2. Eglinton Crosstown LRT Project
2
2
• A 19-kilometre route separated from regular traffic
• 10-kilometres underground; 9-kilometres at surface in east
• 15 underground stations and 10 surface stops
• A maintenance and storage facility
• Transit communications system
• Links to 54 bus routes, 3 subway stations, GO Transit, UP Express station
6. Eglinton Station - Progress
Completed to Date
Demolition of the Salvation Army
Community Church
Demolition of the abandoned TTC bus
depot
Wet utility relocation at the Yonge-
Eglinton intersection
Toronto Hydro relocation along Redpath
Avenue, Duplex Avenue
North, east, and west underground
pedestrian tunnel closures
Shoring at the Salvation Army site
7. Eglinton Station - Progress
Major 2018 Work
• Shoring continues for the
station box and main
entrance
• Toronto Hydro relocation
along Hillsdale Avenue,
Yonge Street
• New TTC Service Building
at Berwick Portal
• Upgrades to subway
station
8. Weekend Subway Closures
• Crosstown Project Agreements requires CTS to make improvements at
Eglinton subway station
• TTC has approved 24 closures in 2018 for this work
– Subway will close 2am Saturday mornings and re-open Monday mornings at 5am
– Closures necessary because CTS must work on and/or needs access to the
subway tracks and Berwick portal
– Work will occur 24 hours a day during the designated weekend closures
• 2018 closures provide benefits to TTC:
– Construction of new subway service building
– Upgrades/improvements to the subway station
• TTC & CTS coordination to limit overall number of Line 1 closures in 2018:
– During 9 of the 24 closures, TTC will undertake states of Good Repair work
– 15 out of the 24 Closures will be strictly from St Clair to Lawrence
9. Upgrades/Improvements to Subway Station
• During 2018, weekend closures also facilitate upgrades/improvements
to existing subway station:
– Smoke evacuation fans
– New electrical systems
– Improved fire detection systems
– New escalators
• Materials and equipment will be delivered on the subway tracks via the
Berwick portal, necessitating the subway closures.
• Additional benefits to TTC/transit users associated with Crosstown
construction:
– Extension of the subway platform by 25 metres
– Upgrading pedestrian tunnels that connect directly to current and future
– development
10. New Subway Station Service Building
• Building will be located over the subway tracks at the Berwick portal
• Provide improved ventilation and life safety systems for existing subway
• Weekend work February – December 2018
• Weekend activities include excavation, shoring and foundation work
12. New Subway Station Service Building
• Construction of this building is part of larger TTC plan to upgrade ventilation
systems on Line 1
13. Description of Construction
• Work will occur day and night on each planned subway closure weekend.
• Three basic phases of work planned: micro-piling, pre-cast installation, and material
supply and removal work
• Micro-piling phase
– Involves the installation of smaller diameter piles within the TTC subway corridor
– Two micro-pile drill rigs, a mobile crane, and a concrete pump will be used continuously
while concrete and steel deliveries will be intermittent. A hydrovac may be required
occasionally depending on site conditions.
• Pre-cast Installation
– Involves the delivery and installation of pre-fabricated concrete components
– A mobile crane and various hand tools will be used regularly with intermittent delivery of
pre-cast and concrete grout
• Material Supply and Removal
– Parts of Eglinton Station will need to be demolished and re-built. Berwick Portal will be
used as the access point for nighttime work within the station
– Construction equipment could involve concrete trucks, mobile cranes, and bin trucks
14. 2018 Weekend Subway Closure Schedule
TTC state of good repair closures (9)
TTC state of good repair closures (9)
15. Upcoming Works
*60% rendering
Activity Anticipated Impacts Schedule
Interior subway station
demolition works
• Work sites on Hillsdale Avenue and Berwick
Avenue
• Truck traffic to and from work sites
Feb 10 at 2am -- Feb 13 at 5am
Feb 17 at 2am -- Feb19 at 5am
Feb 24 at 2am -- Feb 26 at 5am
March 3 at 2am – March 5 at 5am
Berwick Avenue
Work Site and
Truck Routes
Hillsdale Avenue
Work Site and
Truck Routes
16. Upcoming Works
Activity Anticipated Impacts Schedule
Toronto Hydro
infrastructure installation
• Work sites on Berwick Avenue in stages as
per below
• Pedestrian re-routing
• A paid-duty officer will be on duty during
each stage
As early as late February
Approximately 4-6 weeks of work
Regular daytime hours from 7am-11pm
Toronto Hydro
infrastructure
works
17. Noise Monitoring and Mitigation
• CTS will be assessing sound levels during construction to ensure noise
levels remain within allowable limits and to identify possible mitigation
measures for construction activities.
• Noise mitigation measures already planned include:
– Continuous and proactive noise monitoring from key locations
adjacent the work site
– Acoustic enclosures for pumps and generators
– Broadband backup alarms for equipment
– Environmental awareness training and toolbox talks for contractors
and employees