Central West Fall Open House - Oct 28 2019

3,014 views

Published on

Final slide show deck for Central West Fall Open House, including Fairbank, Oakwood, Cedarvale, Forest Hill, Chaplin, Avenue & Eglinton.

Published in: Government & Nonprofit
  • Be the first to comment

  • Be the first to like this

Central West Fall Open House - Oct 28 2019

  1. 1. MISSION: WE CONNECT COMMUNITIES VISION: GETTING YOU THERE BETTER, FASTER, EASIER
  2. 2. Our services • In operation since 1967. • Serves a population of more than seven million. • 70 million customer journeys a year. • Smart card fare payment system. • Seamlessly connecting 11 transit agencies across the GTHA and Ottawa. • Replaces the need for tickets, tokens, passes or cash. • Connects Toronto Pearson International Airport and Union Station • 25-minute journey from end to end • Trains departing every 15 minutes
  3. 3. 2041 Regional Transportation Plan Approved in March 2018 by Metrolinx Board
  4. 4. Fairbank Station Renderings MAIN ENTRANCE SECONDARY ENTRANCE SERVICE BUILDINGEXTERIOR PLAZA
  5. 5. Fairbank Station: What to Expect 6 Year What to Expect Remaining Work for 2019 • Backfill continues on the north side of Eglinton Avenue West. • Traffic flip on the north side of Eglinton Avenue West as early as mid- November 2019. • Reinstatement of the Bell utilities duct bank and the Bell chamber. • Shallow excavation continues at the secondary entrance. • Tieback installation begins. • Extended hours for deep excavation and hauling begins. 2020 • Tieback installation continues until January 2020. • Extended hours for deep excavation and hauling until February 2020. • Final utilities work ongoing until May 2020.
  6. 6. Fairbank Construction Staging Until as early as November 2019
  7. 7. Fairbank Construction Staging: Upcoming Traffic Configuration As early as mid- November 2019 for approximately 2-3 months
  8. 8. Fairbank Progress Photos DEEP EXCAVATION MAIN ENTRANCE ROOF UNDER TRAFFIC BRIDGE
  9. 9. Oakwood Station Renderings MAIN ENTRANCE PLATFORM OVERVIEW SECONDARY ENTERANCE PLATFORM
  10. 10. Oakwood Station: What to Expect 11 Year What to Expect Remaining Work for 2019 • Mining excavation advancing from the Main Entrance towards the Secondary Entrance – mining excavation is expected to be complete at Oakwood Station by the end of 2019 • Permanent works at the Secondary Entrance and inside the caverns, including waterproofing, rebar, and formwork, continue • Concrete pours are ongoing to support the permanent works and create the final station structure underground. 2020 • Ongoing permanent works within the caverns and station entrances. • Completion of the arch concrete pours. • Construction of the station platform.
  11. 11. Oakwood Station Traffic Configuration 12 Through 2019
  12. 12. Oakwood Station Progress Photos MINING EXCAVATION WATERPROOFING
  13. 13. Cedarvale Station Renderings MAIN ENTRANCE SECONDARY ENTRANCE EXTERIOR PLAZA TERTIARY ENTERANCE
  14. 14. Cedarvale Station: What to Expect 15 Year What to Expect Remaining Work for 2019 • Underpinning of the TTC Eglinton West subway tunnel. • Deep excavation under Eglinton Avenue West. • Preparatory works for shoring installation and underpinning inside Eglinton West Subway Station. • Concrete works in select areas. 2020 • Concrete works throughout the entire station area. • Deep excavation under Eglinton Avenue West are expected to be complete by early 2020. • Shoring installation, shallow excavation, and structural works inside Eglinton West Station. • Underpinning works inside Eglinton West Station.
  15. 15. Cedarvale Station Traffic Configuration 16 Through 2019
  16. 16. Cedarvale Station Progress Photos DEEP EXCAVATION TTC UNDERPINNING
  17. 17. Forest Hill Station Renderings MAIN ENTRANCE SECONDARY ENTRANCE PLATFORMAERIAL VIEW
  18. 18. Forest Hill Station: What to Expect 19 Year What to Expect Remaining Work for 2019 • Deep excavation beneath the station roof and at the station entrances • Maintenance hole construction • Concrete works at the Secondary Entrance • Extended construction hours, 6:00 a.m. – 4:00 a.m. 2020 • Continue deep excavation beneath the station roof • Tunnel demolition and removal • Reinstatement of some turns at Bathurst St and Eglinton Ave W • Concrete works
  19. 19. Forest Hill Station Traffic Configuration 20 Through November 2019
  20. 20. Forest Hill Station Progress Photos SECONDARY ENTRANCEDEEP EXCAVATION BENEATH STATION ROOF
  21. 21. Chaplin Station Renderings MAIN ENTRANCE SECONDARY ENTRANCE PLATFORMTERTIARY ENTRANCE
  22. 22. Chaplin Station: What to Expect 23 Year What to Expect Remaining Work for 2019 • Excavation and station roof construction, including concrete pours, on the north side of Eglinton Ave • Deep excavation at the Main and Tertiary Entrances • Extended construction hours, 6:00 a.m. – 11:00 p.m. 2020 • Deep excavation beneath the station roof • Construction of the Secondary Entrance
  23. 23. Chaplin Station Traffic Configuration 24 Through 2019
  24. 24. Chaplin Station Progress Photos MAIN ENTRANCE EXCAVATIONSHALLOW EXCAVATION
  25. 25. Avenue Station Renderings Station Features  Accessible main entrance  Covered & uncovered bicycle parking  Retail space in main entrance?? SECONDARY ENTRANCE MAIN ENTRANCE MAIN ENTRANCE INTERIOR AERIAL VIEW
  26. 26. Avenue Station Mining Works Access Adit Main Entrance Secondary Entrance Cross Cut Cavern Avenue Rd Highbourne Rd Oriole Pkwy S. Eastbourne Ave Lascelles Blvd
  27. 27. Avenue Station: What to Expect 28 Year What to Expect Remaining Work for 2019 • 24 hour mining excavation continues east of Oriole Pkwy, and will continue into spring 2020 • Monitoring and dewatering well maintenance • Final lining of the caverns is underway and will continue into mid-2020, including: • Waterproofing and concrete works for station foundation, walls, ceiling and platforms • Frequent deliveries during concrete pours • Construction of new connection holes to facilitate concrete and final lining works • Final lining works will begin at the Main and Secondary Entrance shafts in late 2019 2020 • Architectural works, track and systems installation will begin in 2020
  28. 28. Avenue Station Traffic Configuration 29 Through 2020
  29. 29. Avenue Station Progress Photos MINING PROGRESSPERMANENT WORKS
  30. 30. Eglinton Station Renderings Station Features  Accessible main entrance  Covered & uncovered bicycle parking  Retail space in main entrance?? PLATFORM MAIN ENTRANCE TTC SERVICE BUILDING AERIAL VIEW
  31. 31. Eglinton Station: What to Expect Year What to Expect Remaining Work for 2019 • Deep excavation beneath road decking on Eglinton Ave • Tunnel ventilation shaft construction on Yonge St • Weekend road closures of Berwick Ave for TTC Line 1 Subway Service Building and TTC system-wide upgrades • Tunnel Boring Machine (TBM) removal at Duplex Ave • Extended construction hours at the Salvation Army and old TTC Bus Depot sites, 4:00 a.m. – 11:00 p.m. 2020 • Deep excavation beneath the road decking • Major concrete works
  32. 32. Eglinton Station Traffic Configuration 33 Beginning mid-October 2019 for approx. six (6) months
  33. 33. Eglinton Station Progress Photos TUNNEL BORING MACHINEDEEP EXCAVATION

×