CLC Eglinton and Mount Pleasant Slide 1 CLC Eglinton and Mount Pleasant Slide 2 CLC Eglinton and Mount Pleasant Slide 3 CLC Eglinton and Mount Pleasant Slide 4 CLC Eglinton and Mount Pleasant Slide 5 CLC Eglinton and Mount Pleasant Slide 6 CLC Eglinton and Mount Pleasant Slide 7 CLC Eglinton and Mount Pleasant Slide 8 CLC Eglinton and Mount Pleasant Slide 9 CLC Eglinton and Mount Pleasant Slide 10 CLC Eglinton and Mount Pleasant Slide 11 CLC Eglinton and Mount Pleasant Slide 12 CLC Eglinton and Mount Pleasant Slide 13
Upcoming SlideShare
What to Upload to SlideShare
Next
Download to read offline and view in fullscreen.

0 Likes

Share

Download to read offline

CLC Eglinton and Mount Pleasant

Download to read offline

Construction Liaison Committee Meeting

  • Be the first to like this

CLC Eglinton and Mount Pleasant

  1. 1. September 8, 2021 Eglinton Crosstown LRT Eglinton – Mt Pleasant CLC
  2. 2. METROLINX LAND ACKNOWLEDGMENT 2 Let us take a moment to acknowledge that we are on the traditional territory of Indigenous Peoples including the Anishnabeg, the Haudenosaunee and the Wendat peoples. We are all Treaty people. Many of us have come here as settlers and immigrants … in this generation or generations past. Metrolinx declares its commitment to building meaningful relationships with Indigenous Peoples. We acknowledge the historic and continued impacts of colonization and the need to work towards meaningful reconciliation with the original caretakers of this land. We acknowledge that Metrolinx operates on lands covered by 20 Treaties, and that we have a responsibility to recognize and value the rights of Indigenous Nations and Peoples and conduct business in a matter that is built on the foundation of trust, respect and collaboration.
  3. 3. Eglinton Station
  4. 4. EGLINTON STATION UPDATE 4 CENTRAL WEST WORKS MONTHLY MEETING Activity Location Approx. Date & Duration Extended Hours for Station Box Construction • Rebar, conduit, formwork, steel installations, and concrete works Beneath Eglinton Avenue and Eglinton TTC Station Underway through 2021 Monday – Friday; 24-hours Berwick Portal Construction • Architectural and mechanical electrical works Berwick Avenue and Eglinton TTC Station Through 2021 • Periodic closures of Berwick Ave; subject to TTC approval TTC Eglinton Station Works • Platform extension and mechanical electrical works Eglinton TTC Station Periodically through 2021 Next TTC Line 1 closure scheduled for: • September 25 – 26, 2021 East Tunnel Ventilation Shaft Construction Salvation Army Site Through 2021 Overnight TTC Connection Works • Excavation for escalator and stair construction North side of Eglinton Ave, west of Yonge St Underway for approximately six (6) weeks North Tunnel Ventilation Shaft Construction Center of Yonge St between Eglinton Ave and Roehampton Ave ✓ Complete Traffic Configuration Change: Stage 9 & 9A • To facilitate construction of the south-west entrance Yonge Street north and south of Eglinton Avenue ✓ Complete Stage 9A: Late-September 2021
  5. 5. CURRENT TRAFFIC CONFIGURATION 5 CENTRAL WEST WORKS MONTHLY MEETING For approximately three (3) weeks
  6. 6. UPCOMING TRAFFIC CONFIGURATION 6 CENTRAL WEST WORKS MONTHLY MEETING As early as late-September 2021 for approximately six (6) months
  7. 7. CONSTRUCTION PROGRESS PHOTOS 7 NORTH TUNNEL VENTILATION SHAFT REBAR AND FORMWORK – UPPER CONCOURSE LEVEL
  8. 8. Mount Pleasant Station
  9. 9. MOUNT PLEASANT STATION UPDATE 9 Activity Location Approx. Date & Duration Station Box Construction • Ceiling framing, escalator installations, masonry works, and tiling Beneath Eglinton Avenue East Underway through 2021 Main Entrance Construction • Waterproofing, formwork, rebar & steel installations, and concrete pours North west corner of Eglinton Ave E and Mt Pleasant Rd. Underway through 2021 Secondary Entrance Construction • Pre-cast installations and mechanical electrical works North side of Eglinton Ave, between 801 Mt Pleasant Rd and 300 Eglinton Ave E Underway through 2021 Utility Reinstatement Works North and south sides of Eglinton Avenue Periodically through 2021
  10. 10. CURRENT TRAFFIC CONFIGURATION 10 Expected to remain in place through late Summer 2021
  11. 11. CONSTRUCTION PROGRESS PHOTOS 11 CENTRAL WEST WORKS MONTHLY MEETING CEILING FRAME INSTALLATIONS – STATION BOX TILING – PLATFORM LEVEL
  12. 12. CONSTRUCTION PROGRESS PHOTOS 12 CENTRAL WEST WORKS MONTHLY MEETING MASONRY WORKS – STATION BOX MAIN ENTRANCE

Construction Liaison Committee Meeting

Views

Total views

5,752

On Slideshare

0

From embeds

0

Number of embeds

5,717

Actions

Downloads

0

Shares

0

Comments

0

Likes

0

×