum power point tracking for partially shaded photovoltaic syste...
A hybrid maximum power point tracking for partially shaded photovoltaic syste...A hybrid maximum power point tracking for partially shaded photovoltaic syste...
A hybrid maximum power point tracking for partially shaded photovoltaic syste...
 
Simulation and analysis of perturb and observe mppt algorithm for array using...
Simulation and analysis of perturb and observe mppt algorithm for array using...Simulation and analysis of perturb and observe mppt algorithm for array using...
Simulation and analysis of perturb and observe mppt algorithm for array using...
 
Matlab based comparative studies on selected mppt
Matlab based comparative studies on selected mpptMatlab based comparative studies on selected mppt
Matlab based comparative studies on selected mppt
 
MPPT-Based Control Algorithm for PV System Using iteration-PSO under Irregula...
MPPT-Based Control Algorithm for PV System Using iteration-PSO under Irregula...MPPT-Based Control Algorithm for PV System Using iteration-PSO under Irregula...
MPPT-Based Control Algorithm for PV System Using iteration-PSO under Irregula...
 
Simplified PV Module Simulator With MPPT
Simplified PV Module Simulator With MPPTSimplified PV Module Simulator With MPPT
Simplified PV Module Simulator With MPPT
 
IJER_2013_308
IJER_2013_308IJER_2013_308
IJER_2013_308
 
Energy Harvesting Using Adaptive Duty-Cycling Algorithm - Wireless Sensor Net...
Energy Harvesting Using Adaptive Duty-Cycling Algorithm - Wireless Sensor Net...Energy Harvesting Using Adaptive Duty-Cycling Algorithm - Wireless Sensor Net...
Energy Harvesting Using Adaptive Duty-Cycling Algorithm - Wireless Sensor Net...
 
Site Acceptance Test for Solar PV System of Bronzeville Community Microgrid
Site Acceptance Test for Solar PV System of Bronzeville Community MicrogridSite Acceptance Test for Solar PV System of Bronzeville Community Microgrid
Site Acceptance Test for Solar PV System of Bronzeville Community Microgrid
 
Incremental Conductance MPPT Algorithm for PV System Implemented Using DC-DC ...
Incremental Conductance MPPT Algorithm for PV System Implemented Using DC-DC ...Incremental Conductance MPPT Algorithm for PV System Implemented Using DC-DC ...
Incremental Conductance MPPT Algorithm for PV System Implemented Using DC-DC ...
 
Maximum Power Point Tracking Method for Single Phase Grid Connected PV System...
Maximum Power Point Tracking Method for Single Phase Grid Connected PV System...Maximum Power Point Tracking Method for Single Phase Grid Connected PV System...
Maximum Power Point Tracking Method for Single Phase Grid Connected PV System...
 
H41015660
H41015660H41015660
H41015660
 
Maximum Power Point Tracking of PV Arrays using Different Techniques
Maximum Power Point Tracking of PV Arrays using Different TechniquesMaximum Power Point Tracking of PV Arrays using Different Techniques
Maximum Power Point Tracking of PV Arrays using Different Techniques
 
Mppt of solar enrgy
Mppt of solar enrgyMppt of solar enrgy
Mppt of solar enrgy
 
MLPE performance modeling
MLPE performance modelingMLPE performance modeling
MLPE performance modeling
 
A MATLAB /Simulink Modal of Triple-Junction Solar Cell and MPPT Based on Incr...
A MATLAB /Simulink Modal of Triple-Junction Solar Cell and MPPT Based on Incr...A MATLAB /Simulink Modal of Triple-Junction Solar Cell and MPPT Based on Incr...
A MATLAB /Simulink Modal of Triple-Junction Solar Cell and MPPT Based on Incr...
 
Improving efficiency of Photovoltaic System with Neural Network Based MPPT Co...
Improving efficiency of Photovoltaic System with Neural Network Based MPPT Co...Improving efficiency of Photovoltaic System with Neural Network Based MPPT Co...
Improving efficiency of Photovoltaic System with Neural Network Based MPPT Co...
 
Dual Mode Control of Grid Connected Photovoltaic System
Dual Mode Control of Grid Connected Photovoltaic SystemDual Mode Control of Grid Connected Photovoltaic System
Dual Mode Control of Grid Connected Photovoltaic System
 
A Case Study of Economic Load Dispatch for a Thermal Power Plant using Partic...
A Case Study of Economic Load Dispatch for a Thermal Power Plant using Partic...A Case Study of Economic Load Dispatch for a Thermal Power Plant using Partic...
A Case Study of Economic Load Dispatch for a Thermal Power Plant using Partic...
 

Similar to Investigation effects-of-supplying-power-distrubition

Harmonic assessment on two photovoltaic inverter modes and mathematical model...
Harmonic assessment on two photovoltaic inverter modes and mathematical model...Harmonic assessment on two photovoltaic inverter modes and mathematical model...
Harmonic assessment on two photovoltaic inverter modes and mathematical model...
IJECEIAES
 
40220130406008
4022013040600840220130406008
40220130406008
IAEME Publication
 
France 2
France 2France 2
Modeling and Simulation of Fuzzy Logic based Maximum Power Point Tracking (MP...
Modeling and Simulation of Fuzzy Logic based Maximum Power Point Tracking (MP...Modeling and Simulation of Fuzzy Logic based Maximum Power Point Tracking (MP...
Modeling and Simulation of Fuzzy Logic based Maximum Power Point Tracking (MP...
IJECEIAES
 
A0411030109
A0411030109A0411030109
A0411030109
IJERA Editor
 
Modeling and Simulation of Solar Photovoltaic System
Modeling and Simulation of Solar Photovoltaic SystemModeling and Simulation of Solar Photovoltaic System
Modeling and Simulation of Solar Photovoltaic System
ijtsrd
 
control-of-dcdc-converters-for-solar-energy-system-with-maximum-.pdf
control-of-dcdc-converters-for-solar-energy-system-with-maximum-.pdfcontrol-of-dcdc-converters-for-solar-energy-system-with-maximum-.pdf
control-of-dcdc-converters-for-solar-energy-system-with-maximum-.pdf
Dsriniva
 
A Simple Control Strategy for Boost Converter Based Wind and Solar Hybrid Ene...
A Simple Control Strategy for Boost Converter Based Wind and Solar Hybrid Ene...A Simple Control Strategy for Boost Converter Based Wind and Solar Hybrid Ene...
A Simple Control Strategy for Boost Converter Based Wind and Solar Hybrid Ene...
IJRES Journal
 
IRJET- Simulation and Analysis of Photovoltaic Solar System for Different Wea...
IRJET- Simulation and Analysis of Photovoltaic Solar System for Different Wea...IRJET- Simulation and Analysis of Photovoltaic Solar System for Different Wea...
IRJET- Simulation and Analysis of Photovoltaic Solar System for Different Wea...
IRJET Journal
 
Drive Applications of Fuzzy Logic Controlled Interleaved Boost Converter for ...
Drive Applications of Fuzzy Logic Controlled Interleaved Boost Converter for ...Drive Applications of Fuzzy Logic Controlled Interleaved Boost Converter for ...
Drive Applications of Fuzzy Logic Controlled Interleaved Boost Converter for ...
EECJOURNAL
 
Power losses reduction of power transmission network using optimal location o...
Power losses reduction of power transmission network using optimal location o...Power losses reduction of power transmission network using optimal location o...
Power losses reduction of power transmission network using optimal location o...
IJECEIAES
 
Attou. photovoltaic grid Boost Converter
Attou. photovoltaic grid Boost ConverterAttou. photovoltaic grid Boost Converter
Attou. photovoltaic grid Boost Converter
Attou
 
MAXIMUM POWER POINT TRACKING WITH ARTIFICIAL NEURAL NET WORK
MAXIMUM POWER POINT TRACKING WITH ARTIFICIAL NEURAL NET WORKMAXIMUM POWER POINT TRACKING WITH ARTIFICIAL NEURAL NET WORK
MAXIMUM POWER POINT TRACKING WITH ARTIFICIAL NEURAL NET WORK
IAEME Publication
 
Design and Implementation of Maximum Power Point Tracking in Photovoltaic Sys...
Design and Implementation of Maximum Power Point Tracking in Photovoltaic Sys...Design and Implementation of Maximum Power Point Tracking in Photovoltaic Sys...
Design and Implementation of Maximum Power Point Tracking in Photovoltaic Sys...
inventionjournals
 
Mini_Project
Mini_ProjectMini_Project
Mini_Project
Pratheek Rajan
 
Optimal Power Flow with Reactive Power Compensation for Cost And Loss Minimiz...
Optimal Power Flow with Reactive Power Compensation for Cost And Loss Minimiz...Optimal Power Flow with Reactive Power Compensation for Cost And Loss Minimiz...
Optimal Power Flow with Reactive Power Compensation for Cost And Loss Minimiz...
ijeei-iaes
 
THREE PHASE GRID CONNECTED SOLAR PV SYSTEM
THREE PHASE GRID CONNECTED SOLAR PV SYSTEMTHREE PHASE GRID CONNECTED SOLAR PV SYSTEM
THREE PHASE GRID CONNECTED SOLAR PV SYSTEM
Er. Satyendra Vishwakarma
 
PV array connected to the grid with the implementation of MPPT algorithms (IN...
PV array connected to the grid with the implementation of MPPT algorithms (IN...PV array connected to the grid with the implementation of MPPT algorithms (IN...
PV array connected to the grid with the implementation of MPPT algorithms (IN...
International Journal of Power Electronics and Drive Systems
 
A Novel Approach on Photovoltaic Technologies for Power Injection in Grid Usi...
A Novel Approach on Photovoltaic Technologies for Power Injection in Grid Usi...A Novel Approach on Photovoltaic Technologies for Power Injection in Grid Usi...
A Novel Approach on Photovoltaic Technologies for Power Injection in Grid Usi...
IJERA Editor
 
40620130101002
4062013010100240620130101002
40620130101002
IAEME Publication
 

Similar to Investigation effects-of-supplying-power-distrubition (20)

Harmonic assessment on two photovoltaic inverter modes and mathematical model...
Harmonic assessment on two photovoltaic inverter modes and mathematical model...Harmonic assessment on two photovoltaic inverter modes and mathematical model...
Harmonic assessment on two photovoltaic inverter modes and mathematical model...
 
40220130406008
4022013040600840220130406008
40220130406008
 
France 2
France 2France 2
France 2
 
Modeling and Simulation of Fuzzy Logic based Maximum Power Point Tracking (MP...
Modeling and Simulation of Fuzzy Logic based Maximum Power Point Tracking (MP...Modeling and Simulation of Fuzzy Logic based Maximum Power Point Tracking (MP...
Modeling and Simulation of Fuzzy Logic based Maximum Power Point Tracking (MP...
 
A0411030109
A0411030109A0411030109
A0411030109
 
Modeling and Simulation of Solar Photovoltaic System
Modeling and Simulation of Solar Photovoltaic SystemModeling and Simulation of Solar Photovoltaic System
Modeling and Simulation of Solar Photovoltaic System
 
control-of-dcdc-converters-for-solar-energy-system-with-maximum-.pdf
control-of-dcdc-converters-for-solar-energy-system-with-maximum-.pdfcontrol-of-dcdc-converters-for-solar-energy-system-with-maximum-.pdf
control-of-dcdc-converters-for-solar-energy-system-with-maximum-.pdf
 
A Simple Control Strategy for Boost Converter Based Wind and Solar Hybrid Ene...
A Simple Control Strategy for Boost Converter Based Wind and Solar Hybrid Ene...A Simple Control Strategy for Boost Converter Based Wind and Solar Hybrid Ene...
A Simple Control Strategy for Boost Converter Based Wind and Solar Hybrid Ene...
 
IRJET- Simulation and Analysis of Photovoltaic Solar System for Different Wea...
IRJET- Simulation and Analysis of Photovoltaic Solar System for Different Wea...IRJET- Simulation and Analysis of Photovoltaic Solar System for Different Wea...
IRJET- Simulation and Analysis of Photovoltaic Solar System for Different Wea...
 
Drive Applications of Fuzzy Logic Controlled Interleaved Boost Converter for ...
Drive Applications of Fuzzy Logic Controlled Interleaved Boost Converter for ...Drive Applications of Fuzzy Logic Controlled Interleaved Boost Converter for ...
Drive Applications of Fuzzy Logic Controlled Interleaved Boost Converter for ...
 
Power losses reduction of power transmission network using optimal location o...
Power losses reduction of power transmission network using optimal location o...Power losses reduction of power transmission network using optimal location o...
Power losses reduction of power transmission network using optimal location o...
 
Attou. photovoltaic grid Boost Converter
Attou. photovoltaic grid Boost ConverterAttou. photovoltaic grid Boost Converter
Attou. photovoltaic grid Boost Converter
 
MAXIMUM POWER POINT TRACKING WITH ARTIFICIAL NEURAL NET WORK
MAXIMUM POWER POINT TRACKING WITH ARTIFICIAL NEURAL NET WORKMAXIMUM POWER POINT TRACKING WITH ARTIFICIAL NEURAL NET WORK
MAXIMUM POWER POINT TRACKING WITH ARTIFICIAL NEURAL NET WORK
 
Design and Implementation of Maximum Power Point Tracking in Photovoltaic Sys...
Design and Implementation of Maximum Power Point Tracking in Photovoltaic Sys...Design and Implementation of Maximum Power Point Tracking in Photovoltaic Sys...
Design and Implementation of Maximum Power Point Tracking in Photovoltaic Sys...
 
Mini_Project
Mini_ProjectMini_Project
Mini_Project
 
Optimal Power Flow with Reactive Power Compensation for Cost And Loss Minimiz...
Optimal Power Flow with Reactive Power Compensation for Cost And Loss Minimiz...Optimal Power Flow with Reactive Power Compensation for Cost And Loss Minimiz...
Optimal Power Flow with Reactive Power Compensation for Cost And Loss Minimiz...
 
THREE PHASE GRID CONNECTED SOLAR PV SYSTEM
THREE PHASE GRID CONNECTED SOLAR PV SYSTEMTHREE PHASE GRID CONNECTED SOLAR PV SYSTEM
THREE PHASE GRID CONNECTED SOLAR PV SYSTEM
 
PV array connected to the grid with the implementation of MPPT algorithms (IN...
PV array connected to the grid with the implementation of MPPT algorithms (IN...PV array connected to the grid with the implementation of MPPT algorithms (IN...
PV array connected to the grid with the implementation of MPPT algorithms (IN...
 
A Novel Approach on Photovoltaic Technologies for Power Injection in Grid Usi...
A Novel Approach on Photovoltaic Technologies for Power Injection in Grid Usi...A Novel Approach on Photovoltaic Technologies for Power Injection in Grid Usi...
A Novel Approach on Photovoltaic Technologies for Power Injection in Grid Usi...
 
40620130101002
4062013010100240620130101002
40620130101002
 

More from slmnsvn

Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system
slmnsvn
 
Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system
slmnsvn
 
Smart home
Smart homeSmart home
Smart home
slmnsvn
 
Smart fuel theft detector
Smart fuel theft detectorSmart fuel theft detector
Smart fuel theft detector
slmnsvn
 
Smart fuel theft detector
Smart fuel theft detectorSmart fuel theft detector
Smart fuel theft detector
slmnsvn
 
Rfid attendace system
Rfid attendace systemRfid attendace system
Rfid attendace system
slmnsvn
 
Quad pod transformable vehicle
Quad pod transformable vehicleQuad pod transformable vehicle
Quad pod transformable vehicle
slmnsvn
 
Quad pod transformable vehicle
Quad pod transformable vehicleQuad pod transformable vehicle
Quad pod transformable vehicle
slmnsvn
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
slmnsvn
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
slmnsvn
 
Optimum performances of ramallah
Optimum performances of ramallahOptimum performances of ramallah
Optimum performances of ramallah
slmnsvn
 
Optimum performances of ramallah
Optimum performances of ramallahOptimum performances of ramallah
Optimum performances of ramallah
slmnsvn
 
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkOptimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate network
slmnsvn
 
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkOptimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate network
slmnsvn
 
Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2
slmnsvn
 
Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2
slmnsvn
 
Optimum performance for aqraba electrical network
Optimum performance for aqraba electrical networkOptimum performance for aqraba electrical network
Optimum performance for aqraba electrical network
slmnsvn
 
Multi tone test
Multi tone testMulti tone test
Multi tone test
slmnsvn
 
Multi tone test
Multi tone testMulti tone test
Multi tone test
slmnsvn
 
Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...
slmnsvn
 

More from slmnsvn (20)

Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system
 
Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system
 
Smart home
Smart homeSmart home
Smart home
 
Smart fuel theft detector
Smart fuel theft detectorSmart fuel theft detector
Smart fuel theft detector
 
Smart fuel theft detector
Smart fuel theft detectorSmart fuel theft detector
Smart fuel theft detector
 
Rfid attendace system
Rfid attendace systemRfid attendace system
Rfid attendace system
 
Quad pod transformable vehicle
Quad pod transformable vehicleQuad pod transformable vehicle
Quad pod transformable vehicle
 
Quad pod transformable vehicle
Quad pod transformable vehicleQuad pod transformable vehicle
Quad pod transformable vehicle
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
Optimum performances of ramallah
Optimum performances of ramallahOptimum performances of ramallah
Optimum performances of ramallah
 
Optimum performances of ramallah
Optimum performances of ramallahOptimum performances of ramallah
Optimum performances of ramallah
 
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkOptimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate network
 
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkOptimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate network
 
Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2
 
Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2
 
Optimum performance for aqraba electrical network
Optimum performance for aqraba electrical networkOptimum performance for aqraba electrical network
Optimum performance for aqraba electrical network
 
Multi tone test
Multi tone testMulti tone test
Multi tone test
 
Multi tone test
Multi tone testMulti tone test
Multi tone test
 
Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...
 

Recently uploaded

一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
upoux
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
ijaia
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
upoux
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
morris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdfmorris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdf
ycwu0509
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
bijceesjournal
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
PriyankaKilaniya
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
MadhavJungKarki
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
RamonNovais6
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf
Yasser Mahgoub
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 

Recently uploaded (20)

一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
morris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdfmorris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdf
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 

Investigation effects-of-supplying-power-distrubition

  • 1. Investigations of the effects of supplying Jenin’s power distribution network by a PV generator with respect to voltage level, power losses, P.F and harmonics By: Ibrahim Anwar Ibrahim Ihsan Abd Alfattah Omareya The supervisor: Dr. Maher Khammash
  • 3. Introduction: Due to the global trend toward the clean energy resources, it is very important to make our projects and researches related with it. Moreover, we need to find the best solutions for improving our power networks taking into consideration the best possible price which represented in the almost free sources such as solar energy, especially that we are under the occupation and we don't have control on our networks or the electricity generation. The share of grid-connected photovoltaic (PV) power sources in power distribution systems is expected to rise due to increasing costs of traditional fossil-fuel sources and continuous reduction of PV generators worldwide. This project will present the schematic diagram of a complete PV generator with control system (design with detailed specifications) to be connected safely with the electric network in Jenin. Problem Statement: We will investigate what is the possibility of using PV generators in order to improve the action of the system was selected from one part of Jenin’s power distribution network that contains 25 bus in the same voltage level that consume 10.076 MW, 3.075 MVAR and total power losses 0.136 MW, 0.096 MVAR at Maximum load and consume 1.878 MW, 0.859 MVAR and total power losses 0.00538 MW, 0.00377 MVAR at Minimum load taking in consideration the voltage levels, power losses, P.F and harmonics. Objectives:  Find the optimal placement and sizing of distribution generation PV units in the network.  Study the impact of the added PV DG units by conducting a new power flow study and harmonic distortion analysis.  Economic evaluation of the added PV DG units.
  • 4. Methodology: This study will be carried out on – Jenin's power distribution network-West Bank – Palestine. Some information about the network and it's component specifications (like cables, transformers, loads, ... etc) will be used. Also some specialized simulation software such as MATLAB, ETAP, and GIS are used to analyze and study the above mentioned effects. After analyzing the targeted network, we will review relevant research work in order to layout and design an appropriate PV generator to be connected with the busses of Jenin network. After that we will use simulation models to investigate the effect s of connecting PV generator with the outlined grid. Through simulation technique, the effects of this PV on P.F, power losses, voltage level, harmonics and reactive power flow in the network will be investigated. We expect that our work will yield an improvement of power quality and distribution reliability of Jenin network by connecting of PV generators. Part 1: From the literature reviews we found that the more suitable methodology to have optimal location and sizing of DG in the system is one of Artificial Intelligent techniques called “Particle Swarm Optimization (PSO)” because it is fast and accurate to find the optimum location and sizing of the photovoltaic
  • 5. distributed generators that we can add to the system was selected from one part of Jenin’s distribution network. No Yes No Yes Yes No BEGIN Set System Parameters Run Power Flow at Base Case Set x=1: N (x=bus no. DG is added; N=total bus number) X>N Add DG to bus X, 𝑃 𝐷𝐺 from 0% to 15% in ratio 0.5% of total load power 𝑃 𝐷𝐺 = ∑ 𝑃𝑖−1 𝑖=𝑗 𝑖=0 + 𝑃𝑖 (𝑃 𝐷𝐺: 𝑝𝑜𝑤𝑒𝑟 𝑜𝑓 𝑃𝑉 𝑎𝑑𝑑, 𝑃𝑖−1: 𝑝𝑟𝑒𝑣𝑖𝑜𝑢𝑠 𝑝𝑜𝑤𝑒𝑟 𝑜𝑓 𝑃𝑉, 𝑃𝑖: 0.5% 𝑜𝑓 𝑡𝑜𝑡𝑎𝑙 𝑙𝑜𝑎𝑑 𝑝𝑜𝑤𝑒𝑟, 𝑗: 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑖𝑛𝑐𝑟𝑒𝑚𝑒𝑛𝑡 = 0 𝑎𝑠 𝑖𝑛𝑖𝑡𝑖𝑎𝑙 𝑣𝑎𝑙𝑢𝑒) Calculate the total power losses Are the voltages in acceptable range? 0.95 𝑝𝑢 ≤ 𝑉 ≤ 1.05 𝑝𝑢 Chose the optimum bus number by using PSO J>30 X=x+1 J=j+1
  • 6. Part 2: After finding the optimal location and sizing of DG that will add to the system, we will study the effects of PV DG added on the system such as; the voltage drop, total power losses, power losses between the branches, P.F, buses voltages and harmonics. Part 3: This part for economic evaluation of the added DG PV on the system, it will contains the capital cost of PV and the other equipment need, the saving money after reduce the total power losses and power generation, total annual saving, the saving money while 20 years (PV life cycle) and the payback period. Results and Analysis: Part 1: As the first results in our methodology to investigate what is the possibility of using PV generators in order to improve the action of the system was selected from one part of Jenin’s power distribution network that contains 25 bus in the same voltage level taking in consideration the voltage levels, power losses, P.F and harmonics is make run of load flow in maximum and minimum loads for the system. End
  • 7. The system that contains 25 bus at the same Voltage levels Load Flow by using MATLAB (Newton Raphson Method): Month Power Factor Q Generation (MVAR) P Generation (MW) P loss (MW) Q loss (MVAR) Jan 0.909 0.859 1.878 0.0054 0.0038 Feb 0.909 0.859 1.878 0.0054 0.0038 Mar 0.909 0.859 1.878 0.0054 0.0038 Apr 0.96 3.075 10.076 0.136 0.096 May 0.96 3.075 10.076 0.136 0.096 Jun 0.96 3.075 10.076 0.136 0.096 Jul 0.96 3.075 10.076 0.136 0.096 Aug 0.96 3.075 10.076 0.136 0.096 Sep 0.96 3.075 10.076 0.136 0.096 Oct 0.909 0.859 1.878 0.0054 0.0038 Nov 0.909 0.859 1.878 0.0054 0.0038 Dec 0.909 0.859 1.878 0.0054 0.0038
  • 8. The yearly load curve for the Main Feeder From this yearly load curve we found that the Average Power=5.977 MW, Max. Power=10.076 MW and Load Factor= 59.32% As we mentioned before the total DG PV added must not exceed 15% of the total load in both situation (min. and max. load) for the main feeder. We saw that the max. load for this feeder in (April., May., Jun., Jul., Aug. and Sep.) months and the min. load for this feeder in (Jan., Feb., Mar., Oct., Nov. and Dec.) months. Solar Energy Parameters for Jenin: The monthly average solar radiation that recorded by Energy Research Center in 2012 in Jenin city as the following table: Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec G(W/m2 ) 208.3 263.6 362.8 464.2 552.6 598.7 585.6 528.8 449.6 335.1 242.1 191.4 T (°C) 11.3 12.7 16.7 23.1 27.9 31.3 34.0 34.2 31.5 25.7 18.7 13.2 Tilt Angle 47 45 35 29 20 15 18 25 32.5 44 55 58.5 Table 6.1 Average monthly solar radiation for Jenin City [7]. Monthly Average Solar Radiation at Jenin City: 0 2 4 6 8 10 12 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec PGeneration(MW) Month P Generation (MW)
  • 9. Average monthly solar radiation for Jenin City Peak Sun Shine Hour 5.4 H. The solar radiation and the temperature are changed during the year in Jenin City. So that mean the energy that generated from the PV array depends on these terms, so to have the maximum efficiency we will use tracking solar system by MPPT algorithm device to change the tilt angle 12 times per year. The maximum demand in these months (April., May., Jun., Jul., Aug. and Sep.) is 10.076 MW and the maximum demand in these months (Jan., Feb., Mar., Oct., Nov. and Dec.) is 1.878 MW, so if we said that the DG PV will be 15% of the total load, we can see that the PV power needed in (April., May., Jun., Jul., Aug. and Sep.) is 1.5 MW from PV and the PV power needed in (Jan., Feb., Mar., Oct., Nov. and Dec.) is 0.2817 MW from PV. However, we use PV module from SUNTECH com. Called (SuperPoly STP300 – 24/Vd) at STP (1000 (w/m²), 25 (⁰C) ) to have maximum efficiency, but the average yearly solar radiation about 400 (W/m²) so we will use 3 MW PV when we need 1.5 MW, and 800 KW PV when we need 218.7 KW by using the previous equations, we have the following that describe the power that generate from the DG PV field during the year and the suitable tilt angle needed to achieve the max. efficiency for this field : Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec G(W/m2 ) 208.3 263.6 362.8 464.2 552.6 598.7 585.6 528.8 449.6 335.1 242.1 191.4 T (°C) 11.3 12.7 16.7 23.1 27.9 31.3 34.0 34.2 31.5 25.7 18.7 13.2 208.3 263.6 362.8 464.2 552.6 598.7 585.6 528.8 449.6 335.1 242.1 191.4 0 100 200 300 400 500 600 700 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec G(W/M²) MONTH Monthly Average Solar Radiation (W/m²)
  • 10. Tilt Angle 47 45 35 29 20 15 18 25 32.5 44 55 58.5 P generation- Max.(MW) 0.591 0.746 1.010 1.253 1.456 1.550 1.495 1.349 1.163 0.892 0.665 0.537 P generation- Min. (MW) 0.158 0.199 0.269 0.334 0.388 0.413 0.399 0.360 0.310 0.238 0.177 0.143 PV Power generation - Used (MW) 0.158 0.199 0.269 1.253 1.456 1.550 1.495 1.349 1.163 0.238 0.177 0.143 The Real Power generated yearly from the Solar Field. After we found the optimum sizing that will add to Ayash Feeder we will find the optimum location for this DG PV field by using PSO algorithm. Firstly, we implement this size in the all buses in the feeder. The PSO algorithm takes for each bus 6 values as an initial values for voltage profile, power factor, total real power losses and total reactive power losses by using the following equations: 𝑉 𝑘+1 = 𝜔 ∗ 𝑉 𝑘 + 𝐶1 ∗ 𝑟2 ∗ (𝑃𝑏𝑒𝑠𝑡 − 𝑆 𝑘 ) + 𝐶2 ∗ 𝑟1 ∗ (𝐺 𝑏𝑒𝑠𝑡 − 𝑆 𝑘 ) 𝑆 𝑘+1 = 𝑉 𝑘+1 + 𝑆 𝑘 Where:  𝜔 is the weighting function is usually used as follows: 𝜔 = 𝜔 𝑚𝑎𝑥 − 𝜔 𝑚𝑎𝑥 − 𝜔 𝑚𝑖𝑛 𝐼𝑡𝑟𝑒 𝑚𝑎𝑥 𝐼𝑡𝑟𝑒 𝜔 𝑚𝑎𝑥 𝑎𝑛𝑑 𝜔 𝑚𝑖𝑛 ∶ Are the maximum and minimum weights, respectively. Appropriate values for 𝜔 𝑚𝑎𝑥 𝑎𝑛𝑑 𝜔 𝑚𝑖𝑛 are 0.4 and 0.9 [3]. The weights for each factor as the following: Voltage profile: 50% Power factor: 30% Total real power losses: 10% Total reactive power losses: 10% The results as the following for maximum and minimum loads as the following:
  • 11. Maximum load case: # Bus Voltages P.F Total P loss Total Q loss 12 25 3 0.09417 0.066817 16 20 2 0.094383 0.066646 18 20 2 0.0944 0.066655 13 15 3 0.09431 0.066902 15 16 2 0.094709 0.06683 11 13 4 0.094734 PSO Bus selection in max. load. As the above table shown the optimum location in max. load is bus #12. Minimum load case: # Bus Voltages P.F Total P loss Total Q loss 12 24 8 0.003887656 0.002744823 13 14 7 0.00388864 0.002745419 14 13 6 0.003911429 0.0027532 15 12 5 0.00391135 0.002751781 16 18 15 0.003910106 0.002745546 18 18 7 0.003908988 0.002744918 PSO Bus selection in min. load. As the above table shown the optimum location in min. load is bus #12. To sum up, we can notice that bus #12 is the optimum location in the both situation. Part 2: Discussion: As we mentioned in the previous chapter that the optimum sizing was 1.5 MW in max. load and 218.7 KW in min. load and the optimum location was bus #12, the effects for this adding on the main feeder as the following: Month Solar Radiation (W/m²) Voltage Profile (P.U) Total Power Factor P Generation (MW) P PV (MW) Q Generation (MVAR) Total P Loss (MW) Total Q Loss(MW) Jan 208.3 0.9965 0.895 1.72 0.158 0.859 0.005 0.003 Feb 263.6 0.9966 0.89 1.678 0.199 0.859 0.004 0.003 Mar 362.8 0.9968 0.882 1.608 0.269 0.858 0.004 0.003 Apr 464.2 0.9848 0.945 10.04 1.253 3.049 0.1001 0.071 May 552.6 0.9853 0.942 10.035 1.456 3.045 0.095 0.068 Jun 598.7 0.9856 0.941 10.033 1.55 3.044 0.093 0.066 Jul 585.6 0.9854 0.942 10.034 1.495 3.045 0.094 0.067 Aug 528.8 0.985 0.944 10.038 1.349 3.047 0.098 0.069
  • 12. Table 8.1 The effects of add DG PV on bus 12 The power factor at the main feeder (Ayash Feeder) after add DG PV as the following fig. 8.1: Fig 8.1 The power factor at the main feeder after add DG PV on bus 12 The total real power feed the all over main feeder (Ayash Feeder) after add DG PV as the following fig. 8.2: 0.895 0.89 0.882 0.945 0.942 0.941 0.942 0.944 0.946 0.886 0.893 0.896 0.84 0.86 0.88 0.9 0.92 0.94 0.96 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec P.F MONTH Ayash Feeder Power Factor Sep 449.6 0.9845 0.946 10.042 1.163 3.05 0.102 0.073 Oct 335.1 0.9967 0.886 1.639 0.238 0.858 0.004 0.003 Nov 242.1 0.9966 0.893 1.7 0.177 0.859 0.004 0.003 Dec 191.4 0.9965 0.896 1.734 0.143 0.859 0.005 0.003
  • 13. Fig 8.2 The total real power feed the all over main feeder after add DG PV on bus 12 Average Power=6.6459 MW, Max. Power=10.042 MW, Load Factor=66.18 % The total Reactive power feed the all over main feeder (Ayash Feeder) after add DG PV as the following fig. 8.3: Fig 8.3 The total reactive power feed the all over main feeder after add DG PV on bus 12 The total real power and reactive power loss for the all over main feeder (Ayash Feeder) after add DG PV as the following fig. 8.4: Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec P PV (MW) 0.158 0.199 0.269 1.253 1.456 1.55 1.495 1.349 1.163 0.238 0.177 0.143 P Generation (MW) 1.72 1.678 1.608 10.04 10.035 10.033 10.034 10.038 10.042 1.639 1.7 1.734 0 2 4 6 8 10 12 14 PGeneration(MW) Total Real Power Generation (MW) P Generation (MW) P PV (MW) 0.859 0.859 0.858 3.049 3.045 3.044 3.045 3.047 3.05 0.858 0.859 0.859 0 0.5 1 1.5 2 2.5 3 3.5 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec QGENERATION(MVAR) MONTH Total Reacive Power Generation (MVAR)
  • 14. Fig 8.4 The total real power and reactive power loss for all over main feeder after add DG PV on bus 12 We can notice from the previous results that:  The power factor at the main feeder sharp decrease  The voltage profile at the main feeder gradual increase  The reactive power generation constant  The real power came from connection point steady decrease  The total real and reactive power losses within the system decrease  The load factor increase to become 66.18% from 59.32% But, the effects on bus #12 as the following figures, we can noticed that the power factor become unity and steady at 1, on the other hand the voltage profile sharp increased during the year: Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total P Loss (MW) 0.005 0.004 0.004 0.1001 0.095 0.093 0.094 0.098 0.102 0.004 0.004 0.005 Total Q Loss(MW) 0.003 0.003 0.003 0.071 0.068 0.066 0.067 0.069 0.073 0.003 0.003 0.003 0 0.02 0.04 0.06 0.08 0.1 0.12 Total Losses Total P Loss (MW) Total Q Loss(MW)
  • 15. The voltage profile for bus #12 after add DG PV as the following fig. 8.5: Fig 8.5 The voltage profile for bus #12 after add DG PV The power factor at bus #12 after add DG PV as the following fig. 8.6: Fig 8.6 The power factor at bus #12 after add DG PV Although, we studied the effects that appear in the all buses when we add DG PV on bus #12, the effects was the following figures and tables: 0.99650.99660.9968 0.98480.98530.98560.9854 0.985 0.9845 0.99670.99660.9965 0.978 0.98 0.982 0.984 0.986 0.988 0.99 0.992 0.994 0.996 0.998 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec V(P.U) MONTH Voltage Profile (P.U) 1 1 1 1 1 1 1 1 1 1 1 1 0 0.2 0.4 0.6 0.8 1 1.2 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec P.F MONTH Power Factor bus #12
  • 16. The following table 8. 2 shows the power factor in each bus before and after added DG PV: # Bus PF Original PF After PV 1 0.909 0.885867 2 0.8917 0.408423 3 0.911 0.654792 4 0.853 0.7676 5 0.934 0.7532 6 0.889 0.64617 7 0.93 0.7979 8 0.912 0.80946 9 0.767 0.643 10 0.707106 0.589 11 0.952 0.6696 12 0.891 1 13 0.879 0.699784 14 0.878 0.607558 15 0.926 0.7217 16 0.855 0.74 17 0.879 0.621 18 0.891 0.6313 19 0.899 0.75 20 0.939 0.617 21 0.903 0.76238 22 0.857 0.6685 23 0.953 0.7402 24 0.908 0.646 25 0.866 0.6159 Table 8.2 The power factor in each bus before and after added DG PV The affects for added DG PV on bus #12 on the power factor for each bus as the following:
  • 17. Fig 8.7 The affects for added DG PV on bus #12 on the power factor for each bus The following table shows the Voltage profile in each bus before and after added DG PV: # Bus V original V after PV 1 1 1 2 0.98889624 0.989987 3 0.98886 0.989765 4 0.98575 0.9872 5 0.98597 0.9875 6 0.985 0.98703 7 0.9848 0.986571 8 0.9835532 0.98567 9 0.9827 0.985091 10 0.9819987 0.98459 11 0.981849 0.984533 12 0.98122843 0.984512 13 0.98099 0.984278 14 0.98093 0.984217 15 0.98177123 0.984363 16 0.98127757 0.98387 17 0.98117745 0.98377 18 0.9811353 0.983728 19 0.98093 0.983524 20 0.9887876 0.9899 21 0.9885 0.98964 22 0.988 0.98957 23 0.9883 0.989393 0 0.2 0.4 0.6 0.8 1 1.2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 PowerFactor Buses Power Factor For Each Bus PF Original PF After PV
  • 18. 24 0.9821263 0.989304 25 0.98820786 0.989299665 Table 8.3 The Voltage profile in each bus before and after added DG PV The affects for added DG PV on bus #12 on the voltage profile for each bus as the following: Fig 8.8 The affects for added DG PV on bus #12 on the voltage profile for each bus The following table shows the total harmonic distortion (THD) in each bus before and after added DG PV to bus #12: 0.97 0.975 0.98 0.985 0.99 0.995 1 1.005 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 V(P.U) Bus Number Voltage Profile For Each Bus V original V after PV Bus Num. Voltage harmonic Before (%) Voltage harmonic After (%) Current harmonic Before (%) Current harmonic After (%) 1 5.42 2.6 11.94 6.32 2 5.32 2.45 11.67 6.8 3 6.85 4.2 8.66 4.6 4 5.26 3.2 11.65 6.3 5 6.35 3.85 7.43 3.5 6 6.22 3.8 10.68 5.02 7 6.96 4.3 7.35 3.4 8 5.62 2.55 10.67 5.01 9 5.36 2.35 9.85 4.8 10 5.68 2.45 10.67 5.1 11 6.52 1.98 7.45 3.6 12 6.35 2.7 7.41 3.8 13 5.59 2.89 10.68 4.89 14 4.99 2.12 11.94 4.52
  • 19. Table 8.4 The total harmonic distortion (THD) in each bus before and after added DG PV to bus #12 The Voltage Harmonic emission in the network after add DG PV to the bus #12 and how it effects on the THD as the following: Fig. 8.9 The Voltage Harmonic emission in the network after add DG PV to the bus #12 The Current Harmonic emission in the network after add DG PV to the bus #12 and how it effects on the THD as the following: 0 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 VTHD(%) Bus Number Voltage Harmonic Voltage harmonic Before (%) Voltage harmonic After (%) 15 5.26 3.2 9.54 4.98 16 6.53 2 8.56 4.6 17 5.33 2.3 9.53 4.88 18 6.43 2.82 7.42 3.89 19 6.42 2.86 8.52 4.99 20 5.95 2.15 9.53 4.62 21 5.69 2.23 10.69 5.08 22 5.2 3.1 11.68 6.2 23 5.36 3.21 10.66 5.6 24 4.98 2.5 9.53 4.9 25 5.96 2.3 10.68 5.6
  • 20. Fig. 8.10 The Current Harmonic emission in the network after add DG PV to the bus #12 We can notice from the previous results:  The power factor at each bus sharp decrease  The Voltage profile increase  The total losses decrease  The THD decrease for voltage and current signal Part 3: the one line diagram for An-Najah solar field that will feed Ayash feeder: 0 2 4 6 8 10 12 14 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 ITHD(%) Bus Number Current Harmonic Current harmonic Before (%) Current harmonic After (%)
  • 21. Fig. 7.3 An-Najah Solar Field. Non Labor: DC Components V line (KV) Nominal Current (A) Breaking Capacity (A) Unit Price ($)/unit Price ($) Fuse 0.4 30 300 150 111 16650 Switch 0.4 30 - 150 64 9600 Contactor 0.4 3000 - 1 1400 1400 DC Wire, 10 mm² 0.4 30 - 5000 4 20000 Total 47650 AC Components V line (KV) Nominal Current (KA) Breaking Capacity (KA) Unit Price ($)/Unit Price ($) Fuse 0.4 5 35 1 14395 14395
  • 22. Table 7.15 DC Components, properties, units and price [12] Table 7.16 AC Components, properties, units and price [12] Table 7.17 other Components, properties, units and price [8,11,12,13] Assets Area $/Year Year Price ($) Site 20 Dunam 75000 20 1500000 Table 7.18 Assets, properties, duration and price DC Components 47650 $ AC Components 229605 $ Other Components 2788852 $ Site 1500000 $ Switch 0.4 5 - 1 7500 7500 C.B, SF6 0.4 5 35 1 18710 18710 C.B, SF6 33 0.05 3 1 29000 29000 Fuse 33 0.05 3 2 23000 46000 Switch 33 0.05 - 2 24500 49000 C.B, SF6 33 0.05 6 2 30000 60000 Bas Bur 33 0.1 - 1 5000 5000 Total 229605 Other Components Properties Unit Price ($)/Unit Price ($) PV Module_SUNTECH 300W/24Vd 10013 250 2503250 Transformer_Schneider 0.4/33 KV , 3MVA 1 30000 30000 DC/DC Converter_ SMA (300-400)V =400 V, 20000 W 150 500 75000 DC/AC Inverter _SMA 400 V = 400 V,50 Hz, 20000 W 150 1000 150000 Capacitor Banks_ABB 20KVAR, 400V 2 185 370 Capacitor Banks_ABB 25KVAR, 400V 9 200 1800 Capacitor Banks_ABB 30KVAR, 400V 13 264 3432 MPPT_SMA 150 100 15000 Motor 3 ph, 400 V, 10 Khp 1 10000 10000 Rotary UPS 400 V, 9 KAH 1 65000 65000 Total 2853852
  • 23. Total ($) 4541107 $ Table 7.19 Total Non-labor resource Cost. Labor: Person Num. $/Hour Hours/ 18 Months Price ($) Engineers 7 45 4320 194400 Technicians 20 23 4320 99360 Others 10 15 5000 75000 Total ($) 368760 $ Table 7.20 Total labor resource Cost. Labor 368760 ($) Non Labor 4631107 ($) Currency Diffusion 133 ($) Total Budget ($) 5000000 ($) Table 7.21 Total Capital Cost. The annual saving for Ayash Feeder: Original: The annual max demand: Pmax= 10.076 MW Since the load factor (L.F) = 59.32 % 𝑃𝑎𝑣𝑔 = 𝐿. 𝐹 ∗ 𝑃𝑚𝑎𝑥 𝑃𝑎𝑣𝑔 = 0.5932 ∗ 10.076 ∗ 103 = 5977 𝐾𝑊 𝐸𝑛𝑒𝑟𝑔𝑦 (𝐸) = 𝑃𝑎𝑣𝑔 ∗ 8760 = 52359249 𝐾𝑊𝐻 𝑦𝑒𝑎𝑟𝑙𝑦 The cost per KWH is 0.62 NIS/KWH: 𝑇𝑜𝑡𝑎𝑙 𝑏𝑖𝑙𝑙 = 𝐸 ∗ 0.62 𝑁𝐼𝑆 𝐾𝑊𝐻⁄ = 32462734 𝑁𝐼𝑆 𝑝𝑒𝑟 𝑦𝑒𝑎𝑟 Since the power factor during the minimum load period less than 0.92 so the company is paying a penalty as explained below: 𝐸𝑛𝑒𝑟𝑔𝑦/𝑚𝑜𝑛𝑡ℎ = 𝑃𝑎𝑣𝑔 ∗ 8760/12 = 4363271 𝐾𝑊𝐻 𝑚𝑜𝑛𝑡ℎ𝑙𝑦
  • 24. 𝑐𝑜𝑠𝑡 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ = 2705228 𝑁𝐼𝑆 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ During the six month of minimum load the power factor =0.909 In Palestine the penalty for 0.8 ≤ 𝑝. 𝑓 ≤ 0.92 is 1% at total bill for each 0.1 under 0.92 0.92-0.909=0.011 𝑃𝑒𝑛𝑎𝑙𝑡𝑦 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ = 0.011 ∗ 𝑇𝑜𝑡𝑎𝑙 𝑚𝑜𝑛𝑡ℎ𝑙𝑦 𝐵𝑖𝑙𝑙 𝑃𝑒𝑛𝑎𝑙𝑡𝑦 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ = 0.011 ∗ 2705228 = 29758 𝑁𝐼𝑆 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ For the six months: 𝑇𝑜𝑡𝑎𝑙 𝑃𝑒𝑛𝑎𝑙𝑡𝑦 = 6 ∗ 29758 = 178548 𝑁𝐼𝑆 The total cost: 𝑇𝑜𝑡𝑎𝑙 𝑎𝑛𝑛𝑢𝑎𝑙 𝑐𝑜𝑠𝑡 = 𝐸𝑛𝑒𝑟𝑔𝑦 𝑐𝑜𝑠𝑡 + 𝑡𝑜𝑡𝑎𝑙 𝑝𝑒𝑛𝑎𝑙𝑡𝑦 = 32462734 + 178548 = 32641282 𝑁𝐼𝑆 = 𝟗𝟒𝟎𝟔𝟕𝟏𝟎 $ . After using DG PV: The annual max demand: Pmax= 8.879 MW Since the load factor (L.F) = 66.18 % 𝑃𝑎𝑣𝑔 = 𝐿. 𝐹 ∗ 𝑃𝑚𝑎𝑥 𝑃𝑎𝑣𝑔 = 0.6618 ∗ 8.879 ∗ 103 = 5070.92 𝐾𝑊 𝑃𝑎𝑣𝑔 = 5070.92 𝐾𝑊 𝐸𝑛𝑒𝑟𝑔𝑦 (𝐸) = 𝑃𝑎𝑣𝑔 ∗ 8760 = 44421259 𝐾𝑊𝐻 𝑦𝑒𝑎𝑟𝑙𝑦 The cost per KWH is 0.62 NIS/KWH 𝑇𝑜𝑡𝑎𝑙 𝑏𝑖𝑙𝑙 = 𝐸 ∗ 0.62 𝑁𝐼𝑆 𝐾𝑊𝐻⁄ = 27541181 𝑁𝐼𝑆 𝑝𝑒𝑟 𝑦𝑒𝑎𝑟
  • 25. Before using PV After using PV Total annual cost 32641282 NIS 27541181 NIS Cost in $ (1$=3.47 NIS) 9406710 $ 7936940 $ Table 7.22 Total annual Cost before and after add DG PV. 𝑇ℎ𝑒 𝑦𝑒𝑎𝑟𝑙𝑦 𝑠𝑎𝑣𝑖𝑛𝑔 = 9406710 − 7936940 = 𝟏𝟒𝟔𝟗𝟕𝟕𝟎 $ The Payback Period: 𝑃. 𝐵. 𝑃 = 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 𝑆𝑎𝑣𝑖𝑛𝑔 𝑃. 𝐵. 𝑃 = 5000000 $ 1469770 $ 𝑃. 𝐵. 𝑃 = 3.5 𝑌𝑒𝑎𝑟 By the way the life cycle of the equipment in the solar field is about 20 Year and the payback period is 3.5 Year, so the total saving after 3.5 years of implemented this project will be 𝑆𝑎𝑣𝑖𝑛𝑔 𝑎𝑓𝑡𝑒𝑟 3.5 𝑌𝑒𝑎𝑟 = (20 − 3.5) ∗ 𝑌𝑒𝑎𝑟𝑙𝑦 𝑆𝑎𝑣𝑖𝑛𝑔 𝑆𝑎𝑣𝑖𝑛𝑔 𝑎𝑓𝑡𝑒𝑟 3.5 𝑌𝑒𝑎𝑟 = 16.5 ∗ 1469770 𝑆𝑎𝑣𝑖𝑛𝑔 𝑎𝑓𝑡𝑒𝑟 3.5 𝑌𝑒𝑎𝑟 = 𝟐𝟒𝟐𝟓𝟏𝟐𝟎𝟓 $ To sum up, one can show that the project is feasible to implement. Conclusions and Recommendation: In general, we can conclude that this project will be a strong solution for this problem due to the improvement that happened after add DG PV on this feeder in Jenin City, especially in bus #12. To sum up, the all effects on the system after add DG PV as the following:  The voltage profile increase within the range (1.05≤ V ≤ 0.95) that can increase the efficiency of the supply from one hand, so the current in the system will decrease that
  • 26. mean the total losses will decrease, so the total bill will decrease, from the other hand we can use the same feeder to add new load within range that did not let the voltage be less than 0.95 P.U, so we can make a long term control without need new transformers.  The total harmonic distortion in the system will decrease it can be seen that only the 12th, 15th, 18th, 21st and 24th harmonics exceeded the threshold limits. However, total voltage harmonics distortion for all of the studied cases is within the Australian regulatory standard limit as stated in AS 4777 [10], total Harmonic Distortion gives us the information about the harmonic content in a signal w.r.t. fundamental component, so that mean increase the power quality for the supply.  The total real and reactive power losses decrease sharply, due to increase the voltage profile and decrease the currents in the system in the same time.  The total saving in the total bill will be about 24 Million $.  The only bad effect for this solution was decrease the power factor in the system, so that mean the penalty will be huge, so we recommend to use capacitor banks to increase the power factor to be equal or more than 92%. The recommendation to improve power factor is to use capacitor banks as the following: # Bus PF Original PF After PV Capacitor Bank (KVAR) 1 0.909 0.885867 20 2 0.8917 0.408423 30 3 0.911 0.654792 30 4 0.853 0.7676 25 5 0.934 0.7532 30 6 0.889 0.64617 25 7 0.93 0.7979 25 8 0.912 0.80946 20 9 0.767 0.643 30 10 0.707106 0.589 30 11 0.952 0.6696 25 12 0.891 1 0 13 0.879 0.699784 25 14 0.878 0.607558 30 15 0.926 0.7217 25 16 0.855 0.74 25 17 0.879 0.621 30 18 0.891 0.6313 30 19 0.899 0.75 25 20 0.939 0.617 30 21 0.903 0.76238 25 22 0.857 0.6685 30 23 0.953 0.7402 25
  • 27. 24 0.908 0.646 30 25 0.866 0.6159 30 Table 9.1 Improve power factor and the value of capacitor banks By using the above values of capacitor banks that will increase the power factor to be at least 92%, on the other hand will increase the voltage at the bus but within the voltage rang. Constraints: As any problem in our life we will find the suitable solution for it in many terms to solve it from one side and to have the stability for this solution during a long term period, so in this case we will use SMART method to solve it. SMART method means that the solution will be specific, measurable, achievable, realistic and have time frame to have long term solution for any problem. So to satisfy this method we faced many constraints and the constraints in our project can be divided into four parts: 1. Leakage in Data base from the supplier. 2. Unrealistic solution for this problem.
  • 28. 3. No Palestinian Standers to assist our work 4. Suitable software that can help us. We find the suitable solution for this constraints as the following: 1. Leakage in Data base from the supplier: The leakage in data base was in the some loads data, cables used, records for some factors and the vision for solving this problem. The solution was that we took the records for some these loads by ourselves under the supervision of supplier and we calculated the parameters for the cables used in the system. 2. Unrealistic solution for this problem: The solution for the problem from the supplier is unrealistic that the solution was to increase the connection points that to feed the increasing in demand for this system. 3. No Palestinian Standers to assist our work: There is no standers for this work from Palestinian government to assist our solution, so we used the Australian standers. 4. Suitable software that can help us: Due to the huge budget needed for this solution, we can’t implement samples as a test sample in the ground, so the software can help us to find the suitable solution, so to solve this problem we built MATLAB codes to simulate the reality for this solution.