Erbil Polytechnic University
Technical Engineering College
Civil Engineering Department
Introduction to Surveying 2020-2021.
LEVELLING PROCEDURES
Prepared by:
Asst. Prof. Salar K.Hussein
Mr. Kamal Y.Abdullah
Asst.Lecturer. Dilveen H. Omar
1
Review of levelling
• In this lecture we will cover :
 Equipment and procedures
 Purposes of levelling
 Some definitions
 Reading a staff
 Temporary adjustment of level
 Booking and reduction
 Methods of booking
 Applications
2
Leveling:-
Leveling defined as an operation for the measurement of the
difference in the elevation between points or for the determination
of the elevation of certain points above some given plane or
surface known as the datum surface , generally is taken as the
mean sea level (M S L)
3
Leveling
Is a type of surveying which is carried out for finding difference in
heights in engineering projects. Leveling is required for various
purposes such as for
calculation of the depth of cutting and fillings, for setting out
grades for sewerage and pipe lines, etc.
4
Types of Leveling and Application
I. Direct Methods :
1. Simple levelling:
2. Compound levelling:
3. Differential or Flying Leveling and Check : Set the equipment at many
different places.
4.Contours map by level instrument.
5. Longitudinal , Profile
6.cross-leveling .
7. Reciprocal Leveling.
8. Precise Leveling.
5
II. Indirect Leveling
If there is a barrier prevent the use of instrument.
1. Trigonometrically, 2. Barometric,
Equipment:
1. Level instrument .
2. Tripod
3. Staff
4. Staff bubble
5. 50 m tape measure (sometimes)
6
1. Simple Levelling : -
This method Set the instrument at one point and read another
point. enables us to determine the difference in level between two points
by placing the instrument approximately mid way between the two
stations ,
while taking the readings, the bubble remain in the center as usual.
A
R.L=100.00
2.200
B.S
2.700
F.S
Staff reading at A = 2.200
Height of collimation = 100 + 2.200 = 102.200
Staff reading at B = 2.700
R.L of B = 102.20 - 2.700 = 99.500 m
7
2. Compound Levelling or Differential Levelling :-
Set the instrument at one point and read the other points. involves
the same process as simple Levelling but in addition, a number of
setting of the instrument are required to find out the difference in
Levelling between two points in (the case where a single setting
cannot serve the purpose), this maybe either due to a large
distance.
8
3.Flying Levelling:
The reduced levels(RL) of some important points is found,
by a few selected setting of the instrument.
to get a rough idea of the nature of the ground.
9
4-Contours map
A map showing the natural and cultural features as well
as showing the nature of the surface of the land (topography of the
land) of the up and downs and its representation in (3D)three
dimensions.
A contour is a line drawn on a plan joining all points of the same
height above or below a datum.
10
5. Longitudinal or profile Levelling:-
Longitudinal levelling is an operation of doing a levelling job to determine
the profile of a ground surface along a given line; this is generally the
center line of a purposed alignment, such as railway, highway, canal,
and pipeline.
The proposed alignment may be a single or series of straight lines
connected by curves,
the points are selected at a uniform interval.
11
6. Cross-section Levelling:-
In longitudinal section the center line is taken, but when a winder belt is
required for some engineering project, e.g. highway, railway etc.
12
7.Reciprocal Levelling :-
When two station are situated far apart and it is not possible to set up the
instrument in between these stations because of a river or deep valley and also
not possible to equalize the back sight and fore sight the process of
(reciprocal Levelling )is adopted. The method avoid of applying any correction due
curvature refraction and imperfect line of collimation.
13
8-Precise Levelling:-
Leveling done with at most careful and pre caution and with the most refined
instrument to establish the control point is called precise Levelling .
A systematic procedure of taking field observation and recording is adopted to
minimized and eliminate all sources of error..
14
Level instrument
Types of Level Instruments & Parts of level instrument
1. Dumpy Level
2. Tilting Level
3. Automatic Level
4. Electronic Level
5. Hand Level
6-Digital level
15
Temporary adjustment of level
1- A suitable position is selected for setting the level from the position it
should be possible to take the greatest number of observation without any
difficulty the ground should be rightly level and firm.
2- The instrument in fixed on the tripod.
3- The tripod are adjusted according to one’s high.
4- The three foot screw are brought to the center
.5- The telescope is placed parallel to any two foot screws and by turning
both the two screws either in or out as required. The bubble of the
telescope is brought to center
6- The telescope is brought over to the third foot screw by rotating it
through 90˚. The bubble is brought to the center by turning the third foot
screw only.
The procedure is repeated.. till the bubble remains in the center in both the
positions.
7- Finally the levelly of the instrument is verified by turning the telescope
in any direction when the bubbles remain in the central position for any
direction of the telescope the (staff reading are taken)
Leveling staves
• The rod Is a graduated straight rod made of wooded rod and Aluminium.
height of staff (3m, 5m ), used for measuring the vertical distance between the
pointes on the ground and the line collimation and rectangular in cross-section.
The graduations are units of staff reading (meters , decimeters ,cm and
millimeters). The bottom of the staff represents zero reading. All divisions are
written in black against white ground,
•
18
Types of staff, (rod)
1) Solid Staff.
2) Folding Staff.
3-Telescope Staff.
4-Invar Leveling Staff.
5-Aluminium levelling staff.
19
Reading an “E -face” staff
0.300
0.33
20
What is levelling?
• A measurement process where by the Elevation or difference in
height between two or more points can be determined.
• Levelling is the method, which is used widely, to obtain the
elevations (RL) of ground points to a reference datum.
21
Introduction to Surveying LEVELLING PROCEDURES

More Related Content

What's hot

Assignment 1 - Levelling
Assignment 1 - LevellingAssignment 1 - Levelling
Assignment 1 - Levelling
Kai Yun Pang
 
Sem 2 Site surveying report 2
Sem 2 Site surveying report 2Sem 2 Site surveying report 2
Sem 2 Site surveying report 2
Est
 
SITE SURVEYING: Transversing
SITE SURVEYING: TransversingSITE SURVEYING: Transversing
SITE SURVEYING: Transversing
Farah Sham
 
Traversing final-report
Traversing final-reportTraversing final-report
Traversing final-report
Felix Vong
 
Site Surveying Report - Traversing
Site Surveying Report - TraversingSite Surveying Report - Traversing
Site Surveying Report - Traversing
XinYee Khoo
 
engineering survey 1 report levelling
engineering survey 1 report levellingengineering survey 1 report levelling
engineering survey 1 report levelling
YASMINE HASLAN
 
Site Surveying Levelling
Site Surveying Levelling Site Surveying Levelling
Site Surveying Levelling
Darren Lee
 
Site surveying report1
Site surveying report1Site surveying report1
Site surveying report1
Est
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversing
Dolat Ram
 
Total Station Topographic Survey
Total Station Topographic Survey Total Station Topographic Survey
Total Station Topographic Survey haroldtaylor1113
 
Theodolite Traversing
Theodolite TraversingTheodolite Traversing
Theodolite Traversing
GAURAV. H .TANDON
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
neharajpl
 
Site surveying-report-2
Site surveying-report-2Site surveying-report-2
Site surveying-report-2Shane Ah
 
Ss report 1 ----levelling eport
Ss report 1 ----levelling eportSs report 1 ----levelling eport
Ss report 1 ----levelling eport
MELVIN tan
 
Project 2- traversing
Project 2- traversingProject 2- traversing
Project 2- traversing
seenyee
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
RAHUL SINHA
 
Levelling report-1
Levelling report-1Levelling report-1
Levelling report-1
tfkc1212
 
Advance surveying equipments
Advance surveying equipmentsAdvance surveying equipments
Advance surveying equipments
Ranjan Kumar Lal
 
Setting out 12042018
Setting out 12042018Setting out 12042018
Setting out 12042018
Noorhazlinda Rahman
 

What's hot (20)

Assignment 1 - Levelling
Assignment 1 - LevellingAssignment 1 - Levelling
Assignment 1 - Levelling
 
Sem 2 Site surveying report 2
Sem 2 Site surveying report 2Sem 2 Site surveying report 2
Sem 2 Site surveying report 2
 
SITE SURVEYING: Transversing
SITE SURVEYING: TransversingSITE SURVEYING: Transversing
SITE SURVEYING: Transversing
 
Traversing final-report
Traversing final-reportTraversing final-report
Traversing final-report
 
Site Surveying Report - Traversing
Site Surveying Report - TraversingSite Surveying Report - Traversing
Site Surveying Report - Traversing
 
engineering survey 1 report levelling
engineering survey 1 report levellingengineering survey 1 report levelling
engineering survey 1 report levelling
 
Site Surveying Levelling
Site Surveying Levelling Site Surveying Levelling
Site Surveying Levelling
 
Site surveying report1
Site surveying report1Site surveying report1
Site surveying report1
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversing
 
Total Station Topographic Survey
Total Station Topographic Survey Total Station Topographic Survey
Total Station Topographic Survey
 
Theodolite Traversing
Theodolite TraversingTheodolite Traversing
Theodolite Traversing
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
 
Site surveying-report-2
Site surveying-report-2Site surveying-report-2
Site surveying-report-2
 
Ss report 1 ----levelling eport
Ss report 1 ----levelling eportSs report 1 ----levelling eport
Ss report 1 ----levelling eport
 
Project 2- traversing
Project 2- traversingProject 2- traversing
Project 2- traversing
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
 
Levelling report-1
Levelling report-1Levelling report-1
Levelling report-1
 
Lecture 1 precise levelling
Lecture 1 precise levellingLecture 1 precise levelling
Lecture 1 precise levelling
 
Advance surveying equipments
Advance surveying equipmentsAdvance surveying equipments
Advance surveying equipments
 
Setting out 12042018
Setting out 12042018Setting out 12042018
Setting out 12042018
 

Similar to Introduction to Surveying LEVELLING PROCEDURES

Site surveying-almost-1
Site surveying-almost-1Site surveying-almost-1
Site surveying-almost-1
Lam Yu
 
UNIT FOUR.pptx
UNIT FOUR.pptxUNIT FOUR.pptx
UNIT FOUR.pptx
warkisafile1
 
Site surveying 1 - done
Site surveying 1 - done Site surveying 1 - done
Site surveying 1 - done
w ss
 
Site surveying 1 - done
Site surveying 1 - done Site surveying 1 - done
Site surveying 1 - done
w ss
 
Site Surveying Leveling
Site Surveying LevelingSite Surveying Leveling
Site Surveying Leveling
ashleyyeap
 
Levelling
LevellingLevelling
Levelling
Arissa Loh
 
chapter 3 levelling @etconp.pdf
chapter 3 levelling @etconp.pdfchapter 3 levelling @etconp.pdf
chapter 3 levelling @etconp.pdf
sandipanpaul16
 
LEVELING AND CONTOURING
LEVELING AND CONTOURINGLEVELING AND CONTOURING
LEVELING AND CONTOURING
ANAND JIBHKATE
 
Tacheometry for Geomatics Enginering.pptx
Tacheometry for Geomatics Enginering.pptxTacheometry for Geomatics Enginering.pptx
Tacheometry for Geomatics Enginering.pptx
CtKamariahMdSaat
 
contouring-180417110533.pdf
contouring-180417110533.pdfcontouring-180417110533.pdf
contouring-180417110533.pdf
shucaybcabdi
 
Contouring
ContouringContouring
Contouring
SachinGunjal7
 
B.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingB.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 leveling
Rai University
 
B.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingB.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 leveling
Rai University
 
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdfLecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
AlwandBarzani
 
CET205 Module 1 Contouring.pdf
CET205 Module 1 Contouring.pdfCET205 Module 1 Contouring.pdf
CET205 Module 1 Contouring.pdf
KumkumaIp
 
levelling survey
levelling surveylevelling survey
levelling survey
prashantsingham
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
Phurba Tamang
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveyingstooty s
 
Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01Sunilkumar Mandal
 
Lecture 06 leveling theory methods and equipment
Lecture 06 leveling theory methods and equipmentLecture 06 leveling theory methods and equipment
Lecture 06 leveling theory methods and equipment
Awais Ahmad
 

Similar to Introduction to Surveying LEVELLING PROCEDURES (20)

Site surveying-almost-1
Site surveying-almost-1Site surveying-almost-1
Site surveying-almost-1
 
UNIT FOUR.pptx
UNIT FOUR.pptxUNIT FOUR.pptx
UNIT FOUR.pptx
 
Site surveying 1 - done
Site surveying 1 - done Site surveying 1 - done
Site surveying 1 - done
 
Site surveying 1 - done
Site surveying 1 - done Site surveying 1 - done
Site surveying 1 - done
 
Site Surveying Leveling
Site Surveying LevelingSite Surveying Leveling
Site Surveying Leveling
 
Levelling
LevellingLevelling
Levelling
 
chapter 3 levelling @etconp.pdf
chapter 3 levelling @etconp.pdfchapter 3 levelling @etconp.pdf
chapter 3 levelling @etconp.pdf
 
LEVELING AND CONTOURING
LEVELING AND CONTOURINGLEVELING AND CONTOURING
LEVELING AND CONTOURING
 
Tacheometry for Geomatics Enginering.pptx
Tacheometry for Geomatics Enginering.pptxTacheometry for Geomatics Enginering.pptx
Tacheometry for Geomatics Enginering.pptx
 
contouring-180417110533.pdf
contouring-180417110533.pdfcontouring-180417110533.pdf
contouring-180417110533.pdf
 
Contouring
ContouringContouring
Contouring
 
B.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingB.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 leveling
 
B.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingB.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 leveling
 
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdfLecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
 
CET205 Module 1 Contouring.pdf
CET205 Module 1 Contouring.pdfCET205 Module 1 Contouring.pdf
CET205 Module 1 Contouring.pdf
 
levelling survey
levelling surveylevelling survey
levelling survey
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveying
 
Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01
 
Lecture 06 leveling theory methods and equipment
Lecture 06 leveling theory methods and equipmentLecture 06 leveling theory methods and equipment
Lecture 06 leveling theory methods and equipment
 

More from Bahzad5

دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
Bahzad5
 
2013 (Total Station & Civil 3D) فێرکاری
2013  (Total Station & Civil 3D) فێرکاری2013  (Total Station & Civil 3D) فێرکاری
2013 (Total Station & Civil 3D) فێرکاری
Bahzad5
 
Engineering field knowledge -زانیاری بواری ئەندازیاری
Engineering field knowledge -زانیاری بواری ئەندازیاریEngineering field knowledge -زانیاری بواری ئەندازیاری
Engineering field knowledge -زانیاری بواری ئەندازیاری
Bahzad5
 
(atmosphere correction) زانیاری دەربارەی
(atmosphere correction) زانیاری دەربارەی(atmosphere correction) زانیاری دەربارەی
(atmosphere correction) زانیاری دەربارەی
Bahzad5
 
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
Bahzad5
 
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی (Municipal guidelines)
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی  (Municipal guidelines)المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی  (Municipal guidelines)
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی (Municipal guidelines)
Bahzad5
 
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
Bahzad5
 
Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)
Bahzad5
 
الشروط العامة لمقاولات اعمال الهندسة المدنية
الشروط العامة لمقاولات اعمال الهندسة المدنيةالشروط العامة لمقاولات اعمال الهندسة المدنية
الشروط العامة لمقاولات اعمال الهندسة المدنية
Bahzad5
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
Bahzad5
 
2 سەرەتاکانی دیزاین
2 سەرەتاکانی دیزاین2 سەرەتاکانی دیزاین
2 سەرەتاکانی دیزاین
Bahzad5
 
Soil Mechanics (Problems & solutions)
Soil Mechanics (Problems & solutions)Soil Mechanics (Problems & solutions)
Soil Mechanics (Problems & solutions)
Bahzad5
 
ڕێبەری بەشە ئەندازیارییەکان
ڕێبەری بەشە ئەندازیارییەکانڕێبەری بەشە ئەندازیارییەکان
ڕێبەری بەشە ئەندازیارییەکان
Bahzad5
 
سەرەتاکانی دیزاین
سەرەتاکانی دیزاینسەرەتاکانی دیزاین
سەرەتاکانی دیزاین
Bahzad5
 
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیەڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
Bahzad5
 
پرۆژەی ناساندنی ئەندازیاری
پرۆژەی ناساندنی ئەندازیاریپرۆژەی ناساندنی ئەندازیاری
پرۆژەی ناساندنی ئەندازیاری
Bahzad5
 
بناغە و بنەپایە Footing and Foundation
بناغە و بنەپایە Footing and Foundationبناغە و بنەپایە Footing and Foundation
بناغە و بنەپایە Footing and Foundation
Bahzad5
 
slump test سڵەمپ تێست
slump test سڵەمپ تێستslump test سڵەمپ تێست
slump test سڵەمپ تێست
Bahzad5
 
Design of Storm Sewer System
Design of Storm Sewer SystemDesign of Storm Sewer System
Design of Storm Sewer System
Bahzad5
 
ڕۆنی بزوێنەر
ڕۆنی بزوێنەرڕۆنی بزوێنەر
ڕۆنی بزوێنەر
Bahzad5
 

More from Bahzad5 (20)

دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
 
2013 (Total Station & Civil 3D) فێرکاری
2013  (Total Station & Civil 3D) فێرکاری2013  (Total Station & Civil 3D) فێرکاری
2013 (Total Station & Civil 3D) فێرکاری
 
Engineering field knowledge -زانیاری بواری ئەندازیاری
Engineering field knowledge -زانیاری بواری ئەندازیاریEngineering field knowledge -زانیاری بواری ئەندازیاری
Engineering field knowledge -زانیاری بواری ئەندازیاری
 
(atmosphere correction) زانیاری دەربارەی
(atmosphere correction) زانیاری دەربارەی(atmosphere correction) زانیاری دەربارەی
(atmosphere correction) زانیاری دەربارەی
 
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
 
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی (Municipal guidelines)
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی  (Municipal guidelines)المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی  (Municipal guidelines)
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی (Municipal guidelines)
 
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
 
Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)
 
الشروط العامة لمقاولات اعمال الهندسة المدنية
الشروط العامة لمقاولات اعمال الهندسة المدنيةالشروط العامة لمقاولات اعمال الهندسة المدنية
الشروط العامة لمقاولات اعمال الهندسة المدنية
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
 
2 سەرەتاکانی دیزاین
2 سەرەتاکانی دیزاین2 سەرەتاکانی دیزاین
2 سەرەتاکانی دیزاین
 
Soil Mechanics (Problems & solutions)
Soil Mechanics (Problems & solutions)Soil Mechanics (Problems & solutions)
Soil Mechanics (Problems & solutions)
 
ڕێبەری بەشە ئەندازیارییەکان
ڕێبەری بەشە ئەندازیارییەکانڕێبەری بەشە ئەندازیارییەکان
ڕێبەری بەشە ئەندازیارییەکان
 
سەرەتاکانی دیزاین
سەرەتاکانی دیزاینسەرەتاکانی دیزاین
سەرەتاکانی دیزاین
 
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیەڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
 
پرۆژەی ناساندنی ئەندازیاری
پرۆژەی ناساندنی ئەندازیاریپرۆژەی ناساندنی ئەندازیاری
پرۆژەی ناساندنی ئەندازیاری
 
بناغە و بنەپایە Footing and Foundation
بناغە و بنەپایە Footing and Foundationبناغە و بنەپایە Footing and Foundation
بناغە و بنەپایە Footing and Foundation
 
slump test سڵەمپ تێست
slump test سڵەمپ تێستslump test سڵەمپ تێست
slump test سڵەمپ تێست
 
Design of Storm Sewer System
Design of Storm Sewer SystemDesign of Storm Sewer System
Design of Storm Sewer System
 
ڕۆنی بزوێنەر
ڕۆنی بزوێنەرڕۆنی بزوێنەر
ڕۆنی بزوێنەر
 

Recently uploaded

Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 

Recently uploaded (20)

Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 

Introduction to Surveying LEVELLING PROCEDURES

  • 1. Erbil Polytechnic University Technical Engineering College Civil Engineering Department Introduction to Surveying 2020-2021. LEVELLING PROCEDURES Prepared by: Asst. Prof. Salar K.Hussein Mr. Kamal Y.Abdullah Asst.Lecturer. Dilveen H. Omar 1
  • 2. Review of levelling • In this lecture we will cover :  Equipment and procedures  Purposes of levelling  Some definitions  Reading a staff  Temporary adjustment of level  Booking and reduction  Methods of booking  Applications 2
  • 3. Leveling:- Leveling defined as an operation for the measurement of the difference in the elevation between points or for the determination of the elevation of certain points above some given plane or surface known as the datum surface , generally is taken as the mean sea level (M S L) 3
  • 4. Leveling Is a type of surveying which is carried out for finding difference in heights in engineering projects. Leveling is required for various purposes such as for calculation of the depth of cutting and fillings, for setting out grades for sewerage and pipe lines, etc. 4
  • 5. Types of Leveling and Application I. Direct Methods : 1. Simple levelling: 2. Compound levelling: 3. Differential or Flying Leveling and Check : Set the equipment at many different places. 4.Contours map by level instrument. 5. Longitudinal , Profile 6.cross-leveling . 7. Reciprocal Leveling. 8. Precise Leveling. 5
  • 6. II. Indirect Leveling If there is a barrier prevent the use of instrument. 1. Trigonometrically, 2. Barometric, Equipment: 1. Level instrument . 2. Tripod 3. Staff 4. Staff bubble 5. 50 m tape measure (sometimes) 6
  • 7. 1. Simple Levelling : - This method Set the instrument at one point and read another point. enables us to determine the difference in level between two points by placing the instrument approximately mid way between the two stations , while taking the readings, the bubble remain in the center as usual. A R.L=100.00 2.200 B.S 2.700 F.S Staff reading at A = 2.200 Height of collimation = 100 + 2.200 = 102.200 Staff reading at B = 2.700 R.L of B = 102.20 - 2.700 = 99.500 m 7
  • 8. 2. Compound Levelling or Differential Levelling :- Set the instrument at one point and read the other points. involves the same process as simple Levelling but in addition, a number of setting of the instrument are required to find out the difference in Levelling between two points in (the case where a single setting cannot serve the purpose), this maybe either due to a large distance. 8
  • 9. 3.Flying Levelling: The reduced levels(RL) of some important points is found, by a few selected setting of the instrument. to get a rough idea of the nature of the ground. 9
  • 10. 4-Contours map A map showing the natural and cultural features as well as showing the nature of the surface of the land (topography of the land) of the up and downs and its representation in (3D)three dimensions. A contour is a line drawn on a plan joining all points of the same height above or below a datum. 10
  • 11. 5. Longitudinal or profile Levelling:- Longitudinal levelling is an operation of doing a levelling job to determine the profile of a ground surface along a given line; this is generally the center line of a purposed alignment, such as railway, highway, canal, and pipeline. The proposed alignment may be a single or series of straight lines connected by curves, the points are selected at a uniform interval. 11
  • 12. 6. Cross-section Levelling:- In longitudinal section the center line is taken, but when a winder belt is required for some engineering project, e.g. highway, railway etc. 12
  • 13. 7.Reciprocal Levelling :- When two station are situated far apart and it is not possible to set up the instrument in between these stations because of a river or deep valley and also not possible to equalize the back sight and fore sight the process of (reciprocal Levelling )is adopted. The method avoid of applying any correction due curvature refraction and imperfect line of collimation. 13
  • 14. 8-Precise Levelling:- Leveling done with at most careful and pre caution and with the most refined instrument to establish the control point is called precise Levelling . A systematic procedure of taking field observation and recording is adopted to minimized and eliminate all sources of error.. 14
  • 15. Level instrument Types of Level Instruments & Parts of level instrument 1. Dumpy Level 2. Tilting Level 3. Automatic Level 4. Electronic Level 5. Hand Level 6-Digital level 15
  • 16. Temporary adjustment of level 1- A suitable position is selected for setting the level from the position it should be possible to take the greatest number of observation without any difficulty the ground should be rightly level and firm. 2- The instrument in fixed on the tripod. 3- The tripod are adjusted according to one’s high. 4- The three foot screw are brought to the center
  • 17. .5- The telescope is placed parallel to any two foot screws and by turning both the two screws either in or out as required. The bubble of the telescope is brought to center 6- The telescope is brought over to the third foot screw by rotating it through 90˚. The bubble is brought to the center by turning the third foot screw only. The procedure is repeated.. till the bubble remains in the center in both the positions. 7- Finally the levelly of the instrument is verified by turning the telescope in any direction when the bubbles remain in the central position for any direction of the telescope the (staff reading are taken)
  • 18. Leveling staves • The rod Is a graduated straight rod made of wooded rod and Aluminium. height of staff (3m, 5m ), used for measuring the vertical distance between the pointes on the ground and the line collimation and rectangular in cross-section. The graduations are units of staff reading (meters , decimeters ,cm and millimeters). The bottom of the staff represents zero reading. All divisions are written in black against white ground, • 18
  • 19. Types of staff, (rod) 1) Solid Staff. 2) Folding Staff. 3-Telescope Staff. 4-Invar Leveling Staff. 5-Aluminium levelling staff. 19
  • 20. Reading an “E -face” staff 0.300 0.33 20
  • 21. What is levelling? • A measurement process where by the Elevation or difference in height between two or more points can be determined. • Levelling is the method, which is used widely, to obtain the elevations (RL) of ground points to a reference datum. 21