Instructor
Zahidul Islam
3
4
Aim
The aim of my presentation is to briefly
discuss about the building construction
and management function and
recommendation for future progress.
5
Contents
 Introduction
 Company Overview
 Study Carried Out
 Problems Identification
and Suggestion
 Conclusions
 Recommendation
6
Introduction
 An eight storied residential building have two parts. These are
sub-structure and super-structure.
 In a construction process both theoretical knowledge and practical work
are equally important.
 The longevity of construction work depends on monitoring of a ‘Site
Engineer’. So he is an important person of a project.
7
Objective
 The main objective of this project is to plan over construction
and to progress the construction process.
 To acquire practical knowledge.
 To increase monitoring work during construction process.
 To decrease amount of wastage materials.
 To optimum use of time and manpower.
 To make the project economical.
8
Company Overview
 Nirapad Real Estate & Development Ltd. is located, House # 9,Road
# 9,Sector # 9, Uttara, Dhaka. Honorable Managing Director Jashim
Uddin Kobir is owner of this Organization.
 Nirapad Real Estate & Development Ltd. is a promising name that
has already marked its success as one of the distinct Real Estate
Companies.
 Established in 2003.
 This Organization has initiated and already handed over several
projects in different locations of Uttara in Dhaka city.
9
The Project of Nirapad Real Estate &
Development Ltd.
Handed Over Projects:
NIRAPAD NILIMA NIRAPAD LUPIN
House #01, Road #12, House # 04, Road # 07,
Sector # 10, Uttara , Dhaka. Sector # 09, Uttara, Dhaka.
10
Project Brief
Project name: NiRApad oasis lodge
Address: House# 32, Road# 12,
Sector# 10, Uttara, Dhaka.
Land area: 5 katha or 3600 sft.
Number of building: 01(One).
Number of apartment: 12(Twelve).
Size of apartment: 1225 sft.
11
Site Survey
 Observed the location of site.
 Site is West and North face.
 Identified the access to the site.
 Measured the length and breath.
 Earth filling not required.
12
Organization Structure 13
Job Responsibility
 Daily work schedule.
 Estimate.
 Preparing materials requisition.
 Monitoring the total construction work.
 Inform the top management about daily work progress.
 Quality control of during construction work.
 Labour maintaining.
14
Employed Designer & Architect
 After the site survey Nirapad Real Estate & Development Ltd.
employed a designer and architect, from:
‘Talukder Designer & Consultant’.
House# 11, Road# 08, Sector# 09, Uttara, Dhaka.
Structural Designer:
Eng. Kawser Talukder
B.Sc. Engg. (BUET)
Architect:
Mahmud-Ul-Aziz
15
DIT Plan
16
17
Use of Materials
 Reinforcement
 Stone
 Cement
 Brick
 Sand
 Sylhet sand (F.M. 1.8-2.5)
 Fine sand (F.M. 1.1-1.4)
 Plumbing and Sanitary Fittings and
Fixtures
 Electrical Fittings and Fixtures
 Tiles
 Paint
18
Estimate
SI Description Unit Qty Rate(TK.) Total Cost
01 Reinforcement
a. 20 mm (60 grade) kg 5600 53.00 296800
b. 16 mm (60 grade) kg 7134 53.00 378102
c. 12 mm (60 grade) kg 31050 53.00 1645650
d. 10 mm (60 grade) kg 1750 53.00 92750
e. 10 mm (40 grade) kg 6550 52.00 340600
02 Shah Special Cement bag 6515 360.00 235400
03 First Class Bricks nos 173400 7.00 1213800
04 Fine Sand cft 17890 14.00 250460
05 Sylhet Sand cft 5682 28.00 159096
06 Stone Chips cft 3984 110.00 438240
19
20
SI Description Unit Qty Rate(TK.) Total Cost
07 Brick Chips cft 12782 65.00 830830
08 Grill Works - - - 150,900
09 Tiles Works - - - 160,700
10 Paint Works - - - 145,080
11 Wooden Work - - - 702,147
12 Electrical Work - - - 799,543
13 Lift + Generator
+Substation
- - - 2,300,000
14 Plumbing Cost - - - 1,123,238
15 Labor - - - 2,000,000
Total Cost 14,940,117
SlabForm work procedure:
 After completed the column casting work,
start slab with beam centering.
 Use bamboo posts @ 2' c/c for slab
centering.
 After that use timber for slab centering.
 Fixed the end of steel sheet with wood by
nails.
 Level the form of slab.
21
Figure: Centering of slab
Reinforcement placing:
 Bottom layer:
 Binding for bottom layer
reinforcement, mainly use two
categories.
 First one is short direction
reinforcement.
 Second one is long direction
reinforcement.
22
Figure: Slab reinforcement placing
 Crank bar :
Crank bar should be used in both way of slab.
 Extra top bar:
Extra top bar are to be used on every crank bar.
23
Clear cover:
 Clear cover 1" was taken
in every slab.
Figure: Clear cover of slab
24
Slab Casting:
 At first slab casting by
concrete.
 After that concrete place in
column and beam joint,
then concrete place over whole
slab.
 Carefully compaction of concrete
by Vibrating machine.
25
Figure: Compaction of concrete
Brick Work
Working procedure of brick
wall:
 Select the first class bricks.
 Chipped and cleaned the
surface and made layout.
 Joint mortar was proper compacted by steel
trowel.
26
Figure : Brick work
 English bond was ensured.
 Vertical and horizontal alignment was maintained.
 1st lift brick work was, for 5" wall 4' and 10" wall 5'.
 Curing for 14 days was ensured.
27
Lintel Work
Working procedure of lintel:
 After completed 7' height brick wall,
lintel mainly made above the door and
window.
 For large span lintel used bamboo
posts.
 According to wall wide, completed the
centering and shattering.
28
Figure: Lintel centering and shattering
 Fixed the end of wood with brick wall
by nails.
 Used reinforcement in lintel.
 Casting properly, ratio is 1:2:4.
 Properly curing at least 7 days.
29
Figure : Reinforcement place in lintel work
Preparation of
background:
 At first clean the masonry and
RCC surface properly.
 If any part of the walls so
high, then cut the high part.
 The surface of wall kept moist
for at lest 6 hours before
plaster is started.
30
Figure : Preparation of background
High part
Preparation of mortar:
 Different works proportion were
different.
 For RCC ceiling surface proportion
was 1:4, brick wall surface
proportion was 1:5.
 Cement and sand mixture were
uniform.
31
Figure: Mortar mixture work
Application of mortar:
 Made pia of plaster 5˝x 5˝,
according to wall area was
divided into a number of
strips as reference level of
plaster.
 Applied the mortar
masonry wall surface and
RCC ceiling surface.
32
Figure: Plaster work
 Did not apply sand cement dry mix on the prepared
surface.
 If required plaster thickness more than 1". Did the plaster in 2 coats
(scratch and finish coat).
 Finished the surface with Gauging trowel, Wooden float and Floating rule.
33
Sanitary & Plumbing
Purpose of sanitary and plumbing:
 Conveying drinking water.
 Conveying wastewater.
 Conveying rain water.
 Waste disposal.
34
PVC/U-PVC pipe work procedure:
 At first made 4" hole in toilet floor.
 Then joint the sewerage and waste water pipes in
to the hole.
 Stand the pipes vertically from ground floor to
roof.
 Fixed the pipes on wall with vertically U-clamp
each 4' interval.
35
 Help to the pipe rain water & waste water
come directly in waste water pit & convey to
the city corporation drain.
 Similarly excreta directly come from toilet in
sewerage pit & go to the septic tank.
36
Figure: Sewerage and drainage work
waste water
pit
Sewerage pit
GI pipe work procedure:
 Did not start groove cutting for pipes
in wall, which is not cured for more
than 24 days.
 Make groove cutting straight
by groove cutting machine.
37
Figure: GI pipe
Problems Identification & Suggestion
SL
.
Problem Identified Suggestion
0
1
In my working site, there
weren’t reputed
contractor and experience
full subcontractor.
I informed project manager.
Then he changed them and also
employed new contractor and
subcontractor.
0
2
Contractor didn’t
maintained proper work
schedule.
I regularly communicated with
them and increased observation.
0
3
So many unskilled mason
and labour were in my
construction site.
So, I have tried to handle
unskilled labour and mason and
sometime trained them.
38
SL. Problem Identified Suggestion
04 Building project neighbor
side there were no proper
safety of during construction
time.
I used Hessian cloth with
bamboo bracing to project
neighbor side, from the brick
bats, plaster mortar etc.
05 Suppliers didn’t supply
good quality sand, during
plastering work.
I have informed to the top
management and they
supplied good quality sand.
39
Conclusion
 Durability of a building depend mainly on proper construction process and
proper use of materials.
 I have supervised slab work, brick work, plaster work, sanitary & plumbing
work etc.
 After supervision of my construction site, I have learned a lot about
theoretical background and achieve practical experience. It seems to me
that the practical knowledge is essential to be an efficient engineer.
40
Recommendation
 Standard quality of material should be ensured first
 Leakage into joint of formwork should not allowed
 Unclean reinforcement should not used
 During casting vibrator should be straight instead of inclined
 Before casting vertical and horizontal level should be checked for all
formwork
 Every day before closing of works, the site should be cleaned
41
42
43

Construction work of a multi storied residential building

  • 1.
  • 2.
  • 3.
  • 4.
  • 5.
    Aim The aim ofmy presentation is to briefly discuss about the building construction and management function and recommendation for future progress. 5
  • 6.
    Contents  Introduction  CompanyOverview  Study Carried Out  Problems Identification and Suggestion  Conclusions  Recommendation 6
  • 7.
    Introduction  An eightstoried residential building have two parts. These are sub-structure and super-structure.  In a construction process both theoretical knowledge and practical work are equally important.  The longevity of construction work depends on monitoring of a ‘Site Engineer’. So he is an important person of a project. 7
  • 8.
    Objective  The mainobjective of this project is to plan over construction and to progress the construction process.  To acquire practical knowledge.  To increase monitoring work during construction process.  To decrease amount of wastage materials.  To optimum use of time and manpower.  To make the project economical. 8
  • 9.
    Company Overview  NirapadReal Estate & Development Ltd. is located, House # 9,Road # 9,Sector # 9, Uttara, Dhaka. Honorable Managing Director Jashim Uddin Kobir is owner of this Organization.  Nirapad Real Estate & Development Ltd. is a promising name that has already marked its success as one of the distinct Real Estate Companies.  Established in 2003.  This Organization has initiated and already handed over several projects in different locations of Uttara in Dhaka city. 9
  • 10.
    The Project ofNirapad Real Estate & Development Ltd. Handed Over Projects: NIRAPAD NILIMA NIRAPAD LUPIN House #01, Road #12, House # 04, Road # 07, Sector # 10, Uttara , Dhaka. Sector # 09, Uttara, Dhaka. 10
  • 11.
    Project Brief Project name:NiRApad oasis lodge Address: House# 32, Road# 12, Sector# 10, Uttara, Dhaka. Land area: 5 katha or 3600 sft. Number of building: 01(One). Number of apartment: 12(Twelve). Size of apartment: 1225 sft. 11
  • 12.
    Site Survey  Observedthe location of site.  Site is West and North face.  Identified the access to the site.  Measured the length and breath.  Earth filling not required. 12
  • 13.
  • 14.
    Job Responsibility  Dailywork schedule.  Estimate.  Preparing materials requisition.  Monitoring the total construction work.  Inform the top management about daily work progress.  Quality control of during construction work.  Labour maintaining. 14
  • 15.
    Employed Designer &Architect  After the site survey Nirapad Real Estate & Development Ltd. employed a designer and architect, from: ‘Talukder Designer & Consultant’. House# 11, Road# 08, Sector# 09, Uttara, Dhaka. Structural Designer: Eng. Kawser Talukder B.Sc. Engg. (BUET) Architect: Mahmud-Ul-Aziz 15
  • 16.
  • 17.
  • 18.
    Use of Materials Reinforcement  Stone  Cement  Brick  Sand  Sylhet sand (F.M. 1.8-2.5)  Fine sand (F.M. 1.1-1.4)  Plumbing and Sanitary Fittings and Fixtures  Electrical Fittings and Fixtures  Tiles  Paint 18
  • 19.
    Estimate SI Description UnitQty Rate(TK.) Total Cost 01 Reinforcement a. 20 mm (60 grade) kg 5600 53.00 296800 b. 16 mm (60 grade) kg 7134 53.00 378102 c. 12 mm (60 grade) kg 31050 53.00 1645650 d. 10 mm (60 grade) kg 1750 53.00 92750 e. 10 mm (40 grade) kg 6550 52.00 340600 02 Shah Special Cement bag 6515 360.00 235400 03 First Class Bricks nos 173400 7.00 1213800 04 Fine Sand cft 17890 14.00 250460 05 Sylhet Sand cft 5682 28.00 159096 06 Stone Chips cft 3984 110.00 438240 19
  • 20.
    20 SI Description UnitQty Rate(TK.) Total Cost 07 Brick Chips cft 12782 65.00 830830 08 Grill Works - - - 150,900 09 Tiles Works - - - 160,700 10 Paint Works - - - 145,080 11 Wooden Work - - - 702,147 12 Electrical Work - - - 799,543 13 Lift + Generator +Substation - - - 2,300,000 14 Plumbing Cost - - - 1,123,238 15 Labor - - - 2,000,000 Total Cost 14,940,117
  • 21.
    SlabForm work procedure: After completed the column casting work, start slab with beam centering.  Use bamboo posts @ 2' c/c for slab centering.  After that use timber for slab centering.  Fixed the end of steel sheet with wood by nails.  Level the form of slab. 21 Figure: Centering of slab
  • 22.
    Reinforcement placing:  Bottomlayer:  Binding for bottom layer reinforcement, mainly use two categories.  First one is short direction reinforcement.  Second one is long direction reinforcement. 22 Figure: Slab reinforcement placing
  • 23.
     Crank bar: Crank bar should be used in both way of slab.  Extra top bar: Extra top bar are to be used on every crank bar. 23
  • 24.
    Clear cover:  Clearcover 1" was taken in every slab. Figure: Clear cover of slab 24
  • 25.
    Slab Casting:  Atfirst slab casting by concrete.  After that concrete place in column and beam joint, then concrete place over whole slab.  Carefully compaction of concrete by Vibrating machine. 25 Figure: Compaction of concrete
  • 26.
    Brick Work Working procedureof brick wall:  Select the first class bricks.  Chipped and cleaned the surface and made layout.  Joint mortar was proper compacted by steel trowel. 26 Figure : Brick work
  • 27.
     English bondwas ensured.  Vertical and horizontal alignment was maintained.  1st lift brick work was, for 5" wall 4' and 10" wall 5'.  Curing for 14 days was ensured. 27
  • 28.
    Lintel Work Working procedureof lintel:  After completed 7' height brick wall, lintel mainly made above the door and window.  For large span lintel used bamboo posts.  According to wall wide, completed the centering and shattering. 28 Figure: Lintel centering and shattering
  • 29.
     Fixed theend of wood with brick wall by nails.  Used reinforcement in lintel.  Casting properly, ratio is 1:2:4.  Properly curing at least 7 days. 29 Figure : Reinforcement place in lintel work
  • 30.
    Preparation of background:  Atfirst clean the masonry and RCC surface properly.  If any part of the walls so high, then cut the high part.  The surface of wall kept moist for at lest 6 hours before plaster is started. 30 Figure : Preparation of background High part
  • 31.
    Preparation of mortar: Different works proportion were different.  For RCC ceiling surface proportion was 1:4, brick wall surface proportion was 1:5.  Cement and sand mixture were uniform. 31 Figure: Mortar mixture work
  • 32.
    Application of mortar: Made pia of plaster 5˝x 5˝, according to wall area was divided into a number of strips as reference level of plaster.  Applied the mortar masonry wall surface and RCC ceiling surface. 32 Figure: Plaster work
  • 33.
     Did notapply sand cement dry mix on the prepared surface.  If required plaster thickness more than 1". Did the plaster in 2 coats (scratch and finish coat).  Finished the surface with Gauging trowel, Wooden float and Floating rule. 33
  • 34.
    Sanitary & Plumbing Purposeof sanitary and plumbing:  Conveying drinking water.  Conveying wastewater.  Conveying rain water.  Waste disposal. 34
  • 35.
    PVC/U-PVC pipe workprocedure:  At first made 4" hole in toilet floor.  Then joint the sewerage and waste water pipes in to the hole.  Stand the pipes vertically from ground floor to roof.  Fixed the pipes on wall with vertically U-clamp each 4' interval. 35
  • 36.
     Help tothe pipe rain water & waste water come directly in waste water pit & convey to the city corporation drain.  Similarly excreta directly come from toilet in sewerage pit & go to the septic tank. 36 Figure: Sewerage and drainage work waste water pit Sewerage pit
  • 37.
    GI pipe workprocedure:  Did not start groove cutting for pipes in wall, which is not cured for more than 24 days.  Make groove cutting straight by groove cutting machine. 37 Figure: GI pipe
  • 38.
    Problems Identification &Suggestion SL . Problem Identified Suggestion 0 1 In my working site, there weren’t reputed contractor and experience full subcontractor. I informed project manager. Then he changed them and also employed new contractor and subcontractor. 0 2 Contractor didn’t maintained proper work schedule. I regularly communicated with them and increased observation. 0 3 So many unskilled mason and labour were in my construction site. So, I have tried to handle unskilled labour and mason and sometime trained them. 38
  • 39.
    SL. Problem IdentifiedSuggestion 04 Building project neighbor side there were no proper safety of during construction time. I used Hessian cloth with bamboo bracing to project neighbor side, from the brick bats, plaster mortar etc. 05 Suppliers didn’t supply good quality sand, during plastering work. I have informed to the top management and they supplied good quality sand. 39
  • 40.
    Conclusion  Durability ofa building depend mainly on proper construction process and proper use of materials.  I have supervised slab work, brick work, plaster work, sanitary & plumbing work etc.  After supervision of my construction site, I have learned a lot about theoretical background and achieve practical experience. It seems to me that the practical knowledge is essential to be an efficient engineer. 40
  • 41.
    Recommendation  Standard qualityof material should be ensured first  Leakage into joint of formwork should not allowed  Unclean reinforcement should not used  During casting vibrator should be straight instead of inclined  Before casting vertical and horizontal level should be checked for all formwork  Every day before closing of works, the site should be cleaned 41
  • 42.