SlideShare a Scribd company logo
1
Grid standards
PSTI
Bangalore - 70
2
1. Short title and commencement and
application
•These are CEA (Grid standards) Regulations, 2010
•They come into force on their publication in official
gazette I.e.June 26, 2010
•These shall apply to the entities, appropriate LDCs, and
RPCs.
2. Definitions
•Bulk consumer – means a consumer who avails supply at
voltages of 33 kV or above
•Entity - means a Generating company or a transmission
licensee or a distribution licensee or a bulk consumer
•Voltage Unbalance – Ration of the maximum voltage
deviation of the phase voltage from the average phase voltage
to the average phase voltage
3
3. Standards for operation and maintenance of
transmission lines
a) Frequency Control
• All entities
• LDCs
• RPCs
Operating Range : 49.2 to 50.3 Hz or as per grid code
4
b) Operating Voltage Limits
S.No. Normal system
Voltage (kV
rms)
Maximum (kV
rms)
Minimum (kV
rms)
1 765 800 728
2 400 420 380
3 220 245 198
4 132 145 122
5 110 121 99
6 66 72 60
7 33 36 30
5
c) Temporary over voltage range d) voltage unbalance limits
S.No. Nominal System
Voltage (kV rms)
Temporary over voltage
Phase to Neutral (kV peak)
Voltage
unbalance (%)
1 765 914 1.5
2 400 514 1.5
3 220 283 2
4 132 170 3
5 33 State grid code 3
6
e) Max fault clearance time
S.No. Normal system Voltage
(kV rms)
Maximum time
in milliseconds
1 765 and 400 100
2 220 and 132 160
Time delay for Back up breaker operation 200 ms.
7
f) Grid shall with stand one of the following
contingencies without loss of stability
• Outage of one single largest generating unit
• Outage of a 132 kV double circuit line
• Outage of a 220 kV double circuit line
• Outage of a 400 kV single circuit line
• Outage of a 400 kV single circuit line with series
compensation
• Outage of a 765 kV single circuit line without series
compensation
• Outage of one pole of HVDC Bipolar line
• Outage of one interconnecting transformer
8
g) N-1 criteria for system stability- system shall be
stable for one of the following contingencies
• Tripping of single largest generating unit
• Transient SLG fault of a 765 kV line close to bus
• A SLG Fault on 400 kV line and isolation of the line
• A fault on one circuit of a 400 kV double circuit line in
operation
• A transient SLG fault in one of the 400 kV double circuit
line when the second circuit is already under outage
• A 3 ph fault in 220 kV or 132 kV line
• A fault in one pole of HVDC bipolar in a HVDC
Converter station
9
h) Limits for harmonic distortion in Transmission
systems
S.No. System Voltage (kV rms) Total harmonic
distortion (%)
Individual
Harmonic of any
particular
frequency (%)
1 765 1.5 1.0
2 400 2.0 1.5
3 220 2.5 2.0
4 33 to 132 5.0 3.0
10
4. Operations planning
• Regional Power Committee shall do the operation planning for good
frequency profile, voltage profile, line loading, grid incident, grid
disturbance, performance of protection schemes and protection
coordination
5. Maintenance planning
• The RPC shall do the maintenance planning for Gen
stations, ISTS
• Coordinate the annual maintenance plan for inter regional
transmission system
• Organise monthly operating committee meetings in the
region
• The SLDC shall do the above for intra-state constituents
11
6. Coordination in operations
• No entity shall introduce or take out the element of the
grid without the concurrence of the appropriate LDC
except in case of risk of safety of plant and personnel in
which case it must intimate the appropriate LDC.
12
7. Operating instructions
• Every generating company and transmission licensee shall
provide written operating instructions for each equipment and
operating procedure for sequence of operations of power
system equipment in their control room
8. Instructions of LD shall be recorded
• All operating instructions given by RLDC and SLDC through phone,
fax, email shall be given a unique operating code number and
recorded . All conversations regarding operating instructions shall be
recorded with voice recorder.
• Above records shall be preserved for six months.
13
9. Under frequency relay settings
• All entities shall set their UF relays and DF/DT relays in
accordance with RPC plan to provide load relief for grid
security and ensure the operation of these relays at the set
frequencies.
• All entities shall include the Fr relay details in their daily
report and the RPC shall inspect the relays as and when
required.
10. Islanding schemes
• The RPC shall prepare islanding schemes for separation of systems
with a view to save healthy system from total collapse in case of grid
disturbance. All entities shall ensure proper implementation of the
islanding schemes.
14
11. Categorization of Grid incident and Grid
disturbance based on severity
• Severity of grid incidents
– GI 1: Tripping of one or more power system elements resulting in no loss
of supply at a substation or loss of integrity of grid at 220 kV level
– GI 2: Tripping of one or more power system elements resulting in no loss
of supply at a substation or loss of integrity of grid at 400 kV level and
above.
• Severity of Grid disturbance
– GD 1: when Generation or Load loss in a region < 10%
– GD 2: When Generation or Load loss in a region is between 10% to
20%
– GD 3: When Generation or Load loss in a region is between 20% to
30%
– GD 4: When Generation or Load loss in a region is between 30% to
40%
15
12. Reporting of events affecting grid operation
• Any tripping of generating station or transmission element
shall be promptly reported by the respective entity to the
appropriate LDC in the prescribed format.
• The appropriate LDC shall intimate the SLDC and RLDC for
further dissemination to all concerned.
13. Reporting of grid disturbance
• The RLDC shall inform occurrence of the grid disturbance to the
constituents and RPC at the earliest
• The disturbance resulting in failure of power supply to large areas
shall also be reported by RLDC to Authority within 24 hours.
• The RLDC shall also post on its web site a brief grid disturbance
report indicating the affected area or the system, extant of outage
and the likely cause of initiation.
16
14. Restoration of grid following incidence or
disturbance
• The RLDC in consultation with RPC shall develop procedures
for enabling restoration and normalization of the grid for inter-
state system.
• The SLDC shall also develop restoration procedures for intra-
state system.
• The restoration procedures shall be reviewed following
addition of generating station or transmission line or at least
once in two years.
• The above procedures shall be made available to, and be
followed by all concerned.
17
15. Operational data during normal and grid
disturbance conditions
• All real time data as required by the appropriate LDC shall
be furnished by the entities.
• All data required by RPC, in discharge of the
responsibilities to it, shall be furnished by RLDC.
• All operational data, including disturbance recorder and
event logger reports, for analysing grid incidence /
disturbance shall be furnished by all entities to RLDC and
RPC.
• The RPC shall recommend remedial measures to be taken
on the disturbance report of RLDC to prevent recurrence .
18
16. Operational data records
• Operational data logged manually and electronically shall
be preserved for at least three years.
• The unmanned sub-station data shall be maintained by the
concerned SS or LDC responsible.
• All observations shall be in chronological order.
• The observations made during inspection including
important parameters and deviation of parameters outside
permissible tolerances also be recorded in the log book.
• The RPC shall keep the record of grid incidences and grid
disturbances for each financial year. It shall include
sequence of tripping, the cause, and the sequence of
restoration, remedial measures taken to avert such incidents
and disturbances.
19
17. Communication facilities
• The communication facilities installed by the transmission
licensee shall be in accordance with CEA Regulations, 2007
and shall be maintained in good condition.
18. Safety procedure
• The entity shall prepare contingency procedures for use of operators
at each sub-station and switchyards and these shall be regularly
updated.
• All operating personnel shall be trained in contingency procedures
and they shall follow the procedures.
• The fire fighting equipment shall be made available at all sub-stations,
switchyards, etc and shall be checked periodically for its upkeep and
mock exercises in fire fighting shall be carried out at least once in a
year.
20
19. Maintenance of tools and equipment
• The maintenance staff shall be made aware of the list of tools,
devices and equipment for various maintenance and
rectification works on Tr lines, SSs, switchyards and converter
stations and the tools shall be made readily available and
certified for usage.
The entity shall prepare maintenance procedures for each
equipment in line with the manufacturer’s recommendations
and prudent utility practices.
20. Maintenance procedures
21
21. Hot line methods
• Each transmission licensee shall have an arrangement for
restoration of transmission lines of 400 kV and above and
strategic 220 kV lines through the use of emergency restoration
system in order to minimise the outage of the tr. Lines in case
of tower failures.
22. Emergency restoration system
• The hot line techniques for maintenance of critical transmission lines
and sub-stations shall be adopted where ever possible
• Only trained staff shall be used for the hot line techniques and the
tools employed shall have necessary certification from a national or
international laboratory before use.
22
• All essential parameters which indicate the health of the equipment in
a sub station, shall be inspected by the shift engineer once in each shift
and periodically by the officer in charge.
• Overhead lines shall be patrolled at periodicity decided by the
transmission licensee and different patrolling schedules shall be
implemented by the transmission licensee for normal terrain,
vulnerable terrain etc.
• The important lines shall be inspected by senior engineers after
patrolling by junior staff and maintenance works such as tree cutting,
replacement of damaged insulators, etc shall be carried out
immediately after patrolling.
23. Inspection and patrolling
23
• Entities shall identify critical equipment and as far as possible,
practice condition based maintenance for such equipment in place of
time based maintenance.
• In case of time based maintenance, the periodicity of maintenance of
lines and SSs in polluted area or coastal area shall be more frequent.
• The maintenance of lines passing through and sub-stations located in
such areas should be completed before on set of winter so as to
minimise tripping under conditions of fog or due to salt deposit on
insulator discs in coastal areas and once before onset of summer.
• The maintenance work on various items of equipment may be
advanced depending on the condition of the equipment.
24. Maintenance schedules
24
25. Condition monitoring
• The diagnostic methods of maintenance shall be preferred over
traditional time based maintenance.
26. Thermo-vision scanning
• The thermo-vision scanning for hot spots on all overhead lines and
sub station equipment at voltage level of 220 kV and above shall be
carried out at least once in a year and necessary remedial measures
shall be taken where hot spots are detected.
25
27. Failure analysis
• All failures of the equipment and tower collapse shall be
analyzed by the entity to avoid recurrence and a copy of the
report shall be submitted to the RPC and Authority
• The authority may appoint a group of experts for investigation
and analysis and the representatives of the manufacturers may
be invited to participate in such analysis.
• All data which may help the group of experts in analysing the
failures shall be furnished by the respective Entities.
• The recommendations of the group of experts shall be
submitted to the authority and the recommendations accepted
by the authority shall be implemented and circulated to all
within the organisation and to other organisations to prevent
recurrence of such failures.
26
28. Inventory control and spare parts
management
• The required spare parts shall be kept in stock, to ensure
speedy maintenance of the equipment.
• Computerised materials management system shall be
developed by the entities to optimise inventory.
29. Maintenance audit
• An internal audit committee may be established by the entities to
verify whether actual maintenance works are carried out at site in
compliance of the procedures and the policy of the transmission
company.
• The observations of the committee shall be put up to the management
of the entity for perusal and taking action, if any.
27
30. Residual life assessment
• The RLA shall be carried out for all major equipment including
transformers, reactors, breakers, etc as envisaged by relevant
standards specified by the Bureau of Indian standards,
manufacturer’s instruction or industry best practices and
suitable remedial action for breach of the same shall be taken
by the management of the entity.
31. Disaster management
• The maintenance staff shall be trained in disaster management and a detailed
procedure for the same shall be developed by the entity and displayed
prominently.
• The detailed procedure shall be reviewed periodically and also based on
mock exercises carried out by the entity.
• The equipment including vehicles, diesel gen sets and fire fighting
equipment, etc shall be kept at sub-station or at appropriate location for
disaster management.
28
32. Maintenance records
• The records of all maintenance carried out for each equipment
shall be kept in the table and formats in electronic form and
hard copy and the next due date for maintenance of each item
of work shall be clearly marked in such tables and formats.
33. Training
• Every person involved in O&M of transmission lines shall be trained
at the induction level and at least once in a year.
• The shift staff shall be trained to make them through in carrying out
operations at each SS and every person concerned with real time
operation shall be trained.
• Every grid operator shall undergo training in real time digital
simulator and a refresher course at least once in two years.
• The maintenance personnel of every entity shall also be trained in
preventive and breakdown maintenance of various equipment and
the personnel shall be trained in detailed maintenance procedures.
29
Thank you

More Related Content

What's hot

Deviation settelment mechanism
Deviation settelment mechanismDeviation settelment mechanism
Deviation settelment mechanism
indianpowerindustry.com
 
Hangout on fa comm 032714 no spkr notes (1)
Hangout on fa comm 032714 no spkr notes (1)Hangout on fa comm 032714 no spkr notes (1)
Hangout on fa comm 032714 no spkr notes (1)
Ginger Hill
 
ABT-UI & Deviation Settlement Mechanism (DSM)
ABT-UI & Deviation Settlement Mechanism (DSM)ABT-UI & Deviation Settlement Mechanism (DSM)
ABT-UI & Deviation Settlement Mechanism (DSM)
shyamies11
 
Basics of electricity market in Ukraine - UARE 2021 en
Basics of electricity market in Ukraine - UARE 2021 enBasics of electricity market in Ukraine - UARE 2021 en
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
michaeljmack
 
Related RE work (LT, 11kV & 33kV)
Related RE work (LT, 11kV & 33kV)Related RE work (LT, 11kV & 33kV)
Related RE work (LT, 11kV & 33kV)
SAJAL KUMAR BAG
 
Rf based boundary detection
Rf based boundary detectionRf based boundary detection
Rf based boundary detection
Arun Raja
 
Evaluation of standby power system architectures
Evaluation of standby power system architecturesEvaluation of standby power system architectures
Evaluation of standby power system architectures
michaeljmack
 
,Article reprint from_erneuerbareenergien
,Article reprint from_erneuerbareenergien,Article reprint from_erneuerbareenergien
,Article reprint from_erneuerbareenergien
Manel Montesinos
 
Critical Power: NFPA 110: Standard for Emergency and Standby Power
Critical Power: NFPA 110: Standard for Emergency and Standby Power Critical Power: NFPA 110: Standard for Emergency and Standby Power
Critical Power: NFPA 110: Standard for Emergency and Standby Power
ConsultingSpecifyingEngineer
 
NAv Topic 4 vhf communication system
NAv Topic 4 vhf communication systemNAv Topic 4 vhf communication system
NAv Topic 4 vhf communication systemIzah Asmadi
 
Ds2460q datasheet
Ds2460q datasheetDs2460q datasheet
VIZIMAX's Renewable Energy Production solutions
VIZIMAX's Renewable Energy Production solutionsVIZIMAX's Renewable Energy Production solutions
VIZIMAX's Renewable Energy Production solutions
Guillaume Leur
 
CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165
michaeljmack
 
Nav Topic 4 hf communication system
Nav Topic 4 hf communication systemNav Topic 4 hf communication system
Nav Topic 4 hf communication systemIzah Asmadi
 
Application overview
Application overviewApplication overview
Application overviewĐặng Hảo
 
Novatek Electro India presentation
Novatek Electro India presentationNovatek Electro India presentation
Novatek Electro India presentation
novatek_india
 
NIGERIA GRID CODE
NIGERIA GRID CODE NIGERIA GRID CODE
NIGERIA GRID CODE
Power System Operation
 
Power System Restoration Drill
Power System Restoration DrillPower System Restoration Drill
Power System Restoration Drill
Power System Operation
 

What's hot (20)

Deviation settelment mechanism
Deviation settelment mechanismDeviation settelment mechanism
Deviation settelment mechanism
 
Hangout on fa comm 032714 no spkr notes (1)
Hangout on fa comm 032714 no spkr notes (1)Hangout on fa comm 032714 no spkr notes (1)
Hangout on fa comm 032714 no spkr notes (1)
 
OPEN ACCESS REGULATION
OPEN ACCESS REGULATIONOPEN ACCESS REGULATION
OPEN ACCESS REGULATION
 
ABT-UI & Deviation Settlement Mechanism (DSM)
ABT-UI & Deviation Settlement Mechanism (DSM)ABT-UI & Deviation Settlement Mechanism (DSM)
ABT-UI & Deviation Settlement Mechanism (DSM)
 
Basics of electricity market in Ukraine - UARE 2021 en
Basics of electricity market in Ukraine - UARE 2021 enBasics of electricity market in Ukraine - UARE 2021 en
Basics of electricity market in Ukraine - UARE 2021 en
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
 
Related RE work (LT, 11kV & 33kV)
Related RE work (LT, 11kV & 33kV)Related RE work (LT, 11kV & 33kV)
Related RE work (LT, 11kV & 33kV)
 
Rf based boundary detection
Rf based boundary detectionRf based boundary detection
Rf based boundary detection
 
Evaluation of standby power system architectures
Evaluation of standby power system architecturesEvaluation of standby power system architectures
Evaluation of standby power system architectures
 
,Article reprint from_erneuerbareenergien
,Article reprint from_erneuerbareenergien,Article reprint from_erneuerbareenergien
,Article reprint from_erneuerbareenergien
 
Critical Power: NFPA 110: Standard for Emergency and Standby Power
Critical Power: NFPA 110: Standard for Emergency and Standby Power Critical Power: NFPA 110: Standard for Emergency and Standby Power
Critical Power: NFPA 110: Standard for Emergency and Standby Power
 
NAv Topic 4 vhf communication system
NAv Topic 4 vhf communication systemNAv Topic 4 vhf communication system
NAv Topic 4 vhf communication system
 
Ds2460q datasheet
Ds2460q datasheetDs2460q datasheet
Ds2460q datasheet
 
VIZIMAX's Renewable Energy Production solutions
VIZIMAX's Renewable Energy Production solutionsVIZIMAX's Renewable Energy Production solutions
VIZIMAX's Renewable Energy Production solutions
 
CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165
 
Nav Topic 4 hf communication system
Nav Topic 4 hf communication systemNav Topic 4 hf communication system
Nav Topic 4 hf communication system
 
Application overview
Application overviewApplication overview
Application overview
 
Novatek Electro India presentation
Novatek Electro India presentationNovatek Electro India presentation
Novatek Electro India presentation
 
NIGERIA GRID CODE
NIGERIA GRID CODE NIGERIA GRID CODE
NIGERIA GRID CODE
 
Power System Restoration Drill
Power System Restoration DrillPower System Restoration Drill
Power System Restoration Drill
 

Viewers also liked

EE 39 Power System Restoration Strategy During Emergency & Blackout
EE 39 Power System Restoration Strategy During Emergency & BlackoutEE 39 Power System Restoration Strategy During Emergency & Blackout
EE 39 Power System Restoration Strategy During Emergency & BlackoutRina Florentes
 
Grid failure on 30th july 2012
Grid failure on 30th july 2012Grid failure on 30th july 2012
Grid failure on 30th july 2012
Ishu Sethi
 
NTPC Ramagundam Station Blackout and Action Plan
NTPC Ramagundam Station Blackout and Action PlanNTPC Ramagundam Station Blackout and Action Plan
NTPC Ramagundam Station Blackout and Action PlanNTPC
 
presentation on 400kv gss heerapura @mnit
presentation on 400kv gss heerapura @mnitpresentation on 400kv gss heerapura @mnit
presentation on 400kv gss heerapura @mnit
Suresh Choudhary
 
Akt tl design01
Akt tl design01Akt tl design01
Akt tl design01
Dr Ashok Tiwari
 
Power grid operation in India
Power grid operation in IndiaPower grid operation in India
Power grid operation in India
Mahim Srivastava
 
PPT POWER GRID CORPORATION OF INDIA LIMITED
PPT POWER GRID CORPORATION OF INDIA LIMITED PPT POWER GRID CORPORATION OF INDIA LIMITED
PPT POWER GRID CORPORATION OF INDIA LIMITED
Aditya Shankar
 
Visit to 400 kV substation, Hadala
Visit to 400 kV substation, HadalaVisit to 400 kV substation, Hadala
Visit to 400 kV substation, Hadala
Nandan Desai
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdf
Ajay Bhatnagar
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohitMohit Awasthi
 
Ppt power grid design
Ppt power grid designPpt power grid design
Ppt power grid design
susanta das
 
Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design conceptKumar VEL
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmissionSumit Kumar
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission Line
SURESH GOPAL
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
Mahesh Sontyal
 

Viewers also liked (16)

EE 39 Power System Restoration Strategy During Emergency & Blackout
EE 39 Power System Restoration Strategy During Emergency & BlackoutEE 39 Power System Restoration Strategy During Emergency & Blackout
EE 39 Power System Restoration Strategy During Emergency & Blackout
 
Grid failure on 30th july 2012
Grid failure on 30th july 2012Grid failure on 30th july 2012
Grid failure on 30th july 2012
 
Blackout
BlackoutBlackout
Blackout
 
NTPC Ramagundam Station Blackout and Action Plan
NTPC Ramagundam Station Blackout and Action PlanNTPC Ramagundam Station Blackout and Action Plan
NTPC Ramagundam Station Blackout and Action Plan
 
presentation on 400kv gss heerapura @mnit
presentation on 400kv gss heerapura @mnitpresentation on 400kv gss heerapura @mnit
presentation on 400kv gss heerapura @mnit
 
Akt tl design01
Akt tl design01Akt tl design01
Akt tl design01
 
Power grid operation in India
Power grid operation in IndiaPower grid operation in India
Power grid operation in India
 
PPT POWER GRID CORPORATION OF INDIA LIMITED
PPT POWER GRID CORPORATION OF INDIA LIMITED PPT POWER GRID CORPORATION OF INDIA LIMITED
PPT POWER GRID CORPORATION OF INDIA LIMITED
 
Visit to 400 kV substation, Hadala
Visit to 400 kV substation, HadalaVisit to 400 kV substation, Hadala
Visit to 400 kV substation, Hadala
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdf
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
 
Ppt power grid design
Ppt power grid designPpt power grid design
Ppt power grid design
 
Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design concept
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmission
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission Line
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
 

Similar to Grid stds

CEA Regulations.pptx
CEA Regulations.pptxCEA Regulations.pptx
CEA Regulations.pptx
CSVenkateswaranCASEs
 
Grid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power SystemGrid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power System
Chandan Kumar
 
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantNet metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Harish Sharma
 
IEGC.pptx
IEGC.pptxIEGC.pptx
CEA Grid Standards
CEA Grid StandardsCEA Grid Standards
CEA Grid Standards
Saravanan Manoharan
 
BOQ _UN.pptx
BOQ _UN.pptxBOQ _UN.pptx
BOQ _UN.pptx
dessalegnd100
 
Defence mechanism in power system
Defence mechanism in power systemDefence mechanism in power system
Defence mechanism in power system
Chandan Kumar
 
2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...
2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...
2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...
vutnm94
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
UdayMujumdar
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
SheelKapar1
 
Sudden three phase short-circuit test
Sudden three phase short-circuit testSudden three phase short-circuit test
Sudden three phase short-circuit testDonald Stephen
 
20BEE042 5th semester Internship PPT.pptx
20BEE042 5th semester Internship PPT.pptx20BEE042 5th semester Internship PPT.pptx
20BEE042 5th semester Internship PPT.pptx
SumitRajput83
 
Scada presentation
Scada presentationScada presentation
Scada presentation
Amit Kumar
 
Water Detection System for Air Conditional&Mechanical Ventilation Installation
Water Detection System for Air Conditional&Mechanical Ventilation InstallationWater Detection System for Air Conditional&Mechanical Ventilation Installation
Water Detection System for Air Conditional&Mechanical Ventilation Installation
Johnny Tsai
 
Unit 6 power quality
Unit 6 power qualityUnit 6 power quality
Unit 6 power quality
hariyenireddy1
 
IRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdfIRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdf
PowerSystemDynamicsS
 
Protective Relay by Shamim Reza
Protective Relay  by Shamim RezaProtective Relay  by Shamim Reza
Protective Relay by Shamim Reza
Narayan Chandra Gharami
 

Similar to Grid stds (20)

CEA Regulations.pptx
CEA Regulations.pptxCEA Regulations.pptx
CEA Regulations.pptx
 
Grid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power SystemGrid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power System
 
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantNet metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
 
IEGC.pptx
IEGC.pptxIEGC.pptx
IEGC.pptx
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
CEA Grid Standards
CEA Grid StandardsCEA Grid Standards
CEA Grid Standards
 
Grid standards reg
Grid standards regGrid standards reg
Grid standards reg
 
BOQ _UN.pptx
BOQ _UN.pptxBOQ _UN.pptx
BOQ _UN.pptx
 
Defence mechanism in power system
Defence mechanism in power systemDefence mechanism in power system
Defence mechanism in power system
 
2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...
2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...
2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
 
Sudden three phase short-circuit test
Sudden three phase short-circuit testSudden three phase short-circuit test
Sudden three phase short-circuit test
 
20BEE042 5th semester Internship PPT.pptx
20BEE042 5th semester Internship PPT.pptx20BEE042 5th semester Internship PPT.pptx
20BEE042 5th semester Internship PPT.pptx
 
Scada presentation
Scada presentationScada presentation
Scada presentation
 
Water Detection System for Air Conditional&Mechanical Ventilation Installation
Water Detection System for Air Conditional&Mechanical Ventilation InstallationWater Detection System for Air Conditional&Mechanical Ventilation Installation
Water Detection System for Air Conditional&Mechanical Ventilation Installation
 
Unit 6 power quality
Unit 6 power qualityUnit 6 power quality
Unit 6 power quality
 
IRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdfIRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdf
 
Protective Relay by Shamim Reza
Protective Relay  by Shamim RezaProtective Relay  by Shamim Reza
Protective Relay by Shamim Reza
 

More from arvind singh rathore

Indiapresentation 090518123848-phpapp02
Indiapresentation 090518123848-phpapp02Indiapresentation 090518123848-phpapp02
Indiapresentation 090518123848-phpapp02arvind singh rathore
 
Case studies in steam system auditing
Case studies in steam system auditingCase studies in steam system auditing
Case studies in steam system auditingarvind singh rathore
 
Steamturbine 140203094808-phpapp01
Steamturbine 140203094808-phpapp01Steamturbine 140203094808-phpapp01
Steamturbine 140203094808-phpapp01arvind singh rathore
 
Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01arvind singh rathore
 
Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01arvind singh rathore
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02arvind singh rathore
 

More from arvind singh rathore (20)

Indiapresentation 090518123848-phpapp02
Indiapresentation 090518123848-phpapp02Indiapresentation 090518123848-phpapp02
Indiapresentation 090518123848-phpapp02
 
Turbo generator & its auxiliaries
Turbo generator & its auxiliariesTurbo generator & its auxiliaries
Turbo generator & its auxiliaries
 
Case studies in steam system auditing
Case studies in steam system auditingCase studies in steam system auditing
Case studies in steam system auditing
 
Generator grid connection_guide
Generator grid connection_guideGenerator grid connection_guide
Generator grid connection_guide
 
Turbinecontrolbasic
TurbinecontrolbasicTurbinecontrolbasic
Turbinecontrolbasic
 
Basic plc-programming
Basic plc-programmingBasic plc-programming
Basic plc-programming
 
Analog output
Analog outputAnalog output
Analog output
 
Transformer guide
Transformer guideTransformer guide
Transformer guide
 
Controller
ControllerController
Controller
 
ge turbine
 ge  turbine ge  turbine
ge turbine
 
steam turbine presentations
steam turbine presentationssteam turbine presentations
steam turbine presentations
 
Steamturbine 140203094808-phpapp01
Steamturbine 140203094808-phpapp01Steamturbine 140203094808-phpapp01
Steamturbine 140203094808-phpapp01
 
Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01
 
Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01
 
4.1.3 properties of coals
4.1.3 properties of coals4.1.3 properties of coals
4.1.3 properties of coals
 
Power quality
Power qualityPower quality
Power quality
 
Ntpc2 111125042448-phpapp02
Ntpc2 111125042448-phpapp02Ntpc2 111125042448-phpapp02
Ntpc2 111125042448-phpapp02
 
An article on fuel
An article on fuelAn article on fuel
An article on fuel
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02
 
Steam turbine oil_challenges
Steam turbine oil_challengesSteam turbine oil_challenges
Steam turbine oil_challenges
 

Grid stds

  • 2. 2 1. Short title and commencement and application •These are CEA (Grid standards) Regulations, 2010 •They come into force on their publication in official gazette I.e.June 26, 2010 •These shall apply to the entities, appropriate LDCs, and RPCs. 2. Definitions •Bulk consumer – means a consumer who avails supply at voltages of 33 kV or above •Entity - means a Generating company or a transmission licensee or a distribution licensee or a bulk consumer •Voltage Unbalance – Ration of the maximum voltage deviation of the phase voltage from the average phase voltage to the average phase voltage
  • 3. 3 3. Standards for operation and maintenance of transmission lines a) Frequency Control • All entities • LDCs • RPCs Operating Range : 49.2 to 50.3 Hz or as per grid code
  • 4. 4 b) Operating Voltage Limits S.No. Normal system Voltage (kV rms) Maximum (kV rms) Minimum (kV rms) 1 765 800 728 2 400 420 380 3 220 245 198 4 132 145 122 5 110 121 99 6 66 72 60 7 33 36 30
  • 5. 5 c) Temporary over voltage range d) voltage unbalance limits S.No. Nominal System Voltage (kV rms) Temporary over voltage Phase to Neutral (kV peak) Voltage unbalance (%) 1 765 914 1.5 2 400 514 1.5 3 220 283 2 4 132 170 3 5 33 State grid code 3
  • 6. 6 e) Max fault clearance time S.No. Normal system Voltage (kV rms) Maximum time in milliseconds 1 765 and 400 100 2 220 and 132 160 Time delay for Back up breaker operation 200 ms.
  • 7. 7 f) Grid shall with stand one of the following contingencies without loss of stability • Outage of one single largest generating unit • Outage of a 132 kV double circuit line • Outage of a 220 kV double circuit line • Outage of a 400 kV single circuit line • Outage of a 400 kV single circuit line with series compensation • Outage of a 765 kV single circuit line without series compensation • Outage of one pole of HVDC Bipolar line • Outage of one interconnecting transformer
  • 8. 8 g) N-1 criteria for system stability- system shall be stable for one of the following contingencies • Tripping of single largest generating unit • Transient SLG fault of a 765 kV line close to bus • A SLG Fault on 400 kV line and isolation of the line • A fault on one circuit of a 400 kV double circuit line in operation • A transient SLG fault in one of the 400 kV double circuit line when the second circuit is already under outage • A 3 ph fault in 220 kV or 132 kV line • A fault in one pole of HVDC bipolar in a HVDC Converter station
  • 9. 9 h) Limits for harmonic distortion in Transmission systems S.No. System Voltage (kV rms) Total harmonic distortion (%) Individual Harmonic of any particular frequency (%) 1 765 1.5 1.0 2 400 2.0 1.5 3 220 2.5 2.0 4 33 to 132 5.0 3.0
  • 10. 10 4. Operations planning • Regional Power Committee shall do the operation planning for good frequency profile, voltage profile, line loading, grid incident, grid disturbance, performance of protection schemes and protection coordination 5. Maintenance planning • The RPC shall do the maintenance planning for Gen stations, ISTS • Coordinate the annual maintenance plan for inter regional transmission system • Organise monthly operating committee meetings in the region • The SLDC shall do the above for intra-state constituents
  • 11. 11 6. Coordination in operations • No entity shall introduce or take out the element of the grid without the concurrence of the appropriate LDC except in case of risk of safety of plant and personnel in which case it must intimate the appropriate LDC.
  • 12. 12 7. Operating instructions • Every generating company and transmission licensee shall provide written operating instructions for each equipment and operating procedure for sequence of operations of power system equipment in their control room 8. Instructions of LD shall be recorded • All operating instructions given by RLDC and SLDC through phone, fax, email shall be given a unique operating code number and recorded . All conversations regarding operating instructions shall be recorded with voice recorder. • Above records shall be preserved for six months.
  • 13. 13 9. Under frequency relay settings • All entities shall set their UF relays and DF/DT relays in accordance with RPC plan to provide load relief for grid security and ensure the operation of these relays at the set frequencies. • All entities shall include the Fr relay details in their daily report and the RPC shall inspect the relays as and when required. 10. Islanding schemes • The RPC shall prepare islanding schemes for separation of systems with a view to save healthy system from total collapse in case of grid disturbance. All entities shall ensure proper implementation of the islanding schemes.
  • 14. 14 11. Categorization of Grid incident and Grid disturbance based on severity • Severity of grid incidents – GI 1: Tripping of one or more power system elements resulting in no loss of supply at a substation or loss of integrity of grid at 220 kV level – GI 2: Tripping of one or more power system elements resulting in no loss of supply at a substation or loss of integrity of grid at 400 kV level and above. • Severity of Grid disturbance – GD 1: when Generation or Load loss in a region < 10% – GD 2: When Generation or Load loss in a region is between 10% to 20% – GD 3: When Generation or Load loss in a region is between 20% to 30% – GD 4: When Generation or Load loss in a region is between 30% to 40%
  • 15. 15 12. Reporting of events affecting grid operation • Any tripping of generating station or transmission element shall be promptly reported by the respective entity to the appropriate LDC in the prescribed format. • The appropriate LDC shall intimate the SLDC and RLDC for further dissemination to all concerned. 13. Reporting of grid disturbance • The RLDC shall inform occurrence of the grid disturbance to the constituents and RPC at the earliest • The disturbance resulting in failure of power supply to large areas shall also be reported by RLDC to Authority within 24 hours. • The RLDC shall also post on its web site a brief grid disturbance report indicating the affected area or the system, extant of outage and the likely cause of initiation.
  • 16. 16 14. Restoration of grid following incidence or disturbance • The RLDC in consultation with RPC shall develop procedures for enabling restoration and normalization of the grid for inter- state system. • The SLDC shall also develop restoration procedures for intra- state system. • The restoration procedures shall be reviewed following addition of generating station or transmission line or at least once in two years. • The above procedures shall be made available to, and be followed by all concerned.
  • 17. 17 15. Operational data during normal and grid disturbance conditions • All real time data as required by the appropriate LDC shall be furnished by the entities. • All data required by RPC, in discharge of the responsibilities to it, shall be furnished by RLDC. • All operational data, including disturbance recorder and event logger reports, for analysing grid incidence / disturbance shall be furnished by all entities to RLDC and RPC. • The RPC shall recommend remedial measures to be taken on the disturbance report of RLDC to prevent recurrence .
  • 18. 18 16. Operational data records • Operational data logged manually and electronically shall be preserved for at least three years. • The unmanned sub-station data shall be maintained by the concerned SS or LDC responsible. • All observations shall be in chronological order. • The observations made during inspection including important parameters and deviation of parameters outside permissible tolerances also be recorded in the log book. • The RPC shall keep the record of grid incidences and grid disturbances for each financial year. It shall include sequence of tripping, the cause, and the sequence of restoration, remedial measures taken to avert such incidents and disturbances.
  • 19. 19 17. Communication facilities • The communication facilities installed by the transmission licensee shall be in accordance with CEA Regulations, 2007 and shall be maintained in good condition. 18. Safety procedure • The entity shall prepare contingency procedures for use of operators at each sub-station and switchyards and these shall be regularly updated. • All operating personnel shall be trained in contingency procedures and they shall follow the procedures. • The fire fighting equipment shall be made available at all sub-stations, switchyards, etc and shall be checked periodically for its upkeep and mock exercises in fire fighting shall be carried out at least once in a year.
  • 20. 20 19. Maintenance of tools and equipment • The maintenance staff shall be made aware of the list of tools, devices and equipment for various maintenance and rectification works on Tr lines, SSs, switchyards and converter stations and the tools shall be made readily available and certified for usage. The entity shall prepare maintenance procedures for each equipment in line with the manufacturer’s recommendations and prudent utility practices. 20. Maintenance procedures
  • 21. 21 21. Hot line methods • Each transmission licensee shall have an arrangement for restoration of transmission lines of 400 kV and above and strategic 220 kV lines through the use of emergency restoration system in order to minimise the outage of the tr. Lines in case of tower failures. 22. Emergency restoration system • The hot line techniques for maintenance of critical transmission lines and sub-stations shall be adopted where ever possible • Only trained staff shall be used for the hot line techniques and the tools employed shall have necessary certification from a national or international laboratory before use.
  • 22. 22 • All essential parameters which indicate the health of the equipment in a sub station, shall be inspected by the shift engineer once in each shift and periodically by the officer in charge. • Overhead lines shall be patrolled at periodicity decided by the transmission licensee and different patrolling schedules shall be implemented by the transmission licensee for normal terrain, vulnerable terrain etc. • The important lines shall be inspected by senior engineers after patrolling by junior staff and maintenance works such as tree cutting, replacement of damaged insulators, etc shall be carried out immediately after patrolling. 23. Inspection and patrolling
  • 23. 23 • Entities shall identify critical equipment and as far as possible, practice condition based maintenance for such equipment in place of time based maintenance. • In case of time based maintenance, the periodicity of maintenance of lines and SSs in polluted area or coastal area shall be more frequent. • The maintenance of lines passing through and sub-stations located in such areas should be completed before on set of winter so as to minimise tripping under conditions of fog or due to salt deposit on insulator discs in coastal areas and once before onset of summer. • The maintenance work on various items of equipment may be advanced depending on the condition of the equipment. 24. Maintenance schedules
  • 24. 24 25. Condition monitoring • The diagnostic methods of maintenance shall be preferred over traditional time based maintenance. 26. Thermo-vision scanning • The thermo-vision scanning for hot spots on all overhead lines and sub station equipment at voltage level of 220 kV and above shall be carried out at least once in a year and necessary remedial measures shall be taken where hot spots are detected.
  • 25. 25 27. Failure analysis • All failures of the equipment and tower collapse shall be analyzed by the entity to avoid recurrence and a copy of the report shall be submitted to the RPC and Authority • The authority may appoint a group of experts for investigation and analysis and the representatives of the manufacturers may be invited to participate in such analysis. • All data which may help the group of experts in analysing the failures shall be furnished by the respective Entities. • The recommendations of the group of experts shall be submitted to the authority and the recommendations accepted by the authority shall be implemented and circulated to all within the organisation and to other organisations to prevent recurrence of such failures.
  • 26. 26 28. Inventory control and spare parts management • The required spare parts shall be kept in stock, to ensure speedy maintenance of the equipment. • Computerised materials management system shall be developed by the entities to optimise inventory. 29. Maintenance audit • An internal audit committee may be established by the entities to verify whether actual maintenance works are carried out at site in compliance of the procedures and the policy of the transmission company. • The observations of the committee shall be put up to the management of the entity for perusal and taking action, if any.
  • 27. 27 30. Residual life assessment • The RLA shall be carried out for all major equipment including transformers, reactors, breakers, etc as envisaged by relevant standards specified by the Bureau of Indian standards, manufacturer’s instruction or industry best practices and suitable remedial action for breach of the same shall be taken by the management of the entity. 31. Disaster management • The maintenance staff shall be trained in disaster management and a detailed procedure for the same shall be developed by the entity and displayed prominently. • The detailed procedure shall be reviewed periodically and also based on mock exercises carried out by the entity. • The equipment including vehicles, diesel gen sets and fire fighting equipment, etc shall be kept at sub-station or at appropriate location for disaster management.
  • 28. 28 32. Maintenance records • The records of all maintenance carried out for each equipment shall be kept in the table and formats in electronic form and hard copy and the next due date for maintenance of each item of work shall be clearly marked in such tables and formats. 33. Training • Every person involved in O&M of transmission lines shall be trained at the induction level and at least once in a year. • The shift staff shall be trained to make them through in carrying out operations at each SS and every person concerned with real time operation shall be trained. • Every grid operator shall undergo training in real time digital simulator and a refresher course at least once in two years. • The maintenance personnel of every entity shall also be trained in preventive and breakdown maintenance of various equipment and the personnel shall be trained in detailed maintenance procedures.