3. SECTION ONE AT-GRADE UPDATE
3
Activity Location Approx. Date & Duration
Light poles, sidewalk, curb and
roadworks
Brentcliffe Road to East Portal
– South Side
Ongoing through to July 14 2020
Excavation, backfill, concrete
works, installation of concrete
blocks
Retaining Wall (East of
Brentcliffe Road)
Late July – November 2020
Deck waterproofing Celestica Bridge
Ongoing through to mid-July
2020
Restoring grade and topsoil West Don River Bridge
Ongoing through to mid-July
2020
WEST DON RIVER BRIDGE
GRADING WORKS
EAST OF BRENTCLIFFE
ROAD – SUBDRAINS AND
ROAD BASE WORKS
4. BRENTCLIFFE PORTAL TO LESLIE STREET
4
July 14, 2020 for approximately one month
• The pedestrian sidewalk will remain on the south
side of Eglington Avenue East only.
• The traffic configuration will accommodate road
works in the centre of Eglinton Avenue East
between Brentcliffe Road and the east portal.
• Construction activities include:
• Excavation
• Concrete and asphalt removal
• Extension of wet utilities
• Backfill
• Compaction
• Paving
5. RETAINING WALL CONSTRUCTION
NORTH SIDE OF EGLINTON, EAST OF BRENTCLIFFE ROAD
5
• This retaining wall is required to hold and stabilize
the embankment created from the newly widened
road.
• Construction is expected to begin late July 2020 for
a period of 4 months.
• Construction activities will include:
• Excavation: Excavators, dump trucks and
loaders
• Hydrovacing
• Backfill and compaction: Loader and vibratory
roller/compactor
• Concrete works: concrete trucks and pumps
• Installation of concrete blocks with mobile
crane
6. RAMP CONSTRUCTION, WEST OF LESLIE STREET
MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK
6
• Crews will be removing three (3) trees near
the West Don River Bridge prior to the
construction of the new path.
• Construction activities for path construction
include:
• Excavation
• Backfill
• Installation of topsoil
• Landscaping will take place in 2021 as part
of the final restoration plan.
Mid-July 2020 through to December 2020
8. CURRENT TRAFFIC CONFIGURATION – DECKING REMOVAL
8
Through to late July 2020
• Science Centre Station has advanced to a state to allow the
temporary traffic deck to be removed.
• The removal will take place in two stages, with the second
stage beginning early May 2020.
• The road will be restored to an improved surface.
• North south traffic will be reduced to two lanes and aligned
to the west side of Don Mills Road.
• Northbound, southbound and eastbound left turns will be
restricted.
Bus Detours:
• Route 34C diverting to Ferrand and Rochefort.
9. SCIENCE CENTRE STATION UPDATE
9
Area Current Activities
Station Box
• Installation of Mechanical plumbing and HVAC duct is ongoing
• First elevator installation is ongoing
• Masonry works, drywall installation and rough ceiling and stud installations are in progress
• Installation of electrical equipment continues
• Decking removal is complete and backfill is in progress
• Floor and wall tiling is ongoing
Main Entrance
• Wall tiling and ceiling works are in progress
• Drywall installation is ongoing
• Elevator and louver installation is ongoing
Pedestrian Tunnel/Bus
Terminal
• Civil works and ceiling installation are ongoing at the pedestrian tunnel
• Glazing continues at the bus terminal
• Masonry works, drywall and civil works are in progress at the bus terminal
• Rough ceiling, wall tiling, and roofing are ongoing at the bus terminal
Portals
• Backfilling is in progress at the east portal
• Installation of lighting fixtures is ongoing at the west and east portals
12. SECTION TWO AT-GRADE UPDATE
12
Activity Location Approx. Date & Duration
North and south platform installation Aga Khan Stop Complete
Placing concrete for shelter curbs Wynford Stop Ongoing
Placing rebar for platforms
Guideway barrier walls
Sloane Stop
East Don River Bridge to Swift Drive
Ongoing
Ongoing
Plinth clean up and demobilization Wynford Bridge Complete
Creek realignment
Hydro seeding
Wilson Brook Culvert
Complete
Summer 2020
-Concrete works for track slab
-Rebar on track slab and guideway walls
-Sidewalk and curb works
Bermondsey Rd to Victoria Park Ave Ongoing through to late July, 2020
13. SIDEWALK, CURB AND DRIVEWAY CONSTRUCTION
EGLINTON AVE E WEST OF JONESVILLE CRES
13
As early as June 17, 2020 for approximately one month
• Crews will be completing final sidewalk, curb and driveway construction.
• Closure of the eastbound curb lane on Eglinton Ave E between Jonesville Crescent and 1765 Eglinton Avenue East.
• The sidewalk on the south side of Eglinton Avenue East will be rerouted north of the work zone between Jonesville
Crescent and 1765 Eglinton Avenue East.