SlideShare a Scribd company logo
Strengthening of Indian Grid
Mohit Kathel indianpowerindutry.com
Deviation Settlement Mechanism and Related Matters
CERC Regulation 2014
CERC on 17.02.2014 has replaced the UI regulation 2009 with Deviation settlement mechanism regulation 2014 in
order to strengthen the grid and improve grid stability. This step was taken to ensure that situations of grid failure
like that of 30th
& 31st
July will not happen again. The grid failure has presented a case where some state were using
the UI as a trading platform, during the grid failure states like Haryana, U.P were overdrawing heavily whereas states
like Rajasthan & MP were under drawing from their schedule resulting in frequency varying in the specified range
and at the same time making the grid unstable thus resulting in grid failure.
With this regulation CERC has implemented volume limit for buyer and seller depending on their approved schedule,
range of frequency has tighten, charges for the unscheduled interchange or deviation has increased to ensure a
better demand predictability by states and to avoid UI as a trading platform.
Deviation & Settlement Mechanism will definitely improve the grid discipline and will help the state to initiate
forecasting of demand and schedule in more accurate and stringent manner. Various provisions made in the
regulation such as volume limits, additional charges etc will force the state to procure power through bilateral route
or on day ahead basis which surely help in fund flow and eventually improve the position of power sector.
A summary of the deviation settlement mechanism and its comparison with the previous prevailing UI regulation is
provided below.
1. Title & Commencement: Deviation settlement mechanism & related matters regulation 2014, came into force on
17.02.2014.
2. Reference Regulation:
a. Grant of connectivity, LTOA & MTOA in interstate transmission regulation 2009.
b. Interface Meters (Installation & operation of meters) regulation 2006.
c. Open Access in interstate transmission regulation 2008.
3. Objective of the regulation is to enhance grid discipline & grid security.
4. Applicable on Inter-state transmission of electricity.
5. Charges receivable for under drawl by buyer and over injection by seller, while charges are payable for over drawl
by buyer and under injection by seller.
6. Provisions made in regulation:
a. Redefined frequency range and rates.
b. Volume limits and deviation limits for generator and buyer
c. Cap Rate applicable
d. Charges & Additional Charges
e. Methodology for calculation of deviation charges.
7. Charges and conditions applicable:
a. Charges for each step increment of frequency for each 0.01 Hz step is now equivalent to increment
of 35.60 Paise/unit in the frequency range of 50.05-50.00 Hz & 20.84 Paise/unit in frequency range
between 50.00Hz to not below 49.70 Hz, resulting in charges at 50.05Hz @ 0.00 Paise/unit, at
50.04Hz @ 35.60 till 50.00 Hz @ 178 Paise/unit and then from 49.99Hz onwards charges will
increase at a rate of 20.84 till 49.7Hz @ 824.04 Paise/unit. In UI regulation 2009 charges for each
step of frequency for each 0.02 Hz was equivalent to 16.50 Paise/Unit from 50.20Hz till 50.02Hz, i.e
charges were at 50.20Hz @ 0.00 Paise/unit & at 50.02 @ 148.50 Paise/Unit, and then from 50.00Hz
Strengthening of Indian Grid
Mohit Kathel indianpowerindutry.com
onwards each step increment was equivalent to Rs. 28.12 Paise/Unit i.e. charges at 50.00Hz @
165.00 Paise/Kwh till 49.5Hz @ 900.00 Paise/Unit.
b. Cap Rates are redefined in the present regulation, now the cap rate for generating stations using fuel
which comes under APM is reduced to 303.04 Paise/Kwh from 421.50 paise/Kwh for higher or lower
injection than the scheduled generation. Also, now there is no cap rate on generating stations which
are regulated by consumer and are using Gas as fuel under APM.
c. Charges for over injection by seller and under drawl by buyer in excess of 12% of schedule or 150
MW whichever is less shall be 0. Earlier over injection upto 120% of schedule is allowed on the
corresponding frequency rate and in excess of 120% there was a cap rate of 450.00 Paise/Unit,
although it was subject to 105% of declared capacity of plant in a time block and 101% of capacity of
plant in a day.
d. Earlier if the injection of plant increases beyond 105% of its declared capacity in a time block or
101% of declared capacity in a day then charges for such injection will be charged at a rate of 165
Paise/unit. In the present regulation there are no such rules applicable on power plants.
e. Clause for infirm injection before COD of generating unit is almost similar to that of UI regulation
2009, There is no volume drawl or injection limit on generating station although there is a cap rate
on injection which is subject to the fuel used, for APM gas cap rate has increased from earlier charge
of 2.60 Rs/Unit to 5.64 Rs/Unit.
f. Volume Limits have been implemented in the present regulation, earlier there wasn’t any volume
limits on the overall injection or drawl, although based upon different UI volume, charges
corresponding to percentage of prevailing UI charges and Cap Rates were there.
g. Earlier for over drawal when frequency is below 49.80Hz, additional charges were there. Now there
are volume limits too which are 12% of schedule or 150 MW whichever is less. Also, now additional
charges are levied based on the deviation from schedule and not upon the frequency range as was
earlier.
In the present regulation no under injection of electricity by a seller shall be permissible when grid frequency is
"below 49.70 Hz" and no over injection of electricity by a seller shall be permissible when grid frequency is "50.10
Hz and above.
However, additional charges shall be levied now depending on the deviation from schedule more than the allowed
limits i.e. 12% or 150 MW whichever is less and also depends upon the frequency. Different charges are defined for
the frequency range 49.70 Hz and above and below 49.70Hz of frequency.
1. When grid frequency is 49.70Hz and above
a. When 12% is lesser or equal to 150 MW
b. When 12% is more or equal to 150 MW
2. When grid frequency is below 49.7 Hz
Each of the cases will apply for over drawal by a buyer and under injection by a seller when the actual
drawl/injection is higher than the specified limits.
For Over-Drawal by a buyer when frequency is 49.70 Hz or above
When 12%<=150MW When 12% >= 150 MW Additional Charges
a. 12%-15% 150MW to 200MW
+20% charges of deviation charge
corresponding to average grid
frequency of the time block.
b. 15%-20% 200 MW to 250 MW +40% charges of deviation charge
Strengthening of Indian Grid
Mohit Kathel indianpowerindutry.com
corresponding to average grid
frequency of the time block.
c. 20% & Above 250 MW and above
+100% charges of deviation charge
corresponding to average grid
frequency of the time block.
For Under-Injection by a seller when frequency is 49.70 Hz or above
When 12%<=150MW When 12% >= 150 MW Additional Charges
a. 12%-15% 150MW to 200MW
+20% charges of deviation charge
corresponding to average grid
frequency of the time block.
b. 15%-20% 200 MW to 250 MW
+40% charges of deviation charge
corresponding to average grid
frequency of the time block.
c. 20% & Above 250 MW and above
+100% charges of deviation charge
corresponding to average grid
frequency of the time block.
For Under-Injection by a seller using fuel coal/gas/lignite under APM & when frequency is 49.70 Hz or above
When 12%<=150MW When 12% >= 150 MW Additional Charges
a. 12%-15% 150MW to 200MW
+20% of 303.04 Paise/Unit or
deviation charge corresponding to
average grid frequency of the time
block whichever is less.
b. 15%-20% 200 MW to 250 MW
+40% of 303.04 Paise/Unit or
deviation charge corresponding to
average grid frequency of the time
block whichever is less.
c. 20% & Above 250 MW and above
+100% of 303.04 Paise/Unit or
deviation charge corresponding to
average grid frequency of the time
block whichever is less.
When grid the frequency is below 49.70Hz, additional charges are levied for over drawal by a buyer or under-
injection by a seller and are equivalent to 100% of 824.04 Paise/unit i.e. 1648.08 Paise/unit for the deviation.
Similarly for generating station using coal/gas/lignite additional charges are equivalent to 100% of the cap rate
(303.04 paise/kwh).
Provided:
1. Additional charge for deviation also be levied for over-injection or under-drawal when grid frequency is
50.10Hz or above at the rates equivalent to charges of deviation corresponding to the grid frequency of
“below 50.01 Hz but not below 50.0 Hz” i.e. 178.00 Paise/unit.
2. No additional charges are levied on generating station prior to COD of unit.
3. These charges and regulation are subject to change depending upon the order, rules, amendments or
regulation of CERC.

More Related Content

What's hot

From centralised long-term planning to market-based access: Proposed change i...
From centralised long-term planning to market-based access: Proposed change i...From centralised long-term planning to market-based access: Proposed change i...
From centralised long-term planning to market-based access: Proposed change i...
Amitava Nag
 
Availability based tariff
Availability based tariffAvailability based tariff
Availability based tariff
Power grid corporation of india limited
 
Tariff structure & Cerc tariff regulation
Tariff structure & Cerc tariff regulationTariff structure & Cerc tariff regulation
Tariff structure & Cerc tariff regulation
Sushant Kumar Sinha
 
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNADay-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
IPPAI
 
Grid code
Grid codeGrid code
Grid code
NAVEENGEHLOT5
 
Indian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorIndian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power Sector
Vijay Menghani
 
CERC Regulation 2022.pptx
CERC  Regulation 2022.pptxCERC  Regulation 2022.pptx
CERC Regulation 2022.pptx
ssuser847b13
 
OPEN ACCESS REGULATION
OPEN ACCESS REGULATIONOPEN ACCESS REGULATION
OPEN ACCESS REGULATION
Leela Krishna Vegi
 
Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
SHOBHIT NARAIN PANDEY
 
Indian electricity market and power exchanges
Indian electricity market and power exchangesIndian electricity market and power exchanges
Indian electricity market and power exchanges
Nageswar Rao
 
Ancillary Services
Ancillary ServicesAncillary Services
Ancillary Services
IPPAI
 
Abt meter
Abt meterAbt meter
Abt meter
Jay Ranvir
 
Open access ppt
Open access pptOpen access ppt
Open access ppt
Vinay Yaduka
 
Multi year tariffs and regulations
Multi year tariffs and regulationsMulti year tariffs and regulations
Multi year tariffs and regulations
Navajyoti Martha
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
Power System Operation
 
Atc calculation methods by shridhar kulkarni
Atc calculation methods by shridhar kulkarniAtc calculation methods by shridhar kulkarni
Atc calculation methods by shridhar kulkarni
Shridhar kulkarni
 
IEGC.pptx
IEGC.pptxIEGC.pptx
Tidal Energy
Tidal EnergyTidal Energy
Tidal Energy
Maharshi Pandya
 
Energy efficient motors
Energy efficient motorsEnergy efficient motors
Energy efficient motors
Jagadeesh Madhura
 
Indian Electricity Grid Code
Indian Electricity Grid CodeIndian Electricity Grid Code
Indian Electricity Grid Code
Power System Operation
 

What's hot (20)

From centralised long-term planning to market-based access: Proposed change i...
From centralised long-term planning to market-based access: Proposed change i...From centralised long-term planning to market-based access: Proposed change i...
From centralised long-term planning to market-based access: Proposed change i...
 
Availability based tariff
Availability based tariffAvailability based tariff
Availability based tariff
 
Tariff structure & Cerc tariff regulation
Tariff structure & Cerc tariff regulationTariff structure & Cerc tariff regulation
Tariff structure & Cerc tariff regulation
 
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNADay-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
 
Grid code
Grid codeGrid code
Grid code
 
Indian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorIndian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power Sector
 
CERC Regulation 2022.pptx
CERC  Regulation 2022.pptxCERC  Regulation 2022.pptx
CERC Regulation 2022.pptx
 
OPEN ACCESS REGULATION
OPEN ACCESS REGULATIONOPEN ACCESS REGULATION
OPEN ACCESS REGULATION
 
Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
 
Indian electricity market and power exchanges
Indian electricity market and power exchangesIndian electricity market and power exchanges
Indian electricity market and power exchanges
 
Ancillary Services
Ancillary ServicesAncillary Services
Ancillary Services
 
Abt meter
Abt meterAbt meter
Abt meter
 
Open access ppt
Open access pptOpen access ppt
Open access ppt
 
Multi year tariffs and regulations
Multi year tariffs and regulationsMulti year tariffs and regulations
Multi year tariffs and regulations
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
 
Atc calculation methods by shridhar kulkarni
Atc calculation methods by shridhar kulkarniAtc calculation methods by shridhar kulkarni
Atc calculation methods by shridhar kulkarni
 
IEGC.pptx
IEGC.pptxIEGC.pptx
IEGC.pptx
 
Tidal Energy
Tidal EnergyTidal Energy
Tidal Energy
 
Energy efficient motors
Energy efficient motorsEnergy efficient motors
Energy efficient motors
 
Indian Electricity Grid Code
Indian Electricity Grid CodeIndian Electricity Grid Code
Indian Electricity Grid Code
 

Viewers also liked

Power tariffs-2014-15
Power tariffs-2014-15Power tariffs-2014-15
Power tariffs-2014-15
iData Insights
 
Dr Devesh Singh- PPT
Dr Devesh Singh- PPTDr Devesh Singh- PPT
Dr Devesh Singh- PPT
mcci175
 
Hr reqrutment renewble energy
Hr reqrutment renewble energyHr reqrutment renewble energy
Hr reqrutment renewble energy
gauravsoni2003
 
paper presentation_national
paper presentation_nationalpaper presentation_national
paper presentation_national
vishal laddha
 
An Analysis of the Challenges of the 2020 Renewable Energy Targets
An Analysis of the Challenges of the 2020 Renewable Energy TargetsAn Analysis of the Challenges of the 2020 Renewable Energy Targets
An Analysis of the Challenges of the 2020 Renewable Energy Targets
Gordon Best
 
The Development of the Renewable Energy Market in Latin America and the Carib...
The Development of the Renewable Energy Market in Latin America and the Carib...The Development of the Renewable Energy Market in Latin America and the Carib...
The Development of the Renewable Energy Market in Latin America and the Carib...
Worldwatch Institute
 
Regulation of Marine Renewables in the US: A 15 Minute Encapsulation
Regulation of Marine Renewables in the US: A 15 Minute EncapsulationRegulation of Marine Renewables in the US: A 15 Minute Encapsulation
Regulation of Marine Renewables in the US: A 15 Minute Encapsulation
guest0c28de
 
Issues and challenges with renewable energy in oman
Issues and challenges with renewable energy in omanIssues and challenges with renewable energy in oman
Issues and challenges with renewable energy in oman
eSAT Journals
 
MREA Energy Fair 2015 - Midwest Solar Market Potential
MREA Energy Fair 2015 - Midwest Solar Market PotentialMREA Energy Fair 2015 - Midwest Solar Market Potential
MREA Energy Fair 2015 - Midwest Solar Market Potential
CUSP | Univ of Guelph
 
ARGENTINA - Renewable Energy Regulation and Market Status 2016/17
ARGENTINA - Renewable Energy Regulation and Market Status 2016/17ARGENTINA - Renewable Energy Regulation and Market Status 2016/17
ARGENTINA - Renewable Energy Regulation and Market Status 2016/17
Mauro G. Soares
 
Argentina Solar PV Status and Market Outlook
Argentina Solar PV Status and Market OutlookArgentina Solar PV Status and Market Outlook
Argentina Solar PV Status and Market Outlook
Mauro G. Soares
 
Tarif based comp_bidding
Tarif based comp_biddingTarif based comp_bidding
Tarif based comp_bidding
Great Lakes IEMR,Gurgaon
 
U.S. Renewable Energy Market And Growth
U.S. Renewable Energy Market And GrowthU.S. Renewable Energy Market And Growth
U.S. Renewable Energy Market And Growth
BrookeHeaton
 
Bridge to-india the-india-solar-handbook-june-2014-edition
Bridge to-india the-india-solar-handbook-june-2014-editionBridge to-india the-india-solar-handbook-june-2014-edition
Bridge to-india the-india-solar-handbook-june-2014-edition
Sanman Rajput
 
Tariff and Duty of Electricity supply in various State of India-A review by CEA
Tariff and Duty of Electricity supply in various State of India-A review by CEATariff and Duty of Electricity supply in various State of India-A review by CEA
Tariff and Duty of Electricity supply in various State of India-A review by CEA
Ashish Verma
 
Electricity Trading in India
Electricity Trading in IndiaElectricity Trading in India
Electricity Trading in India
Nitin Virmani
 
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
Harish Sharma
 

Viewers also liked (18)

How Electricity Tariff is determined ?
How Electricity Tariff is determined ?How Electricity Tariff is determined ?
How Electricity Tariff is determined ?
 
Power tariffs-2014-15
Power tariffs-2014-15Power tariffs-2014-15
Power tariffs-2014-15
 
Dr Devesh Singh- PPT
Dr Devesh Singh- PPTDr Devesh Singh- PPT
Dr Devesh Singh- PPT
 
Hr reqrutment renewble energy
Hr reqrutment renewble energyHr reqrutment renewble energy
Hr reqrutment renewble energy
 
paper presentation_national
paper presentation_nationalpaper presentation_national
paper presentation_national
 
An Analysis of the Challenges of the 2020 Renewable Energy Targets
An Analysis of the Challenges of the 2020 Renewable Energy TargetsAn Analysis of the Challenges of the 2020 Renewable Energy Targets
An Analysis of the Challenges of the 2020 Renewable Energy Targets
 
The Development of the Renewable Energy Market in Latin America and the Carib...
The Development of the Renewable Energy Market in Latin America and the Carib...The Development of the Renewable Energy Market in Latin America and the Carib...
The Development of the Renewable Energy Market in Latin America and the Carib...
 
Regulation of Marine Renewables in the US: A 15 Minute Encapsulation
Regulation of Marine Renewables in the US: A 15 Minute EncapsulationRegulation of Marine Renewables in the US: A 15 Minute Encapsulation
Regulation of Marine Renewables in the US: A 15 Minute Encapsulation
 
Issues and challenges with renewable energy in oman
Issues and challenges with renewable energy in omanIssues and challenges with renewable energy in oman
Issues and challenges with renewable energy in oman
 
MREA Energy Fair 2015 - Midwest Solar Market Potential
MREA Energy Fair 2015 - Midwest Solar Market PotentialMREA Energy Fair 2015 - Midwest Solar Market Potential
MREA Energy Fair 2015 - Midwest Solar Market Potential
 
ARGENTINA - Renewable Energy Regulation and Market Status 2016/17
ARGENTINA - Renewable Energy Regulation and Market Status 2016/17ARGENTINA - Renewable Energy Regulation and Market Status 2016/17
ARGENTINA - Renewable Energy Regulation and Market Status 2016/17
 
Argentina Solar PV Status and Market Outlook
Argentina Solar PV Status and Market OutlookArgentina Solar PV Status and Market Outlook
Argentina Solar PV Status and Market Outlook
 
Tarif based comp_bidding
Tarif based comp_biddingTarif based comp_bidding
Tarif based comp_bidding
 
U.S. Renewable Energy Market And Growth
U.S. Renewable Energy Market And GrowthU.S. Renewable Energy Market And Growth
U.S. Renewable Energy Market And Growth
 
Bridge to-india the-india-solar-handbook-june-2014-edition
Bridge to-india the-india-solar-handbook-june-2014-editionBridge to-india the-india-solar-handbook-june-2014-edition
Bridge to-india the-india-solar-handbook-june-2014-edition
 
Tariff and Duty of Electricity supply in various State of India-A review by CEA
Tariff and Duty of Electricity supply in various State of India-A review by CEATariff and Duty of Electricity supply in various State of India-A review by CEA
Tariff and Duty of Electricity supply in various State of India-A review by CEA
 
Electricity Trading in India
Electricity Trading in IndiaElectricity Trading in India
Electricity Trading in India
 
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
 

Similar to Deviation settelment mechanism

Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India)
Gensol Engineering Limited
 
Commercial presentation
Commercial presentationCommercial presentation
Commercial presentation
Anil Redemption
 
Wind Force Newsletter May, Edition, 2012
Wind Force Newsletter   May, Edition, 2012Wind Force Newsletter   May, Edition, 2012
Wind Force Newsletter May, Edition, 2012
rupeshsingh_1
 
Deviation Settlement Mechanism for Improving Grid Frequency Regime in India.pptx
Deviation Settlement Mechanism for Improving Grid Frequency Regime in India.pptxDeviation Settlement Mechanism for Improving Grid Frequency Regime in India.pptx
Deviation Settlement Mechanism for Improving Grid Frequency Regime in India.pptx
SUBRATAMUKHOPADHYAY9
 
Electricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptxElectricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptx
msounak95
 
1.3 comportamiento de las cargas.
1.3 comportamiento de las cargas.1.3 comportamiento de las cargas.
1.3 comportamiento de las cargas.
Abraham Robles Gonzalez
 
Electricity Tariff (1).pptx
Electricity Tariff (1).pptxElectricity Tariff (1).pptx
Electricity Tariff (1).pptx
suman943324
 
What is availability tariff
What is availability tariffWhat is availability tariff
What is availability tariff
Jay Ranvir
 
Distribution open access Maharashtra
Distribution open access  MaharashtraDistribution open access  Maharashtra
Distribution open access Maharashtra
Jay Ranvir
 
Open access charges chhattisgarh
Open access charges chhattisgarhOpen access charges chhattisgarh
Open access charges chhattisgarh
Jay Ranvir
 
A STAND A
A STAND AA STAND A
A STAND A
Mahesh Maramraju
 
Amendment to grid code
Amendment to grid codeAmendment to grid code
Amendment to grid code
Nitish Singh
 
Cerc
CercCerc
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
electricitygovernance
 
CHAP 3.4 - TARIFF.pdf
CHAP 3.4 - TARIFF.pdfCHAP 3.4 - TARIFF.pdf
CHAP 3.4 - TARIFF.pdf
rajabuneshaanwardin
 
Wind Force Newsletter September, Edition, 2012
Wind Force Newsletter   September, Edition, 2012Wind Force Newsletter   September, Edition, 2012
Wind Force Newsletter September, Edition, 2012
rupeshsingh_1
 
Draft MERC Net Metering for Solar Rooftop Regulations,2015
Draft MERC Net Metering for Solar Rooftop Regulations,2015Draft MERC Net Metering for Solar Rooftop Regulations,2015
Draft MERC Net Metering for Solar Rooftop Regulations,2015
Headway Solar
 
CEA Regulations.pptx
CEA Regulations.pptxCEA Regulations.pptx
CEA Regulations.pptx
CSVenkateswaranCASEs
 
Punjab SERC (Forecasting, Scheduling, Deviation Settlement and Related Matte...
 Punjab SERC (Forecasting, Scheduling, Deviation Settlement and Related Matte... Punjab SERC (Forecasting, Scheduling, Deviation Settlement and Related Matte...
Punjab SERC (Forecasting, Scheduling, Deviation Settlement and Related Matte...
Das A. K.
 
Implementation of ac induction motor control using constant vhz principle and...
Implementation of ac induction motor control using constant vhz principle and...Implementation of ac induction motor control using constant vhz principle and...
Implementation of ac induction motor control using constant vhz principle and...
eSAT Journals
 

Similar to Deviation settelment mechanism (20)

Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India)
 
Commercial presentation
Commercial presentationCommercial presentation
Commercial presentation
 
Wind Force Newsletter May, Edition, 2012
Wind Force Newsletter   May, Edition, 2012Wind Force Newsletter   May, Edition, 2012
Wind Force Newsletter May, Edition, 2012
 
Deviation Settlement Mechanism for Improving Grid Frequency Regime in India.pptx
Deviation Settlement Mechanism for Improving Grid Frequency Regime in India.pptxDeviation Settlement Mechanism for Improving Grid Frequency Regime in India.pptx
Deviation Settlement Mechanism for Improving Grid Frequency Regime in India.pptx
 
Electricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptxElectricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptx
 
1.3 comportamiento de las cargas.
1.3 comportamiento de las cargas.1.3 comportamiento de las cargas.
1.3 comportamiento de las cargas.
 
Electricity Tariff (1).pptx
Electricity Tariff (1).pptxElectricity Tariff (1).pptx
Electricity Tariff (1).pptx
 
What is availability tariff
What is availability tariffWhat is availability tariff
What is availability tariff
 
Distribution open access Maharashtra
Distribution open access  MaharashtraDistribution open access  Maharashtra
Distribution open access Maharashtra
 
Open access charges chhattisgarh
Open access charges chhattisgarhOpen access charges chhattisgarh
Open access charges chhattisgarh
 
A STAND A
A STAND AA STAND A
A STAND A
 
Amendment to grid code
Amendment to grid codeAmendment to grid code
Amendment to grid code
 
Cerc
CercCerc
Cerc
 
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
 
CHAP 3.4 - TARIFF.pdf
CHAP 3.4 - TARIFF.pdfCHAP 3.4 - TARIFF.pdf
CHAP 3.4 - TARIFF.pdf
 
Wind Force Newsletter September, Edition, 2012
Wind Force Newsletter   September, Edition, 2012Wind Force Newsletter   September, Edition, 2012
Wind Force Newsletter September, Edition, 2012
 
Draft MERC Net Metering for Solar Rooftop Regulations,2015
Draft MERC Net Metering for Solar Rooftop Regulations,2015Draft MERC Net Metering for Solar Rooftop Regulations,2015
Draft MERC Net Metering for Solar Rooftop Regulations,2015
 
CEA Regulations.pptx
CEA Regulations.pptxCEA Regulations.pptx
CEA Regulations.pptx
 
Punjab SERC (Forecasting, Scheduling, Deviation Settlement and Related Matte...
 Punjab SERC (Forecasting, Scheduling, Deviation Settlement and Related Matte... Punjab SERC (Forecasting, Scheduling, Deviation Settlement and Related Matte...
Punjab SERC (Forecasting, Scheduling, Deviation Settlement and Related Matte...
 
Implementation of ac induction motor control using constant vhz principle and...
Implementation of ac induction motor control using constant vhz principle and...Implementation of ac induction motor control using constant vhz principle and...
Implementation of ac induction motor control using constant vhz principle and...
 

Recently uploaded

Monthly Management report for the Month of May 2024
Monthly Management report for the Month of May 2024Monthly Management report for the Month of May 2024
Monthly Management report for the Month of May 2024
facilitymanager11
 
在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样
在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样
在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样
v7oacc3l
 
DSSML24_tspann_CodelessGenerativeAIPipelines
DSSML24_tspann_CodelessGenerativeAIPipelinesDSSML24_tspann_CodelessGenerativeAIPipelines
DSSML24_tspann_CodelessGenerativeAIPipelines
Timothy Spann
 
一比一原版(CU毕业证)卡尔顿大学毕业证如何办理
一比一原版(CU毕业证)卡尔顿大学毕业证如何办理一比一原版(CU毕业证)卡尔顿大学毕业证如何办理
一比一原版(CU毕业证)卡尔顿大学毕业证如何办理
bmucuha
 
原版一比一弗林德斯大学毕业证(Flinders毕业证书)如何办理
原版一比一弗林德斯大学毕业证(Flinders毕业证书)如何办理原版一比一弗林德斯大学毕业证(Flinders毕业证书)如何办理
原版一比一弗林德斯大学毕业证(Flinders毕业证书)如何办理
a9qfiubqu
 
Intelligence supported media monitoring in veterinary medicine
Intelligence supported media monitoring in veterinary medicineIntelligence supported media monitoring in veterinary medicine
Intelligence supported media monitoring in veterinary medicine
AndrzejJarynowski
 
一比一原版(UCSF文凭证书)旧金山分校毕业证如何办理
一比一原版(UCSF文凭证书)旧金山分校毕业证如何办理一比一原版(UCSF文凭证书)旧金山分校毕业证如何办理
一比一原版(UCSF文凭证书)旧金山分校毕业证如何办理
nuttdpt
 
一比一原版英属哥伦比亚大学毕业证(UBC毕业证书)学历如何办理
一比一原版英属哥伦比亚大学毕业证(UBC毕业证书)学历如何办理一比一原版英属哥伦比亚大学毕业证(UBC毕业证书)学历如何办理
一比一原版英属哥伦比亚大学毕业证(UBC毕业证书)学历如何办理
z6osjkqvd
 
writing report business partner b1+ .pdf
writing report business partner b1+ .pdfwriting report business partner b1+ .pdf
writing report business partner b1+ .pdf
VyNguyen709676
 
University of New South Wales degree offer diploma Transcript
University of New South Wales degree offer diploma TranscriptUniversity of New South Wales degree offer diploma Transcript
University of New South Wales degree offer diploma Transcript
soxrziqu
 
06-12-2024-BudapestDataForum-BuildingReal-timePipelineswithFLaNK AIM
06-12-2024-BudapestDataForum-BuildingReal-timePipelineswithFLaNK AIM06-12-2024-BudapestDataForum-BuildingReal-timePipelineswithFLaNK AIM
06-12-2024-BudapestDataForum-BuildingReal-timePipelineswithFLaNK AIM
Timothy Spann
 
一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
bmucuha
 
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
hyfjgavov
 
ViewShift: Hassle-free Dynamic Policy Enforcement for Every Data Lake
ViewShift: Hassle-free Dynamic Policy Enforcement for Every Data LakeViewShift: Hassle-free Dynamic Policy Enforcement for Every Data Lake
ViewShift: Hassle-free Dynamic Policy Enforcement for Every Data Lake
Walaa Eldin Moustafa
 
The Ipsos - AI - Monitor 2024 Report.pdf
The  Ipsos - AI - Monitor 2024 Report.pdfThe  Ipsos - AI - Monitor 2024 Report.pdf
The Ipsos - AI - Monitor 2024 Report.pdf
Social Samosa
 
一比一原版(GWU,GW文凭证书)乔治·华盛顿大学毕业证如何办理
一比一原版(GWU,GW文凭证书)乔治·华盛顿大学毕业证如何办理一比一原版(GWU,GW文凭证书)乔治·华盛顿大学毕业证如何办理
一比一原版(GWU,GW文凭证书)乔治·华盛顿大学毕业证如何办理
bopyb
 
End-to-end pipeline agility - Berlin Buzzwords 2024
End-to-end pipeline agility - Berlin Buzzwords 2024End-to-end pipeline agility - Berlin Buzzwords 2024
End-to-end pipeline agility - Berlin Buzzwords 2024
Lars Albertsson
 
一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
aqzctr7x
 
A presentation that explain the Power BI Licensing
A presentation that explain the Power BI LicensingA presentation that explain the Power BI Licensing
A presentation that explain the Power BI Licensing
AlessioFois2
 
一比一原版(harvard毕业证书)哈佛大学毕业证如何办理
一比一原版(harvard毕业证书)哈佛大学毕业证如何办理一比一原版(harvard毕业证书)哈佛大学毕业证如何办理
一比一原版(harvard毕业证书)哈佛大学毕业证如何办理
taqyea
 

Recently uploaded (20)

Monthly Management report for the Month of May 2024
Monthly Management report for the Month of May 2024Monthly Management report for the Month of May 2024
Monthly Management report for the Month of May 2024
 
在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样
在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样
在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样
 
DSSML24_tspann_CodelessGenerativeAIPipelines
DSSML24_tspann_CodelessGenerativeAIPipelinesDSSML24_tspann_CodelessGenerativeAIPipelines
DSSML24_tspann_CodelessGenerativeAIPipelines
 
一比一原版(CU毕业证)卡尔顿大学毕业证如何办理
一比一原版(CU毕业证)卡尔顿大学毕业证如何办理一比一原版(CU毕业证)卡尔顿大学毕业证如何办理
一比一原版(CU毕业证)卡尔顿大学毕业证如何办理
 
原版一比一弗林德斯大学毕业证(Flinders毕业证书)如何办理
原版一比一弗林德斯大学毕业证(Flinders毕业证书)如何办理原版一比一弗林德斯大学毕业证(Flinders毕业证书)如何办理
原版一比一弗林德斯大学毕业证(Flinders毕业证书)如何办理
 
Intelligence supported media monitoring in veterinary medicine
Intelligence supported media monitoring in veterinary medicineIntelligence supported media monitoring in veterinary medicine
Intelligence supported media monitoring in veterinary medicine
 
一比一原版(UCSF文凭证书)旧金山分校毕业证如何办理
一比一原版(UCSF文凭证书)旧金山分校毕业证如何办理一比一原版(UCSF文凭证书)旧金山分校毕业证如何办理
一比一原版(UCSF文凭证书)旧金山分校毕业证如何办理
 
一比一原版英属哥伦比亚大学毕业证(UBC毕业证书)学历如何办理
一比一原版英属哥伦比亚大学毕业证(UBC毕业证书)学历如何办理一比一原版英属哥伦比亚大学毕业证(UBC毕业证书)学历如何办理
一比一原版英属哥伦比亚大学毕业证(UBC毕业证书)学历如何办理
 
writing report business partner b1+ .pdf
writing report business partner b1+ .pdfwriting report business partner b1+ .pdf
writing report business partner b1+ .pdf
 
University of New South Wales degree offer diploma Transcript
University of New South Wales degree offer diploma TranscriptUniversity of New South Wales degree offer diploma Transcript
University of New South Wales degree offer diploma Transcript
 
06-12-2024-BudapestDataForum-BuildingReal-timePipelineswithFLaNK AIM
06-12-2024-BudapestDataForum-BuildingReal-timePipelineswithFLaNK AIM06-12-2024-BudapestDataForum-BuildingReal-timePipelineswithFLaNK AIM
06-12-2024-BudapestDataForum-BuildingReal-timePipelineswithFLaNK AIM
 
一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
 
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
 
ViewShift: Hassle-free Dynamic Policy Enforcement for Every Data Lake
ViewShift: Hassle-free Dynamic Policy Enforcement for Every Data LakeViewShift: Hassle-free Dynamic Policy Enforcement for Every Data Lake
ViewShift: Hassle-free Dynamic Policy Enforcement for Every Data Lake
 
The Ipsos - AI - Monitor 2024 Report.pdf
The  Ipsos - AI - Monitor 2024 Report.pdfThe  Ipsos - AI - Monitor 2024 Report.pdf
The Ipsos - AI - Monitor 2024 Report.pdf
 
一比一原版(GWU,GW文凭证书)乔治·华盛顿大学毕业证如何办理
一比一原版(GWU,GW文凭证书)乔治·华盛顿大学毕业证如何办理一比一原版(GWU,GW文凭证书)乔治·华盛顿大学毕业证如何办理
一比一原版(GWU,GW文凭证书)乔治·华盛顿大学毕业证如何办理
 
End-to-end pipeline agility - Berlin Buzzwords 2024
End-to-end pipeline agility - Berlin Buzzwords 2024End-to-end pipeline agility - Berlin Buzzwords 2024
End-to-end pipeline agility - Berlin Buzzwords 2024
 
一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
 
A presentation that explain the Power BI Licensing
A presentation that explain the Power BI LicensingA presentation that explain the Power BI Licensing
A presentation that explain the Power BI Licensing
 
一比一原版(harvard毕业证书)哈佛大学毕业证如何办理
一比一原版(harvard毕业证书)哈佛大学毕业证如何办理一比一原版(harvard毕业证书)哈佛大学毕业证如何办理
一比一原版(harvard毕业证书)哈佛大学毕业证如何办理
 

Deviation settelment mechanism

  • 1. Strengthening of Indian Grid Mohit Kathel indianpowerindutry.com Deviation Settlement Mechanism and Related Matters CERC Regulation 2014 CERC on 17.02.2014 has replaced the UI regulation 2009 with Deviation settlement mechanism regulation 2014 in order to strengthen the grid and improve grid stability. This step was taken to ensure that situations of grid failure like that of 30th & 31st July will not happen again. The grid failure has presented a case where some state were using the UI as a trading platform, during the grid failure states like Haryana, U.P were overdrawing heavily whereas states like Rajasthan & MP were under drawing from their schedule resulting in frequency varying in the specified range and at the same time making the grid unstable thus resulting in grid failure. With this regulation CERC has implemented volume limit for buyer and seller depending on their approved schedule, range of frequency has tighten, charges for the unscheduled interchange or deviation has increased to ensure a better demand predictability by states and to avoid UI as a trading platform. Deviation & Settlement Mechanism will definitely improve the grid discipline and will help the state to initiate forecasting of demand and schedule in more accurate and stringent manner. Various provisions made in the regulation such as volume limits, additional charges etc will force the state to procure power through bilateral route or on day ahead basis which surely help in fund flow and eventually improve the position of power sector. A summary of the deviation settlement mechanism and its comparison with the previous prevailing UI regulation is provided below. 1. Title & Commencement: Deviation settlement mechanism & related matters regulation 2014, came into force on 17.02.2014. 2. Reference Regulation: a. Grant of connectivity, LTOA & MTOA in interstate transmission regulation 2009. b. Interface Meters (Installation & operation of meters) regulation 2006. c. Open Access in interstate transmission regulation 2008. 3. Objective of the regulation is to enhance grid discipline & grid security. 4. Applicable on Inter-state transmission of electricity. 5. Charges receivable for under drawl by buyer and over injection by seller, while charges are payable for over drawl by buyer and under injection by seller. 6. Provisions made in regulation: a. Redefined frequency range and rates. b. Volume limits and deviation limits for generator and buyer c. Cap Rate applicable d. Charges & Additional Charges e. Methodology for calculation of deviation charges. 7. Charges and conditions applicable: a. Charges for each step increment of frequency for each 0.01 Hz step is now equivalent to increment of 35.60 Paise/unit in the frequency range of 50.05-50.00 Hz & 20.84 Paise/unit in frequency range between 50.00Hz to not below 49.70 Hz, resulting in charges at 50.05Hz @ 0.00 Paise/unit, at 50.04Hz @ 35.60 till 50.00 Hz @ 178 Paise/unit and then from 49.99Hz onwards charges will increase at a rate of 20.84 till 49.7Hz @ 824.04 Paise/unit. In UI regulation 2009 charges for each step of frequency for each 0.02 Hz was equivalent to 16.50 Paise/Unit from 50.20Hz till 50.02Hz, i.e charges were at 50.20Hz @ 0.00 Paise/unit & at 50.02 @ 148.50 Paise/Unit, and then from 50.00Hz
  • 2. Strengthening of Indian Grid Mohit Kathel indianpowerindutry.com onwards each step increment was equivalent to Rs. 28.12 Paise/Unit i.e. charges at 50.00Hz @ 165.00 Paise/Kwh till 49.5Hz @ 900.00 Paise/Unit. b. Cap Rates are redefined in the present regulation, now the cap rate for generating stations using fuel which comes under APM is reduced to 303.04 Paise/Kwh from 421.50 paise/Kwh for higher or lower injection than the scheduled generation. Also, now there is no cap rate on generating stations which are regulated by consumer and are using Gas as fuel under APM. c. Charges for over injection by seller and under drawl by buyer in excess of 12% of schedule or 150 MW whichever is less shall be 0. Earlier over injection upto 120% of schedule is allowed on the corresponding frequency rate and in excess of 120% there was a cap rate of 450.00 Paise/Unit, although it was subject to 105% of declared capacity of plant in a time block and 101% of capacity of plant in a day. d. Earlier if the injection of plant increases beyond 105% of its declared capacity in a time block or 101% of declared capacity in a day then charges for such injection will be charged at a rate of 165 Paise/unit. In the present regulation there are no such rules applicable on power plants. e. Clause for infirm injection before COD of generating unit is almost similar to that of UI regulation 2009, There is no volume drawl or injection limit on generating station although there is a cap rate on injection which is subject to the fuel used, for APM gas cap rate has increased from earlier charge of 2.60 Rs/Unit to 5.64 Rs/Unit. f. Volume Limits have been implemented in the present regulation, earlier there wasn’t any volume limits on the overall injection or drawl, although based upon different UI volume, charges corresponding to percentage of prevailing UI charges and Cap Rates were there. g. Earlier for over drawal when frequency is below 49.80Hz, additional charges were there. Now there are volume limits too which are 12% of schedule or 150 MW whichever is less. Also, now additional charges are levied based on the deviation from schedule and not upon the frequency range as was earlier. In the present regulation no under injection of electricity by a seller shall be permissible when grid frequency is "below 49.70 Hz" and no over injection of electricity by a seller shall be permissible when grid frequency is "50.10 Hz and above. However, additional charges shall be levied now depending on the deviation from schedule more than the allowed limits i.e. 12% or 150 MW whichever is less and also depends upon the frequency. Different charges are defined for the frequency range 49.70 Hz and above and below 49.70Hz of frequency. 1. When grid frequency is 49.70Hz and above a. When 12% is lesser or equal to 150 MW b. When 12% is more or equal to 150 MW 2. When grid frequency is below 49.7 Hz Each of the cases will apply for over drawal by a buyer and under injection by a seller when the actual drawl/injection is higher than the specified limits. For Over-Drawal by a buyer when frequency is 49.70 Hz or above When 12%<=150MW When 12% >= 150 MW Additional Charges a. 12%-15% 150MW to 200MW +20% charges of deviation charge corresponding to average grid frequency of the time block. b. 15%-20% 200 MW to 250 MW +40% charges of deviation charge
  • 3. Strengthening of Indian Grid Mohit Kathel indianpowerindutry.com corresponding to average grid frequency of the time block. c. 20% & Above 250 MW and above +100% charges of deviation charge corresponding to average grid frequency of the time block. For Under-Injection by a seller when frequency is 49.70 Hz or above When 12%<=150MW When 12% >= 150 MW Additional Charges a. 12%-15% 150MW to 200MW +20% charges of deviation charge corresponding to average grid frequency of the time block. b. 15%-20% 200 MW to 250 MW +40% charges of deviation charge corresponding to average grid frequency of the time block. c. 20% & Above 250 MW and above +100% charges of deviation charge corresponding to average grid frequency of the time block. For Under-Injection by a seller using fuel coal/gas/lignite under APM & when frequency is 49.70 Hz or above When 12%<=150MW When 12% >= 150 MW Additional Charges a. 12%-15% 150MW to 200MW +20% of 303.04 Paise/Unit or deviation charge corresponding to average grid frequency of the time block whichever is less. b. 15%-20% 200 MW to 250 MW +40% of 303.04 Paise/Unit or deviation charge corresponding to average grid frequency of the time block whichever is less. c. 20% & Above 250 MW and above +100% of 303.04 Paise/Unit or deviation charge corresponding to average grid frequency of the time block whichever is less. When grid the frequency is below 49.70Hz, additional charges are levied for over drawal by a buyer or under- injection by a seller and are equivalent to 100% of 824.04 Paise/unit i.e. 1648.08 Paise/unit for the deviation. Similarly for generating station using coal/gas/lignite additional charges are equivalent to 100% of the cap rate (303.04 paise/kwh). Provided: 1. Additional charge for deviation also be levied for over-injection or under-drawal when grid frequency is 50.10Hz or above at the rates equivalent to charges of deviation corresponding to the grid frequency of “below 50.01 Hz but not below 50.0 Hz” i.e. 178.00 Paise/unit. 2. No additional charges are levied on generating station prior to COD of unit. 3. These charges and regulation are subject to change depending upon the order, rules, amendments or regulation of CERC.