UNITED NATIONS DEVELOPMENT PROGRAMME
ITB 2016-196
Lot 26
WBS 1150
Bill of Quantities
Programme Title: Right to Education in the Gaza Strip
Project name: Extension and Rehabilitation Works For The Governmental Schools
PAL10- 00094739- LOT 26
Renewable Energy for All – Photovoltaic Cells for Al Fakhoora Schools in Gaza Strip
(Bill of Quantities)
1 .The contractor must provide a detailed cost breakdown for each item.
2.The contractor must provide Technical descriptions for each proposed item and sufficient
detail to allow UNDP to determine compliance of Bid with specifications as per Schedule of
Requirements and Technical Specifications of this ITB. The contractor shall indicate all makes
proposed and must attach relevant manufacturer Catalogue/data.
3. The contractor shall submit the Manufacture testing certificate, country of origion, certified
characteristics, test performance curves, spare parts regular (as recommended by manufacturer ,
maintenance manuals and manufacturers warranty for each components of the system for 5
years.
4. All prices/rates quoted must be exclusive of all taxes, since the United Nations, including its
subsidiary organs, is exempt from taxes.
5. In addition to the hard copy, if possible please provide also the information on diskette (IBM
compatible).
5. Inspection Team
The contractor Shall facilitate the attendance of Engineers from the supervision team and the
Recipient to check the materials of the PV Solar eqipments before delivering to Site.
6. On site training
Upon completion of the installation, the contractor shall organize an on site training program
involving nominated employer's staff. Such a program shall be carried out during the
commissioning phase. The cost of the training shall be deemed to have been included in the
tendered rates.
7.Contractor's Documents
The contractor's documents must include all construction documentation required for the
works. They must include all site information, structural and civil drawings, electrical
services drawings at suitable scales showing final design calculations, symbols list, site
plan, and single line diagrams for distribution boards, solar switchboards, and control
systems.
8.Operation and Maintenace Manuals
The contractor must submit two hard copies on standard sized sheets and two electronic
copy in-PDF format of the as built drawings including the wiring diagrams and PV single line
diagrams, DC and AC wiring sizing calculations including cross sectional area of the wires
used and voltage drop calculations, rating of all fuses and circuit breakers, operation and
maintenance manuals for each different site. The manuals must contain PV system description
and catalogues of all PV system components. They shall also contain maintenance schedules,
commissioning data, PV system test certificates, a step by step startup and shut down procedure
for the entire PV system, and description of the type and operation control of the inverter and
charge controller.
The contractor will maintain monthly visits during the maintenance period to carry out the
necessary maintenance processes needed and respond promptly to any emergency needed to
keep the system performance intact and perfect.
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
Bill No (1)
Photovoltaic Solar System works
General:
• The system is designed to cover the Essential loads in Jamal Abd Alnasser School
•The system will be grid interactive connected with battery backup system, which will allow many power
sources options. The system will import from the grid when loads are being more than the generated from PV
and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be
charged from Grid if PV output is not enough for loads and batteries.
•Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar
system works,including a single line diagram showing all the components of the PV system, DC and AC
distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section
for all the system to be approved by the Engineer before executing the work.
•Contractor shall submit the catalogs of each component showing the requested specifications stated at the
bill of quantity.
•The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics,
test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and
manufacturers warrantyfor each components of the system.
• As-built drawings shall be submitted after handing over the work.
• All junction boxes and DBs will be lockable type.
•Upon completion of the installation, the contractor shall organize an on site training program involving
nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of
the training shall be deemed to have been included in the tendered rates.
•The price includes all builders’ works, making good and reinstatement including necessary materials and
workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete
the job successfully.
• All the following items include supply, install, commission and operate of the complete PV solar system.
• The work includes maintenance period for each device according to BOQ and Specifications.
1
PV Modules – 45 Kwp:
Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all
material needed to have complete job ready for installing high quality PV modules with total arrays capacity to
achieve 45 KWp. The item Includes supply, install &connect the following:
• Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars
,terminals, ducts or trays, supports &labels suitable to the PV arrays loads.
•Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have
a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC
plug and socket connectors . The DC cables must be sized in accordance with the installation requirements
applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%.
KWp 45
•The price includes all works, making good and reinstatement including necessary materials and workmanship
as well as removal of unwanted materials to dump sites approved by the engineer to complete the job
successfully.
• Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years.
• Contractor must submit all the required certificates for each PV solar panel from.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for Jamal Abd Alnasser School
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
2
Inverters – 45 KW:
Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with
Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the
system design and installation proposed and for the future extended also. (Type is SMA or equivalent).
The DC max power input rating should be equal or more than 45 KW of the PV modules capacity at standard
test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65.
The inverter AC nominal power output rating must be equal or greater than 45 KW compatible with the AC
loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic
strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total
inverter capacity must be devided at least 3 inverters. The price includes :
Unit 1
•Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially
compatible with the inverters, with all needed accessories, interface modules & data cables and all connections
needed to complete and connect the monitoring system to internet.
•Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements
and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations
end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC
cables between inverters and PV system not less than 1%.
•Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical
cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the
main distribution panel according to the engineer's instruction and approval and have a complete job.
•The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
3
Battery Inverters – 50 KW:
Supply, install, connect and operate Battery Inverters compatible with on grid inverter rated power 50 Kw with
all necessary (Grid-Connect Automatic Transfer Control Box) ,interface modules and connections for
masters & slaves , electrical cables and data communication unit with Ethernet connection, connectable in
parallel and modularly extendable. (Type is SMA or equivalent).
The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency,
intelligent battery management for maximum battery life, charge level calculation, extreme overload
capability, and battery temperature sensing and battery current measurements).Total battery inverters capacity
must be compatible with the number of the inverters.
The price includes:
Unit 1
•Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data
& communication cables and connection needed to complete the job.
• Supply, install and connect:
DC cables appropriately sized in accordance with the installation requirements to connect the batteryinverters
with DC battery fuses box.
AC electrical cables to connect the battery inverters with the main distribution panel(AC Out).
the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a
complete job,
• The allowable voltage drop for DC cables between battery inverter and batteries less than 1%.
•The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5
years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for Jamal Abd Alnasser School
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
4
Battery Bank:
Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 270
KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc.
The batteries must provide high-quality and achieving superior performance, the manufacturing date must be
new and not more than 6 months, suitable for every type of applications especially for solar renewable energy,
designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery
should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes
supply, install &connect Battery temp. sensor (BTS) and the following:
KWh 270
•All necessary DC cables between the batteries together and to the battery fuse box to have a complete
operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations
and all needed materials to complete the job. All DC cables must be sized in accordance with the installation
requirements applicable on site ,the allowable voltage drop must be less than 1%.
•Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to
finish the job. the rack must be enough to carry all the weight of the required batteries for the system.
•The contractor must submit manufacturer warranty for each battery cell for a period 10 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
5
PV Mounting structure:
Supply and install Module mounting structure from Aluminium profile structures to fix the photovoltaic panels
on the roof including profiles composed of extruded aluminium, rivets with seal of an aluminium body and
shank, a neoprene rubber seal and all accessories and supports.
The structure must be suitable to the dimension of selected PV modules and PV numbers, the mounting
provides a fixed inclination of the modules 30 degree with vertical supports, plates, screws and casting
concrete foundations B250 (0.4*0.3*0.2) m3 for each leg, the structure profile includes bracing and double hot
galvanized angles for dividers.
The mounting structures and the foundations must be designed structurally to be suitable to withstand all static
loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting
structure components are bonded together to guaranty potential equalization.
L.S 1
All works and materials must be according to drawings, specifications and supervisor instructions and
approval.
6
Battery Fuse Box:
Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to
protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall
mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery
side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the
battery bank and to the fuse box and from the fuse box to the batteryinverters to have a complete operational
circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC
cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage
drop must be less than 1%.
•The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3
years.(Type is SMA or equivalent).
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
No 3
Photovoltaic Solar System for Jamal Abd Alnasser School
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
7
AC Air Condition:
Supply , install, test and commission air conditioning Inverter type Split Unit, composed of outdoor unit. filled
with environment friendly refrigerant such as (R410, R407c,..) and COP not less than 3.5,Condensing unit
shall be complete with Inverter compressor/s & air cooled condenser with fan, Well supported on hot
galvanized steel base on the roof, indoor unit with plasma filter as indicated on drawings to be tights installed
completed with all necessary supports, hangers, drain pipes from indoor unit to the nearest floor drain, ( PVC
Ø 1"), cupper pipes , sleeves, thermostat , Remote control and including Isolation Switch MOELLER and all
required electrical power cables from SDB to the unit according to drawings and engineers approval.
CAPACITY:(12000 BTU/HR).
(Type is ELECTRA or equivalent ) .
No 1
8
3-Phase Digital KWH Meter:
Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to
have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect
with the Monitoring System .All works and materials must be according to the drawings, catalogues,
specifications and supervisor engineer instruction’s and approval.
No 2
9
Earthing System For Battery Banks:
Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be
separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes
15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2
flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to
complete the system as specifications and supervisor engineer instruction’s and approval.
Unit 1
10
Earthing for PV Solar System:
Supply,install,connect and operate complete independent earthing system for PV solar system, must be
separated of the main earthing system to obtain 2 ohm max resistance.
the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints,
clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system
components to the electrode to complete the system as specifications and supervisor engineer instruction’s and
approval.
Unit 2
Total Of Bill (1) - US$
Photovoltaic Solar System for Jamal Abd Alnasser School
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
Bill No (2)
Photovoltaic Solar System works
General:
• The system is designed to cover the Essential loads in Ali Bin Abi Taleb School
•The system will be grid interactive connected with battery backup system, which will allow many power
sources options. The system will import from the grid when loads are being more than the generated from PV
and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be
charged from Grid if PV output is not enough for loads and batteries.
•Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar
system works,including a single line diagram showing all the components of the PV system, DC and AC
distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section
for all the system to be approved by the Engineer before executing the work.
•Contractor shall submit the catalogs of each component showing the requested specifications stated at the
bill of quantity.
•The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics,
test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and
manufacturers warranty for each components of the system.
• As-built drawings shall be submitted after handing over the work.
• All junction boxes and DBs will be lockable type.
•Upon completion of the installation, the contractor shall organize an on site training program involving
nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of
the training shall be deemed to have been included in the tendered rates.
•The price includes all builders’ works, making good and reinstatement including necessary materials and
workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete
the job successfully.
• All the following items include supply, install, commission and operate of the complete PV solar system.
• The work includes maintenance period for each device according to BOQ and Specifications.
1
PV Modules – 38 Kwp:
Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all
material needed to have complete job ready for installing high quality PV modules with total arrays capacity to
achieve 38 KWp. The item Includes supply, install &connect the following:
• Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars
,terminals, ducts or trays, supports &labels suitable to the PV arrays loads.
•Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have
a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC
plug and socket connectors . The DC cables must be sized in accordance with the installation requirements
applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%.
KWp 38
•The price includes all works, making good and reinstatement including necessary materials and
workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete
the job successfully.
• Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years.
• Contractor must submit all the required certificates for each PV solar panel from.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for Ali Bin Abi Taleb School
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
2
Inverters – 40 KW:
Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with
Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the
system design and installation proposed and for the future extended also. (Type is SMA or equivalent).
The DC max power input rating should be equal or more than 40 KW of the PV modules capacity at standard
test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65.
The inverter AC nominal power output rating must be equal or greater than 40 KW compatible with the AC
loads design.The inverter must include the safety concepts such as (triple protection with optiprotect,
electronic strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max
availability. Total inverter capacity must be devided at least 3 inverters. The price includes :
Unit 1
•Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially
compatible with the inverters, with all needed accessories, interface modules & data cables and all connections
needed to complete and connect the monitoring system to internet.
•Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements
and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations
end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC
cables between inverters and PV system not less than 1%.
•Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical
cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the
main distribution panel according to the engineer's instruction and approval and have a complete job.
•The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
3
Battery Inverters – 50 KW:
Supply, install, connect and operate Battery Inverters compatible with on grid inverter rated power 50 Kw with
all necessary (Grid-Connect Automatic Transfer Control Box),interface modules and connections for
masters & slaves , electrical cables and data communication unit with Ethernet connection, connectable in
parallel and modularly extendable. (Type is SMA or equivalent).
The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency,
intelligent battery management for maximum battery life, charge level calculation, extreme overload capability,
and battery temperature sensing and battery current measurements).Total battery inverters capacity must be
compatible with the number of the inverters.
The price includes:
Unit 1
•Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data
& communication cables and connection needed to complete the job.
• Supply, install and connect:
DC cables appropriately sized in accordance with the installation requirements to connect the battery inverters
with DC battery fuses box.
AC electrical cables to connect the battery inverters with the main distribution panel(AC Out).
the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a
complete job,
• The allowable voltage drop for DC cables between battery inverter and batteries less than 1%.
•The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5
years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for Ali Bin Abi Taleb School
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
4
Battery Bank :
Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 200
KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc.
The batteries must provide high-quality and achieving superior performance, the manufacturing date must be
new and not more than 6 months, suitable for every type of applications especially for solar renewable energy,
designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery
should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes
supply, install &connect Battery temp. sensor (BTS) and the following:
KWh 200
•All necessary DC cables between the batteries together and to the battery fuse box to have a complete
operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations
and all needed materials to complete the job. All DC cables must be sized in accordance with the installation
requirements applicable on site ,the allowable voltage drop must be less than 1%.
•Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to
finish the job. the rack must be enough to carry all the weight of the required batteries for the system.
•The contractor must submit manufacturer warranty for each battery cell for a period 10 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
5
PV Mounting structure:
Supply and install Module mounting structure from hot galvanized steel profile foundation suitable to the
dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules
30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.4*0.2) m3 for
each leg, the structure profile includes bracing and double hot galvanized angles for dividers.
The mounting structures and the foundations must be designed structurally to be suitable to withstand all static
loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting
structure components are bonded together to guaranty potential equalization.
L.S 1
All works and materials must be according to drawings, specifications and supervisor instructions and
approval.
6
Battery Fuse Box:
Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to
protect the battery connections of the inverters . The box must be water proof protection with IP65, simple
wall mounting, suitable connections for three battery inverters and up to six DC connections inlet on the
battery side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables
from the battery bank and to the fuse box and from the fuse box to the battery inverters to have a complete
operational circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to
fix, all DC cables must be sized in accordance with the installation requirements applicable on site ,the
allowable voltage drop must be less than 1%.
•The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3
years. (Type is SMA or equivalent).
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
No 3
Photovoltaic Solar System for Ali Bin Abi Taleb School
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
7
AC Air Condition:
Supply , install, test and commission air conditioning Inverter type Split Unit, composed of outdoor unit. filled
with environment friendly refrigerant such as (R410, R407c,..) and COP not less than 3.5,Condensing unit
shall be complete with Inverter compressor/s & air cooled condenser with fan, Well supported on hot
galvanized steel base on the roof, indoor unit with plasma filter as indicated on drawings to be tights installed
completed with all necessary supports, hangers, drain pipes from indoor unit to the nearest floor drain, ( PVC
Ø 1"), cupper pipes , sleeves, thermostat , Remote control and including Isolation Switch MOELLER and all
required electrical power cables from SDB to the unit according to drawings and engineers approval.
CAPACITY:(12000 BTU/HR).
(Type is ELECTRA or equivalent ) .
No 1
8
3-Phase Digital KWH Meter:
Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to
have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect
with the Monitoring System .All works and materials must be according to the drawings, catalogues,
specifications and supervisor engineer instruction’s and approval.
No 2
9
Earthing System For Battery Banks:
Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be
separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes
15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2
flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to
complete the system as specifications and supervisor engineer instruction’s and approval.
Unit 1
10
Earthing for PV Solar System:
Supply,install,connect and operate complete independent earthing system for PV solar system, must be
separated of the main earthing system to obtain 2 ohm max resistance.
the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints,
clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system
components to the electrode to complete the system as specifications and supervisor engineer instruction’s
and approval.
Unit 2
Total Of Bill (2) - US$
Photovoltaic Solar System for Ali Bin Abi Taleb School
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
Bill No (4)
Photovoltaic Solar System works
General:
• The system is designed to cover the Essential loads in KHANYOUNIS SECONDARY GIRLS SCHOOL
•The system will be grid interactive connected with battery backup system, which will allow many power
sources options. The system will import from the grid when loads are being more than the generated from PV
and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be
charged from Grid if PV output is not enough for loads and batteries.
•Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar
system works,including a single line diagram showing all the components of the PV system, DC and AC
distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section
for all the system to be approved by the Engineer before executing the work.
•Contractor shall submit the catalogs of each component showing the requested specifications stated at the
bill of quantity.
•The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics,
test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and
manufacturers warrantyfor each components of the system.
• As-built drawings shall be submitted after handing over the work.
• All junction boxes and DBs will be lockable type.
•Upon completion of the installation, the contractor shall organize an on site training program involving
nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of
the training shall be deemed to have been included in the tendered rates.
•The price includes all builders’ works, making good and reinstatement including necessary materials and
workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete
the job successfully.
• All the following items include supply, install, commission and operate of the complete PV solar system.
• The work includes maintenance period for each device according to BOQ and Specifications.
1
PV Modules – 25 Kwp:
Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all
material needed to have complete job ready for installing high quality PV modules with total arrays capacity to
achieve 25 KWp. The item Includes supply, install &connect the following:
• Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars
,terminals, ducts or trays, supports &labels suitable to the PV arrays loads.
•Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have
a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC
plug and socket connectors . The DC cables must be sized in accordance with the installation requirements
applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%.
KWp 25
•The price includes all works, making good and reinstatement including necessary materials and workmanship
as well as removal of unwanted materials to dump sites approved by the engineer to complete the job
successfully.
• Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years.
• Contractor must submit all the required certificates for each PV solar panel from.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for KHANYOUNIS SECONDARY GIRLS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
2
Inverters – 30 KW:
Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with
Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the
system design and installation proposed and for the future extended also. (Type is SMA or equivalent).
The DC max power input rating should be equal or more than 30 KW of the PV modules capacity at standard
test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65.
The inverter AC nominal power output rating must be equal or greater than 30 KW compatible with the AC
loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic
strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total
inverter capacity must be devided at least 2 inverters. The price includes :
Unit 1
•Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially
compatible with the inverters, with all needed accessories, interface modules & data cables and all connections
needed to complete and connect the monitoring system to internet.
•Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements
and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations
end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC
cables between inverters and PV system not less than 1%.
•Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical
cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the
main distribution panel according to the engineer's instruction and approval and have a complete job.
•The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
3
Battery Inverter – 6 KW:
Supply, install, connect and operate Battery Inverter compatible with on grid inverters with total rated power 6
Kw with all necessary interface modules and connections for masters & slaves , electrical cables and data
communication unit,router with Ethernet connection, connectable in parallel and modularly extendable. (Type
is SMA or equivalent).
The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency,
intelligent battery management for maximum battery life, charge level calculation, extreme overload
capability, and batterytemperature sensing and battery current measurements).
The price includes:
No 3
•Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data
& communication cables and connection needed to complete the job.
• Supply, install and connect:
DC cables appropriately sized in accordance with the installation requirements to connect the batteryinverters
with DC battery fuses box.
AC electrical cables to connect the battery inverters with the main distribution panel(AC Out).
the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a
complete job,
• The allowable voltage drop for DC cables between battery inverter and batteries less than 1%.
•The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5
years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for KHANYOUNIS SECONDARY GIRLS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
4
Battery Bank:
Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 120
KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc.
The batteries must provide high-quality and achieving superior performance, the manufacturing date must be
new and not more than 6 months, suitable for every type of applications especially for solar renewable energy,
designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery
should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes
supply, install &connect Battery temp. sensor (BTS) and the following:
KWh 120
•All necessary DC cables between the batteries together and to the battery fuse box to have a complete
operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations
and all needed materials to complete the job. All DC cables must be sized in accordance with the installation
requirements applicable on site ,the allowable voltage drop must be less than 1%.
•Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to
finish the job. the rack must be enough to carry all the weight of the required batteries for the system.
•The contractor must submit manufacturer warranty for each battery cell for a period 10 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
5
PV Mounting structure:
Supply and install Module mounting structure from hot galvanized steel profile foundation suitable to the
dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules
30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.4*0.2) m3 for
each leg, the structure profile includes bracing and double hot galvanized angles for dividers.
The mounting structures and the foundations must be designed structurally to be suitable to withstand all static
loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting
structure components are bonded together to guaranty potential equalization.
L.S 1
All works and materials must be according to drawings, specifications and supervisor instructions and
approval.
6
Battery Fuse Box:
Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to
protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall
mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery
side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the
battery bank and to the fuse box and from the fuse box to the batteryinverters to have a complete operational
circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC
cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage
drop must be less than 1%.
•The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3
years. (Type is SMA or equivalent).
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
No 1
Photovoltaic Solar System for KHANYOUNIS SECONDARY GIRLS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
7
Wall mounted exhaust:
Supply, install, connect and operate wall mounted exhaust fan of 8" diameter Capacity (500 cfm) type is
(VENTA or equivalent ) at static pressure 60 Pascal for the battery room , to be tightly installed complete with
all necessary supports ,cover and an louvers, and all required electrical cables, conduits, mcb 10A and needed
to fix, all according engineer’s approval. The price shall include opening duct in the block for the fan,
plastering, painting, repair all damages and all other materials needed to have a complete job ready according
to the engineer's instruction and approval.
No 1
8
3-Phase Digital KWH Meter:
Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to
have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect
with the Monitoring System .All works and materials must be according to the drawings, catalogues,
specifications and supervisor engineer instruction’s and approval.
No 2
9
Earthing System For Battery Banks:
Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be
separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes
15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2
flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to
complete the system as specifications and supervisor engineer instruction’s and approval.
Unit 1
10
Earthing for PV Solar System:
Supply,install,connect and operate complete independent earthing system for PV solar system, must be
separated of the main earthing system to obtain 2 ohm max resistance.
the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints,
clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system
components to the electrode to complete the system as specifications and supervisor engineer instruction’s and
approval.
Unit 2
Total Of Bill (3) - US$
Photovoltaic Solar System for KHANYOUNIS SECONDARY GIRLS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
Bill No (3)
Photovoltaic Solar System works
General:
• The system is designed to cover the Essential loads in ALMOTANABY PRIMARY BOYS SCHOOL
•The system will be grid interactive connected with battery backup system, which will allow many power
sources options. The system will import from the grid when loads are being more than the generated from PV
and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be
charged from Grid if PV output is not enough for loads and batteries.
•Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar
system works,including a single line diagram showing all the components of the PV system, DC and AC
distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section
for all the system to be approved by the Engineer before executing the work.
•Contractor shall submit the catalogs of each component showing the requested specifications stated at the
bill of quantity.
•The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics,
test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and
manufacturers warrantyfor each components of the system.
• As-built drawings shall be submitted after handing over the work.
• All junction boxes and DBs will be lockable type.
•Upon completion of the installation, the contractor shall organize an on site training program involving
nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of
the training shall be deemed to have been included in the tendered rates.
•The price includes all builders’ works, making good and reinstatement including necessary materials and
workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete
the job successfully.
• All the following items include supply, install, commission and operate of the complete PV solar system.
• The work includes maintenance period for each device according to BOQ and Specifications.
1
PV Modules – 25 Kwp:
Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all
material needed to have complete job ready for installing high quality PV modules with total arrays capacity to
achieve 25 KWp. The item Includes supply, install &connect the following:
• Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars
,terminals, ducts or trays, supports &labels suitable to the PV arrays loads.
•Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have
a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC
plug and socket connectors . The DC cables must be sized in accordance with the installation requirements
applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%.
KWp 25
•The price includes all works, making good and reinstatement including necessary materials and workmanship
as well as removal of unwanted materials to dump sites approved by the engineer to complete the job
successfully.
• Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years.
• Contractor must submit all the required certificates for each PV solar panel from.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for ALMOTANABY PRIMARY BOYS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
2
Inverters – 30 KW:
Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with
Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the
system design and installation proposed and for the future extended also. (Type is SMA or equivalent).
The DC max power input rating should be equal or more than 30 KW of the PV modules capacity at standard
test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65.
The inverter AC nominal power output rating must be equal or greater than 30 KW compatible with the AC
loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic
strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total
inverter capacity must be devided at least 2 inverters. The price includes :
Unit 1
•Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially
compatible with the inverters, with all needed accessories, interface modules & data cables and all connections
needed to complete and connect the monitoring system to internet.
•Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements
and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations
end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC
cables between inverters and PV system not less than 1%.
•Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical
cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the
main distribution panel according to the engineer's instruction and approval and have a complete job.
•The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
3
Battery Inverter – 6 KW:
Supply, install, connect and operate Battery Inverter compatible with on grid inverters with total rated power 6
Kw with all necessary interface modules and connections for masters & slaves , electrical cables and data
communication unit,router with Ethernet connection, connectable in parallel and modularly extendable. (Type
is SMA or equivalent).
The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency,
intelligent battery management for maximum battery life, charge level calculation, extreme overload
capability, and batterytemperature sensing and battery current measurements).
The price includes:
No 3
•Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data
& communication cables and connection needed to complete the job.
• Supply, install and connect:
DC cables appropriately sized in accordance with the installation requirements to connect the batteryinverters
with DC battery fuses box.
AC electrical cables to connect the battery inverters with the main distribution panel(AC Out).
the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a
complete job,
• The allowable voltage drop for DC cables between battery inverter and batteries less than 1%.
•The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5
years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for ALMOTANABY PRIMARY BOYS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
4
Battery Bank:
Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 120
KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc.
The batteries must provide high-quality and achieving superior performance, the manufacturing date must be
new and not more than 6 months, suitable for every type of applications especially for solar renewable energy,
designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery
should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes
supply, install &connect Battery temp. sensor (BTS) and the following:
KWh 120
•All necessary DC cables between the batteries together and to the battery fuse box to have a complete
operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations
and all needed materials to complete the job. All DC cables must be sized in accordance with the installation
requirements applicable on site ,the allowable voltage drop must be less than 1%.
•Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to
finish the job. the rack must be enough to carry all the weight of the required batteries for the system.
•The contractor must submit manufacturer warranty for each battery cell for a period 10 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
5
PV Mounting structure:
Supply and install Module mounting structure from hot galvanized steel profile foundation suitable to the
dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules
30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.4*0.2) m3 for
each leg, the structure profile includes bracing and double hot galvanized angles for dividers.
The mounting structures and the foundations must be designed structurally to be suitable to withstand all static
loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting
structure components are bonded together to guaranty potential equalization.
L.S 1
All works and materials must be according to drawings, specifications and supervisor instructions and
approval.
6
Battery Fuse Box:
Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to
protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall
mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery
side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the
battery bank and to the fuse box and from the fuse box to the batteryinverters to have a complete operational
circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC
cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage
drop must be less than 1%.
•The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3
years. (Type is SMA or equivalent).
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
No 1
Photovoltaic Solar System for ALMOTANABY PRIMARY BOYS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
7
Wall mounted exhaust:
Supply, install, connect and operate wall mounted exhaust fan of 8" diameter Capacity (500 cfm) type is
(VENTA or equivalent ) at static pressure 60 Pascal for the battery room , to be tightly installed complete with
all necessary supports ,cover and an louvers, and all required electrical cables, conduits, mcb 10A and needed
to fix, all according engineer’s approval. The price shall include opening duct in the block for the fan,
plastering, painting, repair all damages and all other materials needed to have a complete job ready according
to the engineer's instruction and approval.
No 1
8
3-Phase Digital KWH Meter:
Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to
have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect
with the Monitoring System .All works and materials must be according to the drawings, catalogues,
specifications and supervisor engineer instruction’s and approval.
No 2
9
Earthing System For Battery Banks:
Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be
separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes
15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2
flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to
complete the system as specifications and supervisor engineer instruction’s and approval.
Unit 1
10
Earthing for PV Solar System:
Supply,install,connect and operate complete independent earthing system for PV solar system, must be
separated of the main earthing system to obtain 2 ohm max resistance.
the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints,
clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system
components to the electrode to complete the system as specifications and supervisor engineer instruction’s and
approval.
Unit 2
Total Of Bill (4) - US$
Photovoltaic Solar System for ALMOTANABY PRIMARY BOYS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
Bill No (5)
Photovoltaic Solar System works
General:
• The system is designed to cover the Essential loads in Al Ma'ari Primary Boys School
•The system will be grid interactive connected with battery backup system, which will allow many power
sources options. The system will import from the grid when loads are being more than the generated from PV
and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be
charged from Grid if PV output is not enough for loads and batteries.
•Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar
system works,including a single line diagram showing all the components of the PV system, DC and AC
distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section
for all the system to be approved by the Engineer before executing the work.
•Contractor shall submit the catalogs of each component showing the requested specifications stated at the
bill of quantity.
•The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics,
test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and
manufacturers warrantyfor each components of the system.
• As-built drawings shall be submitted after handing over the work.
• All junction boxes and DBs will be lockable type.
•Upon completion of the installation, the contractor shall organize an on site training program involving
nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of
the training shall be deemed to have been included in the tendered rates.
•The price includes all builders’ works, making good and reinstatement including necessary materials and
workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete
the job successfully.
• All the following items include supply, install, commission and operate of the complete PV solar system.
• The work includes maintenance period for each device according to BOQ and Specifications.
1
PV Modules – 25 Kwp:
Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all
material needed to have complete job ready for installing high quality PV modules with total arrays capacity to
achieve 25 KWp. The item Includes supply, install &connect the following:
• Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars
,terminals, ducts or trays, supports &labels suitable to the PV arrays loads.
•Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have
a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC
plug and socket connectors . The DC cables must be sized in accordance with the installation requirements
applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%.
KWp 25
•The price includes all works, making good and reinstatement including necessary materials and workmanship
as well as removal of unwanted materials to dump sites approved by the engineer to complete the job
successfully.
• Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years.
• Contractor must submit all the required certificates for each PV solar panel from.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for Al Ma'ari Primary Boys School
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
2
Inverters – 30 KW:
Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with
Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the
system design and installation proposed and for the future extended also. (Type is SMA or equivalent).
The DC max power input rating should be equal or more than 30 KW of the PV modules capacity at standard
test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65.
The inverter AC nominal power output rating must be equal or greater than 30 KW compatible with the AC
loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic
strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total
inverter capacity must be devided at least 2 inverters. The price includes :
Unit 1
•Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially
compatible with the inverters, with all needed accessories, interface modules & data cables and all connections
needed to complete and connect the monitoring system to internet.
•Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements
and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations
end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC
cables between inverters and PV system not less than 1%.
•Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical
cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the
main distribution panel according to the engineer's instruction and approval and have a complete job.
•The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
3
Battery Inverter – 6 KW:
Supply, install, connect and operate Battery Inverter compatible with on grid inverters with total rated power 6
Kw with all necessary interface modules and connections for masters & slaves , electrical cables and data
communication unit,router with Ethernet connection, connectable in parallel and modularly extendable. (Type
is SMA or equivalent).
The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency,
intelligent battery management for maximum battery life, charge level calculation, extreme overload
capability, and batterytemperature sensing and battery current measurements).
The price includes:
No 3
•Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data
& communication cables and connection needed to complete the job.
• Supply, install and connect:
DC cables appropriately sized in accordance with the installation requirements to connect the batteryinverters
with DC battery fuses box.
AC electrical cables to connect the battery inverters with the main distribution panel(AC Out).
the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a
complete job,
• The allowable voltage drop for DC cables between battery inverter and batteries less than 1%.
•The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5
years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for Al Ma'ari Primary Boys School
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
4
Battery Bank:
Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 120
KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc.
The batteries must provide high-quality and achieving superior performance, the manufacturing date must be
new and not more than 6 months, suitable for every type of applications especially for solar renewable energy,
designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery
should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes
supply, install &connect Battery temp. sensor (BTS) and the following:
KWh 120
•All necessary DC cables between the batteries together and to the battery fuse box to have a complete
operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations
and all needed materials to complete the job. All DC cables must be sized in accordance with the installation
requirements applicable on site ,the allowable voltage drop must be less than 1%.
•Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to
finish the job. the rack must be enough to carry all the weight of the required batteries for the system.
•The contractor must submit manufacturer warranty for each battery cell for a period 10 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
5
PV Mounting structure:
Supply and install Module mounting structure from hot galvanized steel profile foundation suitable to the
dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules
30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.4*0.2) m3 for
each leg, the structure profile includes bracing and double hot galvanized angles for dividers.
The mounting structures and the foundations must be designed structurally to be suitable to withstand all static
loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting
structure components are bonded together to guaranty potential equalization.
L.S 1
All works and materials must be according to drawings, specifications and supervisor instructions and
approval.
6
Battery Fuse Box:
Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to
protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall
mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery
side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the
battery bank and to the fuse box and from the fuse box to the batteryinverters to have a complete operational
circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC
cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage
drop must be less than 1%.
•The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3
years. (Type is SMA or equivalent).
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
No 1
Photovoltaic Solar System for Al Ma'ari Primary Boys School
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
7
Wall mounted exhaust:
Supply, install, connect and operate wall mounted exhaust fan of 8" diameter Capacity (500 cfm) type is
(VENTA or equivalent ) at static pressure 60 Pascal for the battery room , to be tightly installed complete with
all necessary supports ,cover and an louvers, and all required electrical cables, conduits, mcb 10A and needed
to fix, all according engineer’s approval. The price shall include opening duct in the block for the fan,
plastering, painting, repair all damages and all other materials needed to have a complete job ready according
to the engineer's instruction and approval.
No 1
8
3-Phase Digital KWH Meter:
Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to
have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect
with the Monitoring System .All works and materials must be according to the drawings, catalogues,
specifications and supervisor engineer instruction’s and approval.
No 2
9
Earthing System For Battery Banks:
Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be
separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes
15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2
flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to
complete the system as specifications and supervisor engineer instruction’s and approval.
Unit 1
10
Earthing for PV Solar System:
Supply,install,connect and operate complete independent earthing system for PV solar system, must be
separated of the main earthing system to obtain 2 ohm max resistance.
the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints,
clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system
components to the electrode to complete the system as specifications and supervisor engineer instruction’s and
approval.
Unit 2
Total Of Bill (5) - US$
Photovoltaic Solar System for Al Ma'ari Primary Boys School
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
Bill No (6)
Photovoltaic Solar System works
General:
• The system is designed to cover the Essential loads in SHEJAIAA PRIMARY BOYS SCHOOL
•The system will be grid interactive connected with battery backup system, which will allow many power
sources options. The system will import from the grid when loads are being more than the generated from PV
and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be
charged from Grid if PV output is not enough for loads and batteries.
•Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar
system works,including a single line diagram showing all the components of the PV system, DC and AC
distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section
for all the system to be approved by the Engineer before executing the work.
•Contractor shall submit the catalogs of each component showing the requested specifications stated at the
bill of quantity.
•The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics,
test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and
manufacturers warrantyfor each components of the system.
• As-built drawings shall be submitted after handing over the work.
• All junction boxes and DBs will be lockable type.
•Upon completion of the installation, the contractor shall organize an on site training program involving
nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of
the training shall be deemed to have been included in the tendered rates.
•The price includes all builders’ works, making good and reinstatement including necessary materials and
workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete
the job successfully.
• All the following items include supply, install, commission and operate of the complete PV solar system.
• The work includes maintenance period for each device according to BOQ and Specifications.
1
PV Modules – 25 Kwp:
Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all
material needed to have complete job ready for installing high quality PV modules with total arrays capacity to
achieve 25 KWp. The item Includes supply, install &connect the following:
• Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars
,terminals, ducts or trays, supports &labels suitable to the PV arrays loads.
•Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have
a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC
plug and socket connectors . The DC cables must be sized in accordance with the installation requirements
applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%.
KWp 25
•The price includes all works, making good and reinstatement including necessary materials and workmanship
as well as removal of unwanted materials to dump sites approved by the engineer to complete the job
successfully.
• Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years.
• Contractor must submit all the required certificates for each PV solar panel from.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for SHEJAIAA PRIMARY BOYS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
2
Inverters – 30 KW:
Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with
Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the
system design and installation proposed and for the future extended also. (Type is SMA or equivalent).
The DC max power input rating should be equal or more than 30 KW of the PV modules capacity at standard
test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65.
The inverter AC nominal power output rating must be equal or greater than 30 KW compatible with the AC
loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic
strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total
inverter capacity must be devided at least 2 inverters. The price includes :
Unit 1
•Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially
compatible with the inverters, with all needed accessories, interface modules & data cables and all connections
needed to complete and connect the monitoring system to internet.
•Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements
and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations
end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC
cables between inverters and PV system not less than 1%.
•Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical
cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the
main distribution panel according to the engineer's instruction and approval and have a complete job.
•The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
3
Battery Inverter – 6 KW:
Supply, install, connect and operate Battery Inverter compatible with on grid inverters with total rated power 6
Kw with all necessary interface modules and connections for masters & slaves , electrical cables and data
communication unit,router with Ethernet connection, connectable in parallel and modularly extendable. (Type
is SMA or equivalent).
The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency,
intelligent battery management for maximum battery life, charge level calculation, extreme overload
capability, and batterytemperature sensing and battery current measurements).
The price includes:
No 3
•Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data
& communication cables and connection needed to complete the job.
• Supply, install and connect:
DC cables appropriately sized in accordance with the installation requirements to connect the batteryinverters
with DC battery fuses box.
AC electrical cables to connect the battery inverters with the main distribution panel(AC Out).
the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a
complete job,
• The allowable voltage drop for DC cables between battery inverter and batteries less than 1%.
•The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5
years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for SHEJAIAA PRIMARY BOYS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
4
Battery Bank:
Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 120
KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc.
The batteries must provide high-quality and achieving superior performance, the manufacturing date must be
new and not more than 6 months, suitable for every type of applications especially for solar renewable energy,
designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery
should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes
supply, install &connect Battery temp. sensor (BTS) and the following:
KWh 120
•All necessary DC cables between the batteries together and to the battery fuse box to have a complete
operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations
and all needed materials to complete the job. All DC cables must be sized in accordance with the installation
requirements applicable on site ,the allowable voltage drop must be less than 1%.
•Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to
finish the job. the rack must be enough to carry all the weight of the required batteries for the system.
•The contractor must submit manufacturer warranty for each battery cell for a period 10 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
5
PV Mounting structure:
Supply and install Module mounting structure from hot galvanized steel profile foundation suitable to the
dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules
30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.4*0.2) m3 for
each leg, the structure profile includes bracing and double hot galvanized angles for dividers.
The mounting structures and the foundations must be designed structurally to be suitable to withstand all static
loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting
structure components are bonded together to guaranty potential equalization.
L.S 1
All works and materials must be according to drawings, specifications and supervisor instructions and
approval.
6
Battery Fuse Box:
Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to
protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall
mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery
side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the
battery bank and to the fuse box and from the fuse box to the batteryinverters to have a complete operational
circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC
cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage
drop must be less than 1%.
•The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3
years. (Type is SMA or equivalent).
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
No 1
Photovoltaic Solar System for SHEJAIAA PRIMARY BOYS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
7
Wall mounted exhaust:
Supply, install, connect and operate wall mounted exhaust fan of 8" diameter Capacity (500 cfm) type is
(VENTA or equivalent ) at static pressure 60 Pascal for the battery room , to be tightly installed complete with
all necessary supports ,cover and an louvers, and all required electrical cables, conduits, mcb 10A and needed
to fix, all according engineer’s approval. The price shall include opening duct in the block for the fan,
plastering, painting, repair all damages and all other materials needed to have a complete job ready according
to the engineer's instruction and approval.
No 1
8
3-Phase Digital KWH Meter:
Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to
have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect
with the Monitoring System .All works and materials must be according to the drawings, catalogues,
specifications and supervisor engineer instruction’s and approval.
No 2
9
Earthing System For Battery Banks:
Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be
separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes
15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2
flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to
complete the system as specifications and supervisor engineer instruction’s and approval.
Unit 1
10
Earthing for PV Solar System:
Supply,install,connect and operate complete independent earthing system for PV solar system, must be
separated of the main earthing system to obtain 2 ohm max resistance.
the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints,
clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system
components to the electrode to complete the system as specifications and supervisor engineer instruction’s and
approval.
Unit 2
Total Of Bill (6) - US$
Photovoltaic Solar System for SHEJAIAA PRIMARY BOYS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
Bill No (7)
Photovoltaic Solar System works
General:
• The system is designed to cover the Essential loads in ABU TAMMAM PRIMARY BOYS SCHOOL
•The system will be grid interactive connected with battery backup system, which will allow many power
sources options. The system will import from the grid when loads are being more than the generated from PV
and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be
charged from Grid if PV output is not enough for loads and batteries.
•Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar
system works,including a single line diagram showing all the components of the PV system, DC and AC
distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section
for all the system to be approved by the Engineer before executing the work.
•Contractor shall submit the catalogs of each component showing the requested specifications stated at the
bill of quantity.
•The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics,
test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and
manufacturers warrantyfor each components of the system.
• As-built drawings shall be submitted after handing over the work.
• All junction boxes and DBs will be lockable type.
•Upon completion of the installation, the contractor shall organize an on site training program involving
nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of
the training shall be deemed to have been included in the tendered rates.
•The price includes all builders’ works, making good and reinstatement including necessary materials and
workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete
the job successfully.
• All the following items include supply, install, commission and operate of the complete PV solar system.
• The work includes maintenance period for each device according to BOQ and Specifications.
1
PV Modules – 25 Kwp:
Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all
material needed to have complete job ready for installing high quality PV modules with total arrays capacity to
achieve 25 KWp. The item Includes supply, install &connect the following:
• Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars
,terminals, ducts or trays, supports &labels suitable to the PV arrays loads.
•Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have
a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC
plug and socket connectors . The DC cables must be sized in accordance with the installation requirements
applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%.
KWp 25
•The price includes all works, making good and reinstatement including necessary materials and workmanship
as well as removal of unwanted materials to dump sites approved by the engineer to complete the job
successfully.
• Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years.
• Contractor must submit all the required certificates for each PV solar panel from.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for ABU TAMMAM PRIMARY BOYS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
2
Inverters – 30 KW:
Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with
Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the
system design and installation proposed and for the future extended also. (Type is SMA or equivalent).
The DC max power input rating should be equal or more than 30 KW of the PV modules capacity at standard
test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65.
The inverter AC nominal power output rating must be equal or greater than 30 KW compatible with the AC
loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic
strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total
inverter capacity must be devided at least 2 inverters. The price includes :
Unit 1
•Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially
compatible with the inverters, with all needed accessories, interface modules & data cables and all connections
needed to complete and connect the monitoring system to internet.
•Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements
and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations
end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC
cables between inverters and PV system not less than 1%.
•Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical
cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the
main distribution panel according to the engineer's instruction and approval and have a complete job.
•The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
3
Battery Inverter – 6 KW:
Supply, install, connect and operate Battery Inverter compatible with on grid inverters with total rated power 6
Kw with all necessary interface modules and connections for masters & slaves , electrical cables and data
communication unit,router with Ethernet connection, connectable in parallel and modularly extendable. (Type
is SMA or equivalent).
The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency,
intelligent battery management for maximum battery life, charge level calculation, extreme overload
capability, and batterytemperature sensing and battery current measurements).
The price includes:
No 3
•Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data
& communication cables and connection needed to complete the job.
• Supply, install and connect:
DC cables appropriately sized in accordance with the installation requirements to connect the batteryinverters
with DC battery fuses box.
AC electrical cables to connect the battery inverters with the main distribution panel(AC Out).
the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a
complete job,
• The allowable voltage drop for DC cables between battery inverter and batteries less than 1%.
•The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5
years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
Photovoltaic Solar System for ABU TAMMAM PRIMARY BOYS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
4
Battery Bank:
Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 120
KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc.
The batteries must provide high-quality and achieving superior performance, the manufacturing date must be
new and not more than 6 months, suitable for every type of applications especially for solar renewable energy,
designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery
should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes
supply, install &connect Battery temp. sensor (BTS) and the following:
KWh 120
•All necessary DC cables between the batteries together and to the battery fuse box to have a complete
operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations
and all needed materials to complete the job. All DC cables must be sized in accordance with the installation
requirements applicable on site ,the allowable voltage drop must be less than 1%.
•Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to
finish the job. the rack must be enough to carry all the weight of the required batteries for the system.
•The contractor must submit manufacturer warranty for each battery cell for a period 10 years.
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
5
PV Mounting structure:
Supply and install Module mounting structure from hot galvanized steel profile foundation suitable to the
dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules
30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.4*0.2) m3 for
each leg, the structure profile includes bracing and double hot galvanized angles for dividers.
The mounting structures and the foundations must be designed structurally to be suitable to withstand all static
loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting
structure components are bonded together to guaranty potential equalization.
L.S 1
All works and materials must be according to drawings, specifications and supervisor instructions and
approval.
6
Battery Fuse Box:
Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to
protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall
mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery
side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the
battery bank and to the fuse box and from the fuse box to the batteryinverters to have a complete operational
circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC
cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage
drop must be less than 1%.
•The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3
years. (Type is SMA or equivalent).
All works and materials must be according to the drawings, specifications and supervisor engineer
instruction’s and approval.
No 1
Photovoltaic Solar System for ABU TAMMAM PRIMARY BOYS SCHOOL
Item
No.
Description Unit Quantity
Unit Rate
US $
(Numbers)
Total
Amount
US $
7
Wall mounted exhaust:
Supply, install, connect and operate wall mounted exhaust fan of 8" diameter Capacity (500 cfm) type is
(VENTA or equivalent ) at static pressure 60 Pascal for the battery room , to be tightly installed complete with
all necessary supports ,cover and an louvers, and all required electrical cables, conduits, mcb 10A and needed
to fix, all according engineer’s approval. The price shall include opening duct in the block for the fan,
plastering, painting, repair all damages and all other materials needed to have a complete job ready according
to the engineer's instruction and approval.
No 1
8
3-Phase Digital KWH Meter:
Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to
have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect
with the Monitoring System .All works and materials must be according to the drawings, catalogues,
specifications and supervisor engineer instruction’s and approval.
No 2
9
Earthing System For Battery Banks:
Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be
separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes
15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2
flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to
complete the system as specifications and supervisor engineer instruction’s and approval.
Unit 1
10
Earthing for PV Solar System:
Supply,install,connect and operate complete independent earthing system for PV solar system, must be
separated of the main earthing system to obtain 2 ohm max resistance.
the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints,
clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system
components to the electrode to complete the system as specifications and supervisor engineer instruction’s and
approval.
Unit 2
Total Of Bill (7) - US$
Photovoltaic Solar System for ABU TAMMAM PRIMARY BOYS SCHOOL
BOQ _UN.pptx
BOQ _UN.pptx
BOQ _UN.pptx
BOQ _UN.pptx
BOQ _UN.pptx
BOQ _UN.pptx
BOQ _UN.pptx
BOQ _UN.pptx

More Related Content

What's hot

planificacion instalac. y aplicaciones de la energia-4° año
planificacion  instalac. y aplicaciones de la energia-4° añoplanificacion  instalac. y aplicaciones de la energia-4° año
planificacion instalac. y aplicaciones de la energia-4° año
Alberto Vazquez
 
Wire Harness Test Simple
Wire Harness Test SimpleWire Harness Test Simple
Wire Harness Test Simple
Ron Spohrer
 
Electrical Deliverables - Interdisciplinary Interfaces
Electrical Deliverables - Interdisciplinary InterfacesElectrical Deliverables - Interdisciplinary Interfaces
Electrical Deliverables - Interdisciplinary Interfacesbiiswashruta
 
Senior Electrical Engineer CV
Senior Electrical Engineer CVSenior Electrical Engineer CV
Senior Electrical Engineer CVHosam Elbanna
 
Resume electrical engineer- for oil & gas
Resume  electrical engineer- for oil & gasResume  electrical engineer- for oil & gas
Resume electrical engineer- for oil & gas
vineeth ravi
 
Ahmed -solar engineer-cv
Ahmed -solar engineer-cvAhmed -solar engineer-cv
Ahmed -solar engineer-cv
Ahmed Abd El baqi
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
Fazlur Rahman
 
Contract - Construction Contracts and Specification
Contract - Construction Contracts and SpecificationContract - Construction Contracts and Specification
Contract - Construction Contracts and Specification
MANNU KUMAR
 
Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Vijay Kumar
 
Senior electrical engineer resume
Senior electrical engineer    resumeSenior electrical engineer    resume
Senior electrical engineer resume
VEERABHARATHI MUNI
 
TESTING AND COMMISSIONING ENGINEER
TESTING AND COMMISSIONING ENGINEERTESTING AND COMMISSIONING ENGINEER
TESTING AND COMMISSIONING ENGINEERsaravanan muthu
 
Resume - Electrical Engineer (MEP) 9+ Years Exp
Resume - Electrical Engineer (MEP) 9+ Years ExpResume - Electrical Engineer (MEP) 9+ Years Exp
Resume - Electrical Engineer (MEP) 9+ Years Exp
Subhash +966535838322
 
Muthukumar Civil engineer resume UPDATED (1).pdf
Muthukumar Civil engineer resume UPDATED (1).pdfMuthukumar Civil engineer resume UPDATED (1).pdf
Muthukumar Civil engineer resume UPDATED (1).pdf
MUTHUKUMAR428109
 
Planning For Engineering
Planning For EngineeringPlanning For Engineering
Planning For Engineering
Joe Kalchbrenner
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
Kai Yun Pang
 
Electrical Engineer Resume
Electrical Engineer ResumeElectrical Engineer Resume
Electrical Engineer Resume
Abdul Rahiman
 
CV- electrical engineer-Ismail1 (2) (1)
CV- electrical engineer-Ismail1 (2) (1)CV- electrical engineer-Ismail1 (2) (1)
CV- electrical engineer-Ismail1 (2) (1)Mohd ismail
 
1.arun das mep resume
1.arun das mep resume  1.arun das mep resume
1.arun das mep resume
Arun Das
 
Types of wiring diagram 22.pptx
Types of wiring diagram 22.pptxTypes of wiring diagram 22.pptx
Types of wiring diagram 22.pptx
JasonPDelosSantos
 

What's hot (20)

planificacion instalac. y aplicaciones de la energia-4° año
planificacion  instalac. y aplicaciones de la energia-4° añoplanificacion  instalac. y aplicaciones de la energia-4° año
planificacion instalac. y aplicaciones de la energia-4° año
 
Wire Harness Test Simple
Wire Harness Test SimpleWire Harness Test Simple
Wire Harness Test Simple
 
Electrical Deliverables - Interdisciplinary Interfaces
Electrical Deliverables - Interdisciplinary InterfacesElectrical Deliverables - Interdisciplinary Interfaces
Electrical Deliverables - Interdisciplinary Interfaces
 
Senior Electrical Engineer CV
Senior Electrical Engineer CVSenior Electrical Engineer CV
Senior Electrical Engineer CV
 
Resume electrical engineer- for oil & gas
Resume  electrical engineer- for oil & gasResume  electrical engineer- for oil & gas
Resume electrical engineer- for oil & gas
 
Ahmed -solar engineer-cv
Ahmed -solar engineer-cvAhmed -solar engineer-cv
Ahmed -solar engineer-cv
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
 
Contract - Construction Contracts and Specification
Contract - Construction Contracts and SpecificationContract - Construction Contracts and Specification
Contract - Construction Contracts and Specification
 
Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings
 
Senior electrical engineer resume
Senior electrical engineer    resumeSenior electrical engineer    resume
Senior electrical engineer resume
 
TESTING AND COMMISSIONING ENGINEER
TESTING AND COMMISSIONING ENGINEERTESTING AND COMMISSIONING ENGINEER
TESTING AND COMMISSIONING ENGINEER
 
Resume - Electrical Engineer (MEP) 9+ Years Exp
Resume - Electrical Engineer (MEP) 9+ Years ExpResume - Electrical Engineer (MEP) 9+ Years Exp
Resume - Electrical Engineer (MEP) 9+ Years Exp
 
Muthukumar Civil engineer resume UPDATED (1).pdf
Muthukumar Civil engineer resume UPDATED (1).pdfMuthukumar Civil engineer resume UPDATED (1).pdf
Muthukumar Civil engineer resume UPDATED (1).pdf
 
Planning For Engineering
Planning For EngineeringPlanning For Engineering
Planning For Engineering
 
Detailed engineering-design-phase
Detailed engineering-design-phaseDetailed engineering-design-phase
Detailed engineering-design-phase
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Electrical Engineer Resume
Electrical Engineer ResumeElectrical Engineer Resume
Electrical Engineer Resume
 
CV- electrical engineer-Ismail1 (2) (1)
CV- electrical engineer-Ismail1 (2) (1)CV- electrical engineer-Ismail1 (2) (1)
CV- electrical engineer-Ismail1 (2) (1)
 
1.arun das mep resume
1.arun das mep resume  1.arun das mep resume
1.arun das mep resume
 
Types of wiring diagram 22.pptx
Types of wiring diagram 22.pptxTypes of wiring diagram 22.pptx
Types of wiring diagram 22.pptx
 

Similar to BOQ _UN.pptx

66 k v_sf6_bkr_r3_may12
66 k v_sf6_bkr_r3_may1266 k v_sf6_bkr_r3_may12
66 k v_sf6_bkr_r3_may12
Yendapalli Chinnarao
 
11.docx
11.docx11.docx
Inspecting pv systems_for_code_compliance
Inspecting pv systems_for_code_complianceInspecting pv systems_for_code_compliance
Inspecting pv systems_for_code_compliance
Ankit Saxena
 
Inspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code ComplianceInspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code Compliance
JLanka Technologies (Pvt) Limited
 
INSTRUMENTATION ENGINNER - QC INSPECTOR ARAMCO SAP 70013071
INSTRUMENTATION ENGINNER - QC INSPECTOR ARAMCO SAP 70013071INSTRUMENTATION ENGINNER - QC INSPECTOR ARAMCO SAP 70013071
INSTRUMENTATION ENGINNER - QC INSPECTOR ARAMCO SAP 70013071Nithy Anantham
 
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantNet metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Harish Sharma
 
3D_Distribution transformer_Specification.pdf
3D_Distribution transformer_Specification.pdf3D_Distribution transformer_Specification.pdf
3D_Distribution transformer_Specification.pdf
ShahrukhKhan424745
 
Ahmed Rageh_CV (3)
Ahmed Rageh_CV (3)Ahmed Rageh_CV (3)
Ahmed Rageh_CV (3)Ahmed Rageh
 
Generator step-up and system intertie power transformers Securing high-qualit...
Generator step-up and system intertie power transformers Securing high-qualit...Generator step-up and system intertie power transformers Securing high-qualit...
Generator step-up and system intertie power transformers Securing high-qualit...
Krishna P. Sharma
 
Presentation 1
Presentation 1Presentation 1
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSTESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
Power System Operation
 
Quotation 50 kva_std_ongrid
Quotation 50 kva_std_ongridQuotation 50 kva_std_ongrid
Quotation 50 kva_std_ongrid
Exalta Insparc Technologies pvt. Limited
 
1 80 fineshed
1 80 fineshed1 80 fineshed
1 80 fineshed
rkarthick8
 
Fire alarm checklist
Fire alarm checklistFire alarm checklist
Fire alarm checklist
irhabsyam
 
Specifications of Solar Power system (Issue-II).pdf
Specifications of Solar Power system (Issue-II).pdfSpecifications of Solar Power system (Issue-II).pdf
Specifications of Solar Power system (Issue-II).pdf
AmjiShah
 

Similar to BOQ _UN.pptx (20)

PROJECT ENGINEER- ELECTRICAL._L
PROJECT ENGINEER-  ELECTRICAL._LPROJECT ENGINEER-  ELECTRICAL._L
PROJECT ENGINEER- ELECTRICAL._L
 
66 k v_sf6_bkr_r3_may12
66 k v_sf6_bkr_r3_may1266 k v_sf6_bkr_r3_may12
66 k v_sf6_bkr_r3_may12
 
11.docx
11.docx11.docx
11.docx
 
Inspecting pv systems_for_code_compliance
Inspecting pv systems_for_code_complianceInspecting pv systems_for_code_compliance
Inspecting pv systems_for_code_compliance
 
Inspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code ComplianceInspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code Compliance
 
INSTRUMENTATION ENGINNER - QC INSPECTOR ARAMCO SAP 70013071
INSTRUMENTATION ENGINNER - QC INSPECTOR ARAMCO SAP 70013071INSTRUMENTATION ENGINNER - QC INSPECTOR ARAMCO SAP 70013071
INSTRUMENTATION ENGINNER - QC INSPECTOR ARAMCO SAP 70013071
 
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantNet metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
 
Grid stds
Grid stdsGrid stds
Grid stds
 
3D_Distribution transformer_Specification.pdf
3D_Distribution transformer_Specification.pdf3D_Distribution transformer_Specification.pdf
3D_Distribution transformer_Specification.pdf
 
Ahmed Rageh_CV (3)
Ahmed Rageh_CV (3)Ahmed Rageh_CV (3)
Ahmed Rageh_CV (3)
 
Generator step-up and system intertie power transformers Securing high-qualit...
Generator step-up and system intertie power transformers Securing high-qualit...Generator step-up and system intertie power transformers Securing high-qualit...
Generator step-up and system intertie power transformers Securing high-qualit...
 
Presentation 1
Presentation 1Presentation 1
Presentation 1
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSTESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
 
Quotation 50 kva_std_ongrid
Quotation 50 kva_std_ongridQuotation 50 kva_std_ongrid
Quotation 50 kva_std_ongrid
 
1 80 fineshed
1 80 fineshed1 80 fineshed
1 80 fineshed
 
Fire alarm checklist
Fire alarm checklistFire alarm checklist
Fire alarm checklist
 
Specifications of Solar Power system (Issue-II).pdf
Specifications of Solar Power system (Issue-II).pdfSpecifications of Solar Power system (Issue-II).pdf
Specifications of Solar Power system (Issue-II).pdf
 
Sathish Kumar-Resume.
Sathish Kumar-Resume.Sathish Kumar-Resume.
Sathish Kumar-Resume.
 
Resume mohan
Resume mohanResume mohan
Resume mohan
 

Recently uploaded

The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
By Design, not by Accident - Agile Venture Bolzano 2024
By Design, not by Accident - Agile Venture Bolzano 2024By Design, not by Accident - Agile Venture Bolzano 2024
By Design, not by Accident - Agile Venture Bolzano 2024
Pierluigi Pugliese
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
Free Complete Python - A step towards Data Science
Free Complete Python - A step towards Data ScienceFree Complete Python - A step towards Data Science
Free Complete Python - A step towards Data Science
RinaMondal9
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
Thijs Feryn
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
ThousandEyes
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
Product School
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
Ana-Maria Mihalceanu
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
James Anderson
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
Safe Software
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
Elena Simperl
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Product School
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptxSecstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
nkrafacyberclub
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
sonjaschweigert1
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
Cheryl Hung
 

Recently uploaded (20)

The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
By Design, not by Accident - Agile Venture Bolzano 2024
By Design, not by Accident - Agile Venture Bolzano 2024By Design, not by Accident - Agile Venture Bolzano 2024
By Design, not by Accident - Agile Venture Bolzano 2024
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
Free Complete Python - A step towards Data Science
Free Complete Python - A step towards Data ScienceFree Complete Python - A step towards Data Science
Free Complete Python - A step towards Data Science
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptxSecstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 

BOQ _UN.pptx

  • 1. UNITED NATIONS DEVELOPMENT PROGRAMME ITB 2016-196 Lot 26 WBS 1150 Bill of Quantities Programme Title: Right to Education in the Gaza Strip Project name: Extension and Rehabilitation Works For The Governmental Schools PAL10- 00094739- LOT 26 Renewable Energy for All – Photovoltaic Cells for Al Fakhoora Schools in Gaza Strip
  • 2. (Bill of Quantities) 1 .The contractor must provide a detailed cost breakdown for each item. 2.The contractor must provide Technical descriptions for each proposed item and sufficient detail to allow UNDP to determine compliance of Bid with specifications as per Schedule of Requirements and Technical Specifications of this ITB. The contractor shall indicate all makes proposed and must attach relevant manufacturer Catalogue/data. 3. The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics, test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and manufacturers warranty for each components of the system for 5 years. 4. All prices/rates quoted must be exclusive of all taxes, since the United Nations, including its subsidiary organs, is exempt from taxes. 5. In addition to the hard copy, if possible please provide also the information on diskette (IBM compatible). 5. Inspection Team The contractor Shall facilitate the attendance of Engineers from the supervision team and the Recipient to check the materials of the PV Solar eqipments before delivering to Site. 6. On site training Upon completion of the installation, the contractor shall organize an on site training program involving nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of the training shall be deemed to have been included in the tendered rates. 7.Contractor's Documents The contractor's documents must include all construction documentation required for the works. They must include all site information, structural and civil drawings, electrical services drawings at suitable scales showing final design calculations, symbols list, site plan, and single line diagrams for distribution boards, solar switchboards, and control systems. 8.Operation and Maintenace Manuals The contractor must submit two hard copies on standard sized sheets and two electronic copy in-PDF format of the as built drawings including the wiring diagrams and PV single line diagrams, DC and AC wiring sizing calculations including cross sectional area of the wires used and voltage drop calculations, rating of all fuses and circuit breakers, operation and maintenance manuals for each different site. The manuals must contain PV system description and catalogues of all PV system components. They shall also contain maintenance schedules, commissioning data, PV system test certificates, a step by step startup and shut down procedure for the entire PV system, and description of the type and operation control of the inverter and charge controller. The contractor will maintain monthly visits during the maintenance period to carry out the necessary maintenance processes needed and respond promptly to any emergency needed to keep the system performance intact and perfect.
  • 3. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ Bill No (1) Photovoltaic Solar System works General: • The system is designed to cover the Essential loads in Jamal Abd Alnasser School •The system will be grid interactive connected with battery backup system, which will allow many power sources options. The system will import from the grid when loads are being more than the generated from PV and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be charged from Grid if PV output is not enough for loads and batteries. •Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar system works,including a single line diagram showing all the components of the PV system, DC and AC distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section for all the system to be approved by the Engineer before executing the work. •Contractor shall submit the catalogs of each component showing the requested specifications stated at the bill of quantity. •The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics, test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and manufacturers warrantyfor each components of the system. • As-built drawings shall be submitted after handing over the work. • All junction boxes and DBs will be lockable type. •Upon completion of the installation, the contractor shall organize an on site training program involving nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of the training shall be deemed to have been included in the tendered rates. •The price includes all builders’ works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • All the following items include supply, install, commission and operate of the complete PV solar system. • The work includes maintenance period for each device according to BOQ and Specifications. 1 PV Modules – 45 Kwp: Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all material needed to have complete job ready for installing high quality PV modules with total arrays capacity to achieve 45 KWp. The item Includes supply, install &connect the following: • Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars ,terminals, ducts or trays, supports &labels suitable to the PV arrays loads. •Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC plug and socket connectors . The DC cables must be sized in accordance with the installation requirements applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%. KWp 45 •The price includes all works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years. • Contractor must submit all the required certificates for each PV solar panel from. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for Jamal Abd Alnasser School
  • 4. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 2 Inverters – 45 KW: Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the system design and installation proposed and for the future extended also. (Type is SMA or equivalent). The DC max power input rating should be equal or more than 45 KW of the PV modules capacity at standard test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65. The inverter AC nominal power output rating must be equal or greater than 45 KW compatible with the AC loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total inverter capacity must be devided at least 3 inverters. The price includes : Unit 1 •Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially compatible with the inverters, with all needed accessories, interface modules & data cables and all connections needed to complete and connect the monitoring system to internet. •Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC cables between inverters and PV system not less than 1%. •Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the main distribution panel according to the engineer's instruction and approval and have a complete job. •The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 3 Battery Inverters – 50 KW: Supply, install, connect and operate Battery Inverters compatible with on grid inverter rated power 50 Kw with all necessary (Grid-Connect Automatic Transfer Control Box) ,interface modules and connections for masters & slaves , electrical cables and data communication unit with Ethernet connection, connectable in parallel and modularly extendable. (Type is SMA or equivalent). The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency, intelligent battery management for maximum battery life, charge level calculation, extreme overload capability, and battery temperature sensing and battery current measurements).Total battery inverters capacity must be compatible with the number of the inverters. The price includes: Unit 1 •Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data & communication cables and connection needed to complete the job. • Supply, install and connect: DC cables appropriately sized in accordance with the installation requirements to connect the batteryinverters with DC battery fuses box. AC electrical cables to connect the battery inverters with the main distribution panel(AC Out). the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a complete job, • The allowable voltage drop for DC cables between battery inverter and batteries less than 1%. •The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for Jamal Abd Alnasser School
  • 5. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 4 Battery Bank: Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 270 KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc. The batteries must provide high-quality and achieving superior performance, the manufacturing date must be new and not more than 6 months, suitable for every type of applications especially for solar renewable energy, designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes supply, install &connect Battery temp. sensor (BTS) and the following: KWh 270 •All necessary DC cables between the batteries together and to the battery fuse box to have a complete operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations and all needed materials to complete the job. All DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to finish the job. the rack must be enough to carry all the weight of the required batteries for the system. •The contractor must submit manufacturer warranty for each battery cell for a period 10 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 5 PV Mounting structure: Supply and install Module mounting structure from Aluminium profile structures to fix the photovoltaic panels on the roof including profiles composed of extruded aluminium, rivets with seal of an aluminium body and shank, a neoprene rubber seal and all accessories and supports. The structure must be suitable to the dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules 30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.3*0.2) m3 for each leg, the structure profile includes bracing and double hot galvanized angles for dividers. The mounting structures and the foundations must be designed structurally to be suitable to withstand all static loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting structure components are bonded together to guaranty potential equalization. L.S 1 All works and materials must be according to drawings, specifications and supervisor instructions and approval. 6 Battery Fuse Box: Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the battery bank and to the fuse box and from the fuse box to the batteryinverters to have a complete operational circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3 years.(Type is SMA or equivalent). All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. No 3 Photovoltaic Solar System for Jamal Abd Alnasser School
  • 6. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 7 AC Air Condition: Supply , install, test and commission air conditioning Inverter type Split Unit, composed of outdoor unit. filled with environment friendly refrigerant such as (R410, R407c,..) and COP not less than 3.5,Condensing unit shall be complete with Inverter compressor/s & air cooled condenser with fan, Well supported on hot galvanized steel base on the roof, indoor unit with plasma filter as indicated on drawings to be tights installed completed with all necessary supports, hangers, drain pipes from indoor unit to the nearest floor drain, ( PVC Ø 1"), cupper pipes , sleeves, thermostat , Remote control and including Isolation Switch MOELLER and all required electrical power cables from SDB to the unit according to drawings and engineers approval. CAPACITY:(12000 BTU/HR). (Type is ELECTRA or equivalent ) . No 1 8 3-Phase Digital KWH Meter: Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect with the Monitoring System .All works and materials must be according to the drawings, catalogues, specifications and supervisor engineer instruction’s and approval. No 2 9 Earthing System For Battery Banks: Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2 flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 1 10 Earthing for PV Solar System: Supply,install,connect and operate complete independent earthing system for PV solar system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system components to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 2 Total Of Bill (1) - US$ Photovoltaic Solar System for Jamal Abd Alnasser School
  • 7. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ Bill No (2) Photovoltaic Solar System works General: • The system is designed to cover the Essential loads in Ali Bin Abi Taleb School •The system will be grid interactive connected with battery backup system, which will allow many power sources options. The system will import from the grid when loads are being more than the generated from PV and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be charged from Grid if PV output is not enough for loads and batteries. •Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar system works,including a single line diagram showing all the components of the PV system, DC and AC distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section for all the system to be approved by the Engineer before executing the work. •Contractor shall submit the catalogs of each component showing the requested specifications stated at the bill of quantity. •The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics, test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and manufacturers warranty for each components of the system. • As-built drawings shall be submitted after handing over the work. • All junction boxes and DBs will be lockable type. •Upon completion of the installation, the contractor shall organize an on site training program involving nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of the training shall be deemed to have been included in the tendered rates. •The price includes all builders’ works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • All the following items include supply, install, commission and operate of the complete PV solar system. • The work includes maintenance period for each device according to BOQ and Specifications. 1 PV Modules – 38 Kwp: Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all material needed to have complete job ready for installing high quality PV modules with total arrays capacity to achieve 38 KWp. The item Includes supply, install &connect the following: • Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars ,terminals, ducts or trays, supports &labels suitable to the PV arrays loads. •Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC plug and socket connectors . The DC cables must be sized in accordance with the installation requirements applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%. KWp 38 •The price includes all works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years. • Contractor must submit all the required certificates for each PV solar panel from. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for Ali Bin Abi Taleb School
  • 8. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 2 Inverters – 40 KW: Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the system design and installation proposed and for the future extended also. (Type is SMA or equivalent). The DC max power input rating should be equal or more than 40 KW of the PV modules capacity at standard test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65. The inverter AC nominal power output rating must be equal or greater than 40 KW compatible with the AC loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total inverter capacity must be devided at least 3 inverters. The price includes : Unit 1 •Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially compatible with the inverters, with all needed accessories, interface modules & data cables and all connections needed to complete and connect the monitoring system to internet. •Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC cables between inverters and PV system not less than 1%. •Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the main distribution panel according to the engineer's instruction and approval and have a complete job. •The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 3 Battery Inverters – 50 KW: Supply, install, connect and operate Battery Inverters compatible with on grid inverter rated power 50 Kw with all necessary (Grid-Connect Automatic Transfer Control Box),interface modules and connections for masters & slaves , electrical cables and data communication unit with Ethernet connection, connectable in parallel and modularly extendable. (Type is SMA or equivalent). The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency, intelligent battery management for maximum battery life, charge level calculation, extreme overload capability, and battery temperature sensing and battery current measurements).Total battery inverters capacity must be compatible with the number of the inverters. The price includes: Unit 1 •Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data & communication cables and connection needed to complete the job. • Supply, install and connect: DC cables appropriately sized in accordance with the installation requirements to connect the battery inverters with DC battery fuses box. AC electrical cables to connect the battery inverters with the main distribution panel(AC Out). the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a complete job, • The allowable voltage drop for DC cables between battery inverter and batteries less than 1%. •The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for Ali Bin Abi Taleb School
  • 9. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 4 Battery Bank : Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 200 KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc. The batteries must provide high-quality and achieving superior performance, the manufacturing date must be new and not more than 6 months, suitable for every type of applications especially for solar renewable energy, designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes supply, install &connect Battery temp. sensor (BTS) and the following: KWh 200 •All necessary DC cables between the batteries together and to the battery fuse box to have a complete operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations and all needed materials to complete the job. All DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to finish the job. the rack must be enough to carry all the weight of the required batteries for the system. •The contractor must submit manufacturer warranty for each battery cell for a period 10 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 5 PV Mounting structure: Supply and install Module mounting structure from hot galvanized steel profile foundation suitable to the dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules 30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.4*0.2) m3 for each leg, the structure profile includes bracing and double hot galvanized angles for dividers. The mounting structures and the foundations must be designed structurally to be suitable to withstand all static loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting structure components are bonded together to guaranty potential equalization. L.S 1 All works and materials must be according to drawings, specifications and supervisor instructions and approval. 6 Battery Fuse Box: Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the battery bank and to the fuse box and from the fuse box to the battery inverters to have a complete operational circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3 years. (Type is SMA or equivalent). All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. No 3 Photovoltaic Solar System for Ali Bin Abi Taleb School
  • 10. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 7 AC Air Condition: Supply , install, test and commission air conditioning Inverter type Split Unit, composed of outdoor unit. filled with environment friendly refrigerant such as (R410, R407c,..) and COP not less than 3.5,Condensing unit shall be complete with Inverter compressor/s & air cooled condenser with fan, Well supported on hot galvanized steel base on the roof, indoor unit with plasma filter as indicated on drawings to be tights installed completed with all necessary supports, hangers, drain pipes from indoor unit to the nearest floor drain, ( PVC Ø 1"), cupper pipes , sleeves, thermostat , Remote control and including Isolation Switch MOELLER and all required electrical power cables from SDB to the unit according to drawings and engineers approval. CAPACITY:(12000 BTU/HR). (Type is ELECTRA or equivalent ) . No 1 8 3-Phase Digital KWH Meter: Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect with the Monitoring System .All works and materials must be according to the drawings, catalogues, specifications and supervisor engineer instruction’s and approval. No 2 9 Earthing System For Battery Banks: Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2 flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 1 10 Earthing for PV Solar System: Supply,install,connect and operate complete independent earthing system for PV solar system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system components to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 2 Total Of Bill (2) - US$ Photovoltaic Solar System for Ali Bin Abi Taleb School
  • 11. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ Bill No (4) Photovoltaic Solar System works General: • The system is designed to cover the Essential loads in KHANYOUNIS SECONDARY GIRLS SCHOOL •The system will be grid interactive connected with battery backup system, which will allow many power sources options. The system will import from the grid when loads are being more than the generated from PV and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be charged from Grid if PV output is not enough for loads and batteries. •Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar system works,including a single line diagram showing all the components of the PV system, DC and AC distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section for all the system to be approved by the Engineer before executing the work. •Contractor shall submit the catalogs of each component showing the requested specifications stated at the bill of quantity. •The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics, test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and manufacturers warrantyfor each components of the system. • As-built drawings shall be submitted after handing over the work. • All junction boxes and DBs will be lockable type. •Upon completion of the installation, the contractor shall organize an on site training program involving nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of the training shall be deemed to have been included in the tendered rates. •The price includes all builders’ works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • All the following items include supply, install, commission and operate of the complete PV solar system. • The work includes maintenance period for each device according to BOQ and Specifications. 1 PV Modules – 25 Kwp: Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all material needed to have complete job ready for installing high quality PV modules with total arrays capacity to achieve 25 KWp. The item Includes supply, install &connect the following: • Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars ,terminals, ducts or trays, supports &labels suitable to the PV arrays loads. •Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC plug and socket connectors . The DC cables must be sized in accordance with the installation requirements applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%. KWp 25 •The price includes all works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years. • Contractor must submit all the required certificates for each PV solar panel from. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for KHANYOUNIS SECONDARY GIRLS SCHOOL
  • 12. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 2 Inverters – 30 KW: Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the system design and installation proposed and for the future extended also. (Type is SMA or equivalent). The DC max power input rating should be equal or more than 30 KW of the PV modules capacity at standard test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65. The inverter AC nominal power output rating must be equal or greater than 30 KW compatible with the AC loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total inverter capacity must be devided at least 2 inverters. The price includes : Unit 1 •Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially compatible with the inverters, with all needed accessories, interface modules & data cables and all connections needed to complete and connect the monitoring system to internet. •Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC cables between inverters and PV system not less than 1%. •Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the main distribution panel according to the engineer's instruction and approval and have a complete job. •The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 3 Battery Inverter – 6 KW: Supply, install, connect and operate Battery Inverter compatible with on grid inverters with total rated power 6 Kw with all necessary interface modules and connections for masters & slaves , electrical cables and data communication unit,router with Ethernet connection, connectable in parallel and modularly extendable. (Type is SMA or equivalent). The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency, intelligent battery management for maximum battery life, charge level calculation, extreme overload capability, and batterytemperature sensing and battery current measurements). The price includes: No 3 •Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data & communication cables and connection needed to complete the job. • Supply, install and connect: DC cables appropriately sized in accordance with the installation requirements to connect the batteryinverters with DC battery fuses box. AC electrical cables to connect the battery inverters with the main distribution panel(AC Out). the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a complete job, • The allowable voltage drop for DC cables between battery inverter and batteries less than 1%. •The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for KHANYOUNIS SECONDARY GIRLS SCHOOL
  • 13. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 4 Battery Bank: Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 120 KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc. The batteries must provide high-quality and achieving superior performance, the manufacturing date must be new and not more than 6 months, suitable for every type of applications especially for solar renewable energy, designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes supply, install &connect Battery temp. sensor (BTS) and the following: KWh 120 •All necessary DC cables between the batteries together and to the battery fuse box to have a complete operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations and all needed materials to complete the job. All DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to finish the job. the rack must be enough to carry all the weight of the required batteries for the system. •The contractor must submit manufacturer warranty for each battery cell for a period 10 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 5 PV Mounting structure: Supply and install Module mounting structure from hot galvanized steel profile foundation suitable to the dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules 30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.4*0.2) m3 for each leg, the structure profile includes bracing and double hot galvanized angles for dividers. The mounting structures and the foundations must be designed structurally to be suitable to withstand all static loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting structure components are bonded together to guaranty potential equalization. L.S 1 All works and materials must be according to drawings, specifications and supervisor instructions and approval. 6 Battery Fuse Box: Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the battery bank and to the fuse box and from the fuse box to the batteryinverters to have a complete operational circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3 years. (Type is SMA or equivalent). All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. No 1 Photovoltaic Solar System for KHANYOUNIS SECONDARY GIRLS SCHOOL
  • 14. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 7 Wall mounted exhaust: Supply, install, connect and operate wall mounted exhaust fan of 8" diameter Capacity (500 cfm) type is (VENTA or equivalent ) at static pressure 60 Pascal for the battery room , to be tightly installed complete with all necessary supports ,cover and an louvers, and all required electrical cables, conduits, mcb 10A and needed to fix, all according engineer’s approval. The price shall include opening duct in the block for the fan, plastering, painting, repair all damages and all other materials needed to have a complete job ready according to the engineer's instruction and approval. No 1 8 3-Phase Digital KWH Meter: Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect with the Monitoring System .All works and materials must be according to the drawings, catalogues, specifications and supervisor engineer instruction’s and approval. No 2 9 Earthing System For Battery Banks: Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2 flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 1 10 Earthing for PV Solar System: Supply,install,connect and operate complete independent earthing system for PV solar system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system components to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 2 Total Of Bill (3) - US$ Photovoltaic Solar System for KHANYOUNIS SECONDARY GIRLS SCHOOL
  • 15. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ Bill No (3) Photovoltaic Solar System works General: • The system is designed to cover the Essential loads in ALMOTANABY PRIMARY BOYS SCHOOL •The system will be grid interactive connected with battery backup system, which will allow many power sources options. The system will import from the grid when loads are being more than the generated from PV and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be charged from Grid if PV output is not enough for loads and batteries. •Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar system works,including a single line diagram showing all the components of the PV system, DC and AC distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section for all the system to be approved by the Engineer before executing the work. •Contractor shall submit the catalogs of each component showing the requested specifications stated at the bill of quantity. •The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics, test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and manufacturers warrantyfor each components of the system. • As-built drawings shall be submitted after handing over the work. • All junction boxes and DBs will be lockable type. •Upon completion of the installation, the contractor shall organize an on site training program involving nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of the training shall be deemed to have been included in the tendered rates. •The price includes all builders’ works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • All the following items include supply, install, commission and operate of the complete PV solar system. • The work includes maintenance period for each device according to BOQ and Specifications. 1 PV Modules – 25 Kwp: Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all material needed to have complete job ready for installing high quality PV modules with total arrays capacity to achieve 25 KWp. The item Includes supply, install &connect the following: • Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars ,terminals, ducts or trays, supports &labels suitable to the PV arrays loads. •Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC plug and socket connectors . The DC cables must be sized in accordance with the installation requirements applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%. KWp 25 •The price includes all works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years. • Contractor must submit all the required certificates for each PV solar panel from. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for ALMOTANABY PRIMARY BOYS SCHOOL
  • 16. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 2 Inverters – 30 KW: Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the system design and installation proposed and for the future extended also. (Type is SMA or equivalent). The DC max power input rating should be equal or more than 30 KW of the PV modules capacity at standard test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65. The inverter AC nominal power output rating must be equal or greater than 30 KW compatible with the AC loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total inverter capacity must be devided at least 2 inverters. The price includes : Unit 1 •Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially compatible with the inverters, with all needed accessories, interface modules & data cables and all connections needed to complete and connect the monitoring system to internet. •Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC cables between inverters and PV system not less than 1%. •Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the main distribution panel according to the engineer's instruction and approval and have a complete job. •The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 3 Battery Inverter – 6 KW: Supply, install, connect and operate Battery Inverter compatible with on grid inverters with total rated power 6 Kw with all necessary interface modules and connections for masters & slaves , electrical cables and data communication unit,router with Ethernet connection, connectable in parallel and modularly extendable. (Type is SMA or equivalent). The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency, intelligent battery management for maximum battery life, charge level calculation, extreme overload capability, and batterytemperature sensing and battery current measurements). The price includes: No 3 •Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data & communication cables and connection needed to complete the job. • Supply, install and connect: DC cables appropriately sized in accordance with the installation requirements to connect the batteryinverters with DC battery fuses box. AC electrical cables to connect the battery inverters with the main distribution panel(AC Out). the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a complete job, • The allowable voltage drop for DC cables between battery inverter and batteries less than 1%. •The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for ALMOTANABY PRIMARY BOYS SCHOOL
  • 17. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 4 Battery Bank: Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 120 KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc. The batteries must provide high-quality and achieving superior performance, the manufacturing date must be new and not more than 6 months, suitable for every type of applications especially for solar renewable energy, designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes supply, install &connect Battery temp. sensor (BTS) and the following: KWh 120 •All necessary DC cables between the batteries together and to the battery fuse box to have a complete operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations and all needed materials to complete the job. All DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to finish the job. the rack must be enough to carry all the weight of the required batteries for the system. •The contractor must submit manufacturer warranty for each battery cell for a period 10 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 5 PV Mounting structure: Supply and install Module mounting structure from hot galvanized steel profile foundation suitable to the dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules 30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.4*0.2) m3 for each leg, the structure profile includes bracing and double hot galvanized angles for dividers. The mounting structures and the foundations must be designed structurally to be suitable to withstand all static loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting structure components are bonded together to guaranty potential equalization. L.S 1 All works and materials must be according to drawings, specifications and supervisor instructions and approval. 6 Battery Fuse Box: Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the battery bank and to the fuse box and from the fuse box to the batteryinverters to have a complete operational circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3 years. (Type is SMA or equivalent). All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. No 1 Photovoltaic Solar System for ALMOTANABY PRIMARY BOYS SCHOOL
  • 18. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 7 Wall mounted exhaust: Supply, install, connect and operate wall mounted exhaust fan of 8" diameter Capacity (500 cfm) type is (VENTA or equivalent ) at static pressure 60 Pascal for the battery room , to be tightly installed complete with all necessary supports ,cover and an louvers, and all required electrical cables, conduits, mcb 10A and needed to fix, all according engineer’s approval. The price shall include opening duct in the block for the fan, plastering, painting, repair all damages and all other materials needed to have a complete job ready according to the engineer's instruction and approval. No 1 8 3-Phase Digital KWH Meter: Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect with the Monitoring System .All works and materials must be according to the drawings, catalogues, specifications and supervisor engineer instruction’s and approval. No 2 9 Earthing System For Battery Banks: Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2 flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 1 10 Earthing for PV Solar System: Supply,install,connect and operate complete independent earthing system for PV solar system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system components to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 2 Total Of Bill (4) - US$ Photovoltaic Solar System for ALMOTANABY PRIMARY BOYS SCHOOL
  • 19. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ Bill No (5) Photovoltaic Solar System works General: • The system is designed to cover the Essential loads in Al Ma'ari Primary Boys School •The system will be grid interactive connected with battery backup system, which will allow many power sources options. The system will import from the grid when loads are being more than the generated from PV and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be charged from Grid if PV output is not enough for loads and batteries. •Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar system works,including a single line diagram showing all the components of the PV system, DC and AC distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section for all the system to be approved by the Engineer before executing the work. •Contractor shall submit the catalogs of each component showing the requested specifications stated at the bill of quantity. •The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics, test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and manufacturers warrantyfor each components of the system. • As-built drawings shall be submitted after handing over the work. • All junction boxes and DBs will be lockable type. •Upon completion of the installation, the contractor shall organize an on site training program involving nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of the training shall be deemed to have been included in the tendered rates. •The price includes all builders’ works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • All the following items include supply, install, commission and operate of the complete PV solar system. • The work includes maintenance period for each device according to BOQ and Specifications. 1 PV Modules – 25 Kwp: Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all material needed to have complete job ready for installing high quality PV modules with total arrays capacity to achieve 25 KWp. The item Includes supply, install &connect the following: • Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars ,terminals, ducts or trays, supports &labels suitable to the PV arrays loads. •Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC plug and socket connectors . The DC cables must be sized in accordance with the installation requirements applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%. KWp 25 •The price includes all works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years. • Contractor must submit all the required certificates for each PV solar panel from. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for Al Ma'ari Primary Boys School
  • 20. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 2 Inverters – 30 KW: Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the system design and installation proposed and for the future extended also. (Type is SMA or equivalent). The DC max power input rating should be equal or more than 30 KW of the PV modules capacity at standard test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65. The inverter AC nominal power output rating must be equal or greater than 30 KW compatible with the AC loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total inverter capacity must be devided at least 2 inverters. The price includes : Unit 1 •Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially compatible with the inverters, with all needed accessories, interface modules & data cables and all connections needed to complete and connect the monitoring system to internet. •Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC cables between inverters and PV system not less than 1%. •Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the main distribution panel according to the engineer's instruction and approval and have a complete job. •The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 3 Battery Inverter – 6 KW: Supply, install, connect and operate Battery Inverter compatible with on grid inverters with total rated power 6 Kw with all necessary interface modules and connections for masters & slaves , electrical cables and data communication unit,router with Ethernet connection, connectable in parallel and modularly extendable. (Type is SMA or equivalent). The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency, intelligent battery management for maximum battery life, charge level calculation, extreme overload capability, and batterytemperature sensing and battery current measurements). The price includes: No 3 •Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data & communication cables and connection needed to complete the job. • Supply, install and connect: DC cables appropriately sized in accordance with the installation requirements to connect the batteryinverters with DC battery fuses box. AC electrical cables to connect the battery inverters with the main distribution panel(AC Out). the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a complete job, • The allowable voltage drop for DC cables between battery inverter and batteries less than 1%. •The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for Al Ma'ari Primary Boys School
  • 21. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 4 Battery Bank: Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 120 KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc. The batteries must provide high-quality and achieving superior performance, the manufacturing date must be new and not more than 6 months, suitable for every type of applications especially for solar renewable energy, designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes supply, install &connect Battery temp. sensor (BTS) and the following: KWh 120 •All necessary DC cables between the batteries together and to the battery fuse box to have a complete operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations and all needed materials to complete the job. All DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to finish the job. the rack must be enough to carry all the weight of the required batteries for the system. •The contractor must submit manufacturer warranty for each battery cell for a period 10 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 5 PV Mounting structure: Supply and install Module mounting structure from hot galvanized steel profile foundation suitable to the dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules 30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.4*0.2) m3 for each leg, the structure profile includes bracing and double hot galvanized angles for dividers. The mounting structures and the foundations must be designed structurally to be suitable to withstand all static loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting structure components are bonded together to guaranty potential equalization. L.S 1 All works and materials must be according to drawings, specifications and supervisor instructions and approval. 6 Battery Fuse Box: Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the battery bank and to the fuse box and from the fuse box to the batteryinverters to have a complete operational circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3 years. (Type is SMA or equivalent). All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. No 1 Photovoltaic Solar System for Al Ma'ari Primary Boys School
  • 22. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 7 Wall mounted exhaust: Supply, install, connect and operate wall mounted exhaust fan of 8" diameter Capacity (500 cfm) type is (VENTA or equivalent ) at static pressure 60 Pascal for the battery room , to be tightly installed complete with all necessary supports ,cover and an louvers, and all required electrical cables, conduits, mcb 10A and needed to fix, all according engineer’s approval. The price shall include opening duct in the block for the fan, plastering, painting, repair all damages and all other materials needed to have a complete job ready according to the engineer's instruction and approval. No 1 8 3-Phase Digital KWH Meter: Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect with the Monitoring System .All works and materials must be according to the drawings, catalogues, specifications and supervisor engineer instruction’s and approval. No 2 9 Earthing System For Battery Banks: Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2 flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 1 10 Earthing for PV Solar System: Supply,install,connect and operate complete independent earthing system for PV solar system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system components to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 2 Total Of Bill (5) - US$ Photovoltaic Solar System for Al Ma'ari Primary Boys School
  • 23. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ Bill No (6) Photovoltaic Solar System works General: • The system is designed to cover the Essential loads in SHEJAIAA PRIMARY BOYS SCHOOL •The system will be grid interactive connected with battery backup system, which will allow many power sources options. The system will import from the grid when loads are being more than the generated from PV and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be charged from Grid if PV output is not enough for loads and batteries. •Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar system works,including a single line diagram showing all the components of the PV system, DC and AC distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section for all the system to be approved by the Engineer before executing the work. •Contractor shall submit the catalogs of each component showing the requested specifications stated at the bill of quantity. •The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics, test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and manufacturers warrantyfor each components of the system. • As-built drawings shall be submitted after handing over the work. • All junction boxes and DBs will be lockable type. •Upon completion of the installation, the contractor shall organize an on site training program involving nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of the training shall be deemed to have been included in the tendered rates. •The price includes all builders’ works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • All the following items include supply, install, commission and operate of the complete PV solar system. • The work includes maintenance period for each device according to BOQ and Specifications. 1 PV Modules – 25 Kwp: Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all material needed to have complete job ready for installing high quality PV modules with total arrays capacity to achieve 25 KWp. The item Includes supply, install &connect the following: • Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars ,terminals, ducts or trays, supports &labels suitable to the PV arrays loads. •Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC plug and socket connectors . The DC cables must be sized in accordance with the installation requirements applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%. KWp 25 •The price includes all works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years. • Contractor must submit all the required certificates for each PV solar panel from. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for SHEJAIAA PRIMARY BOYS SCHOOL
  • 24. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 2 Inverters – 30 KW: Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the system design and installation proposed and for the future extended also. (Type is SMA or equivalent). The DC max power input rating should be equal or more than 30 KW of the PV modules capacity at standard test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65. The inverter AC nominal power output rating must be equal or greater than 30 KW compatible with the AC loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total inverter capacity must be devided at least 2 inverters. The price includes : Unit 1 •Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially compatible with the inverters, with all needed accessories, interface modules & data cables and all connections needed to complete and connect the monitoring system to internet. •Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC cables between inverters and PV system not less than 1%. •Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the main distribution panel according to the engineer's instruction and approval and have a complete job. •The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 3 Battery Inverter – 6 KW: Supply, install, connect and operate Battery Inverter compatible with on grid inverters with total rated power 6 Kw with all necessary interface modules and connections for masters & slaves , electrical cables and data communication unit,router with Ethernet connection, connectable in parallel and modularly extendable. (Type is SMA or equivalent). The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency, intelligent battery management for maximum battery life, charge level calculation, extreme overload capability, and batterytemperature sensing and battery current measurements). The price includes: No 3 •Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data & communication cables and connection needed to complete the job. • Supply, install and connect: DC cables appropriately sized in accordance with the installation requirements to connect the batteryinverters with DC battery fuses box. AC electrical cables to connect the battery inverters with the main distribution panel(AC Out). the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a complete job, • The allowable voltage drop for DC cables between battery inverter and batteries less than 1%. •The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for SHEJAIAA PRIMARY BOYS SCHOOL
  • 25. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 4 Battery Bank: Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 120 KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc. The batteries must provide high-quality and achieving superior performance, the manufacturing date must be new and not more than 6 months, suitable for every type of applications especially for solar renewable energy, designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes supply, install &connect Battery temp. sensor (BTS) and the following: KWh 120 •All necessary DC cables between the batteries together and to the battery fuse box to have a complete operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations and all needed materials to complete the job. All DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to finish the job. the rack must be enough to carry all the weight of the required batteries for the system. •The contractor must submit manufacturer warranty for each battery cell for a period 10 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 5 PV Mounting structure: Supply and install Module mounting structure from hot galvanized steel profile foundation suitable to the dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules 30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.4*0.2) m3 for each leg, the structure profile includes bracing and double hot galvanized angles for dividers. The mounting structures and the foundations must be designed structurally to be suitable to withstand all static loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting structure components are bonded together to guaranty potential equalization. L.S 1 All works and materials must be according to drawings, specifications and supervisor instructions and approval. 6 Battery Fuse Box: Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the battery bank and to the fuse box and from the fuse box to the batteryinverters to have a complete operational circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3 years. (Type is SMA or equivalent). All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. No 1 Photovoltaic Solar System for SHEJAIAA PRIMARY BOYS SCHOOL
  • 26. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 7 Wall mounted exhaust: Supply, install, connect and operate wall mounted exhaust fan of 8" diameter Capacity (500 cfm) type is (VENTA or equivalent ) at static pressure 60 Pascal for the battery room , to be tightly installed complete with all necessary supports ,cover and an louvers, and all required electrical cables, conduits, mcb 10A and needed to fix, all according engineer’s approval. The price shall include opening duct in the block for the fan, plastering, painting, repair all damages and all other materials needed to have a complete job ready according to the engineer's instruction and approval. No 1 8 3-Phase Digital KWH Meter: Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect with the Monitoring System .All works and materials must be according to the drawings, catalogues, specifications and supervisor engineer instruction’s and approval. No 2 9 Earthing System For Battery Banks: Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2 flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 1 10 Earthing for PV Solar System: Supply,install,connect and operate complete independent earthing system for PV solar system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system components to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 2 Total Of Bill (6) - US$ Photovoltaic Solar System for SHEJAIAA PRIMARY BOYS SCHOOL
  • 27. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ Bill No (7) Photovoltaic Solar System works General: • The system is designed to cover the Essential loads in ABU TAMMAM PRIMARY BOYS SCHOOL •The system will be grid interactive connected with battery backup system, which will allow many power sources options. The system will import from the grid when loads are being more than the generated from PV and supply surplus electricity to the batteries when PV generates more than the loads, the batteries can be charged from Grid if PV output is not enough for loads and batteries. •Contractor shall submit shop drawings for all architectural, civil, electrical and a complete photovoltaic solar system works,including a single line diagram showing all the components of the PV system, DC and AC distribution boards, PV Arrays lay out and battery backup systems connections and cables, wires cross section for all the system to be approved by the Engineer before executing the work. •Contractor shall submit the catalogs of each component showing the requested specifications stated at the bill of quantity. •The contractor shall submit the Manufacture testing certificate, country of origion, certified characteristics, test performance curves, spare parts regular (as recommended by manufacturer , maintenance manuals and manufacturers warrantyfor each components of the system. • As-built drawings shall be submitted after handing over the work. • All junction boxes and DBs will be lockable type. •Upon completion of the installation, the contractor shall organize an on site training program involving nominated employer's staff. Such a program shall be carried out during the commissioning phase. The cost of the training shall be deemed to have been included in the tendered rates. •The price includes all builders’ works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • All the following items include supply, install, commission and operate of the complete PV solar system. • The work includes maintenance period for each device according to BOQ and Specifications. 1 PV Modules – 25 Kwp: Supply, install, connect and operate Mono Crystalline or Polycrystalline Photovoltaic Solar Modules with all material needed to have complete job ready for installing high quality PV modules with total arrays capacity to achieve 25 KWp. The item Includes supply, install &connect the following: • Water proof PV junction boxes IP65 for each array including DC Fuses, DC switch disconnectors, bus bars ,terminals, ducts or trays, supports &labels suitable to the PV arrays loads. •Solar DC cables appropriately sized to connect the PV solar cells together and to the inverter directly to have a complete operational circuit with all conduits, clamps , trays and cable end terminations which shall be DC plug and socket connectors . The DC cables must be sized in accordance with the installation requirements applicable on site, the allowable voltage drop for DC cables between PV Arrays and inverter less than 1%. KWp 25 •The price includes all works, making good and reinstatement including necessary materials and workmanship as well as removal of unwanted materials to dump sites approved by the engineer to complete the job successfully. • Contractor must submit manufacturer warranty for solar panel for a period not less than 20 years. • Contractor must submit all the required certificates for each PV solar panel from. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for ABU TAMMAM PRIMARY BOYS SCHOOL
  • 28. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 2 Inverters – 30 KW: Supply, install, connect and operate DC/AC grid tie 3-phase inverter with data communication unit with Ethernet connection .The inverterwith must be suited to any PV module configuration, and depending on the system design and installation proposed and for the future extended also. (Type is SMA or equivalent). The DC max power input rating should be equal or more than 30 KW of the PV modules capacity at standard test condition. The inverter unit shall be suitable for indoor and outdoor installations with IP65. The inverter AC nominal power output rating must be equal or greater than 30 KW compatible with the AC loads design.The inverter must include the safety concepts such as (triple protection with optiprotect, electronic strings fuses, self-learning string failure detection, DC surge arrestor type 2 ) to ensure max availability. Total inverter capacity must be devided at least 2 inverters. The price includes : Unit 1 •Supply, install and connect (monitoring and controlling unit) for all PV solar system installed especially compatible with the inverters, with all needed accessories, interface modules & data cables and all connections needed to complete and connect the monitoring system to internet. •Supply ,install and connect all DC cables appropriately sized in accordance with the installation requirements and to connect the inverters with PV system designed with all conduits, clamps, trays and cable terminations end which shall be DC plug and socket connectors to have a complete job, the allowable voltage drop for DC cables between inverters and PV system not less than 1%. •Inverters shall allow an adjustable power factor minimum AC output power with all necessary electrical cables, earthing system, Conduits, trays and all other materials and workmanship needed to connect with the main distribution panel according to the engineer's instruction and approval and have a complete job. •The contractor must submit manufacturer warranty for each inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 3 Battery Inverter – 6 KW: Supply, install, connect and operate Battery Inverter compatible with on grid inverters with total rated power 6 Kw with all necessary interface modules and connections for masters & slaves , electrical cables and data communication unit,router with Ethernet connection, connectable in parallel and modularly extendable. (Type is SMA or equivalent). The Battery Inverter must include the following concepts such as (Ac and DC coupling, High efficiency, intelligent battery management for maximum battery life, charge level calculation, extreme overload capability, and batterytemperature sensing and battery current measurements). The price includes: No 3 •Supply, install and connect Remote Control Units (RC Unit) for the installed battery inverters with all data & communication cables and connection needed to complete the job. • Supply, install and connect: DC cables appropriately sized in accordance with the installation requirements to connect the batteryinverters with DC battery fuses box. AC electrical cables to connect the battery inverters with the main distribution panel(AC Out). the works includes all conduits, clamps, trays and cable terminations end and workmanship needed to have a complete job, • The allowable voltage drop for DC cables between battery inverter and batteries less than 1%. •The contractor must submit manufacturer warranty for each battery inverter for a period not less than 5 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. Photovoltaic Solar System for ABU TAMMAM PRIMARY BOYS SCHOOL
  • 29. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 4 Battery Bank: Supply, install, connect and operate VRLA tubular design deep cycle batteries, the total demand energy is 120 KWh, @ C10 , 1.8V per cell. The battery bank voltage is 48 Vdc. The batteries must provide high-quality and achieving superior performance, the manufacturing date must be new and not more than 6 months, suitable for every type of applications especially for solar renewable energy, designed Service Life 10 years with low internal resistance, designed to be deeply discharged. The Battery should provide benefits of being maintenance free, case flame retardant & non-hazardous. The price Includes supply, install &connect Battery temp. sensor (BTS) and the following: KWh 120 •All necessary DC cables between the batteries together and to the battery fuse box to have a complete operational circuit with all bus bars, conduits, clamps, stainless steel bolts, washers and cable end terminations and all needed materials to complete the job. All DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •Battery Banks rack from the same manufacturer of the batteries with dividers and all needed accessories to finish the job. the rack must be enough to carry all the weight of the required batteries for the system. •The contractor must submit manufacturer warranty for each battery cell for a period 10 years. All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. 5 PV Mounting structure: Supply and install Module mounting structure from hot galvanized steel profile foundation suitable to the dimension of selected PV modules and PV numbers, the mounting provides a fixed inclination of the modules 30 degree with vertical supports, plates, screws and casting concrete foundations B250 (0.4*0.4*0.2) m3 for each leg, the structure profile includes bracing and double hot galvanized angles for dividers. The mounting structures and the foundations must be designed structurally to be suitable to withstand all static loads (weight of modules, wind loads etc) that might occur according to the Site conditions. The mounting structure components are bonded together to guaranty potential equalization. L.S 1 All works and materials must be according to drawings, specifications and supervisor instructions and approval. 6 Battery Fuse Box: Supply, install, connect and operate battery DC fuse box (500*375*225 mm) as an external DC distributor to protect the battery connections of the inverters . The box must be water proof protection with IP65, simple wall mounting, suitable connections for three battery inverters and up to six DC connections inlet on the battery side, the item includes (2 LTL 250/400A , 6 fuses 250A , cable glands, with all necessary DC cables from the battery bank and to the fuse box and from the fuse box to the batteryinverters to have a complete operational circuit with all conduits, clamps, stainless steel bolts, washers and cable end terminations needed to fix, all DC cables must be sized in accordance with the installation requirements applicable on site ,the allowable voltage drop must be less than 1%. •The contractor must submit manufacturer warranty for each battery fuse box for a period not less than 3 years. (Type is SMA or equivalent). All works and materials must be according to the drawings, specifications and supervisor engineer instruction’s and approval. No 1 Photovoltaic Solar System for ABU TAMMAM PRIMARY BOYS SCHOOL
  • 30. Item No. Description Unit Quantity Unit Rate US $ (Numbers) Total Amount US $ 7 Wall mounted exhaust: Supply, install, connect and operate wall mounted exhaust fan of 8" diameter Capacity (500 cfm) type is (VENTA or equivalent ) at static pressure 60 Pascal for the battery room , to be tightly installed complete with all necessary supports ,cover and an louvers, and all required electrical cables, conduits, mcb 10A and needed to fix, all according engineer’s approval. The price shall include opening duct in the block for the fan, plastering, painting, repair all damages and all other materials needed to have a complete job ready according to the engineer's instruction and approval. No 1 8 3-Phase Digital KWH Meter: Supply,install,connect and operate 3-phase digital KWH meter,with all CT's and any other material needed to have a complete job ,The KWh meter has monitoring LCD with all needed data & interface cables to connect with the Monitoring System .All works and materials must be according to the drawings, catalogues, specifications and supervisor engineer instruction’s and approval. No 2 9 Earthing System For Battery Banks: Supply,install,connect and operate complete independent earthing system for Battery Banks system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 50 mm2 flexible earthing copper wires and cables from the Negative bus bar in the battery fuse box to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 1 10 Earthing for PV Solar System: Supply,install,connect and operate complete independent earthing system for PV solar system, must be separated of the main earthing system to obtain 2 ohm max resistance. the item includes (2 copper electrodes 15mm2 driven into ground, manholes with iron cover, earth joints, clamps, ducts , conduits and 25 mm2 flexible earthing copper wires and cables from the PV system components to the electrode to complete the system as specifications and supervisor engineer instruction’s and approval. Unit 2 Total Of Bill (7) - US$ Photovoltaic Solar System for ABU TAMMAM PRIMARY BOYS SCHOOL