In this pdf one can get the different types of equipment used in surface mines which is very important from the examination point of view. important regulations are also included in this .
rock excavation, different open cast or open pit excavation machinery, application, limitations, highwall miner, bucket wheel excavatorr, bucket chain excavator, shovels
An analysis of the dumper cycle time and its implications on the overall productivity of the concerned mine.
This project was carried out while the author was a summer trainee at the Katamati Iron Ore Mines, Orissa, India. The mine was owned by Tata Steel Ltd. at the time of the project period and was one of the most efficient open cast iron ore mines in India.
In this pdf one can get the different types of equipment used in surface mines which is very important from the examination point of view. important regulations are also included in this .
rock excavation, different open cast or open pit excavation machinery, application, limitations, highwall miner, bucket wheel excavatorr, bucket chain excavator, shovels
An analysis of the dumper cycle time and its implications on the overall productivity of the concerned mine.
This project was carried out while the author was a summer trainee at the Katamati Iron Ore Mines, Orissa, India. The mine was owned by Tata Steel Ltd. at the time of the project period and was one of the most efficient open cast iron ore mines in India.
It's a case Study for High wall Mining thats done in SCCL.
Also you can find awesome videos related to Mining activities in my YOUTUBE CHANNEL i.e. Knowledge Stuff. Please SUBSCRIBE my channel. My youtube link is given below:-
https://www.youtube.com/channel/UCKgkj6M1M-AWlonTzn_51Gw
Also there are some videos you may like:-
HIGHWALL Mining in INDIA :-
https://www.youtube.com/watch?v=uqlmBm81aIw
Drilling and Blasting Videos at Bauxite OCP - https://www.youtube.com/watch?v=dNwSZq5T3bg
Biggest Dragline Excavator in INDIA -
https://www.youtube.com/watch?v=FLg6ZPtfzHs
A typical day at an OPEN cast mine :-
https://www.youtube.com/watch?v=JYeqqX7BaTw
I hope you like it and share it.
Shovel and dumper combination is a type of heavy equipment used in open cast mining operations. It is composed of two separate machines, a front-end loader (shovel) and a backhoe (dumper). The shovel is used to scoop ore, rock, or other materials out of the mine, while the dumper carries the load to a designated area for further processing. This combination of machines allows for faster and more efficient mining operations, as the shovel can quickly scoop up large quantities of material, while the dumper can move the load quickly and safely. The shovel and dumper combination is an indispensable asset for any open cast mine, allowing for fast, efficient, and safe extraction of materials.
Its a presentation about the design aspect of open cast mine. The author believes it will surely help the mining engineering students at the beginning level.
Presentation economic assessment copper rotorsLeonardo ENERGY
Economic assessment for copper rotor induction motors compared to aluminium rotor technology. For a given efficiency level, copper rotor technology offers a reduced size and weight, that translates into savings in electrical steel and a positive economic case for this technology.
Study carried out by Aquila University
It's a case Study for High wall Mining thats done in SCCL.
Also you can find awesome videos related to Mining activities in my YOUTUBE CHANNEL i.e. Knowledge Stuff. Please SUBSCRIBE my channel. My youtube link is given below:-
https://www.youtube.com/channel/UCKgkj6M1M-AWlonTzn_51Gw
Also there are some videos you may like:-
HIGHWALL Mining in INDIA :-
https://www.youtube.com/watch?v=uqlmBm81aIw
Drilling and Blasting Videos at Bauxite OCP - https://www.youtube.com/watch?v=dNwSZq5T3bg
Biggest Dragline Excavator in INDIA -
https://www.youtube.com/watch?v=FLg6ZPtfzHs
A typical day at an OPEN cast mine :-
https://www.youtube.com/watch?v=JYeqqX7BaTw
I hope you like it and share it.
Shovel and dumper combination is a type of heavy equipment used in open cast mining operations. It is composed of two separate machines, a front-end loader (shovel) and a backhoe (dumper). The shovel is used to scoop ore, rock, or other materials out of the mine, while the dumper carries the load to a designated area for further processing. This combination of machines allows for faster and more efficient mining operations, as the shovel can quickly scoop up large quantities of material, while the dumper can move the load quickly and safely. The shovel and dumper combination is an indispensable asset for any open cast mine, allowing for fast, efficient, and safe extraction of materials.
Its a presentation about the design aspect of open cast mine. The author believes it will surely help the mining engineering students at the beginning level.
Presentation economic assessment copper rotorsLeonardo ENERGY
Economic assessment for copper rotor induction motors compared to aluminium rotor technology. For a given efficiency level, copper rotor technology offers a reduced size and weight, that translates into savings in electrical steel and a positive economic case for this technology.
Study carried out by Aquila University
Performance Evaluation of 830kW Wind Turbine and an Analysis of Various Param...Rohan Raibagkar
The project aimed at
1) Understanding the performance of wind power project of 830KW
2) Determining system reliability (Grid availability, Machine availability, System availability) and
operating hours of the wind conversion system from the data obtained at site
3) Analyzing the effect of various parameters like velocity, blade length, temperature, pressure, air
density on the power generation of a wind turbine
4) Forecasting or Predicting the performance of the wind turbine generators based on the above
parameters
This analysis can be used to existing sites which are nearby the above evaluated wind power project for Maximizing power generation
It helps us to understand effect of various parameters viz. air density, air pressure, air temperature, blade length, velocity on the power generation
According to the results, there is a high effect of air characteristics on the mechanical power.
The environment’s parameter has a massive effect on the generated power, which will lead the researchers to concentrate on it with highest priority
Complete one year data was used for the analysis of the wind power project
Results were executed using Matlab
International Journal of Engineering and Science Invention (IJESI) is an international journal intended for professionals and researchers in all fields of computer science and electronics. IJESI publishes research articles and reviews within the whole field Engineering Science and Technology, new teaching methods, assessment, validation and the impact of new technologies and it will continue to provide information on the latest trends and developments in this ever-expanding subject. The publications of papers are selected through double peer reviewed to ensure originality, relevance, and readability. The articles published in our journal can be accessed online.
Synthetic Fiber Construction in lab .pptxPavel ( NSTU)
Synthetic fiber production is a fascinating and complex field that blends chemistry, engineering, and environmental science. By understanding these aspects, students can gain a comprehensive view of synthetic fiber production, its impact on society and the environment, and the potential for future innovations. Synthetic fibers play a crucial role in modern society, impacting various aspects of daily life, industry, and the environment. ynthetic fibers are integral to modern life, offering a range of benefits from cost-effectiveness and versatility to innovative applications and performance characteristics. While they pose environmental challenges, ongoing research and development aim to create more sustainable and eco-friendly alternatives. Understanding the importance of synthetic fibers helps in appreciating their role in the economy, industry, and daily life, while also emphasizing the need for sustainable practices and innovation.
Macroeconomics- Movie Location
This will be used as part of your Personal Professional Portfolio once graded.
Objective:
Prepare a presentation or a paper using research, basic comparative analysis, data organization and application of economic information. You will make an informed assessment of an economic climate outside of the United States to accomplish an entertainment industry objective.
Model Attribute Check Company Auto PropertyCeline George
In Odoo, the multi-company feature allows you to manage multiple companies within a single Odoo database instance. Each company can have its own configurations while still sharing common resources such as products, customers, and suppliers.
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdfTechSoup
In this webinar you will learn how your organization can access TechSoup's wide variety of product discount and donation programs. From hardware to software, we'll give you a tour of the tools available to help your nonprofit with productivity, collaboration, financial management, donor tracking, security, and more.
Operation “Blue Star” is the only event in the history of Independent India where the state went into war with its own people. Even after about 40 years it is not clear if it was culmination of states anger over people of the region, a political game of power or start of dictatorial chapter in the democratic setup.
The people of Punjab felt alienated from main stream due to denial of their just demands during a long democratic struggle since independence. As it happen all over the word, it led to militant struggle with great loss of lives of military, police and civilian personnel. Killing of Indira Gandhi and massacre of innocent Sikhs in Delhi and other India cities was also associated with this movement.
A Strategic Approach: GenAI in EducationPeter Windle
Artificial Intelligence (AI) technologies such as Generative AI, Image Generators and Large Language Models have had a dramatic impact on teaching, learning and assessment over the past 18 months. The most immediate threat AI posed was to Academic Integrity with Higher Education Institutes (HEIs) focusing their efforts on combating the use of GenAI in assessment. Guidelines were developed for staff and students, policies put in place too. Innovative educators have forged paths in the use of Generative AI for teaching, learning and assessments leading to pockets of transformation springing up across HEIs, often with little or no top-down guidance, support or direction.
This Gasta posits a strategic approach to integrating AI into HEIs to prepare staff, students and the curriculum for an evolving world and workplace. We will highlight the advantages of working with these technologies beyond the realm of teaching, learning and assessment by considering prompt engineering skills, industry impact, curriculum changes, and the need for staff upskilling. In contrast, not engaging strategically with Generative AI poses risks, including falling behind peers, missed opportunities and failing to ensure our graduates remain employable. The rapid evolution of AI technologies necessitates a proactive and strategic approach if we are to remain relevant.
How to Make a Field invisible in Odoo 17Celine George
It is possible to hide or invisible some fields in odoo. Commonly using “invisible” attribute in the field definition to invisible the fields. This slide will show how to make a field invisible in odoo 17.
Read| The latest issue of The Challenger is here! We are thrilled to announce that our school paper has qualified for the NATIONAL SCHOOLS PRESS CONFERENCE (NSPC) 2024. Thank you for your unwavering support and trust. Dive into the stories that made us stand out!
Francesca Gottschalk - How can education support child empowerment.pptxEduSkills OECD
Francesca Gottschalk from the OECD’s Centre for Educational Research and Innovation presents at the Ask an Expert Webinar: How can education support child empowerment?
Francesca Gottschalk - How can education support child empowerment.pptx
Analysing shovel dumper productivity for coal mine
1.
2.
3. To estimate normative productivity of shovel-
dumper combination with different material
characteristic and different equipment
combination.
To validate the normative productivity with the
actual productivity of similar equipment
combination in certain selected coal mine.
To analyse the reasons for variation between
normal and actual productivity in different cases.
To give suggestion for improvement in the
productivity of shovel dumper system.
4. The study was conducted for sonepur bazari of ECL
considering the actual performance data of 2011-
12 for Shovel-Dumper operation.
The project deploys both departmental and hired
equipments. The study was only conducted for
departmental equipment(Shovel-Dumper).
The productivity of shovel dumper considered in
approved project report of sonepur bazari
OCP(3.4mt capacity) was compared with the actual
shovel-Dumper productivity obtained in the mine.
7. Category of the
material to be
excavated
Cycle time (Minutes)
for 90 degree swing
angle
Cycle time(Minutes)
for 180 degree swing
angle
I .44 .55
II .47 .58
III .50 .61
IV .53 .64
V .56 .67
8. Category of the
material to be
excavated
Cycle time (Minutes)
for 90 degree swing
angle
Cycle time(Minutes)
for 180 degree swing
angle
I .42 .49
II .44 .51
III .46 .53
IV .48 .55
V .50 .57
9. Category of the
material to be
excavated
Fill factor for 3cubic
mt. bucket
Fill factor for 13cubic
mt. bucket
I .95 1.05
II .925 1.025
III .90 1.00
IV .875 .99
V 85. .95
14. Calculation for productivity of shovel and
dumper
SL. No. Particulars 10 cu.m. Electric rope
shove+120 ton. Dumper
1 Dumper pay load(Tns) 108.970
2 Assumed category of rock 50% of category III+50%
of category IV
3 Swell factor 0.719
4 Bucket fill factor 0.958
5 Swell cum bucket fill factor(3x4) 0.689
6 Bucket capacity(CUM) 10.000
7 Solid bucket capacity(5x6 CUM) 6.898
15. SL. No. Particulars 10 cu.m. Electric rope
shove+120 ton.
Dumper
8 Volume weight(TE/CUM) 2.4(Assumed)
9 Solid capacity of Dumper for Full pay
load (1/8 CUM)
45.404
10 Loose capacity of Dumper for pay-
Load(9/3 CUM)
63.149
11
11A
Struck capacity of Dumper(CUM)
Heaped capacity of Dumper(CUM)
60.000
80.000
12 Solid capacity of Dumper(cum.) 41.340
13 Number of buckets per Dumper(12/7) 5.99=6
14 Load per Dumper(13*7 CUM) 41.34
16. SL.
No.
Particulars 10 cu.m. Electric rope
shove+120 ton.
Dumper
15 Bucket cycle time (MIN.) 0.625
16 Direct Loading time
(13x15MIN.)
3.750
17 Time for placement of 1
Dumper(MIN.)
0.600
18 Total time for loading 1
Dumper (16+17 Min.)
4.350
19 Hourly output per
Shovel(60x14/18 cum)
570.207
20 Factor for travel, position etc. 0.80
21 Average standard hourly
output(19x20Cum.)
456.166
17. SL. No. Particulars 10 cu.m. Electric rope
shove+120 ton.
Dumper
22 Spotting, Loading, Waiting time
(min.)
3.4
23 Annual Shift hours 7200
24 Average standard utilisation % 58
25 Average standard utilised hours 4158
26 Annual output/Shovel(25x21
M.cum.)
1.897
27 Annual productivity adopted for
project planning/Shovel(M.Cum.)
1.890
18. Sl.
NO.
Details Unit 10. cum. Electric shovel with 120 ton.
Dumper.
1 Lead KMS 0.5 1.0 1.5 2.0 2.5 3.0
3.5
2 Average Dumper speed KM/H
R
13 16 18 20 22 23
24
3 Dumper travel time Minut
es
4.615 7.5 10 12 13.636
15.652 17.5
4 Dumper spotting,
unloading and waiting
time
Minut
es
3.4 3.4 3.4 3.4 3.4
3.4 3.4
5 Dumper loading time Minut
es
3.75 3.75 3.75 3.75 3.75
3.75 3.75
6 Total Dumper cycle time Minut
es
11.765 14.650 17.150 19.150
20.786 22.802 24.65
7
8
Total Dumper loading time
No. of Dumpers to work
MIN.
UNIT
4.35 4.35 4.35 4.35 4.35
4.35 4.35
19. Sl.
No.
Details Uni
ts
10. cum. Electric shovel with
120 ton. Dumper.
9 Working Dumper
avalibality
% 67 67 67 67 67 67
67
10 Population of dumpers
with 1 working shovel
(8/9)
Nos. 4.037 5.027 5.885 6.570 7.131 7.821
8.448
11 Annual productivity of
dumper
M.C
UM.
0.4682 0.3760 0.3212 0.2877 0.2650
0.2417 0.2237
20. Unit
Total Out
source
d
dept.
Coal Mt 5.15 1.75 3.4
OB
S/D Mcum 23.1 14.6 8.5
D/L 3.04 3.04
TOTAL 26.14 14.6 11.5
4
Sp.Gr 1.4 t/cum
Stripping ratio 5.07 cum/t
SONEPUR BAZARI Project report data
21. System factor as in Project
Report
Machine Work load
as in PR
Digging
capacity as
in PR
System
factor
Shovel 10.9286 18.01 0.6068
22. LEAD COAL 3
KMOB 2.5
Wt LEAD 2.61111111
Lead from operational plan for 2011-12
26. EQIPMEN
T
Total Trips Productivity
COAL OB
TOTAL
(CU.
M.)
Assessed cap.( M. Cum.) %
Ach.35T 50T 120
T
35
T
50
T
120T UNIT
CAP.
ROLL
TOTAL
CAP.
10 cum.
shovel
0 4099 7867 0 8264 127160 5598758 1.89 6 11.34 49.37
5/4.6 Cum.
shovel 0 644 0 0 9961 0 210490 0.89 2 1.78 11.83
Hyd. Shovel
TOTAL 0 62166 193 0 25716 0 1608980 3.57 45.13
DUMPER -
WISE
0 66909 8060 0 43941 127160 7418228 13.35 55.57
35t 0 0 0 0.095 2 0.18 0.00
50t 66909 43941 2049728 0.118 24.5 2.90 70.66
120t 8060 127160 5368500 0.311 33 10.27 52.28
27. General analysis:-
(1)No. of days
(2)System factor is itself less
Reasons:-
Shovel idle hours:-
(A)Management factors-
Delay in starting of shift.
Delay in return from Tiffin break.
Early ending of shift.
(B)External factors(Stoppage of Shovel)
Land dispute with villagers
Short supply of explosives.
Power supply
28. (C)Job factors:-
Low explosive supply(Hourly productivity)
Frequent blasting
Inexperienced operator
Improper fragmentation
Maintenance and breakdown of Shovel
Maintenance schedule is not followed.
Poor spare management and delay in procurement of spares.
Dumper Analysis:-
(A)Extra Dumper
(B)Haulage road –High gradient than 1in16
-Not paved
-Slushy due to rain and alluvium layer.
29. System factor should not be lower than 0.85.
Dumper factor should be equal to1.
Separate equipments to be used for COAL/OB.
Hot seat change to be implemented.
Maintenance to be outsourced to the company.
Haulage road consideration.
Blasting should be in big rounds.
Miscellaneous issues (like land, explosive,
power)should be resolved.