Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting

  1. 1. CROSSTOWN LRT CLC Meeting Brentcliffe to Victoria Park Stop January 2020
  2. 2. 2 Section 1 At-Grade Updates Brentcliffe Portal to Sunnybrook Park Stop Brentcliffe Portal 2
  3. 3. 3 Extended Construction Hours Continue • Starting November 11, 2019, crews will work extended hours to accelerate construction (4:30 a.m. – 11:00 p.m.). Construction activities may include, guideway construction, road widening, retaining wall construction, hydro utility installation and bridge rehabilitation. • The period between 4:30 a.m. – 7:00 a.m. will be primarily used to perform less noisy work, such as site and traffic staging, preparatory works, excavation, concrete pours, deliveries and hauling What to Expect • Daily temporary lane closures along Eglinton Ave E and cross streets between theWest Don River Bridge andVictoria Park Ave will be in effect to facilitate construction and deliveries • Short-term pedestrian rerouting as well as temporary sidewalk and crosswalk closures may be required to safely facilitate construction • Noise from construction activities and equipment, such as removal of asphalt, excavation, trucks and generators can be expected • Site lighting can be expected
  4. 4. 4 Brentcliffe Portal to Leslie Street December 19 through to Summer 2020 • The new configuration will accommodate: • Guideway construction on the West Don River Bridge and portal. • Retaining wall construction on the north side of Eglinton Avenue East. • The pedestrian sidewalk will be available on the south side of EglingtonAvenue East only. • Electrical work will continue at the Brentcliffe Portal.
  5. 5. 5 Sunnybrook Park Stop (Leslie Street) Year What to Expect 2020 • Preparatory work for the new pedestrian staircase on the south side of Eglinton at Leslie began January 2020. Construction will continue through to spring 2020. • Guideway construction will continue east and west of the intersection. • Stop construction will continue through to spring 2020. • Track work will begin, including rail installation and the installation of overhead catenary system to support light rail vehicles. DUCT BANK EXCAVATION AT WEST DON RIVER BRIDGE DUCT BANK EXCAVATION AT WEST DON RIVER BRIDGE
  6. 6. 6 Science Centre Station Don Mills Road
  7. 7. 7 Science Centre Station Current Traffic Configuration Current through to January 15, 2020
  8. 8. 8 Science Centre Station Upcoming Traffic Configuration January 15, 2020 through to late January 2020
  9. 9. 9 Science Centre Station Upcoming Traffic Configuration Late January for one weekend
  10. 10. 10 Science Centre Station Upcoming Traffic Configuration February 2020 to late 2020 *Note: An additional traffic stage will be required for decking removal at the intersection.This interim stage will be in place for approximately 2 months sometime between March – August 2020.
  11. 11. 11 Science Centre Station Year What to Expect 2020 • Rail installation began October 2019 and will continue through to spring 2020. • Electrical and mechanical work began November 2019 and will continue through to spring 2020. • Track work and rail installation will continue through to Spring 2020. • Waterproofing and backfill will continue through spring 2020. Station Box • Backfill of the roof slab is ongoing • Interior works are ongoing Main Entrance/PedestrianTunnels/BusTerminal • Structural steel work and steel decking installation is ongoing at the bus terminal • Glazing has started at the main entrance • Structural steel work is complete at main entrance, glass installation will continue in early 2020 Portals • All rebar and concrete works are complete • Installation of lighting fixtures is ongoing at the west and east portals
  12. 12. 12 Science Centre Station Progress Photos GLASS INSTALLATION AT THE MAIN ENTRANCE STRUCTURAL STEEL AT BUS TERMINAL FORMWORK INSTALLATION OF ROOF SLAB AT STATION BOX FORMWORK INSTALLATION OF STAIRS AT STATION BOX
  13. 13. 13 Section 2 At-Grade Updates Aga Khan Park & Museum Stop to O’Connor Stop
  14. 14. 14 Section 2 At-Grade Ongoing Construction Activities Activities Area & Impacts Date East Don River Bridge • Conduit installation under the bridge • Scaffolding removal under the bridge • Guideway construction Ongoing to late January 2020 Early February 2020 Wynford Bridge • Guideway construction Early February 2020 Wilson Brook Culvert • East wing wall construction • Backfill of wing wall • Creek realignment Complete Early February 2020 Spring 2020 Retaining Wall at the East Don River Bridge (north side Eglinton Ave) • Final grading Ongoing to mid January 2020 Retaining Wall at Saddle Ridge Drive (south side Eglinton Ave) • Formwork and concrete • Backfill and cul-de-sac reconstruction • New sidewalk Complete February 2020 Spring 2020 TPSS 10 • Delivery and installation of structure February 7-9, 2020
  15. 15. 15 Aga Khan Park Stop (Don Valley Parkway) Year What to Expect 2020 • Stop construction will continue through to February 2020 • Guideway construction east and west of the DonValley Parkway will continue through to mid 2020. • Track work will begin including rail installation and the installment of an overhead catenary system to support light rail vehicles REBAR INSTALLATION AND TRACK SLAB REBAR INSTALLATION AND TRACK SLAB
  16. 16. 16 Aga Khan Park Stop Traffic Configuration Early November through 2020
  17. 17. 17 Wynford Stop (Wynford Drive) Year What to Expect 2020 • Bridge rehabilitation is complete • Guideway and stop construction will begin February 2020 • Track work will begin, including rail installation and the installment of an overhead catenary system to support light rail vehicles
  18. 18. 18 Sloane Stop (Sloane Ave and Bermondsey Road) Year What to Expect 2020 • Guideway construction east and west of the intersection will continue • Sloane stop construction will continue • Guideway construction will continue between Jonesville Cres andVictoria Park Ave • Reconstruction of theWilson Brook Culvert will continue through to mid-2020 • Road reconstruction on the north of Eglinton Avenue East west of Jonesville Cres and Wilson Brook Culvert will begin spring 2020 • Track work will begin, including rail installation and the installment of an overhead catenary system to support light rail vehicles
  19. 19. 19 Credit Union and Swift Drive Traffic Configuration Traffic movements reflect the permanent intersection configuration. The westbound left turn movement will be permanently prohibited. Guideway construction will continue east and west of the intersection. Through 2020
  20. 20. 20 Sloane Stop Traffic Configuration Mid December 2019 through to spring 2020  Guideway construction continues east and west of the Sloane/Bermondsey intersection. o Concrete barriers may be temporarily removed for construction vehicles entering and exiting the guideway work zone. o Temporary lane closures may be required.
  21. 21. 21 Progress Photos DELIVERY OF TPSS 9 WILSON BROOK CULVERT EAST DON RIVER BRIDGE GUIDEWAY EAST OF CREDIT UNION DRIVE
  22. 22. 22 416-782-8118 or 416-482-7411 24 hours/7days a week www.thecrosstown.ca crosstown@metrolinx.com facebook.com/thecrosstown twitter.com/crosstownTO instagram.com/eglinton_crosstown Crosstown West Office 1848 Eglinton Ave W (at Dufferin) Crosstown East Office 660 Eglinton Ave E (at Bayview) Stay in Touch