SlideShare a Scribd company logo
NET METERING REQUIREMENTS IN PUNJAB
FOR GRID INTERACTIVE ROOFTOP SOLAR
PV POWER PLANTS
EnvironmentFirst Energy Services Pvt.
Ltd.
ELIGIBILITY
All the consumers of the State Distribution licensee or PSPCL
who intend to encourage solar energy and set up solar PV plants
at available places on roof-tops of Individual households,
industries, Government or Semi-Government or Local Body
offices, commercial establishments, institutions, residential
complexes shall be eligible with project capacity ranging from
minimum 1 KWp upto 1MWp (AC side) with or without
battery back-up support. Consumers may generate solar
power for self consumption and may feed excess power into
the grid to be adjusted
NET METERING
( 1) The distribution licensee shall allow non- discriminatory net-
metering arrangement on first-cum-first serve basis for both
self-owned and third party owned rooftop PV systems as long
as the total capacity (in MW) does not exceed the target capacity
determined.
(2) The distribution licensee shall accept the solar PV power for 25
years as per the useful life of the SPV system.
INSTALLED CAPACITY
The maximum capacity of the Roof Top Solar PV system, as
mentioned on AC side at the output of inverter based on
rated inverter capacity, shall not be more than 80% of the
Sanctioned Connected Load or Contract Demand (in KVA
converted to KW at normative Power Factor of 0.90) of
the consumer and the minimum capacity shall not be less
than 1 KW. Eligible Consumers shall assess their rooftop solar
PV plant capacity based on the shadow less clear roof top
area or vacant spaces, SCL or CD, actual annual energy
consumption pattern and the capacity of Distribution transformer.
APPLICABILITY OF RENEWABLE
ENERGY CERTIFICATES AND
RPO
Net-metering injection is not eligible for REC. The quantum of
electricity consumed by an eligible consumer, who is not defined as
an obligated entity from the rooftop solar system under net-metering
arrangement shall qualify as deemed Renewable Purchase Obligation
(RPO) for the distribution licensee.
Energy Meter(s) Detail
12
Serial
No.
Meter Description Accuracy Load of
Consumer
Voltage
Level
1 Single Phase 10-60 A,
whole current
Class-I upto 7 KW Single Phase
LT 230 V
2 3 Phase 10-60 A,
whole current
Class-I More than 7KW
& up to 25 KW
Three Phase
LT 400 V
3 LT AC 3-Phase 4-
Wires CT operated
static DLMC
compliant energy
meter
Class- 0.5s
or better
More than 25 KW
& up to 100 KW
Three Phase
LT 400 V
4 HT TPT Meter, DLMS
Compliant & AMR
Compatible
Class- 0.5s
or better
More than 100
KW
Three Phase
HT (11 KV)
Harmonics Standard
As per the standard of IEEE 519, the permissible individual harmonics level shall be less
than 3% (for both voltage and current harmonics) and Total Harmonics Distortion (THD) for both
voltage and current harmonics of the system shall be less than 5%.
13
Inverter Standards
Inverter should comply with IEC 61683/IS 61683 for efficiency and Measurements and
should comply IEC 60068-2 (1,2,14,30) / Equivalent BIS Standard for environmental testing.
Inverter should supervise the grid condition continuously and in the event of grid failure
(or) under voltage (or) over voltage, Solar System should be disconnected by the circuit Breaker
/ Auto switch provided in the inverter.
14
Technical and interconnection requirements
15
Parameter Reference Requirement
Overall conditions
of service
State Distribution/Supply Code State Distribution/Supply
Code
Overall Grid
Standards
Central Electricity Authority (Grid
Standard) Regulations 2010
Central Electricity Authority
(Grid Standard) Regulations
2010
Equipment BIS / IEC / IEEE BIS / IEC / IEEE
Meters Central Electricity authority (Installation
& operation of
meters) Regulation 2006 as
amended time to time
Central Electricity authority
(Installation & operation of
meters) Regulation 2006 as
amended time to time
Safety and supply Central Electricity
Authority(measures of safety
and electricity supply)
Regulations, 2010
Central Electricity
Authority(measures of safety
and electricity supply)
Regulations, 2010
Harmonic
Requirements
Harmonic Current IEEE 519
CEA (Technical Standards for
Connectivity of the Distributed
Generation
Resources) Regulations 2013
IEEE 519
CEA (Technical Standards for
Connectivity of the Distributed
Generation
Resources) Regulations 2013
Synchronization IEEE 519
CEA (Technical Standards for
Connectivity of the Distributed
Generation Resources) Regulations
2013
Photovoltaic system must be
equipped with a grid frequency
synchronization device. Every time
the generating station is
synchronized to the electricity
system. It shall not cause voltage
fluctuation greater than +/- 5% at
point of connection.
Voltage IEEE 519
CEA (Technical Standards for
Connectivity of the Distributed
Generation Resources) Regulations
2013
The voltage-operating window
should minimize nuisance
tripping and should be under
operating range of 80% to 110%
of the nominal connected
voltage. Beyond a clearing time
of 2 second, the photovoltaic
system must isolate itself from
the grid.
Flicker IEEE 519
CEA (Technical Standards for
Connectivity of the Distributed
Generation Resources) Regulations
2013
Operation of Photovoltaic
system should not cause
voltage flicker in excess of
the limits stated in IEC 61000
standards or other
equivalent Indian standards, if
any.
Note: The standards/specifications shall be subject to amendments/revisions from time to time
as duly notified by PEDA on its website.
16
Frequency IEEE 519
CEA (Technical Standards for
Connectivity of the Distributed
Generation Resources) Regulations
2013
When the Distribution system
frequency deviates outside the
specified conditions (50.5 Hz
on upper side and 47.5 Hz on
lower side), There should be over
and under frequency trip
functions with a clearing time of 0.2
seconds.
DC injection IEEE 519
CEA (Technical Standards for
Connectivity of the Distributed
Generation Resources) Regulations
2013
Photovoltaic system should
not inject DC power more than
0.5% of full rated output
at the interconnection point or
1% of rated inverter output current
into distribution system under any
operating conditions.
Power Factor IEEE 519
CEA (Technical Standards for
Connectivity of the Distributed
Generation Resources) Regulations
2013
While the output of the inverter is
greater than 50%, a lagging power
factor of greater than 0.9 should
operate.
Islanding and
Disconnection
IEEE 519
CEA (Technical Standards for
Connectivity of the Distributed
Generation Resources) Regulations
2013
The photovoltaic system in the
event of fault, voltage or frequency
variations must island/disconnect
itself within IEC standard on
stipulated period.
Overload and
Overheat
IEEE 519
CEA (Technical Standards for
Connectivity of the Distributed
Generation Resources) Regulations
2013
The inverter should have the facility
to automatically switch off in case of
overload or overheating and
should restart when normal
conditions are restored.
Paralleling Device IEEE 519
CEA (Technical Standards for
Connectivity of the Distributed
Generation Resources) Regulations
2013
Paralleling device of photovoltaic
system shall be capable of
withstanding 220% of the normal
voltage at the interconnection point.
10 days
Timelines to set-up Grid Interactive Roof-Top Solar Photovoltaic Power Plants
Application submitted
to designated officer
of PSPCL
30 days maximum
180 days maximum from LOA
10 days
17
Site verification, installation,
sealing & initial reading of energy
meter(s) by PSPCL
Set-up the plant and submit work
completion report alongwith SLD
to PSPCL
Letter of Approval
(LOA) by PSPCL
Meter Configuration options
The metering system for rooftop solar system, under net-metering arrangement, shall
be as elaborated below which should be applicable till such time the Central Electricity
Authority notifies the standards in this matter.
a) Two Meter Configuration without Storage
The metering protocol for ‘Grid connected rooftop solar PV system without storage’ and
location of solar meter
schematic below:-
and consumer meter shall be in accordance with the
The utility meter (Net-meter) has to be bi-directional meter to register both import grid
electricity amount as well as export solar electricity amount.
18
b) Two Meter Configuration with Storage
The metering protocol for ‘Grid connected rooftop solar PV system with storage’ and location of
Solar Meter (SM) and Utility Meter (UM) shall be in accordance with the schematic below:-
The utility meter (Net-meter) has to be bi-directional meter to register both import grid electricity
amount as well as export solar electricity amount
.
19
• 405 A, Prakrati Corporate, Y N Road,
Indore (INDIA) 452001
• +91-731 2970493, 6007860
Registered
Office
• SCO 48, 2nd Floor, Opposite
P.O., Sector-8, Panchkula (INDIA)
134109
• +91-172-4014288
Chandigarh
Office:
• A1-1603, Runwal Garden City,
Balkum, Thane (W), Mumbai (INDIA)
– 400607
Mumbai
Office:
Email ID: info@environmentfirst.in

More Related Content

What's hot

Inspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code ComplianceInspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code Compliance
JLanka Technologies (Pvt) Limited
 
Renewable Energy Conversion
Renewable Energy ConversionRenewable Energy Conversion
Renewable Energy Conversion
rob_1v
 
Brian Patterson: Reinventing Building Power
Brian Patterson: Reinventing Building PowerBrian Patterson: Reinventing Building Power
Brian Patterson: Reinventing Building Power
EnergyTech2015
 
Pv solar plant components
Pv solar plant componentsPv solar plant components
Pv solar plant components
Jay Ranvir
 
Trusted Solar Panel Suppliers & Installation
Trusted Solar Panel Suppliers & InstallationTrusted Solar Panel Suppliers & Installation
Trusted Solar Panel Suppliers & Installation
anshparmar
 
Specification grid tie_spv_plant
Specification grid tie_spv_plantSpecification grid tie_spv_plant
Specification grid tie_spv_plant
Jay Ranvir
 
Younes Sina, Jonathan Rhyne ,Sabina Ude, Huidong Zang, Mary Waddle ,A report ...
Younes Sina, Jonathan Rhyne ,Sabina Ude, Huidong Zang, Mary Waddle ,A report ...Younes Sina, Jonathan Rhyne ,Sabina Ude, Huidong Zang, Mary Waddle ,A report ...
Younes Sina, Jonathan Rhyne ,Sabina Ude, Huidong Zang, Mary Waddle ,A report ...
Younes Sina
 
Session 06 balance of system components
Session 06   balance of system componentsSession 06   balance of system components
Session 06 balance of system components
Chirag Jain
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1Murugappa Group
 
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
Headway Solar
 
NABCEP Exam Prep Review for PV Installation & Tech Sales 
NABCEP Exam Prep Review for PV Installation & Tech Sales NABCEP Exam Prep Review for PV Installation & Tech Sales 
NABCEP Exam Prep Review for PV Installation & Tech Sales 
solpowerpeople
 
Session 07 site assessment & planning
Session 07   site assessment & planningSession 07   site assessment & planning
Session 07 site assessment & planning
Chirag Jain
 
Session 03 solar pv rooftop technology overview
Session 03   solar pv rooftop technology overviewSession 03   solar pv rooftop technology overview
Session 03 solar pv rooftop technology overview
Chirag Jain
 
IRJET- Power Quality Assessment of Photovoltaic System
IRJET- Power Quality Assessment of Photovoltaic SystemIRJET- Power Quality Assessment of Photovoltaic System
IRJET- Power Quality Assessment of Photovoltaic System
IRJET Journal
 
Maximum Energy Case Studies - EUPVSEC
Maximum Energy Case Studies - EUPVSECMaximum Energy Case Studies - EUPVSEC
Maximum Energy Case Studies - EUPVSEC
SolarEdge Technologies
 
SOLAR SOLUTIONS A STEP TOWARDS A GREENER FUTURE
SOLAR SOLUTIONS A STEP TOWARDS A GREENER FUTURESOLAR SOLUTIONS A STEP TOWARDS A GREENER FUTURE
SOLAR SOLUTIONS A STEP TOWARDS A GREENER FUTURE
urjarathi
 
Session 02 solar energy technologies
Session 02   solar energy technologiesSession 02   solar energy technologies
Session 02 solar energy technologies
Chirag Jain
 

What's hot (18)

Inspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code ComplianceInspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code Compliance
 
Renewable Energy Conversion
Renewable Energy ConversionRenewable Energy Conversion
Renewable Energy Conversion
 
Brian Patterson: Reinventing Building Power
Brian Patterson: Reinventing Building PowerBrian Patterson: Reinventing Building Power
Brian Patterson: Reinventing Building Power
 
Pv solar plant components
Pv solar plant componentsPv solar plant components
Pv solar plant components
 
Trusted Solar Panel Suppliers & Installation
Trusted Solar Panel Suppliers & InstallationTrusted Solar Panel Suppliers & Installation
Trusted Solar Panel Suppliers & Installation
 
Specification grid tie_spv_plant
Specification grid tie_spv_plantSpecification grid tie_spv_plant
Specification grid tie_spv_plant
 
Younes Sina, Jonathan Rhyne ,Sabina Ude, Huidong Zang, Mary Waddle ,A report ...
Younes Sina, Jonathan Rhyne ,Sabina Ude, Huidong Zang, Mary Waddle ,A report ...Younes Sina, Jonathan Rhyne ,Sabina Ude, Huidong Zang, Mary Waddle ,A report ...
Younes Sina, Jonathan Rhyne ,Sabina Ude, Huidong Zang, Mary Waddle ,A report ...
 
Session 06 balance of system components
Session 06   balance of system componentsSession 06   balance of system components
Session 06 balance of system components
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1
 
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
 
NABCEP Exam Prep Review for PV Installation & Tech Sales 
NABCEP Exam Prep Review for PV Installation & Tech Sales NABCEP Exam Prep Review for PV Installation & Tech Sales 
NABCEP Exam Prep Review for PV Installation & Tech Sales 
 
Session 07 site assessment & planning
Session 07   site assessment & planningSession 07   site assessment & planning
Session 07 site assessment & planning
 
Session 03 solar pv rooftop technology overview
Session 03   solar pv rooftop technology overviewSession 03   solar pv rooftop technology overview
Session 03 solar pv rooftop technology overview
 
IRJET- Power Quality Assessment of Photovoltaic System
IRJET- Power Quality Assessment of Photovoltaic SystemIRJET- Power Quality Assessment of Photovoltaic System
IRJET- Power Quality Assessment of Photovoltaic System
 
Maximum Energy Case Studies - EUPVSEC
Maximum Energy Case Studies - EUPVSECMaximum Energy Case Studies - EUPVSEC
Maximum Energy Case Studies - EUPVSEC
 
Products & services (new)
Products & services (new)Products & services (new)
Products & services (new)
 
SOLAR SOLUTIONS A STEP TOWARDS A GREENER FUTURE
SOLAR SOLUTIONS A STEP TOWARDS A GREENER FUTURESOLAR SOLUTIONS A STEP TOWARDS A GREENER FUTURE
SOLAR SOLUTIONS A STEP TOWARDS A GREENER FUTURE
 
Session 02 solar energy technologies
Session 02   solar energy technologiesSession 02   solar energy technologies
Session 02 solar energy technologies
 

Similar to Net metering requirements in punjab for grid interactive rooftop SPV Power Plant

Power Plant Controller-Putting the Power back into the hands of the Developer
Power Plant Controller-Putting the Power back into the hands of the DeveloperPower Plant Controller-Putting the Power back into the hands of the Developer
Power Plant Controller-Putting the Power back into the hands of the Developer
SgurrEnergy Pvt. Ltd.
 
CEA Regulations.pptx
CEA Regulations.pptxCEA Regulations.pptx
CEA Regulations.pptx
CSVenkateswaranCASEs
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
UdayMujumdar
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
SheelKapar1
 
Grid Connected Photovoltaic System with Energy Management Scheme
Grid Connected Photovoltaic System with Energy Management SchemeGrid Connected Photovoltaic System with Energy Management Scheme
Grid Connected Photovoltaic System with Energy Management Scheme
IRJET Journal
 
IRJET- High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET-  	  High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...IRJET-  	  High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET- High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET Journal
 
Session 10 grid interconnections & commissioning test procedures
Session 10   grid interconnections & commissioning test proceduresSession 10   grid interconnections & commissioning test procedures
Session 10 grid interconnections & commissioning test procedures
Chirag Jain
 
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
theijes
 
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion SystemIRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET Journal
 
IRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdfIRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdf
PowerSystemDynamicsS
 
IRJET- Solar H8 Inverter to Reduce Leakage Currents in Grid Connected Applic...
IRJET-	 Solar H8 Inverter to Reduce Leakage Currents in Grid Connected Applic...IRJET-	 Solar H8 Inverter to Reduce Leakage Currents in Grid Connected Applic...
IRJET- Solar H8 Inverter to Reduce Leakage Currents in Grid Connected Applic...
IRJET Journal
 
A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...
A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...
A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...
IRJET Journal
 
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET Journal
 
IRJET - Power Quality Improvement using Statcom in PV Grid Connected System
IRJET - Power Quality Improvement using Statcom in PV Grid Connected SystemIRJET - Power Quality Improvement using Statcom in PV Grid Connected System
IRJET - Power Quality Improvement using Statcom in PV Grid Connected System
IRJET Journal
 
Requerimientos ERCOT para Recursos Renovables.pdf
Requerimientos ERCOT para Recursos Renovables.pdfRequerimientos ERCOT para Recursos Renovables.pdf
Requerimientos ERCOT para Recursos Renovables.pdf
ssuserf19e47
 
IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...
IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...
IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...
IRJET Journal
 
IRJET- Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...
IRJET-  	  Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...IRJET-  	  Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...
IRJET- Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...
IRJET Journal
 
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET Journal
 
IRJET- Grid Integrated Single Phase PV with Shunt Active Filter based Control...
IRJET- Grid Integrated Single Phase PV with Shunt Active Filter based Control...IRJET- Grid Integrated Single Phase PV with Shunt Active Filter based Control...
IRJET- Grid Integrated Single Phase PV with Shunt Active Filter based Control...
IRJET Journal
 
Voltage Stability & Power Quality Assessment of Distributed Generation Based ...
Voltage Stability & Power Quality Assessment of Distributed Generation Based ...Voltage Stability & Power Quality Assessment of Distributed Generation Based ...
Voltage Stability & Power Quality Assessment of Distributed Generation Based ...
ijsrd.com
 

Similar to Net metering requirements in punjab for grid interactive rooftop SPV Power Plant (20)

Power Plant Controller-Putting the Power back into the hands of the Developer
Power Plant Controller-Putting the Power back into the hands of the DeveloperPower Plant Controller-Putting the Power back into the hands of the Developer
Power Plant Controller-Putting the Power back into the hands of the Developer
 
CEA Regulations.pptx
CEA Regulations.pptxCEA Regulations.pptx
CEA Regulations.pptx
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
 
Grid Connected Photovoltaic System with Energy Management Scheme
Grid Connected Photovoltaic System with Energy Management SchemeGrid Connected Photovoltaic System with Energy Management Scheme
Grid Connected Photovoltaic System with Energy Management Scheme
 
IRJET- High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET-  	  High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...IRJET-  	  High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET- High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
 
Session 10 grid interconnections & commissioning test procedures
Session 10   grid interconnections & commissioning test proceduresSession 10   grid interconnections & commissioning test procedures
Session 10 grid interconnections & commissioning test procedures
 
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
 
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion SystemIRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
 
IRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdfIRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdf
 
IRJET- Solar H8 Inverter to Reduce Leakage Currents in Grid Connected Applic...
IRJET-	 Solar H8 Inverter to Reduce Leakage Currents in Grid Connected Applic...IRJET-	 Solar H8 Inverter to Reduce Leakage Currents in Grid Connected Applic...
IRJET- Solar H8 Inverter to Reduce Leakage Currents in Grid Connected Applic...
 
A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...
A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...
A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...
 
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
 
IRJET - Power Quality Improvement using Statcom in PV Grid Connected System
IRJET - Power Quality Improvement using Statcom in PV Grid Connected SystemIRJET - Power Quality Improvement using Statcom in PV Grid Connected System
IRJET - Power Quality Improvement using Statcom in PV Grid Connected System
 
Requerimientos ERCOT para Recursos Renovables.pdf
Requerimientos ERCOT para Recursos Renovables.pdfRequerimientos ERCOT para Recursos Renovables.pdf
Requerimientos ERCOT para Recursos Renovables.pdf
 
IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...
IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...
IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...
 
IRJET- Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...
IRJET-  	  Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...IRJET-  	  Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...
IRJET- Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...
 
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
 
IRJET- Grid Integrated Single Phase PV with Shunt Active Filter based Control...
IRJET- Grid Integrated Single Phase PV with Shunt Active Filter based Control...IRJET- Grid Integrated Single Phase PV with Shunt Active Filter based Control...
IRJET- Grid Integrated Single Phase PV with Shunt Active Filter based Control...
 
Voltage Stability & Power Quality Assessment of Distributed Generation Based ...
Voltage Stability & Power Quality Assessment of Distributed Generation Based ...Voltage Stability & Power Quality Assessment of Distributed Generation Based ...
Voltage Stability & Power Quality Assessment of Distributed Generation Based ...
 

More from Harish Sharma

MNRE recomendations to States for the Solar Street Lighting Systems
MNRE recomendations to States for the Solar Street Lighting SystemsMNRE recomendations to States for the Solar Street Lighting Systems
MNRE recomendations to States for the Solar Street Lighting Systems
Harish Sharma
 
MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...
Harish Sharma
 
MNRE Guidelines for off-grid and grid connected Solar DC System
MNRE Guidelines for off-grid and grid connected Solar DC SystemMNRE Guidelines for off-grid and grid connected Solar DC System
MNRE Guidelines for off-grid and grid connected Solar DC System
Harish Sharma
 
Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in India
Harish Sharma
 
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVRfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
Harish Sharma
 
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
Harish Sharma
 
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIRfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
Harish Sharma
 
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHRfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
Harish Sharma
 
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Harish Sharma
 
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
Harish Sharma
 
PPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of KarnatakaPPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of Karnataka
Harish Sharma
 
RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...
Harish Sharma
 
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
Harish Sharma
 
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKARfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
Harish Sharma
 
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Harish Sharma
 
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Harish Sharma
 
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabScheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Harish Sharma
 
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
Harish Sharma
 
Water Benefit Standard (WBS)
Water Benefit Standard (WBS) Water Benefit Standard (WBS)
Water Benefit Standard (WBS)
Harish Sharma
 
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Harish Sharma
 

More from Harish Sharma (20)

MNRE recomendations to States for the Solar Street Lighting Systems
MNRE recomendations to States for the Solar Street Lighting SystemsMNRE recomendations to States for the Solar Street Lighting Systems
MNRE recomendations to States for the Solar Street Lighting Systems
 
MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...
 
MNRE Guidelines for off-grid and grid connected Solar DC System
MNRE Guidelines for off-grid and grid connected Solar DC SystemMNRE Guidelines for off-grid and grid connected Solar DC System
MNRE Guidelines for off-grid and grid connected Solar DC System
 
Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in India
 
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVRfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
 
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
 
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIRfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
 
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHRfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
 
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
 
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
 
PPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of KarnatakaPPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of Karnataka
 
RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...
 
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
 
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKARfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
 
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
 
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
 
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabScheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
 
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
 
Water Benefit Standard (WBS)
Water Benefit Standard (WBS) Water Benefit Standard (WBS)
Water Benefit Standard (WBS)
 
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
 

Recently uploaded

Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Recently uploaded (20)

Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 

Net metering requirements in punjab for grid interactive rooftop SPV Power Plant

  • 1. NET METERING REQUIREMENTS IN PUNJAB FOR GRID INTERACTIVE ROOFTOP SOLAR PV POWER PLANTS EnvironmentFirst Energy Services Pvt. Ltd.
  • 2. ELIGIBILITY All the consumers of the State Distribution licensee or PSPCL who intend to encourage solar energy and set up solar PV plants at available places on roof-tops of Individual households, industries, Government or Semi-Government or Local Body offices, commercial establishments, institutions, residential complexes shall be eligible with project capacity ranging from minimum 1 KWp upto 1MWp (AC side) with or without battery back-up support. Consumers may generate solar power for self consumption and may feed excess power into the grid to be adjusted
  • 3. NET METERING ( 1) The distribution licensee shall allow non- discriminatory net- metering arrangement on first-cum-first serve basis for both self-owned and third party owned rooftop PV systems as long as the total capacity (in MW) does not exceed the target capacity determined. (2) The distribution licensee shall accept the solar PV power for 25 years as per the useful life of the SPV system.
  • 4. INSTALLED CAPACITY The maximum capacity of the Roof Top Solar PV system, as mentioned on AC side at the output of inverter based on rated inverter capacity, shall not be more than 80% of the Sanctioned Connected Load or Contract Demand (in KVA converted to KW at normative Power Factor of 0.90) of the consumer and the minimum capacity shall not be less than 1 KW. Eligible Consumers shall assess their rooftop solar PV plant capacity based on the shadow less clear roof top area or vacant spaces, SCL or CD, actual annual energy consumption pattern and the capacity of Distribution transformer.
  • 5. APPLICABILITY OF RENEWABLE ENERGY CERTIFICATES AND RPO Net-metering injection is not eligible for REC. The quantum of electricity consumed by an eligible consumer, who is not defined as an obligated entity from the rooftop solar system under net-metering arrangement shall qualify as deemed Renewable Purchase Obligation (RPO) for the distribution licensee.
  • 6. Energy Meter(s) Detail 12 Serial No. Meter Description Accuracy Load of Consumer Voltage Level 1 Single Phase 10-60 A, whole current Class-I upto 7 KW Single Phase LT 230 V 2 3 Phase 10-60 A, whole current Class-I More than 7KW & up to 25 KW Three Phase LT 400 V 3 LT AC 3-Phase 4- Wires CT operated static DLMC compliant energy meter Class- 0.5s or better More than 25 KW & up to 100 KW Three Phase LT 400 V 4 HT TPT Meter, DLMS Compliant & AMR Compatible Class- 0.5s or better More than 100 KW Three Phase HT (11 KV)
  • 7. Harmonics Standard As per the standard of IEEE 519, the permissible individual harmonics level shall be less than 3% (for both voltage and current harmonics) and Total Harmonics Distortion (THD) for both voltage and current harmonics of the system shall be less than 5%. 13
  • 8. Inverter Standards Inverter should comply with IEC 61683/IS 61683 for efficiency and Measurements and should comply IEC 60068-2 (1,2,14,30) / Equivalent BIS Standard for environmental testing. Inverter should supervise the grid condition continuously and in the event of grid failure (or) under voltage (or) over voltage, Solar System should be disconnected by the circuit Breaker / Auto switch provided in the inverter. 14
  • 9. Technical and interconnection requirements 15 Parameter Reference Requirement Overall conditions of service State Distribution/Supply Code State Distribution/Supply Code Overall Grid Standards Central Electricity Authority (Grid Standard) Regulations 2010 Central Electricity Authority (Grid Standard) Regulations 2010 Equipment BIS / IEC / IEEE BIS / IEC / IEEE Meters Central Electricity authority (Installation & operation of meters) Regulation 2006 as amended time to time Central Electricity authority (Installation & operation of meters) Regulation 2006 as amended time to time Safety and supply Central Electricity Authority(measures of safety and electricity supply) Regulations, 2010 Central Electricity Authority(measures of safety and electricity supply) Regulations, 2010 Harmonic Requirements Harmonic Current IEEE 519 CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013 IEEE 519 CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013 Synchronization IEEE 519 CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013 Photovoltaic system must be equipped with a grid frequency synchronization device. Every time the generating station is synchronized to the electricity system. It shall not cause voltage fluctuation greater than +/- 5% at point of connection. Voltage IEEE 519 CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013 The voltage-operating window should minimize nuisance tripping and should be under operating range of 80% to 110% of the nominal connected voltage. Beyond a clearing time of 2 second, the photovoltaic system must isolate itself from the grid. Flicker IEEE 519 CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013 Operation of Photovoltaic system should not cause voltage flicker in excess of the limits stated in IEC 61000 standards or other equivalent Indian standards, if any.
  • 10. Note: The standards/specifications shall be subject to amendments/revisions from time to time as duly notified by PEDA on its website. 16 Frequency IEEE 519 CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013 When the Distribution system frequency deviates outside the specified conditions (50.5 Hz on upper side and 47.5 Hz on lower side), There should be over and under frequency trip functions with a clearing time of 0.2 seconds. DC injection IEEE 519 CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013 Photovoltaic system should not inject DC power more than 0.5% of full rated output at the interconnection point or 1% of rated inverter output current into distribution system under any operating conditions. Power Factor IEEE 519 CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013 While the output of the inverter is greater than 50%, a lagging power factor of greater than 0.9 should operate. Islanding and Disconnection IEEE 519 CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013 The photovoltaic system in the event of fault, voltage or frequency variations must island/disconnect itself within IEC standard on stipulated period. Overload and Overheat IEEE 519 CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013 The inverter should have the facility to automatically switch off in case of overload or overheating and should restart when normal conditions are restored. Paralleling Device IEEE 519 CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013 Paralleling device of photovoltaic system shall be capable of withstanding 220% of the normal voltage at the interconnection point.
  • 11. 10 days Timelines to set-up Grid Interactive Roof-Top Solar Photovoltaic Power Plants Application submitted to designated officer of PSPCL 30 days maximum 180 days maximum from LOA 10 days 17 Site verification, installation, sealing & initial reading of energy meter(s) by PSPCL Set-up the plant and submit work completion report alongwith SLD to PSPCL Letter of Approval (LOA) by PSPCL
  • 12. Meter Configuration options The metering system for rooftop solar system, under net-metering arrangement, shall be as elaborated below which should be applicable till such time the Central Electricity Authority notifies the standards in this matter. a) Two Meter Configuration without Storage The metering protocol for ‘Grid connected rooftop solar PV system without storage’ and location of solar meter schematic below:- and consumer meter shall be in accordance with the The utility meter (Net-meter) has to be bi-directional meter to register both import grid electricity amount as well as export solar electricity amount. 18
  • 13. b) Two Meter Configuration with Storage The metering protocol for ‘Grid connected rooftop solar PV system with storage’ and location of Solar Meter (SM) and Utility Meter (UM) shall be in accordance with the schematic below:- The utility meter (Net-meter) has to be bi-directional meter to register both import grid electricity amount as well as export solar electricity amount . 19
  • 14. • 405 A, Prakrati Corporate, Y N Road, Indore (INDIA) 452001 • +91-731 2970493, 6007860 Registered Office • SCO 48, 2nd Floor, Opposite P.O., Sector-8, Panchkula (INDIA) 134109 • +91-172-4014288 Chandigarh Office: • A1-1603, Runwal Garden City, Balkum, Thane (W), Mumbai (INDIA) – 400607 Mumbai Office: Email ID: info@environmentfirst.in