Outline of Presentation
๏ƒ˜ Introduction
๏ƒ˜ Need of Power Grids
๏ƒ˜ Selection Site
๏ƒ˜ Layout Design
1.Busbar Schemes
2.Electrical Layout Drawing
3.Bill of Material
๏ƒ˜ Safety Clearance in Grid
๏ƒ˜ Design of Earth Mat
๏ƒ˜ Control Room
๏ƒ˜ Switch/Relay Room
๏ƒ˜ Grid Equipments
๏ƒ˜ Conclusion
๏ƒ˜ Reference
Department of Electrical Engg.SIET,Dhenkanal.
INTRODUCTION
๏‚— An electrical grid is an
interconnected network for
delivering electricity from
suppliers to consumers. It
consists of three main
components; 1) power
station that produce
electricity from combustible
fuels or non-combustible
fuels; 2) transmission
lines that carry electricity
from power plants to
demand centers; and
3) transformers that reduce
voltage so distribution lines
carry power for final
delivery.
Department of Electrical Engg.SIET,Dhenkanal.
WHY WE NEED GRID?
๏ƒ˜ Improvement of
Reliability
๏ƒ˜ Improvement of
economics
๏ƒ˜ Improvement of
efficiency
๏ƒ˜ Imrovement of power
quality
๏ƒ˜ Improvement of security
& safety
๏ƒ˜ Controller of entire power
system
Department of Electrical Engg.SIET,Dhenkanal.
SELECTION OF SITE
๏ƒ˜ Selection of site for construction of a Grid Sub Station is the first
and important activity. This needs meticulous planning, fore-sight,
skillful observation and handling so that the selected site is
technically, environmentally, economically and socially optimal
and is the best suited to the requirements
The site should be:-
๏ƒ˜ As near the load centre as possible.
๏ƒ˜ Easily accessible to the public road to facilitate transport of
material
๏ƒ˜ Above highest flood level (HFL) so that there is no water logging.
๏ƒ˜ Sufficiently away from areas where police and military rifle
practices are held.
๏ƒ˜ Free from master plans / layouts or future development activities
to have free line
๏ƒ˜ The should be far away from Airport
Department of Electrical Engg.SIET,Dhenkanal.
REQUIREMENT OF LAND / AREA:-
๏ƒ˜ The site should have sufficient area to properly accommodate
the Sub Station buildings, structures, equipments, etc. and
should have the sufficient area for future extension of the
buildings and / or switchyard.
๏‚— The requirement of land for construction of Sub Station including
staff colony is as under:
S.No. Voltage Class of GSS Required Area
1 400 20.0 Hectare
2 220 6.0 Hectare
3 132 3.5 Hectare
Department of Electrical Engg.SIET,Dhenkanal.
Layout Design-Bus bar Schemes
The commonly used
bus bar schemes at
Sub Stations are:
๏ƒ˜ Single bus bar.
๏ƒ˜ Main and Auxiliary
bus bar.
๏ƒ˜ Double bus bar.
๏ƒ˜ Double Main and
Auxiliary bus bar
๏ƒ˜ One and a half
breaker scheme.
Department of Electrical Engg.SIET,Dhenkanal.
Single bus bar:-
๏‚— This is the simplest switching scheme
in which each circuit is provided with
one circuit breaker.
๏‚— This arrangement offers little security
against bus bar faults .
๏‚— The entire Sub Station is lost in case
of a fault on the bus bar.
๏‚— In case of maintenance of circuit
breaker, the associated feeder has
also to be shutdown.
Main and Auxiliary bus
Bar:-
๏‚— This is technically a single bus bar
arrangement with an additional
bus bar called โ€œAuxiliary busโ€.
๏‚— As in the case of single bus
arrangement, due to the fault the
entire substation is lost.
๏‚— This bus arrangement has been
extensively used in 132 kV Sub
Stations.
Department of Electrical Engg.SIET,Dhenkanal.
Double Bus Bar
๏‚— In this scheme, a double bus bar
arrangement is provided. Each circuit
can be connected to either one of these
bus bars through respective bus bar
isolator.
๏‚— Bus coupler breaker is also provided so
that the circuits can be switched on from
one bus to the other on load.
๏‚— This scheme suffers from the
disadvantage that when any circuit
breaker is taken out for maintenance, the
associated feeder has to be shutdown
๏‚— This Bus bar arrangement was generally
used in earlier 220 kV sub stations.
DOUBLE MAIN AND
AUXILIARY BUS BAR
ARRANGEMENT
๏‚— The limitation of double bus bar
scheme can be overcome by using
additional Auxiliary bus,.
๏‚— The feeder is transferred to the
Auxiliary bus during maintenance of its
controlling circuit breaker without
affecting the other ckt.
Department of Electrical Engg.SIET,Dhenkanal.
One & A Half Breaker Arrangement
๏‚— In this scheme, three circuit breakers
are used for controlling two circuits
which are connected between two bus
bars. Normally, both the bus bars are
in service.
๏‚— A fault on any one of the bus bars is
cleared by opening of the associated
circuit breakers connected to the faulty
bus bar without affecting continuity of
supply. Similarly any circuit breaker
can be taken out for maintenance
without causing interruption.
๏‚— Load transfer is achieved through the
breakers and, therefore, the operation
is simple.
๏‚— The breaker and a half scheme is best
for those substations which handle
large quantities of power and where
the orientation of out going.
๏‚— This scheme has been used in the
400 kV substations.
Department of Electrical Engg.SIET,Dhenkanal.
Electrical Layout Drawing
Department of Electrical Engg.SIET,Dhenkanal.
Department of Electrical Engg.SIET,Dhenkanal.
List of Material๏‚— The lists of material are only typical and cover the general requirement. Any
other
๏‚— equipment / structure / material which may be required for construction of
Sub Station as
๏‚— per layout and other requirements and not included in the above typical lists
of
Department of Electrical Engg.SIET,Dhenkanal.
Department of Electrical Engg.SIET,Dhenkanal.
Safety Clearance๏‚— The various equipments and associated / required facilities have to be so arranged within the substation that
specified minimum clearances are always available from the point of view of the system reliability and safety
of operating personnel. These include the minimum clearances from live parts to earth, between live parts of
adjacent phases and sectional clearance between live parts of adjacent circuits / bays. It must be ensured
that sufficient clearance to ground is also available within the Sub Station so as to ensure safety of the
personnel moving about within the switchyard.
๏‚— As per Rule 64 (2) of the Indian Electricity Rules, 1956, the following safety working
๏‚— clearances shall be maintained for the bare conductors and live parts of any apparatus in any
๏‚— Sub Stations, excluding over head lines of HV and EHV installations:
Nominal
system
Voltage
in (kv)
Highes
t
Syste
m
Voltag
e in(kv)
Lightin
g
impulse
Level(K
Vp)
Switching
Implulse
Voltage in
(KVp)
Minm
Clearance
Betn Phase
&Earth(mm)
Minm
clearanc
e Betn
Phases
(in mm)
Safety
Clearan
ce(mm)
Grou
nd
Clear
ance(
mm)
11 12 70 ---- 178 229 2600 3700
33 36 170 ---- 320 320 2800 3700
132 145 550
650
---- 1100
1300
1100
1300
3700
3800
4600
4600
220 245 950
1050
---- 1900
2100
1900
2100
4300
4600
5500
5500
400 420 1425 1050(Ph-
E)
3400
----
----
4200
6400 8000
Earth Mat Design
๏‚— Provision of adequate earthing system
in a Sub Station is extremely important
for the safety of the operating
personnel as well as for proper system
operation and performance of the
protective devices.
๏‚— The primary requirements of a good
earthing system in a Sub Station are
a):-The impedance to ground should
be as low as possible but it should not
exceed 1.0 (ONE) Ohm.
b):- The Step Potential, which is the
maximum value of the potential
difference possible of being shunted by
a human body between two accessible
points on the ground separated by the
distance of one pace (which may be
assumed to be one metre), should be
within safe limits.
c):- Touch Potential, which is the
maximum value of potential difference
between a point on the ground and a
point on an object likely to carry fault
current such that the points can be
touched by a person, should also be
within safe limits.
Department of Electrical Engg.SIET,Dhenkanal.
Cont.
The details of the earthing material generally used in a
sub station are given below:
Design of Control Room
๏‚— The control room is the
main command centre of
the substation. The entire
operation of the site is
monitored and controlled
from this central location.
๏‚— A control room may range
from a small, seldom
manned, non-ventilated
room to a large, air
conditioned area containing
numerous staff members
and electronic equipment
(PCs, control
panels/consoles, electrical
and electronic switching
devices, under floor
cabling, etc.).
Department of Electrical Engg.SIET,Dhenkanal.
Design of battery Room
๏‚— The Battery Room houses lead acid or
nickel cadmium batteries for uninterrupted
power supply (UPS) to the substation.
๏‚— In power grid normally 110 no. of batteries
are present, having each capacity of 2.1V
to maintain 220V output & the specific
gravity of liquid is 1.835.
๏‚— Power House FCBC are designed to
supply continuous power to the DC load
and simultaneously charge the batteries
connected. Input supply form 415V. AC 3
Phase or 220V. AC 1 Ph. is converted to
regulated DC. The charger has two
independent systems.
๏‚— Normally the DC Power is supplied to he
load by the Float Charger. It also supplies
trickle current to the battery to keep it
healthy. If the charging current under Float
Mode exceeds a set level.Boost charger is
switched ON. It supplies Quick charging
current to the battery. On battery reaching
the set value the Boost Charger is switched
OFF.
Department of Electrical Engg.SIET,Dhenkanal.
Design of Switch/Relay Room
๏‚— The Switch Room
accommodates high density of
electronic equipment housed
in cabinets and automated
switch-gear. In-cabinet
equipment maintain the
primary functions of the facility
and form the switching
interface between the Control
Room and the field
equipment. The area may also
accommodate a significant
amount of metering and
logging equipment. Due to the
high volume of critical
electronic equipment, it is
essential that a fire event be
detected before the operation
of the plant is compromised.Department of Electrical Engg.SIET,Dhenkanal.
Grid Equipments
Lighting Arrestor
๏ƒ˜ It is an instrument that protect
vital equipments in the grid
๏ƒ˜ when a lightning strikes a
power transmission line, the
induced high voltage travels
along the line towards both
ends; this arrester will bypass
this high voltage to the ground
so that the nearby transformer
will not be damaged.
Line Volt.(KV) L.A.Rating(KV)
400 327
220 180
132 108
33 27
CVT:-
๏ƒ˜ It is that type tfr which is used to
measure potential
๏ƒ˜ It is the major advantage of PT, &
also used for carrier
communication, which replace the
coupling capacitor.
๏ƒ˜ At first for carrier communication a
coupling capacitor is used with a
PT, which is costlier than CVT.
๏ƒ˜ It act as a high pass filter.
Connection diagram of CVT
Potential
transformer:-
๏‚— Potential Transformer or Voltage
Transformer are used in electrical
power system for stepping down
the system voltage to a safe value
which can be fed to low ratings
meters and relays. Commercially
available relays and meters used
for protection and metering, are
designed for low voltage.
Current Transformer:-
๏‚— A current transformer is
used in high voltage
circuits where it is not
possible to measure
current directly.
๏‚— A CT is a step up
transformer with only one
turn in primary. There will
be as many cores based
on the purposes like
metering, protection etc.
๏‚— The secondary of a CT
should never be kept open
circuited because very high
flux will be developed in the
secondary and hence it
may be damaged.
Power TRANSFORMER
๏ƒ˜ It is a static device which
transforms electrical energy from
one ckt to another ckt without
change of frequency, but changing
voltage with the principle mutual
induction.
๏ƒ˜ Most of the power transformer are
in MVA ratings.
๏ƒ˜ It is the most costlier equipments
in the grid.
๏‚— INSULATOR:-
๏‚— Insulators are used to prevent
flow of current from
conducting material to non
conducting material.
๏‚— It should be mechanically
strong & high dielectric
strength.
๏‚— Each insulator rating is of
11kv to 16kv.
Wave Trap:-
๏ƒ˜It is the combination of inductance &
capacitance, which act as a low pass filter,
which passes low frequencies in to the
grid, & this frequency is used in the grid.
๏ƒ˜The Line trap offers high impedance to
the high frequency communication signals
thus obstructs the flow of these signals in
to the substation bus bars. If there were
not to be there, then signal loss is more
and communication will be
ineffective/probably impossible.
Circuit breaker:-
๏ƒ˜ It is protective equipments in the
grid.
๏ƒ˜ It is the automatic on load switch.
๏ƒ˜ There are of 5 medium type of
circuit breaker., but SF6 ckt
breaker is used for best.
Isolators:-
๏ƒ˜ This is an off load switching
device to used open or close for
flow of current or not to flow
respectively in the grid.
Conclusion:-
๏‚— Grid is the nodal point of the
entire power system.
๏‚— It has two objectives i.e.1: Supply
Quality Power, 2:Supply the power
from source to load with an
economic reasons.
๏‚— AS Grids are interconnected so,
there is an improvement of
reliability of can achieved.
๏‚— As grid is the nodal point, if it fails
to work, then entire power system
will fails.
๏‚— Grid efficiency is lower i.e. 50-
70%.
๏‚— As Grid has too many equipments
so, design of grid is too costlier.
Reference:-
๏ƒ˜ Construction Manual for substations by Shreemat Pandey Chairman &
Managing Director Jaipur Rajasthan Rajya Vidyut Prasaran Nigam Ltd.
๏ƒ˜ Albert, R., Albert, I., and Nakarado, G. L. (2004). Structural Vulnerability of
the North American Power Grid. Physical Review E 69 025103(R). 1-4 pgs.
๏ƒ˜ Grid Manual of OPTCL.
๏ƒ˜ http://www.powergridindia.com
33Dept of Electrical Engg.

More Related Content

What's hot

Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss Calculation
Ameen San
ย 
Load flow studies 19
Load flow studies 19Load flow studies 19
Load flow studies 19
Asha Anu Kurian
ย 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parameters
firaoltemesgen1
ย 
Load flow study
Load flow studyLoad flow study
Load flow study
Hozefa Jinya
ย 
Flexible ac transmission system
Flexible ac transmission systemFlexible ac transmission system
Flexible ac transmission system
Uday Wankar
ย 
Sssc
SsscSssc
Sssc
Divya Yennam
ย 
Transmission & distribution of electrical power
Transmission & distribution of electrical powerTransmission & distribution of electrical power
Transmission & distribution of electrical power
priyanka1432
ย 
Wide Area Monitoring System WAMS & Applications
Wide Area Monitoring System WAMS & ApplicationsWide Area Monitoring System WAMS & Applications
Wide Area Monitoring System WAMS & Applications
Power System Operation
ย 
Electrical Power substation
Electrical Power substationElectrical Power substation
Electrical Power substation
Emran Ali
ย 
Distributed Generation
Distributed Generation Distributed Generation
Distributed Generation
Anshul Shrivastava
ย 
Facts controller
Facts controllerFacts controller
Facts controller
Debayon Saha
ย 
Unit 1 Power System Stability
Unit 1 Power System Stability Unit 1 Power System Stability
Unit 1 Power System Stability
SANTOSH GADEKAR
ย 
Grid integration issues and solutions
Grid integration issues and solutionsGrid integration issues and solutions
Grid integration issues and solutions
Swathi Venugopal
ย 
Distributed generation b 3
Distributed generation b 3Distributed generation b 3
Distributed generation b 3
Naresh Thakur
ย 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
vishalgohel12195
ย 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substation
raiamitesh8
ย 
Load dispatch center
Load dispatch centerLoad dispatch center
Load dispatch center
ddxdharmesh
ย 
Structure of power system
Structure of power systemStructure of power system
Structure of power system
Revathi Subramaniam
ย 
Protection of Transmission lines
Protection of Transmission linesProtection of Transmission lines
Protection of Transmission lines
Power System Operation
ย 
Energy meter
Energy meterEnergy meter
Energy meter
Dinesh Sharma
ย 

What's hot (20)

Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss Calculation
ย 
Load flow studies 19
Load flow studies 19Load flow studies 19
Load flow studies 19
ย 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parameters
ย 
Load flow study
Load flow studyLoad flow study
Load flow study
ย 
Flexible ac transmission system
Flexible ac transmission systemFlexible ac transmission system
Flexible ac transmission system
ย 
Sssc
SsscSssc
Sssc
ย 
Transmission & distribution of electrical power
Transmission & distribution of electrical powerTransmission & distribution of electrical power
Transmission & distribution of electrical power
ย 
Wide Area Monitoring System WAMS & Applications
Wide Area Monitoring System WAMS & ApplicationsWide Area Monitoring System WAMS & Applications
Wide Area Monitoring System WAMS & Applications
ย 
Electrical Power substation
Electrical Power substationElectrical Power substation
Electrical Power substation
ย 
Distributed Generation
Distributed Generation Distributed Generation
Distributed Generation
ย 
Facts controller
Facts controllerFacts controller
Facts controller
ย 
Unit 1 Power System Stability
Unit 1 Power System Stability Unit 1 Power System Stability
Unit 1 Power System Stability
ย 
Grid integration issues and solutions
Grid integration issues and solutionsGrid integration issues and solutions
Grid integration issues and solutions
ย 
Distributed generation b 3
Distributed generation b 3Distributed generation b 3
Distributed generation b 3
ย 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
ย 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substation
ย 
Load dispatch center
Load dispatch centerLoad dispatch center
Load dispatch center
ย 
Structure of power system
Structure of power systemStructure of power system
Structure of power system
ย 
Protection of Transmission lines
Protection of Transmission linesProtection of Transmission lines
Protection of Transmission lines
ย 
Energy meter
Energy meterEnergy meter
Energy meter
ย 

Viewers also liked

Financial Analysis HINDALCO 2009
Financial Analysis HINDALCO 2009Financial Analysis HINDALCO 2009
Financial Analysis HINDALCO 2009
Govind Kumar Rai
ย 
PPT POWER GRID CORPORATION OF INDIA LIMITED
PPT POWER GRID CORPORATION OF INDIA LIMITED PPT POWER GRID CORPORATION OF INDIA LIMITED
PPT POWER GRID CORPORATION OF INDIA LIMITED
Aditya Shankar
ย 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantDr. Ramesh B
ย 
Best ppt onRenewable & hydropower
Best ppt onRenewable & hydropowerBest ppt onRenewable & hydropower
Best ppt onRenewable & hydropower
Ronak Thakare
ย 
Auto Cad Powerpoint
Auto Cad PowerpointAuto Cad Powerpoint
Auto Cad Powerpoint
valariawillis
ย 
Smart grid ppt
Smart grid pptSmart grid ppt
Smart grid ppt
Ravish Pandey
ย 
Smart Grid Technology
Smart Grid TechnologySmart Grid Technology
Smart Grid Technology
ShriramGokhale
ย 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plant
pranavn007
ย 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
Yuri Melliza
ย 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
Nimesh Mahadik
ย 
Anurag Arpan (PPT on AutoCAD )
Anurag Arpan (PPT on AutoCAD )Anurag Arpan (PPT on AutoCAD )
Anurag Arpan (PPT on AutoCAD )Anurag Arpan
ย 

Viewers also liked (11)

Financial Analysis HINDALCO 2009
Financial Analysis HINDALCO 2009Financial Analysis HINDALCO 2009
Financial Analysis HINDALCO 2009
ย 
PPT POWER GRID CORPORATION OF INDIA LIMITED
PPT POWER GRID CORPORATION OF INDIA LIMITED PPT POWER GRID CORPORATION OF INDIA LIMITED
PPT POWER GRID CORPORATION OF INDIA LIMITED
ย 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
ย 
Best ppt onRenewable & hydropower
Best ppt onRenewable & hydropowerBest ppt onRenewable & hydropower
Best ppt onRenewable & hydropower
ย 
Auto Cad Powerpoint
Auto Cad PowerpointAuto Cad Powerpoint
Auto Cad Powerpoint
ย 
Smart grid ppt
Smart grid pptSmart grid ppt
Smart grid ppt
ย 
Smart Grid Technology
Smart Grid TechnologySmart Grid Technology
Smart Grid Technology
ย 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plant
ย 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
ย 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
ย 
Anurag Arpan (PPT on AutoCAD )
Anurag Arpan (PPT on AutoCAD )Anurag Arpan (PPT on AutoCAD )
Anurag Arpan (PPT on AutoCAD )
ย 

Similar to Ppt power grid design

Universal Four Leg v4
Universal Four Leg v4Universal Four Leg v4
Universal Four Leg v4
AxelDijksman
ย 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
Shuvam Pathania
ย 
power grid design
power grid designpower grid design
power grid designsusanta das
ย 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )
AnandMohan271812
ย 
NTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportNTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship report
Aneel-k Suthar
ย 
33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-systemMasterhead Jack
ย 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
Rajashekar Gurrala
ย 
internship report of 220/132 kV substation
internship report of 220/132 kV substationinternship report of 220/132 kV substation
internship report of 220/132 kV substation
ShivamUpadhyay86734
ย 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
IJERD Editor
ย 
Smart Wireless Battery Charger with Charging Monitor: A Review
Smart Wireless Battery Charger with Charging Monitor: A ReviewSmart Wireless Battery Charger with Charging Monitor: A Review
Smart Wireless Battery Charger with Charging Monitor: A Review
IRJET Journal
ย 
Design of substation
Design of substationDesign of substation
Design of substation
SayanSarkar55
ย 
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdfDesign_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Engnr Kami Zeb
ย 
Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...
Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...
Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...
IRJET Journal
ย 
33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-system
babu yadav
ย 
Green power zone
Green power zoneGreen power zone
Green power zone
CHESF
ย 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation
Madeen Kumar
ย 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
Tejveer Choudhary
ย 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
Devesh54
ย 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
Ashutosh Srivastava
ย 

Similar to Ppt power grid design (20)

Universal Four Leg v4
Universal Four Leg v4Universal Four Leg v4
Universal Four Leg v4
ย 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
ย 
power grid design
power grid designpower grid design
power grid design
ย 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )
ย 
NTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportNTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship report
ย 
33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-system
ย 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
ย 
internship report of 220/132 kV substation
internship report of 220/132 kV substationinternship report of 220/132 kV substation
internship report of 220/132 kV substation
ย 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
ย 
Smart Wireless Battery Charger with Charging Monitor: A Review
Smart Wireless Battery Charger with Charging Monitor: A ReviewSmart Wireless Battery Charger with Charging Monitor: A Review
Smart Wireless Battery Charger with Charging Monitor: A Review
ย 
Design of substation
Design of substationDesign of substation
Design of substation
ย 
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdfDesign_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
ย 
Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...
Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...
Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...
ย 
33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-system
ย 
Green power zone
Green power zoneGreen power zone
Green power zone
ย 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation
ย 
bhuwnesh
bhuwneshbhuwnesh
bhuwnesh
ย 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
ย 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
ย 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
ย 

Recently uploaded

Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
ย 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
tjcomstrang
ย 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
ย 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
ย 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
fisherameliaisabella
ย 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
ย 
Bร i tแบญp - Tiแบฟng anh 11 Global Success UNIT 1 - Bแบฃn HS.doc
Bร i tแบญp - Tiแบฟng anh 11 Global Success UNIT 1 - Bแบฃn HS.docBร i tแบญp - Tiแบฟng anh 11 Global Success UNIT 1 - Bแบฃn HS.doc
Bร i tแบญp - Tiแบฟng anh 11 Global Success UNIT 1 - Bแบฃn HS.doc
daothibichhang1
ย 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
ย 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
ย 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
ย 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
ย 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
ย 
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Lviv Startup Club
ย 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
ย 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
Lviv Startup Club
ย 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
ย 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
Norma Mushkat Gaffin
ย 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
ย 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
ย 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
Corey Perlman, Social Media Speaker and Consultant
ย 

Recently uploaded (20)

Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
ย 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
ย 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
ย 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
ย 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ย 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
ย 
Bร i tแบญp - Tiแบฟng anh 11 Global Success UNIT 1 - Bแบฃn HS.doc
Bร i tแบญp - Tiแบฟng anh 11 Global Success UNIT 1 - Bแบฃn HS.docBร i tแบญp - Tiแบฟng anh 11 Global Success UNIT 1 - Bแบฃn HS.doc
Bร i tแบญp - Tiแบฟng anh 11 Global Success UNIT 1 - Bแบฃn HS.doc
ย 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
ย 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
ย 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
ย 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
ย 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
ย 
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
ย 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
ย 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
ย 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
ย 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
ย 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
ย 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
ย 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
ย 

Ppt power grid design

  • 1. Department of Electrical Engg.SIET,Dhenkanal.
  • 2. Synergy Institute of Engineering & Technology,Dhenkanal Seminar on Power Grid Design Submitted by Susanta Das 7th Semester B.Tech Reg.No-0901230234 Seminar Guide Mr. A. Panda Department of Electrical Engg.SIET,Dhenkanal. 2
  • 3. Outline of Presentation ๏ƒ˜ Introduction ๏ƒ˜ Need of Power Grids ๏ƒ˜ Selection Site ๏ƒ˜ Layout Design 1.Busbar Schemes 2.Electrical Layout Drawing 3.Bill of Material ๏ƒ˜ Safety Clearance in Grid ๏ƒ˜ Design of Earth Mat ๏ƒ˜ Control Room ๏ƒ˜ Switch/Relay Room ๏ƒ˜ Grid Equipments ๏ƒ˜ Conclusion ๏ƒ˜ Reference Department of Electrical Engg.SIET,Dhenkanal.
  • 4. INTRODUCTION ๏‚— An electrical grid is an interconnected network for delivering electricity from suppliers to consumers. It consists of three main components; 1) power station that produce electricity from combustible fuels or non-combustible fuels; 2) transmission lines that carry electricity from power plants to demand centers; and 3) transformers that reduce voltage so distribution lines carry power for final delivery. Department of Electrical Engg.SIET,Dhenkanal.
  • 5. WHY WE NEED GRID? ๏ƒ˜ Improvement of Reliability ๏ƒ˜ Improvement of economics ๏ƒ˜ Improvement of efficiency ๏ƒ˜ Imrovement of power quality ๏ƒ˜ Improvement of security & safety ๏ƒ˜ Controller of entire power system Department of Electrical Engg.SIET,Dhenkanal.
  • 6. SELECTION OF SITE ๏ƒ˜ Selection of site for construction of a Grid Sub Station is the first and important activity. This needs meticulous planning, fore-sight, skillful observation and handling so that the selected site is technically, environmentally, economically and socially optimal and is the best suited to the requirements The site should be:- ๏ƒ˜ As near the load centre as possible. ๏ƒ˜ Easily accessible to the public road to facilitate transport of material ๏ƒ˜ Above highest flood level (HFL) so that there is no water logging. ๏ƒ˜ Sufficiently away from areas where police and military rifle practices are held. ๏ƒ˜ Free from master plans / layouts or future development activities to have free line ๏ƒ˜ The should be far away from Airport Department of Electrical Engg.SIET,Dhenkanal.
  • 7. REQUIREMENT OF LAND / AREA:- ๏ƒ˜ The site should have sufficient area to properly accommodate the Sub Station buildings, structures, equipments, etc. and should have the sufficient area for future extension of the buildings and / or switchyard. ๏‚— The requirement of land for construction of Sub Station including staff colony is as under: S.No. Voltage Class of GSS Required Area 1 400 20.0 Hectare 2 220 6.0 Hectare 3 132 3.5 Hectare Department of Electrical Engg.SIET,Dhenkanal.
  • 8. Layout Design-Bus bar Schemes The commonly used bus bar schemes at Sub Stations are: ๏ƒ˜ Single bus bar. ๏ƒ˜ Main and Auxiliary bus bar. ๏ƒ˜ Double bus bar. ๏ƒ˜ Double Main and Auxiliary bus bar ๏ƒ˜ One and a half breaker scheme. Department of Electrical Engg.SIET,Dhenkanal.
  • 9. Single bus bar:- ๏‚— This is the simplest switching scheme in which each circuit is provided with one circuit breaker. ๏‚— This arrangement offers little security against bus bar faults . ๏‚— The entire Sub Station is lost in case of a fault on the bus bar. ๏‚— In case of maintenance of circuit breaker, the associated feeder has also to be shutdown. Main and Auxiliary bus Bar:- ๏‚— This is technically a single bus bar arrangement with an additional bus bar called โ€œAuxiliary busโ€. ๏‚— As in the case of single bus arrangement, due to the fault the entire substation is lost. ๏‚— This bus arrangement has been extensively used in 132 kV Sub Stations. Department of Electrical Engg.SIET,Dhenkanal.
  • 10. Double Bus Bar ๏‚— In this scheme, a double bus bar arrangement is provided. Each circuit can be connected to either one of these bus bars through respective bus bar isolator. ๏‚— Bus coupler breaker is also provided so that the circuits can be switched on from one bus to the other on load. ๏‚— This scheme suffers from the disadvantage that when any circuit breaker is taken out for maintenance, the associated feeder has to be shutdown ๏‚— This Bus bar arrangement was generally used in earlier 220 kV sub stations. DOUBLE MAIN AND AUXILIARY BUS BAR ARRANGEMENT ๏‚— The limitation of double bus bar scheme can be overcome by using additional Auxiliary bus,. ๏‚— The feeder is transferred to the Auxiliary bus during maintenance of its controlling circuit breaker without affecting the other ckt. Department of Electrical Engg.SIET,Dhenkanal.
  • 11. One & A Half Breaker Arrangement ๏‚— In this scheme, three circuit breakers are used for controlling two circuits which are connected between two bus bars. Normally, both the bus bars are in service. ๏‚— A fault on any one of the bus bars is cleared by opening of the associated circuit breakers connected to the faulty bus bar without affecting continuity of supply. Similarly any circuit breaker can be taken out for maintenance without causing interruption. ๏‚— Load transfer is achieved through the breakers and, therefore, the operation is simple. ๏‚— The breaker and a half scheme is best for those substations which handle large quantities of power and where the orientation of out going. ๏‚— This scheme has been used in the 400 kV substations. Department of Electrical Engg.SIET,Dhenkanal.
  • 12. Electrical Layout Drawing Department of Electrical Engg.SIET,Dhenkanal.
  • 13. Department of Electrical Engg.SIET,Dhenkanal.
  • 14. List of Material๏‚— The lists of material are only typical and cover the general requirement. Any other ๏‚— equipment / structure / material which may be required for construction of Sub Station as ๏‚— per layout and other requirements and not included in the above typical lists of Department of Electrical Engg.SIET,Dhenkanal.
  • 15. Department of Electrical Engg.SIET,Dhenkanal.
  • 16.
  • 17. Safety Clearance๏‚— The various equipments and associated / required facilities have to be so arranged within the substation that specified minimum clearances are always available from the point of view of the system reliability and safety of operating personnel. These include the minimum clearances from live parts to earth, between live parts of adjacent phases and sectional clearance between live parts of adjacent circuits / bays. It must be ensured that sufficient clearance to ground is also available within the Sub Station so as to ensure safety of the personnel moving about within the switchyard. ๏‚— As per Rule 64 (2) of the Indian Electricity Rules, 1956, the following safety working ๏‚— clearances shall be maintained for the bare conductors and live parts of any apparatus in any ๏‚— Sub Stations, excluding over head lines of HV and EHV installations: Nominal system Voltage in (kv) Highes t Syste m Voltag e in(kv) Lightin g impulse Level(K Vp) Switching Implulse Voltage in (KVp) Minm Clearance Betn Phase &Earth(mm) Minm clearanc e Betn Phases (in mm) Safety Clearan ce(mm) Grou nd Clear ance( mm) 11 12 70 ---- 178 229 2600 3700 33 36 170 ---- 320 320 2800 3700 132 145 550 650 ---- 1100 1300 1100 1300 3700 3800 4600 4600 220 245 950 1050 ---- 1900 2100 1900 2100 4300 4600 5500 5500 400 420 1425 1050(Ph- E) 3400 ---- ---- 4200 6400 8000
  • 18. Earth Mat Design ๏‚— Provision of adequate earthing system in a Sub Station is extremely important for the safety of the operating personnel as well as for proper system operation and performance of the protective devices. ๏‚— The primary requirements of a good earthing system in a Sub Station are a):-The impedance to ground should be as low as possible but it should not exceed 1.0 (ONE) Ohm. b):- The Step Potential, which is the maximum value of the potential difference possible of being shunted by a human body between two accessible points on the ground separated by the distance of one pace (which may be assumed to be one metre), should be within safe limits. c):- Touch Potential, which is the maximum value of potential difference between a point on the ground and a point on an object likely to carry fault current such that the points can be touched by a person, should also be within safe limits. Department of Electrical Engg.SIET,Dhenkanal.
  • 19. Cont. The details of the earthing material generally used in a sub station are given below:
  • 20. Design of Control Room ๏‚— The control room is the main command centre of the substation. The entire operation of the site is monitored and controlled from this central location. ๏‚— A control room may range from a small, seldom manned, non-ventilated room to a large, air conditioned area containing numerous staff members and electronic equipment (PCs, control panels/consoles, electrical and electronic switching devices, under floor cabling, etc.). Department of Electrical Engg.SIET,Dhenkanal.
  • 21. Design of battery Room ๏‚— The Battery Room houses lead acid or nickel cadmium batteries for uninterrupted power supply (UPS) to the substation. ๏‚— In power grid normally 110 no. of batteries are present, having each capacity of 2.1V to maintain 220V output & the specific gravity of liquid is 1.835. ๏‚— Power House FCBC are designed to supply continuous power to the DC load and simultaneously charge the batteries connected. Input supply form 415V. AC 3 Phase or 220V. AC 1 Ph. is converted to regulated DC. The charger has two independent systems. ๏‚— Normally the DC Power is supplied to he load by the Float Charger. It also supplies trickle current to the battery to keep it healthy. If the charging current under Float Mode exceeds a set level.Boost charger is switched ON. It supplies Quick charging current to the battery. On battery reaching the set value the Boost Charger is switched OFF. Department of Electrical Engg.SIET,Dhenkanal.
  • 22. Design of Switch/Relay Room ๏‚— The Switch Room accommodates high density of electronic equipment housed in cabinets and automated switch-gear. In-cabinet equipment maintain the primary functions of the facility and form the switching interface between the Control Room and the field equipment. The area may also accommodate a significant amount of metering and logging equipment. Due to the high volume of critical electronic equipment, it is essential that a fire event be detected before the operation of the plant is compromised.Department of Electrical Engg.SIET,Dhenkanal.
  • 23. Grid Equipments Lighting Arrestor ๏ƒ˜ It is an instrument that protect vital equipments in the grid ๏ƒ˜ when a lightning strikes a power transmission line, the induced high voltage travels along the line towards both ends; this arrester will bypass this high voltage to the ground so that the nearby transformer will not be damaged. Line Volt.(KV) L.A.Rating(KV) 400 327 220 180 132 108 33 27
  • 24. CVT:- ๏ƒ˜ It is that type tfr which is used to measure potential ๏ƒ˜ It is the major advantage of PT, & also used for carrier communication, which replace the coupling capacitor. ๏ƒ˜ At first for carrier communication a coupling capacitor is used with a PT, which is costlier than CVT. ๏ƒ˜ It act as a high pass filter. Connection diagram of CVT
  • 25. Potential transformer:- ๏‚— Potential Transformer or Voltage Transformer are used in electrical power system for stepping down the system voltage to a safe value which can be fed to low ratings meters and relays. Commercially available relays and meters used for protection and metering, are designed for low voltage.
  • 26. Current Transformer:- ๏‚— A current transformer is used in high voltage circuits where it is not possible to measure current directly. ๏‚— A CT is a step up transformer with only one turn in primary. There will be as many cores based on the purposes like metering, protection etc. ๏‚— The secondary of a CT should never be kept open circuited because very high flux will be developed in the secondary and hence it may be damaged.
  • 27. Power TRANSFORMER ๏ƒ˜ It is a static device which transforms electrical energy from one ckt to another ckt without change of frequency, but changing voltage with the principle mutual induction. ๏ƒ˜ Most of the power transformer are in MVA ratings. ๏ƒ˜ It is the most costlier equipments in the grid.
  • 28. ๏‚— INSULATOR:- ๏‚— Insulators are used to prevent flow of current from conducting material to non conducting material. ๏‚— It should be mechanically strong & high dielectric strength. ๏‚— Each insulator rating is of 11kv to 16kv. Wave Trap:- ๏ƒ˜It is the combination of inductance & capacitance, which act as a low pass filter, which passes low frequencies in to the grid, & this frequency is used in the grid. ๏ƒ˜The Line trap offers high impedance to the high frequency communication signals thus obstructs the flow of these signals in to the substation bus bars. If there were not to be there, then signal loss is more and communication will be ineffective/probably impossible.
  • 29. Circuit breaker:- ๏ƒ˜ It is protective equipments in the grid. ๏ƒ˜ It is the automatic on load switch. ๏ƒ˜ There are of 5 medium type of circuit breaker., but SF6 ckt breaker is used for best. Isolators:- ๏ƒ˜ This is an off load switching device to used open or close for flow of current or not to flow respectively in the grid.
  • 30. Conclusion:- ๏‚— Grid is the nodal point of the entire power system. ๏‚— It has two objectives i.e.1: Supply Quality Power, 2:Supply the power from source to load with an economic reasons. ๏‚— AS Grids are interconnected so, there is an improvement of reliability of can achieved. ๏‚— As grid is the nodal point, if it fails to work, then entire power system will fails. ๏‚— Grid efficiency is lower i.e. 50- 70%. ๏‚— As Grid has too many equipments so, design of grid is too costlier.
  • 31. Reference:- ๏ƒ˜ Construction Manual for substations by Shreemat Pandey Chairman & Managing Director Jaipur Rajasthan Rajya Vidyut Prasaran Nigam Ltd. ๏ƒ˜ Albert, R., Albert, I., and Nakarado, G. L. (2004). Structural Vulnerability of the North American Power Grid. Physical Review E 69 025103(R). 1-4 pgs. ๏ƒ˜ Grid Manual of OPTCL. ๏ƒ˜ http://www.powergridindia.com