SlideShare a Scribd company logo
Page | 1
INTRODUCTION
Levelling is a method to measure the elevation difference between two (2) or more
points. In this practical, focus is shifted to one of levelling techniques namely , fly level
observation or also known as the rise and fall method . The observation will be initiated
from a known reduced level (RL) value of a benchmark (BM) and end at another
known RL value of BM. In between the BMs, a number of change points (CPs) will be
set up to observe the fore sight reading and the back sight reading of each stationed
staves and the values are booked. Upon completion of the observation, the RL values
will be calculated and booked. After the RL values are known, three (3) arithmetical
checks will be calculated to ensure the precision of the works. Consequently, the
adjustment value can be computed where this value will be distributed accordingly to
each station. Finally, the adjusted RL values are booked and the misclosure will be
calculated to be compared with the adjusted values to determine whether the levelling
works is accepted or unsatisfactory.
Page | 2
OBJECTIVE
Objective in this report for :
1. To carry out fly level observation (Rise and Fall method) from bench mark (BM)
to temporary bench mark (TBM).
2. To compute the transferred RL from BM/SBM to TBM.
3. To adjust and check the levelling data.
Page | 3
INSTRUMENT
1. Tripod
2. Staff
3. Level
Page | 4
4. Staff bubble
5. Picket
6. Hammer
Page | 5
PROCEDURE
GENERAL PROCEDURE
1. Adjust the height of the tripod to balanced the level properly.
2. Set the level. Adjust the screw below of the tripod to tighten the level on the
tripod.
3. Adjust the bubble until the bubble stay on the center.
4. Ask your groupmate to hold the staff at the BM, and take the reading.
SPECIFIC PROEDURE
FIGURE 1.1
1. The level is set up at a convenient position, I1. The staff is held on the BM and a
reading is taken. This will be a back sight (BS), because it is the first staff reading
after the levelling instrument has been set up. The length of foresight and back
2. The staff is moved to point A and take reading. This will be a foresight (FS). And
point A will be a change point (CP).
3. Next, the levelling instrument is moved to position I2 and the staff is left at point A
and point B on the change point (CP). The staff is turned so that it faces the level
and a reading is taken. This will be a back sight for point A and fore sight for
point B.
Page | 6
4. Next, the levelling instrument is moved to position I3 and the staff is left at point B
and point C on the change point (CP). The staff is turned so that it faces the level
and a reading is taken. This will be a back sight for point B and fore sight for
point C.
5. The same step is repeated for the position I4. The level instrument is set up and
the reading for both staff at point C and D are taken.
6. While the staff remains at D, the instrument level is moved to another position, I5.
A reading taken from new position to the staff at D and E. D is a BS and E is a
FS.
7. The level moved to position I6 and staff at point E be a BS. The staff at TBM1 be
a FS.
8. The staff is moved to TBM and F in turn and reading taken while the level at I7
Point F will be the FS and TBM will be an BS.
9. When the level is at position I8, the staff have been moved at point F and G. the
point F will be the BS and the G will be the FS.
10.Staff moved to position I9 and the point will be at G and H. The point G will be
the BS and H will be the FS.
11.Move the level at position I10 and move the staff at point I and point H then take
both readings. The BS is point I and FS is point H.
12.The same step for position I11,move the staff at point I and point J and take the
readings.
13.Finally, the level is moved to I12, a BS is point J and FS is the BM. The final staff
position is at a point of known RL. This is most important as all levelling
fieldwork must start and finish at points of known reduced level, otherwise it is
not possible to detect misclosures in the levelling.
Page | 7
RESULT & ANALYSIS
The reading are shown booked by the rise and fall method in table 1.1. These are
normally recorded in a level book containing all the relevant column. Each line of the
level book corresponds to a staff position and this is confirmed by the entries in the
Remarks column. The calculation proceeds in the following manner, in which the
reduced level of a points is related to that of a previous point.
BS IS FS RISE FALL REDUCED
LEVEL
CORRECTION ADJUSTMENT
REDUCED
LEVEL
DISTANCE REMARKS
1.090 12.875 0 12.875 TBM =
12.875
1.127 1.117 0.027 12.848 -0.010 12.838 A
1.118 1.120 0.007 12.855 -0.019 12.836 B
1.129 1.126 0.008 12.847 -0.029 12.818 C
1.118 1.120 0.009 12.856 -0.038 12.818 D
0.290 1.120 0.002 12.854 -0.048 12.806 E
2.162 1.144 0.854 12.000 -0.057 11.943 TBM 2=
11.943
1.180 1.255 0.907 12.907 -0.067 12.840 F
1.230 1.305 0.125 12.782 -0.076 12.706 G
1.412 1.250 0.030 12.812 -0.086 12.726 H
1.261 1.335 0.077 12.889 -0.095 12.794 I
1.155 1.081 0.180 13.069 -0.105 12.964 J
1.235 0.080 12.989 -0.114 12.875 TBM =
12.875
TABLE 1.1
1. From the first BM to A a BS of 1.090 m has been recorded at the BM and FS of
1.117 m at A. The resulting height difference is given by (1.090 m – 1.117 m) = -
0.027 m. The positive sign indicates the fall and is entered at point A.
2. The procedure is repeated and the height difference from A to B is given by
(1.127 m – 1.120 m) = + 0.007 m. This is entered as rise at point B.
Page | 8
3. When calculating the rises or falls in the FS or IS column must be subtracted
from the line immediately above, either in the same column or one column to the
left. The FS is subtracted from the IS or BS in the line above and the BS on the
same line as the FS is the used to continue the calculation with the next IS or FS
in the line below.
4. When the table is complete, a check on the arithmetic involved is possible and
must always be applied. This check is
∑ (BS ) -∑ ( FS ) = ∑ ( RISES ) -∑ ( FALLS ) = RL – ADJUSTMENT RL
5. In table 1.1, the difference between the adjusted RL of the first BM and adjusted
RL of the final BM is 0.00. The result show that the levelling is accurate and
pricise. It is mean that we do not have to make an adjustment.
6. The allowable misclosure for any levelling sequence is allowable misclosure
= ±5√ n mm where n is the number of instrument positions. If the actual value is
greater than the allowable value, the levelling should be repeated. However, if
the actual value is less than the allowable value, the misclosure should be
distributed equally between the instrument positions.
Page | 9
BS IS FS RISE FALL REDUCED
LEVEL
CORRECTION ADJUSTMENT
REDUCED
LEVEL
DISTANCE REMARKS
1.251 11.891 0 11.891 0 TBM=11.891
0.451 0.800 12.691 -0.007 12.684 5 1
0.453 0.002 12.689 -0.007 12.682 10 2
0.448 0.005 12.694 -0.007 12.687 15 3
0.495 0.047 12.647 -0.007 12.640 20 4
0.425 0.070 12.717 -0.007 12.710 25 5
0.452 0.027 12.690 -0.007 12.683 30 6
0.460 0.008 12.682 -0.007 12.675 35 7
0.475 0.015 12.667 -0.007 12.660 40 8
0.483 0.008 12.659 -0.007 12.652 45 9
0.480 0.003 12.662 -0.007 12.655 50 10
1.442 0.472 0.008 12.670 -0.007 12.653 55 11 CP)
2.140 0.698 11.972 -0.014 11.958 62.071 13
2.159 0.019 11.953 -0.014 11.939 67.071 14
2.109 0.050 12.003 -0.014 11.989 72.071 15
2.105 0.004 12.007 -0.014 11.993 77.071 16
2.158 0.053 11.954 -0.014 11.940 82.071 17
2.179 0.021 11.933 -0.014 11.919 87.071 18
2.210 0.031 11.902 -0.014 11.888 92.071 19
2.215 0.005 11.897 -0.014 11.883 97.071 20
1.240 2.190 0.025 11.922 -0.014 11.908 102.071 21 (CP)
1.365 0.125 11.797 -0.02 11.959 109.142 23
1.354 0.011 11.808 -0.02 11.788 114.142 24
1.369 0.015 11.793 -0.02 11.773 119.142 25
1.405 0.036 11.757 -0.02 11.737 124.142 26
1.388 0.017 11.774 -0.02 11.754 129.142 27
1.400 0.012 11.762 -0.02 11.743 134.142 28
1.389 0.011 11.773 -0.02 11.753 139.142 29
1.408 0.019 11.754 -0.02 11.734 144.142 30
1.370 0.038 11.792 -0.02 11.772 149.142 31
1.425 0.055 11.737 -0.02 11.717 154.142 32
1.356 0.069 11.806 -0.02 11.786 159.142 33
1.251 0.105 11.911 -0.02 11.891 164.142 TBM=11.891
TABLE 1.2
Page | 10
COMPUTATION
1. Arimethic checking
FORMULA : ∑ (BS ) -∑ ( FS ) = ∑ ( RISES ) -∑ ( FALLS ) = LAST RL – LAST ARL
3.936 – 3.853 = 1.216 – 1.196 = 11.911 – 11.891 = 0.020
2. Misclosure
FORMULA : (± 5 √ 𝑛) = 𝑛 = 𝑡𝑜𝑡𝑎𝑙 𝑝𝑜𝑠𝑖𝑡𝑖𝑜𝑛 𝑜𝑓 𝑙𝑒𝑣𝑒𝑙
±5√3 = 8.66 𝑚𝑚
FORMULA : (± 0.012 √ 𝐽)𝑚 = 𝐽 = 𝑡𝑜𝑡𝑎𝑙 𝑑𝑖𝑠𝑡𝑎𝑛𝑐𝑒 𝑖𝑛 𝐾𝑀
= (±0.012√0.164)
= ±0.00486
3. Correction
0.02
3
=0.07
Page | 11
CONCLUSION
We manage to carry out fly level observation from Bench Mark (BM) to Temporary
Bench Mark (TBM). All the readings data were booked by the rise and fall method.
Arithmetical check was applied in fly level method for verify the accuracy of calculation.
ƩBS – ƩFS = Ʃ RISES – Ʃ FALLS = LAST RL – LAST ARL is the arithmetical check to
verified the accuracy of calculation. The leveling was done from a known BM to
unknown TBM and reversed to the known BM again. Then we compute the transferred
level from BM to TBM and compute the level back to the BM to checked our data is
correct.
Page | 12
REFERENCES
1. SURVEYING FOR ENGINEERS : J.UREN AND W.F.PRICE : THIRD EDITION :
ISBN 0-333-57705-1 .
2. LECTURE NOTE, PROF SR. DR. HJ. ABD MANAN BIN HJ.SAMAD,
ENGINEERING SURVEYING 1
3. MODUL POLITEKNIK KEMENTERIAN PENDIDIKAN MALAYSIA, C1005 UKUR
KEJURUTERAAN 1 : MOHAMAD KELANA BINTI JUWIT: MOHD FAHMI BIN
ABD RAZAK

More Related Content

What's hot

Sem 2 Site surveying report 2
Sem 2 Site surveying report 2Sem 2 Site surveying report 2
Sem 2 Site surveying report 2
Est
 
Assignment 2 - Traverse
Assignment 2 - TraverseAssignment 2 - Traverse
Assignment 2 - Traverse
Kai Yun Pang
 
Profile and Cross-Section - Report
Profile and Cross-Section - ReportProfile and Cross-Section - Report
Profile and Cross-Section - Report
Sarchia Khursheed
 
SITE SURVEYING: Transversing
SITE SURVEYING: TransversingSITE SURVEYING: Transversing
SITE SURVEYING: Transversing
Farah Sham
 
Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)
Haziq1511
 
Theodolite report
Theodolite reportTheodolite report
Theodolite report
Shze Hwa Lee
 
DCC3113 DETERMINATION OF AGGREGATE IMPACT VALUE.
DCC3113 DETERMINATION OF AGGREGATE IMPACT VALUE.DCC3113 DETERMINATION OF AGGREGATE IMPACT VALUE.
DCC3113 DETERMINATION OF AGGREGATE IMPACT VALUE.
YASMINE HASLAN
 
Curves and there application in Survey
Curves and there application in SurveyCurves and there application in Survey
Curves and there application in Survey
Lord1911
 
Site surveying report1
Site surveying report1Site surveying report1
Site surveying report1
Est
 
Atterberg
AtterbergAtterberg
Atterberg
Natalie Ulza
 
Area and Volume Survey Engineering (RZ)
Area and Volume Survey Engineering (RZ)Area and Volume Survey Engineering (RZ)
Area and Volume Survey Engineering (RZ)
Riezat Zainal
 
Setting out of curve (Survey)
Setting out of curve (Survey)Setting out of curve (Survey)
Setting out of curve (Survey)
Bhavik Patel
 
Tacheometry @surveyingreport
Tacheometry @surveyingreportTacheometry @surveyingreport
Tacheometry @surveyingreport
KiplimoCalvin
 
tacheometric surveying
tacheometric surveyingtacheometric surveying
tacheometric surveying
Mujeeb Muji
 
SLUMP TEST REPORT DCC 2042
SLUMP TEST REPORT DCC 2042 SLUMP TEST REPORT DCC 2042
SLUMP TEST REPORT DCC 2042
YASMINE HASLAN
 
Slump test report
Slump test reportSlump test report
Slump test report
Sanduli Weerasekara
 
Site Surveying Report - Traversing
Site Surveying Report - TraversingSite Surveying Report - Traversing
Site Surveying Report - Traversing
XinYee Khoo
 
Sand replacement
Sand replacementSand replacement
Sand replacement
Natalie Ulza
 
Levelling final
Levelling finalLevelling final
Levelling finalseenyee
 

What's hot (20)

Sem 2 Site surveying report 2
Sem 2 Site surveying report 2Sem 2 Site surveying report 2
Sem 2 Site surveying report 2
 
Assignment 2 - Traverse
Assignment 2 - TraverseAssignment 2 - Traverse
Assignment 2 - Traverse
 
Profile and Cross-Section - Report
Profile and Cross-Section - ReportProfile and Cross-Section - Report
Profile and Cross-Section - Report
 
Probe machintosh
Probe machintoshProbe machintosh
Probe machintosh
 
SITE SURVEYING: Transversing
SITE SURVEYING: TransversingSITE SURVEYING: Transversing
SITE SURVEYING: Transversing
 
Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)
 
Theodolite report
Theodolite reportTheodolite report
Theodolite report
 
DCC3113 DETERMINATION OF AGGREGATE IMPACT VALUE.
DCC3113 DETERMINATION OF AGGREGATE IMPACT VALUE.DCC3113 DETERMINATION OF AGGREGATE IMPACT VALUE.
DCC3113 DETERMINATION OF AGGREGATE IMPACT VALUE.
 
Curves and there application in Survey
Curves and there application in SurveyCurves and there application in Survey
Curves and there application in Survey
 
Site surveying report1
Site surveying report1Site surveying report1
Site surveying report1
 
Atterberg
AtterbergAtterberg
Atterberg
 
Area and Volume Survey Engineering (RZ)
Area and Volume Survey Engineering (RZ)Area and Volume Survey Engineering (RZ)
Area and Volume Survey Engineering (RZ)
 
Setting out of curve (Survey)
Setting out of curve (Survey)Setting out of curve (Survey)
Setting out of curve (Survey)
 
Tacheometry @surveyingreport
Tacheometry @surveyingreportTacheometry @surveyingreport
Tacheometry @surveyingreport
 
tacheometric surveying
tacheometric surveyingtacheometric surveying
tacheometric surveying
 
SLUMP TEST REPORT DCC 2042
SLUMP TEST REPORT DCC 2042 SLUMP TEST REPORT DCC 2042
SLUMP TEST REPORT DCC 2042
 
Slump test report
Slump test reportSlump test report
Slump test report
 
Site Surveying Report - Traversing
Site Surveying Report - TraversingSite Surveying Report - Traversing
Site Surveying Report - Traversing
 
Sand replacement
Sand replacementSand replacement
Sand replacement
 
Levelling final
Levelling finalLevelling final
Levelling final
 

Similar to engineering survey 1 report levelling

LEVELING.pdf
LEVELING.pdfLEVELING.pdf
LEVELING.pdf
pradeep madhuranga
 
Ss report 1
Ss report 1Ss report 1
Ss report 1
Hasif Alias
 
Site surveying report 1
Site surveying report 1Site surveying report 1
Site surveying report 1
Doreen Yeo
 
Fly Levelling
Fly LevellingFly Levelling
Fly Levelling
Bahzad5
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
Phurba Tamang
 
Leveling
Leveling Leveling
Leveling
AlwandBarzani
 
S2 2 leveling
S2 2 levelingS2 2 leveling
S2 2 leveling
Est
 
Levelling
LevellingLevelling
Levelling
Diana Dian
 
Ss report 1 ----levelling eport
Ss report 1 ----levelling eportSs report 1 ----levelling eport
Ss report 1 ----levelling eport
MELVIN tan
 
levelling survey
levelling surveylevelling survey
levelling survey
prashantsingham
 
Site surveying-report-leveling
Site surveying-report-levelingSite surveying-report-leveling
Site surveying-report-levelingXinYee Khoo
 
Site Surveying Report - Traversing
Site Surveying Report - TraversingSite Surveying Report - Traversing
Site Surveying Report - Traversing
XinYee Khoo
 
Site surveying-almost-1
Site surveying-almost-1Site surveying-almost-1
Site surveying-almost-1
Lam Yu
 
Site surveying 1 - done
Site surveying 1 - done Site surveying 1 - done
Site surveying 1 - done
w ss
 
Site surveying 1 - done
Site surveying 1 - done Site surveying 1 - done
Site surveying 1 - done
w ss
 
chapter 3 up to booking method.pdf
chapter 3 up to booking method.pdfchapter 3 up to booking method.pdf
chapter 3 up to booking method.pdf
LeulDamtew
 
SWE 112 soil and water conservation engineering
SWE 112 soil and water conservation engineeringSWE 112 soil and water conservation engineering
SWE 112 soil and water conservation engineering
MelusinaNorwood
 
Activity no 1
Activity no 1Activity no 1
Activity no 1
Ramesh Ranjan
 
Levelling
LevellingLevelling
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument method
Manicka Mamallan Andavar
 

Similar to engineering survey 1 report levelling (20)

LEVELING.pdf
LEVELING.pdfLEVELING.pdf
LEVELING.pdf
 
Ss report 1
Ss report 1Ss report 1
Ss report 1
 
Site surveying report 1
Site surveying report 1Site surveying report 1
Site surveying report 1
 
Fly Levelling
Fly LevellingFly Levelling
Fly Levelling
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
 
Leveling
Leveling Leveling
Leveling
 
S2 2 leveling
S2 2 levelingS2 2 leveling
S2 2 leveling
 
Levelling
LevellingLevelling
Levelling
 
Ss report 1 ----levelling eport
Ss report 1 ----levelling eportSs report 1 ----levelling eport
Ss report 1 ----levelling eport
 
levelling survey
levelling surveylevelling survey
levelling survey
 
Site surveying-report-leveling
Site surveying-report-levelingSite surveying-report-leveling
Site surveying-report-leveling
 
Site Surveying Report - Traversing
Site Surveying Report - TraversingSite Surveying Report - Traversing
Site Surveying Report - Traversing
 
Site surveying-almost-1
Site surveying-almost-1Site surveying-almost-1
Site surveying-almost-1
 
Site surveying 1 - done
Site surveying 1 - done Site surveying 1 - done
Site surveying 1 - done
 
Site surveying 1 - done
Site surveying 1 - done Site surveying 1 - done
Site surveying 1 - done
 
chapter 3 up to booking method.pdf
chapter 3 up to booking method.pdfchapter 3 up to booking method.pdf
chapter 3 up to booking method.pdf
 
SWE 112 soil and water conservation engineering
SWE 112 soil and water conservation engineeringSWE 112 soil and water conservation engineering
SWE 112 soil and water conservation engineering
 
Activity no 1
Activity no 1Activity no 1
Activity no 1
 
Levelling
LevellingLevelling
Levelling
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument method
 

More from YASMINE HASLAN

lab report structure continuous beam
lab report structure continuous beamlab report structure continuous beam
lab report structure continuous beam
YASMINE HASLAN
 
lab report structure deflection of cantilever
lab report structure deflection of cantileverlab report structure deflection of cantilever
lab report structure deflection of cantilever
YASMINE HASLAN
 
LAB REPORT SHEAR FORCE IN A BEAM
LAB REPORT SHEAR FORCE IN A BEAMLAB REPORT SHEAR FORCE IN A BEAM
LAB REPORT SHEAR FORCE IN A BEAM
YASMINE HASLAN
 
PAST YEAR DCC5183; project management and practices DISEMBER2015
PAST YEAR DCC5183; project management and practices DISEMBER2015PAST YEAR DCC5183; project management and practices DISEMBER2015
PAST YEAR DCC5183; project management and practices DISEMBER2015
YASMINE HASLAN
 
LAB REPORT HYDRAULIC EXP 1 : PROPERTIES OF FLUID.
LAB REPORT HYDRAULIC EXP 1 : PROPERTIES OF FLUID.LAB REPORT HYDRAULIC EXP 1 : PROPERTIES OF FLUID.
LAB REPORT HYDRAULIC EXP 1 : PROPERTIES OF FLUID.
YASMINE HASLAN
 
PRESENTATION MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK
PRESENTATION MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK PRESENTATION MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK
PRESENTATION MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK
YASMINE HASLAN
 
MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK
MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIKMINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK
MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK
YASMINE HASLAN
 
Determination of elongation index
Determination of elongation indexDetermination of elongation index
Determination of elongation index
YASMINE HASLAN
 
determination of flakiness index test.
determination of flakiness index test. determination of flakiness index test.
determination of flakiness index test.
YASMINE HASLAN
 
Sieve test
Sieve testSieve test
Sieve test
YASMINE HASLAN
 
Silt test
Silt testSilt test
Silt test
YASMINE HASLAN
 
Softhening point REPORT DCC2042
Softhening point REPORT DCC2042 Softhening point REPORT DCC2042
Softhening point REPORT DCC2042
YASMINE HASLAN
 
Soalan peperiksaan akhir jun 2015
Soalan peperiksaan akhir jun 2015Soalan peperiksaan akhir jun 2015
Soalan peperiksaan akhir jun 2015
YASMINE HASLAN
 
Soalan peperiksaan akhir politeknik dbm1013 dis 2015
Soalan peperiksaan akhir  politeknik dbm1013  dis 2015Soalan peperiksaan akhir  politeknik dbm1013  dis 2015
Soalan peperiksaan akhir politeknik dbm1013 dis 2015
YASMINE HASLAN
 
Peperiksaan akhir dis2014 dbm1013
Peperiksaan akhir dis2014 dbm1013Peperiksaan akhir dis2014 dbm1013
Peperiksaan akhir dis2014 dbm1013
YASMINE HASLAN
 
Report waste water
Report waste waterReport waste water
Report waste water
YASMINE HASLAN
 
Report kayu
Report kayuReport kayu
Report kayu
YASMINE HASLAN
 
Carpentry labsheet polimas
Carpentry labsheet  polimasCarpentry labsheet  polimas
Carpentry labsheet polimas
YASMINE HASLAN
 
Lukisan bangunan
Lukisan bangunanLukisan bangunan
Lukisan bangunan
YASMINE HASLAN
 
Garden chair cutting list
Garden chair  cutting listGarden chair  cutting list
Garden chair cutting list
YASMINE HASLAN
 

More from YASMINE HASLAN (20)

lab report structure continuous beam
lab report structure continuous beamlab report structure continuous beam
lab report structure continuous beam
 
lab report structure deflection of cantilever
lab report structure deflection of cantileverlab report structure deflection of cantilever
lab report structure deflection of cantilever
 
LAB REPORT SHEAR FORCE IN A BEAM
LAB REPORT SHEAR FORCE IN A BEAMLAB REPORT SHEAR FORCE IN A BEAM
LAB REPORT SHEAR FORCE IN A BEAM
 
PAST YEAR DCC5183; project management and practices DISEMBER2015
PAST YEAR DCC5183; project management and practices DISEMBER2015PAST YEAR DCC5183; project management and practices DISEMBER2015
PAST YEAR DCC5183; project management and practices DISEMBER2015
 
LAB REPORT HYDRAULIC EXP 1 : PROPERTIES OF FLUID.
LAB REPORT HYDRAULIC EXP 1 : PROPERTIES OF FLUID.LAB REPORT HYDRAULIC EXP 1 : PROPERTIES OF FLUID.
LAB REPORT HYDRAULIC EXP 1 : PROPERTIES OF FLUID.
 
PRESENTATION MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK
PRESENTATION MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK PRESENTATION MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK
PRESENTATION MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK
 
MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK
MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIKMINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK
MINI PROJECT STATISTIC SEMESTER 3 POLITEKNIK
 
Determination of elongation index
Determination of elongation indexDetermination of elongation index
Determination of elongation index
 
determination of flakiness index test.
determination of flakiness index test. determination of flakiness index test.
determination of flakiness index test.
 
Sieve test
Sieve testSieve test
Sieve test
 
Silt test
Silt testSilt test
Silt test
 
Softhening point REPORT DCC2042
Softhening point REPORT DCC2042 Softhening point REPORT DCC2042
Softhening point REPORT DCC2042
 
Soalan peperiksaan akhir jun 2015
Soalan peperiksaan akhir jun 2015Soalan peperiksaan akhir jun 2015
Soalan peperiksaan akhir jun 2015
 
Soalan peperiksaan akhir politeknik dbm1013 dis 2015
Soalan peperiksaan akhir  politeknik dbm1013  dis 2015Soalan peperiksaan akhir  politeknik dbm1013  dis 2015
Soalan peperiksaan akhir politeknik dbm1013 dis 2015
 
Peperiksaan akhir dis2014 dbm1013
Peperiksaan akhir dis2014 dbm1013Peperiksaan akhir dis2014 dbm1013
Peperiksaan akhir dis2014 dbm1013
 
Report waste water
Report waste waterReport waste water
Report waste water
 
Report kayu
Report kayuReport kayu
Report kayu
 
Carpentry labsheet polimas
Carpentry labsheet  polimasCarpentry labsheet  polimas
Carpentry labsheet polimas
 
Lukisan bangunan
Lukisan bangunanLukisan bangunan
Lukisan bangunan
 
Garden chair cutting list
Garden chair  cutting listGarden chair  cutting list
Garden chair cutting list
 

Recently uploaded

aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
Scholarhat
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
Mohammed Sikander
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
Wasim Ak
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
chanes7
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
Kartik Tiwari
 
Group Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana BuscigliopptxGroup Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana Buscigliopptx
ArianaBusciglio
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Marketing internship report file for MBA
Marketing internship report file for MBAMarketing internship report file for MBA
Marketing internship report file for MBA
gb193092
 

Recently uploaded (20)

aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
 
Group Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana BuscigliopptxGroup Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana Buscigliopptx
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Marketing internship report file for MBA
Marketing internship report file for MBAMarketing internship report file for MBA
Marketing internship report file for MBA
 

engineering survey 1 report levelling

  • 1. Page | 1 INTRODUCTION Levelling is a method to measure the elevation difference between two (2) or more points. In this practical, focus is shifted to one of levelling techniques namely , fly level observation or also known as the rise and fall method . The observation will be initiated from a known reduced level (RL) value of a benchmark (BM) and end at another known RL value of BM. In between the BMs, a number of change points (CPs) will be set up to observe the fore sight reading and the back sight reading of each stationed staves and the values are booked. Upon completion of the observation, the RL values will be calculated and booked. After the RL values are known, three (3) arithmetical checks will be calculated to ensure the precision of the works. Consequently, the adjustment value can be computed where this value will be distributed accordingly to each station. Finally, the adjusted RL values are booked and the misclosure will be calculated to be compared with the adjusted values to determine whether the levelling works is accepted or unsatisfactory.
  • 2. Page | 2 OBJECTIVE Objective in this report for : 1. To carry out fly level observation (Rise and Fall method) from bench mark (BM) to temporary bench mark (TBM). 2. To compute the transferred RL from BM/SBM to TBM. 3. To adjust and check the levelling data.
  • 3. Page | 3 INSTRUMENT 1. Tripod 2. Staff 3. Level
  • 4. Page | 4 4. Staff bubble 5. Picket 6. Hammer
  • 5. Page | 5 PROCEDURE GENERAL PROCEDURE 1. Adjust the height of the tripod to balanced the level properly. 2. Set the level. Adjust the screw below of the tripod to tighten the level on the tripod. 3. Adjust the bubble until the bubble stay on the center. 4. Ask your groupmate to hold the staff at the BM, and take the reading. SPECIFIC PROEDURE FIGURE 1.1 1. The level is set up at a convenient position, I1. The staff is held on the BM and a reading is taken. This will be a back sight (BS), because it is the first staff reading after the levelling instrument has been set up. The length of foresight and back 2. The staff is moved to point A and take reading. This will be a foresight (FS). And point A will be a change point (CP). 3. Next, the levelling instrument is moved to position I2 and the staff is left at point A and point B on the change point (CP). The staff is turned so that it faces the level and a reading is taken. This will be a back sight for point A and fore sight for point B.
  • 6. Page | 6 4. Next, the levelling instrument is moved to position I3 and the staff is left at point B and point C on the change point (CP). The staff is turned so that it faces the level and a reading is taken. This will be a back sight for point B and fore sight for point C. 5. The same step is repeated for the position I4. The level instrument is set up and the reading for both staff at point C and D are taken. 6. While the staff remains at D, the instrument level is moved to another position, I5. A reading taken from new position to the staff at D and E. D is a BS and E is a FS. 7. The level moved to position I6 and staff at point E be a BS. The staff at TBM1 be a FS. 8. The staff is moved to TBM and F in turn and reading taken while the level at I7 Point F will be the FS and TBM will be an BS. 9. When the level is at position I8, the staff have been moved at point F and G. the point F will be the BS and the G will be the FS. 10.Staff moved to position I9 and the point will be at G and H. The point G will be the BS and H will be the FS. 11.Move the level at position I10 and move the staff at point I and point H then take both readings. The BS is point I and FS is point H. 12.The same step for position I11,move the staff at point I and point J and take the readings. 13.Finally, the level is moved to I12, a BS is point J and FS is the BM. The final staff position is at a point of known RL. This is most important as all levelling fieldwork must start and finish at points of known reduced level, otherwise it is not possible to detect misclosures in the levelling.
  • 7. Page | 7 RESULT & ANALYSIS The reading are shown booked by the rise and fall method in table 1.1. These are normally recorded in a level book containing all the relevant column. Each line of the level book corresponds to a staff position and this is confirmed by the entries in the Remarks column. The calculation proceeds in the following manner, in which the reduced level of a points is related to that of a previous point. BS IS FS RISE FALL REDUCED LEVEL CORRECTION ADJUSTMENT REDUCED LEVEL DISTANCE REMARKS 1.090 12.875 0 12.875 TBM = 12.875 1.127 1.117 0.027 12.848 -0.010 12.838 A 1.118 1.120 0.007 12.855 -0.019 12.836 B 1.129 1.126 0.008 12.847 -0.029 12.818 C 1.118 1.120 0.009 12.856 -0.038 12.818 D 0.290 1.120 0.002 12.854 -0.048 12.806 E 2.162 1.144 0.854 12.000 -0.057 11.943 TBM 2= 11.943 1.180 1.255 0.907 12.907 -0.067 12.840 F 1.230 1.305 0.125 12.782 -0.076 12.706 G 1.412 1.250 0.030 12.812 -0.086 12.726 H 1.261 1.335 0.077 12.889 -0.095 12.794 I 1.155 1.081 0.180 13.069 -0.105 12.964 J 1.235 0.080 12.989 -0.114 12.875 TBM = 12.875 TABLE 1.1 1. From the first BM to A a BS of 1.090 m has been recorded at the BM and FS of 1.117 m at A. The resulting height difference is given by (1.090 m – 1.117 m) = - 0.027 m. The positive sign indicates the fall and is entered at point A. 2. The procedure is repeated and the height difference from A to B is given by (1.127 m – 1.120 m) = + 0.007 m. This is entered as rise at point B.
  • 8. Page | 8 3. When calculating the rises or falls in the FS or IS column must be subtracted from the line immediately above, either in the same column or one column to the left. The FS is subtracted from the IS or BS in the line above and the BS on the same line as the FS is the used to continue the calculation with the next IS or FS in the line below. 4. When the table is complete, a check on the arithmetic involved is possible and must always be applied. This check is ∑ (BS ) -∑ ( FS ) = ∑ ( RISES ) -∑ ( FALLS ) = RL – ADJUSTMENT RL 5. In table 1.1, the difference between the adjusted RL of the first BM and adjusted RL of the final BM is 0.00. The result show that the levelling is accurate and pricise. It is mean that we do not have to make an adjustment. 6. The allowable misclosure for any levelling sequence is allowable misclosure = ±5√ n mm where n is the number of instrument positions. If the actual value is greater than the allowable value, the levelling should be repeated. However, if the actual value is less than the allowable value, the misclosure should be distributed equally between the instrument positions.
  • 9. Page | 9 BS IS FS RISE FALL REDUCED LEVEL CORRECTION ADJUSTMENT REDUCED LEVEL DISTANCE REMARKS 1.251 11.891 0 11.891 0 TBM=11.891 0.451 0.800 12.691 -0.007 12.684 5 1 0.453 0.002 12.689 -0.007 12.682 10 2 0.448 0.005 12.694 -0.007 12.687 15 3 0.495 0.047 12.647 -0.007 12.640 20 4 0.425 0.070 12.717 -0.007 12.710 25 5 0.452 0.027 12.690 -0.007 12.683 30 6 0.460 0.008 12.682 -0.007 12.675 35 7 0.475 0.015 12.667 -0.007 12.660 40 8 0.483 0.008 12.659 -0.007 12.652 45 9 0.480 0.003 12.662 -0.007 12.655 50 10 1.442 0.472 0.008 12.670 -0.007 12.653 55 11 CP) 2.140 0.698 11.972 -0.014 11.958 62.071 13 2.159 0.019 11.953 -0.014 11.939 67.071 14 2.109 0.050 12.003 -0.014 11.989 72.071 15 2.105 0.004 12.007 -0.014 11.993 77.071 16 2.158 0.053 11.954 -0.014 11.940 82.071 17 2.179 0.021 11.933 -0.014 11.919 87.071 18 2.210 0.031 11.902 -0.014 11.888 92.071 19 2.215 0.005 11.897 -0.014 11.883 97.071 20 1.240 2.190 0.025 11.922 -0.014 11.908 102.071 21 (CP) 1.365 0.125 11.797 -0.02 11.959 109.142 23 1.354 0.011 11.808 -0.02 11.788 114.142 24 1.369 0.015 11.793 -0.02 11.773 119.142 25 1.405 0.036 11.757 -0.02 11.737 124.142 26 1.388 0.017 11.774 -0.02 11.754 129.142 27 1.400 0.012 11.762 -0.02 11.743 134.142 28 1.389 0.011 11.773 -0.02 11.753 139.142 29 1.408 0.019 11.754 -0.02 11.734 144.142 30 1.370 0.038 11.792 -0.02 11.772 149.142 31 1.425 0.055 11.737 -0.02 11.717 154.142 32 1.356 0.069 11.806 -0.02 11.786 159.142 33 1.251 0.105 11.911 -0.02 11.891 164.142 TBM=11.891 TABLE 1.2
  • 10. Page | 10 COMPUTATION 1. Arimethic checking FORMULA : ∑ (BS ) -∑ ( FS ) = ∑ ( RISES ) -∑ ( FALLS ) = LAST RL – LAST ARL 3.936 – 3.853 = 1.216 – 1.196 = 11.911 – 11.891 = 0.020 2. Misclosure FORMULA : (± 5 √ 𝑛) = 𝑛 = 𝑡𝑜𝑡𝑎𝑙 𝑝𝑜𝑠𝑖𝑡𝑖𝑜𝑛 𝑜𝑓 𝑙𝑒𝑣𝑒𝑙 ±5√3 = 8.66 𝑚𝑚 FORMULA : (± 0.012 √ 𝐽)𝑚 = 𝐽 = 𝑡𝑜𝑡𝑎𝑙 𝑑𝑖𝑠𝑡𝑎𝑛𝑐𝑒 𝑖𝑛 𝐾𝑀 = (±0.012√0.164) = ±0.00486 3. Correction 0.02 3 =0.07
  • 11. Page | 11 CONCLUSION We manage to carry out fly level observation from Bench Mark (BM) to Temporary Bench Mark (TBM). All the readings data were booked by the rise and fall method. Arithmetical check was applied in fly level method for verify the accuracy of calculation. ƩBS – ƩFS = Ʃ RISES – Ʃ FALLS = LAST RL – LAST ARL is the arithmetical check to verified the accuracy of calculation. The leveling was done from a known BM to unknown TBM and reversed to the known BM again. Then we compute the transferred level from BM to TBM and compute the level back to the BM to checked our data is correct.
  • 12. Page | 12 REFERENCES 1. SURVEYING FOR ENGINEERS : J.UREN AND W.F.PRICE : THIRD EDITION : ISBN 0-333-57705-1 . 2. LECTURE NOTE, PROF SR. DR. HJ. ABD MANAN BIN HJ.SAMAD, ENGINEERING SURVEYING 1 3. MODUL POLITEKNIK KEMENTERIAN PENDIDIKAN MALAYSIA, C1005 UKUR KEJURUTERAAN 1 : MOHAMAD KELANA BINTI JUWIT: MOHD FAHMI BIN ABD RAZAK