Module-4
Specifications
Contract
Specification &
Estimation
Course Code- 011828P
Syllabus
 Specifications : Introduction, Object of specification, Types, General specification of
buildings
Specification
 A specification is a specific description of a particular subject. An engineering specification contains
detailed description of all workmanship and materials which are required to complete an engineering
project in accordance with its drawings and details.
Objective of Specification:
 The cost of a unit quantity of work is governed by its specification.
 Specification of work is required to specify the quality and quantity of different materials required in a
construction work and is one of the essential contract documents.
 This also specifies the workmanship and the method of doing work.
 A work is carried out according to its specification and the contractor is paid for the same. Any change
in specification changes the tendered rate.
 The necessity of specification is to verify and check the strength of materials for a work involved in a
project.
 Specification is an essential contract document and is required for Arbitration or court cases.
 Specification is necessary to specify the equipment, tools and plants to be engaged for a work and thus
enables to procure them beforehand.
Principles of specifications
 Description of materials: The quality and size of materials required to do an item of work shall be fully
described for checking up at site according to the bindings provided in the specification.
 Workmanship: Complete description of workmanship, the method of mixing to the proportion, the method of
laying, preparation of base or surface, compaction, finishing and curing etc. specifically applicable to the item of
work shall be clearly stated in different clauses.
 Tools and plants: The tools and plants to be engaged to carry out a work shall be described. The method of
operation and by whom to be supplied shall be stated.
 Protection of new work: The method of protection of new works against damage or the method of curing if
required, the test of completed work if necessary shall be described in separate clauses
 Expression: While writing a specification endeavor shall be made to express the requirements of the
specification clearly and in concise form avoiding repetition and unusual words. The style of tense shall remain
same throughout.
 Clauses of specifications: As far as possible, the clauses shall be arranged in the order in which work shall be
carried out. This does not mean to follow the works according to the order of arrangements but it facilitates
reference. While framing clauses for quality of materials, workmanship, tools and plants etc. practical
possibilities shall be realized.
Type of Specification
There are two types of specifications
1. General Specifications
2. Detailed Specifications
General specifications
 In this type of specification, nature and class of works and names of materials that should be used are described.
 General specifications provide a very brief explanation about construction materials and construction work.
 These specifications are not a part of contract document. These specifications help about knowing the name of
different materials, their ratios, and quantities.
Detailed specifications
 Detailed specifications convey the requirements of project to contractor through a detailed explanation of materials
and work.
 It provides a complete knowledge about the construction material, workmanship of construction work, ratio of
different materials, mixing method, quantity of individual material, how to prepare the materials and conduct the
installation, different testing requirements to be followed and how work will be measured.
 Detailed specifications are a part of contract, that’s why it helps in understanding the contract.
 Detailed specifications should be written in a pattern which is to be followed during execution of work
General Specification of a First
Class Building
 Foundation and plinth: Brickwork in foundation and plinth shall be of first-class brick in cement or lime
mortar over cement or lime concrete
 Filling: Foundation trenches and plinth shall be filled up with local sand.
 Damp-proof course: D.P.C. shall be 2.5 cm thick cement concrete or 2 cm thick cement mortar with 5%
waterproof compound by weight of cement or other standard water-proofing material.
 Superstructure: Superstructure shall be of first-class brickwork in cement mortar
 Flooring: Mosaic flooring shall be provided on all the floors including the staircase.
 Roofing: The roof shall be 10 cm average thick lime terracing over it.
 Finishing: Inside and outside wall shall be 12 mm thick cement plastered. The inside of the drawing, dining and
bedrooms shall be distempered and remaining portions white-washed three coats. The outside shall be two coats
decorative waterproof cement coating.
 Doors and windows: Doors and windows frames shall be of seasoned teak wood and shutter of 3 cm thick teak
wood panelled. Brass fittings shall be provided. Doors and windows shall be varnished and French polish.
 Miscellaneous: Rain-water pipes shall be of asbestos cement or cast-iron, finished with paint. All sanitary,
water-supply and electrical fittings shall be of first-class materials.
General Specification of a Second
Class Building
 Foundation and plinth: The brickwork in foundation and plinth shall be of first class brick with lime mortar over lime
concrete
 Filling: Foundation trenches and plinth shall be filled up with earth
 Damp -proof course: D.P.C. shall be 2 cm thick cement mortar with 5% Pudlo (waterproof concrete) by weight of
cement or other standard water-proofing materials.
 Superstructure: Superstructure shall be 2nd class brickwork in mud mortar.
 Flooring: The flooring shall be 2.5 cm cement concrete over 7.5 cm lime concrete
 Roofing: The roof shall be flat terraced roof or R.B roof or jack arch roof.
 Finishing: The inside walls shall be plastered with lime or cement mortar, outside walls shall be pointed or plastered with
lime or cement mortar. Inside shall be white-washed three coats, and outside colour – washed two coats over one coat of
white-wash.
 Doors and windows: Doors and windows frames hall be of seasoned teak wood and shutters of 4.5 cm Shisham or
Deodar wood, panelled. They shall be fitted with iron fittings. Doors and windows shall be painted with two coats.
 Miscellaneous: Rain-water pipes shall be cast-iron. Electrification, sanitary and water supply fittings shall be of class B-
type.
THANKS

More Related Content

What's hot

Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
JIT KUMAR GUPTA
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential building
K.MAHESH KUMAR
 
Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil Engineering
Kailash Chander
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
sooricivil
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveyingAwanish Shukla
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
Simarpreet Singh
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
Ar Naveen Naveen
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
Archistudent Portal
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
Nikhil Kumar
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
Dr K M SONI
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
AB MAKASANA
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
gayu pandian
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
Kailash Chander
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
Rajat Nainwal
 
Maintenance and repair of buildings.
Maintenance and repair of buildings.Maintenance and repair of buildings.
Maintenance and repair of buildings.Satyaki Sikdar
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
Simarpreet Singh
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
Aishwarya Deopujari
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
srinivas2036
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
Namrata Agnihotri
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 

What's hot (20)

Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential building
 
Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil Engineering
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Maintenance and repair of buildings.
Maintenance and repair of buildings.Maintenance and repair of buildings.
Maintenance and repair of buildings.
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 

Similar to Unit-4_Specification

SPECIFICATION
SPECIFICATIONSPECIFICATION
SPECIFICATION
Simran Vats
 
Lec - 2.ppt ganbella university quantity estimta
Lec - 2.ppt ganbella university quantity estimtaLec - 2.ppt ganbella university quantity estimta
Lec - 2.ppt ganbella university quantity estimta
2cd
 
Quality
QualityQuality
Quality
Tejas Doshi
 
Quality
QualityQuality
Quality
Tejas Doshi
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
DougDos
 
Specification Handout for 4th year civil engineering students
Specification Handout for 4th year civil engineering studentsSpecification Handout for 4th year civil engineering students
Specification Handout for 4th year civil engineering students
abrahaam21astu
 
start.docx
start.docxstart.docx
start.docx
YitayihAsnake
 
15CV81-Module-3.pdf
15CV81-Module-3.pdf15CV81-Module-3.pdf
15CV81-Module-3.pdf
ReenaraniMalik
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
LAKSHITHA RAJAPAKSHA
 
Specification- Contracts, Accounts and Tenders.pptx
Specification- Contracts, Accounts and Tenders.pptxSpecification- Contracts, Accounts and Tenders.pptx
Specification- Contracts, Accounts and Tenders.pptx
Vinod Nejkar
 
IMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATIONIMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATION
Sagar Kaptan
 
specifications of buildings.pptx
specifications of buildings.pptxspecifications of buildings.pptx
specifications of buildings.pptx
rakesh11032000
 
Specification of Work in Estimation and Accounts (EA)
Specification of Work in Estimation and Accounts (EA)Specification of Work in Estimation and Accounts (EA)
Specification of Work in Estimation and Accounts (EA)
Vasu Goel
 
2011 CTM Session 2: Terminology for Products
2011 CTM Session 2: Terminology for Products2011 CTM Session 2: Terminology for Products
2011 CTM Session 2: Terminology for Products
novacsi
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
LAKSHITHA RAJAPAKSHA
 
3 specification_2008 fitsium.pdf
3 specification_2008 fitsium.pdf3 specification_2008 fitsium.pdf
3 specification_2008 fitsium.pdf
AdisalemBelay
 
Specifications 2
Specifications 2Specifications 2
Specifications 2
Lumbad 1989
 
Bill Of Quantities Issued For Construction
Bill Of Quantities Issued For ConstructionBill Of Quantities Issued For Construction
Bill Of Quantities Issued For Construction
Ahmed El Ashry
 

Similar to Unit-4_Specification (20)

SPECIFICATION
SPECIFICATIONSPECIFICATION
SPECIFICATION
 
Lec - 2.ppt ganbella university quantity estimta
Lec - 2.ppt ganbella university quantity estimtaLec - 2.ppt ganbella university quantity estimta
Lec - 2.ppt ganbella university quantity estimta
 
Quality
QualityQuality
Quality
 
Quality
QualityQuality
Quality
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
 
Specification Handout for 4th year civil engineering students
Specification Handout for 4th year civil engineering studentsSpecification Handout for 4th year civil engineering students
Specification Handout for 4th year civil engineering students
 
start.docx
start.docxstart.docx
start.docx
 
15CV81-Module-3.pdf
15CV81-Module-3.pdf15CV81-Module-3.pdf
15CV81-Module-3.pdf
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
Specification- Contracts, Accounts and Tenders.pptx
Specification- Contracts, Accounts and Tenders.pptxSpecification- Contracts, Accounts and Tenders.pptx
Specification- Contracts, Accounts and Tenders.pptx
 
M.Salah cv1
M.Salah cv1M.Salah cv1
M.Salah cv1
 
IMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATIONIMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATION
 
specifications of buildings.pptx
specifications of buildings.pptxspecifications of buildings.pptx
specifications of buildings.pptx
 
Specification of Work in Estimation and Accounts (EA)
Specification of Work in Estimation and Accounts (EA)Specification of Work in Estimation and Accounts (EA)
Specification of Work in Estimation and Accounts (EA)
 
2011 CTM Session 2: Terminology for Products
2011 CTM Session 2: Terminology for Products2011 CTM Session 2: Terminology for Products
2011 CTM Session 2: Terminology for Products
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
3 specification_2008 fitsium.pdf
3 specification_2008 fitsium.pdf3 specification_2008 fitsium.pdf
3 specification_2008 fitsium.pdf
 
Site report 1
Site report 1Site report 1
Site report 1
 
Specifications 2
Specifications 2Specifications 2
Specifications 2
 
Bill Of Quantities Issued For Construction
Bill Of Quantities Issued For ConstructionBill Of Quantities Issued For Construction
Bill Of Quantities Issued For Construction
 

More from Akash Bharti

Module 4 flexural stresses- theory of bending
Module 4 flexural stresses- theory of bendingModule 4 flexural stresses- theory of bending
Module 4 flexural stresses- theory of bending
Akash Bharti
 
Module 3 SFD &BMD PART-1
Module 3 SFD &BMD PART-1Module 3 SFD &BMD PART-1
Module 3 SFD &BMD PART-1
Akash Bharti
 
Module 5
Module 5Module 5
Module 5
Akash Bharti
 
Unit-3_Measurement and payment
Unit-3_Measurement and paymentUnit-3_Measurement and payment
Unit-3_Measurement and payment
Akash Bharti
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
Akash Bharti
 
Unit-1_Contracts
Unit-1_ContractsUnit-1_Contracts
Unit-1_Contracts
Akash Bharti
 
Module 4
Module 4Module 4
Module 4
Akash Bharti
 

More from Akash Bharti (7)

Module 4 flexural stresses- theory of bending
Module 4 flexural stresses- theory of bendingModule 4 flexural stresses- theory of bending
Module 4 flexural stresses- theory of bending
 
Module 3 SFD &BMD PART-1
Module 3 SFD &BMD PART-1Module 3 SFD &BMD PART-1
Module 3 SFD &BMD PART-1
 
Module 5
Module 5Module 5
Module 5
 
Unit-3_Measurement and payment
Unit-3_Measurement and paymentUnit-3_Measurement and payment
Unit-3_Measurement and payment
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
 
Unit-1_Contracts
Unit-1_ContractsUnit-1_Contracts
Unit-1_Contracts
 
Module 4
Module 4Module 4
Module 4
 

Recently uploaded

Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 

Recently uploaded (20)

Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 

Unit-4_Specification

  • 1. Mr. Akash Assistant Professor Department of Civil Engineering DCE Darbhanga Module-4 Specifications Contract Specification & Estimation Course Code- 011828P
  • 2. Syllabus  Specifications : Introduction, Object of specification, Types, General specification of buildings
  • 3. Specification  A specification is a specific description of a particular subject. An engineering specification contains detailed description of all workmanship and materials which are required to complete an engineering project in accordance with its drawings and details. Objective of Specification:  The cost of a unit quantity of work is governed by its specification.  Specification of work is required to specify the quality and quantity of different materials required in a construction work and is one of the essential contract documents.  This also specifies the workmanship and the method of doing work.  A work is carried out according to its specification and the contractor is paid for the same. Any change in specification changes the tendered rate.  The necessity of specification is to verify and check the strength of materials for a work involved in a project.  Specification is an essential contract document and is required for Arbitration or court cases.  Specification is necessary to specify the equipment, tools and plants to be engaged for a work and thus enables to procure them beforehand.
  • 4. Principles of specifications  Description of materials: The quality and size of materials required to do an item of work shall be fully described for checking up at site according to the bindings provided in the specification.  Workmanship: Complete description of workmanship, the method of mixing to the proportion, the method of laying, preparation of base or surface, compaction, finishing and curing etc. specifically applicable to the item of work shall be clearly stated in different clauses.  Tools and plants: The tools and plants to be engaged to carry out a work shall be described. The method of operation and by whom to be supplied shall be stated.  Protection of new work: The method of protection of new works against damage or the method of curing if required, the test of completed work if necessary shall be described in separate clauses  Expression: While writing a specification endeavor shall be made to express the requirements of the specification clearly and in concise form avoiding repetition and unusual words. The style of tense shall remain same throughout.  Clauses of specifications: As far as possible, the clauses shall be arranged in the order in which work shall be carried out. This does not mean to follow the works according to the order of arrangements but it facilitates reference. While framing clauses for quality of materials, workmanship, tools and plants etc. practical possibilities shall be realized.
  • 5. Type of Specification There are two types of specifications 1. General Specifications 2. Detailed Specifications General specifications  In this type of specification, nature and class of works and names of materials that should be used are described.  General specifications provide a very brief explanation about construction materials and construction work.  These specifications are not a part of contract document. These specifications help about knowing the name of different materials, their ratios, and quantities. Detailed specifications  Detailed specifications convey the requirements of project to contractor through a detailed explanation of materials and work.  It provides a complete knowledge about the construction material, workmanship of construction work, ratio of different materials, mixing method, quantity of individual material, how to prepare the materials and conduct the installation, different testing requirements to be followed and how work will be measured.  Detailed specifications are a part of contract, that’s why it helps in understanding the contract.  Detailed specifications should be written in a pattern which is to be followed during execution of work
  • 6. General Specification of a First Class Building  Foundation and plinth: Brickwork in foundation and plinth shall be of first-class brick in cement or lime mortar over cement or lime concrete  Filling: Foundation trenches and plinth shall be filled up with local sand.  Damp-proof course: D.P.C. shall be 2.5 cm thick cement concrete or 2 cm thick cement mortar with 5% waterproof compound by weight of cement or other standard water-proofing material.  Superstructure: Superstructure shall be of first-class brickwork in cement mortar  Flooring: Mosaic flooring shall be provided on all the floors including the staircase.  Roofing: The roof shall be 10 cm average thick lime terracing over it.  Finishing: Inside and outside wall shall be 12 mm thick cement plastered. The inside of the drawing, dining and bedrooms shall be distempered and remaining portions white-washed three coats. The outside shall be two coats decorative waterproof cement coating.  Doors and windows: Doors and windows frames shall be of seasoned teak wood and shutter of 3 cm thick teak wood panelled. Brass fittings shall be provided. Doors and windows shall be varnished and French polish.  Miscellaneous: Rain-water pipes shall be of asbestos cement or cast-iron, finished with paint. All sanitary, water-supply and electrical fittings shall be of first-class materials.
  • 7. General Specification of a Second Class Building  Foundation and plinth: The brickwork in foundation and plinth shall be of first class brick with lime mortar over lime concrete  Filling: Foundation trenches and plinth shall be filled up with earth  Damp -proof course: D.P.C. shall be 2 cm thick cement mortar with 5% Pudlo (waterproof concrete) by weight of cement or other standard water-proofing materials.  Superstructure: Superstructure shall be 2nd class brickwork in mud mortar.  Flooring: The flooring shall be 2.5 cm cement concrete over 7.5 cm lime concrete  Roofing: The roof shall be flat terraced roof or R.B roof or jack arch roof.  Finishing: The inside walls shall be plastered with lime or cement mortar, outside walls shall be pointed or plastered with lime or cement mortar. Inside shall be white-washed three coats, and outside colour – washed two coats over one coat of white-wash.  Doors and windows: Doors and windows frames hall be of seasoned teak wood and shutters of 4.5 cm Shisham or Deodar wood, panelled. They shall be fitted with iron fittings. Doors and windows shall be painted with two coats.  Miscellaneous: Rain-water pipes shall be cast-iron. Electrification, sanitary and water supply fittings shall be of class B- type.