SlideShare a Scribd company logo
Fire risk analysis of structures and
infrastructures: theory and
application in highway tunnels
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO, AA: 2015-’16
1November 10 2015www.francobontempi.org
Konstantinos Gkoumas, PhD, PE
Facoltà di Ingegneria
Sapienza Università di Roma
Corso di Progettazione Strutturale Antincendio
Docente: Prof. Ing. Franco Bontempi
Outline
• System approach to fire safety design
• Risk/fire risk/risk analysis
• Risk assessment process
• Risk analysis
• Hazard analysis
• Risk acceptance
• Risk reduction
• Risk assessment of road tunnels using PIARC/OECD QRAM
• Case study: risk assessment of a long highway tunnel
• References
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
2
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
3
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
• System approach to fire safety design
• Risk
- fire risk
- risk types
- risk analysis
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
4
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
System approach to fire safety design
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
MINOR
SPREAD
FIRE SPREADSTOP FIRE
suppression
Y
MAJOR
SPREAD
STRUCTURAL
INTEGRITY
AVOID
CASUALITIES
LOCALISED
DAMAGE
STRUCTURAL
FAILURES
N
mitigation
Y
N
fire safe design
Y
N
FIRE
robust design
Y
N
MAJOR
COLLAPSE
AVOID
DIRECT
DAMAGE
AVOID
COLLAPSE
1
2
3
4
0 preventionOBJECTIVE
fire safety design -
structural
fire safety design -
non structural
GLOBAL
SAFETY
LOSS OF
GLOBAL
SAFETY
AVOID
INDIRECT
DAMAGE
NY
The fire safety is framed in different
“safety levels”, corresponding to
different safety objectives.
5
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
(Fire) Risk Estimation*
*(following SFPE Handbook of Fire Protection Engineering)
Provide answer to the following questions
1. What could happen?
2. How bad would it be if it did happen?
3. How likely is it to happen
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
6
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
What is risk?
Risk can be defined as the probability that the harm or damage from a particular
hazard is realized.
Risk is measured in terms of consequences and likelihood (a qualitative description
of probability or frequency). In mathematical terms risk can be defined as:
risk = f (frequency or probability, consequence) (1)
In the case of an activity with only one event with potential consequences, a risk (R)
is the probability (P) that this event will occur multiplied with the consequences (C)
given the event occurs:
R = PC (2)
The risk of a system is the sum of the risks of all harmful events of that system:
(3)
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
𝑅𝑆 = 𝑅𝑖
𝑛
𝑖=1
7
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
Risk types
• Life safety risks are normally presented in two ways:
- Individual risk and
- Societal risk
• Individual risk:
The purpose of the individual risk is to ensure that individuals in the society
are not exposed to unacceptably high risks. It can be defined as the risk to any
occupant on the scene for the event/hazard scenario i.e. it is the risk to an
individual and not to a group of people.
• Societal risk:
Societal risk is not looking at one individual but is concerned with the risk of
multiple fatalities. People are treated as a group, there are no considerations
taken to the individuals within the group i.e. the definition of the risk is from a
societal point of view.
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Source: Jönsson, 2007
8
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
What is risk analysis?
• A big family of different approaches, methods
and complex models combining various
methododical components for specific tasks
• Systematic analysis of sequences and interaction
effects in potential accidents, thereby identifying
weak points in the system and recognizing
possible improvement measures
• Risk analysis makes the quantification of risks
feasible
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
9
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
The risk assessment process
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
10
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
The risk assessment process
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Start
Definition of the system
Hazard identification
Probability analysis Consequence analysis
Additional safety
measures
Risk estimation
Risk evaluation Risk criteria
Acceptable
risk?
Stop
Risk analysis
Risk evaluation
YES
NO
Risk reduction
11
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
Definition of the system (context establishment)
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Define the operational environment and the context of the risk assessment
process
– Definition of the scope or the risk assessment process
• This includes determining the timeframe (e.g. from planning to dismantling), the
required resources and the depth of analysis required.
– Definition of the strategic and organizational context
• The nature of the organization in charge of the risk management and the
environment in which it operates is established
– Identification of the stakeholders (portatori di interesse) and objectives
• The relationships that are interdependent with the organization are defined, the
impacts that might occur are accounted for, as well as and what each is wanting
out of the relationship
– Determination of the evaluation criteria
• Decide what level of risk the organization is prepared to accept
12
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
Hazard identification
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Hazard identification
a. What can happen
b. How can it happen
Means for hazard identification:
• Decomposition of the system into a number of
components and/or subsystems
• Identification of possible states of failure for the
considered system and sub-systems
• Identification of how the hazards might be realized
for the considered system and subsystems
Source: Faber, 2008
13
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Hazard identification – system decomposition
A. Structure
1. Main components
(d) Foundations
(c) Towers
(b) Anchor systems
(a) Main cables
(h) Cable saddle
(e) Railway girder
(f) Highway girders
(g) Expansion joints
(e) Non str.elements
(a) Steel
(b) Concrete
(c) Prestressed c.
(d) Alluminium/iron
3. Materials
(f) Coating
4. Systems
(a) Electrical
(c) Hydraulics
(b) Mechanical
(e) Bitumen
(e) Plastic
2. Secondary comp.
(d) H.R. attachments
(c) TMD
(b) Buffers
(a) Hanger ropes
B. Users
1. Highway traffic
(b) Commercial
(a) Private
2. Railway traffic
(b) Commercial
(a) Private
(a) Heavy
(b) Hazard mat.
(c) Military
3. Exceptional traffic
C. Facilities
1. Over the bridge
(b) Railway
(a) Highway
2. By the bridge
(a) Highway
(b) Railway
(c) Toll booths
(d) Control center
(e) Parking
(a) Maritime traffic
3. Under the bridge
D. Dependencies
1. Power
3. Financial
2. Communications
4. Supplies
5. Emerg. Responce
(a) First aid
(b) Police
(c) Fire brigade
(d) Hospitals
6. Ext. Contractors
E. Linkage
1. Economy
3. Military
2. Social
F. Operation
1. Authorities
(b) Management
2. Aspects
(a) Bridge authorities
(b) Goverment
(c) Region
5. Personnel
(c) Maintenance
(a) Financial
(b) Other
(a) Technical
G. Technology
(a) GPS
(b) Accelerometers
(c) Strain gauges
(e) Thermometers
(g) CCTV
(f) WIM
(d) Seismographs
(h) Field equipment
1. Monitoring
2. Control
(a) Cable control
(d) Railway traffic
(c) Highway traffic
(b) TMD
3. Data transmission
(b) Wireless
(a) Cable
4. Computer center
(b) Software
(a) Hardware
(d) Internet/LAN
(c) Data bases
4. Regulations
3. Policies
4. Location
(c) External
HierarchicalHolographicModels(HHM)
(DefinedinHaimes,1981)
14
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
Risk analysis: hazard identification
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
• Qualitative methods
Studies based on the generic experience of personnel and do not
involve mathematical estimations.
• Quantitative methods
Mathematical estimations that rely upon historical evidence or
estimates of failures to predict the occurrence of an event.
• Semi-quantitative methods
Combination of the above (mostly, qualitative methods with
applied numerical values).
Source: Nolan, D. P. Handbook of Fire and Explosion Protection
Engineering Principles for Oil, Gas, Chemical, and Related Facilities, 1986
15
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Source: Aven, T. Risk Analysis: Assessing Uncertainties beyond Expected Values and Probabilities.
John Wiley & Sons, 2008
Risk analysis: hazard identification
16
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
Hazard identification. Qualitative Methods
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Checklist or Worksheet
A standardized listing which identifies common protection features required for typical
facilities is compared against the facility design and operation. Risks are expressed by
the omission of safety systems or system features.
Preliminary Hazard Analysis (PHA)
Each hazard is identified with potential causes and effects. Recommendations or known
protective measures are listed.
What-If analysis
A safety study which by which “What-If’ investigative questions (brainstorming
approach) are asked by an experienced team of a hydrocarbon system or components
under examination. Risks are normally expressed in a qualitative numerical series (e.g., 1
to 5).
HAZOP - HAZard and OPerability analysis (analisi di pericolo e operabilità)
A formal systematic critical safety study where deviations of design intent of each
component are formulated and analyzed from a standardized list. Risks are typically
expressed in a qualitative numerical series (e.g., 1 to 5) relative to one another.
Source: Nolan, D.P. 1986. Handbook of Fire and Explosion Protection Engineering Principles for …. Noyes, New Jersey
17
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
Hazard identification. Qualitative Methods
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Event Trees (ET) –albero degli eventi
A mathematical logic model that mathematically and graphically
portrays the combination of events and circumstances in an
accident sequence, expressed in an annual estimation.
Fault Trees (FT) – alberi dei guasti
A mathematical logic model that mathematically and graphically
portrays the combination of failures that can lead to a specific main
failure or accident of interest, expressed in an annual estimation.
Failure Modes and Effects Analysis (FMEA)
A systematic, tabular method of evaluating the causes and effects
of known types of component failures, expressed in an annual
estimation.
Source: Nolan, D.P. 1986. Handbook of Fire and Explosion Protection Engineering Principles for …. Noyes, New Jersey
18
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
• Risk analysis
• Qualitative risk analysis
• Quantitative risk analysis
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
19
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Risk analysis
• Risk analysis
– Probability- as the likelihood of the risk occurrence
– Impact - consequences if the risk occurs
• risk proximity, meant as the point in time during which
a risk will impact
• Risk analysis - methods
– Qualitative Risk Analysis, in which numbers and
probabilities are used not extensively or at all
– Quantified Risk Analysis (QRA)
– Probabilistic Risk Analysis (PRA), in which the system risk
is represented as a probability distribution
20
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Risk analysis and system complexity
High-Probability/
Low-Consequences
(HPLC)
Low-Probability/
High-Consequences
(LPHC)
High-Probability/
Low-Consequences
(HPLC)
Low-Probability/
High-Consequences
(LPHC)
High-Probability/
Low-Consequences
(HPLC)
Low-Probability/
High-Consequences
(LPHC)
High-Probability/
Low-Consequences
(HPLC)
Stochastic
Complexity
Deterministic
Analysis
Methods
Qualitative
Risk
Analysis
Quantitative/Probabilistic
Risk
Analysis
Pragmatic
Risk
Scenarios
Stochastic
Complexity
Deterministic
Analysis
Methods
Qualitative
Risk
Analysis
Quantitative/Probabilistic
Risk
Analysis
Pragmatic
Risk
Scenarios
21
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Qualitative Risk analysis
• Qualitative Risk Analysis is the simplest method of risk analysis, and
generally is used during the preliminary analysis phases.
• It consists in using subjective assessments of risks, and consequently, in
ranking them in a subjective manner.
• Sources for information to be used in the analysis can be drown from
previous experiences, history of events and consultation of experts.
• The ranking of risks is qualitative, e.g. risk (1) > risk (2) > risk (3),
while a description can be added. Eventually, a likelihood-consequence
matrix can be constructed.
• The biggest drawback of QRA is that there is neither a clear indication
of the risk’s magnitude nor an absolute scale of how serious the risk
might be, so, for a comprehensive risk analysis of more complex
systems, quantitative methods should be preferred.
22
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Qualitative risk analysis methods: risk matrix
• A risk matrix typically provides a discrete partitioning of relative consequences
along one dimension and relative likelihood along the other.
• The entry in each matrix cell may include a description of hazards known or
believed to have that combination of consequence severity and likelihood.
Source: NFPA, SFPE Handbook of
Fire Protection Engineering,
3rd edition, 2002
Source: Furness, A., Muckett, M.
Introduction to Fire Safety
Management. Elsevier, 2007.
23
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Qualitative risk analysis methods: SWOT analysis
24
Strengths (forza): characteristics of
the business or project that give it
an advantage over others.
Weaknesses (debolezza):
characteristics that place the
business or project at a
disadvantage relative to others
Opportunities (opportunità):
elements that the project could
exploit to its advantage
Threats (minacce): elements in the
environment that could cause
trouble for the business or project
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Quantitative Risk analysis
• Quantified (or quantitative) Risk Analysis (QRA) combines
the consequences and frequencies of accident scenarios to
estimate the level of risk.
• In respect to the Qualitative method, QRA implicates the
acquaintance of probabilities that describe the likelihood of
the outcomes and their consequences.
• QRA started with the chemical industries from the 70s and
the offshore industry from the 80s.
• QRA is traditionally expressed through the decomposition
of the system. This frequently is done by the use of event
trees and fault trees.
25
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
FTA and ETA
• ETA (event tree analysis – albero degli eventi)
provides a structure for postulating an initiating
event and analyzing the potential outcomes
• FTA (fault tree analysis – albero dei guasti)
begins with a failure and provides a structure to
look for potential causes
26
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Event tree analysis
• Event trees pictorially represent the logical order in which
events in a system can occur. Event trees begin with an
initiating event, and then the consequences of the event are
followed through a series of possible paths.
• Each path is assigned a probability of occurrence. Therefore,
the probability of the various possible outcomes can be
calculated.
• Event tree analysis is based on binary logic, in which an
event has either happened or not, or a component has failed
or has not.
• It is valuable to analyze the consequences arising from a
failure or undesired event.
27
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Event tree analysis: illustration (1)
28
Event trees are helpful in
considering all the possible
outcomes (on the right-hand side)
from an initiating event (on the
left-hand side), which is usually
ignition for fire risks.
The frequency of the initiating
event can be estimated from fire
report data, and the conditional
probabilities of the sub-events can
be quantified from fire report data
or fault trees.
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Event tree analysis: illustration (2)
Source: Fire Risk in Metro Tunnels and Stations Hyder Consulting
29
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Fault tree analysis
30
Fault trees are helpful in
quantifying the
probability of a top
event of concern (such
as the failure of a fire
protection system) from
all the potential root
causes (at the bottom),
again quantified from fire
report data.
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Fault tree analysis
general conclusion (event)
• Fault trees look like a complement
to event trees.
• The idea is to begin with a general
conclusion (event) and, using a
top-down approach, to generate a
logic model that provides for both
qualitative and quantitative
evaluation of the system
reliability.
Source: google pictures search “Fault tree”
31
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Fault tree analysis - symbols
Basic event - failure or error in a system component or element
(example: switch stuck in open position)
Initiating event - an external event (example: bird strike to aircraft)
Undeveloped event - an event about which insufficient information is
available, or which is of no consequence
Conditioning event - conditions that restrict or affect logic gates
(example: mode of operation in effect)
Intermediate event: can be used immediately above a primary event to
provide more room to type the event description.
Source: Fault Tree Handbook. Nuclear Regulatory Commission. NUREG–0492
32
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Fault tree analysis – gate symbols
OR gate - the output occurs if any input occurs
AND gate - the output occurs only if all inputs occur (inputs are
independent)
Exclusive OR gate - the output occurs if exactly one input occurs
Priority AND gate - the output occurs if the inputs occur in a specific
sequence specified by a conditioning event
Inhibit gate - the output occurs if the input occurs under an enabling
condition specified by a conditioning event
Source: Fault Tree Handbook. Nuclear Regulatory Commission. NUREG–0492
33
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Advantages and disadvantages of FTA
• Disadvantages
1. There is a possibility of oversight and omission of significant failure
modes.
2. It is difficult to apply Boolean logic to describe failures of system
components that can be partially successful in operation and thereby
affect the operation of the system, e.g. leakage through a valve.
3. For the quantitative analysis there is usually a lack of pertinent failure
data. Even when there are data they may have been obtained from a
different environment.
• Advantages
1. It provides a systematic procedure for identifying faults that can exist
within a system.
2. It forces the analyst to understand the system thoroughly.
Source: Hasofer et al. 2007, Risk Analysis in Building Fire Safety Engineering
34
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Cause – consequence diagrams
• The combination of fault trees and event trees leads to the creation of
cause-consequence diagrams.
Time
Revealed from the
Monitoring system
S3
S2
S1
Consequences
Infraction of traffic law
Improper speed
Road condition
Vehicle flow
blocked
YES
YES
NO
NO
Other
Iniziative event
Road
Accident
35
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
SCENARIO PROBABILITY
A1 PA*P1
A2 PA*(1-P1) *P2 *P3
A3 PA*(1-P1) *P2*(1-P3 )
A4 PA*(1-P1) *(1-P2)*P3
A5 PA*(1-P1) *(1-P2)*(1-P3)
B1 PB*P1
B2 PB*(1-P1) *P2 *P3
B3 PB*(1-P1) *P2*(1-P3 )
B4 PB*(1-P1) *(1-P2)*P3
B5 PB*(1-P1) *(1-P2)*(1-P3)
C1 PC*P1
C2 PC*(1-P1) *P2 *P3
C3 PC*(1-P1) *P2*(1-P3 )
C4 PC*(1-P1) *(1-P2)*P3
C5 PC*(1-P1) *(1-P2)*(1-P3)
Triggering
event
Fire
ignition
1. Fire
extinguished
by personnel
2. Intrusion of
fire fighters
Arson
Explosion
Short
circuit
Cigarette
fire
YES (P1)
NO (1-P1) YES (P2)
NO (1-P2)
Scenario
Other
A1
A2
A3
A4
A5
3. Fire
suppression
YES (P3)
NO (1-P3)
YES (P3)
NO (1-P3)
Fire
location
AREA A
(PA)
YES (P1)
NO (1-P1) YES (P2)
NO (1-P2)
B1
B2
B3
B4
B5
YES (P3)
NO (1-P3)
YES (P3)
NO (1-P3)
AREA B
(PB)
YES (P1)
NO (1-P1) YES (P2)
NO (1-P2)
C1
C2
C3
C4
C5
YES (P3)
NO (1-P3)
YES (P3)
NO (1-P3)
AREA C
(PC)
Quantified Risk Analysis: cause – effect diagrams
36
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
F (frequency) – N (number of fatalities) curve
• An F–N curve is an alternative way of describing the
risk associated with loss of lives.
• An F–N curve shows the frequency (i.e. the expected
number) of accident events with at least N fatalities,
where the axes normally are Logarithmic.
• The F–N curve describes risk related to large-scale
accidents, and is thus especially suited for
characterizing societal risk.
Source: Aven, T. Risk Analysis: Assessing Uncertainties beyond Expected Values and Probabilities. John Wiley & Sons, 2008
37
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
F (frequency) – N (number of fatalities) curve
Source: Aven, T. Risk Analysis: Assessing Uncertainties beyond Expected Values and Probabilities. John Wiley & Sons, 2008
38
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
F (frequency) – N (number of fatalities) curve
Source: NFPA, SFPE Handbook of Fire Protection Engineering, 3rd edition, 2002
39
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
Index
• Risk acceptance
- ALARP
- Human life (!)
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
40
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Risk acceptance
Source: Persson, M. Quantitative Risk Analysis Procedure for the Fire Evacuation of a Road Tunnel -An Illustrative Example. Lund, 2002
41
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Risk acceptance – ALARP (1)
RISK MAGNITUDE
INTOLERABLE
REGION
As
Low
As
Reasonably
Practicable
BROADLY ACCEPTABLE
REGION
Risk cannot be justified
in any circumstances
Tolerable only if risk
reduction is impracticable
or if its cost is greatly
disproportionate to the
improvement gained
Tolerable if cost of
reduction would exceed
the improvements gained
Necessary to maintain
assurance that the risk
remains at this level
As
Low
As
Reasonably
Achievable
RISK MAGNITUDE
INTOLERABLE
REGION
As
Low
As
Reasonably
Practicable
BROADLY ACCEPTABLE
REGION
Risk cannot be justified
in any circumstances
Tolerable only if risk
reduction is impracticable
or if its cost is greatly
disproportionate to the
improvement gained
Tolerable if cost of
reduction would exceed
the improvements gained
Necessary to maintain
assurance that the risk
remains at this level
As
Low
As
Reasonably
Achievable
42
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Risk acceptance – ALARP (2)
Source: google pictures search “ALARP”
43
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Monetary values – cost of human life (!)
• What is the maximum amount the society (or the decision-maker) is willing
to pay to reduce the expected number of fatalities by 1?
• Typical numbers for the value of a statistical life used in cost-benefit analysis
are 1–10 million euros. The Ministry of Finance in Norway has arrived at a
value at approximately 2 million euros.
www.francobontempi.org
Guideline values for the cost to
avert a statistical life (euros), used
by an oil company
Source: Aven, T. Risk Analysis: Assessing
Uncertainties beyond Expected Values and
Probabilities. John Wiley & Sons, 2008
44
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
Risk reduction
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
45
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Risk reduction
Source: Brussaard et al. 2004. The Dutch Model for the Quantitative Risk Analysis of Road Tunnels.
46
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
Risk reduction (2) - monitoring and system response
Time
1
3
2
Accident Accident evolution
Pre-accident
situation
Pre-accident
Monitoring
Pre-accident
System Response
Accident
Localization
Evolution of System Response
Accident evolution Monitoring
System
Response
47
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
48
Parte 2a: Analisi del rischio di gallerie stradali
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
Source:
"Risk analysis for severe traffic accidents in road tunnels". “Laurea Magistrale”
(M.Sc.) Thesis at the Sapienza University of Rome, Faculty of Civil and Industrial
Engineering. Candidate: Carmine Di Santo. Final grade: 110/110 “Summa cum
Laude”. Advisor: Prof. Franco Bontempi, co-advisor: Konstantinos Gkoumas, PhD.
Defended in January 2015.
www.francobontempi.org 49
The issue of SAFETY in tunnels
Mont Blanc Tunnel Fire (1999)
39 Fatalities
Italia (Courmayer) – France (Chamonix)
single – bore, bidirectional tunnel
Length = 11.6 km
St. Gotthard Tunnel Fire (2001)
11 Fatalities
Switzerland (Göschenen) – Switzerland (Airolo)
single – bore, bidirectional tunnel
Length = 16,9 km
Frejus Tunnel Fire (2005)
2 Fatalities
Italia (Bardonecchia) – France (Modane)
single – bore, bidirectional tunnel
Length = 12,9 km
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 50
The issue of SAFETY in tunnels
Directive
2004/54/EC
Quantitative Risk
Analysis
Objectives
Parameters
Requirements
Transport of Dangerous Goods through road tunnels
OECD/PIARC/EU
Quantitative Risk Assessment Model
• OECD (Organisation of Economic Co-
operation and Development)
• PIARC (World Road Association)
• European Commission
• France (INERIS), Canada (WS Atkins),
UK (IRR)
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 51
PIARC/OECD QRAM OUTPUTS
𝑅 = 𝐹 ∙ 𝐶
F probability of occurrence / frequency
C extent of damage / consequences
• Fatalities
• Injured
• Destruction of buildings and structures
• Environmental Damage
PIARC/OECD
QRAM
Societal Risk
Individual Risk F[1/year]
N [Fat]
𝐸𝑉𝑠 =
𝑖=0
∞
𝐹 𝑁𝑖 ∙ 𝑁𝑖
The risk to which a group of people
is subjected in case a scenario s
occurs.
Prob. that a person (among local
population and within a certain
distance from the road) dies due to
the scenario s.
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 52
PIARC/OECD QRAM OUTPUTS
𝑅 = 𝐹 ∙ 𝐶
F probability of occurrence / frequency
C extent of damage / consequences
• Fatalities
• Injured
• Destruction of buildings and structures
• Environmental Damage
PIARC/OECD
QRAM
Societal Risk
F[1/year]
N [Fat]
𝐸𝑉𝑠 =
𝑖=0
∞
𝐹 𝑁𝑖 ∙ 𝑁𝑖
The risk to which a group of
people is subjected in case a
scenario s occurs.
SR = F(N) ∙ N
The F-N diagrams may be
applied to illustrate the risk
profile for a specific hazard
such as a fire in a road tunnel.
Expected amount of victims
in a certain time period
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 53
F-N curve construction process flow
1 – Dangerous Goods and
Accident Scenarios selection
2 – Effect j (due to the scenario s )
and its Range from the epicentre
Ej=f(d) Rj
3 – Mortality Rate within the range Rj
%LETHj
4 – Mortality Rate corrected
considering the possibility of escape
%LETHj=f(tevac)
5 – Scenario s Probability of
occurrence fs
6 – Number of victims due to the
scenario s
N= jNj=f(Rj, Dru, Ljam, %LETHj)
7 – F-N curve for the scenario s and
its relative Expected Value
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 54
Tunnel risk assessment procedure
Data Collection
Data Preparation
Risk Calculation
Using QRAM
Is Risk
acceptable?
NO
Additional risk
reduction
measures
YES
End
Mean Data:
• Traffic
• Accident Frequencies
• Tunnel Geometry
• Tunnel Equipment
• .....
Risk Acceptability:
• Absolute criteria
• Relative criteria
Risk
Analysis
Prevention Measures:
• Signs and road markings
• Lighting
• Traffic control
• Route geometry
• Prohibition of access to
certain types of vehicles
Protection Measures:
• Monitoring
• Fires/Accident Detection
system
• Ventilation system
• Emergency lighting
• Protection of escape routes
• System of emergency
management
• Emergency Procedures
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 55
Societal Risk Acceptability criteria
Absolute
Criteria
𝐸𝑉𝑠 ≤ 𝐸𝑉𝑙𝑖𝑚𝑖𝑡 (𝐸𝑉𝑠: Expected Value of Victims)
0,000001
0,00001
0,0001
0,001
0,01
0,1
1
1 10 100
F(N)[1/year]
N
Tollerable Risk Line Acceptable Risk Line
Not Acceptable area
ALARP
Acceptable area
As Low As Reasonably Practicable
ALARP area:
• prevention and/or
mitigation actions must be
taken to reduce the risk, as
far as reasonably
practicable
• Cost – Benefit Analysis
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 56
Societal Risk Acceptability criteria
Relative Criteria 𝐸𝑉𝑠 ≤ 𝐸𝑉𝑠,𝑟𝑒𝑓
1,00E-06
1,00E-05
1,00E-04
1,00E-03
1,00E-02
1,00E-01
1,00E+00
1,00 10,00 100,00 1000,00
Tunnel Tunnel Reference
Applying the same calculation method, compare the examined risk with:
• the risk of an alternative route
• that calculated for a reference tunnel, which must have characteristics similar to the one
examined, but with all the safety requirements required by the relevant regulations
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 57
Probit analysis
Is a type of regression used to analysing the relationsheep between a stimulus
(dose) and “all or nothing” (such as death) response
The following items must be identified:
• The toxicant
• The target
• The effect or response to be monitored
• The dose range
• The period of the test
Biological organisms respond differently
to the same dose of a toxicant.
Each individual is exposed to the same
dose and the response is recorded.
Curves are frequently represented by a
normal or Gaussian distribution
A Gaussian or normal distribution
representing the biological response to
exposure to a toxicant.
𝑓 𝑥 =
1
𝜎 2𝜋
𝑒
−
𝑥−𝜇 2
2𝜎2
probability (or fraction) of individuals
experiencing a specific response
x is the response, σ is the standard
deviation, and μ is the mean.
σ determines the shape and μ characterize the location of the curve with respect to the x axis
the percentage
of individuals
affected for a
specified
response interval
• The toxicological experiment is repeated for a number
of different doses, and normal curves are drawn.
• The standard deviation and mean response are
determined from the data for each dose.
FINNEY 1971
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 58
Probit analysis
A complete dose-response curve is produced
by plotting the cumulative mean response at
each dose.
The response is plotted versus the logarithm of the
dose, to provide a much straighter line in the
middle of the response curve
For comparison purposes the dose that results
in 50% lethality of the subjects is frequently
reported. This is called the LD50 dose
(lethal dose for 50% of the subjects).
For computational purposes the response
versus dose curve is not convenient.
For single exposures the probit method is
particularly suited, providing a straight-line
equivalent to the response-dose curve.
P or RATIO =
1
2𝜋
−∞
Pr−5
𝑒−
1
2
𝑢2
𝑑𝑢
provides a relationship between the
probability P and the probit variable Pr.
Many methods exist for representing the
response-dose curve.
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 59
Probit analysis
Transformation from Percentages to Probits
The probit relationship transforms the sigmoid shape of the normal response versus
dose curve into a straight line when plotted using a linear probit scale
The probit variable Pr is computed from
𝑃𝑟 = 𝑎 + 𝑏 ln 𝐷
P or RATIO =
1
2𝜋
−∞
Pr−5
𝑒−
1
2 𝑢2
𝑑𝑢
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 60
1) Dangerous goods and accident scenarios
Liquefied
Petroleum Gas
(LPG)
Motor Spirit
Acrolein
(Toxic Liquid)
Chlorine
(Toxic Gas)
Ammonia
(Toxic Gas)
Liquified CO2
Boiling Liquid Expanding
Vapor Explosion (BLEVE)
Toxic Release in the air
Torch Fire
Pool Fire
Vapor Cloud Explosion (VCE)
Vapor Cloud Explosion
BLEVE
No DGs 20MW Fire
100 MW Fire
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 61
0
20
40
60
80
100
120
140
0,00 10,00 20,00 30,00 40,00 50,00 60,00 70,00
qr[kW/m2]
d [m]
2) scenario physical effects
Thermal Effects Pressure Effects Toxicity Effects
• Fires
• VCEs
• BLEVEs
• VCEs
• BLEVEs
• Fires (smokes)
• Toxis Releases in
air
qr [kW/m2] = f(d)
Radiative Heat Flux
which is experienced
by the receiver per
unit area
Side-on Blast Overpressure
∆Ps [bar] = f(d)
Wave Positive-phase
t+[bar] = f(d)
Concentration
C [ppmv] = f(d)
Effect
Intensity
Distance from
the epicentre
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 62
3) Physiological effects
𝐹𝑖𝑛𝑛𝑒𝑦,1971
𝑅𝑎𝑡𝑖𝑜 = 𝑓(Pr) =
−∞
𝑃𝑟−5
𝑒
−
1
2
𝑢2
𝑑𝑢
𝑃𝑟𝑜𝑏𝑖𝑡 𝑇𝑟𝑎𝑛𝑠𝑓𝑜𝑟𝑚𝑎𝑡𝑖𝑜𝑛
𝑃𝑟𝑗 = 𝑎 + 𝑏 ln 𝐸𝑗 ∙ 𝑡 𝑒𝑥𝑝,𝑗
Thermal
Pressure
Toxicity
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 63
4) probability of occurrence of the scenarios
𝑓𝑠,𝑖 = 𝑃𝑠,𝑖 ∙ 𝑓𝑎𝑐𝑐,𝑖 ∙ 𝑇𝐻𝑖 ∙ 𝐿𝑖 ∙ 24 ∙ 365 ∙ 10−6
Frequency of occurrence of the scenario s on the section i in a year [scen/year]
Conditional probability
that scenario j occurs
once an accident
implying an HGV has
taken place on the
section i
Annual frequency of accidents involving HGVs on the section i
[acc/(MVkm*year)]
Traffic of HGVs passing through the section i in one hour
[veh/h]
𝑓𝑎𝑐𝑐,𝑖 =
𝐻𝐺𝑉𝑎𝑐𝑐,𝑖
𝑇𝐻𝑖 ∙ 𝐿𝑖
FaultTreeAnalysis
• HGV/h
• % DG-HGV
• DGs types
• Accidents/year
𝐏 = 𝐏𝟏. 𝟏 ∙ 𝐏𝟏. 𝟐 + 𝐏𝟐. 𝟏 ∙ 𝐏𝟐. 𝟐
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 64
5) Possibility of escape or of finding shelter
𝐷𝑖𝑗 =
𝑡 𝑖𝑛
𝑡 𝑜𝑢𝑡
𝐷𝑗 𝑡 𝑑𝑡
Dose of physical effect j
that affects a man
crossing the segment i
𝐷𝑗,𝑇𝑂𝑇 =
𝑖
𝐷𝑖𝑗
Total dose
received during
the escape
𝑃𝑟𝑗 = 𝑎 + 𝑏 ∙ ln 𝐸𝑗 ∙ 𝑡 𝑒𝑥𝑝,𝑗
𝐷𝑗,𝑇𝑂𝑇
𝑡 𝑒𝑣𝑎𝑐
𝑡 𝑝𝑟𝑒 𝑡 𝑚𝑜𝑣
Pre-movement
time
Movement
time
𝑣
𝑑 𝑠𝑎𝑓𝑒𝑡𝑦
𝑡 𝑝𝑟𝑒 = 𝑡 𝑝𝑟𝑒−𝑏𝑝𝑠 ∙ 𝑤 𝑒𝑓𝑓
𝑤 𝑒𝑓𝑓 =
5
𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑟𝑎𝑡𝑖𝑛𝑔 𝑜𝑓 𝑝𝑎𝑟𝑎𝑚𝑒𝑡𝑒𝑟𝑠
• Alertness (4)
• Mobility (4)
• Social Affiliation (3)
• Commitment (3)
• Familiarity (2)
• Distance from the accident (by calc)
• Perceived severity (4)
Occupant
Response Model
𝑡 𝑟𝑒𝑐 + 𝑡 𝑟𝑒𝑠
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 65
6) Societal risk indicators
Number of Victims
tsce Occurs the accident
scenario
tbarr Delay for stopping
approaching traffic
tjam min (tsce, tbarr).
N = 𝑅 ∙ 𝐷 𝑅𝑈𝐽 + 𝑅 − 𝐿𝑗𝑎𝑚 ∙ 𝐷 𝑅𝑈𝐹 ∙ %𝐿𝐸𝑇𝐻
Road Users Density in a Traffic Jam [users/m]
Road Users Density in a Fluid Traffic [users/m]
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 66
7) Societal risk indicators
F-N curve construction
Each scenario s may appear as different events Ei depending on:
 the section of the path being considered (section i)
 the accident location on the section
 the traffic direction (A, B)
 the reference period of the day (QUIET, NORMAL, PEAK)
 ....
Event Event Frequency Fatalities Cumulative Frequency
Ei fi Ni Fi
[-] [1/year] [Fat] [1/year]
E1 f1 N1 F1 = f1
E2 f2 N2 F2 = f1+f2
E3 f3 N3 F3 = f1+f2+f3
E4 f4 N4 F4 = f1+f2+f3+f4
... ... ... ...
En fn Nn Fn = f1+f2+f3+f4+...+fn
Scenario "s"
F[1/year] N [Fat]
𝐸𝑉𝑠 =
1
+∞
)𝐹(𝑁 𝑑𝑁
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 67
Parte 2b: Analisi del rischio della galleria St. Demetrio
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 68
Tunnel St. Demetrio
Motorway Catania – Syracuse
(European route E45)
ANAS s.p.a.
Construction:
2007-2009
Pizzarotti & C. S.p.A. Parma
Courtesy of Dr. Luigi Carrarini
(ANAS S.p.A.)
Courtesy of Ing. Alessandra Lo Cane
(M.I.T.)
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 69
Tunnel St. Demetrio
(Central Design Management ANAS S.p.A.)
Height from the Roadway to the Inner Wall 8.06 [m]
Road Platform Width 11.2 [m]
Cross Sectional Area 87.31 [m
2
]
Natural Tunnel
TWIN BORE TUNNEL,
ONE DIRECTION PER BORE
Polycentric Circular Section
Traditional Excavation
Bore in direction SOUTH (Syracuse)
portal of entry [km] 4+800
portal altitude above sea level [m] 10642
portal of exit [km] 7+695
portal altitude above sea level [m] 19242
Length [km] 2895
maximum longitudinal slope [%] 0.32
minimum longitudinal slope [%] 0.32
average longitudinal slope [%] 0.32
Bore in direction NORTH (Catania)
portal of entry [km] 7+698
portal altitude above sea level [m] 19273
portal of exit [km] 4+750
portal altitude above sea level [m] 10480
Length [km] 2949
maximum longitudinal slope [%] -0.32
minimum longitudinal slope [%] -0.32
average longitudinal slope [%] -0.32
Catania – Syracuse (E45), ANAS s.p.a.
2007-2009, Pizzarotti & C. S.p.A. Parma
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 70
Tunnel St. Demetrio: equipment & traffic data
• Pedestrian Bypass every 300m
• Bypass Carriageable every 900m
• Control Centre → Catania
• CCTV cameras placed every 282m
• CO sensors
• Smoke Meters (Opacimeters)
• Linear Thermal Sensors (heat sensing
cable)
• Variable Message Panels every 300m
• SOS stations every 200m
9 Jet Fan
10 Jet Fan 9 Jet Fan
9 Jet Fan
Equipment Emergency Ventilation System
Longitudinal Ventilation
average speed (on the cross section) of
3 m/s in the direction of traffic
time of fire detection (via thermo sensitive
cable) of 3 minutes from the ignition
a time of 5 minutes for the emergency
ventilation establishment
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 71
Tunnel St. Demetrio: equipment & traffic data
Traffic
QUIET NORMAL PEAK
AADT = 21190 veh/day
(1 direction)
22÷07
325 veh/h
HGV-ratio = 2%
vcar = 126.4 km/h
vHGV = 90.5 km/h
1050 veh/h
HGV-ratio = 10%
vcar = 126.4 km/h
vHGV = 90.5 km/h
1553 veh/h
HGV-ratio = 11.7%
vcar = 114.5 km/h
vHGV = 82 km/h
SOUTH NORTH
QUIET 1 1
NORMAL 7 3
PEAK 12 5
DG-HGV / h
63% Flammable Liquids (motor spirit, diesel oil, etc.)
31% LPG
6% Others
[acc /(MVkm*year)] [acc /(veh*km*year)]
SOUTH 0.161 0.000000161
NORTH 0.160 0.000000160
facc
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 72
21 - TUNNEL 3
2 3 - TUNNEL1
SOUTH (Syracuse)
NORTH (Catania)
x
Tunnel St. Demetrio: QRAM input data
Accident Scenarios
Tunnel
QRAM Model
Average number of people in a light vehicle [-] 2
Average number of people in a HGV [-] 1.1
Average number of people in a Bus/Coach [-] 40
Bus/Coaches ratio [-] 0.01
Delay for stopping approaching traffic [s] 9000
Area (Urban/Rural) [-] urban
Average density of population [hab/km2
] 0.01
DG transport correction factor [-] 1.00E+00
Traffic & Population Data
W (effective width) [m] 11
H (effective height) [m] 7.9
A (open cross sectional area) [m
2
] 86.9
Cam (camber) [%] 0
Gs (Segment gradient) [%] 0.32
VnN (volume flow rate along tunnel at nodes) [m3
/s] 0
VnE (volume flow rate along tunnel at nodes) [m3
/s] 261
Ad (open area of discrete drains) [m2
] 0.075
Xd (interval between drains) [m] 20
Xe (average spacing between emergency exits) [m] 300
Ecom (emergency coms) → 1, 2 o 3 [-] 3
Tunnel Data
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 73
Tunnel St. Demetrio: F-N curve in the south direction
1,00E-06
1,00E-05
1,00E-04
1,00E-03
1,00E-02
1,00E-01
1,00E+00
1,00 10,00 100,00 1000,00
FCUM[acc/year]
N [FAT]
Tollerable Risk Line
Acceptable Risk Line
EV [Fat/year] 1.68E-02
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 74
Tunnel St. Demetrio: QRAM Sensitivity analysis
input parameter Variation Initial Value Final Value Initial Value Final Value
0 0.01 0.00 0.01 0.00
equal to HGV ratio 0.01 0.02; 0.1; 0.117 0.01 0.02; 0.1; 0.117
0.15 - 0.15 0.30 ; 0.00 0.15 ; 0.15 0.30 ; 0.00 0.15 ; 0.15
0 - 0.30 0.30 ; 0.00 0.00 ; 0.30 0.30 ; 0.00 0.00 ; 0.30
1 2 1 2 1
1.5 2 1.5 2 1.5
2.5 2 2.5 2 2.5
3 2 3 2 3
1.5 1.1 1.5 1.1 1.5
2 1.1 2 1.1 2
3 1.1 3 1.1 3
x 10 1.61E-07 1.61E-06 1.60E-07 1.60E-06
x 10-1
1.61E-07 1.61E-08 1.60E-07 1.60E-08
x 10-1
1.00 0.10 1.00 0.10
x 10 1.00 10.00 1.00 10.00
2.5 0.00 2.50 0.00 2.50
4.12 0.00 4.12 0.00 4.12
1 3 1 3 1
2 3 2 3 2
A,B: 0 0.32 0.00 0.32 0.00
A,B: 3 0.32 3.00 0.32 3.00
A: -0.32 0.32 -0.32 - -
B: -0.32 - - 0.32 -0.32
A,B: -3 0.32 -3.00 0.32 -3.00
1 2 1 2 1
3 2 3 2 3
XI Type of Construction (1 Circular, 2 Rectangualar cross-section) 2 [-] 1 2 1 2
105 0.00 105.00 0.00 -105.00
210 0.00 210.00 0.00 -210.00
200 261.00 200.00 -261.00 -200.00
300 261.00 300.00 -261.00 -300.00
REVERSE 261.00 -261.00 -261.00 261.00
0 0.075 0.00 0.075 0.00
0.15 0.075 0.15 0.075 0.15
1 3 1 3 1
2 3 2 3 2
200 300.00 200.00 300.00 200.00
400 300.00 400.00 300.00 400.00
1 150 1 150 1
2 150 2 150 2
3 150 3 150 3
4 150 4 150 4
5 150 5 150 5
10 150 10 150 10
XVII
Safety
equipment
XII
XIII
XIV
XV
XVI
VII
VIII
IX
X
Changes to
the
structure
Frequency
of
Accidents
I
II
Bus Coaches Ratio (for each period: QUIET, NORMAL, PEAK)
Propane in Bulk ratio - Propane in Cylinder ratio
Average Number of People in a Light Vehicle
Average Number of People in a HGV
III
IV
TRAFFIC
V
VI
Average Spacing between Emergency Exits
Delay for Stopping Approaching Traffic
Accidents Frequency (facc)
DG-HGV transport correction factor
Camber (transversal slope)
Ground Type: 1 (Bedrock), 2 (Fragmented), 3 (Fragmented and
Under Water
Segments Gradient
Number of Lanes
[m3/s]
Normal Longitudinal Ventilation, Volume Flow Rate along tunnel (at
each node)
Emergency Longitudinal Ventilation, Volume Flow Rate along tunnel
(at each node)
Open Area of discrete Drains
Emergency Coms: 1 (bell/siren), 2 (Public Address system)
[min]
[-]
[-]
[m2
]
[m3
/s]
Societal Risk A - SOUTH Syr B - NORTH Cat
[-]
[%]
[-]
[%]
[-]
[-]
[acc/(veh*
km*year)]
[pass]
[pass]
[-]
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 75
1,00E-03
1,00E-02
1,00E-01
initialcurve
Busratio=0
BusCoachesRatio=HGVRatio
LPGinBulk=LPGinCylinder=0.15
LPGinCylinder=0.30
PeopleinaLightVehicle=1
PeopleinaLightVehicle=1.5
PeopleinaLightVehicle=2.5
PeopleinaLightVehicle=3
PeopleinaHGV=1.5
PeopleinaHGV=2
PeopleinaHGV=3
faccx10
faccx10-1
DG-HGVcorrectionfactor*10-1
DG-HGVtransportcorrectionfactor*10
Camber=2.5
Camber=4.12
Ground(BadRock):1
GroundType(Fragmented):2
SegmentGradient=0
SegmentGradient=3
SegmentGradient(SOUTH)=-0.32
SegmentGradient(NORTH)=-0.32
SegmentGradient=-3
NumberofLanes1
NumberofLanes3
Construction2(Rectangualarcross-section)
NormalLongitudinalVentilation105
NormalLongitudinalVentilation210
OpenAreaofdiscreteDrains=0
OpenAreaofdiscreteDrains*2
EmergencyComs=1(bell/siren)
EmergencyComs=2(PublicAddresssystem)
EmergencyLongitudinalVentilation200
EmergencyLongitudinalVentilation300
EmergencyLongitudinalVentilation→ReverseFlow
AverageSpacingbetweenEmergencyExits=200
AverageSpacingbetweenEmergencyExits=400
DelayforStoppingTraffic=1min
DelayforStoppingTraffic=2min
DelayforStoppingTraffic=3min
DelayforStoppingTraffic=4min
DelayforStoppingTraffic=5min
DelayforStoppingTraffic=10min
EVs in Direction South
Tunnel St. Demetrio: Sensitivity analysis results
Traffic
Frequency
of accidents
Structure
details
Safety
equipment
Number
of Lanes
facc x
10
DG-HGV
factor x 10
Delay for stopping
approaching trafficBUS ratio
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 76
1,00E-07
1,00E-06
1,00E-05
1,00E-04
1,00E-03
1,00E-02
1,00E-01
1,00E+00
1,00 10,00 100,00 1000,00
initial curve
Delayfor Stopping Approaching Traffic = 1 min
Delay for Stopping Approaching Traffic = 5 min
Tollerable Risk Line
Acceptable Risk Line
Delayfor Stopping Approaching Traffic = 10 min
Delayfor Stopping Approaching Traffic = 2 min
Delayfor Stopping Approaching Traffic = 3 min
Delayfor Stopping Approaching Traffic = 4 min
Sensitivity to parameter: “delay for stopping approaching traffic”
N = 𝑅 ∙ 𝐷 𝑅𝑈𝐽 + 𝑅 − 𝐿𝑗𝑎𝑚 ∙ 𝐷 𝑅𝑈𝐹 ∙ %𝐿𝐸𝑇𝐻
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 77
1,00E-07
1,00E-06
1,00E-05
1,00E-04
1,00E-03
1,00E-02
1,00E-01
1,00E+00
1,00 10,00 100,00 1000,00
initial curve
Number of Lanes (for every section and in both directions) = 1
Number of Lanes (for every section and in both directions) = 3
Tollerable Risk Line
Acceptable Risk Line
𝑁 = 𝑅 ∙ 𝐷 𝑅𝑈𝐽 ∙ %𝐿𝐸𝑇𝐻
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
Sensitivity to parameter: “number of lanes”
www.francobontempi.org 78
1,00E-07
1,00E-06
1,00E-05
1,00E-04
1,00E-03
1,00E-02
1,00E-01
1,00E+00
1,00 10,00 100,00 1000,00
initial curve
facc x 10
facc x 10-1
Tollerable Risk Line
Acceptable Risk Line
𝑓𝑖𝑗 = 𝑃𝑖𝑗 ∙ 𝑓𝑎𝑐𝑐,𝑖 ∙ 𝑇𝐻𝑖 ∙ 𝐿𝑖 ∙ 24 ∙ 365 ∙ 10−6
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
Sensitivity to parameter: “HGVs accident frequency”
www.francobontempi.org 79
1,00E-07
1,00E-06
1,00E-05
1,00E-04
1,00E-03
1,00E-02
1,00E-01
1,00E+00
1,00 10,00 100,00 1000,00
initial curve
Propane in Bulk ratio =Propane in Cylinder ratio =0.15
Propane in Cylinder ratio = 0.30
Tollerable Risk Line
Acceptable Risk Line
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
Sensitivity to parameter: “LPG (Liquefied Petroleum Gas) ratio”
www.francobontempi.org 80
conclusions
The parameters that most affect the risk curve:
• Density of people on the road
• Traffic (veh/h)
• Bus ratio (%)
• Number of lanes
• Delay for stopping approaching traffic
• Average vehicle occupancy
• Accident scenarios frequency [scen/year]
• facc
• DG-HGV traffic
• HGV traffic
• Proportion of each DG
𝑓𝑖𝑗𝑘 = 𝑃𝑖𝑗𝑘 ∙ 𝑓𝑎𝑐𝑐_𝐷𝐺,𝑖 ∙ 𝑇𝐷𝑖𝑘 ∙ 𝐿𝑖 ∙ 24 ∙ 365 ∙ 10−6
• Further risk mitigation measures (adopted only after a cost benefit analysis)
• The safety margin is high
San Demetrio Tunnel Risk Analysis
General Conclusions on the PIARC/OECD QRA model
N = 𝑅 ∙ 𝐷 𝑅𝑈𝐽 + 𝑅 − 𝐿𝑗𝑎𝑚 ∙ 𝐷 𝑅𝑈𝐹 ∙ %𝐿𝐸𝑇𝐻
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org 81
CONCLUSIONS: QRAM AND Fluid Dynamics/evacuation models
Data Collection
Data Preparation
Risk Calculation
Using QRAM
Is Risk
acceptable?
NO
Additional
risk reduction
measures
START
YES
End
Idintification of
Critical Scenarios
Single Scenario
Simulation
CFD Simulation
(Fire, Ventilation)
Evacuation Model
(Evacuation, Rescue)
Qualitative Risk
Estimation
Measures
Included
in the model?
YES NO
(Gai et al., Proceedings IF CRASC’ 15)
An operating method to follow can be to
identify the critical scenarios that give the most
significant contribution to the overall risk
through the QRAM, and then to simulate those
scenarios in detail in order to define risk
reduction measures (Petelin S. 2009)
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
• NFPA, SFPE Handbook of Fire Protection Engineering, 3rd edition, 2002
• Jönsson, J. Combined Qualitative and Quantitative Fire Risk Analysis – Complex Urban Road Tunnel. Arup partners, 2007.
• Faber, M.H. (2008) Risk and Safety in Civil, Environmental and Geomatic Engineering. ETH Zürich, lecture notes, available online on
01/2011 at: http://www.ibk.ethz.ch/fa
• Haimes, Y. Y. (1981). Hierarchical holographic modeling. IEEE Transactions on Systems, Man, and Cybernetics, 11(9), pp. 606– 617.
• Nolan, D.P. 1986. Handbook of Fire and Explosion Protection Engineering Principles for Oil, Gas, Chemical, and Related Facilities.
Noyes, New Jersey
• Aven, T. Risk Analysis: Assessing Uncertainties beyond Expected Values and Probabilities. John Wiley & Sons, 2008
• Furness, A. , Muckett, M. Introduction to Fire Safety Management. Elsevier, 2007.
• Fire Risk in Metro Tunnels and Stations, Hyder Consulting, available on 05.2011 at
http://hkarms.myftp.org/web_resources/Conference_Presentation/Fire_Risk_Metro_Tunnels_Stations.pdf
• Fault Tree Handbook. Nuclear Regulatory Commission. NUREG–0492
• Hasofer et al. 2007, Risk Analysis in Building Fire Safety Engineering
• Persson, M. Quantitative Risk Analysis Procedure for the Fire Evacuation of a Road Tunnel -An Illustrative Example. Lund, 2002
• Brussaard et al. 2004. The Dutch Model for the Quantitative Risk Analysis of Road Tunnels. Available on 05.2011 at
http://www.rws.nl/rws/bwd/home/Tunnelveiligheid/dutch%20model.pdf
• Gkoumas, K. 2008. Basic aspects of risk-analysis for civil engineering structures. Handling Exceptions in Structural Engineering:
Robustezza Strutturale, Scenari Accidentali, Complessità di Progetto, Roma, 13-14 novembre.
http://www.francobontempi.org/handling_papers.php
References (1/2)
82
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels
www.francobontempi.org
CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO
References (2/2)
83
• Di Santo, C., Gkoumas, K., Bontempi. F. “Risk analysis for severe traffic accidents in road tunnels (Part I)”, Ingegneria Forense, Crolli,
Affidabilità Strutturale e Consolidamento. Atti del Convegno IF CRASC '15 - 14/16 maggio 2015, Roma, Nicola Augenti & Franco
Bontempi (ed), Dario Flaccovio Editore, pp. 971-979, ISBN 9788857904474
• Di Santo, C., Gkoumas, K. “Risk analysis for severe traffic accidents in road tunnels (Part II)”, Ingegneria Forense, Crolli, Affidabilità
Strutturale e Consolidamento. Atti del Convegno IF CRASC '15 - 14/16 maggio 2015, Roma, Nicola Augenti & Franco Bontempi (ed),
Dario Flaccovio Editore, pp. 959-969, ISBN 9788857904474
• DG MOVE (2014). Harmonised Risk Acceptance Criteria for Transport of Dangerous Goods. London: Det Norske Veritas Ltd.
• Diernhofer, F., Kohl, B. and Hörhan, R. (2010). New Austrian Guideline for the Transport of Dangerous Goods through Road Tunnels. 5th
International Conference on Tunnel Safety and Ventilation, Graz, 2010.
• Evans, A.W. (2003). Transport Fatal Accidents and FN-curves: 1967-2001. HSE Research Report 073. HSE Books: Sudbury,
Suffolk.Directive 2004/54/EC of the European Parlament and the Concil of 29 April 2004 on minimum safety requirements for tunnels in
the trans-European road network, 7.6.2004
• Impresa Pizzarotti & C. S.p.A. (2007). Affidamento dell’opera di completamento del tratto stradale Catania Siracusa con caratteristiche
autostradali, compreso tra le località passo s. martino ed Il Km 130+400 Della Ss. 114, Analisi Di Rischio (in Italian).
• Melchers, R.E. 1993. Society, tolerable risk and the ALARP principle. In: Melchers RE, Stewart MG, editors. Probabilistic risk and
hazard assessment. Netherlands, Balkema: 243–252
• Petelin S., Luin, B. and Vidmar, P. (2010). Risk Analysis Methodology for Road Tunnels and Alternative Routes. Journal of Mechanical
Engineering, Vol. 56, No. 1, pp. 41-51.
• PIARC Technical Committee C3.3 (2008) Road Tunnel Operation, Risk Analysis for Road Tunnels, ISBN 2-84060-202-4.
• PIARC-OECD (2001). Safety in Tunnels, Transport of dangerous goods through road tunnels. OECD Publications.
• UNCED AGENDA 21. 1992. Program of Action for Sustainable Development. United Nations Publication - Sales No. E.93.I.
• Vagiokas, N., Bletsas, A. and Nelisse, R.M.L. (2013) Methodological approaches for tunnel classification according to ADR agreement.
World Tunnel Congress 2013 Geneva Underground – the way to the future! G. Anagnostou & H. Ehrbar (eds).
Fire risk analysis of structures
and infrastructures: theory and
application in highway tunnels

More Related Content

What's hot

Engineers responsibility for safety and risk
Engineers responsibility for safety and riskEngineers responsibility for safety and risk
Engineers responsibility for safety and risk
Student
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
Joe
 
Emergency preparedness plan for mines
Emergency preparedness plan for minesEmergency preparedness plan for mines
Emergency preparedness plan for mines
Krishna Deo Prasad
 
Horizontal Directional Drilling Reamer Selection Guide
Horizontal Directional Drilling Reamer Selection GuideHorizontal Directional Drilling Reamer Selection Guide
Horizontal Directional Drilling Reamer Selection Guide
nodigseo
 
Enhancement module lecture 4-fma and regulations
Enhancement module lecture 4-fma and regulationsEnhancement module lecture 4-fma and regulations
Enhancement module lecture 4-fma and regulations
Ridzwan Hj Hussain
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
Parth Desani
 
Confined space-entry
Confined space-entryConfined space-entry
Confined space-entry
Reliance
 
Search and rescue
Search and rescueSearch and rescue
Search and rescue
Shafiq Ridz
 
Explosives & safety
Explosives & safetyExplosives & safety
Explosives & safety
Rathin Biswas
 
Cybersecurity.pptx
Cybersecurity.pptxCybersecurity.pptx
Cybersecurity.pptx
ssuser2209e8
 
Physical security.ppt
Physical security.pptPhysical security.ppt
Physical security.ppt
Faheem Ul Hasan
 
Dust control measures
Dust control measuresDust control measures
Dust control measures
Safdar Ali
 
1.2.2.front end loaders
1.2.2.front end loaders1.2.2.front end loaders
1.2.2.front end loaders
Coomarasamy Chidambaram
 
Electrical Commissioning and Arc-Flash Safety presentation
Electrical Commissioning and Arc-Flash Safety presentationElectrical Commissioning and Arc-Flash Safety presentation
Electrical Commissioning and Arc-Flash Safety presentation
Michael Luffred
 
MAJOR CHALLENGES FOR HSE/OSHA PRACTITIONERS: 2015 and BEYOND. (Prof. Shukor)
MAJOR CHALLENGES FOR HSE/OSHA PRACTITIONERS: 2015 and BEYOND. (Prof. Shukor)MAJOR CHALLENGES FOR HSE/OSHA PRACTITIONERS: 2015 and BEYOND. (Prof. Shukor)
MAJOR CHALLENGES FOR HSE/OSHA PRACTITIONERS: 2015 and BEYOND. (Prof. Shukor)
Abdul Shukor
 
Operational Security Intelligence
Operational Security IntelligenceOperational Security Intelligence
Operational Security Intelligence
Splunk
 
Accident Investigation and Analysis
Accident Investigation and AnalysisAccident Investigation and Analysis
Accident Investigation and Analysis
Khawar Nehal khawar.nehal@atrc.net.pk
 
FAULT & EVENT TREE ANALYSIS
FAULT & EVENT TREE ANALYSISFAULT & EVENT TREE ANALYSIS
FAULT & EVENT TREE ANALYSIS
Nitesh Dongare
 
Environment & Industrial disasters
Environment & Industrial disastersEnvironment & Industrial disasters
Environment & Industrial disasters
Ankur Sharma
 
HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12
HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12
HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12
Quintus Murphy
 

What's hot (20)

Engineers responsibility for safety and risk
Engineers responsibility for safety and riskEngineers responsibility for safety and risk
Engineers responsibility for safety and risk
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
 
Emergency preparedness plan for mines
Emergency preparedness plan for minesEmergency preparedness plan for mines
Emergency preparedness plan for mines
 
Horizontal Directional Drilling Reamer Selection Guide
Horizontal Directional Drilling Reamer Selection GuideHorizontal Directional Drilling Reamer Selection Guide
Horizontal Directional Drilling Reamer Selection Guide
 
Enhancement module lecture 4-fma and regulations
Enhancement module lecture 4-fma and regulationsEnhancement module lecture 4-fma and regulations
Enhancement module lecture 4-fma and regulations
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
 
Confined space-entry
Confined space-entryConfined space-entry
Confined space-entry
 
Search and rescue
Search and rescueSearch and rescue
Search and rescue
 
Explosives & safety
Explosives & safetyExplosives & safety
Explosives & safety
 
Cybersecurity.pptx
Cybersecurity.pptxCybersecurity.pptx
Cybersecurity.pptx
 
Physical security.ppt
Physical security.pptPhysical security.ppt
Physical security.ppt
 
Dust control measures
Dust control measuresDust control measures
Dust control measures
 
1.2.2.front end loaders
1.2.2.front end loaders1.2.2.front end loaders
1.2.2.front end loaders
 
Electrical Commissioning and Arc-Flash Safety presentation
Electrical Commissioning and Arc-Flash Safety presentationElectrical Commissioning and Arc-Flash Safety presentation
Electrical Commissioning and Arc-Flash Safety presentation
 
MAJOR CHALLENGES FOR HSE/OSHA PRACTITIONERS: 2015 and BEYOND. (Prof. Shukor)
MAJOR CHALLENGES FOR HSE/OSHA PRACTITIONERS: 2015 and BEYOND. (Prof. Shukor)MAJOR CHALLENGES FOR HSE/OSHA PRACTITIONERS: 2015 and BEYOND. (Prof. Shukor)
MAJOR CHALLENGES FOR HSE/OSHA PRACTITIONERS: 2015 and BEYOND. (Prof. Shukor)
 
Operational Security Intelligence
Operational Security IntelligenceOperational Security Intelligence
Operational Security Intelligence
 
Accident Investigation and Analysis
Accident Investigation and AnalysisAccident Investigation and Analysis
Accident Investigation and Analysis
 
FAULT & EVENT TREE ANALYSIS
FAULT & EVENT TREE ANALYSISFAULT & EVENT TREE ANALYSIS
FAULT & EVENT TREE ANALYSIS
 
Environment & Industrial disasters
Environment & Industrial disastersEnvironment & Industrial disasters
Environment & Industrial disasters
 
HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12
HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12
HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12
 

Viewers also liked

Dcee4 paper 9
Dcee4 paper 9Dcee4 paper 9
Dcee4 paper 9
Konstantinos Gkoumas
 
2015.12.17 kg bim
2015.12.17 kg bim2015.12.17 kg bim
2015.12.17 kg bim
Konstantinos Gkoumas
 
Structural robustness: concepts and applications.
Structural robustness: concepts and applications.Structural robustness: concepts and applications.
Structural robustness: concepts and applications.
Franco Bontempi Org Didattica
 
2015.12.17 kg diagrid
2015.12.17 kg diagrid2015.12.17 kg diagrid
2015.12.17 kg diagrid
Konstantinos Gkoumas
 
Dcee 2016 program and abstracts
Dcee 2016 program and abstractsDcee 2016 program and abstracts
Dcee 2016 program and abstracts
Konstantinos Gkoumas
 
SCENARIO DAMAGE ANALYSIS OF RC PRECAST INDUSTRIAL STRUCTURES IN TUSCANY, ITALY
SCENARIO DAMAGE ANALYSIS OF RC PRECAST INDUSTRIAL STRUCTURES IN TUSCANY, ITALYSCENARIO DAMAGE ANALYSIS OF RC PRECAST INDUSTRIAL STRUCTURES IN TUSCANY, ITALY
SCENARIO DAMAGE ANALYSIS OF RC PRECAST INDUSTRIAL STRUCTURES IN TUSCANY, ITALY
Global Earthquake Model Foundation
 
Risk Governance: the challenge of risk transfer instruments and catastrophic ...
Risk Governance: the challenge of risk transfer instruments and catastrophic ...Risk Governance: the challenge of risk transfer instruments and catastrophic ...
Risk Governance: the challenge of risk transfer instruments and catastrophic ...
Global Risk Forum GRFDavos
 
Abdullahi chowdhury presentation slides
Abdullahi chowdhury presentation slidesAbdullahi chowdhury presentation slides
Abdullahi chowdhury presentation slides
International Center for Research & Development
 
8th Hellenic National Conference of Steel Structures
8th Hellenic National Conference of Steel Structures 8th Hellenic National Conference of Steel Structures
8th Hellenic National Conference of Steel Structures
Konstantinos Gkoumas
 
Gender mainstreaming and gender analysis in work addressing risk reduction: W...
Gender mainstreaming and gender analysis in work addressing risk reduction: W...Gender mainstreaming and gender analysis in work addressing risk reduction: W...
Gender mainstreaming and gender analysis in work addressing risk reduction: W...
Oxfam GB
 
Chapter 02
Chapter 02Chapter 02
Chapter 02
Joe
 
FPG High Hazard Tunnel Brochure Web
FPG High Hazard Tunnel Brochure WebFPG High Hazard Tunnel Brochure Web
FPG High Hazard Tunnel Brochure Web
Kenneth Strachan
 
Chapter 13
Chapter 13Chapter 13
Chapter 13
Joe
 
Chapter 14
Chapter 14Chapter 14
Chapter 14
Joe
 
Chapter 08
Chapter 08Chapter 08
Chapter 08
Joe
 
Enigma-CG Tunnel Safety & Fire Protection Conference Programme
Enigma-CG Tunnel Safety & Fire Protection Conference ProgrammeEnigma-CG Tunnel Safety & Fire Protection Conference Programme
Enigma-CG Tunnel Safety & Fire Protection Conference Programme
Tony Cash
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
Joe
 
Scenario Models and Sensitivity Analysis in Operational Risk
Scenario Models and Sensitivity Analysis in Operational Risk Scenario Models and Sensitivity Analysis in Operational Risk
Scenario Models and Sensitivity Analysis in Operational Risk
RUIXIN BAO
 
Operational Risk Loss Forecasting Model for Stress Testing
Operational Risk Loss Forecasting Model for Stress TestingOperational Risk Loss Forecasting Model for Stress Testing
Operational Risk Loss Forecasting Model for Stress Testing
CRISIL Limited
 
Development of derivatives market in malaysia present
Development of derivatives market in malaysia   presentDevelopment of derivatives market in malaysia   present
Development of derivatives market in malaysia present
Noorfazilah Muhamadjahari
 

Viewers also liked (20)

Dcee4 paper 9
Dcee4 paper 9Dcee4 paper 9
Dcee4 paper 9
 
2015.12.17 kg bim
2015.12.17 kg bim2015.12.17 kg bim
2015.12.17 kg bim
 
Structural robustness: concepts and applications.
Structural robustness: concepts and applications.Structural robustness: concepts and applications.
Structural robustness: concepts and applications.
 
2015.12.17 kg diagrid
2015.12.17 kg diagrid2015.12.17 kg diagrid
2015.12.17 kg diagrid
 
Dcee 2016 program and abstracts
Dcee 2016 program and abstractsDcee 2016 program and abstracts
Dcee 2016 program and abstracts
 
SCENARIO DAMAGE ANALYSIS OF RC PRECAST INDUSTRIAL STRUCTURES IN TUSCANY, ITALY
SCENARIO DAMAGE ANALYSIS OF RC PRECAST INDUSTRIAL STRUCTURES IN TUSCANY, ITALYSCENARIO DAMAGE ANALYSIS OF RC PRECAST INDUSTRIAL STRUCTURES IN TUSCANY, ITALY
SCENARIO DAMAGE ANALYSIS OF RC PRECAST INDUSTRIAL STRUCTURES IN TUSCANY, ITALY
 
Risk Governance: the challenge of risk transfer instruments and catastrophic ...
Risk Governance: the challenge of risk transfer instruments and catastrophic ...Risk Governance: the challenge of risk transfer instruments and catastrophic ...
Risk Governance: the challenge of risk transfer instruments and catastrophic ...
 
Abdullahi chowdhury presentation slides
Abdullahi chowdhury presentation slidesAbdullahi chowdhury presentation slides
Abdullahi chowdhury presentation slides
 
8th Hellenic National Conference of Steel Structures
8th Hellenic National Conference of Steel Structures 8th Hellenic National Conference of Steel Structures
8th Hellenic National Conference of Steel Structures
 
Gender mainstreaming and gender analysis in work addressing risk reduction: W...
Gender mainstreaming and gender analysis in work addressing risk reduction: W...Gender mainstreaming and gender analysis in work addressing risk reduction: W...
Gender mainstreaming and gender analysis in work addressing risk reduction: W...
 
Chapter 02
Chapter 02Chapter 02
Chapter 02
 
FPG High Hazard Tunnel Brochure Web
FPG High Hazard Tunnel Brochure WebFPG High Hazard Tunnel Brochure Web
FPG High Hazard Tunnel Brochure Web
 
Chapter 13
Chapter 13Chapter 13
Chapter 13
 
Chapter 14
Chapter 14Chapter 14
Chapter 14
 
Chapter 08
Chapter 08Chapter 08
Chapter 08
 
Enigma-CG Tunnel Safety & Fire Protection Conference Programme
Enigma-CG Tunnel Safety & Fire Protection Conference ProgrammeEnigma-CG Tunnel Safety & Fire Protection Conference Programme
Enigma-CG Tunnel Safety & Fire Protection Conference Programme
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
Scenario Models and Sensitivity Analysis in Operational Risk
Scenario Models and Sensitivity Analysis in Operational Risk Scenario Models and Sensitivity Analysis in Operational Risk
Scenario Models and Sensitivity Analysis in Operational Risk
 
Operational Risk Loss Forecasting Model for Stress Testing
Operational Risk Loss Forecasting Model for Stress TestingOperational Risk Loss Forecasting Model for Stress Testing
Operational Risk Loss Forecasting Model for Stress Testing
 
Development of derivatives market in malaysia present
Development of derivatives market in malaysia   presentDevelopment of derivatives market in malaysia   present
Development of derivatives market in malaysia present
 

Similar to Fire risk analysis of structures and infrastructures: theory and application in highway tunnels.

Risk analysis for fire: the case of civil structures
Risk analysis for fire: the case of civil structuresRisk analysis for fire: the case of civil structures
Risk analysis for fire: the case of civil structures
Konstantinos Gkoumas
 
PSA - Lezione 28 ottobre 2014 - RISK
PSA - Lezione 28 ottobre 2014 - RISKPSA - Lezione 28 ottobre 2014 - RISK
PSA - Lezione 28 ottobre 2014 - RISK
Franco Bontempi Org Didattica
 
2nd European Conference on Earthquake Engineering and Seismology. 24-29 Augus...
2nd European Conference on Earthquake Engineering and Seismology. 24-29 Augus...2nd European Conference on Earthquake Engineering and Seismology. 24-29 Augus...
2nd European Conference on Earthquake Engineering and Seismology. 24-29 Augus...
Infra Risk
 
InfraRisk Brochure
InfraRisk BrochureInfraRisk Brochure
InfraRisk Brochure
Infra Risk
 
Multi-Hazard Assessment of Bridges in Case of Hazard Chain: State of Play and...
Multi-Hazard Assessment of Bridges in Case of Hazard Chain: State of Play and...Multi-Hazard Assessment of Bridges in Case of Hazard Chain: State of Play and...
Multi-Hazard Assessment of Bridges in Case of Hazard Chain: State of Play and...
Franco Bontempi
 
Criticality analysis of Critical Infrastructures (CI) – parameters and criter...
Criticality analysis of Critical Infrastructures (CI) – parameters and criter...Criticality analysis of Critical Infrastructures (CI) – parameters and criter...
Criticality analysis of Critical Infrastructures (CI) – parameters and criter...
Global Risk Forum GRFDavos
 
Kost for china-2011
Kost for china-2011Kost for china-2011
Kost for china-2011
Mathmodels Net
 
Kostogryzov 10.12.2009
Kostogryzov 10.12.2009Kostogryzov 10.12.2009
Kostogryzov 10.12.2009
Mathmodels Net
 
WCRR 2016 paper 392
WCRR 2016 paper 392WCRR 2016 paper 392
WCRR 2016 paper 392
tonylancia
 
Cp18 cyrail final conference en
Cp18 cyrail final conference enCp18 cyrail final conference en
Cp18 cyrail final conference en
UICcom
 
An Analysis on the Safety Networks and Risk Level of Crane-related Accidents ...
An Analysis on the Safety Networks and Risk Level of Crane-related Accidents ...An Analysis on the Safety Networks and Risk Level of Crane-related Accidents ...
An Analysis on the Safety Networks and Risk Level of Crane-related Accidents ...
coreconferences
 
StroNGER + cistec 19 09 2014
StroNGER + cistec 19 09 2014StroNGER + cistec 19 09 2014
StroNGER + cistec 19 09 2014
Konstantinos Gkoumas
 
An overarching process to evaluate risks associated with infrastructure netwo...
An overarching process to evaluate risks associated with infrastructure netwo...An overarching process to evaluate risks associated with infrastructure netwo...
An overarching process to evaluate risks associated with infrastructure netwo...
Infra Risk
 
CSIAC_V1N4_FINAL_2
CSIAC_V1N4_FINAL_2CSIAC_V1N4_FINAL_2
A Method for Prioritization of Vulnerability Assessment of Technical Transpor...
A Method for Prioritization of Vulnerability Assessment of Technical Transpor...A Method for Prioritization of Vulnerability Assessment of Technical Transpor...
A Method for Prioritization of Vulnerability Assessment of Technical Transpor...
Global Risk Forum GRFDavos
 
Accident prediction models
Accident prediction modelsAccident prediction models
Accident prediction models
Anton Budiharjo
 
D12 1 risk assessment_final-web
D12 1 risk assessment_final-webD12 1 risk assessment_final-web
D12 1 risk assessment_final-web
Dir Jan
 
InfraRisk EU FACT SHEET
InfraRisk EU FACT SHEETInfraRisk EU FACT SHEET
InfraRisk EU FACT SHEET
Infra Risk
 
InfraRIsk EPA FACT SHEET
InfraRIsk EPA FACT SHEETInfraRIsk EPA FACT SHEET
InfraRIsk EPA FACT SHEET
Infra Risk
 
Design of the Stampede Preventing Monitoring and Early Warning System Based o...
Design of the Stampede Preventing Monitoring and Early Warning System Based o...Design of the Stampede Preventing Monitoring and Early Warning System Based o...
Design of the Stampede Preventing Monitoring and Early Warning System Based o...
IJRES Journal
 

Similar to Fire risk analysis of structures and infrastructures: theory and application in highway tunnels. (20)

Risk analysis for fire: the case of civil structures
Risk analysis for fire: the case of civil structuresRisk analysis for fire: the case of civil structures
Risk analysis for fire: the case of civil structures
 
PSA - Lezione 28 ottobre 2014 - RISK
PSA - Lezione 28 ottobre 2014 - RISKPSA - Lezione 28 ottobre 2014 - RISK
PSA - Lezione 28 ottobre 2014 - RISK
 
2nd European Conference on Earthquake Engineering and Seismology. 24-29 Augus...
2nd European Conference on Earthquake Engineering and Seismology. 24-29 Augus...2nd European Conference on Earthquake Engineering and Seismology. 24-29 Augus...
2nd European Conference on Earthquake Engineering and Seismology. 24-29 Augus...
 
InfraRisk Brochure
InfraRisk BrochureInfraRisk Brochure
InfraRisk Brochure
 
Multi-Hazard Assessment of Bridges in Case of Hazard Chain: State of Play and...
Multi-Hazard Assessment of Bridges in Case of Hazard Chain: State of Play and...Multi-Hazard Assessment of Bridges in Case of Hazard Chain: State of Play and...
Multi-Hazard Assessment of Bridges in Case of Hazard Chain: State of Play and...
 
Criticality analysis of Critical Infrastructures (CI) – parameters and criter...
Criticality analysis of Critical Infrastructures (CI) – parameters and criter...Criticality analysis of Critical Infrastructures (CI) – parameters and criter...
Criticality analysis of Critical Infrastructures (CI) – parameters and criter...
 
Kost for china-2011
Kost for china-2011Kost for china-2011
Kost for china-2011
 
Kostogryzov 10.12.2009
Kostogryzov 10.12.2009Kostogryzov 10.12.2009
Kostogryzov 10.12.2009
 
WCRR 2016 paper 392
WCRR 2016 paper 392WCRR 2016 paper 392
WCRR 2016 paper 392
 
Cp18 cyrail final conference en
Cp18 cyrail final conference enCp18 cyrail final conference en
Cp18 cyrail final conference en
 
An Analysis on the Safety Networks and Risk Level of Crane-related Accidents ...
An Analysis on the Safety Networks and Risk Level of Crane-related Accidents ...An Analysis on the Safety Networks and Risk Level of Crane-related Accidents ...
An Analysis on the Safety Networks and Risk Level of Crane-related Accidents ...
 
StroNGER + cistec 19 09 2014
StroNGER + cistec 19 09 2014StroNGER + cistec 19 09 2014
StroNGER + cistec 19 09 2014
 
An overarching process to evaluate risks associated with infrastructure netwo...
An overarching process to evaluate risks associated with infrastructure netwo...An overarching process to evaluate risks associated with infrastructure netwo...
An overarching process to evaluate risks associated with infrastructure netwo...
 
CSIAC_V1N4_FINAL_2
CSIAC_V1N4_FINAL_2CSIAC_V1N4_FINAL_2
CSIAC_V1N4_FINAL_2
 
A Method for Prioritization of Vulnerability Assessment of Technical Transpor...
A Method for Prioritization of Vulnerability Assessment of Technical Transpor...A Method for Prioritization of Vulnerability Assessment of Technical Transpor...
A Method for Prioritization of Vulnerability Assessment of Technical Transpor...
 
Accident prediction models
Accident prediction modelsAccident prediction models
Accident prediction models
 
D12 1 risk assessment_final-web
D12 1 risk assessment_final-webD12 1 risk assessment_final-web
D12 1 risk assessment_final-web
 
InfraRisk EU FACT SHEET
InfraRisk EU FACT SHEETInfraRisk EU FACT SHEET
InfraRisk EU FACT SHEET
 
InfraRIsk EPA FACT SHEET
InfraRIsk EPA FACT SHEETInfraRIsk EPA FACT SHEET
InfraRIsk EPA FACT SHEET
 
Design of the Stampede Preventing Monitoring and Early Warning System Based o...
Design of the Stampede Preventing Monitoring and Early Warning System Based o...Design of the Stampede Preventing Monitoring and Early Warning System Based o...
Design of the Stampede Preventing Monitoring and Early Warning System Based o...
 

More from Franco Bontempi Org Didattica

50 anni.Image.Marked.pdf
50 anni.Image.Marked.pdf50 anni.Image.Marked.pdf
50 anni.Image.Marked.pdf
Franco Bontempi Org Didattica
 
4. Comportamento di elementi inflessi.pdf
4. Comportamento di elementi inflessi.pdf4. Comportamento di elementi inflessi.pdf
4. Comportamento di elementi inflessi.pdf
Franco Bontempi Org Didattica
 
Calcolo della precompressione: DOMINI e STRAUS7
Calcolo della precompressione: DOMINI e STRAUS7Calcolo della precompressione: DOMINI e STRAUS7
Calcolo della precompressione: DOMINI e STRAUS7
Franco Bontempi Org Didattica
 
II evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdf
II evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdfII evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdf
II evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdf
Franco Bontempi Org Didattica
 
ICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdf
ICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdfICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdf
ICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdf
Franco Bontempi Org Didattica
 
Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...
Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...
Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...
Franco Bontempi Org Didattica
 
Soft computing based multilevel strategy for bridge integrity monitoring
Soft computing based multilevel strategy for bridge integrity monitoringSoft computing based multilevel strategy for bridge integrity monitoring
Soft computing based multilevel strategy for bridge integrity monitoring
Franco Bontempi Org Didattica
 
Systemic approach for the maintenance of complex structural systems
Systemic approach for the maintenance of complex structural systemsSystemic approach for the maintenance of complex structural systems
Systemic approach for the maintenance of complex structural systems
Franco Bontempi Org Didattica
 
Elenco studenti esaminandi
Elenco studenti esaminandiElenco studenti esaminandi
Elenco studenti esaminandi
Franco Bontempi Org Didattica
 
Costruzione di ponti in cemento armato.
Costruzione di ponti in cemento armato.Costruzione di ponti in cemento armato.
Costruzione di ponti in cemento armato.
Franco Bontempi Org Didattica
 
Costruzione di ponti in acciaio
Costruzione di ponti in acciaioCostruzione di ponti in acciaio
Costruzione di ponti in acciaio
Franco Bontempi Org Didattica
 
Costruzione di Ponti - Ceradini
Costruzione di Ponti - CeradiniCostruzione di Ponti - Ceradini
Costruzione di Ponti - Ceradini
Franco Bontempi Org Didattica
 
The role of softening in the numerical analysis of R.C. framed structures
The role of softening in the numerical analysis of R.C. framed structuresThe role of softening in the numerical analysis of R.C. framed structures
The role of softening in the numerical analysis of R.C. framed structures
Franco Bontempi Org Didattica
 
Reliability of material and geometrically non-linear reinforced and prestress...
Reliability of material and geometrically non-linear reinforced and prestress...Reliability of material and geometrically non-linear reinforced and prestress...
Reliability of material and geometrically non-linear reinforced and prestress...
Franco Bontempi Org Didattica
 
Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...
Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...
Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...
Franco Bontempi Org Didattica
 
Cellular Automata Approach to Durability Analysis of Concrete Structures in A...
Cellular Automata Approach to Durability Analysis of Concrete Structures in A...Cellular Automata Approach to Durability Analysis of Concrete Structures in A...
Cellular Automata Approach to Durability Analysis of Concrete Structures in A...
Franco Bontempi Org Didattica
 
UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...
UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...
UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...
Franco Bontempi Org Didattica
 
Esami a distanza. Severgnini. Corriere della sera.
Esami a distanza. Severgnini. Corriere della sera.Esami a distanza. Severgnini. Corriere della sera.
Esami a distanza. Severgnini. Corriere della sera.
Franco Bontempi Org Didattica
 
Tdc prova 2022 01-26
Tdc prova 2022 01-26Tdc prova 2022 01-26
Tdc prova 2022 01-26
Franco Bontempi Org Didattica
 
Risultati
RisultatiRisultati

More from Franco Bontempi Org Didattica (20)

50 anni.Image.Marked.pdf
50 anni.Image.Marked.pdf50 anni.Image.Marked.pdf
50 anni.Image.Marked.pdf
 
4. Comportamento di elementi inflessi.pdf
4. Comportamento di elementi inflessi.pdf4. Comportamento di elementi inflessi.pdf
4. Comportamento di elementi inflessi.pdf
 
Calcolo della precompressione: DOMINI e STRAUS7
Calcolo della precompressione: DOMINI e STRAUS7Calcolo della precompressione: DOMINI e STRAUS7
Calcolo della precompressione: DOMINI e STRAUS7
 
II evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdf
II evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdfII evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdf
II evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdf
 
ICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdf
ICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdfICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdf
ICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdf
 
Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...
Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...
Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...
 
Soft computing based multilevel strategy for bridge integrity monitoring
Soft computing based multilevel strategy for bridge integrity monitoringSoft computing based multilevel strategy for bridge integrity monitoring
Soft computing based multilevel strategy for bridge integrity monitoring
 
Systemic approach for the maintenance of complex structural systems
Systemic approach for the maintenance of complex structural systemsSystemic approach for the maintenance of complex structural systems
Systemic approach for the maintenance of complex structural systems
 
Elenco studenti esaminandi
Elenco studenti esaminandiElenco studenti esaminandi
Elenco studenti esaminandi
 
Costruzione di ponti in cemento armato.
Costruzione di ponti in cemento armato.Costruzione di ponti in cemento armato.
Costruzione di ponti in cemento armato.
 
Costruzione di ponti in acciaio
Costruzione di ponti in acciaioCostruzione di ponti in acciaio
Costruzione di ponti in acciaio
 
Costruzione di Ponti - Ceradini
Costruzione di Ponti - CeradiniCostruzione di Ponti - Ceradini
Costruzione di Ponti - Ceradini
 
The role of softening in the numerical analysis of R.C. framed structures
The role of softening in the numerical analysis of R.C. framed structuresThe role of softening in the numerical analysis of R.C. framed structures
The role of softening in the numerical analysis of R.C. framed structures
 
Reliability of material and geometrically non-linear reinforced and prestress...
Reliability of material and geometrically non-linear reinforced and prestress...Reliability of material and geometrically non-linear reinforced and prestress...
Reliability of material and geometrically non-linear reinforced and prestress...
 
Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...
Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...
Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...
 
Cellular Automata Approach to Durability Analysis of Concrete Structures in A...
Cellular Automata Approach to Durability Analysis of Concrete Structures in A...Cellular Automata Approach to Durability Analysis of Concrete Structures in A...
Cellular Automata Approach to Durability Analysis of Concrete Structures in A...
 
UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...
UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...
UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...
 
Esami a distanza. Severgnini. Corriere della sera.
Esami a distanza. Severgnini. Corriere della sera.Esami a distanza. Severgnini. Corriere della sera.
Esami a distanza. Severgnini. Corriere della sera.
 
Tdc prova 2022 01-26
Tdc prova 2022 01-26Tdc prova 2022 01-26
Tdc prova 2022 01-26
 
Risultati
RisultatiRisultati
Risultati
 

Recently uploaded

Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
Ratnakar Mikkili
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 

Recently uploaded (20)

Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 

Fire risk analysis of structures and infrastructures: theory and application in highway tunnels.

  • 1. Fire risk analysis of structures and infrastructures: theory and application in highway tunnels CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO, AA: 2015-’16 1November 10 2015www.francobontempi.org Konstantinos Gkoumas, PhD, PE Facoltà di Ingegneria Sapienza Università di Roma Corso di Progettazione Strutturale Antincendio Docente: Prof. Ing. Franco Bontempi
  • 2. Outline • System approach to fire safety design • Risk/fire risk/risk analysis • Risk assessment process • Risk analysis • Hazard analysis • Risk acceptance • Risk reduction • Risk assessment of road tunnels using PIARC/OECD QRAM • Case study: risk assessment of a long highway tunnel • References www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO 2 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 3. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO 3 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 4. • System approach to fire safety design • Risk - fire risk - risk types - risk analysis www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO 4 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 5. System approach to fire safety design www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO MINOR SPREAD FIRE SPREADSTOP FIRE suppression Y MAJOR SPREAD STRUCTURAL INTEGRITY AVOID CASUALITIES LOCALISED DAMAGE STRUCTURAL FAILURES N mitigation Y N fire safe design Y N FIRE robust design Y N MAJOR COLLAPSE AVOID DIRECT DAMAGE AVOID COLLAPSE 1 2 3 4 0 preventionOBJECTIVE fire safety design - structural fire safety design - non structural GLOBAL SAFETY LOSS OF GLOBAL SAFETY AVOID INDIRECT DAMAGE NY The fire safety is framed in different “safety levels”, corresponding to different safety objectives. 5 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 6. (Fire) Risk Estimation* *(following SFPE Handbook of Fire Protection Engineering) Provide answer to the following questions 1. What could happen? 2. How bad would it be if it did happen? 3. How likely is it to happen www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO 6 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 7. What is risk? Risk can be defined as the probability that the harm or damage from a particular hazard is realized. Risk is measured in terms of consequences and likelihood (a qualitative description of probability or frequency). In mathematical terms risk can be defined as: risk = f (frequency or probability, consequence) (1) In the case of an activity with only one event with potential consequences, a risk (R) is the probability (P) that this event will occur multiplied with the consequences (C) given the event occurs: R = PC (2) The risk of a system is the sum of the risks of all harmful events of that system: (3) www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO 𝑅𝑆 = 𝑅𝑖 𝑛 𝑖=1 7 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 8. Risk types • Life safety risks are normally presented in two ways: - Individual risk and - Societal risk • Individual risk: The purpose of the individual risk is to ensure that individuals in the society are not exposed to unacceptably high risks. It can be defined as the risk to any occupant on the scene for the event/hazard scenario i.e. it is the risk to an individual and not to a group of people. • Societal risk: Societal risk is not looking at one individual but is concerned with the risk of multiple fatalities. People are treated as a group, there are no considerations taken to the individuals within the group i.e. the definition of the risk is from a societal point of view. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Source: Jönsson, 2007 8 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 9. What is risk analysis? • A big family of different approaches, methods and complex models combining various methododical components for specific tasks • Systematic analysis of sequences and interaction effects in potential accidents, thereby identifying weak points in the system and recognizing possible improvement measures • Risk analysis makes the quantification of risks feasible www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO 9 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 10. The risk assessment process www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO 10 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 11. The risk assessment process www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Start Definition of the system Hazard identification Probability analysis Consequence analysis Additional safety measures Risk estimation Risk evaluation Risk criteria Acceptable risk? Stop Risk analysis Risk evaluation YES NO Risk reduction 11 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 12. Definition of the system (context establishment) www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Define the operational environment and the context of the risk assessment process – Definition of the scope or the risk assessment process • This includes determining the timeframe (e.g. from planning to dismantling), the required resources and the depth of analysis required. – Definition of the strategic and organizational context • The nature of the organization in charge of the risk management and the environment in which it operates is established – Identification of the stakeholders (portatori di interesse) and objectives • The relationships that are interdependent with the organization are defined, the impacts that might occur are accounted for, as well as and what each is wanting out of the relationship – Determination of the evaluation criteria • Decide what level of risk the organization is prepared to accept 12 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 13. Hazard identification www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Hazard identification a. What can happen b. How can it happen Means for hazard identification: • Decomposition of the system into a number of components and/or subsystems • Identification of possible states of failure for the considered system and sub-systems • Identification of how the hazards might be realized for the considered system and subsystems Source: Faber, 2008 13 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 14. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Hazard identification – system decomposition A. Structure 1. Main components (d) Foundations (c) Towers (b) Anchor systems (a) Main cables (h) Cable saddle (e) Railway girder (f) Highway girders (g) Expansion joints (e) Non str.elements (a) Steel (b) Concrete (c) Prestressed c. (d) Alluminium/iron 3. Materials (f) Coating 4. Systems (a) Electrical (c) Hydraulics (b) Mechanical (e) Bitumen (e) Plastic 2. Secondary comp. (d) H.R. attachments (c) TMD (b) Buffers (a) Hanger ropes B. Users 1. Highway traffic (b) Commercial (a) Private 2. Railway traffic (b) Commercial (a) Private (a) Heavy (b) Hazard mat. (c) Military 3. Exceptional traffic C. Facilities 1. Over the bridge (b) Railway (a) Highway 2. By the bridge (a) Highway (b) Railway (c) Toll booths (d) Control center (e) Parking (a) Maritime traffic 3. Under the bridge D. Dependencies 1. Power 3. Financial 2. Communications 4. Supplies 5. Emerg. Responce (a) First aid (b) Police (c) Fire brigade (d) Hospitals 6. Ext. Contractors E. Linkage 1. Economy 3. Military 2. Social F. Operation 1. Authorities (b) Management 2. Aspects (a) Bridge authorities (b) Goverment (c) Region 5. Personnel (c) Maintenance (a) Financial (b) Other (a) Technical G. Technology (a) GPS (b) Accelerometers (c) Strain gauges (e) Thermometers (g) CCTV (f) WIM (d) Seismographs (h) Field equipment 1. Monitoring 2. Control (a) Cable control (d) Railway traffic (c) Highway traffic (b) TMD 3. Data transmission (b) Wireless (a) Cable 4. Computer center (b) Software (a) Hardware (d) Internet/LAN (c) Data bases 4. Regulations 3. Policies 4. Location (c) External HierarchicalHolographicModels(HHM) (DefinedinHaimes,1981) 14 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 15. Risk analysis: hazard identification www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO • Qualitative methods Studies based on the generic experience of personnel and do not involve mathematical estimations. • Quantitative methods Mathematical estimations that rely upon historical evidence or estimates of failures to predict the occurrence of an event. • Semi-quantitative methods Combination of the above (mostly, qualitative methods with applied numerical values). Source: Nolan, D. P. Handbook of Fire and Explosion Protection Engineering Principles for Oil, Gas, Chemical, and Related Facilities, 1986 15 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 16. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Source: Aven, T. Risk Analysis: Assessing Uncertainties beyond Expected Values and Probabilities. John Wiley & Sons, 2008 Risk analysis: hazard identification 16 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 17. Hazard identification. Qualitative Methods www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Checklist or Worksheet A standardized listing which identifies common protection features required for typical facilities is compared against the facility design and operation. Risks are expressed by the omission of safety systems or system features. Preliminary Hazard Analysis (PHA) Each hazard is identified with potential causes and effects. Recommendations or known protective measures are listed. What-If analysis A safety study which by which “What-If’ investigative questions (brainstorming approach) are asked by an experienced team of a hydrocarbon system or components under examination. Risks are normally expressed in a qualitative numerical series (e.g., 1 to 5). HAZOP - HAZard and OPerability analysis (analisi di pericolo e operabilità) A formal systematic critical safety study where deviations of design intent of each component are formulated and analyzed from a standardized list. Risks are typically expressed in a qualitative numerical series (e.g., 1 to 5) relative to one another. Source: Nolan, D.P. 1986. Handbook of Fire and Explosion Protection Engineering Principles for …. Noyes, New Jersey 17 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 18. Hazard identification. Qualitative Methods www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Event Trees (ET) –albero degli eventi A mathematical logic model that mathematically and graphically portrays the combination of events and circumstances in an accident sequence, expressed in an annual estimation. Fault Trees (FT) – alberi dei guasti A mathematical logic model that mathematically and graphically portrays the combination of failures that can lead to a specific main failure or accident of interest, expressed in an annual estimation. Failure Modes and Effects Analysis (FMEA) A systematic, tabular method of evaluating the causes and effects of known types of component failures, expressed in an annual estimation. Source: Nolan, D.P. 1986. Handbook of Fire and Explosion Protection Engineering Principles for …. Noyes, New Jersey 18 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 19. • Risk analysis • Qualitative risk analysis • Quantitative risk analysis www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO 19 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 20. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Risk analysis • Risk analysis – Probability- as the likelihood of the risk occurrence – Impact - consequences if the risk occurs • risk proximity, meant as the point in time during which a risk will impact • Risk analysis - methods – Qualitative Risk Analysis, in which numbers and probabilities are used not extensively or at all – Quantified Risk Analysis (QRA) – Probabilistic Risk Analysis (PRA), in which the system risk is represented as a probability distribution 20 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 21. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Risk analysis and system complexity High-Probability/ Low-Consequences (HPLC) Low-Probability/ High-Consequences (LPHC) High-Probability/ Low-Consequences (HPLC) Low-Probability/ High-Consequences (LPHC) High-Probability/ Low-Consequences (HPLC) Low-Probability/ High-Consequences (LPHC) High-Probability/ Low-Consequences (HPLC) Stochastic Complexity Deterministic Analysis Methods Qualitative Risk Analysis Quantitative/Probabilistic Risk Analysis Pragmatic Risk Scenarios Stochastic Complexity Deterministic Analysis Methods Qualitative Risk Analysis Quantitative/Probabilistic Risk Analysis Pragmatic Risk Scenarios 21 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 22. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Qualitative Risk analysis • Qualitative Risk Analysis is the simplest method of risk analysis, and generally is used during the preliminary analysis phases. • It consists in using subjective assessments of risks, and consequently, in ranking them in a subjective manner. • Sources for information to be used in the analysis can be drown from previous experiences, history of events and consultation of experts. • The ranking of risks is qualitative, e.g. risk (1) > risk (2) > risk (3), while a description can be added. Eventually, a likelihood-consequence matrix can be constructed. • The biggest drawback of QRA is that there is neither a clear indication of the risk’s magnitude nor an absolute scale of how serious the risk might be, so, for a comprehensive risk analysis of more complex systems, quantitative methods should be preferred. 22 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 23. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Qualitative risk analysis methods: risk matrix • A risk matrix typically provides a discrete partitioning of relative consequences along one dimension and relative likelihood along the other. • The entry in each matrix cell may include a description of hazards known or believed to have that combination of consequence severity and likelihood. Source: NFPA, SFPE Handbook of Fire Protection Engineering, 3rd edition, 2002 Source: Furness, A., Muckett, M. Introduction to Fire Safety Management. Elsevier, 2007. 23 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 24. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Qualitative risk analysis methods: SWOT analysis 24 Strengths (forza): characteristics of the business or project that give it an advantage over others. Weaknesses (debolezza): characteristics that place the business or project at a disadvantage relative to others Opportunities (opportunità): elements that the project could exploit to its advantage Threats (minacce): elements in the environment that could cause trouble for the business or project Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 25. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Quantitative Risk analysis • Quantified (or quantitative) Risk Analysis (QRA) combines the consequences and frequencies of accident scenarios to estimate the level of risk. • In respect to the Qualitative method, QRA implicates the acquaintance of probabilities that describe the likelihood of the outcomes and their consequences. • QRA started with the chemical industries from the 70s and the offshore industry from the 80s. • QRA is traditionally expressed through the decomposition of the system. This frequently is done by the use of event trees and fault trees. 25 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 26. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO FTA and ETA • ETA (event tree analysis – albero degli eventi) provides a structure for postulating an initiating event and analyzing the potential outcomes • FTA (fault tree analysis – albero dei guasti) begins with a failure and provides a structure to look for potential causes 26 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 27. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Event tree analysis • Event trees pictorially represent the logical order in which events in a system can occur. Event trees begin with an initiating event, and then the consequences of the event are followed through a series of possible paths. • Each path is assigned a probability of occurrence. Therefore, the probability of the various possible outcomes can be calculated. • Event tree analysis is based on binary logic, in which an event has either happened or not, or a component has failed or has not. • It is valuable to analyze the consequences arising from a failure or undesired event. 27 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 28. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Event tree analysis: illustration (1) 28 Event trees are helpful in considering all the possible outcomes (on the right-hand side) from an initiating event (on the left-hand side), which is usually ignition for fire risks. The frequency of the initiating event can be estimated from fire report data, and the conditional probabilities of the sub-events can be quantified from fire report data or fault trees. Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 29. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Event tree analysis: illustration (2) Source: Fire Risk in Metro Tunnels and Stations Hyder Consulting 29 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 30. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Fault tree analysis 30 Fault trees are helpful in quantifying the probability of a top event of concern (such as the failure of a fire protection system) from all the potential root causes (at the bottom), again quantified from fire report data. Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 31. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Fault tree analysis general conclusion (event) • Fault trees look like a complement to event trees. • The idea is to begin with a general conclusion (event) and, using a top-down approach, to generate a logic model that provides for both qualitative and quantitative evaluation of the system reliability. Source: google pictures search “Fault tree” 31 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 32. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Fault tree analysis - symbols Basic event - failure or error in a system component or element (example: switch stuck in open position) Initiating event - an external event (example: bird strike to aircraft) Undeveloped event - an event about which insufficient information is available, or which is of no consequence Conditioning event - conditions that restrict or affect logic gates (example: mode of operation in effect) Intermediate event: can be used immediately above a primary event to provide more room to type the event description. Source: Fault Tree Handbook. Nuclear Regulatory Commission. NUREG–0492 32 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 33. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Fault tree analysis – gate symbols OR gate - the output occurs if any input occurs AND gate - the output occurs only if all inputs occur (inputs are independent) Exclusive OR gate - the output occurs if exactly one input occurs Priority AND gate - the output occurs if the inputs occur in a specific sequence specified by a conditioning event Inhibit gate - the output occurs if the input occurs under an enabling condition specified by a conditioning event Source: Fault Tree Handbook. Nuclear Regulatory Commission. NUREG–0492 33 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 34. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Advantages and disadvantages of FTA • Disadvantages 1. There is a possibility of oversight and omission of significant failure modes. 2. It is difficult to apply Boolean logic to describe failures of system components that can be partially successful in operation and thereby affect the operation of the system, e.g. leakage through a valve. 3. For the quantitative analysis there is usually a lack of pertinent failure data. Even when there are data they may have been obtained from a different environment. • Advantages 1. It provides a systematic procedure for identifying faults that can exist within a system. 2. It forces the analyst to understand the system thoroughly. Source: Hasofer et al. 2007, Risk Analysis in Building Fire Safety Engineering 34 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 35. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Cause – consequence diagrams • The combination of fault trees and event trees leads to the creation of cause-consequence diagrams. Time Revealed from the Monitoring system S3 S2 S1 Consequences Infraction of traffic law Improper speed Road condition Vehicle flow blocked YES YES NO NO Other Iniziative event Road Accident 35 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 36. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO SCENARIO PROBABILITY A1 PA*P1 A2 PA*(1-P1) *P2 *P3 A3 PA*(1-P1) *P2*(1-P3 ) A4 PA*(1-P1) *(1-P2)*P3 A5 PA*(1-P1) *(1-P2)*(1-P3) B1 PB*P1 B2 PB*(1-P1) *P2 *P3 B3 PB*(1-P1) *P2*(1-P3 ) B4 PB*(1-P1) *(1-P2)*P3 B5 PB*(1-P1) *(1-P2)*(1-P3) C1 PC*P1 C2 PC*(1-P1) *P2 *P3 C3 PC*(1-P1) *P2*(1-P3 ) C4 PC*(1-P1) *(1-P2)*P3 C5 PC*(1-P1) *(1-P2)*(1-P3) Triggering event Fire ignition 1. Fire extinguished by personnel 2. Intrusion of fire fighters Arson Explosion Short circuit Cigarette fire YES (P1) NO (1-P1) YES (P2) NO (1-P2) Scenario Other A1 A2 A3 A4 A5 3. Fire suppression YES (P3) NO (1-P3) YES (P3) NO (1-P3) Fire location AREA A (PA) YES (P1) NO (1-P1) YES (P2) NO (1-P2) B1 B2 B3 B4 B5 YES (P3) NO (1-P3) YES (P3) NO (1-P3) AREA B (PB) YES (P1) NO (1-P1) YES (P2) NO (1-P2) C1 C2 C3 C4 C5 YES (P3) NO (1-P3) YES (P3) NO (1-P3) AREA C (PC) Quantified Risk Analysis: cause – effect diagrams 36 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 37. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO F (frequency) – N (number of fatalities) curve • An F–N curve is an alternative way of describing the risk associated with loss of lives. • An F–N curve shows the frequency (i.e. the expected number) of accident events with at least N fatalities, where the axes normally are Logarithmic. • The F–N curve describes risk related to large-scale accidents, and is thus especially suited for characterizing societal risk. Source: Aven, T. Risk Analysis: Assessing Uncertainties beyond Expected Values and Probabilities. John Wiley & Sons, 2008 37 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 38. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO F (frequency) – N (number of fatalities) curve Source: Aven, T. Risk Analysis: Assessing Uncertainties beyond Expected Values and Probabilities. John Wiley & Sons, 2008 38 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 39. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO F (frequency) – N (number of fatalities) curve Source: NFPA, SFPE Handbook of Fire Protection Engineering, 3rd edition, 2002 39 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 40. Index • Risk acceptance - ALARP - Human life (!) www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO 40 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 41. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Risk acceptance Source: Persson, M. Quantitative Risk Analysis Procedure for the Fire Evacuation of a Road Tunnel -An Illustrative Example. Lund, 2002 41 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 42. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Risk acceptance – ALARP (1) RISK MAGNITUDE INTOLERABLE REGION As Low As Reasonably Practicable BROADLY ACCEPTABLE REGION Risk cannot be justified in any circumstances Tolerable only if risk reduction is impracticable or if its cost is greatly disproportionate to the improvement gained Tolerable if cost of reduction would exceed the improvements gained Necessary to maintain assurance that the risk remains at this level As Low As Reasonably Achievable RISK MAGNITUDE INTOLERABLE REGION As Low As Reasonably Practicable BROADLY ACCEPTABLE REGION Risk cannot be justified in any circumstances Tolerable only if risk reduction is impracticable or if its cost is greatly disproportionate to the improvement gained Tolerable if cost of reduction would exceed the improvements gained Necessary to maintain assurance that the risk remains at this level As Low As Reasonably Achievable 42 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 43. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Risk acceptance – ALARP (2) Source: google pictures search “ALARP” 43 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 44. CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Monetary values – cost of human life (!) • What is the maximum amount the society (or the decision-maker) is willing to pay to reduce the expected number of fatalities by 1? • Typical numbers for the value of a statistical life used in cost-benefit analysis are 1–10 million euros. The Ministry of Finance in Norway has arrived at a value at approximately 2 million euros. www.francobontempi.org Guideline values for the cost to avert a statistical life (euros), used by an oil company Source: Aven, T. Risk Analysis: Assessing Uncertainties beyond Expected Values and Probabilities. John Wiley & Sons, 2008 44 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 45. Risk reduction www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO 45 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 46. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Risk reduction Source: Brussaard et al. 2004. The Dutch Model for the Quantitative Risk Analysis of Road Tunnels. 46 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 47. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO Risk reduction (2) - monitoring and system response Time 1 3 2 Accident Accident evolution Pre-accident situation Pre-accident Monitoring Pre-accident System Response Accident Localization Evolution of System Response Accident evolution Monitoring System Response 47 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 48. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO 48 Parte 2a: Analisi del rischio di gallerie stradali Fire risk analysis of structures and infrastructures: theory and application in highway tunnels Source: "Risk analysis for severe traffic accidents in road tunnels". “Laurea Magistrale” (M.Sc.) Thesis at the Sapienza University of Rome, Faculty of Civil and Industrial Engineering. Candidate: Carmine Di Santo. Final grade: 110/110 “Summa cum Laude”. Advisor: Prof. Franco Bontempi, co-advisor: Konstantinos Gkoumas, PhD. Defended in January 2015.
  • 49. www.francobontempi.org 49 The issue of SAFETY in tunnels Mont Blanc Tunnel Fire (1999) 39 Fatalities Italia (Courmayer) – France (Chamonix) single – bore, bidirectional tunnel Length = 11.6 km St. Gotthard Tunnel Fire (2001) 11 Fatalities Switzerland (Göschenen) – Switzerland (Airolo) single – bore, bidirectional tunnel Length = 16,9 km Frejus Tunnel Fire (2005) 2 Fatalities Italia (Bardonecchia) – France (Modane) single – bore, bidirectional tunnel Length = 12,9 km Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 50. www.francobontempi.org 50 The issue of SAFETY in tunnels Directive 2004/54/EC Quantitative Risk Analysis Objectives Parameters Requirements Transport of Dangerous Goods through road tunnels OECD/PIARC/EU Quantitative Risk Assessment Model • OECD (Organisation of Economic Co- operation and Development) • PIARC (World Road Association) • European Commission • France (INERIS), Canada (WS Atkins), UK (IRR) Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 51. www.francobontempi.org 51 PIARC/OECD QRAM OUTPUTS 𝑅 = 𝐹 ∙ 𝐶 F probability of occurrence / frequency C extent of damage / consequences • Fatalities • Injured • Destruction of buildings and structures • Environmental Damage PIARC/OECD QRAM Societal Risk Individual Risk F[1/year] N [Fat] 𝐸𝑉𝑠 = 𝑖=0 ∞ 𝐹 𝑁𝑖 ∙ 𝑁𝑖 The risk to which a group of people is subjected in case a scenario s occurs. Prob. that a person (among local population and within a certain distance from the road) dies due to the scenario s. Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 52. www.francobontempi.org 52 PIARC/OECD QRAM OUTPUTS 𝑅 = 𝐹 ∙ 𝐶 F probability of occurrence / frequency C extent of damage / consequences • Fatalities • Injured • Destruction of buildings and structures • Environmental Damage PIARC/OECD QRAM Societal Risk F[1/year] N [Fat] 𝐸𝑉𝑠 = 𝑖=0 ∞ 𝐹 𝑁𝑖 ∙ 𝑁𝑖 The risk to which a group of people is subjected in case a scenario s occurs. SR = F(N) ∙ N The F-N diagrams may be applied to illustrate the risk profile for a specific hazard such as a fire in a road tunnel. Expected amount of victims in a certain time period Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 53. www.francobontempi.org 53 F-N curve construction process flow 1 – Dangerous Goods and Accident Scenarios selection 2 – Effect j (due to the scenario s ) and its Range from the epicentre Ej=f(d) Rj 3 – Mortality Rate within the range Rj %LETHj 4 – Mortality Rate corrected considering the possibility of escape %LETHj=f(tevac) 5 – Scenario s Probability of occurrence fs 6 – Number of victims due to the scenario s N= jNj=f(Rj, Dru, Ljam, %LETHj) 7 – F-N curve for the scenario s and its relative Expected Value Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 54. www.francobontempi.org 54 Tunnel risk assessment procedure Data Collection Data Preparation Risk Calculation Using QRAM Is Risk acceptable? NO Additional risk reduction measures YES End Mean Data: • Traffic • Accident Frequencies • Tunnel Geometry • Tunnel Equipment • ..... Risk Acceptability: • Absolute criteria • Relative criteria Risk Analysis Prevention Measures: • Signs and road markings • Lighting • Traffic control • Route geometry • Prohibition of access to certain types of vehicles Protection Measures: • Monitoring • Fires/Accident Detection system • Ventilation system • Emergency lighting • Protection of escape routes • System of emergency management • Emergency Procedures Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 55. www.francobontempi.org 55 Societal Risk Acceptability criteria Absolute Criteria 𝐸𝑉𝑠 ≤ 𝐸𝑉𝑙𝑖𝑚𝑖𝑡 (𝐸𝑉𝑠: Expected Value of Victims) 0,000001 0,00001 0,0001 0,001 0,01 0,1 1 1 10 100 F(N)[1/year] N Tollerable Risk Line Acceptable Risk Line Not Acceptable area ALARP Acceptable area As Low As Reasonably Practicable ALARP area: • prevention and/or mitigation actions must be taken to reduce the risk, as far as reasonably practicable • Cost – Benefit Analysis Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 56. www.francobontempi.org 56 Societal Risk Acceptability criteria Relative Criteria 𝐸𝑉𝑠 ≤ 𝐸𝑉𝑠,𝑟𝑒𝑓 1,00E-06 1,00E-05 1,00E-04 1,00E-03 1,00E-02 1,00E-01 1,00E+00 1,00 10,00 100,00 1000,00 Tunnel Tunnel Reference Applying the same calculation method, compare the examined risk with: • the risk of an alternative route • that calculated for a reference tunnel, which must have characteristics similar to the one examined, but with all the safety requirements required by the relevant regulations Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 57. www.francobontempi.org 57 Probit analysis Is a type of regression used to analysing the relationsheep between a stimulus (dose) and “all or nothing” (such as death) response The following items must be identified: • The toxicant • The target • The effect or response to be monitored • The dose range • The period of the test Biological organisms respond differently to the same dose of a toxicant. Each individual is exposed to the same dose and the response is recorded. Curves are frequently represented by a normal or Gaussian distribution A Gaussian or normal distribution representing the biological response to exposure to a toxicant. 𝑓 𝑥 = 1 𝜎 2𝜋 𝑒 − 𝑥−𝜇 2 2𝜎2 probability (or fraction) of individuals experiencing a specific response x is the response, σ is the standard deviation, and μ is the mean. σ determines the shape and μ characterize the location of the curve with respect to the x axis the percentage of individuals affected for a specified response interval • The toxicological experiment is repeated for a number of different doses, and normal curves are drawn. • The standard deviation and mean response are determined from the data for each dose. FINNEY 1971 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 58. www.francobontempi.org 58 Probit analysis A complete dose-response curve is produced by plotting the cumulative mean response at each dose. The response is plotted versus the logarithm of the dose, to provide a much straighter line in the middle of the response curve For comparison purposes the dose that results in 50% lethality of the subjects is frequently reported. This is called the LD50 dose (lethal dose for 50% of the subjects). For computational purposes the response versus dose curve is not convenient. For single exposures the probit method is particularly suited, providing a straight-line equivalent to the response-dose curve. P or RATIO = 1 2𝜋 −∞ Pr−5 𝑒− 1 2 𝑢2 𝑑𝑢 provides a relationship between the probability P and the probit variable Pr. Many methods exist for representing the response-dose curve. Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 59. www.francobontempi.org 59 Probit analysis Transformation from Percentages to Probits The probit relationship transforms the sigmoid shape of the normal response versus dose curve into a straight line when plotted using a linear probit scale The probit variable Pr is computed from 𝑃𝑟 = 𝑎 + 𝑏 ln 𝐷 P or RATIO = 1 2𝜋 −∞ Pr−5 𝑒− 1 2 𝑢2 𝑑𝑢 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 60. www.francobontempi.org 60 1) Dangerous goods and accident scenarios Liquefied Petroleum Gas (LPG) Motor Spirit Acrolein (Toxic Liquid) Chlorine (Toxic Gas) Ammonia (Toxic Gas) Liquified CO2 Boiling Liquid Expanding Vapor Explosion (BLEVE) Toxic Release in the air Torch Fire Pool Fire Vapor Cloud Explosion (VCE) Vapor Cloud Explosion BLEVE No DGs 20MW Fire 100 MW Fire Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 61. www.francobontempi.org 61 0 20 40 60 80 100 120 140 0,00 10,00 20,00 30,00 40,00 50,00 60,00 70,00 qr[kW/m2] d [m] 2) scenario physical effects Thermal Effects Pressure Effects Toxicity Effects • Fires • VCEs • BLEVEs • VCEs • BLEVEs • Fires (smokes) • Toxis Releases in air qr [kW/m2] = f(d) Radiative Heat Flux which is experienced by the receiver per unit area Side-on Blast Overpressure ∆Ps [bar] = f(d) Wave Positive-phase t+[bar] = f(d) Concentration C [ppmv] = f(d) Effect Intensity Distance from the epicentre Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 62. www.francobontempi.org 62 3) Physiological effects 𝐹𝑖𝑛𝑛𝑒𝑦,1971 𝑅𝑎𝑡𝑖𝑜 = 𝑓(Pr) = −∞ 𝑃𝑟−5 𝑒 − 1 2 𝑢2 𝑑𝑢 𝑃𝑟𝑜𝑏𝑖𝑡 𝑇𝑟𝑎𝑛𝑠𝑓𝑜𝑟𝑚𝑎𝑡𝑖𝑜𝑛 𝑃𝑟𝑗 = 𝑎 + 𝑏 ln 𝐸𝑗 ∙ 𝑡 𝑒𝑥𝑝,𝑗 Thermal Pressure Toxicity Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 63. www.francobontempi.org 63 4) probability of occurrence of the scenarios 𝑓𝑠,𝑖 = 𝑃𝑠,𝑖 ∙ 𝑓𝑎𝑐𝑐,𝑖 ∙ 𝑇𝐻𝑖 ∙ 𝐿𝑖 ∙ 24 ∙ 365 ∙ 10−6 Frequency of occurrence of the scenario s on the section i in a year [scen/year] Conditional probability that scenario j occurs once an accident implying an HGV has taken place on the section i Annual frequency of accidents involving HGVs on the section i [acc/(MVkm*year)] Traffic of HGVs passing through the section i in one hour [veh/h] 𝑓𝑎𝑐𝑐,𝑖 = 𝐻𝐺𝑉𝑎𝑐𝑐,𝑖 𝑇𝐻𝑖 ∙ 𝐿𝑖 FaultTreeAnalysis • HGV/h • % DG-HGV • DGs types • Accidents/year 𝐏 = 𝐏𝟏. 𝟏 ∙ 𝐏𝟏. 𝟐 + 𝐏𝟐. 𝟏 ∙ 𝐏𝟐. 𝟐 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 64. www.francobontempi.org 64 5) Possibility of escape or of finding shelter 𝐷𝑖𝑗 = 𝑡 𝑖𝑛 𝑡 𝑜𝑢𝑡 𝐷𝑗 𝑡 𝑑𝑡 Dose of physical effect j that affects a man crossing the segment i 𝐷𝑗,𝑇𝑂𝑇 = 𝑖 𝐷𝑖𝑗 Total dose received during the escape 𝑃𝑟𝑗 = 𝑎 + 𝑏 ∙ ln 𝐸𝑗 ∙ 𝑡 𝑒𝑥𝑝,𝑗 𝐷𝑗,𝑇𝑂𝑇 𝑡 𝑒𝑣𝑎𝑐 𝑡 𝑝𝑟𝑒 𝑡 𝑚𝑜𝑣 Pre-movement time Movement time 𝑣 𝑑 𝑠𝑎𝑓𝑒𝑡𝑦 𝑡 𝑝𝑟𝑒 = 𝑡 𝑝𝑟𝑒−𝑏𝑝𝑠 ∙ 𝑤 𝑒𝑓𝑓 𝑤 𝑒𝑓𝑓 = 5 𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑟𝑎𝑡𝑖𝑛𝑔 𝑜𝑓 𝑝𝑎𝑟𝑎𝑚𝑒𝑡𝑒𝑟𝑠 • Alertness (4) • Mobility (4) • Social Affiliation (3) • Commitment (3) • Familiarity (2) • Distance from the accident (by calc) • Perceived severity (4) Occupant Response Model 𝑡 𝑟𝑒𝑐 + 𝑡 𝑟𝑒𝑠 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 65. www.francobontempi.org 65 6) Societal risk indicators Number of Victims tsce Occurs the accident scenario tbarr Delay for stopping approaching traffic tjam min (tsce, tbarr). N = 𝑅 ∙ 𝐷 𝑅𝑈𝐽 + 𝑅 − 𝐿𝑗𝑎𝑚 ∙ 𝐷 𝑅𝑈𝐹 ∙ %𝐿𝐸𝑇𝐻 Road Users Density in a Traffic Jam [users/m] Road Users Density in a Fluid Traffic [users/m] Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 66. www.francobontempi.org 66 7) Societal risk indicators F-N curve construction Each scenario s may appear as different events Ei depending on:  the section of the path being considered (section i)  the accident location on the section  the traffic direction (A, B)  the reference period of the day (QUIET, NORMAL, PEAK)  .... Event Event Frequency Fatalities Cumulative Frequency Ei fi Ni Fi [-] [1/year] [Fat] [1/year] E1 f1 N1 F1 = f1 E2 f2 N2 F2 = f1+f2 E3 f3 N3 F3 = f1+f2+f3 E4 f4 N4 F4 = f1+f2+f3+f4 ... ... ... ... En fn Nn Fn = f1+f2+f3+f4+...+fn Scenario "s" F[1/year] N [Fat] 𝐸𝑉𝑠 = 1 +∞ )𝐹(𝑁 𝑑𝑁 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 67. www.francobontempi.org 67 Parte 2b: Analisi del rischio della galleria St. Demetrio Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 68. www.francobontempi.org 68 Tunnel St. Demetrio Motorway Catania – Syracuse (European route E45) ANAS s.p.a. Construction: 2007-2009 Pizzarotti & C. S.p.A. Parma Courtesy of Dr. Luigi Carrarini (ANAS S.p.A.) Courtesy of Ing. Alessandra Lo Cane (M.I.T.) Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 69. www.francobontempi.org 69 Tunnel St. Demetrio (Central Design Management ANAS S.p.A.) Height from the Roadway to the Inner Wall 8.06 [m] Road Platform Width 11.2 [m] Cross Sectional Area 87.31 [m 2 ] Natural Tunnel TWIN BORE TUNNEL, ONE DIRECTION PER BORE Polycentric Circular Section Traditional Excavation Bore in direction SOUTH (Syracuse) portal of entry [km] 4+800 portal altitude above sea level [m] 10642 portal of exit [km] 7+695 portal altitude above sea level [m] 19242 Length [km] 2895 maximum longitudinal slope [%] 0.32 minimum longitudinal slope [%] 0.32 average longitudinal slope [%] 0.32 Bore in direction NORTH (Catania) portal of entry [km] 7+698 portal altitude above sea level [m] 19273 portal of exit [km] 4+750 portal altitude above sea level [m] 10480 Length [km] 2949 maximum longitudinal slope [%] -0.32 minimum longitudinal slope [%] -0.32 average longitudinal slope [%] -0.32 Catania – Syracuse (E45), ANAS s.p.a. 2007-2009, Pizzarotti & C. S.p.A. Parma Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 70. www.francobontempi.org 70 Tunnel St. Demetrio: equipment & traffic data • Pedestrian Bypass every 300m • Bypass Carriageable every 900m • Control Centre → Catania • CCTV cameras placed every 282m • CO sensors • Smoke Meters (Opacimeters) • Linear Thermal Sensors (heat sensing cable) • Variable Message Panels every 300m • SOS stations every 200m 9 Jet Fan 10 Jet Fan 9 Jet Fan 9 Jet Fan Equipment Emergency Ventilation System Longitudinal Ventilation average speed (on the cross section) of 3 m/s in the direction of traffic time of fire detection (via thermo sensitive cable) of 3 minutes from the ignition a time of 5 minutes for the emergency ventilation establishment Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 71. www.francobontempi.org 71 Tunnel St. Demetrio: equipment & traffic data Traffic QUIET NORMAL PEAK AADT = 21190 veh/day (1 direction) 22÷07 325 veh/h HGV-ratio = 2% vcar = 126.4 km/h vHGV = 90.5 km/h 1050 veh/h HGV-ratio = 10% vcar = 126.4 km/h vHGV = 90.5 km/h 1553 veh/h HGV-ratio = 11.7% vcar = 114.5 km/h vHGV = 82 km/h SOUTH NORTH QUIET 1 1 NORMAL 7 3 PEAK 12 5 DG-HGV / h 63% Flammable Liquids (motor spirit, diesel oil, etc.) 31% LPG 6% Others [acc /(MVkm*year)] [acc /(veh*km*year)] SOUTH 0.161 0.000000161 NORTH 0.160 0.000000160 facc Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 72. www.francobontempi.org 72 21 - TUNNEL 3 2 3 - TUNNEL1 SOUTH (Syracuse) NORTH (Catania) x Tunnel St. Demetrio: QRAM input data Accident Scenarios Tunnel QRAM Model Average number of people in a light vehicle [-] 2 Average number of people in a HGV [-] 1.1 Average number of people in a Bus/Coach [-] 40 Bus/Coaches ratio [-] 0.01 Delay for stopping approaching traffic [s] 9000 Area (Urban/Rural) [-] urban Average density of population [hab/km2 ] 0.01 DG transport correction factor [-] 1.00E+00 Traffic & Population Data W (effective width) [m] 11 H (effective height) [m] 7.9 A (open cross sectional area) [m 2 ] 86.9 Cam (camber) [%] 0 Gs (Segment gradient) [%] 0.32 VnN (volume flow rate along tunnel at nodes) [m3 /s] 0 VnE (volume flow rate along tunnel at nodes) [m3 /s] 261 Ad (open area of discrete drains) [m2 ] 0.075 Xd (interval between drains) [m] 20 Xe (average spacing between emergency exits) [m] 300 Ecom (emergency coms) → 1, 2 o 3 [-] 3 Tunnel Data Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 73. www.francobontempi.org 73 Tunnel St. Demetrio: F-N curve in the south direction 1,00E-06 1,00E-05 1,00E-04 1,00E-03 1,00E-02 1,00E-01 1,00E+00 1,00 10,00 100,00 1000,00 FCUM[acc/year] N [FAT] Tollerable Risk Line Acceptable Risk Line EV [Fat/year] 1.68E-02 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 74. www.francobontempi.org 74 Tunnel St. Demetrio: QRAM Sensitivity analysis input parameter Variation Initial Value Final Value Initial Value Final Value 0 0.01 0.00 0.01 0.00 equal to HGV ratio 0.01 0.02; 0.1; 0.117 0.01 0.02; 0.1; 0.117 0.15 - 0.15 0.30 ; 0.00 0.15 ; 0.15 0.30 ; 0.00 0.15 ; 0.15 0 - 0.30 0.30 ; 0.00 0.00 ; 0.30 0.30 ; 0.00 0.00 ; 0.30 1 2 1 2 1 1.5 2 1.5 2 1.5 2.5 2 2.5 2 2.5 3 2 3 2 3 1.5 1.1 1.5 1.1 1.5 2 1.1 2 1.1 2 3 1.1 3 1.1 3 x 10 1.61E-07 1.61E-06 1.60E-07 1.60E-06 x 10-1 1.61E-07 1.61E-08 1.60E-07 1.60E-08 x 10-1 1.00 0.10 1.00 0.10 x 10 1.00 10.00 1.00 10.00 2.5 0.00 2.50 0.00 2.50 4.12 0.00 4.12 0.00 4.12 1 3 1 3 1 2 3 2 3 2 A,B: 0 0.32 0.00 0.32 0.00 A,B: 3 0.32 3.00 0.32 3.00 A: -0.32 0.32 -0.32 - - B: -0.32 - - 0.32 -0.32 A,B: -3 0.32 -3.00 0.32 -3.00 1 2 1 2 1 3 2 3 2 3 XI Type of Construction (1 Circular, 2 Rectangualar cross-section) 2 [-] 1 2 1 2 105 0.00 105.00 0.00 -105.00 210 0.00 210.00 0.00 -210.00 200 261.00 200.00 -261.00 -200.00 300 261.00 300.00 -261.00 -300.00 REVERSE 261.00 -261.00 -261.00 261.00 0 0.075 0.00 0.075 0.00 0.15 0.075 0.15 0.075 0.15 1 3 1 3 1 2 3 2 3 2 200 300.00 200.00 300.00 200.00 400 300.00 400.00 300.00 400.00 1 150 1 150 1 2 150 2 150 2 3 150 3 150 3 4 150 4 150 4 5 150 5 150 5 10 150 10 150 10 XVII Safety equipment XII XIII XIV XV XVI VII VIII IX X Changes to the structure Frequency of Accidents I II Bus Coaches Ratio (for each period: QUIET, NORMAL, PEAK) Propane in Bulk ratio - Propane in Cylinder ratio Average Number of People in a Light Vehicle Average Number of People in a HGV III IV TRAFFIC V VI Average Spacing between Emergency Exits Delay for Stopping Approaching Traffic Accidents Frequency (facc) DG-HGV transport correction factor Camber (transversal slope) Ground Type: 1 (Bedrock), 2 (Fragmented), 3 (Fragmented and Under Water Segments Gradient Number of Lanes [m3/s] Normal Longitudinal Ventilation, Volume Flow Rate along tunnel (at each node) Emergency Longitudinal Ventilation, Volume Flow Rate along tunnel (at each node) Open Area of discrete Drains Emergency Coms: 1 (bell/siren), 2 (Public Address system) [min] [-] [-] [m2 ] [m3 /s] Societal Risk A - SOUTH Syr B - NORTH Cat [-] [%] [-] [%] [-] [-] [acc/(veh* km*year)] [pass] [pass] [-] Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 75. www.francobontempi.org 75 1,00E-03 1,00E-02 1,00E-01 initialcurve Busratio=0 BusCoachesRatio=HGVRatio LPGinBulk=LPGinCylinder=0.15 LPGinCylinder=0.30 PeopleinaLightVehicle=1 PeopleinaLightVehicle=1.5 PeopleinaLightVehicle=2.5 PeopleinaLightVehicle=3 PeopleinaHGV=1.5 PeopleinaHGV=2 PeopleinaHGV=3 faccx10 faccx10-1 DG-HGVcorrectionfactor*10-1 DG-HGVtransportcorrectionfactor*10 Camber=2.5 Camber=4.12 Ground(BadRock):1 GroundType(Fragmented):2 SegmentGradient=0 SegmentGradient=3 SegmentGradient(SOUTH)=-0.32 SegmentGradient(NORTH)=-0.32 SegmentGradient=-3 NumberofLanes1 NumberofLanes3 Construction2(Rectangualarcross-section) NormalLongitudinalVentilation105 NormalLongitudinalVentilation210 OpenAreaofdiscreteDrains=0 OpenAreaofdiscreteDrains*2 EmergencyComs=1(bell/siren) EmergencyComs=2(PublicAddresssystem) EmergencyLongitudinalVentilation200 EmergencyLongitudinalVentilation300 EmergencyLongitudinalVentilation→ReverseFlow AverageSpacingbetweenEmergencyExits=200 AverageSpacingbetweenEmergencyExits=400 DelayforStoppingTraffic=1min DelayforStoppingTraffic=2min DelayforStoppingTraffic=3min DelayforStoppingTraffic=4min DelayforStoppingTraffic=5min DelayforStoppingTraffic=10min EVs in Direction South Tunnel St. Demetrio: Sensitivity analysis results Traffic Frequency of accidents Structure details Safety equipment Number of Lanes facc x 10 DG-HGV factor x 10 Delay for stopping approaching trafficBUS ratio Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 76. www.francobontempi.org 76 1,00E-07 1,00E-06 1,00E-05 1,00E-04 1,00E-03 1,00E-02 1,00E-01 1,00E+00 1,00 10,00 100,00 1000,00 initial curve Delayfor Stopping Approaching Traffic = 1 min Delay for Stopping Approaching Traffic = 5 min Tollerable Risk Line Acceptable Risk Line Delayfor Stopping Approaching Traffic = 10 min Delayfor Stopping Approaching Traffic = 2 min Delayfor Stopping Approaching Traffic = 3 min Delayfor Stopping Approaching Traffic = 4 min Sensitivity to parameter: “delay for stopping approaching traffic” N = 𝑅 ∙ 𝐷 𝑅𝑈𝐽 + 𝑅 − 𝐿𝑗𝑎𝑚 ∙ 𝐷 𝑅𝑈𝐹 ∙ %𝐿𝐸𝑇𝐻 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 77. www.francobontempi.org 77 1,00E-07 1,00E-06 1,00E-05 1,00E-04 1,00E-03 1,00E-02 1,00E-01 1,00E+00 1,00 10,00 100,00 1000,00 initial curve Number of Lanes (for every section and in both directions) = 1 Number of Lanes (for every section and in both directions) = 3 Tollerable Risk Line Acceptable Risk Line 𝑁 = 𝑅 ∙ 𝐷 𝑅𝑈𝐽 ∙ %𝐿𝐸𝑇𝐻 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels Sensitivity to parameter: “number of lanes”
  • 78. www.francobontempi.org 78 1,00E-07 1,00E-06 1,00E-05 1,00E-04 1,00E-03 1,00E-02 1,00E-01 1,00E+00 1,00 10,00 100,00 1000,00 initial curve facc x 10 facc x 10-1 Tollerable Risk Line Acceptable Risk Line 𝑓𝑖𝑗 = 𝑃𝑖𝑗 ∙ 𝑓𝑎𝑐𝑐,𝑖 ∙ 𝑇𝐻𝑖 ∙ 𝐿𝑖 ∙ 24 ∙ 365 ∙ 10−6 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels Sensitivity to parameter: “HGVs accident frequency”
  • 79. www.francobontempi.org 79 1,00E-07 1,00E-06 1,00E-05 1,00E-04 1,00E-03 1,00E-02 1,00E-01 1,00E+00 1,00 10,00 100,00 1000,00 initial curve Propane in Bulk ratio =Propane in Cylinder ratio =0.15 Propane in Cylinder ratio = 0.30 Tollerable Risk Line Acceptable Risk Line Fire risk analysis of structures and infrastructures: theory and application in highway tunnels Sensitivity to parameter: “LPG (Liquefied Petroleum Gas) ratio”
  • 80. www.francobontempi.org 80 conclusions The parameters that most affect the risk curve: • Density of people on the road • Traffic (veh/h) • Bus ratio (%) • Number of lanes • Delay for stopping approaching traffic • Average vehicle occupancy • Accident scenarios frequency [scen/year] • facc • DG-HGV traffic • HGV traffic • Proportion of each DG 𝑓𝑖𝑗𝑘 = 𝑃𝑖𝑗𝑘 ∙ 𝑓𝑎𝑐𝑐_𝐷𝐺,𝑖 ∙ 𝑇𝐷𝑖𝑘 ∙ 𝐿𝑖 ∙ 24 ∙ 365 ∙ 10−6 • Further risk mitigation measures (adopted only after a cost benefit analysis) • The safety margin is high San Demetrio Tunnel Risk Analysis General Conclusions on the PIARC/OECD QRA model N = 𝑅 ∙ 𝐷 𝑅𝑈𝐽 + 𝑅 − 𝐿𝑗𝑎𝑚 ∙ 𝐷 𝑅𝑈𝐹 ∙ %𝐿𝐸𝑇𝐻 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 81. www.francobontempi.org 81 CONCLUSIONS: QRAM AND Fluid Dynamics/evacuation models Data Collection Data Preparation Risk Calculation Using QRAM Is Risk acceptable? NO Additional risk reduction measures START YES End Idintification of Critical Scenarios Single Scenario Simulation CFD Simulation (Fire, Ventilation) Evacuation Model (Evacuation, Rescue) Qualitative Risk Estimation Measures Included in the model? YES NO (Gai et al., Proceedings IF CRASC’ 15) An operating method to follow can be to identify the critical scenarios that give the most significant contribution to the overall risk through the QRAM, and then to simulate those scenarios in detail in order to define risk reduction measures (Petelin S. 2009) Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 82. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO • NFPA, SFPE Handbook of Fire Protection Engineering, 3rd edition, 2002 • Jönsson, J. Combined Qualitative and Quantitative Fire Risk Analysis – Complex Urban Road Tunnel. Arup partners, 2007. • Faber, M.H. (2008) Risk and Safety in Civil, Environmental and Geomatic Engineering. ETH Zürich, lecture notes, available online on 01/2011 at: http://www.ibk.ethz.ch/fa • Haimes, Y. Y. (1981). Hierarchical holographic modeling. IEEE Transactions on Systems, Man, and Cybernetics, 11(9), pp. 606– 617. • Nolan, D.P. 1986. Handbook of Fire and Explosion Protection Engineering Principles for Oil, Gas, Chemical, and Related Facilities. Noyes, New Jersey • Aven, T. Risk Analysis: Assessing Uncertainties beyond Expected Values and Probabilities. John Wiley & Sons, 2008 • Furness, A. , Muckett, M. Introduction to Fire Safety Management. Elsevier, 2007. • Fire Risk in Metro Tunnels and Stations, Hyder Consulting, available on 05.2011 at http://hkarms.myftp.org/web_resources/Conference_Presentation/Fire_Risk_Metro_Tunnels_Stations.pdf • Fault Tree Handbook. Nuclear Regulatory Commission. NUREG–0492 • Hasofer et al. 2007, Risk Analysis in Building Fire Safety Engineering • Persson, M. Quantitative Risk Analysis Procedure for the Fire Evacuation of a Road Tunnel -An Illustrative Example. Lund, 2002 • Brussaard et al. 2004. The Dutch Model for the Quantitative Risk Analysis of Road Tunnels. Available on 05.2011 at http://www.rws.nl/rws/bwd/home/Tunnelveiligheid/dutch%20model.pdf • Gkoumas, K. 2008. Basic aspects of risk-analysis for civil engineering structures. Handling Exceptions in Structural Engineering: Robustezza Strutturale, Scenari Accidentali, Complessità di Progetto, Roma, 13-14 novembre. http://www.francobontempi.org/handling_papers.php References (1/2) 82 Fire risk analysis of structures and infrastructures: theory and application in highway tunnels
  • 83. www.francobontempi.org CORSO DI PROGETTAZIONE STRUTTURALE ANTINCENDIO References (2/2) 83 • Di Santo, C., Gkoumas, K., Bontempi. F. “Risk analysis for severe traffic accidents in road tunnels (Part I)”, Ingegneria Forense, Crolli, Affidabilità Strutturale e Consolidamento. Atti del Convegno IF CRASC '15 - 14/16 maggio 2015, Roma, Nicola Augenti & Franco Bontempi (ed), Dario Flaccovio Editore, pp. 971-979, ISBN 9788857904474 • Di Santo, C., Gkoumas, K. “Risk analysis for severe traffic accidents in road tunnels (Part II)”, Ingegneria Forense, Crolli, Affidabilità Strutturale e Consolidamento. Atti del Convegno IF CRASC '15 - 14/16 maggio 2015, Roma, Nicola Augenti & Franco Bontempi (ed), Dario Flaccovio Editore, pp. 959-969, ISBN 9788857904474 • DG MOVE (2014). Harmonised Risk Acceptance Criteria for Transport of Dangerous Goods. London: Det Norske Veritas Ltd. • Diernhofer, F., Kohl, B. and Hörhan, R. (2010). New Austrian Guideline for the Transport of Dangerous Goods through Road Tunnels. 5th International Conference on Tunnel Safety and Ventilation, Graz, 2010. • Evans, A.W. (2003). Transport Fatal Accidents and FN-curves: 1967-2001. HSE Research Report 073. HSE Books: Sudbury, Suffolk.Directive 2004/54/EC of the European Parlament and the Concil of 29 April 2004 on minimum safety requirements for tunnels in the trans-European road network, 7.6.2004 • Impresa Pizzarotti & C. S.p.A. (2007). Affidamento dell’opera di completamento del tratto stradale Catania Siracusa con caratteristiche autostradali, compreso tra le località passo s. martino ed Il Km 130+400 Della Ss. 114, Analisi Di Rischio (in Italian). • Melchers, R.E. 1993. Society, tolerable risk and the ALARP principle. In: Melchers RE, Stewart MG, editors. Probabilistic risk and hazard assessment. Netherlands, Balkema: 243–252 • Petelin S., Luin, B. and Vidmar, P. (2010). Risk Analysis Methodology for Road Tunnels and Alternative Routes. Journal of Mechanical Engineering, Vol. 56, No. 1, pp. 41-51. • PIARC Technical Committee C3.3 (2008) Road Tunnel Operation, Risk Analysis for Road Tunnels, ISBN 2-84060-202-4. • PIARC-OECD (2001). Safety in Tunnels, Transport of dangerous goods through road tunnels. OECD Publications. • UNCED AGENDA 21. 1992. Program of Action for Sustainable Development. United Nations Publication - Sales No. E.93.I. • Vagiokas, N., Bletsas, A. and Nelisse, R.M.L. (2013) Methodological approaches for tunnel classification according to ADR agreement. World Tunnel Congress 2013 Geneva Underground – the way to the future! G. Anagnostou & H. Ehrbar (eds). Fire risk analysis of structures and infrastructures: theory and application in highway tunnels