Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020

  1. 1. 1 CROSSTOWN LRT Construction Liaison Committee May 2020
  2. 2. 2 Leaside Station Update
  3. 3. 3 Leaside Station Construction Activities Area Current Activities Main Entrance • Formwork and rebar installation continues • Waterproofing is ongoing • Concrete works are underway Station Box • Rebar and formwork is in progress • Waterproofing is ongoing. • Concrete works have commenced. Secondary Entrance • Steel installation is underway. • Shallow excavation and backfilling is in progress. Surface Level • Traffic change implemented on January 22, 2020, will be in place through to late 2020.
  4. 4. 4 Year What to Expect 2020 • Extended construction hours will continue through 2020 • Periodic lane closures may be required to facilitate deliveries, dewatering and concrete works • Permanent works have commenced at the main entrance and will continue into late 2020, including waterproofing, formwork, rebar installation and concrete works • At the secondary entrance, excavation and backfilling are nearing completion. • Permanent works are expected to commence at the secondary entrance in June 2020 and will continue into early 2021. Leaside Station: Look Ahead
  5. 5. 5 Leaside Station Traffic Configuration Through to late 2020
  6. 6. 6 Leaside Station Progress Photos SECONDARY ENTRANCE MAIN ENTRANCE
  7. 7. 7 Laird Station Update
  8. 8. 8 Laird Station Construction Activities Area Current Activities Main Entrance • Rebar and formwork installation • Concrete works Secondary Entrance • Platform rebar installation Cavern • Ongoing formwork, rebar, ductbank and conduit installation at the platform • Concrete works continue within the tunnels and at the platform • Installation of falsework, rebar and OCS continues at the concourse
  9. 9. 9 Laird Station: Look Ahead Year What to Expect 2020 • Permanent works will continue: • Waterproofing, form and rebar and concrete works will occur inside of the completed cavern • During the concrete works, there will be continuous delivery of concrete to the surface sites, lane restrictions may be required • Utility and road restoration to begin mid-2020 • Overnight works will continue through to summer 2020
  10. 10. 10 Laird Station Traffic Configuration Current through to late 2020
  11. 11. 11 Laird Station Progress Photos COMPLETED CONCRETE POUR AT WEST END OF TUNNEL REBAR AND FORMWORK INSTALLATION AT MAIN ENTRANCE FORMWORK INSTALLATION AT THE WEST CONCOURSE MAIN ENTRANCE CONCRETE POUR
  12. 12. 12 Brentcliffe Portal to Leslie Street December 19 through to Mid-June 2020 • The traffic configuration will accommodate: • Guideway construction on the West Don River Bridge and portal. • Wet utility relocations, electrical works, road widening, sidewalks and curb works on the south side of Eglinton Ave East between Brentcliffe Road and the east portal. • The pedestrian sidewalk will be available on the south side of Eglinton Avenue East only.
  13. 13. 13 Brentcliffe Portal to Leslie Street June 2020 for approximately one month • The traffic configuration will accommodate road works in the centre of Eglinton Avenue East between Brentcliffe Road and the east portal. • Construction activities include: • Excavation • Concrete and asphalt removal • Backfill • Compaction • Paving • The pedestrian sidewalk will be available on the south side of Eglington Avenue East only.
  14. 14. 14 Retaining Wall Construction North Side of Eglinton, East of Brentcliffe Road • This retaining wall is required to hold and stabilize the embankment created from the newly widened road. • Construction is expected to begin late May 2020 for a period of 4 months. • Construction activities will include: • Excavation: Excavators, dump trucks and loaders • Hydrovacing • Backfill and compaction: Loader and vibratory roller/compactor • Concrete works: concrete trucks and pumps • Installation of concrete blocks with mobile crane
  15. 15. 15 Brentcliffe Portal Progress Photos SOUTH SIDE EGLINTON AVE FACING WEST SOUTH SIDE EGLINTON AVE FACING EAST
  16. 16. 16 416-782-8118 or 416-482-7411 24 hours/7days a week www.thecrosstown.ca crosstown@metrolinx.com facebook.com/thecrosstown twitter.com/crosstownTO instagram.com/eglinton_crosstown Crosstown West Office 1848 Eglinton Ave W (at Dufferin) Crosstown East Office 660 Eglinton Ave E (at Bayview) Stay in Touch

×