Construction updates were provided for the Chaplin and Avenue stations of the Crosstown LRT. At Chaplin Station, piling and excavation work was ongoing in preparation for the station structure. Renderings showed the design of the main, secondary, and tertiary entrances as well as the exterior and interior spaces. For Avenue Station, short term construction activities over the next few months were outlined, including dewatering, sewer lining, watermain installations, and monitoring equipment installation around the station area. Site visits were also discussed to view current work.
3. 3
Chaplin Station: What to Expect March 2018
ACTIVITY AREA IMPACT DURATION START DATE
Support of
Excavation - Piling
Within northeast work
zone on Eglinton Ave
W west of 564
Eglinton Ave W
Driveway
• Noise and vibration from drilling activity Ongoing February 2018
Shallow Excavation,
Struts and Walers
Installation
Within northeast
work zone on
Eglinton Ave W
• Noise from excavation equipment
• Generator running during day shift
• Noise from grinding operations
6-8 months March 16, 2018
Support of
Excavation - Piling
Main Entrance • Noise and vibration from drilling activity Complete March 16, 2018
Valve Chamber
Construction and
Watermain Bypass
Southwest work zone
on Eglinton Ave W
• Noise from construction activity
• Noise from a pump and surface equipment
7 weeks
remaining
January 22,
2018
Sanitary Diversion
Northeast work zone
on Eglinton Ave W in
front of 564 EAW
• Noise from a pump and surface equipment 3 days remaining March 28, 2018
17. 17
Short Term Activities Area & Impacts Duration
Tentative
Date
Dewatering work
(daytime) Installation
and trenching
• Eglinton north and south from Oriole
Pkwy to Lascelles
• Sidewalk, road and parking impacts
depending on location of trench and
equipment
• Pedestrians will be routed around
location of work
Approx. 3 weeks
remaining
Underway
Sewer Lining – final
piece
• Burnaby Road and Eglinton One overnight
period, 6-8 hours
April
Watermain Valve
Installations
• Watermain valve installations
required in two locations
• NW corner, inside site
• SW corner, sidewalk area –
pedestrians rerouted around
workzone
• Both installations will include a
water shut off from Avenue Road
to Elmsthorpe Ave.
Approx. 3 days
of work per
valve
One overnight
water shut off
per valve
(*pending
permit)
May
Avenue Station: What to Expect 2018
18. 18
Watermain Lining & Temporary Water Service
Short Term
Activities
Area & Impacts Duration Tentative Date
Watermain
lining
• Properties from 282 Eglinton Ave to the
east will be serviced through the laneway
• Properties from 284 Eglinton Ave to the
west will be serviced from the front
• Temporary water supply pipes will be
installed in the City right of way
• An area in front of each property will be
excavated to access the water connection
and it will be plated for the duration of
the lining (one to two months)
• After the lining is completed, the area will
be restored and that will take
approximately one week
• Access to laneway maintained during
works, there may be 2-5 min delay while
equipment is moved
2 weeks to install
temporary
service
4 – 6 weeks for
lining
Approximately
one week of
overnight work
remaining for
temporary
service
installation
Lining operations
upcoming.
19. 19
Temporary Water Service Installation (for watermain lining)
• Work is planned from 7pm to 7am
• Excavation in front of each property (shown in blue)
• Parking will be unavailable during work hours (red hash marks)
• Pedestrians will have a 1.5m walkway around the work zone (shown in green)
• Minor trenching in laneway between 280 Eglinton Avenue and Oriole Parkway
and on Oriole Parkway from closure to laneway (shown in red)
20. 20
Main Entrance Installation
Short Term
Activities
Area & Impacts Duration Tentative Date
Crane Delivery and
Installation
- A Gantry Crane
will be erected
above the Main
Entrance excavation
shaft
• The crane will be delivered to the
Main Entrance site.
• Due to the size of the beams for the
crane supports, the deliveries may
temporarily delay traffic movements
while the truck enters the site to
deliver the materials.
Periodic during 1
week
PENDING
21. 21
Short Term
Activities
Area & Impacts Duration Tentative Date
Monitoring Work
• Equipment is
installed in
various
locations
around the
station area to
monitor ground
movement
during
construction.
• To install the monitoring equipment in
the ground, crews move from location
to location around the station area.
Typically a drilling machine is used to
drill the hole where the monitor will be
installed.
• If on the sidewalk, pedestrians may
need to be routed around the work
zone (sidewalks stay open). If on the
roadway, a short term lane closure may
be required.
Installations
planned to be
complete in the
next few months.
Readings will be
taken regularly
for the duration
of the project.
Ongoing
Currently
focused around
the Main
Entrance site.
Avenue Station: What to Expect 2018