Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) (Fourth Amendment) Regulations, 2018 effective from 01.01.2019
Transmission Deviation charges are payable by regional utilities for deviating by over-injecting or over- drawing power beyond the total approved open access ,ie sum total of Long Term Injection/Drawal Access, Medium Term Injection/Drawal Open Access and Short Term Injection/Drawak Open Access.
Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) (Fourth Amendment) Regulations, 2018 effective from 01.01.2019
Transmission Deviation charges are payable by regional utilities for deviating by over-injecting or over- drawing power beyond the total approved open access ,ie sum total of Long Term Injection/Drawal Access, Medium Term Injection/Drawal Open Access and Short Term Injection/Drawak Open Access.
The document covers the newly implemented regulation "Deviation settlement and mechanism" by CERC (central electricity regulatory commission.
This regulation has replaced the UI Regulation and mechanism.
Central Electricity Regulatory Commission implemented the Deviation Settlement Mechanism w.e.f 17.02.2014 throughout the country by bringing out the CERC (Deviation Settlement Regulations and other matters) Regulations, 2014. This regulation had a far-reaching consequences on any stakeholder like STUs, IPPs, ISGS for deviating from the injection/drawal Schedule in a time block beyond a certain prescribed limit by levying Deviation Charges including Additional Deviation Charges
Consulting engineers who specify emergency power equipment understand that installations for mission critical facilities, such as hospitals and data centers, are required to comply with NFPA 110: Standard for Emergency and Standby Power Systems, in conjunction with NFPA 70: National Electrical Code. System designers must interpret the requirements of NFPA 110, ensure their designs follow them, and educate their clients about how the standard affects their operations.
NFPA 110 provides performance requirements for emergency and standby power systems that supply reliable auxiliary power to critical and essential loads when the primary power source fails. The standard covers installation, maintenance, operation, and testing requirements as they pertain to the performance of the emergency power supply system (EPSS) including power sources, transfer equipment, controls, supervisory equipment, and all related electrical and mechanical auxiliary and accessory equipment.
VIZIMAX's Renewable Energy Production solutionsGuillaume Leur
VIZIMAX offers Renewable Energy Production's solutions such wind power plant, solar power plant and Distributed Energy Resources (DER) for Grid connection, Volt-VAR-PF Control and ROCOF Monitoring.
Review major system events.
Provide fundamental knowledge and skills in restoration issues and proven solution techniques.
Refresh restoration principles and processes
Certificate of Completion by ….
The document covers the newly implemented regulation "Deviation settlement and mechanism" by CERC (central electricity regulatory commission.
This regulation has replaced the UI Regulation and mechanism.
Central Electricity Regulatory Commission implemented the Deviation Settlement Mechanism w.e.f 17.02.2014 throughout the country by bringing out the CERC (Deviation Settlement Regulations and other matters) Regulations, 2014. This regulation had a far-reaching consequences on any stakeholder like STUs, IPPs, ISGS for deviating from the injection/drawal Schedule in a time block beyond a certain prescribed limit by levying Deviation Charges including Additional Deviation Charges
Consulting engineers who specify emergency power equipment understand that installations for mission critical facilities, such as hospitals and data centers, are required to comply with NFPA 110: Standard for Emergency and Standby Power Systems, in conjunction with NFPA 70: National Electrical Code. System designers must interpret the requirements of NFPA 110, ensure their designs follow them, and educate their clients about how the standard affects their operations.
NFPA 110 provides performance requirements for emergency and standby power systems that supply reliable auxiliary power to critical and essential loads when the primary power source fails. The standard covers installation, maintenance, operation, and testing requirements as they pertain to the performance of the emergency power supply system (EPSS) including power sources, transfer equipment, controls, supervisory equipment, and all related electrical and mechanical auxiliary and accessory equipment.
VIZIMAX's Renewable Energy Production solutionsGuillaume Leur
VIZIMAX offers Renewable Energy Production's solutions such wind power plant, solar power plant and Distributed Energy Resources (DER) for Grid connection, Volt-VAR-PF Control and ROCOF Monitoring.
Review major system events.
Provide fundamental knowledge and skills in restoration issues and proven solution techniques.
Refresh restoration principles and processes
Certificate of Completion by ….
It's a full fledged presentation about visit to a substation. It's about when we visited the 400 kV substation situated at Hadala, Rajkot, Gujarat, India. It includes almost aa details about it. Juz go for it!!!
Complete details of EHV Transmission Line. Consolidated this presentation from those experts who had contributed separately on slider share and other web pages.Thanks for their valuable inputs.
Grid Event Analysis In Indian Power SystemChandan Kumar
The Presentation discusses how Grid Events in Indian Power System are detected, classified, Analysed and Reported with various practical studies. It also discusses the challenges faced in the process and associated regulation.
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantHarish Sharma
All the consumers of the State Distribution licensee or PSPCL who intend to encourage solar energy and set up solar PV plants at available places on roof-tops of Individual households, industries, Government or Semi-Government or Local Body offices, commercial establishments, institutions, residential complexes shall be eligible with project capacity ranging from minimum 1 KWp upto 1MWp (AC side) with or without battery back-up support. Consumers may generate solar power for self consumption and may feed excess power into the grid to be adjusted.
2. 2
1. Short title and commencement and
application
•These are CEA (Grid standards) Regulations, 2010
•They come into force on their publication in official
gazette I.e.June 26, 2010
•These shall apply to the entities, appropriate LDCs, and
RPCs.
2. Definitions
•Bulk consumer – means a consumer who avails supply at
voltages of 33 kV or above
•Entity - means a Generating company or a transmission
licensee or a distribution licensee or a bulk consumer
•Voltage Unbalance – Ration of the maximum voltage
deviation of the phase voltage from the average phase voltage
to the average phase voltage
3. 3
3. Standards for operation and maintenance of
transmission lines
a) Frequency Control
• All entities
• LDCs
• RPCs
Operating Range : 49.2 to 50.3 Hz or as per grid code
4. 4
b) Operating Voltage Limits
S.No. Normal system
Voltage (kV
rms)
Maximum (kV
rms)
Minimum (kV
rms)
1 765 800 728
2 400 420 380
3 220 245 198
4 132 145 122
5 110 121 99
6 66 72 60
7 33 36 30
5. 5
c) Temporary over voltage range d) voltage unbalance limits
S.No. Nominal System
Voltage (kV rms)
Temporary over voltage
Phase to Neutral (kV peak)
Voltage
unbalance (%)
1 765 914 1.5
2 400 514 1.5
3 220 283 2
4 132 170 3
5 33 State grid code 3
6. 6
e) Max fault clearance time
S.No. Normal system Voltage
(kV rms)
Maximum time
in milliseconds
1 765 and 400 100
2 220 and 132 160
Time delay for Back up breaker operation 200 ms.
7. 7
f) Grid shall with stand one of the following
contingencies without loss of stability
• Outage of one single largest generating unit
• Outage of a 132 kV double circuit line
• Outage of a 220 kV double circuit line
• Outage of a 400 kV single circuit line
• Outage of a 400 kV single circuit line with series
compensation
• Outage of a 765 kV single circuit line without series
compensation
• Outage of one pole of HVDC Bipolar line
• Outage of one interconnecting transformer
8. 8
g) N-1 criteria for system stability- system shall be
stable for one of the following contingencies
• Tripping of single largest generating unit
• Transient SLG fault of a 765 kV line close to bus
• A SLG Fault on 400 kV line and isolation of the line
• A fault on one circuit of a 400 kV double circuit line in
operation
• A transient SLG fault in one of the 400 kV double circuit
line when the second circuit is already under outage
• A 3 ph fault in 220 kV or 132 kV line
• A fault in one pole of HVDC bipolar in a HVDC
Converter station
9. 9
h) Limits for harmonic distortion in Transmission
systems
S.No. System Voltage (kV rms) Total harmonic
distortion (%)
Individual
Harmonic of any
particular
frequency (%)
1 765 1.5 1.0
2 400 2.0 1.5
3 220 2.5 2.0
4 33 to 132 5.0 3.0
10. 10
4. Operations planning
• Regional Power Committee shall do the operation planning for good
frequency profile, voltage profile, line loading, grid incident, grid
disturbance, performance of protection schemes and protection
coordination
5. Maintenance planning
• The RPC shall do the maintenance planning for Gen
stations, ISTS
• Coordinate the annual maintenance plan for inter regional
transmission system
• Organise monthly operating committee meetings in the
region
• The SLDC shall do the above for intra-state constituents
11. 11
6. Coordination in operations
• No entity shall introduce or take out the element of the
grid without the concurrence of the appropriate LDC
except in case of risk of safety of plant and personnel in
which case it must intimate the appropriate LDC.
12. 12
7. Operating instructions
• Every generating company and transmission licensee shall
provide written operating instructions for each equipment and
operating procedure for sequence of operations of power
system equipment in their control room
8. Instructions of LD shall be recorded
• All operating instructions given by RLDC and SLDC through phone,
fax, email shall be given a unique operating code number and
recorded . All conversations regarding operating instructions shall be
recorded with voice recorder.
• Above records shall be preserved for six months.
13. 13
9. Under frequency relay settings
• All entities shall set their UF relays and DF/DT relays in
accordance with RPC plan to provide load relief for grid
security and ensure the operation of these relays at the set
frequencies.
• All entities shall include the Fr relay details in their daily
report and the RPC shall inspect the relays as and when
required.
10. Islanding schemes
• The RPC shall prepare islanding schemes for separation of systems
with a view to save healthy system from total collapse in case of grid
disturbance. All entities shall ensure proper implementation of the
islanding schemes.
14. 14
11. Categorization of Grid incident and Grid
disturbance based on severity
• Severity of grid incidents
– GI 1: Tripping of one or more power system elements resulting in no loss
of supply at a substation or loss of integrity of grid at 220 kV level
– GI 2: Tripping of one or more power system elements resulting in no loss
of supply at a substation or loss of integrity of grid at 400 kV level and
above.
• Severity of Grid disturbance
– GD 1: when Generation or Load loss in a region < 10%
– GD 2: When Generation or Load loss in a region is between 10% to
20%
– GD 3: When Generation or Load loss in a region is between 20% to
30%
– GD 4: When Generation or Load loss in a region is between 30% to
40%
15. 15
12. Reporting of events affecting grid operation
• Any tripping of generating station or transmission element
shall be promptly reported by the respective entity to the
appropriate LDC in the prescribed format.
• The appropriate LDC shall intimate the SLDC and RLDC for
further dissemination to all concerned.
13. Reporting of grid disturbance
• The RLDC shall inform occurrence of the grid disturbance to the
constituents and RPC at the earliest
• The disturbance resulting in failure of power supply to large areas
shall also be reported by RLDC to Authority within 24 hours.
• The RLDC shall also post on its web site a brief grid disturbance
report indicating the affected area or the system, extant of outage
and the likely cause of initiation.
16. 16
14. Restoration of grid following incidence or
disturbance
• The RLDC in consultation with RPC shall develop procedures
for enabling restoration and normalization of the grid for inter-
state system.
• The SLDC shall also develop restoration procedures for intra-
state system.
• The restoration procedures shall be reviewed following
addition of generating station or transmission line or at least
once in two years.
• The above procedures shall be made available to, and be
followed by all concerned.
17. 17
15. Operational data during normal and grid
disturbance conditions
• All real time data as required by the appropriate LDC shall
be furnished by the entities.
• All data required by RPC, in discharge of the
responsibilities to it, shall be furnished by RLDC.
• All operational data, including disturbance recorder and
event logger reports, for analysing grid incidence /
disturbance shall be furnished by all entities to RLDC and
RPC.
• The RPC shall recommend remedial measures to be taken
on the disturbance report of RLDC to prevent recurrence .
18. 18
16. Operational data records
• Operational data logged manually and electronically shall
be preserved for at least three years.
• The unmanned sub-station data shall be maintained by the
concerned SS or LDC responsible.
• All observations shall be in chronological order.
• The observations made during inspection including
important parameters and deviation of parameters outside
permissible tolerances also be recorded in the log book.
• The RPC shall keep the record of grid incidences and grid
disturbances for each financial year. It shall include
sequence of tripping, the cause, and the sequence of
restoration, remedial measures taken to avert such incidents
and disturbances.
19. 19
17. Communication facilities
• The communication facilities installed by the transmission
licensee shall be in accordance with CEA Regulations, 2007
and shall be maintained in good condition.
18. Safety procedure
• The entity shall prepare contingency procedures for use of operators
at each sub-station and switchyards and these shall be regularly
updated.
• All operating personnel shall be trained in contingency procedures
and they shall follow the procedures.
• The fire fighting equipment shall be made available at all sub-stations,
switchyards, etc and shall be checked periodically for its upkeep and
mock exercises in fire fighting shall be carried out at least once in a
year.
20. 20
19. Maintenance of tools and equipment
• The maintenance staff shall be made aware of the list of tools,
devices and equipment for various maintenance and
rectification works on Tr lines, SSs, switchyards and converter
stations and the tools shall be made readily available and
certified for usage.
The entity shall prepare maintenance procedures for each
equipment in line with the manufacturer’s recommendations
and prudent utility practices.
20. Maintenance procedures
21. 21
21. Hot line methods
• Each transmission licensee shall have an arrangement for
restoration of transmission lines of 400 kV and above and
strategic 220 kV lines through the use of emergency restoration
system in order to minimise the outage of the tr. Lines in case
of tower failures.
22. Emergency restoration system
• The hot line techniques for maintenance of critical transmission lines
and sub-stations shall be adopted where ever possible
• Only trained staff shall be used for the hot line techniques and the
tools employed shall have necessary certification from a national or
international laboratory before use.
22. 22
• All essential parameters which indicate the health of the equipment in
a sub station, shall be inspected by the shift engineer once in each shift
and periodically by the officer in charge.
• Overhead lines shall be patrolled at periodicity decided by the
transmission licensee and different patrolling schedules shall be
implemented by the transmission licensee for normal terrain,
vulnerable terrain etc.
• The important lines shall be inspected by senior engineers after
patrolling by junior staff and maintenance works such as tree cutting,
replacement of damaged insulators, etc shall be carried out
immediately after patrolling.
23. Inspection and patrolling
23. 23
• Entities shall identify critical equipment and as far as possible,
practice condition based maintenance for such equipment in place of
time based maintenance.
• In case of time based maintenance, the periodicity of maintenance of
lines and SSs in polluted area or coastal area shall be more frequent.
• The maintenance of lines passing through and sub-stations located in
such areas should be completed before on set of winter so as to
minimise tripping under conditions of fog or due to salt deposit on
insulator discs in coastal areas and once before onset of summer.
• The maintenance work on various items of equipment may be
advanced depending on the condition of the equipment.
24. Maintenance schedules
24. 24
25. Condition monitoring
• The diagnostic methods of maintenance shall be preferred over
traditional time based maintenance.
26. Thermo-vision scanning
• The thermo-vision scanning for hot spots on all overhead lines and
sub station equipment at voltage level of 220 kV and above shall be
carried out at least once in a year and necessary remedial measures
shall be taken where hot spots are detected.
25. 25
27. Failure analysis
• All failures of the equipment and tower collapse shall be
analyzed by the entity to avoid recurrence and a copy of the
report shall be submitted to the RPC and Authority
• The authority may appoint a group of experts for investigation
and analysis and the representatives of the manufacturers may
be invited to participate in such analysis.
• All data which may help the group of experts in analysing the
failures shall be furnished by the respective Entities.
• The recommendations of the group of experts shall be
submitted to the authority and the recommendations accepted
by the authority shall be implemented and circulated to all
within the organisation and to other organisations to prevent
recurrence of such failures.
26. 26
28. Inventory control and spare parts
management
• The required spare parts shall be kept in stock, to ensure
speedy maintenance of the equipment.
• Computerised materials management system shall be
developed by the entities to optimise inventory.
29. Maintenance audit
• An internal audit committee may be established by the entities to
verify whether actual maintenance works are carried out at site in
compliance of the procedures and the policy of the transmission
company.
• The observations of the committee shall be put up to the management
of the entity for perusal and taking action, if any.
27. 27
30. Residual life assessment
• The RLA shall be carried out for all major equipment including
transformers, reactors, breakers, etc as envisaged by relevant
standards specified by the Bureau of Indian standards,
manufacturer’s instruction or industry best practices and
suitable remedial action for breach of the same shall be taken
by the management of the entity.
31. Disaster management
• The maintenance staff shall be trained in disaster management and a detailed
procedure for the same shall be developed by the entity and displayed
prominently.
• The detailed procedure shall be reviewed periodically and also based on
mock exercises carried out by the entity.
• The equipment including vehicles, diesel gen sets and fire fighting
equipment, etc shall be kept at sub-station or at appropriate location for
disaster management.
28. 28
32. Maintenance records
• The records of all maintenance carried out for each equipment
shall be kept in the table and formats in electronic form and
hard copy and the next due date for maintenance of each item
of work shall be clearly marked in such tables and formats.
33. Training
• Every person involved in O&M of transmission lines shall be trained
at the induction level and at least once in a year.
• The shift staff shall be trained to make them through in carrying out
operations at each SS and every person concerned with real time
operation shall be trained.
• Every grid operator shall undergo training in real time digital
simulator and a refresher course at least once in two years.
• The maintenance personnel of every entity shall also be trained in
preventive and breakdown maintenance of various equipment and
the personnel shall be trained in detailed maintenance procedures.